FR3028080A1 - METHOD OF MANAGING THE REAL-TIME ELECTRIC POWER DISTRIBUTION OVER AN ILOTE NETWORK - Google Patents

METHOD OF MANAGING THE REAL-TIME ELECTRIC POWER DISTRIBUTION OVER AN ILOTE NETWORK Download PDF

Info

Publication number
FR3028080A1
FR3028080A1 FR1460503A FR1460503A FR3028080A1 FR 3028080 A1 FR3028080 A1 FR 3028080A1 FR 1460503 A FR1460503 A FR 1460503A FR 1460503 A FR1460503 A FR 1460503A FR 3028080 A1 FR3028080 A1 FR 3028080A1
Authority
FR
France
Prior art keywords
network
sources
electrical energy
energy
source
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
FR1460503A
Other languages
French (fr)
Inventor
Guillaume Vriet
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Societe Technique pour lEnergie Atomique Technicatome SA
Original Assignee
Societe Technique pour lEnergie Atomique Technicatome SA
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Societe Technique pour lEnergie Atomique Technicatome SA filed Critical Societe Technique pour lEnergie Atomique Technicatome SA
Priority to FR1460503A priority Critical patent/FR3028080A1/en
Publication of FR3028080A1 publication Critical patent/FR3028080A1/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2300/00Systems for supplying or distributing electric power characterised by decentralized, dispersed, or local generation
    • H02J2300/40Systems for supplying or distributing electric power characterised by decentralized, dispersed, or local generation wherein a plurality of decentralised, dispersed or local energy generation technologies are operated simultaneously
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2310/00The network for supplying or distributing electric power characterised by its spatial reach or by the load
    • H02J2310/10The network having a local or delimited stationary reach
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • Y02B70/3225Demand response systems, e.g. load shedding, peak shaving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/222Demand response systems, e.g. load shedding, peak shaving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S40/00Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them
    • Y04S40/20Information technology specific aspects, e.g. CAD, simulation, modelling, system security

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Theoretical Computer Science (AREA)
  • Health & Medical Sciences (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Marketing (AREA)
  • Physics & Mathematics (AREA)
  • Water Supply & Treatment (AREA)
  • Primary Health Care (AREA)
  • General Health & Medical Sciences (AREA)
  • Public Health (AREA)
  • Power Engineering (AREA)
  • Development Economics (AREA)
  • Game Theory and Decision Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

L'invention se rapporte à une méthode de gestion pour la distribution de l'énergie électrique d'un réseau ilôté (100) comportant : une étape (201) d'identification d'un ensemble de critères d'exploitation qualifiant les différentes sources d'énergie électrique (S1, S2, S3) du réseau (100); une étape (203) de modélisation sous la forme quadratique de chacun des indices de chaque source (S1, S2, S3) ; une étape (204) d'optimisation sous contrainte consistant à déterminer, en temps réel, le minimum ou le maximum de chaque critère (C1, C2, C3, C4, C5) du réseau (100) en fonction des contraintes du réseau à l'instant donné ; une étape (205) de distribution des consignes de pilotage aux sources (S1, S2, S3) dudit réseau (100).The invention relates to a management method for the distribution of electrical energy of an ilôté network (100) comprising: a step (201) of identification of a set of operating criteria qualifying the various sources of electrical energy (S1, S2, S3) of the network (100); a step (203) modeling in the quadratic form of each of the indices of each source (S1, S2, S3); a constrained optimization step (204) of determining, in real time, the minimum or maximum of each criterion (C1, C2, C3, C4, C5) of the network (100) as a function of the network constraints; given moment; a step (205) for distributing control commands to the sources (S1, S2, S3) of said network (100).

Description

METHODE DE GESTION DE LA DISTRIBUTION D'ENERGIE ELECTRIQUE EN TEMPS REEL SUR UN RESEAU ILOTE DOMAINE TECHNIQUE DE L'INVENTION [0001] L'invention se rapporte à un réseau de distribution d'énergie « intelligent » qui utilise des technologies informatiques de manière à optimiser la production, la distribution, et la consommation d'énergie électrique du réseau afin d'améliorer l'efficacité énergétique de l'ensemble. [0002] L'invention concerne plus particulièrement une méthode de gestion de la distribution d'énergie électrique en temps réel sur un réseau électrique ilôté (c'est-à-dire déconnecté d'un réseau principal d'un fournisseur d'énergie) comportant un ensemble de sources d'énergie électrique et un ensemble de charges associées, l'ensemble des sources d'énergie électrique et des charges étant de puissance comparable.FIELD OF THE INVENTION [0001] The invention relates to an "intelligent" energy distribution network that uses computer technologies in such a way as to: optimize the production, distribution, and consumption of electricity in the network to improve the energy efficiency of the whole. The invention relates more particularly to a method of managing the distribution of electrical energy in real time on an electrical network ilôté (that is to say, disconnected from a main network of a power supplier) comprising a set of electric power sources and a set of associated loads, all the sources of electrical energy and loads being of comparable power.

ETAT DE LA TECHNIQUE ANTERIEURE [0003] Compte tenu des difficultés de stockage de l'énergie électrique en grandes quantités, les réseaux intelligents (ou « smart grid » en langue anglaise) permettent avantageusement d'ajuster la production et la distribution de l'électricité en fonction des besoins. [0004] Pour cela, il est connu différentes méthodes de gestion de la distribution de l'énergie électrique sur un « smart grid ». Un exemple de gestion de la distribution de l'énergie sur un réseau « smart grid » est de hiérarchiser les besoins de consommations en fonction des urgences afin d'optimiser le rendement des sources de production d'énergie, de minimiser les pertes de lignes, d'optimiser la production décentralisée d'origine renouvelable, de distribuer l'électricité au meilleur prix possible en sélectionnant par exemple les sources les moins chères. [0005] Les algorithmes de gestion de la distribution d'énergie connus sont développés pour gérer et optimiser la production et la distribution sur des réseaux de distribution nationaux, voire internationaux, en fonction de la demande. [0006] En revanche, ces algorithmes de gestion d'énergie sont généralement complexes et nécessitent de grandes capacités de calculs de manière à prendre en considération une multitude de paramètres relatifs à l'exploitation tels que par exemple : le coût énergétique de la source, l'impact environnemental de la source, le coût de maintenance, la disponibilité de la source, la capacité énergétique de la source, la durée de vie, la fiabilité de la source etc. [0007] La grande complexité de ces algorithmes de calculs induit une augmentation des temps de calculs compte tenu des l'ensemble des paramètres à prendre en considération. Ainsi, les temps de calculs de ces algorithmes sont de l'ordre de plusieurs secondes ce qui ne permet pas de réaliser réellement des adaptations en temps réel. [0008] De plus, les méthodes de gestion connues ne sont pas adaptées pour la gestion particulière de réseaux ilôtés présentant des sources et des charges de puissances comparables et dont les ressources sont limitées et variables dans le temps, en opposition avec des sources de type centrale nucléaire. [0009] Ainsi, pour la gestion de réseaux ilôtés présentant des sources de faible puissance et dont les ressources sont variables très rapidement, il est nécessaire de disposer d'une méthode de gestion utilisant un algorithme de calcul permettant de réaliser une adaptation en temps réel de la distribution électrique sur le réseau.PRIOR ART [0003] Given the difficulties of storing electrical energy in large quantities, smart grids (or "smart grids" in English) advantageously make it possible to adjust the production and distribution of electricity. depending on the needs. For this, it is known different methods of managing the distribution of electrical energy on a "smart grid". An example of managing the distribution of energy on a "smart grid" network is to prioritize consumption requirements according to emergencies in order to optimize the efficiency of the sources of energy production, to minimize line losses, to optimize the decentralized production of renewable origin, to distribute the electricity at the best price possible by selecting for example the cheapest sources. [0005] The known energy distribution management algorithms are developed to manage and optimize the production and distribution on national or even international distribution networks, depending on the demand. [0006] On the other hand, these energy management algorithms are generally complex and require large computing capacities so as to take into consideration a multitude of operating parameters such as, for example: the energy cost of the source, the environmental impact of the source, the cost of maintenance, the availability of the source, the energy capacity of the source, the service life, the reliability of the source etc. The great complexity of these computational algorithms induces an increase in computation time taking into account all the parameters to be taken into consideration. Thus, the computation times of these algorithms are of the order of several seconds, which makes it impossible to realistically adapt in real time. In addition, the known management methods are not suitable for the particular management of ilôté networks having sources and loads of comparable powers and whose resources are limited and variable over time, in opposition with sources of type nuclear plant. Thus, for the management of remote networks with low power sources and whose resources are variable very quickly, it is necessary to have a management method using a calculation algorithm to achieve a real-time adaptation of the electrical distribution on the network.

EXPOSE DE L'INVENTION [0010] Ainsi, l'invention vise à proposer une méthode de gestion pour la distribution de l'énergie électrique d'un réseau ilôté, ledit réseau ilôté comportant : - une pluralité de sources d'énergie électrique ; - une pluralité de charges consommant ladite énergie électrique produite par lesdites sources ; - des moyens de gestion et de distribution à ladite pluralité de charges de l'énergie électrique produite par ladite pluralité de sources, les moyens de gestion et de distribution étant formés par un calculateur et par une interface homme/machine ; ladite méthode étant caractérisée en ce qu'elle comporte : - une étape d'identification d'un ensemble de critères d'exploitation qualifiant les différentes sources d'énergie électrique du réseau, chaque source dudit réseau présentant un indice associé à chacun des critères d'exploitation ; - une étape de modélisation sous la forme quadratique de chacun des indices de chaque source ; - une étape d'optimisation sous contrainte consistant à déterminer, en temps réel, le minimum ou le maximum de chaque critère du réseau en fonction des contraintes du réseau à l'instant donné ; ladite quatrième étape comportant : - une première sous-étape de construction de l'algorithme de résolution au moyen de multiplicateurs de Lagrange de sorte que chaque critère du réseau soit énoncé sous la forme d'une équation linéaire [A].[X]=[b] avec : - [A] représentant une matrice de dimension nX n , avec n nombre entier, représentant le nombre de sources du réseau additionné au nombre de contraintes par critère d'exploitation, - [b] représentant une matrice colonne à71 lignes ; - [X] représentant une matrice colonne à n lignes représentant les solutions de l'algorithme ; - une deuxième sous-étape de résolution des équations linéaires [A].[X]=[b] en utilisant la méthode des gradients conjugués de manière à résoudre lesdites équations linéaires en au moins n itérations ; - une troisième sous-étape de vérification des contraintes d'inégalités ; - une étape de distribution des consignes de pilotage aux sources dudit réseau. [0011] La méthode selon l'invention permet donc d'obtenir une mise à jour en temps réel des consignes de pilotage, c'est-à-dire avec une fréquence de mise à jour inférieure à la milliseconde, et typiquement de l'ordre de la centaine de microsecondes, par la mise en place d'une méthode de calcul très rapide qui est cohérente avec des calculs dits en temps-réels pour l'optimisation en temps-réel de la distribution de puissance sur les charges d'un réseau électrique ilôté. La méthode selon l'invention permet ainsi de mieux gérer les différentes sources du réseau et de mieux répartir la production d'énergie électrique d'un réseau ilôté présentant des sources de faibles puissances, et/ou de moyennes puissances et dont les ressources de production d'énergie sont limitées et/ou variable dans le temps. [0012] La méthode selon l'invention est particulièrement adaptée pour la gestion d'un réseau ilôté présentant une pluralité de sources d'énergie électrique et une pluralité de charges dont les puissances sont comparables et typiquement inférieures à 10 MW. [0013] Ainsi, pour un état de charge donné du réseau, la méthode selon l'invention permet de déterminer la répartition de puissance optimale entre des différentes sources d'énergie électrique en prenant en compte à l'instant donné, les différents indices propres de chaque source qui caractérisent chaque source par rapport aux critères d'exploitation identifiés (critère techniques, critère économique, critère énergétique, ...). [0014] La méthode de gestion proposée par l'invention a pour avantage d'utiliser uniquement, pour la résolution de l'algorithme de calcul, les multiplicateurs de Lagrange et la méthode des gradients conjugués, ce qui permet de d'obtenir une résolution de l'algorithme en temps réel (dans un temps inférieur à la milliseconde). La méthode de gestion selon l'invention permet également d'assurer une fréquence de résolution de l'algorithme constante par rapport aux algorithmes de gestion de l'état de la technique dont le temps de réponse n'est pas maîtrisé ni constant car dépendant d'un nombre d'itérations qui n'est pas maîtrisé. La méthode de gestion selon l'invention permet d'avoir un temps de résolution au moins cent fois plus rapide pour un même calculateur qu'avec une méthode de gestion selon l'invention. [0015] Ainsi, l'invention propose une méthode de gestion simple, nécessitant peu de temps de calcul et permettant d'obtenir une rapidité de mise à jour de l'algorithme de calcul tout en assurant une précision suffisante ce qui permet en exploitation du réseau d'optimiser en temps réel les points de fonctionnement des sources et donc de réduire les coûts d'exploitation et de maintenance, notamment sur les réseaux présentant une forte mixité de nature et de puissance de sources. [0016] Avantageusement la méthode selon l'invention comporte postérieurement à l'étape d'identification, une étape de hiérarchisation desdits critères d'exploitation par ordre de priorité par l'adjonction d'un coefficient de priorité via l'interface Homme/Machine. Ainsi, la méthode de gestion selon l'invention permet de réaliser une répartition en privilégiant tel ou tel critère d'exploitation par rapport à d'autres. [0017] L'invention a également pour objet un réseau ilôté comportant : - une pluralité de sources d'énergie électrique ; - une pluralité de charges consommant ladite énergie électrique produite par lesdites sources ; - des moyens de gestion et de distribution à ladite pluralité de charges de l'énergie électrique produite par ladite pluralité de sources, les moyens de gestion et de distribution étant formés par un calculateur et par une interface homme/machine. [0018] Avantageusement, le réseau ilôté comporte des sources d'énergie d'origine éolienne et/ou des sources d'énergie d'origine photovoltaïque et/ou des sources d'énergie d'origine fossile. BREVE DESCRIPTION DES FIGURES [0019] D'autres caractéristiques et avantages de l'invention ressortiront à la lecture de la description qui suit, en référence aux figures suivantes. [0020] La figure 1 représente schématiquement un réseau ilôté. [0021] La figure 2 représente sous la forme d'un histogramme les caractéristiques associées aux critères d'exploitation du réseau pour une source d'énergie électrique du réseau illustré à la figure 1. [0022] La figure 3 représente un exemple de classement par priorité des critères d'exploitation du réseau par l'adjonction d'un coefficient de priorité. [0023] La figure 4 est un schéma synoptique illustrant les différentes étapes de la méthode de gestion selon l'invention. [0024] La figure 5 illustre sous la forme de trois histogrammes les caractéristiques de trois sources Si, S2, S3 sur les critères d'exploitation du réseau. [0025] La figure 6 illustre un exemple des puissances absorbées et des 5 résistances associées pour chacune des charges du réseau sur une période de 90 secondes. [0026] La figure 7 illustre sous la forme d'un tableau l'évolution de la puissance nécessaire sur le réseau pour alimenter les charges illustrées à la figure 6 sur une période de 90 secondes. 10 [0027] La figure 8 représente sous la forme d'un tableau un exemple de gain réalisé sur les coûts d'exploitation avec la méthode de gestion selon l'invention en comparaison avec une méthode de gestion classique selon l'état de la technique. [0028] Les figures 9a, 9b, 9c illustrent sous la forme de graphique les courants délivrés en fonction du temps pour chaque source du réseau. 15 DESCRIPTION DETAILLEE D'UN MODE DE REALISATION [0029] La figure 1 illustre de manière schématique un réseau intelligent 100 (« smartgrid » en langue anglaise) ilôté, c'est-à-dire déconnecté d'un réseau principal d'un fournisseur d'énergie et destiné à fonctionner de manière autonome. Le réseau 100 comporte : 20 une pluralité de sources d'énergie électrique Si, S2, et S3 (trois sources sont représentées à titre d'exemple) aptes à produire et/ou à stocker de l'énergie électrique de manière à la distribuer sur le réseau ; - une pluralité de charges 10 (quatre charges sont représentées à titre d'exemple) consommant ladite énergie électrique produite et/ou fournie par 25 lesdites sources Si, S2, S3. [0030] L'ensemble est piloté par des moyens de gestion permettant d'adapter la quantité d'énergie électrique produite et/ou distribué sur le réseau 100 en fonction de la demande des charges 10 qui varient dans le temps et de la production des sources Si, S2, S3 dont la production peut également varier dans 30 le temps. Les moyens de gestion sont formés par un calculateur 30 et par une Interface Homme-Machine (IHM) 20. [0031] Chacun des équipements du réseau 100 formés par les sources Si, S2, S3 possède des caractéristiques techniques, économiques, énergétiques, etc qui lui sont propres. Ces caractéristiques (différentes pour chaque source du réseau) forment ainsi un ensemble appelé « critères d'exploitation du réseau ».SUMMARY OF THE INVENTION [0010] Thus, the invention aims at providing a management method for the distribution of electrical energy of an on-board network, said remote network comprising: a plurality of sources of electrical energy; a plurality of charges consuming said electric energy produced by said sources; means for managing and distributing to said plurality of charges the electrical energy produced by said plurality of sources, the management and distribution means being formed by a computer and a man / machine interface; said method being characterized in that it comprises: a step of identifying a set of operating criteria qualifying the different sources of electrical energy of the network, each source of said network having an index associated with each of the criteria of exploitation; a modeling step in the quadratic form of each of the indices of each source; a constrained optimization step of determining, in real time, the minimum or the maximum of each criterion of the network as a function of the constraints of the network at the given instant; said fourth step comprising: - a first substep of constructing the algorithm of resolution by means of Lagrange multipliers so that each criterion of the network is expressed in the form of a linear equation [A]. [X] = [b] with: - [A] representing a matrix of dimension nX n, with n integer, representing the number of sources of the network added to the number of constraints per operating criterion, - [b] representing a column matrix at 71 lines ; - [X] representing a n-row column matrix representing the solutions of the algorithm; a second substep of solving the linear equations [A]. [X] = [b] by using the conjugated gradient method so as to solve said linear equations in at least n iterations; a third substep of checking the inequality constraints; a step of distributing control commands to the sources of said network. The method according to the invention therefore provides a real-time update of the control instructions, that is to say with a lower update frequency millisecond, and typically the order of a hundred microseconds, by setting up a very fast calculation method that is consistent with so-called real-time calculations for the real-time optimization of the power distribution on the loads of a electrical network ilôté. The method according to the invention thus makes it possible to better manage the various sources of the network and to better distribute the electrical energy production of an on-grid network having low power sources, and / or medium power sources and whose production resources of energy are limited and / or variable in time. The method according to the invention is particularly suitable for the management of an island network having a plurality of electrical energy sources and a plurality of loads whose powers are comparable and typically less than 10 MW. Thus, for a given state of charge of the network, the method according to the invention makes it possible to determine the optimal power distribution between the different sources of electrical energy taking into account at the given moment, the different indices proper each source that characterizes each source in relation to the identified exploitation criteria (technical criteria, economic criterion, energy criterion, etc.). The management method proposed by the invention has the advantage of using only, for the resolution of the calculation algorithm, the Lagrange multipliers and the conjugated gradient method, which allows to obtain a resolution of the algorithm in real time (in a time less than the millisecond). The management method according to the invention also makes it possible to ensure a frequency of resolution of the constant algorithm with respect to management algorithms of the state of the art whose response time is not controlled nor constant because it is dependent on a number of iterations that is not mastered. The management method according to the invention makes it possible to have a resolution time at least one hundred times faster for the same computer than with a management method according to the invention. Thus, the invention provides a simple management method, requiring little computing time and to obtain a speed of updating the calculation algorithm while ensuring sufficient accuracy which allows in operation of the network to optimize in real time the operating points of the sources and thus reduce operating and maintenance costs, especially on networks with a strong mix of nature and power sources. Advantageously, the method according to the invention comprises, after the identification step, a step of prioritizing said operating criteria in order of priority by the addition of a priority coefficient via the Human / Machine interface. . Thus, the management method according to the invention makes it possible to achieve a distribution by favoring one or another operating criterion over others. The invention also relates to an island network comprising: a plurality of sources of electrical energy; a plurality of charges consuming said electric energy produced by said sources; means for managing and distributing to said plurality of charges the electrical energy produced by said plurality of sources, the management and distribution means being formed by a computer and a man / machine interface. Advantageously, the ilôté network comprises wind energy sources and / or sources of energy of photovoltaic origin and / or sources of energy of fossil origin. BRIEF DESCRIPTION OF THE FIGURES [0019] Other features and advantages of the invention will emerge on reading the description which follows, with reference to the following figures. [0020] Figure 1 schematically shows an ilôté network. FIG. 2 represents in the form of a histogram the characteristics associated with the operating criteria of the network for a source of electrical energy of the network illustrated in FIG. 1. FIG. 3 represents an example of classification. by priority of the criteria of exploitation of the network by the addition of a coefficient of priority. Figure 4 is a block diagram illustrating the different steps of the management method according to the invention. Figure 5 illustrates in the form of three histograms the characteristics of three sources Si, S2, S3 on the operating criteria of the network. FIG. 6 illustrates an example of the absorbed powers and the associated resistances for each of the loads of the network over a period of 90 seconds. Figure 7 illustrates in the form of a table the evolution of the power required on the network to power the loads illustrated in Figure 6 over a period of 90 seconds. FIG. 8 represents in the form of a table an example of gain realized on the operating costs with the management method according to the invention in comparison with a conventional management method according to the state of the art. . Figures 9a, 9b, 9c illustrate in graphical form the currents delivered as a function of time for each source of the network. DETAILED DESCRIPTION OF AN EMBODIMENT FIG. 1 schematically illustrates an intelligent network 100 ("smartgrid" in English) on the side, that is to say, disconnected from a main network of a provider. of energy and intended to operate autonomously. The network 100 comprises: a plurality of sources of electrical energy Si, S2, and S3 (three sources are represented by way of example) capable of producing and / or storing electrical energy so as to distribute it on the network ; a plurality of charges 10 (four charges are represented by way of example) consuming said electrical energy produced and / or supplied by said sources Si, S2, S3. The assembly is controlled by management means for adapting the amount of electrical energy produced and / or distributed on the network 100 according to the demand of the charges 10 which vary over time and the production of Si sources, S2, S3 whose production may also vary over time. The management means are formed by a computer 30 and a Human Machine Interface (HMI) 20. Each of the network equipment 100 formed by the sources Si, S2, S3 has technical, economic, energy, etc. characteristics. which are his own. These characteristics (different for each source of the network) thus form a set called "network operating criteria".

Ces différents critères d'exploitation Cl, C2, C3, C4, C5 à prendre en compte sont par exemple : - la puissance délivrée ; - le mode de fonctionnement ; - le coût énergétique ; - la quantité d'énergie emmagasinée ; - la fiabilité ; - l'impact environnemental ; - la durée de vie ; - coût de maintenance ; - dimensionnement ; [0032] Ainsi, chaque source 51, S2, S3 du réseau 100 présente des caractéristiques différentes pour chaque critère d'exploitation du réseau 100. [0033] La figure 2 illustre sous la forme d'un histogramme les caractéristiques d'une source du réseau 100 (par exemple la source Si) sur cinq critères d'exploitation Ci, C2, C3, C4, C5. Pour chaque critère d'exploitation Ci, C2, C3, C4, C5 est donc associé un indice représentant les caractéristiques de la source. Cet indice est par exemple une valeur sur une échelle de 0 à 10 comme représenté à la figure 2. Cette répartition permet avantageusement de caractériser, sur une même échelle, chaque source 51, S2, S3 du réseau 100 sur l'ensemble des critères d'exploitation du réseau 100 prédéfinis. On notera que la figure 2 représente une distribution sur une sélection de cinq critères d'exploitation ; bien entendu la liste des critères donnée précédemment n'est pas exhaustive. [0034] Les sources Si, S2, S3 sont des sources de nature différente, par exemple des éoliennes, des panneaux photovoltaïque, des sources produisant de l'énergie électrique à partir de l'énergie fossile, etc. Les sources Si, S2, S3 du réseau 100 sont des sources dont les ressources sont limitées dans le temps et/ou dont la production d'énergie électrique est variable dans le temps. Ainsi les sources du réseau 100 selon l'invention sont différentes des sources de type centrales nucléaires dont les ressources sont considérées continues. Les sources sont des sources de faible et/ou de moyenne puissance dont la somme des puissances du réseau est typiquement inférieure à 10 MW. Ainsi, les sources du réseau sont différentes des sources de type centrale nucléaire de forte puissance. [0035] Le calculateur 30 comportant l'algorithme de gestion est relié directement au réseau 100 et aux installations du réseau et est programmé via l'IHM 20. Ainsi, le calculateur 30 reçoit comme données d'entrée : - des mesures issues des installations permettant d'identifier l'état des sources, l'état des équipements du réseau et l'état des charges du réseau ; - des critères de consigne du réseau formant ainsi les contraintes de l'algorithme de gestion ; - des informations sur l'état à venir de l'installation ; par exemple sur les charges, les ressources disponibles, les pannes, les maintenances prévisionnelles sur l'installation. [0036] La figure 4 représente un schéma synoptique illustrant les différentes étapes de la méthode de gestion selon l'invention. [0037] La méthode de gestion selon l'invention consiste dans une première étape 201 à déterminer ou à identifier les critères d'exploitation du réseau 100 en fonction des sources de production d'énergie du réseau. Cette première étape 201 permet de qualifier les différentes sources d'énergie électrique du réseau. [0038] Dans une deuxième étape 202, les critères d'exploitation identifiés sont hiérarchisés par l'adjonction d'un coefficient de priorité en fonction de l'importance accordée à chacun des critères. La figure 3 illustre à ce titre un exemple de pondération des critères d'exploitation par l'adjonction d'un coefficient de priorité plus ou moins élevé. Dans l'exemple de réalisation illustré, plus la valeur du coefficient de priorité est faible plus le degré d'importance du critère d'exploitation est élevé. [0039] La troisième étape 203 consiste à modéliser sous la forme quadratique chacun des indices de chaque source Si, S2, S3 qui sont associés aux critères d'exploitation du réseau 100. Ainsi, à titre d'exemple, si C2s1, C2s2, C2s3 représente le coût énergétique de chaque source Si, S2, S3 débitant respectivement des puissances W1, W2, W3 alors cette troisième étape permet de formuler le coût énergétique de chaque source de la manière suivante : = :7210 C2s, -) = C2s'(1 )= [0040] La quatrième étape 204 est une étape d'optimisation sous contrainte consistant à déterminer, en temps réel, le minimum ou le maximum de chacun des critères d'exploitation du réseau en fonction des contraintes de fonctionnement du réseau à l'instant donné. Ainsi, dans l'exemple précédemment énoncé, la quatrième étape 204 permet de : minimiser : :2eq, =2i + 2s, + sous les contraintes de fonctionnement à l'instant donné du calcul : [0041] Pour cela, le problème d'optimisation est le suivant : on cherche à trouver les puissances de chaque source Wl, W2, W3, tel que : avec les contraintes : =0 [0042] Une première sous-étape 214 consiste à construire l'algorithme de résolution au moyen de multiplicateurs de Lagrange de sorte que chacun des critères d'exploitation du réseau soit énoncé sous la forme d'une équation linéaire de type A -X = b. [0043] Par conséquent le problème d'optimisation énoncé précédemment devient, par l'intégration des multiplicateurs de Lagrange, le problème suivant : selon l'exemple de réalisation décrit précédemment, on cherche à déterminer les puissances de chaque source W1, W2, W3 ainsi que le multiplicateur de Lagrange À, tel que : Soit sous la forme matricielle A = 2 x , TV, + + = 0 + b1 +2 = 0 + c +2 = 0 _ =0 =0 Avec les contraintes : [0044] Une deuxième sous-étape 224 consiste à résoudre les équations linéaires A°X = b déterminées lors de la première sous-étape 214 par l'utilisation de la méthode des gradients conjugués de manière à déterminer la solution en au moins n itérations (n étant la taille du système). . [0045] Une troisième sous-étape 234 consiste à vérifier les contraintes d'inégalités pour les solutions trouvées. Si les contraintes sont vérifiées alors le problème est résolu ; en revanche, si au moins une contrainte n'est pas vérifiée alors on fixe la valeur correspondante à sa borne supérieure ou inférieure et on recommence la résolution du reste du problème avec une dimension qui est à présent réduite (n - 1). [0046] Lorsque que l'optimisation est réalisée et les solutions déterminées, les consignes de pilotage sont distribuées aux sources du réseau Si, S2, S3 dans une cinquième étape 205. [0047] La méthode de gestion selon l'invention permet donc de déterminer en temps réel une configuration de l'installation électrique qui satisfait prioritairement les critères définis comme les plus importants lors de la deuxième étape 202, en prenant en compte des objectifs ou des contraintes du réseau à chaque instant de calcul. EXEMPLE DE REALISATION [0048] Afin d'appréhender les gains réalisés en utilisant la méthode de gestion des flux énergétiques du réseau selon l'invention par rapport aux méthodes de l'état de la technique, une comparaison est effectuée entre une gestion optimale, telle que présentée selon l'invention et une gestion classique, sur un exemple de performances en termes de coût d'exploitation et d'impact environnementale. [0049] Dans cet exemple de réalisation, on supposera que les coûts d'exploitation du réseau sont définis par les critères suivants : Avec : : Coûts d'exploitation du réseau ; : Impact environnemental ; : Coût de l'énergie ; : Coût de maintenance. [0050] Dans cet exemple de réalisation, trois sources sont choisies de la façon suivante : - la source 1 Si correspond à une source d'énergie d'origine éolienne ; - la source 2 S2 correspond à une source d'énergie d'origine photovoltaïque ; - la source 3 S3 correspond à une source d'énergie d'origine fossile. [0051] La figure 5 illustre sous la forme de trois histogrammes les caractéristiques des trois sources Si, S2, S3, définies précédemment, sur les critères d'exploitation : , les caractéristiques étant définies sur une échelle de 1 à 10. [0052] Ainsi, lors de la troisième étape 203 de modélisation sous la forme quadratique des critères d'exploitation, on obtient le coût cumulé d'exploitation par source sous la forme suivante : - Pour la source 1 . - Pour la source 2 : - Pour la source 3 : Avec les contraintes suivantes : E E 1.71 E ri.71 [0053] Dans cet exemple de réalisation, le réseau comporte cinq charges présentant des caractéristiques de puissance absorbée et de résistance propres. La figure 6 illustre un exemple des puissances absorbées et des résistances associées pour chacune des charges du réseau et la figure 7 illustre sous la forme d'un tableau l'évolution de la puissance nécessaire sur le réseau qui sera simulé pour alimenter ces charges en fonction du temps sur une période de 90 secondes. [0054] Les graphiques illustrés aux figures 9a, 9b, 9c illustrent la répartition des courants délivrés par les sources du réseau en fonction de la sollicitation des charges donnée à la figure 7 et en fonction des contraintes du réseau. [0055] On notera que sur chacune des figures 9a, 9b, 9c comporte deux courbes. Une première courbe illustre la consigne de pilotage délivrée par le calculateur et une deuxième courbe correspondant à la réponse de la source. On remarque qu'à chaque modification de la puissance nécessaire pour alimenter le réseau, un léger décalage apparaît entre les deux courbes due au temps de réponse des sources du réseau.. [0056] Le tableau de la figure 8 illustre les gains réalisés sur cet exemple de réalisation en comparaison avec une méthode de gestion classique de l'état de la technique. On observe ainsi que le gain en coût d'exploitation varie en fonction de la puissance appelée cotée charge et en fonction du paramétrage des fonctions de coûts pour les sources. Ainsi, sur cette simulation la méthode de gestion selon l'invention permet de réaliser un gain jusqu'à 28% sur une période donnée. [0057] Ainsi, la méthode de gestion proposée par l'invention est basée uniquement sur la résolution d'un problème d'optimisation sous contraintes. La méthode des multiplicateurs de Lagrange et l'algorithme des gradients conjugués permettent d'arriver à un algorithme global que le calculateur peut rapidement mettre en exécution et mettre à jour en temps réel en fonction des données du réseau évoluant à chaque instant.20These various operating criteria C1, C2, C3, C4, C5 to be taken into account are for example: the power delivered; - operating mode ; - the energy cost; - the amount of energy stored; - reliability; - the environmental impact; - lifetime ; - maintenance cost; - dimensioning; Thus, each source 51, S2, S3 of the network 100 has different characteristics for each operating criterion of the network 100. FIG. 2 illustrates in the form of a histogram the characteristics of a source of the network. network 100 (for example the source Si) on five operating criteria Ci, C2, C3, C4, C5. For each criterion of exploitation Ci, C2, C3, C4, C5 is thus associated an index representing the characteristics of the source. This index is for example a value on a scale of 0 to 10 as represented in FIG. 2. This distribution advantageously makes it possible to characterize, on the same scale, each source 51, S2, S3 of the network 100 on all the criteria of FIG. operation of the network 100 predefined. It will be noted that Figure 2 represents a distribution on a selection of five operating criteria; of course the list of criteria given above is not exhaustive. The sources Si, S2, S3 are sources of different nature, for example wind turbines, photovoltaic panels, sources producing electrical energy from fossil energy, etc. The sources Si, S2, S3 of the network 100 are sources whose resources are limited in time and / or whose production of electrical energy is variable over time. Thus the sources of the network 100 according to the invention are different from nuclear-type sources whose resources are considered continuous. The sources are sources of low and / or medium power whose sum of the powers of the network is typically less than 10 MW. Thus, the sources of the network are different from the sources of type nuclear power plant. The computer 30 comprising the management algorithm is directly connected to the network 100 and network facilities and is programmed via the HMI 20. Thus, the computer 30 receives as input: - measurements from the facilities to identify the state of the sources, the state of the network equipment and the state of the network loads; - Setpoint criteria of the network thus forming the constraints of the management algorithm; - information on the future state of the installation; for example on the loads, the available resources, the breakdowns, the forecast maintenances on the installation. FIG. 4 represents a block diagram illustrating the various steps of the management method according to the invention. The management method according to the invention consists in a first step 201 to determine or identify the operating criteria of the network 100 according to the power generation sources of the network. This first step 201 makes it possible to qualify the various sources of electrical energy of the network. In a second step 202, the operating criteria identified are prioritized by the addition of a priority coefficient according to the importance given to each of the criteria. In this respect, Figure 3 illustrates an example of weighting of the operating criteria by the addition of a higher or lower priority coefficient. In the exemplary embodiment illustrated, the lower the value of the priority coefficient, the higher the degree of importance of the operating criterion. The third step 203 consists in modeling in the quadratic form each of the indices of each source Si, S2, S3 which are associated with the operating criteria of the network 100. Thus, for example, if C2s1, C2s2, C2s3 represents the energy cost of each source Si, S2, S3 respectively delivering powers W1, W2, W3 while this third step makes it possible to formulate the energy cost of each source as follows: =: 7210 C2s, -) = C2s' (1) = [0040] The fourth step 204 is a constrained optimization step consisting in determining, in real time, the minimum or the maximum of each of the operating criteria of the network according to the operating constraints of the network in question. the given moment. Thus, in the example previously stated, the fourth step 204 makes it possible to: minimize:: 2eq, = 2i + 2s, + under the operating constraints at the given time of calculation: [0041] For this, the problem of optimization is the following: we seek to find the powers of each source Wl, W2, W3, such that: with the constraints: = 0 [0042] A first substep 214 consists in constructing the resolution algorithm by means of multipliers of Lagrange so that each of the network's operating criteria is expressed in the form of a linear equation of type A -X = b. Consequently, the problem of optimization stated above becomes, by the integration of the Lagrange multipliers, the following problem: according to the embodiment described above, it is sought to determine the powers of each source W1, W2, W3. as well as the Lagrange multiplier A, such that: In the matrix form A = 2 x, TV, + + = 0 + b1 + 2 = 0 + c + 2 = 0 = 0 = 0 With the constraints: [0044 A second substep 224 consists of solving the linear equations A ° X = b determined during the first substep 214 by the use of the conjugate gradient method so as to determine the solution in at least n iterations (n being the size of the system). . A third substep 234 is to check the inequality constraints for the solutions found. If the constraints are checked then the problem is solved; on the other hand, if at least one constraint is not satisfied then the corresponding value is fixed at its upper or lower bound and the resolution of the rest of the problem is resumed with a dimension which is now reduced (n - 1). When the optimization is carried out and the solutions determined, the control instructions are distributed to the sources of the network Si, S2, S3 in a fifth step 205. The management method according to the invention thus makes it possible to determining in real time a configuration of the electrical installation that satisfies priority criteria defined as the most important in the second step 202, taking into account objectives or constraints of the network at each time of calculation. EXEMPLARY EMBODIMENT In order to apprehend the gains made by using the method of managing the energy flows of the network according to the invention compared to the methods of the state of the art, a comparison is made between optimal management, such as that presented according to the invention and conventional management, on an example of performance in terms of operating cost and environmental impact. In this embodiment, it will be assumed that the operating costs of the network are defined by the following criteria: With: Network operating costs; : Environmental impact ; : Cost of energy; : Maintenance cost. In this embodiment, three sources are chosen as follows: the source 1 Si corresponds to a wind energy source; source 2 S2 corresponds to a source of energy of photovoltaic origin; source 3 S3 corresponds to a source of energy of fossil origin. FIG. 5 illustrates in the form of three histograms the characteristics of the three sources Si, S2, S3, defined above, on the operating criteria:, the characteristics being defined on a scale of 1 to 10. [0052] Thus, during the third step 203 modeling in the quadratic form of the operating criteria, we obtain the cumulative exploitation cost by source in the following form: - For source 1. - For source 2: - For source 3: With the following constraints: E E 1.71 E ri.71 [0053] In this exemplary embodiment, the network comprises five loads having characteristics of absorbed power and own resistance. FIG. 6 illustrates an example of the absorbed powers and the associated resistances for each of the loads of the network and FIG. 7 illustrates in the form of a table the evolution of the necessary power on the network which will be simulated to feed these charges in function time over a period of 90 seconds. The graphs illustrated in FIGS. 9a, 9b and 9c illustrate the distribution of the currents delivered by the sources of the network as a function of the load demand given in FIG. 7 and as a function of the constraints of the network. Note that in each of Figures 9a, 9b, 9c has two curves. A first curve illustrates the control setpoint delivered by the computer and a second curve corresponding to the response of the source. It is noted that each time the power required to power the network is changed, a slight difference appears between the two curves due to the response time of the network sources. The table in FIG. 8 illustrates the gains made on this network. embodiment in comparison with a conventional management method of the state of the art. It can thus be seen that the gain in operating cost varies according to the power demand called on the load and according to the setting of the cost functions for the sources. Thus, on this simulation, the management method according to the invention makes it possible to achieve a gain of up to 28% over a given period. Thus, the management method proposed by the invention is based solely on the resolution of an optimization problem under constraints. The Lagrange multiplier method and the conjugated gradient algorithm allow to arrive at a global algorithm that the computer can quickly put into execution and update in real time according to the data of the network evolving at every moment.

Claims (3)

REVENDICATIONS1. Méthode de gestion pour la distribution de l'énergie électrique d'un réseau ilôté (100), ledit réseau ilôté comportant : une pluralité de sources d'énergie électrique (Si, 52, S3) ; une pluralité de charges (10) consommant ladite énergie électrique produite par lesdites sources (Si, 52, S3) ; des moyens de gestion et de distribution à ladite pluralité de charges (10) de l'énergie électrique produite par ladite pluralité de sources (S1, S2, S3), les moyens de gestion et de distribution étant formés par un calculateur (30) et par une interface homme/machine (20) ; ladite méthode étant caractérisée en ce qu'elle comporte : une étape (201) d'identification d'un ensemble de critères d'exploitation (Cl, C2, C3, C4, C5) qualifiant les différentes sources d'énergie électrique (S1, S2, S3) du réseau (100), chaque source (S1, S2, S3) dudit réseau (100) présentant un indice associé à chacun des critères d'exploitation (C1, C2, C3, C4, C5) ; une étape (203) de modélisation sous la forme quadratique de chacun des indices de chaque source (Si, S2, 53); une étape (204) d'optimisation sous contrainte consistant à déterminer, en temps réel, le minimum ou le maximum de chaque critère (C1, C2, C3, C4, C5) du réseau (100) en fonction des contraintes du réseau à l'instant donné ; ladite quatrième étape comportant : une première sous-étape (214) de construction de l'algorithme de résolution au moyen de multiplicateurs de Lagrange de sorte que chaque critère (C1, C2, C3, C4, C5) du réseau soit énoncé sous la forme d'une équation linéaire [A].[X]=[b] avec : [A] représentant une matrice de dimension n x n, avec n nombre entier, représentant le nombre de sources du réseau additionné au nombre de contraintes par critère d'exploitation, [b] représentant une matrice colonne à n lignes ;- [X] représentant une matrice colonne à n lignes représentant les solutions de l'algorithme ; une deuxième sous-étape (224) de résolution des équations linéaires [A].[X]=[b] en utilisant la méthode des gradients conjugués de manière à résoudre lesdites équations linéaires en au moins n itérations ; - une troisième sous-étape (234) de vérification des contraintes d'inégalités ; une étape (205) de distribution des consignes de pilotage aux sources (S1, S2, S3) dudit réseau (100).REVENDICATIONS1. A management method for distributing electrical energy of an on-grid network (100), said remote network comprising: a plurality of electric power sources (Si, 52, S3); a plurality of charges (10) consuming said electrical energy produced by said sources (Si, 52, S3); means for managing and distributing to said plurality of charges (10) the electrical energy produced by said plurality of sources (S1, S2, S3), the management and distribution means being formed by a computer (30) and by a man / machine interface (20); said method being characterized in that it comprises: a step (201) of identification of a set of operating criteria (C1, C2, C3, C4, C5) qualifying the different sources of electrical energy (S1, S2, S3) of the network (100), each source (S1, S2, S3) of said network (100) having an index associated with each of the operating criteria (C1, C2, C3, C4, C5); a step (203) modeling in the quadratic form of each of the indices of each source (Si, S2, 53); a constrained optimization step (204) of determining, in real time, the minimum or maximum of each criterion (C1, C2, C3, C4, C5) of the network (100) as a function of the network constraints; given moment; said fourth step comprising: a first substep (214) of constructing the resolution algorithm by means of Lagrange multipliers so that each criterion (C1, C2, C3, C4, C5) of the network is stated in the form of a linear equation [A]. [X] = [b] with: [A] representing a matrix of dimension nxn, with n integer, representing the number of sources of the network added to the number of constraints per operating criterion , [b] representing an n-row column matrix; - [X] representing a column matrix with n rows representing the solutions of the algorithm; a second substep (224) of solving the linear equations [A]. [X] = [b] using the conjugate gradient method so as to solve said linear equations in at least n iterations; a third substep (234) for checking inequality constraints; a step (205) for distributing control commands to the sources (S1, S2, S3) of said network (100). 2. Méthode de gestion pour la distribution de l'énergie électrique d'un réseau ilôté (100) selon la revendication précédente caractérisé en ce qu'elle comporte, postérieurement à l'étape d'identification (201), une étape (202) de hiérarchisation desdits critères d'exploitation (Cl, C2, C3, C4, C5) par ordre de priorité par l'adjonction d'un coefficient de priorité via l'interface Homme/Machine.2. Management method for the distribution of the electrical energy of an island network (100) according to the preceding claim characterized in that it comprises, after the identification step (201), a step (202). prioritizing said operating criteria (C1, C2, C3, C4, C5) in order of priority by adding a priority coefficient via the Man / Machine interface. 3. Réseau ilôté caractérisé en ce qu'il comporte : des sources d'énergie d'origine éolienne et/ou des sources d'énergie d'origine photovoltaïque et/ou des sources d'énergie d'origine fossile ; des moyens de gestion et de distribution de l'énergie électrique mettant en oeuvre ladite méthode de gestion pour la distribution de l'énergie électrique d'un réseau ilôté (100) selon l'une des revendications précédentes.253. Ilôté network characterized in that it comprises: wind energy sources and / or sources of energy of photovoltaic origin and / or sources of energy of fossil origin; means for managing and distributing electrical energy implementing said management method for distributing the electrical energy of an island network (100) according to one of the preceding claims.
FR1460503A 2014-10-31 2014-10-31 METHOD OF MANAGING THE REAL-TIME ELECTRIC POWER DISTRIBUTION OVER AN ILOTE NETWORK Pending FR3028080A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
FR1460503A FR3028080A1 (en) 2014-10-31 2014-10-31 METHOD OF MANAGING THE REAL-TIME ELECTRIC POWER DISTRIBUTION OVER AN ILOTE NETWORK

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
FR1460503A FR3028080A1 (en) 2014-10-31 2014-10-31 METHOD OF MANAGING THE REAL-TIME ELECTRIC POWER DISTRIBUTION OVER AN ILOTE NETWORK

Publications (1)

Publication Number Publication Date
FR3028080A1 true FR3028080A1 (en) 2016-05-06

Family

ID=53298421

Family Applications (1)

Application Number Title Priority Date Filing Date
FR1460503A Pending FR3028080A1 (en) 2014-10-31 2014-10-31 METHOD OF MANAGING THE REAL-TIME ELECTRIC POWER DISTRIBUTION OVER AN ILOTE NETWORK

Country Status (1)

Country Link
FR (1) FR3028080A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP3255594A1 (en) * 2016-06-10 2017-12-13 Schneider Electric Industries SAS Method for controlling the electric power generation of a network for the production and distribution of electric power
EP3454142A1 (en) * 2017-09-12 2019-03-13 Schneider Electric Industries SAS Method for monitoring and controlling an electrical power network

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
DANIEL ZELAZO ET AL: "An energy management system for off-grid power systems", ENERGY SYSTEMS, vol. 3, no. 2, 31 January 2012 (2012-01-31), pages 153 - 179, XP055129534, ISSN: 1868-3967, DOI: 10.1007/s12667-012-0050-4 *
KENNETH H. CARPENTER: "Lagrange Multipliers for Quadratic Forms With Linear Constraints", ECE.K-STATE.EDU/PEOPLE/FACULTY/CARPENTER/DOCUMENTS/LAGRANGE.PDF, October 2005 (2005-10-01), XP009185697 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP3255594A1 (en) * 2016-06-10 2017-12-13 Schneider Electric Industries SAS Method for controlling the electric power generation of a network for the production and distribution of electric power
FR3052579A1 (en) * 2016-06-10 2017-12-15 Schneider Electric Ind Sas METHOD FOR OPTIMIZING THE ELECTRIC POWER GENERATION OF A POWER GENERATION AND DISTRIBUTION NETWORK
CN107492912A (en) * 2016-06-10 2017-12-19 施耐德电器工业公司 Method for optimizing the production of electric power in a network for producing and distributing electric power
EP3454142A1 (en) * 2017-09-12 2019-03-13 Schneider Electric Industries SAS Method for monitoring and controlling an electrical power network
FR3071110A1 (en) * 2017-09-12 2019-03-15 Schneider Electric Industries Sas METHOD FOR MONITORING AND CONTROLLING AN ELECTRICAL NETWORK
US10985561B2 (en) 2017-09-12 2021-04-20 Schneider Electric Industries Sas Method for monitoring and controlling an electrical network

Similar Documents

Publication Publication Date Title
Capizzi et al. Advanced and adaptive dispatch for smart grids by means of predictive models
Paliwal et al. Optimal sizing and operation of battery storage for economic operation of hybrid power system using artificial bee colony algorithm
EP3598598B1 (en) Method and system for determining a voltage state of a low voltage power supply network located at at least one transformer station
Dang-Ha et al. The role of big data on smart grid transition
FR2997804A1 (en) METHOD FOR CONTROLLING A VSC-HVDC MULTI-TERMINAL NETWORK
FR3028080A1 (en) METHOD OF MANAGING THE REAL-TIME ELECTRIC POWER DISTRIBUTION OVER AN ILOTE NETWORK
Tu et al. Optimal sizing and operating strategy of a stand‐alone generation–load–storage system: An island case study
US11398727B2 (en) Method of controlling a microgrid, power management system, and energy management system
Perles An adaptive multi-agent system for the distribution of intelligence in electrical distribution networks: state estimation
EP2688174B1 (en) Method and device for distributing flows of electrical power and electrical system comprising such a device
Silva Optimization of the planning and operations of electric distribution grids in the context of high renewable energy penetration
Hsu et al. A systematic evaluation model for solar cell technologies
CN115577903A (en) Method, device, equipment and medium for evaluating influence of new energy on power grid peak regulation
FR3072794A1 (en) METHOD FOR DETERMINING THE PARAMETERS OF A SIMPLIFIED MODEL OF AN ENERGY STORAGE SYSTEM, A STEERING METHOD USING SUCH A MODEL AND ASSOCIATED DEVICE
EP3454142B1 (en) Method for monitoring and controlling an electrical power network
EP4026217B1 (en) Method for controlling a hybrid system and device therefor
WO2017102732A1 (en) Design and control of a mixed energy generation system
Gui et al. Intra-day unit commitment for wind farm using model predictive control method
Bâra et al. Comparative analysis between wind and solar forecasting methods using artificial neural networks
EP3453095B1 (en) Method, computer program, system, and equipment for optimising the functioning of an electrical current transmission network
FR3105502A1 (en) Method for optimizing the physical model of an energy installation and control method using such a model
FR3143803A1 (en) Method for determining electrical flows within an energy community
US20240195174A1 (en) Energy prediction device, energy prediction method, and energy prediction program
US20240070352A1 (en) Simulating electrical grid transmission and distribution using multiple simulators
EP4203222A1 (en) Method for joint voltage regulation in a medium voltage branch and low voltage branches including a three-phase low voltage branch

Legal Events

Date Code Title Description
PLFP Fee payment

Year of fee payment: 2

PLSC Publication of the preliminary search report

Effective date: 20160506