ES302244A3 - Improvements in the steaming tunnels to accelerate the finishing of finished concrete elements. (Machine-translation by Google Translate, not legally binding)
- Google Patents
Improvements in the steaming tunnels to accelerate the finishing of finished concrete elements. (Machine-translation by Google Translate, not legally binding)
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BAUUNTERNEHMUG LORENZ KESTING
Original Assignee
BAUUNTERNEHMUG LORENZ KESTING
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BAUUNTERNEHMUG LORENZ KESTINGfiledCriticalBAUUNTERNEHMUG LORENZ KESTING
Priority to ES0302244ApriorityCriticalpatent/ES302244A3/en
Publication of ES302244A3publicationCriticalpatent/ES302244A3/en
Improvements in the vaporization tunnels to accelerate the setting of finished concrete elements, characterized in that the vaporization tunnel is subdivided into transportable sections by road, which are reinforced by one or more intermediate bottoms, constituting alignable cells in the form of prismatic bodies open at both ends, whose upper surface (roof) is structured as a work platform, thus also having lanes for the molds in the form of trolleys. (Machine-translation by Google Translate, not legally binding)
ES0302244A1964-07-171964-07-17Improvements in the steaming tunnels to accelerate the finishing of finished concrete elements. (Machine-translation by Google Translate, not legally binding)
ExpiredES302244A3
(en)
Improvements in the steaming tunnels to accelerate the finishing of finished concrete elements. (Machine-translation by Google Translate, not legally binding)
Improvements in the steaming tunnels to accelerate the finishing of finished concrete elements. (Machine-translation by Google Translate, not legally binding)
Improvements in the steaming tunnels to accelerate the finishing of finished concrete elements. (Machine-translation by Google Translate, not legally binding)
Improvements in the steaming tunnels to accelerate the finishing of finished concrete elements. (Machine-translation by Google Translate, not legally binding)
A procedure for the manufacture of large sections of the superstructures of a bridge of various sections. (Machine-translation by Google Translate, not legally binding)
A procedure for forging floors with trapezoid beams of armed concrete and trapezoid blocks (Machine-translation by Google Translate, not legally binding)