EP3530814B1 - Method for the construction of a transformer platform and foundation set for a transformer platform - Google Patents
Method for the construction of a transformer platform and foundation set for a transformer platform Download PDFInfo
- Publication number
- EP3530814B1 EP3530814B1 EP19159324.3A EP19159324A EP3530814B1 EP 3530814 B1 EP3530814 B1 EP 3530814B1 EP 19159324 A EP19159324 A EP 19159324A EP 3530814 B1 EP3530814 B1 EP 3530814B1
- Authority
- EP
- European Patent Office
- Prior art keywords
- piles
- seabed
- platform
- pile driver
- location
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000000034 method Methods 0.000 title claims description 21
- 238000010276 construction Methods 0.000 title 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 5
- 238000005553 drilling Methods 0.000 description 2
- 241001136792 Alle Species 0.000 description 1
- 235000021168 barbecue Nutrition 0.000 description 1
- 238000006073 displacement reaction Methods 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/52—Submerged foundations, i.e. submerged in open water
- E02D27/525—Submerged foundations, i.e. submerged in open water using elements penetrating the underwater ground
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B17/00—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D7/00—Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
- E02D7/02—Placing by driving
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B17/00—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
- E02B17/02—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor placed by lowering the supporting construction to the bottom, e.g. with subsequent fixing thereto
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B17/00—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
- E02B2017/0039—Methods for placing the offshore structure
- E02B2017/0043—Placing the offshore structure on a pre-installed foundation structure
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B17/00—Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
- E02B2017/0056—Platforms with supporting legs
Definitions
- the invention relates to a method for establishing a substation platform with at least three piles.
- the invention also relates to the transformer platform, which is preferably installed using such a method and has at least three piles, and a foundation set for carrying out the method.
- Substation platforms Due to the expansion of wind energy in the offshore area, substation platforms are becoming necessary. The electricity generated by the individual wind turbines is transformed on the substation platforms and brought to shore from there via a cable. Substation platforms or converter platforms are installed in particular on the German west coast in the North Sea. The area is characterized by extremely high and energetic waves with comparatively shallow water. Known foundation structures such as jackets have a high degree of obstruction and therefore attract high loads by design, making them heavy in design and therefore expensive. It is known to provide pile foundations for substation platforms, in the foundation of which a template is arranged on the seabed and the piles are rammed through the template into the seabed. Several different pile drivers are used for this purpose.
- a disadvantage of the known ramming methods is that they do not work with sufficient precision or are relatively expensive.
- a method for establishing an offshore platform in which a buoyant platform with raised support legs is brought to the location, some of the support legs are first temporarily extended and the platform is lifted out of the water using a jacking system and then piles using a hammer are rammed into the seabed and the provisionally lowered support legs are additionally rammed further into the seabed.
- the object of the present invention is, in a first aspect, to improve an initially mentioned method for founding a substation platform and, in a second aspect, to provide an improved foundation set with which the substation platform can be founded.
- the method according to the invention makes use of the idea of using exactly one piling device that is brought to the location and that is supported on the seabed by means of extendable support legs.
- the piling device can be a jack-up platform or the like, which preferably has a crane and a hammer.
- ramming is to be understood here in a very general manner. Ramming is also to be understood, for example, as drilling.
- a piling device can also be understood here as a drill or a drilling device.
- Templates are attached to the pile driver.
- the templates can be arranged on the outside or inside of a platform of the piling rig, the relative distance between the templates corresponds exactly to the position of the posts of the substation on the seabed, the posts are each rammed vertically into the seabed one after the other.
- the piles are each inserted through a ramming template assigned to them on the substation platform. They are favorably suspended vertically.
- the piles are driven into the seabed one after the other, preferably while maintaining the position of the piling rig.
- the support legs of the pile driver are preferably not changed during the entire pile driving process.
- the piles driven into the seabed remain at the same level as or above the driving template assigned to them. "Up” and “down” refer to orientations away from the seabed and toward the seabed, respectively.
- the support legs of the piling rig are then retracted and the piling rig is moved away from the location with the support legs retracted.
- the tops of the piles project above the sea surface, preferably all at the same height.
- the relative distances between the upper ends of the piles correspond exactly to the relative distances of supports of a platform top which is placed on top of the ends of the piles.
- the piles are rammed into the ground until the upper ends are at most level with the ramming template, preferably +3 m, preferably +2 m, preferably up to +1 m, preferably +0.5 m above the ramming template.
- the top ends are not rammed through the template.
- the arrangement of the driving templates corresponds exactly to the relative arrangement of the supports of the platform top as well as the contact points of the piles with the seabed in a horizontal plane.
- the platform upper part which is brought to the location and is placed on the upper pile ends at the location, is arranged on a grillage and on a pontoon.
- a bottom of the platform top has a height above the sea surface when moving to location, which is higher than all ends of the piles above the sea surface.
- the pontoon is lowered after the upper part of the platform has been moved over the piles and placed on the ends of the piles.
- the pontoon is arranged relative to the posts in such a way that when the upper part of the platform is lowered, supports on an underside of the upper part of the platform lie exactly on the ends of the posts.
- a transformer platform is preferably installed using one of the methods mentioned above; conversely, one of the methods mentioned above is suitable for installing the transformer platform.
- the substation has at least four piles that are rammed into a seabed parallel to one another.
- the only constructive connection between the piles is the platform top.
- the piles are connected in some way above the seabed, but this is not a constructive connection between the piles within the meaning of the invention.
- the upper platform part rests on the upper ends of the posts, so in particular the posts are not lowered laterally in guides or held laterally in guides of the upper platform part, but the platform has an underside with receptacles that are preferably closed at the top and rest on the upper ends of the posts .
- a foundation set for a substation platform with the features of claim 4, which initially consists of a piling device, for example in the form of a lifting platform, and a pontoon with a grillage.
- the piling device has piling templates which are arranged on it and are fixed to one another.
- the relative arrangement of the driving templates corresponds exactly to the arrangement of piles of the transformer platform in the assembled state in a horizontal cross-section, i.e. the relative arrangement of the contact points of the piles with the seabed when only considering the horizontal extension.
- the piling templates are preferably all arranged at the same height above the seabed on the piling device placed thereon.
- the piling device advantageously has a hammer with which each of the piles can be rammed into the seabed through the piling template associated with it.
- the hammer is intended for ramming all piles.
- the piling rig has support legs which enable the piling rig to be supported in location on the seabed and thus prevent displacement of the piling rig during driving of the at least four, preferably five or any greater number of piles.
- the pile driver's support legs are all retractable and extendable.
- the extended support legs support a platform of the piling rig on the seabed so that the platform can be lifted out of the sea by means of a jacking system or the like.
- the pile driver is preferably buoyant so that it can be moved away from the location after the piles have been driven in.
- the pontoon is then moved with the upper platform part between the posts and placed in a position such that the supports on an underside of the upper platform part for the posts are arranged exactly vertically above the ends of the posts above the post ends.
- the platform is lowered and the pads are positioned exactly on top of the piles.
- the pile driver has as many piling templates as there are piles.
- the position of the piling templates can be adjusted for the respective substation platform, i. H. their position can be changed on the pile driver. In their changed position, they are then again fixed in position on the pile driver during the foundation.
- the method according to the invention uses a foundation set that includes a piling device 1, for example in the form of a jack-up platform, and a pontoon 2 on which a grillage 3 is arranged, on which in turn a platform upper part 4 of a substation 6 to be installed can be arranged.
- a piling device 1 is spent on location.
- the piling device 1 itself can be buoyant, for which purpose it has retracted support legs 7 and a buoyant platform 8 .
- the piling device 1 can also be brought to the location by means of a barge or the like.
- the piling device 1 is located in a predetermined manner on location, i. H. in a predetermined orientation with respect to the seabed 9, and then the support legs 7 of the piling rig 1 are lowered so that the piling rig 1 rests on the seabed 9.
- the platform 8 can be lifted out of the water using jacking systems.
- Ramming templates 11 are preferably arranged on the side.
- the piling templates 11 are arranged on or on the piling device 1 in such a way that, when piles 12 are pushed through vertically, the upper ends of the piles 12 exactly have the distance from one another which corresponds to a distance between supports on an underside of the upper platform part 4, so that the upper platform part 4 can be placed with its receptacles 16 on the upper ends of the posts 12.
- the piling device 1 has a crane 13 with a hammer 14 in accordance with Figures 1 - 4 on. This can be a heavy weight.
- the crane 13 inserts the first pile 12 through the first jig 11 until it is plumb over the seabed 9 and then it is lowered onto the seabed 9 . It is placed vertically on the seabed 9 .
- the templates 12 can be foldable and/or removable. Then the pile 12 is rammed into the seabed 9 by means of the hammer 14 .
- the piling device 1 After driving in a first pile 12, the piling device 1 remains in the predetermined position on the seabed 9, and a second pile 12 is inserted through a second ramming template 11, and the second pile 12 is rammed into the seafloor 9 by means of the hammer 14.
- piles 12 are rammed into the seabed 9 as are required to support the upper part 4 of the platform.
- Four or any higher number of piles 12 can be driven in, preferably exactly four piles 12 are driven in.
- the piles 12 are rammed into the seabed 9 to such an extent that the upper end is at least level with the ramming template 11, preferably higher than the ramming template 11.
- the top of the pile 12 is level with the top of the template 11 after it has been driven into the seabed 9.
- the piles 12 are after they are driven according to figure 5 all parallel to each other and perpendicular. Then the platform shell 4 is brought to the location.
- the grillage 3 or the like is arranged on the pontoon 2 in advance.
- the Grillage 3 is a scaffolding.
- the upper part of the platform 4 is placed horizontally on the grillage 3 .
- the pontoon 2 is also buoyant together with the platform top 4 and is pulled together with the platform top 4 to location. This process is in figure 5 and 6 shown.
- the pontoon 2 is dimensioned such that according to 6 fits between the posts 12, and the platform top 4 is arranged on the grillage 3 and on the pontoon 2 such that when passing through the pontoon 2 it is in a position relative to the posts 12 has, so that by simply lowering the upper platform part 4, the receptacles 16 on the underside of the upper platform part 4 touch down directly on the upper ends of the posts 12.
- the pontoon 2 can be lowered by flooding water tanks. Flooding is indicated by the two arrows in 6 shown.
- the transformer platform 6 has relatively thin piles 12 that do not have a lattice structure, so that the entire foundation body has only a very low degree of blockage for the impact of the waves. Due to the low degree of obstruction, the piles 12 can be designed with a small diameter.
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Mechanical Engineering (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
- Foundations (AREA)
Description
Die Erfindung betrifft ein Verfahren zur Gründung einer Umspannplattform mit wenigstens drei Pfählen. Die Erfindung betrifft auch die Umspannplattform, die vorzugsweise mit einem derartigen Verfahren installiert wird und wenigstens drei Pfähle aufweist, sowie ein Gründungsset zur Durchführung des Verfahrens.The invention relates to a method for establishing a substation platform with at least three piles. The invention also relates to the transformer platform, which is preferably installed using such a method and has at least three piles, and a foundation set for carrying out the method.
Durch den Ausbau der Windenergie im Offshore-Bereich werden Umspannplattformen erforderlich. Auf den Umspannplattformen wird der von den einzelnen Windenergieanlagen erzeugte Strom transformiert und von dort durch ein Kabel an Land gebracht. Umspannplattformen oder Konverterplattformen werden insbesondere an der deutschen Westküste in der Nordsee installiert. Das Revier zeichnet sich durch extrem hohe und energiegeladene Wellen bei vergleichsweise geringer Wassertiefe aus. Bekannte Gründungsstrukturen wie Jacketts weisen einen hohen Versperrungsgrad auf und ziehen daher konstruktionsbedingt hohe Lasten an, wodurch sie schwer ausgelegt und dadurch teuer werden. Bekannt ist es, Pfahlgründungen für Umspannplattformen vorzusehen, bei deren Gründung eine Schablone am Meeresboden angeordnet wird und die Pfähle durch die Schablone in den Meeresboden gerammt werden. Dazu werden mehrere verschiedene Rammgeräte verwendet.Due to the expansion of wind energy in the offshore area, substation platforms are becoming necessary. The electricity generated by the individual wind turbines is transformed on the substation platforms and brought to shore from there via a cable. Substation platforms or converter platforms are installed in particular on the German west coast in the North Sea. The area is characterized by extremely high and energetic waves with comparatively shallow water. Known foundation structures such as jackets have a high degree of obstruction and therefore attract high loads by design, making them heavy in design and therefore expensive. It is known to provide pile foundations for substation platforms, in the foundation of which a template is arranged on the seabed and the piles are rammed through the template into the seabed. Several different pile drivers are used for this purpose.
Nachteilig an den bekannten Rammverfahren ist, dass sie nicht hinreichend präzise funktionieren oder relativ aufwendig sind.A disadvantage of the known ramming methods is that they do not work with sufficient precision or are relatively expensive.
Aus der
Die Aufgabe der vorliegenden Erfindung ist es in einem ersten Aspekt, ein eingangs genanntes Verfahren zur Gründung einer Umspannplattform zu verbessern und in einem zweiten Aspekt, ein verbessertes Gründungsset, mit dem die Umspannplattform gegründet werden kann, zur Verfügung zu stellen.The object of the present invention is, in a first aspect, to improve an initially mentioned method for founding a substation platform and, in a second aspect, to provide an improved foundation set with which the substation platform can be founded.
Diese Aufgabe ist gelöst durch die unabhängigen Ansprüche 1 und 4.This object is solved by the
Das erfindungsgemäße Verfahren macht von der Idee Gebrauch, genau ein Rammgerät zu verwenden, das auf Lokation verbracht wird und das mittels ausfahrbarer Stützbeine auf dem Meeresboden abgestützt wird. Bei dem Rammgerät kann es sich um eine Hubinsel oder Ähnliches handeln, die vorzugsweise einen Kran und einen Hammer aufweist.The method according to the invention makes use of the idea of using exactly one piling device that is brought to the location and that is supported on the seabed by means of extendable support legs. The piling device can be a jack-up platform or the like, which preferably has a crane and a hammer.
Der Begriff des Rammens ist hier sehr allgemein zu verstehen unter Rammen ist beispielsweise auch ein Bohren zu verstehen. Unter einem Rammgerät kann hier auch ein Bohrer oder ein Bohrgerät zu verstehen sein.The term ramming is to be understood here in a very general manner. Ramming is also to be understood, for example, as drilling. A piling device can also be understood here as a drill or a drilling device.
An dem Rammgerät werden Schablonen angebracht. Die Schablonen können außenseitig oder innenseitig an einer Plattform des Rammgerätes angeordnet werden, der relative Abstand der Schablonen zueinander entspricht genau der Position der Pfähle der Umspannplattform am Meeresboden, die Pfähle werden jeder einzeln, nacheinander lotrecht in den Meeresboden gerammt.Templates are attached to the pile driver. The templates can be arranged on the outside or inside of a platform of the piling rig, the relative distance between the templates corresponds exactly to the position of the posts of the substation on the seabed, the posts are each rammed vertically into the seabed one after the other.
Die Pfähle werden jeweils durch eine ihnen zugeordnete Rammschablone der Umspannplattform gesteckt. Sie werden günstigerweise lotrecht ausgependelt.The piles are each inserted through a ramming template assigned to them on the substation platform. They are favorably suspended vertically.
Die Pfähle werden nacheinander vorzugsweise unter Beibehaltung der Position des Rammgerätes in den Meeresboden gerammt. Die Stützbeine des Rammgerätes werden vorzugsweise während des gesamten Rammvorganges aller Pfähle nicht verändert. Die in den Meeresboden gerammten Pfähle bleiben auf Höhe oder oberhalb der ihnen zugeordneten Rammschablone angeordnet. "Oben" und "unten" beziehen sich auf Orientierungen vom Meeresboden weg bzw. zum Meeresboden hin.The piles are driven into the seabed one after the other, preferably while maintaining the position of the piling rig. The support legs of the pile driver are preferably not changed during the entire pile driving process. The piles driven into the seabed remain at the same level as or above the driving template assigned to them. "Up" and "down" refer to orientations away from the seabed and toward the seabed, respectively.
Es ist auch denkbar, dass eine Gruppe von Pfähle unter Beibehaltung der Position des Rammgerätes in den Meeresboden gerammt wird und das Rammgerät dann umgesetzt wird und wieder eine Gruppe von Pfählen in den Meeresboden gerammt wird. Auf alle Pfähle wird dann die Plattform aufgesetzt.It is also conceivable that a group of piles is driven into the seabed while maintaining the position of the piling rig and the piling rig is then relocated and another group of piles is rammed into the seabed. The platform is then placed on all the posts.
Anschließend werden die Stützbeine des Rammgerätes eingezogen und das Rammgerät mit eingezogenen Stützbeinen von der Lokation weg verbracht. Nach dem Einrammen stehen die oberen Enden der Pfähle über die Meeresoberfläche heraus ab, vorzugsweise alle in identischer Höhe. Die relativen Abstände der oberen Enden der Pfähle zueinander entspricht exakt den relativen Abständen von Auflagen eines Plattformoberteils, das oben auf die Enden der Pfähle aufgesetzt wird. Günstigerweise werden die Pfähle soweit in den Boden gerammt, bis obere Enden höchstens auf Höhe der Rammschablone angeordnet sind, vorzugsweise + 3 m, vorzugsweise + 2 m, vorzugsweise bis + 1 m, vorzugsweise + 0,5 m, oberhalb der Rammschablone angeordnet sind. Die oberen Enden werden nicht durch die Rammschablone hindurchgerammt. Die Anordnung der Rammschablonen entspricht exakt der relativen Anordnung der Auflagen des Plattformoberteils wie auch den Kontaktpunkten der Pfähle mit dem Meeresboden in einer horizontalen Ebene.The support legs of the piling rig are then retracted and the piling rig is moved away from the location with the support legs retracted. After driving, the tops of the piles project above the sea surface, preferably all at the same height. The relative distances between the upper ends of the piles correspond exactly to the relative distances of supports of a platform top which is placed on top of the ends of the piles. Advantageously, the piles are rammed into the ground until the upper ends are at most level with the ramming template, preferably +3 m, preferably +2 m, preferably up to +1 m, preferably +0.5 m above the ramming template. The top ends are not rammed through the template. The arrangement of the driving templates corresponds exactly to the relative arrangement of the supports of the platform top as well as the contact points of the piles with the seabed in a horizontal plane.
Gemäß der Erfindung ist das Plattformoberteil, das auf Lokation verbracht wird und auf Lokation auf die oberen Pfahlenden aufgesetzt wird, auf einer Grillage und die auf einem Ponton angeordnet. Eine Unterseite des Plattformoberteils weist beim Verbringen auf Lokation eine Höhe über der Meeresoberfläche auf, die höher ist als alle Enden der Pfähle über der Meeresoberfläche. Der Ponton wird abgesenkt, nachdem das Plattformoberteil über die Pfähle verfahren ist und auf die Pfahlenden aufgesetzt. Dabei wird der Ponton so relativ zu den Pfählen angeordnet, dass bei Absenken das Plattformoberteils Auflagen einer Unterseite des Plattformoberteils exakt auf den Pfahlenden aufliegen.According to the invention, the platform upper part, which is brought to the location and is placed on the upper pile ends at the location, is arranged on a grillage and on a pontoon. A bottom of the platform top has a height above the sea surface when moving to location, which is higher than all ends of the piles above the sea surface. The pontoon is lowered after the upper part of the platform has been moved over the piles and placed on the ends of the piles. The pontoon is arranged relative to the posts in such a way that when the upper part of the platform is lowered, supports on an underside of the upper part of the platform lie exactly on the ends of the posts.
Eine Umspannplattform wird vorzugsweise in einem der oben genannten Verfahren installiert, umgekehrt eignet sich eines der oben genannten Verfahren zur Installation der Umspannplattform.A transformer platform is preferably installed using one of the methods mentioned above; conversely, one of the methods mentioned above is suitable for installing the transformer platform.
Die Umspannplattform weist wenigstens vier Pfähle auf, die parallel zueinander in einen Meeresboden gerammt sind. Die einzige konstruktive Verbindung zwischen den Pfählen ist das Plattformoberteil. Natürlich sind die Pfähle in gewisser Weise über dem Meeresboden miteinander verbunden, dieses ist jedoch im Sinne der Erfindung keine konstruktive Verbindung zwischen den Pfählen.The substation has at least four piles that are rammed into a seabed parallel to one another. The only constructive connection between the piles is the platform top. Of course, the piles are connected in some way above the seabed, but this is not a constructive connection between the piles within the meaning of the invention.
Das Plattformoberteil setzt auf oberen Enden der Pfähle auf, die Pfähle werden also insbesondere nicht seitlich in Führungen abgesenkt oder seitlich in Führungen des Plattformoberteils gehalten, sondern die Plattform weist eine Unterseite auf mit vorzugsweise nach oben geschlossenen Aufnahmen, die auf den oberen Enden der Pfähle aufliegen.The upper platform part rests on the upper ends of the posts, so in particular the posts are not lowered laterally in guides or held laterally in guides of the upper platform part, but the platform has an underside with receptacles that are preferably closed at the top and rest on the upper ends of the posts .
In dem zweiten Aspekt wird die Aufgabe durch ein Gründungsset für eine Umspannplattform mit den Merkmalen des Anspruchs 4 gelöst, das zunächst aus einem Rammgerät, beispielsweise in Form einer Hubplattform, und einem Ponton mit einer Grillage besteht. Das Rammgerät weist an ihm angeordnete, zueinander fixierte Rammschablonen auf. Die relative Anordnung der Rammschablonen entspricht exakt der Anordnung von Pfählen der Umspannplattform im montierten Zustand in einem horizontalen Querschnitt, also der relativen Anordnung der Kontaktpunkte der Pfähle mit dem Meeresboden bei Betrachtung nur der horizontalen Ausdehnung. Die Rammschablonen sind vorzugsweise alle auf gleicher Höhe über dem Meeresboden an dem aufgesetzten Rammgerät angeordnet.In the second aspect, the object is achieved by a foundation set for a substation platform with the features of
Das Rammgerät weist günstigerweise einen Hammer auf, mit dem jeder der Pfähle durch die ihm zugeordnete Rammschablone in den Meeresboden eingerammt werden kann. Der Hammer ist zum Rammen aller Pfähle bestimmt. Das Rammgerät weist Stützbeine auf, die es ermöglichen, das Rammgerät auf Lokation auf dem Meeresboden abzustützen und so ein Verschieben des Rammgerätes während des Rammens der wenigstens vier, vorzugweise fünf oder jeder höheren Anzahl an Pfählen zu verhindern.The piling device advantageously has a hammer with which each of the piles can be rammed into the seabed through the piling template associated with it. The hammer is intended for ramming all piles. The piling rig has support legs which enable the piling rig to be supported in location on the seabed and thus prevent displacement of the piling rig during driving of the at least four, preferably five or any greater number of piles.
Die Stützbeine des Rammgeräts sind alle günstigerweise einziehbar und ausfahrbar. Die ausgefahrenen Stützbeine stützen eine Plattform des Rammgerätes am Meeresboden ab, so dass die Plattform mittels eines Jacking Systems oder Ähnlichem aus dem Meer herausgehoben werden kann. Bei eingezogenen Stützbeinen ist das Rammgerät vorzugsweise schwimmfähig, so dass es nach dem Einrammen der Pfähle von der Lokation weg verfahren wird.Conveniently, the pile driver's support legs are all retractable and extendable. The extended support legs support a platform of the piling rig on the seabed so that the platform can be lifted out of the sea by means of a jacking system or the like. When the support legs are retracted, the pile driver is preferably buoyant so that it can be moved away from the location after the piles have been driven in.
Anschließend wird der Ponton mit dem Plattformoberteil zwischen die Pfähle verfahren und in eine Position verbracht, so dass oberhalb der Enden der Pfähle die Auflagen an einer Unterseite des Plattformoberteils für die Pfähle exakt lotrecht über den Pfahlenden angeordnet sind. Durch ein Absenken des Pontons, beispielsweise durch Fluten von Wassertanks, wird die Plattform abgesenkt, und die Auflagen werden exakt auf den oberen Enden der Pfähle positioniert. Günstigerweise weist das Rammgerät genauso viele Rammschablonen wie Pfähle auf.The pontoon is then moved with the upper platform part between the posts and placed in a position such that the supports on an underside of the upper platform part for the posts are arranged exactly vertically above the ends of the posts above the post ends. By lowering the pontoon, for example by flooding water tanks, the platform is lowered and the pads are positioned exactly on top of the piles. Conveniently, the pile driver has as many piling templates as there are piles.
Die Rammschablonen sind in ihrer Position für die jeweilige Umspannplattform anpassbar, d. h. sie können an dem Rammgerät in ihrer Position verändert werden. In ihrer veränderten Position sind sie dann während der Gründung wieder positionsfest am Rammgerät angeordnet.The position of the piling templates can be adjusted for the respective substation platform, i. H. their position can be changed on the pile driver. In their changed position, they are then again fixed in position on the pile driver during the foundation.
Die Erfindung wird anhand eines Ausführungsbeispiels in sieben Figuren beschrieben. Dabei zeigen die
- Fig. 1
- einen ersten Schritt eines erfindungsgemäßen Verfahrens zur Gründung einer Umspannplattform mittels einer Hubinsel, die einen Pfahl der Umspannplattform in den Boden rammt,
- Fig. 2
- einen zweiten Schritt, bei dem der Pfahl bereits ein Stück weit in den Meeresboden eingerammt ist,
- Fig. 3
- einen Schritt des erfindungsgemäßen Verfahrens, bei dem der Pfahl bereits vollständig in den Meeresboden eingerammt ist.
- Fig. 4
- einen vierten Schritt, bei dem der zweite Pfahl der Umspannplattform bereits vollständig in den Boden eingerammt ist,
- Fig. 5
- einen fünften Schritt des erfindungsgemäßen Verfahrens, bei dem bereits alle Pfähle der Umspannplattform in den Meeresboden eingerammt sind und ein Plattformoberteil mittels eines Pontons auf Lokation verbracht wird,
- Fig. 6
- einen sechsten Schritt des erfindungsgemäßen Verfahrens, bei dem das Plattformoberteil mittels des Pontons über die Pfahlenden der eingerammten Pfähle verbracht wird und abgesenkt wird,
- Fig. 7
- die installierte Umspannplattform mit dem auf den Pfählen aufgesetzten Plattformoberteil.
- 1
- a first step of a method according to the invention for establishing a substation by means of a jack-up platform that rams a post of the substation into the ground,
- 2
- a second step, in which the stake is already driven a little way into the seabed,
- 3
- a step of the method according to the invention, in which the pile is already completely driven into the seabed.
- 4
- a fourth step, in which the second post of the substation platform is already fully driven into the ground,
- figure 5
- a fifth step of the method according to the invention, in which all the piles of the substation have already been rammed into the seabed and a platform upper part is brought to the location by means of a pontoon,
- 6
- a sixth step of the method according to the invention, in which the upper part of the platform is brought over the pile ends of the piles that have been driven in and is lowered by means of the pontoon,
- 7
- the installed transformer platform with the upper part of the platform placed on the piles.
Die erfindungsgemäßen Verfahren sind in den
Zunächst wird das erfindungsgemäße Verfahren beschrieben. Es macht von einem Gründungsset Gebrauch, das ein Rammgerät 1, beispielsweise in Form einer Hubinsel, umfasst sowie einen Ponton 2, auf dem eine Grillage 3 angeordnet ist, auf der wiederum ein Plattformoberteil 4 einer zu installierenden Umspannplattform 6 angeordnet werden kann. Zunächst wird das Rammgerät 1 auf Lokation verbracht. Das Rammgerät 1 kann selbst schwimmfähig sein, dazu weist es eingezogene Stützbeine 7 und eine schwimmfähige Plattform 8 auf.First, the method according to the invention is described. It uses a foundation set that includes a
Das Rammgerät 1 kann aber auch mittels einer Barge oder Ähnlichem auf Lokation verbracht werden. Das Rammgerät 1 wird in einer vorgebestimmten Weise auf Lokation, d. h. in einer vorbestimmten Ausrichtung gegenüber dem Meeresboden 9 angeordnet, und dann werden die Stützbeine 7 des Rammgerätes 1 abgesenkt, so dass sich das Rammgerät 1 auf dem Meeresboden 9 abstützt. Die Plattform 8 kann mittels Jacking Systemen aus dem Wasser herausgehoben werden.However, the
An dem Rammgerät 1 werden gemäß
Insbesondere ist zur Gründung der Pfähle 12 keine Schablone auf dem Meeresboden 9 erforderlich.In particular, no template is required on the
Das Rammgerät 1 weist einen Kran 13 mit einem Hammer 14 gemäß
Die Pfähle 12 stehen, nachdem sie eingerammt sind, gemäß
Der Ponton 2 ist derart dimensioniert, dass er gemäß
Das Absenken des Pontons 2 kann durch Fluten von Wassertanks erfolgen. Das Fluten ist durch die zwei Pfeile in
- 11
- Rammgerätpile driver
- 22
- Pontonpontoon
- 33
- Grillagebarbecue
- 44
- Plattformoberteilplatform top
- 66
- Umspannplattformsubstation
- 77
- Stützbeinesupport legs
- 88th
- Plattformplatform
- 99
- MeeresbodenSeabed
- 1111
- Rammschablonendriving templates
- 1212
- Pfahlstake
- 1313
- Krancrane
- 1414
- Hammerhammer
- 1616
- AufnahmenRecordings
Claims (5)
- Method for the foundation of a transformer platform having at least four piles (12), in which precisely one pile driver (1) is brought to a location, the pile driver (1) is supported on the seabed (9) by means of extendable supporting legs (7), driving jigs (11) are attached on or to the pile driver (1), the piles (12) are inserted through the associated driving jigs (11), the piles (12) are successively driven into the seabed (9), upper ends of the piles (12) driven into the seabed (9) are arranged level with or above the associated driving jig (11), the supporting legs (7) of the pile driver (1) are retracted, characterised in that the pile driver (1) is moved away from the location and an upper platform part (4) is arranged on a pontoon (2) and is brought to the location, and at the location is placed onto the upper ends of the piles (12).
- Method according to claim 1, characterised in that the piles (12) are driven into the seabed (9) until the upper ends of the piles (12) are driven into the seabed (9) to the height of the driving jig (11) plus + 3 m, preferably plus 1 m, preferably plus + 0.5 m, preferably driven into the seabed (9) exactly at the height of the driving jig (11).
- Method according to claim 1 or 2, characterised in that the upper platform part (4) is arranged on a framework (3) on the pontoon (2) and an underside of the upper platform part (4), when it is brought to the location, has a height above the surface of the sea which is projecting higher above the surface of the sea than all upper ends of the piles (12) and, after the upper platform part (4) is moved over the piles (12), the pontoon (2) is lowered until it is placed onto the upper ends of the piles (12).
- Foundation set for a transformer platform with a pile driver (1) which can be supported on the seabed (9) at the location by means of extendable supporting legs (7), and the pile driver (1) has driving jigs (11) through which the piles (12) of the transformer platform (6) can be inserted, and the pile driver (1) has a hammer (14) for driving all piles (12), characterised by a pontoon (2) which can be raised and lowered, and is provided with a framework (3) on which an upper platform part (4) is arranged, wherein a height of the framework (3) with the pontoon (2) raised is higher than all the upper ends of the piles (12) driven into the seabed (9).
- Foundation set according to claim 4, characterised in that on the pile driver (1) precisely the same number of driving jigs (11) are provided as the number of piles (12) necessary for the foundation of the transformer platform (6).
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE102018104329.5A DE102018104329B4 (en) | 2018-02-26 | 2018-02-26 | Method for the foundation of a substation and substation with at least four piles |
Publications (3)
Publication Number | Publication Date |
---|---|
EP3530814A1 EP3530814A1 (en) | 2019-08-28 |
EP3530814B1 true EP3530814B1 (en) | 2023-06-14 |
EP3530814C0 EP3530814C0 (en) | 2023-06-14 |
Family
ID=65598487
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP19159324.3A Active EP3530814B1 (en) | 2018-02-26 | 2019-02-26 | Method for the construction of a transformer platform and foundation set for a transformer platform |
Country Status (3)
Country | Link |
---|---|
US (1) | US11131073B2 (en) |
EP (1) | EP3530814B1 (en) |
DE (1) | DE102018104329B4 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112627177A (en) * | 2020-12-09 | 2021-04-09 | 保利长大工程有限公司 | Leveling method of pile stabilizing platform |
Family Cites Families (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5219451A (en) * | 1992-04-24 | 1993-06-15 | Atlantic Richfield Company | Offshore deck to substructure mating system and method |
FR2711687B1 (en) * | 1993-10-29 | 1995-12-29 | Etpm Sa | Method for installing the bridge of a marine platform on a support structure at sea. |
US6347909B1 (en) * | 2000-05-23 | 2002-02-19 | J. Ray Mcdermott, S.A. | Method to transport and install a deck |
NO317848B1 (en) * | 2003-01-17 | 2004-12-20 | Aker Marine Contractors As | Procedure and arrangement for installation and removal of objects at sea |
DE202009006507U1 (en) | 2009-04-30 | 2009-08-06 | Bard Engineering Gmbh | A guide frame for vertically guiding at least one foundation pile when constructing a foundation of an offshore wind turbine and stacking, erecting and lowering device for erecting a foundation of an offshore wind turbine |
EP2431531A1 (en) * | 2010-09-17 | 2012-03-21 | N. prior energy GmbH | Method and device for producing a ramming assembly on a sea or lake bed |
DE102010046732A1 (en) | 2010-09-28 | 2012-03-29 | Werner Möbius Engineering GmbH | Method for installing heavy-weight foundation for wind turbine, involves partially or completely sinking base part into bottom of sea by fluidizing and suctioning off of bottom by suction and pressure pumps underneath sole of base part |
BE1020071A5 (en) * | 2011-07-11 | 2013-04-02 | Geosea N V | METHOD FOR PROVIDING A FOUNDATION FOR A MASS FIXED AT HEIGHT AND A POSITIONING FRAME FOR CARRYING OUT THE METHOD. |
JP5830423B2 (en) * | 2012-03-29 | 2015-12-09 | 新日鉄住金エンジニアリング株式会社 | Pile type offshore structure construction method and pile type offshore structure |
DE102016116166A1 (en) | 2016-08-30 | 2018-03-01 | Overdick Gmbh & Co. Kg | pile foundation |
-
2018
- 2018-02-26 DE DE102018104329.5A patent/DE102018104329B4/en active Active
-
2019
- 2019-02-26 US US16/285,585 patent/US11131073B2/en active Active
- 2019-02-26 EP EP19159324.3A patent/EP3530814B1/en active Active
Also Published As
Publication number | Publication date |
---|---|
EP3530814A1 (en) | 2019-08-28 |
US11131073B2 (en) | 2021-09-28 |
DE102018104329B4 (en) | 2022-09-29 |
US20190264408A1 (en) | 2019-08-29 |
DE102018104329A1 (en) | 2019-08-29 |
EP3530814C0 (en) | 2023-06-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE60126984T2 (en) | METHOD AND DEVICE FOR ARRANGING AT LEAST ONE WIND TURBINE ON OPEN WATER | |
EP2423390B1 (en) | Swivelling module for use when producing an underwater foundation of a structure | |
DE2452560C2 (en) | Method for transferring a working platform from the floating position to a position raised out of the water and working platform for carrying out the method | |
DE102010020995B4 (en) | Foundation system for the foundation of an offshore wind energy plant | |
DE202009006507U1 (en) | A guide frame for vertically guiding at least one foundation pile when constructing a foundation of an offshore wind turbine and stacking, erecting and lowering device for erecting a foundation of an offshore wind turbine | |
DE102010009466A1 (en) | Device for the transport and installation of a flat foundation comprehensive arrangement of an offshore wind turbine and method for transport and installation of such arrangement with flat foundation | |
EP3428345A1 (en) | Foundation for an offshore wind motor | |
EP3530814B1 (en) | Method for the construction of a transformer platform and foundation set for a transformer platform | |
DE2334468A1 (en) | METHOD OF MANUFACTURING LARGE FLOATING UNITS | |
EP2623674A1 (en) | Substructure for an offshore platform and method for installing same | |
DE102016116166A1 (en) | pile foundation | |
EP2565329A2 (en) | Driving template for installation of steel jacket foundations on the sea bed | |
EP2396537B1 (en) | Apparatus and method for producing offshore wind energy plants | |
DE202010010094U1 (en) | Foundation system for the foundation of an offshore wind energy plant | |
DE2532775A1 (en) | FLOAT FOUNDATION IN THE FORM OF A RIVER AND PROCESS FOR ITS MANUFACTURING AND ASSOCIATION WITH A TOWER CONSTRUCTION | |
DE102011012450A1 (en) | Method for installing heavyweight foundation system for offshore-wind energy plant, involves prestressing heavyweight foundation in laterally limited manner by ballast bodies before tower and/or housing of tower is mounted | |
DE2457536B2 (en) | PROCEDURE FOR TRANSPORTING AND SITTING AN OFFSHORE PLATFORM ON THE SEA BOLT AND OFFSHORE PLATFORM | |
EP2935701A2 (en) | Mounting device and method for installing fixing elements | |
DE202022102234U1 (en) | Precast steel trestle bridge | |
EP1634998A1 (en) | Transport and foundation of functional units, in particular offshore wind turbines. | |
DE2323135A1 (en) | METHOD OF BUILDING A TOWER OD. DGL. ON THE SEA BOTTOM | |
EP1321669B1 (en) | System for the transport and installation of offshore wind turbines | |
DE202004021468U1 (en) | Device for transport and erection of a wind turbine | |
EP2623675A1 (en) | Platform topside for an offshore platform and method for installing such a platform topside | |
EP2208824A1 (en) | Method and aquatic vehicle for installing an offshore structure on the sea bed |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE APPLICATION HAS BEEN PUBLISHED |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
AX | Request for extension of the european patent |
Extension state: BA ME |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE |
|
17P | Request for examination filed |
Effective date: 20200225 |
|
RBV | Designated contracting states (corrected) |
Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: EXAMINATION IS IN PROGRESS |
|
17Q | First examination report despatched |
Effective date: 20220221 |
|
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: GRANT OF PATENT IS INTENDED |
|
RIC1 | Information provided on ipc code assigned before grant |
Ipc: E02B 17/02 20060101ALI20230125BHEP Ipc: E02D 7/02 20060101ALI20230125BHEP Ipc: E02D 27/52 20060101AFI20230125BHEP |
|
INTG | Intention to grant announced |
Effective date: 20230221 |
|
GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE PATENT HAS BEEN GRANTED |
|
RAP1 | Party data changed (applicant data changed or rights of an application transferred) |
Owner name: TRACTEBEL OVERDICK GMBH |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: EP |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R096 Ref document number: 502019008152 Country of ref document: DE |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: REF Ref document number: 1579317 Country of ref document: AT Kind code of ref document: T Effective date: 20230715 |
|
U01 | Request for unitary effect filed |
Effective date: 20230703 |
|
U07 | Unitary effect registered |
Designated state(s): AT BE BG DE DK EE FI FR IT LT LU LV MT NL PT SE SI Effective date: 20230711 |
|
REG | Reference to a national code |
Ref country code: LT Ref legal event code: MG9D |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230914 Ref country code: ES Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230614 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: RS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230614 Ref country code: HR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230614 Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230915 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230614 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20231014 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SM Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230614 Ref country code: SK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230614 Ref country code: RO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230614 Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20231014 Ref country code: CZ Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230614 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: PL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230614 |
|
U20 | Renewal fee paid [unitary effect] |
Year of fee payment: 6 Effective date: 20240202 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R097 Ref document number: 502019008152 Country of ref document: DE |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
26N | No opposition filed |
Effective date: 20240315 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MC Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20230614 |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |