EP3332932A2 - A beam and a method for producing a beam - Google Patents

A beam and a method for producing a beam Download PDF

Info

Publication number
EP3332932A2
EP3332932A2 EP17202678.3A EP17202678A EP3332932A2 EP 3332932 A2 EP3332932 A2 EP 3332932A2 EP 17202678 A EP17202678 A EP 17202678A EP 3332932 A2 EP3332932 A2 EP 3332932A2
Authority
EP
European Patent Office
Prior art keywords
pipe
space
concrete
moisture
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
EP17202678.3A
Other languages
German (de)
French (fr)
Other versions
EP3332932B1 (en
EP3332932C0 (en
EP3332932A3 (en
Inventor
Juha Pulkkanen
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anstar Oy
Original Assignee
Anstar Oy
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Family has litigation
First worldwide family litigation filed litigation Critical https://patents.darts-ip.com/?family=60582397&utm_source=google_patent&utm_medium=platform_link&utm_campaign=public_patent_search&patent=EP3332932(A2) "Global patent litigation dataset” by Darts-ip is licensed under a Creative Commons Attribution 4.0 International License.
Application filed by Anstar Oy filed Critical Anstar Oy
Publication of EP3332932A2 publication Critical patent/EP3332932A2/en
Publication of EP3332932A3 publication Critical patent/EP3332932A3/en
Application granted granted Critical
Publication of EP3332932B1 publication Critical patent/EP3332932B1/en
Publication of EP3332932C0 publication Critical patent/EP3332932C0/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/29Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces built-up from parts of different material, i.e. composite structures
    • E04C3/293Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces built-up from parts of different material, i.e. composite structures the materials being steel and concrete
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B11/00Apparatus or processes for treating or working the shaped or preshaped articles
    • B28B11/24Apparatus or processes for treating or working the shaped or preshaped articles for curing, setting or hardening
    • B28B11/247Controlling the humidity during curing, setting or hardening
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/16Moulds for making shaped articles with cavities or holes open to the surface, e.g. with blind holes
    • B28B7/18Moulds for making shaped articles with cavities or holes open to the surface, e.g. with blind holes the holes passing completely through the article
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/40Moulds; Cores; Mandrels characterised by means for modifying the properties of the moulding material
    • B28B7/46Moulds; Cores; Mandrels characterised by means for modifying the properties of the moulding material for humidifying or dehumidifying
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/17Floor structures partly formed in situ
    • E04B5/23Floor structures partly formed in situ with stiffening ribs or other beam-like formations wholly or partly prefabricated
    • E04B5/29Floor structures partly formed in situ with stiffening ribs or other beam-like formations wholly or partly prefabricated the prefabricated parts of the beams consisting wholly of metal
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24DDOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
    • F24D3/00Hot-water central heating systems
    • F24D3/12Tube and panel arrangements for ceiling, wall, or underfloor heating
    • F24D3/14Tube and panel arrangements for ceiling, wall, or underfloor heating incorporated in a ceiling, wall or floor
    • F24D3/141Tube mountings specially adapted therefor
    • F24D3/142Tube mountings specially adapted therefor integrated in prefab construction elements

Definitions

  • the object of the invention is a beam according to claim 1. Furthermore, the object of the invention is a method for producing a beam.
  • the invention relates to a steel beam, on which hollow-core slabs, composite slabs, thin shell slabs and other load-bearing structures of a building can be supported.
  • a beam is filled with concrete, and after the concrete has hardened, the beam serves as a composite structure. With a composite structure longer beam spans can be achieved, and with regular beam spans the amount of steel can be reduced.
  • a beam is filled with concrete at the assembling place or at the manufacturing place and transported to the assembling place after the concrete has hardened.
  • a problem with assembling and producing of beams is the long drying time of concrete, which is typically weeks, even months. This requires more assembling time and higher assembling costs. Furthermore, there has to be a storage room in the factory for drying of concrete, which might restrict the production capacity of beams. If a beam is filled with concrete only at the installation place, drying of concrete might delay the initiating of other operation stages.
  • the aim of this invention is to achieve a beam by means of which the above mentioned problems can be reduced.
  • a beam according to claim 1 which beam comprises a base plate, two web plates and a top plate, which define a space, which can be filled with concrete.
  • a pipe is provided in the space, through the wall of which pipe moisture is arranged to transfer from the outside of the pipe to the inside of the pipe, and which pipe is arranged to be in the flow connection with the outside of the space for transferring moisture along the pipe to the outside of the space.
  • the space defined by a base plate, web plates and a top plate of a beam is filled with concrete.
  • a pipe is arranged in the space through the wall of which pipe moisture is arranged to transfer from concrete to the inside of the pipe. Moisture is transferred along the pipe to the outside of the space.
  • Moisture of concrete inside of the beam is transferred to the pipe, and further along the pipe to the outside of the beam, wherein concrete can be dried faster than earlier, which for one shortens the manufacturing time of a beam at the factory or the installation time at the installation place. Drying of concrete can be made more effective by conducting pressurized air into the pipe. The pressurized air can be heated, if necessary.
  • Slab systems of a building such as hollow-core slabs, composite slabs and shell slabs and in-situ cast concrete slabs can be supported on a steel beam 1 presented in the drawings.
  • the beam 1 is filled with concrete, and after the concrete has hardened, the beam 1 serves with concrete as a load-carrying composite structure for slab systems.
  • the beam 1 is filled with concrete at the assembling place or in the factory during the manufacturing phase, and will be delivered to the assembling place ready-concreted.
  • Beam 1 comprises a base plate 2, to which two web plates 3 are fixed, which form the sides of the beam 1.
  • the web plates 3 are arranged parallel at a distance from each other.
  • the base plate 2 extends in lateral direction of the beam 1 into both sides of the web plates 3, and thus forms protruding parts 4 for slab systems to be supported on beam. If beam 1 is so-called edge beam, there is only on one side of the beam 1 a protruding part 4, on which the plate is supported.
  • the angle between the web plates 3 and the base plate 2 is less than 90°, wherein the distance between the web plates 3 is smaller in upper parts of the web plates 3 than in lower parts.
  • one web plate 3 can be perpendicularly against the base plate 2, if beam 1 is a so-called edge beam.
  • Web plates 3 are connected to each other with their upper edges by a top plate 5.
  • Base plate 2, web plates 3 and top plate 5 form a space 6, which can be filled with concrete.
  • Web plates 3 are fixed to base plate 2 and to top plate 5 by welding, for example.
  • top plate 5 and web plates 3 can be formed of the same plate by bending.
  • the ends of beam 1 can be closed by end plates 15.
  • there are air venting openings 8 in the upper parts of web plates 3 for removing air from the space 6 during concreting.
  • Beam 1 comprises fire steels 9 extending in the longitudinal direction of the beam, which are arranged in the space 6.
  • fire steels are fixed on their place by steel bands. Steel bands are looplike.
  • fire steels can be placed to be supported by supports fixed to base plate 2 of the beam.
  • Supports 7 are placed at regular intervals in the longitudinal direction of the beam 1.
  • Fire steels 9 are fixed to supports with seal bands 13, for example.
  • fire steels 9 are placed on top surface of the top plate 5 of the beam and to corners between top plate 5 and web plates 3 in space 6.
  • Fire steels 9 are corrugated bars.
  • One or more pipes 10 are arranged in the space 6, which comprises a moisture-permeable wall, through which moisture, such as water and/or steam, is arranged to transfer.
  • the space 6 which comprises a moisture-permeable wall, through which moisture, such as water and/or steam, is arranged to transfer.
  • pipe 10 which has been placed in the space 6, is illustrated with dotted lines in order to illustrate the location of the pipe 10.
  • Moisture is arranged to transfer from the outside of the pipe 10, i.e. from concrete in the space 6 to the inside of the pipe 10. This can be provided so that there are holes 11 in the wall of the pipe 10, through which holes 11 moisture can transfer through the wall. Holes 11 are placed at a distance from each other in the longitudinal direction of the pipe 10 and in the direction of circle. Typically, holes 11 are placed over the length of the whole pipe 10.
  • Diameter of holes 11 is less than 3 mm, typically less than 2 mm.
  • the pipe 10 is of plastic, or of other material suitable for the purpose.
  • a drainage pipe for example, can be used as a pipe 10.
  • the pipe 10 can be made of moisture-permeable material.
  • the pipe 10 can be a drainage pipe without holes, for example, through the wall of which moisture permeates from the outside of the pipe 10 to the inside of the pipe 10.
  • the inner diameter of the pipe 10 is at least 30 mm, typically at least 40 mm.
  • the pipe 10 is in the longitudinal direction of the beam 1.
  • the horizontal part of the pipe 10 is parallel to the longitudinal axis of the beam 1.
  • the horizontal part of the pipe 10 is placed in vertical direction in the center of the space 6, wherein the lateral force influencing on the pipe 10 is smallest.
  • the pipe 10 is placed in horizontal direction in the center of the space 6.
  • the pipe 10 is fixed or supported on fire steels 9, seal bands of fire steels or supports or concrete feeding openings 7, for example.
  • the inner part of the pipe 10 is arranged to be in the flow contact with the outside of the space 6 for transferring moisture along the pipe 10 to the outside of the space 6.
  • the flow contact with the inner part of the pipe 10 and with the outside of the space 6 can be provided e.g. so that in the plate, such as a bottom plate 2, of the beam defining the space 6, there is a hole 14 through which the end of the pipe is arranged or to which the end of the pipe 10 is connected with the help of a pipe fitting, for example. Additionally, in the plate, such as a bottom plate 2, of the beam defining the space 6, there is another hole 14' through which the other end of the pipe is arranged or to which the other end of the pipe 10 is connected with the help of the pipe fitting, for example.
  • the end/ends of the pipe 10 can be provided with valves, with which the air flow in the pipe 10 can be regulated and the pipe 10 can be closed.
  • the end of the pipe 10 is connected to the hole 14 in the bottom plate 2, and the other end of the pipe 10 to the other hole 14' in the bottom plate 2.
  • the hole 14 and/or the other hole 14' can locate in the upper plate 5 or in the web plate 3.
  • the hole 14 and the other hole 14' are placed as close as possible to the end and to the other end of the beam 10, wherein moisture transfers from concrete to the pipe 10 over the longest possible length.
  • beam 1 is generally supported at its ends, wherein the bending moment influencing on the beam 1 is smallest at the ends. Because of this the ends of the pipe 10 can easily be fixed to the holes 14, 14'.
  • the hole 14 is next to the end of the beam 1. Typically, the distance of the hole 14 from the end is max. 1/10 of the length of the beam.
  • the other hole 14' is next to the other end of the beam, respectively. Typically, the distance of the other hole 14' from the other end is max. 1/10 of the length of the beam.
  • beam 1 comprises at least one moisture sensor 12 for measuring moisture content of concrete in the space 6. Proportional or absolute moisture content of concrete is measured with the moisture sensor 12. Additionally, temperature of concrete can be measured with the moisture sensor 12. The moisture sensor 12 is placed in the space 6, for example it is fixed to the inner surface of the upper plate 5. Measurement data in the moisture sensor 12 is transferred wireless or with wire to a display from which the measurement data can be read.
  • Beam 1 is produced as follows. Bottom plate 2, web plates 3 and upper plate 4 are fixed to each other so that they form a space 6.
  • a pipe 10 is arranged in the space 6 so that the pipe 10 is arranged or supported on desired place before the plates 2, 3, 4 are fixed to each other, or thereafter.
  • Flow connection is formed between the inside of the pipe 10 and the outside of the space 6 so that water and/or vapour is able to transfer along the pipe 10 to the outside of the space 6.
  • the end and/or the ends of the pipe 10 are connected to the first hole 14 and/or to the other hole 14', or are arranged through the first hole 14 and through the other hole 14' to the outside of the space 6.
  • the moisture sensor 12 is fixed to the inner surface of the upper plate 5.
  • the ends of the space 6 are closed with end plates 15. Concrete is fed into the space 6 through concrete feeding openings 7. Moisture (water and/or vapour) in concrete is transferred from concrete through the wall of the pipe 10 to the inside of the pipe 10. Moisture is transferred along the pipe 10 to
  • air is conducted through the pipe 10 with a blower.
  • the pressurized air is then conducted from the outlet to the pipe 10.
  • air is heated, if for example humidity is high in the surrounding air.
  • air can be sucked through the pipe 10 with a blower.
  • Moisture content of concrete is measured with a moisture sensor 12 locating in the space 6. Measurement data of the moisture sensor 12 is transferred wireless or with wire to a display from which measurement data is readable. When measured moisture content has been lowered to a desired value, possible air conducting with a blower through the pipe 10 is ended.
  • the blower can be provided with a guiding unit, into which measuring data of the moisture sensor 12 is transferred, and which switches air blowing off, when measured moisture content has been lowered to a predetermined value.
  • a heating cable can be placed in the space 6, with which heating cable concrete in the space 6 is heated. Concrete in the space 6 can be cooled down, if it warms too much. This can be made by arranging a hosepipe into the pipe 10, into which hosepipe cold water is led, wherein water flowing in the hose cools concrete off.
  • the ends of the pipe 10 can be closed with fire-resistant mass to improve the fire resistance of the beam 1.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Mechanical Engineering (AREA)
  • Structural Engineering (AREA)
  • Ceramic Engineering (AREA)
  • Civil Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Composite Materials (AREA)
  • Manufacturing & Machinery (AREA)
  • Combustion & Propulsion (AREA)
  • Thermal Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Electromagnetism (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Building Environments (AREA)
  • Devices For Post-Treatments, Processing, Supply, Discharge, And Other Processes (AREA)
  • Manufacturing Of Tubular Articles Or Embedded Moulded Articles (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

A beam (1), which comprises a bottom plate (2), two web plates (3) and a top plate (5), which define a space (6), which can be filled with concrete. A pipe (10) is arranged in the space (6), through which pipe's wall moisture is arranged to transfer from the outside of the pipe (10) to the inside of the pipe (10), and which pipe (10) is arranged to be in the flow contact with the outside of the space (6) for transferring moisture along the pipe (10) to the outside of the space (6).

Description

  • The object of the invention is a beam according to claim 1. Furthermore, the object of the invention is a method for producing a beam.
  • The invention relates to a steel beam, on which hollow-core slabs, composite slabs, thin shell slabs and other load-bearing structures of a building can be supported. A beam is filled with concrete, and after the concrete has hardened, the beam serves as a composite structure. With a composite structure longer beam spans can be achieved, and with regular beam spans the amount of steel can be reduced. A beam is filled with concrete at the assembling place or at the manufacturing place and transported to the assembling place after the concrete has hardened.
  • A problem with assembling and producing of beams is the long drying time of concrete, which is typically weeks, even months. This requires more assembling time and higher assembling costs. Furthermore, there has to be a storage room in the factory for drying of concrete, which might restrict the production capacity of beams. If a beam is filled with concrete only at the installation place, drying of concrete might delay the initiating of other operation stages.
  • The aim of this invention is to achieve a beam by means of which the above mentioned problems can be reduced.
  • The aim of the invention is achieved with a beam according to claim 1, which beam comprises a base plate, two web plates and a top plate, which define a space, which can be filled with concrete. A pipe is provided in the space, through the wall of which pipe moisture is arranged to transfer from the outside of the pipe to the inside of the pipe, and which pipe is arranged to be in the flow connection with the outside of the space for transferring moisture along the pipe to the outside of the space.
  • In the method according to the invention the space defined by a base plate, web plates and a top plate of a beam is filled with concrete. A pipe is arranged in the space through the wall of which pipe moisture is arranged to transfer from concrete to the inside of the pipe. Moisture is transferred along the pipe to the outside of the space.
  • Significant advantages are achieved by the invention. Moisture of concrete inside of the beam is transferred to the pipe, and further along the pipe to the outside of the beam, wherein concrete can be dried faster than earlier, which for one shortens the manufacturing time of a beam at the factory or the installation time at the installation place. Drying of concrete can be made more effective by conducting pressurized air into the pipe. The pressurized air can be heated, if necessary.
  • In the following, the invention will be described in more detail by the aid of embodiments with reference to the attached drawings, wherein
  • Fig. 1
    shows a side view of a beam according to one embodiment of the invention,
    Fig. 2
    shows a cross-section of a beam of Fig. 1, and
    Fig. 3
    shows a side view of a pipe placed in a beam of Figures 1 and 2.
  • Slab systems of a building, such as hollow-core slabs, composite slabs and shell slabs and in-situ cast concrete slabs can be supported on a steel beam 1 presented in the drawings. During seam concreting or other concreting, the beam 1 is filled with concrete, and after the concrete has hardened, the beam 1 serves with concrete as a load-carrying composite structure for slab systems. The beam 1 is filled with concrete at the assembling place or in the factory during the manufacturing phase, and will be delivered to the assembling place ready-concreted.
  • Beam 1 comprises a base plate 2, to which two web plates 3 are fixed, which form the sides of the beam 1. The web plates 3 are arranged parallel at a distance from each other. The base plate 2 extends in lateral direction of the beam 1 into both sides of the web plates 3, and thus forms protruding parts 4 for slab systems to be supported on beam. If beam 1 is so-called edge beam, there is only on one side of the beam 1 a protruding part 4, on which the plate is supported.
  • The angle between the web plates 3 and the base plate 2 is less than 90°, wherein the distance between the web plates 3 is smaller in upper parts of the web plates 3 than in lower parts. Alternatively, one web plate 3 can be perpendicularly against the base plate 2, if beam 1 is a so-called edge beam.
  • Web plates 3 are connected to each other with their upper edges by a top plate 5. Base plate 2, web plates 3 and top plate 5 form a space 6, which can be filled with concrete. Web plates 3 are fixed to base plate 2 and to top plate 5 by welding, for example. Alternatively, top plate 5 and web plates 3 can be formed of the same plate by bending. The ends of beam 1 can be closed by end plates 15. There are concrete feeding openings 7 in web plates 3 through which feeding openings 7 concrete is fed into the space 6 defined by base plate 2, web plates 3, and top plate 5. Moreover, there are air venting openings 8 in the upper parts of web plates 3 for removing air from the space 6 during concreting.
  • Beam 1 comprises fire steels 9 extending in the longitudinal direction of the beam, which are arranged in the space 6. In an embodiment according to drawings fire steels are fixed on their place by steel bands. Steel bands are looplike. Alternatively, fire steels can be placed to be supported by supports fixed to base plate 2 of the beam. Supports 7 are placed at regular intervals in the longitudinal direction of the beam 1. Fire steels 9 are fixed to supports with seal bands 13, for example. Moreover, fire steels 9 are placed on top surface of the top plate 5 of the beam and to corners between top plate 5 and web plates 3 in space 6. Fire steels 9 are corrugated bars.
  • One or more pipes 10 are arranged in the space 6, which comprises a moisture-permeable wall, through which moisture, such as water and/or steam, is arranged to transfer. In fig. 1, pipe 10, which has been placed in the space 6, is illustrated with dotted lines in order to illustrate the location of the pipe 10. Moisture is arranged to transfer from the outside of the pipe 10, i.e. from concrete in the space 6 to the inside of the pipe 10. This can be provided so that there are holes 11 in the wall of the pipe 10, through which holes 11 moisture can transfer through the wall. Holes 11 are placed at a distance from each other in the longitudinal direction of the pipe 10 and in the direction of circle. Typically, holes 11 are placed over the length of the whole pipe 10. Diameter of holes 11 is less than 3 mm, typically less than 2 mm. The pipe 10 is of plastic, or of other material suitable for the purpose. A drainage pipe, for example, can be used as a pipe 10. Alternatively, or addition to the holes, the pipe 10 can be made of moisture-permeable material. The pipe 10 can be a drainage pipe without holes, for example, through the wall of which moisture permeates from the outside of the pipe 10 to the inside of the pipe 10. The inner diameter of the pipe 10 is at least 30 mm, typically at least 40 mm.
  • The pipe 10 is in the longitudinal direction of the beam 1. The horizontal part of the pipe 10 is parallel to the longitudinal axis of the beam 1. Advantageously, the horizontal part of the pipe 10 is placed in vertical direction in the center of the space 6, wherein the lateral force influencing on the pipe 10 is smallest. The pipe 10 is placed in horizontal direction in the center of the space 6. The pipe 10 is fixed or supported on fire steels 9, seal bands of fire steels or supports or concrete feeding openings 7, for example.
  • The inner part of the pipe 10 is arranged to be in the flow contact with the outside of the space 6 for transferring moisture along the pipe 10 to the outside of the space 6. The flow contact with the inner part of the pipe 10 and with the outside of the space 6 can be provided e.g. so that in the plate, such as a bottom plate 2, of the beam defining the space 6, there is a hole 14 through which the end of the pipe is arranged or to which the end of the pipe 10 is connected with the help of a pipe fitting, for example. Additionally, in the plate, such as a bottom plate 2, of the beam defining the space 6, there is another hole 14' through which the other end of the pipe is arranged or to which the other end of the pipe 10 is connected with the help of the pipe fitting, for example. The end/ends of the pipe 10 can be provided with valves, with which the air flow in the pipe 10 can be regulated and the pipe 10 can be closed.
  • In an embodiment according to drawings the end of the pipe 10 is connected to the hole 14 in the bottom plate 2, and the other end of the pipe 10 to the other hole 14' in the bottom plate 2. Alternatively, the hole 14 and/or the other hole 14' can locate in the upper plate 5 or in the web plate 3. The hole 14 and the other hole 14' are placed as close as possible to the end and to the other end of the beam 10, wherein moisture transfers from concrete to the pipe 10 over the longest possible length. Additionally, beam 1 is generally supported at its ends, wherein the bending moment influencing on the beam 1 is smallest at the ends. Because of this the ends of the pipe 10 can easily be fixed to the holes 14, 14'.
  • The hole 14 is next to the end of the beam 1. Typically, the distance of the hole 14 from the end is max. 1/10 of the length of the beam. The other hole 14' is next to the other end of the beam, respectively. Typically, the distance of the other hole 14' from the other end is max. 1/10 of the length of the beam.
  • Additionally, beam 1 comprises at least one moisture sensor 12 for measuring moisture content of concrete in the space 6. Proportional or absolute moisture content of concrete is measured with the moisture sensor 12. Additionally, temperature of concrete can be measured with the moisture sensor 12. The moisture sensor 12 is placed in the space 6, for example it is fixed to the inner surface of the upper plate 5. Measurement data in the moisture sensor 12 is transferred wireless or with wire to a display from which the measurement data can be read.
  • Beam 1 is produced as follows. Bottom plate 2, web plates 3 and upper plate 4 are fixed to each other so that they form a space 6. A pipe 10 is arranged in the space 6 so that the pipe 10 is arranged or supported on desired place before the plates 2, 3, 4 are fixed to each other, or thereafter. Flow connection is formed between the inside of the pipe 10 and the outside of the space 6 so that water and/or vapour is able to transfer along the pipe 10 to the outside of the space 6. The end and/or the ends of the pipe 10 are connected to the first hole 14 and/or to the other hole 14', or are arranged through the first hole 14 and through the other hole 14' to the outside of the space 6. The moisture sensor 12 is fixed to the inner surface of the upper plate 5. The ends of the space 6 are closed with end plates 15. Concrete is fed into the space 6 through concrete feeding openings 7. Moisture (water and/or vapour) in concrete is transferred from concrete through the wall of the pipe 10 to the inside of the pipe 10. Moisture is transferred along the pipe 10 to the outside of the space 6.
  • If it is desired to make the transfer of moisture from concrete to the pipe 10 more effective, air is conducted through the pipe 10 with a blower. The pressurized air is then conducted from the outlet to the pipe 10. If needed, air is heated, if for example humidity is high in the surrounding air. Alternatively, air can be sucked through the pipe 10 with a blower. Moisture content of concrete is measured with a moisture sensor 12 locating in the space 6. Measurement data of the moisture sensor 12 is transferred wireless or with wire to a display from which measurement data is readable. When measured moisture content has been lowered to a desired value, possible air conducting with a blower through the pipe 10 is ended. If needed, the blower can be provided with a guiding unit, into which measuring data of the moisture sensor 12 is transferred, and which switches air blowing off, when measured moisture content has been lowered to a predetermined value. If needed, a heating cable can be placed in the space 6, with which heating cable concrete in the space 6 is heated. Concrete in the space 6 can be cooled down, if it warms too much. This can be made by arranging a hosepipe into the pipe 10, into which hosepipe cold water is led, wherein water flowing in the hose cools concrete off.
  • If it is noticed from the measurement data in the moisture sensor 12 that concrete is drying too fast, concrete in the space can be moistened. This happens so that water is led into the pipe 10, for example a water hose is arranged in the pipe 10, from which water hose water is led into the pipe 10, from which moisture is further transferred through the wall of the pipe 10 into concrete in the space 6. With the pipe 10 moisture content in concrete in the space 6 can be regulated by moisten and/or by drying concrete, where necessary.
  • The ends of the pipe 10 can be closed with fire-resistant mass to improve the fire resistance of the beam 1.
  • Regulation of moisture content and temperature influencing on hardening and usability of concrete structures of the invention is not restricted only to the structure beam presented in the patent application, but it can be utilized also in other concrete structures.

Claims (11)

  1. A beam (1), which comprises a bottom plate (2), two web plates (3) and a top plate (5), which define a space (6), which can be filled with concrete, characterized in that a pipe (10) is fitted in the space (6), through which wall of the pipe (10) moisture is arranged to transfer from the outside of the pipe (10) to the inside of the pipe (10), and which pipe (10) is arranged to be in the flow connection with the outside of the space (6) for transferring moisture along the pipe (10) to the outside of the space (6).
  2. A beam (1) according to claim 1, characterized in that the end of the pipe (10) is arranged through the hole (14) in plate (2, 3, 4) defining the space (6) to the outside of the space (6) or connected to the hole (14).
  3. A beam (1) according to claim 2, characterized in that the other end of the pipe (10) is arranged through the other hole (14') in plate (2, 3, 4) defining the space (6) to the outside of the space (6) or connected to the other hole (14').
  4. A beam (1) according to any of preceding claims, characterized in that the wall of the pipe (10) comprises holes, through which moisture is arranged to transfer from the outside of the pipe (10) to the inside of the pipe.
  5. A beam (1) according to any of preceding claims, characterized in that there is a hole (14) in the bottom plate (2) of the beam, into which hole (14) the end of the pipe is connected, and/or there is another hole (14') in the bottom plate of the beam, into which another hole (14') the other end of the pipe is connected.
  6. A beam (1) according to claim 3, characterized in that the hole (14) of the bottom plate is next to the end of the beam and/or the other hole (14') is next to the other end of the beam.
  7. A beam (1) according to any of preceding claims, characterized in that the pipe (10) is placed in vertical direction in the center of the space (6).
  8. A beam (1) according to any of preceding claims, characterized in that a moisture sensor (12) is placed in the space (6) for measuring moisture content and/or temperature of concrete.
  9. A method for producing a beam (1), in which method a space (6) defined by a bottom plate (2), web plates (3) and a top plate (5), is filled with concrete, characterized in that a pipe (10) is arranged in the space (6), through the wall of which pipe (10) moisture is transferred from concrete to the inside of the pipe (10), and along the pipe (10) to the outside of the space (6).
  10. A method according to claim 9, characterized in that air is conducted through the pipe (10).
  11. A method according to any of preceding claims, characterized in that a moisture sensor (12) is arranged in the space (6) with which moisture content and/or temperature of concrete is measured.
EP17202678.3A 2016-12-08 2017-11-21 A beam and a method for producing a beam Active EP3332932B1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
FI20165934A FI127611B (en) 2016-12-08 2016-12-08 Beam

Publications (4)

Publication Number Publication Date
EP3332932A2 true EP3332932A2 (en) 2018-06-13
EP3332932A3 EP3332932A3 (en) 2018-06-20
EP3332932B1 EP3332932B1 (en) 2024-09-18
EP3332932C0 EP3332932C0 (en) 2024-09-18

Family

ID=60582397

Family Applications (1)

Application Number Title Priority Date Filing Date
EP17202678.3A Active EP3332932B1 (en) 2016-12-08 2017-11-21 A beam and a method for producing a beam

Country Status (3)

Country Link
EP (1) EP3332932B1 (en)
FI (1) FI127611B (en)
PL (1) PL3332932T3 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2023021238A1 (en) 2021-08-20 2023-02-23 Peikko Group Oy Steel beam and method for producing a steel-concrete composite beam

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62185943A (en) * 1986-02-10 1987-08-14 三菱重工業株式会社 Steel pipe concrete member
SE524158C2 (en) * 1998-11-16 2004-07-06 Jonatan Paulsson Concrete slab with embedded channels
FI20021934L (en) * 2002-10-31 2004-07-16 Tartuntamarkkinointi Oy Joint beam
CN203752296U (en) * 2014-02-11 2014-08-06 徐州共进机械有限公司 Absorption-type square-outside and circular-inside flue gas channel maker

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2023021238A1 (en) 2021-08-20 2023-02-23 Peikko Group Oy Steel beam and method for producing a steel-concrete composite beam

Also Published As

Publication number Publication date
FI20165934L (en) 2018-06-09
EP3332932B1 (en) 2024-09-18
PL3332932T3 (en) 2025-01-27
EP3332932C0 (en) 2024-09-18
FI127611B (en) 2018-10-15
EP3332932A3 (en) 2018-06-20
FI20165934A7 (en) 2018-06-09

Similar Documents

Publication Publication Date Title
KR101845860B1 (en) Cold Storage Warehouse for Dehumidification and Preventing Frost Damage
KR101419014B1 (en) Refigeration equipment building process and Refigeration equipment in ice rink
EP3332932A2 (en) A beam and a method for producing a beam
US20090120026A1 (en) Core-Insulated Pre-Fabricated Wall Piece With Connector Pins
JP5208841B2 (en) Installation method of ceiling air conditioner
US20110247291A1 (en) Reinforcement Bar Support Device
JP2013139828A (en) Refrigerant piping unit and refrigerant piping installation method
JP5779113B2 (en) Cooling method for concrete structures
EP3348732B1 (en) Support for a hollow-core slab
CN115324347A (en) Construction method of high-strength concrete crack prevention in nuclear island workshop
JP2009007898A (en) Composite hollow floor structure
CN104120217B (en) Assembly type thermal treatment heating furnace and constructing method thereof
CN214575183U (en) An inverted roof drainage structure
FI126697B (en) Method of making a steel beam
NZ760970A (en) Temperature control of a modular building
KR101576615B1 (en) Hollowcore slab integrated ventilation deckplate
RU2221119C1 (en) Laminated panel of ventilated wall fence
RU2503781C1 (en) Quick-mounting energy-efficient frame building
EP3423646B1 (en) Base floor of a building and a method for construction of a base of a building
CN222065212U (en) A concrete winter curing formwork device
WO2023021238A1 (en) Steel beam and method for producing a steel-concrete composite beam
EP2906761A1 (en) Lattice structure for forming the reinforcing structure of a reinforced concrete floor
CN217652141U (en) Prefabricated lintel structure
CN216840049U (en) Fireproof cement hollow brick
CN109723177A (en) An integrated steel-concrete composite floor based on I-beam

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION HAS BEEN PUBLISHED

PUAL Search report despatched

Free format text: ORIGINAL CODE: 0009013

AK Designated contracting states

Kind code of ref document: A2

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

AX Request for extension of the european patent

Extension state: BA ME

AK Designated contracting states

Kind code of ref document: A3

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

AX Request for extension of the european patent

Extension state: BA ME

RIC1 Information provided on ipc code assigned before grant

Ipc: B28B 7/46 20060101AFI20180517BHEP

Ipc: E04C 3/293 20060101ALI20180517BHEP

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE

17P Request for examination filed

Effective date: 20181219

RBV Designated contracting states (corrected)

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: EXAMINATION IS IN PROGRESS

17Q First examination report despatched

Effective date: 20210830

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: GRANT OF PATENT IS INTENDED

INTG Intention to grant announced

Effective date: 20240411

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE PATENT HAS BEEN GRANTED

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: DE

Ref legal event code: R096

Ref document number: 602017084895

Country of ref document: DE

U01 Request for unitary effect filed

Effective date: 20241010

U07 Unitary effect registered

Designated state(s): AT BE BG DE DK EE FI FR IT LT LU LV MT NL PT RO SE SI

Effective date: 20241029

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20241219

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: HR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240918

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: RS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20241218

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: RS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20241218

Ref country code: HR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240918

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20241219

U20 Renewal fee for the european patent with unitary effect paid

Year of fee payment: 8

Effective date: 20250115

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20250118

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SM

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240918

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240918

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: CZ

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240918

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240918

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MC

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240918

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20241130

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

26N No opposition filed

Effective date: 20250619

GBPC Gb: european patent ceased through non-payment of renewal fee

Effective date: 20241218

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20241218

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20241121

U20 Renewal fee for the european patent with unitary effect paid

Year of fee payment: 9

Effective date: 20251117

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: NO

Payment date: 20251120

Year of fee payment: 9

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: PL

Payment date: 20251031

Year of fee payment: 9

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: HU

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO

Effective date: 20171121

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: CY

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO

Effective date: 20171121