EP4051850A1 - Scaffolding and intermediate element therefor - Google Patents
Scaffolding and intermediate element thereforInfo
- Publication number
- EP4051850A1 EP4051850A1 EP20820520.3A EP20820520A EP4051850A1 EP 4051850 A1 EP4051850 A1 EP 4051850A1 EP 20820520 A EP20820520 A EP 20820520A EP 4051850 A1 EP4051850 A1 EP 4051850A1
- Authority
- EP
- European Patent Office
- Prior art keywords
- scaffold
- hook members
- intermediate element
- scaffolding
- scaffold element
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 230000008878 coupling Effects 0.000 claims description 19
- 238000010168 coupling process Methods 0.000 claims description 19
- 238000005859 coupling reaction Methods 0.000 claims description 19
- 229910000831 Steel Inorganic materials 0.000 description 3
- XAGFODPZIPBFFR-UHFFFAOYSA-N aluminium Chemical compound [Al] XAGFODPZIPBFFR-UHFFFAOYSA-N 0.000 description 3
- 229910052782 aluminium Inorganic materials 0.000 description 3
- 239000004411 aluminium Substances 0.000 description 3
- 238000010276 construction Methods 0.000 description 3
- 239000010959 steel Substances 0.000 description 3
- 238000003466 welding Methods 0.000 description 2
- 238000005452 bending Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G5/00—Component parts or accessories for scaffolds
- E04G5/16—Struts or stiffening rods, e.g. diagonal rods
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G7/00—Connections between parts of the scaffold
- E04G7/30—Scaffolding bars or members with non-detachably fixed coupling elements
- E04G7/302—Scaffolding bars or members with non-detachably fixed coupling elements for connecting crossing or intersecting bars or members
- E04G7/303—Scaffolding bars or members with non-detachably fixed coupling elements for connecting crossing or intersecting bars or members the added coupling elements are only fixed at one of the bars or members to connect
- E04G7/304—Scaffolding bars or members with non-detachably fixed coupling elements for connecting crossing or intersecting bars or members the added coupling elements are only fixed at one of the bars or members to connect with tying means for connecting the bars or members
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G7/00—Connections between parts of the scaffold
- E04G7/30—Scaffolding bars or members with non-detachably fixed coupling elements
- E04G7/302—Scaffolding bars or members with non-detachably fixed coupling elements for connecting crossing or intersecting bars or members
- E04G7/303—Scaffolding bars or members with non-detachably fixed coupling elements for connecting crossing or intersecting bars or members the added coupling elements are only fixed at one of the bars or members to connect
- E04G7/305—Scaffolding bars or members with non-detachably fixed coupling elements for connecting crossing or intersecting bars or members the added coupling elements are only fixed at one of the bars or members to connect without tying means for connecting the bars or members
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G7/00—Connections between parts of the scaffold
- E04G7/30—Scaffolding bars or members with non-detachably fixed coupling elements
- E04G7/32—Scaffolding bars or members with non-detachably fixed coupling elements with coupling elements using wedges
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G7/00—Connections between parts of the scaffold
- E04G7/30—Scaffolding bars or members with non-detachably fixed coupling elements
- E04G7/34—Scaffolding bars or members with non-detachably fixed coupling elements with coupling elements using positive engagement, e.g. hooks or pins
Definitions
- the present invention relates to a scaffolding, comprising a system of scaffold elements, comprising uprights and ledgers which extend therebetween and are coupled to the uprights, and comprising at least one intermediate element which mutually connects a first scaffold element and a second scaffold element at least substantially along a mutual perpendicular line.
- a scaffolding of the type described in the preamble is applied on large scale during work at height on buildings and installations.
- a scaffolding of usually tubular uprights and ledgers extending therebetween, these together defining a system of scaffold sections lying adjacently of each other and above each other.
- the ledgers here moreover provide, in addition to a structural cohesion, a basis for placing floor parts whereby the scaffold sections are accessible to and can be walked on by workers.
- An additional ledger is often arranged on an exposed side halfway along a scaffold section and serves here as rail and fall protection.
- the scaffolding is usually anchored mechanically to the structure and provides from that moment a safe working environment from which maintenance and building operations can be carried out. For sufficient strength and load-bearing capacity, intermediate elements are often arranged diagonally between adjacent scaffold elements, and thereby form a diagonal.
- the present invention has for its object, among others, to provide a scaffolding with an intermediate element which can be placed therein in efficient manner.
- a scaffolding of the type described in the preamble has the feature according to the invention that the intermediate element comprises an elongate body from which extends at a distal outer end a set of at least substantially parallel hook members, each having an at least substantially cup-like jaw which engages round the first scaffold element connected thereto, wherein the hook members have an opposite orientation so that the jaws engage round the first scaffold element from opposite sides and here maintain a mutual distance which is greater than a distance between the opposite sides of the first scaffold element.
- Said perpendicular line extends here particularly along a diagonal between the two scaffold elements connected thereby.
- the scaffolding according to the invention more particularly has the feature here that by a rotation of the intermediate element about an axis thereof the hook members are adjustable between a position in which they engage round the first scaffold element and a position in which they release the first scaffold element. In this latter position the intermediate element can be disengaged from the first scaffold element in simple manner, while it is coupled thereto in the first stated position.
- Said axis coincides here at least substantially with the perpendicular line along which the intermediate element connects the two scaffold elements mutually connected thereby.
- the scaffold element For a coupling of the intermediate element at this distal outer end to the first scaffold element it thus suffices for the scaffold element to be brought between the two hook members, after which a connection to the scaffold element can be brought about by a simple rotation of the intermediate element about its longitudinal axis. Coupling and disengaging of the intermediate element can thus be performed wholly on site.
- a scaffolder is able to perform these manipulations at a distance from the first scaffold element and need not kneel down for this purpose, nor reach or move to a different position. The same applies when the scaffolding is dismantled afterwards, wherein the two manipulations are performed in reverse order.
- the scaffolding according to the invention is characterized in that the first scaffold element is tubular and the hook members are at least substantially identical in form and each have a substantially U-shaped jaw.
- the scaffolding is thereby in line with common scaffold elements which are generally constructed from tubular scaffold elements.
- the hook members here particularly have a U-shaped jaw with a curve which is concentric to the first scaffold element.
- a preferred embodiment of the scaffolding according to the invention is more particularly characterized here in that the hook members lie round the first scaffold element in at least substantially form-fitting manner. Such a placement of the intermediate element on the first scaffold element minimizes a mutual clearance, which enhances the rigidity and strength of the scaffolding.
- the invention is applicable in principle to many forms and embodiments of the intermediate element
- a particularly practical embodiment of the scaffolding has the feature according to the invention that the intermediate element comprises a duct-like body and is particularly tubular. Such a construction is in line with common scaffold elements in a scaffolding.
- a further preferred embodiment of the scaffolding has here the feature according to the invention that the hook members are mounted on opposite flanks of the intermediate element, and more particularly that the hook members are substantially plate-like, at least were separated from a plate.
- the hook members thus comprise a set of side pieces which are connected to the duct-like body by means of common connecting techniques, such as welding or screwing, in order to receive therebetween the scaffold element to be connected.
- a further preferred embodiment of the scaffold element has the feature according to the invention that the intermediate element comprises at an opposite, second distal outer end a scaffold coupling and, with interposing thereof, is coupled non-rotatably to a second scaffold element.
- the scaffold coupling thus prevents a rotation of the intermediate element, whereby the connection at the opposite outer end would otherwise be broken.
- the scaffold coupling comprises a set of at least substantially parallel hook members which extend from the second outer end of the intermediate element and each engage with an at least substantially cup-like jaw round the second scaffold element connected thereto, wherein the hook members have at least substantially the same orientation so that the jaws engage round the second scaffold element from the same side, wherein a latch is provided which locks the second scaffold element non-rotatably from an opposite side.
- the hook members can here be similar or even identical to the hook members which are applied at the first outer end, albeit that the two hook members are here connected to the intermediate element in the same orientation.
- the latch locks the second scaffold element in the coupling and thus prevents breaking of the scaffold coupling and furthermore a rotation of the intermediate element about its axis, so that the opposite coupling to the first scaffold element is also locked thereby.
- the scaffolding according to the invention is characterized here in that the second scaffold element is tubular and the scaffold coupling comprises a tube clamp which engages clampingly round the second scaffold element.
- the tube clamp provides for a tightly clamped connection to the second scaffold element and furthermore prevents a rotation of the intermediate element about its axis, so that the opposite coupling to the first scaffold element is also locked.
- the invention also relates to an intermediate element of the type as applied in the scaffolding according to one or more of the preceding claims, comprising an elongate body having on at least one distal outer end a set of hook members which have mutually opposite orientations and each have a jaw, which jaws open toward each other so as to receive therein a joint scaffold element.
- Figure 1 shows an exemplary embodiment of a scaffolding according to the invention
- Figure 2 shows a side view of an intermediate element as applied in the scaffolding of figure 1;
- Figure 3 shows a perspective view of a first distal outer end of the intermediate element of figure 2;
- Figure 4 shows a perspective view of an opposite, second distal outer end of the intermediate element of figure 2.
- Figures 5A-5F show the scaffolding of figure 1 at successive stages of a fastening of the intermediate element of figure 2 therein.
- Figure 1 shows a common system of mutually connected uprights 10 and horizontal ledgers 20 from which a scaffolding can be constructed.
- the horizontal ledgers 20 are coupled to uprights 10 by means of system couplings 12, for which purpose the uprights are provided at regular distances with such couplings and the ledgers are provided at their outer ends with matching coupling members.
- This example relates to a so-called cuplock system, although the invention can likewise be applied in other types of system scaffolds and also in non-system scaffolds, wherein a mutual connection between uprights and ledgers is brought about only or mainly by means of tube couplings. From a viewpoint of strength and durability, use is usually made here of thick-walled hollow scaffold elements of steel or aluminium; so-called scaffolding tubes or scaffolding pipes.
- the scaffolding can comprise both in height direction and laterally a plurality of the construction shown in figure 1 and thereby completely cover an outer wall portion to be worked on.
- the (lowermost) uprights 10 have at their base a rotatable foot 15 whereby uprights 10 can be adjusted if necessary, so that the whole is securely positioned.
- ledgers 20 also serve as a basis for scaffold floor parts from which a scaffold floor is constructed per level.
- Intermediate elements 30, which form a diagonal in the scaffolding in and/or outside a scaffold section, are arranged for the purpose of additional load-bearing capacity and rigidity.
- an intermediate element 30 is arranged between a first ledger 21 and a second ledger 22, each at a different level, but such intermediate elements can also be applied between ledgers at the same level and between uprights, optionally in the same row.
- the intermediate element comprises an elongate duct-like body, in this case with a rectangular and even square cross-section, for which use is in practice also made of aluminium or steel. Instead of this, it is also possible to opt for a tube body with a round cross-section, and a solid body can also be applied, although with a view to weight and bending stiffness use is preferably made of a hollow duct-like body.
- the two hook members 31, 32 extend from intermediate element 30, see also figures 2 and 3.
- the two hook members comprise a U-shaped jaw 40 whereby the hook members engage round a first ledger 21, see also figure 2.
- the two hook members are substantially plate-like and were therefore separated from a steel or aluminium plate, typically with a material thickness of between 5 and 15 millimetres.
- the two hook members 31, 32 are connected by means of screwing or welding to the distal outer end of the intermediate element 30.
- the flanks of the rectangular tube which is used for intermediate element 30 in this example provide an ideal mounting base for hook members 31, 32.
- the two hook members have here an opposite orientation so that the two hook members 31, 32 will engage from opposite sides round the first ledger 21 to be connected thereto.
- Hook members 31, 32 maintain a mutual distance w which roughly corresponds to a diameter of ledger 21 or is (slightly) greater.
- the intermediate element has on an opposite, second distal outer end a similar set of hook members 33, 34, see figure 4. Other than the first set of hook members 31, 32, this set has the same orientation, and both hook members fall with their U-shaped jaw 40 from a common side over second ledger 22.
- a latch 35 locks the second scaffold element 22 on an opposite side. Latch 35 is here wedge-shaped and is arranged via a wedge mortise 36, see figure 4, with clamping fit between on one side the outer end of intermediate element 30 and on the other the second scaffold element 22, so that a non-rotatable, play-free locking and connection is obtained.
- FIGS 5A-5F show schematically successive stages of the fastening of the intermediate element 30 to the two ledgers 21, 22.
- Intermediate element 30 is firstly placed with the first distal outer end, which is provided with the two hook members 31, 32 with opposite orientation, at first ledger 21, see figure 5A.
- Intermediate element 30 is placed with both hook members 31, 32 over ledger 21, wherein ledger 21 is received between the two hook members, see figure 5B.
- Hook members 31, 32 now lie with their jaw parallel to an axis of ledger 21 and are not yet connected. The distance w here allows ledger 21 to be received between the two hook members 31, 32.
- intermediate element 30 now lies immovably between the two ledgers 21, 22, and provides thereby additional load-bearing capacity and structural cohesion in the scaffolding. It is only at the position of the second scaffold element 22 that the scaffolder had to be present in order to knock latch 35 into place there.
- the invention thereby provides a particularly practical intermediate element 30 which can be advantageously applied in scaffolding of diverse nature and size.
- first distal outer end of the intermediate element is thus provided with a set of hook members with opposite orientation, but a similar set can also be provided at the opposite, second distal outer end.
- a tube clamp can also be provided at the second distal outer end for the purpose of a connection to the second ledger or the second scaffold element.
- a similar connection is also possible between opposite uprights.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mutual Connection Of Rods And Tubes (AREA)
Abstract
Description
Claims
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
NL1043444A NL1043444B1 (en) | 2019-10-31 | 2019-10-31 | Scaffolding and supporting element for it |
PCT/IB2020/060052 WO2021084412A1 (en) | 2019-10-31 | 2020-10-27 | Scaffolding and intermediate element therefor |
Publications (2)
Publication Number | Publication Date |
---|---|
EP4051850A1 true EP4051850A1 (en) | 2022-09-07 |
EP4051850B1 EP4051850B1 (en) | 2024-10-09 |
Family
ID=73740433
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP20820520.3A Active EP4051850B1 (en) | 2019-10-31 | 2020-10-27 | Scaffolding and intermediate element therefor |
Country Status (3)
Country | Link |
---|---|
EP (1) | EP4051850B1 (en) |
NL (1) | NL1043444B1 (en) |
WO (1) | WO2021084412A1 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CH717986A1 (en) * | 2020-10-22 | 2022-04-29 | Vitra Ag | Cross brace and furniture kit. |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR1587165A (en) * | 1968-10-21 | 1970-03-13 | ||
DE7128051U (en) * | 1971-07-22 | 1971-12-09 | Lawil Ag | STRENGTHENING ELEMENT FOR METAL FRAMEWORK |
DE20005629U1 (en) * | 2000-03-25 | 2000-06-29 | Krause-Werk GmbH & Co KG, 36304 Alsfeld | strut |
KR101011595B1 (en) * | 2010-09-14 | 2011-01-27 | 주식회사 한발 | Assembly method of block scaffolding and block scaffolding with trolley and stand assembly type scaffold operated during uneven movement and assembling |
-
2019
- 2019-10-31 NL NL1043444A patent/NL1043444B1/en active
-
2020
- 2020-10-27 WO PCT/IB2020/060052 patent/WO2021084412A1/en unknown
- 2020-10-27 EP EP20820520.3A patent/EP4051850B1/en active Active
Also Published As
Publication number | Publication date |
---|---|
EP4051850B1 (en) | 2024-10-09 |
NL1043444B1 (en) | 2021-07-19 |
WO2021084412A1 (en) | 2021-05-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US9719267B2 (en) | High capacity vertical member for use with modular scaffolding | |
US6151851A (en) | Stackable support column system and method for multistory building construction | |
US8393439B2 (en) | Scaffold system and method | |
US9861190B2 (en) | Wood gang form and method for constructing concrete building using same | |
EP2880228B1 (en) | Scaffold structure | |
MX2013008244A (en) | Scaffold apparatus, method and system. | |
EP4051850B1 (en) | Scaffolding and intermediate element therefor | |
CN107912050B (en) | Scaffold clamp | |
GB2537067A (en) | Suspended platform system | |
US3323271A (en) | Framework systems | |
RU2603645C2 (en) | Connecting element for scaffolding | |
WO2011005087A1 (en) | Forkhead for use in a modular scaffolding system, and method of constructing a scaffold frame using the same | |
WO2015188249A1 (en) | Scaffolding section | |
JPH08312164A (en) | Clamp for post and reinforcing material with the clamp | |
CN111219046A (en) | Composite scaffold erecting structure and construction process thereof | |
CN1022430C (en) | Composite steel pipe scaffolding | |
US20190330862A1 (en) | Scaffolding system for use with curvilinear walls and method of use | |
EP1327733A2 (en) | Module for cantilevered scaffolding | |
CN214785944U (en) | Portable high strength formwork structure | |
US20150144427A1 (en) | Scaffold extension systems and methods | |
CN211598005U (en) | Rail guard is used in engineering construction | |
JP3020115U (en) | The frame of the material receiving landing | |
WO2017011860A1 (en) | Method of lifting panel with inserts | |
CN2573611Y (en) | Combined floor type steel pipe scaffold | |
WO2007012107A1 (en) | Hook-on scaffold |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: UNKNOWN |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE INTERNATIONAL PUBLICATION HAS BEEN MADE |
|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE |
|
17P | Request for examination filed |
Effective date: 20220531 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
DAV | Request for validation of the european patent (deleted) | ||
DAX | Request for extension of the european patent (deleted) | ||
P01 | Opt-out of the competence of the unified patent court (upc) registered |
Effective date: 20230602 |
|
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: GRANT OF PATENT IS INTENDED |
|
INTG | Intention to grant announced |
Effective date: 20240216 |
|
GRAJ | Information related to disapproval of communication of intention to grant by the applicant or resumption of examination proceedings by the epo deleted |
Free format text: ORIGINAL CODE: EPIDOSDIGR1 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE |
|
INTC | Intention to grant announced (deleted) | ||
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: GRANT OF PATENT IS INTENDED |
|
INTG | Intention to grant announced |
Effective date: 20240603 |
|
GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE PATENT HAS BEEN GRANTED |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |