EP3264005A1 - Sealed air boiler air inlet chamber - Google Patents
Sealed air boiler air inlet chamber Download PDFInfo
- Publication number
- EP3264005A1 EP3264005A1 EP17178153.7A EP17178153A EP3264005A1 EP 3264005 A1 EP3264005 A1 EP 3264005A1 EP 17178153 A EP17178153 A EP 17178153A EP 3264005 A1 EP3264005 A1 EP 3264005A1
- Authority
- EP
- European Patent Office
- Prior art keywords
- air
- boiler
- outlet
- sealed
- inlet chamber
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 43
- 230000004888 barrier function Effects 0.000 claims abstract description 38
- 238000010438 heat treatment Methods 0.000 claims abstract description 26
- 125000006850 spacer group Chemical group 0.000 claims description 12
- 230000002401 inhibitory effect Effects 0.000 claims description 6
- 238000002485 combustion reaction Methods 0.000 description 6
- 238000000926 separation method Methods 0.000 description 3
- 239000000853 adhesive Substances 0.000 description 2
- 230000001070 adhesive effect Effects 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 238000004891 communication Methods 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 239000000446 fuel Substances 0.000 description 1
- 239000000565 sealant Substances 0.000 description 1
- 239000012945 sealing adhesive Substances 0.000 description 1
- 238000009423 ventilation Methods 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Images
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24H—FLUID HEATERS, e.g. WATER OR AIR HEATERS, HAVING HEAT-GENERATING MEANS, e.g. HEAT PUMPS, IN GENERAL
- F24H1/00—Water heaters, e.g. boilers, continuous-flow heaters or water-storage heaters
- F24H1/0027—Water heaters, e.g. boilers, continuous-flow heaters or water-storage heaters using fluid fuel
- F24H1/0036—Water heaters, e.g. boilers, continuous-flow heaters or water-storage heaters using fluid fuel of the sealed type
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F23—COMBUSTION APPARATUS; COMBUSTION PROCESSES
- F23L—SUPPLYING AIR OR NON-COMBUSTIBLE LIQUIDS OR GASES TO COMBUSTION APPARATUS IN GENERAL ; VALVES OR DAMPERS SPECIALLY ADAPTED FOR CONTROLLING AIR SUPPLY OR DRAUGHT IN COMBUSTION APPARATUS; INDUCING DRAUGHT IN COMBUSTION APPARATUS; TOPS FOR CHIMNEYS OR VENTILATING SHAFTS; TERMINALS FOR FLUES
- F23L1/00—Passages or apertures for delivering primary air for combustion
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F23—COMBUSTION APPARATUS; COMBUSTION PROCESSES
- F23L—SUPPLYING AIR OR NON-COMBUSTIBLE LIQUIDS OR GASES TO COMBUSTION APPARATUS IN GENERAL ; VALVES OR DAMPERS SPECIALLY ADAPTED FOR CONTROLLING AIR SUPPLY OR DRAUGHT IN COMBUSTION APPARATUS; INDUCING DRAUGHT IN COMBUSTION APPARATUS; TOPS FOR CHIMNEYS OR VENTILATING SHAFTS; TERMINALS FOR FLUES
- F23L17/00—Inducing draught; Tops for chimneys or ventilating shafts; Terminals for flues
- F23L17/02—Tops for chimneys or ventilating shafts; Terminals for flues
- F23L17/14—Draining devices
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24D—DOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
- F24D19/00—Details
- F24D19/08—Arrangements for drainage, venting or aerating
- F24D19/082—Arrangements for drainage, venting or aerating for water heating systems
- F24D19/088—Draining arrangements
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24H—FLUID HEATERS, e.g. WATER OR AIR HEATERS, HAVING HEAT-GENERATING MEANS, e.g. HEAT PUMPS, IN GENERAL
- F24H9/00—Details
- F24H9/0005—Details for water heaters
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24H—FLUID HEATERS, e.g. WATER OR AIR HEATERS, HAVING HEAT-GENERATING MEANS, e.g. HEAT PUMPS, IN GENERAL
- F24H9/00—Details
- F24H9/12—Arrangements for connecting heaters to circulation pipes
- F24H9/13—Arrangements for connecting heaters to circulation pipes for water heaters
Definitions
- Embodiments of the present invention relate to a sealed air boiler air inlet chamber, a sealed air boiler including the air inlet chamber and a heating system including the sealed air boiler.
- Commercial boilers may be used for large scale heating, and may be located in a specifically designated room, e.g. a plant room.
- Air is required for the combustion of fuel (e.g. gas or oil) to produce heat energy.
- fuel e.g. gas or oil
- air may be admitted to a boiler from the surrounding environment (e.g. a plant room), for example, through an opening in the housing of the boiler.
- boiler housings may be sealed to the surrounding environment (e.g. a plant room), and instead receive air through an inlet such as a ventilation shaft or other pipe.
- a ventilation shaft or other pipe Such a pipe may be open to outdoor air. Government regulations or other factors may favour boilers that are sealed to the surrounding environment.
- Such boilers may be known by various names, such as “sealed air boilers” or “room-sealed boilers”.
- Outdoor air may be damp, i.e. contain water. Therefore, air entering a sealed air boiler from outdoors may contain a significant fraction of water. It may be advantageous for the air entering the furnace of a boiler to be relatively dry.
- an inlet chamber for a sealed air boiler which may reduce the amount of water within the air which is fed to the furnace of the boiler.
- a sealed air boiler air inlet chamber comprising a casing, defining a volume, an air and water inlet aperture, a first outlet for water, and a second outlet for air, and a barrier, spaced from the second outlet, demarking a first region of the casing including the first outlet and a second region of the casing including the second outlet, wherein the barrier may be configured to inhibit the flow of water from the first region to the second region and to permit the flow of air from the first region to the second region.
- the barrier may extend a height from a plane of the casing including the second outlet.
- the barrier may extend between a first surface and a second surface of the casing.
- a surface of the casing may be inclined towards the first outlet in use.
- the sealed air boiler air inlet chamber may further comprise a connector for connecting the first outlet to a drain.
- the sealed air boiler air inlet chamber may further comprise a connector for connecting the second outlet to a furnace.
- the first outlet and the second outlet may be of different sizes.
- the first outlet may be smaller than the second outlet.
- the sealed air boiler air inlet chamber may further comprise a spacer.
- the spacer may be for inhibiting an object within the chamber from contacting a surface of the chamber.
- the object may be an air inlet pipe.
- the spacer may be for inhibiting an open end of the pipe from contacting a surface of the chamber, such that the pipe remains open.
- the sealed air boiler air inlet chamber may further comprise a fixing for fitting the air inlet chamber to a sealed-air boiler.
- the chamber may have an outer rim and the fixing may be located on the outer rim of the chamber.
- the boiler may be a sealed air boiler.
- thermoelectric heating system comprising a boiler as described above.
- the heating system may be a central heating system and/or a water heating system.
- a sealed air boiler (sometimes referred to as a room sealed boiler) draws in air for combustion from outside the space in which the boiler is located. Accordingly, the air drawn into the boiler may have different characteristics from the air in the space in which the boiler is located (for example, the air drawn into a sealed air boiler may be wetter than air in the immediate surrounds of the boiler).
- boilers can function more effectively when the air used for combustion is drier, that is, not wet. It is therefore a first non-exclusive aim to provide a sealed air boiler air inlet chamber, which can separate water from combustion air.
- a sealed air boiler air inlet chamber indicated generally at 1 comprises a casing, defining a volume, an air and water inlet aperture 101, a first outlet 3 for water, and a second outlet 4 for air.
- the barrier 2 demarks a first region 30 of the casing which includes the first outlet 3 and a second region 40 of the casing which includes the second outlet 4.
- the barrier 2 is configured to inhibit the flow of water from the first region 30 to the second region 40 and to permit the flow of air from the first region 30 to the second region 40.
- Such a sealed air boiler air inlet chamber 1 may provide an advantageous high separation of water from feed air (e.g. outside air).
- feed air e.g. outside air
- water which may be present as a contaminate in the feed air will predominantly exit through the first outlet 3 in the first region 30 and air will predominantly exit through the second outlet 4 in the second region 40.
- drier air may be provided to the furnace of a sealed air boiler.
- the sealed air boiler air inlet chamber 1 may be used with a sealed air boiler which can still operate as a sealed air boiler even when the housing of the boiler is open, as will be described in more detail below.
- the casing may include side surfaces and/or a base.
- the side surfaces may be substantially vertical walls 10.
- Surfaces 100 of the casing may be inclined with respect to the walls 10.
- the walls 10 may include inclined portions 100.
- the barrier 2 may extend a height from a plane of the casing including the second outlet 4. Such a construction may be particularly simple, and therefore economic.
- the barrier 3 may extend between a first surface and a second surface of the casing.
- the barrier 2 may contact a first surface and a second surface of the chamber 1.
- the first surface may be a wall 10 or an inclined surface 100.
- the second surface may be a wall 10 or an inclined surface 100.
- the barrier may contact multiple walls 10.
- the barrier may extend between opposite walls 10.
- the barrier may contact multiple points on the same wall 10.
- the barrier 2 may be a substantially straight barrier 2, as shown in Figs 1 to 4 .
- the barrier 2 may define an angle.
- the barrier 2 may extend between a first wall 10 and a second wall 10 that are substantially perpendicular to one another, such that the barrier 2 defines a right angle.
- the barrier 2 may extend between a first wall 10 and a second wall 10 at any angle, e.g. any other angle.
- the barrier 2 may extend between a first wall 10 and a second wall 10 where both walls 10 are on the same side of the casing.
- the barrier 2 may extend a height that is generally level with the top of an inclined surface 100.
- the barrier 2 may extend a height based on the expected volume of water that may enter the first region 30 of the casing in use. Additionally or alternatively, the barrier 2 may extend a height based on the efficiency with which water leaves the chamber 1 via the first outlet 3.
- the barrier 2 may contact a base of the casing of the chamber 1 such that the contact is air-and-water-tight. Such contact may be achieved by any means apparent to the skilled person, for example, by welding the barrier 2 to the chamber 1. Alternatively, such contact may be achieved by forming the barrier 2 integrally with the chamber 1. Air-and-water-tight contacts between the barrier 2 and a wall 10 and/or a base of the casing of the chamber 1 may be achieved using any means apparent to the skilled person.
- the barrier 2 may also be spaced from the first outlet 3.
- the barrier as described above can provide a particularly distinct second region 40 for the second outlet 4, which in turn can be used to provide good separation of water from the air to be fed to the furnace of the boiler.
- a surface of the casing may be inclined towards the first outlet 3 in use. Such inclined surfaces may contribute to the flow of water towards the first outlet 3 within the first region 30, thereby providing good or increased separation efficiency.
- the first outlet 3 may be in a base of the chamber 1. However, the first outlet 3 may be defined in a wall 10 or inclined surface 100 of the chamber 1, within the first region 30 of the casing. For example, the first outlet 3 may be defined in a corner of the chamber 1.
- the sealed air boiler air inlet chamber 1 may further comprise a connector 301 for connecting the first outlet 3 to a drain.
- the first outlet 3 may be connected to a first connector 301 for connecting the chamber 1 to a pipe.
- the first connector 301 may extend a length away from the surface defining the first outlet 3.
- the first connector 301 may form part of the inner surface of the first outlet 3.
- the first connector 301 may be integrally formed as part of the chamber 1, or may be otherwise attached to the chamber 1.
- the first connector 301 may be continuous around the circumference of the first outlet 3.
- the first connector 301 may be another type of connector, designed so as to mesh with the desired exhaust means, such as a pipe.
- the first connector 301 may provide a water-tight connection between the chamber 1 and an exhaust means. As shown in Fig. 1 , the first connector 301 can be seen extending a vertical length from the casing 1.
- the sealed air boiler air inlet chamber 1 may further comprise a second connector 401 for connecting the second outlet 4 to a furnace.
- the second connector 401 may extend a length away from the surface defining the second outlet 4.
- the second connector 401 may form part of the inner surface of the second outlet 4.
- the second connector 401 may be integrally formed as part of the chamber 1, or may be otherwise attached to the chamber 1.
- the second connector 401 may be continuous around the circumference of the second outlet 4, as shown in figure 1 .
- the second connector 401 may be another type of connector, designed so as to mesh with the desired exhaust means, such as a pipe.
- the second connector 401 can be seen extending a vertical length from the circumference of the second outlet 4.
- the second connector 401 may extend a horizontal length away from the second outlet 4, and may extend along the outer surface of the chamber 1, in order to connect the chamber 1 to an exhaust means.
- the second connector 401 may otherwise mate with the chamber 1.
- the sealed air boiler air inlet chamber 1 may have a first outlet 3 and the second outlet 4 of different sizes.
- the first outlet 3 may be smaller than the second outlet 4. This may be advantageous, as the volume of air passing through the inlet chamber 1 and out of the second outlet 4 will usually be much larger than the volume of water passing through the inlet chamber 1 and out of the first outlet 3.
- the sealed air boiler air inlet chamber 1 may further comprise a spacer 5.
- the function of the spacer 5 can be for inhibiting (e.g. for stopping or substantially preventing) an object within the chamber 1 from contacting the base of the casing.
- the spacer 5 may be located within the first region 30 of the casing.
- the spacer 5 can space an open end of an air (and water) inlet pipe, from the casing of the chamber 1, to inhibit (e.g. substantially prevent) the open end of such a pipe from contacting and therefore being closed off by contacting a surface of the chamber 1. Accordingly, the pipe may remain open.
- multiple spacers 5 may be provided.
- the spacer 5 may extend across a width of the chamber 1.
- the chamber 1 may comprise a fixing 12 for fitting the air inlet chamber 1 to a sealed-air boiler. As shown in Figs 1 to 4 , the fixing 12 may be located on an outer rim 11 of the chamber.
- the outer rim 11 may be continuous around the perimeter of the casing of the chamber 1, as shown in figures 1 to 4 . Additionally or alternatively, the outer rim 11 may be a continuation of the walls 10, e.g. the top of the walls 10 may be shaped to form the outer rim 11.
- the outer rim 11 may define a plane which may be substantially perpendicular to that of the walls 10 of the chamber 1.
- the fixing 12 may be a cut-out, for use with a further means of fixing the chamber 1 in place.
- the cut-out may be of dimensions to fit a screw or another fixing.
- the outer rim 11 may not define cut-outs 12 and may instead be designed to fit in any other way, as will be apparent to the skilled person.
- the outer rim 11 may further include hooks or another type of fixing means.
- rails or another receiving means for the chamber 1 may be positioned in a boiler to allow the chamber 1 to be fixed in place.
- the chamber 1 may be fixed in place within a boiler using an adhesive, e.g. a sealing adhesive or a sealant.
- an adhesive may be applied to the outer rim 11.
- the chamber 1 may be removably fixable to a boiler, for example to facilitate servicing of the boiler including removal of the chamber 1.
- a boiler 6 including an air-inlet chamber 1 as described above.
- the boiler 6 may be a sealed air boiler 6.
- Inclusion of the air inlet chamber 1 in a sealed air boiler 6, may be particularly advantageous as it can help to provide a sealed air boiler which is sealed both when the housing of the boiler is open (e.g. during adjustment) and whilst the housing of the boiler is closed (e.g. during normal use). Accordingly, a sealed air boiler 6 which is more easily correctly commissioned can be provided.
- the chamber 1 may be positioned at the top of the boiler 6, as shown.
- a surface of the boiler 6 may close-off a top of the chamber 1 that is open when not installed within the boiler 6.
- the chamber 1 may be closed-off or contained in some other way, as would be apparent to the skilled person.
- the chamber 1 is for use between the air and water inlet (for example the air and water inlet aperture 101) of a boiler 6 and the rest of the boiler system.
- the boiler 6 may include an air and water inlet pipe.
- the air and water inlet aperture 101 of the chamber 1 may receive an air and water inlet pipe in use. Accordingly, water may drip from the air and water inlet pipe. Any water admitted to the inlet chamber 1, is admitted in the first region 30 of the casing, accordingly, the water can exit the first outlet 3.
- the air and water inlet aperture 101 should not open directly into the second region 40 of the casing, as the barrier 2 would not then be able to fulfil its function of substantially preventing or inhibiting water from entering the second region 40 of the casing and exiting the second outlet 4.
- Air from the air and water inlet aperture 101 is passable over the barrier 2 into the second region 40 of the casing, such that air may exit the chamber 1 via the second outlet 4 and may be drawn beyond the chamber 1 further into the boiler 6 for combustion.
- air is the useful part of the intake into the chamber 1 and may be drawn into the boiler 6 from the second outlet 4 in any suitable way.
- the sealed air boiler air inlet chamber 1 can be suitable for use with any suitable suction means known in the art of boilers.
- the term 'drawn' does not exclude the free flow of air into the boiler 6 without the use of any particular suction means or other means of inciting air flow.
- a first pipe 302 is shown, which can connect the first outlet 3 of the chamber 1, for example using a first connector 301, to part of the boiler 6.
- the first outlet 3 may be connected to a drain 303.
- the drain 303 may be external to the boiler 6 such that the first pipe 302 traverses the boiler 6.
- the drain 303 may be external to the boiler 6 such that water from the first outlet 3 does not interact with any other part of the interior of the boiler 6 except for the first pipe 302.
- the drain 303 may otherwise be a drainage component inside the boiler 6 that includes a reservoir or a similar water collecting receptacle.
- the drain 303 may be the same drain as is used for condensate from the boiler.
- a second pipe 402 which connects the chamber 1 at the second outlet 4, by the second connector 401, to a further part of the boiler 6.
- the second outlet 4 may be connected directly or indirectly to a furnace.
- the second pipe 402 may have a diameter corresponding to that of the second outlet 4.
- the second pipe 402 may be connected in an air-tight manner to the second outlet 4.
- An air tight connection may be advantageous as it can allow the boiler to be air sealed even when a cover of the boiler is not in place.
- the chamber 1 may be shaped to fit to the shape of part of the boiler 6.
- a heating system 8 comprising a boiler 6 as described above, including the inlet 1 described above.
- the heating system 8 may be a central heating system. Additionally or alternatively, the heating system 8 may be a water heating system.
- the heating system 8 may comprise a heating element 7, which is in communication with the boiler 6.
- the heating element 7 may be a wall-mounted radiator.
- the heating element 7 may be a water heater.
- a single heating system 8 may comprise multiple heating elements 7 and may comprise different types of heating elements 7.
- the heating system 8 may include a single boiler 6.
- the heating system 8 may include multiple boilers 6 if the heating system 8 is large-scale.
- the heating system 8 may include one or more boilers 6 that include a sealed air boiler air inlet chamber 1 and one or more boilers 6 without a chamber 1, i.e. the heating system 8 may comprise a combination of sealed air boilers and open boilers.
Landscapes
- Engineering & Computer Science (AREA)
- Chemical & Material Sciences (AREA)
- Combustion & Propulsion (AREA)
- Mechanical Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Thermal Sciences (AREA)
- Air Supply (AREA)
Abstract
Description
- Embodiments of the present invention relate to a sealed air boiler air inlet chamber, a sealed air boiler including the air inlet chamber and a heating system including the sealed air boiler.
- Commercial boilers may be used for large scale heating, and may be located in a specifically designated room, e.g. a plant room.
- Air is required for the combustion of fuel (e.g. gas or oil) to produce heat energy.
- In some arrangements, air may be admitted to a boiler from the surrounding environment (e.g. a plant room), for example, through an opening in the housing of the boiler.
- Alternatively, boiler housings may be sealed to the surrounding environment (e.g. a plant room), and instead receive air through an inlet such as a ventilation shaft or other pipe. Such a pipe may be open to outdoor air. Government regulations or other factors may favour boilers that are sealed to the surrounding environment. Such boilers may be known by various names, such as "sealed air boilers" or "room-sealed boilers".
- Outdoor air may be damp, i.e. contain water. Therefore, air entering a sealed air boiler from outdoors may contain a significant fraction of water. It may be advantageous for the air entering the furnace of a boiler to be relatively dry.
- Accordingly, it is a non-exclusive object of the invention to provide an inlet chamber for a sealed air boiler, which may reduce the amount of water within the air which is fed to the furnace of the boiler.
- There is provided a sealed air boiler air inlet chamber, comprising a casing, defining a volume, an air and water inlet aperture, a first outlet for water, and a second outlet for air, and a barrier, spaced from the second outlet, demarking a first region of the casing including the first outlet and a second region of the casing including the second outlet, wherein the barrier may be configured to inhibit the flow of water from the first region to the second region and to permit the flow of air from the first region to the second region.
- The barrier may extend a height from a plane of the casing including the second outlet.
- The barrier may extend between a first surface and a second surface of the casing.
- A surface of the casing may be inclined towards the first outlet in use.
- The sealed air boiler air inlet chamber may further comprise a connector for connecting the first outlet to a drain.
- The sealed air boiler air inlet chamber may further comprise a connector for connecting the second outlet to a furnace.
- The first outlet and the second outlet may be of different sizes. In particular, the first outlet may be smaller than the second outlet.
- The sealed air boiler air inlet chamber may further comprise a spacer.
- The spacer may be for inhibiting an object within the chamber from contacting a surface of the chamber. In particular, the object may be an air inlet pipe.
- The spacer may be for inhibiting an open end of the pipe from contacting a surface of the chamber, such that the pipe remains open.
- The sealed air boiler air inlet chamber may further comprise a fixing for fitting the air inlet chamber to a sealed-air boiler.
- The chamber may have an outer rim and the fixing may be located on the outer rim of the chamber.
- There is also provided a boiler comprising an air-inlet chamber as described above.
- The boiler may be a sealed air boiler.
- There is also provided a heating system comprising a boiler as described above.
- The heating system may be a central heating system and/or a water heating system.
- Embodiments of the present invention are described herein, by way of example only, with reference to the accompanying drawings, in which:
-
Fig. 1 shows a perspective view of a sealed air boiler air inlet chamber in accordance with embodiments of the invention; -
Fig. 2 shows a plan view of the sealed air boiler air inlet chamber ofFig. 1 ; -
Fig. 3 shows a part-sectional side view of the sealed air boiler air inlet chamber ofFig. 1 ; -
Fig. 4 shows a part-sectional front view of the air inlet chamber ofFig. 1 ; -
Fig. 5 shows a part-sectional front view of a boiler including the sealed air boiler air inlet chamber ofFig. 1 ; -
Fig. 6 shows a part-sectional side view of the boiler ofFig. 5 ; and -
Fig. 7 shows a heating system including the boiler ofFig. 5 . - A sealed air boiler (sometimes referred to as a room sealed boiler) draws in air for combustion from outside the space in which the boiler is located. Accordingly, the air drawn into the boiler may have different characteristics from the air in the space in which the boiler is located (for example, the air drawn into a sealed air boiler may be wetter than air in the immediate surrounds of the boiler).
- In general, boilers can function more effectively when the air used for combustion is drier, that is, not wet. It is therefore a first non-exclusive aim to provide a sealed air boiler air inlet chamber, which can separate water from combustion air.
- Most boilers (including sealed air boilers) require adjustment during commissioning, for example, it may be necessary to adjust a gas valve when commissioning a boiler. For example, during commissioning it may be necessary to adjust maximum load and minimum load adjusters on a gas valve of a boiler when the boiler is in place. Normally, such gas valve adjusters are within the housing of the boiler to hinder unauthorised or inappropriate access. If the adjusters are located inside the housing of the boiler, the housing must be opened to allow access to the adjusters. It is a common feature of prior art sealed air boilers that the housing is used to isolate the combustion air from the surroundings of the boiler. As will be apparent, in such an arrangement the sealed air boiler is not isolated from its surroundings whilst the boiler housing is open. Accordingly, adjustments made whilst the housing is open may not result in the optimum parameters being set for operation whilst the housing is closed.
- It is therefore a second non-exclusive aim to provide a sealed air boiler inlet chamber, which can be used in the provision of a sealed air boiler, which is sealed both when the housing is open (e.g. during adjustment) and whilst the housing is closed (e.g. during normal use).
- Referring firstly to
Figs 1 to 4 of the accompanying drawings, a sealed air boiler air inlet chamber indicated generally at 1, comprises a casing, defining a volume, an air andwater inlet aperture 101, afirst outlet 3 for water, and asecond outlet 4 for air. - There is also a
barrier 2, spaced from thesecond outlet 4. Thebarrier 2 demarks afirst region 30 of the casing which includes thefirst outlet 3 and asecond region 40 of the casing which includes thesecond outlet 4. Thebarrier 2 is configured to inhibit the flow of water from thefirst region 30 to thesecond region 40 and to permit the flow of air from thefirst region 30 to thesecond region 40. - Such a sealed air boiler
air inlet chamber 1 may provide an advantageous high separation of water from feed air (e.g. outside air). In particular, water which may be present as a contaminate in the feed air will predominantly exit through thefirst outlet 3 in thefirst region 30 and air will predominantly exit through thesecond outlet 4 in thesecond region 40. In this way drier air may be provided to the furnace of a sealed air boiler. - Additionally, the sealed air boiler
air inlet chamber 1 may be used with a sealed air boiler which can still operate as a sealed air boiler even when the housing of the boiler is open, as will be described in more detail below. - As shown, the casing may include side surfaces and/or a base. The side surfaces may be substantially
vertical walls 10.Surfaces 100 of the casing may be inclined with respect to thewalls 10. In some example embodiments, thewalls 10 may includeinclined portions 100. - As shown in
Fig. 1 , thebarrier 2 may extend a height from a plane of the casing including thesecond outlet 4. Such a construction may be particularly simple, and therefore economic. - The
barrier 3 may extend between a first surface and a second surface of the casing. In particular, thebarrier 2 may contact a first surface and a second surface of thechamber 1. The first surface may be awall 10 or aninclined surface 100. The second surface may be awall 10 or aninclined surface 100. - The barrier may contact
multiple walls 10. For example, the barrier may extend betweenopposite walls 10. The barrier may contact multiple points on thesame wall 10. - The
barrier 2 may be a substantiallystraight barrier 2, as shown inFigs 1 to 4 . Alternatively, thebarrier 2 may define an angle. For example, thebarrier 2 may extend between afirst wall 10 and asecond wall 10 that are substantially perpendicular to one another, such that thebarrier 2 defines a right angle. Thebarrier 2 may extend between afirst wall 10 and asecond wall 10 at any angle, e.g. any other angle. Thebarrier 2 may extend between afirst wall 10 and asecond wall 10 where bothwalls 10 are on the same side of the casing. - The
barrier 2 may extend a height that is generally level with the top of aninclined surface 100. Thebarrier 2 may extend a height based on the expected volume of water that may enter thefirst region 30 of the casing in use. Additionally or alternatively, thebarrier 2 may extend a height based on the efficiency with which water leaves thechamber 1 via thefirst outlet 3. - The
barrier 2 may contact a base of the casing of thechamber 1 such that the contact is air-and-water-tight. Such contact may be achieved by any means apparent to the skilled person, for example, by welding thebarrier 2 to thechamber 1. Alternatively, such contact may be achieved by forming thebarrier 2 integrally with thechamber 1. Air-and-water-tight contacts between thebarrier 2 and awall 10 and/or a base of the casing of thechamber 1 may be achieved using any means apparent to the skilled person. - The
barrier 2 may also be spaced from thefirst outlet 3. - The barrier as described above can provide a particularly distinct
second region 40 for thesecond outlet 4, which in turn can be used to provide good separation of water from the air to be fed to the furnace of the boiler. - A surface of the casing may be inclined towards the
first outlet 3 in use. Such inclined surfaces may contribute to the flow of water towards thefirst outlet 3 within thefirst region 30, thereby providing good or increased separation efficiency. - As shown in
Fig. 2 , thefirst outlet 3 may be in a base of thechamber 1. However, thefirst outlet 3 may be defined in awall 10 orinclined surface 100 of thechamber 1, within thefirst region 30 of the casing. For example, thefirst outlet 3 may be defined in a corner of thechamber 1. - The sealed air boiler
air inlet chamber 1 may further comprise aconnector 301 for connecting thefirst outlet 3 to a drain. Thefirst outlet 3 may be connected to afirst connector 301 for connecting thechamber 1 to a pipe. Thefirst connector 301 may extend a length away from the surface defining thefirst outlet 3. Thefirst connector 301 may form part of the inner surface of thefirst outlet 3. Thefirst connector 301 may be integrally formed as part of thechamber 1, or may be otherwise attached to thechamber 1. Thefirst connector 301 may be continuous around the circumference of thefirst outlet 3. Thefirst connector 301 may be another type of connector, designed so as to mesh with the desired exhaust means, such as a pipe. Thefirst connector 301 may provide a water-tight connection between thechamber 1 and an exhaust means. As shown inFig. 1 , thefirst connector 301 can be seen extending a vertical length from thecasing 1. - The sealed air boiler
air inlet chamber 1 may further comprise asecond connector 401 for connecting thesecond outlet 4 to a furnace. Thesecond connector 401 may extend a length away from the surface defining thesecond outlet 4. Thesecond connector 401 may form part of the inner surface of thesecond outlet 4. Thesecond connector 401 may be integrally formed as part of thechamber 1, or may be otherwise attached to thechamber 1. Thesecond connector 401 may be continuous around the circumference of thesecond outlet 4, as shown infigure 1 . Thesecond connector 401 may be another type of connector, designed so as to mesh with the desired exhaust means, such as a pipe. - In
Fig. 1 thesecond connector 401 can be seen extending a vertical length from the circumference of thesecond outlet 4. In some examples thesecond connector 401 may extend a horizontal length away from thesecond outlet 4, and may extend along the outer surface of thechamber 1, in order to connect thechamber 1 to an exhaust means. Thesecond connector 401 may otherwise mate with thechamber 1. - The sealed air boiler
air inlet chamber 1 may have afirst outlet 3 and thesecond outlet 4 of different sizes. In particular, thefirst outlet 3 may be smaller than thesecond outlet 4. This may be advantageous, as the volume of air passing through theinlet chamber 1 and out of thesecond outlet 4 will usually be much larger than the volume of water passing through theinlet chamber 1 and out of thefirst outlet 3. - The sealed air boiler
air inlet chamber 1 may further comprise aspacer 5. The function of thespacer 5 can be for inhibiting (e.g. for stopping or substantially preventing) an object within thechamber 1 from contacting the base of the casing. - As shown in the Figs, the
spacer 5 may be located within thefirst region 30 of the casing. Thespacer 5 can space an open end of an air (and water) inlet pipe, from the casing of thechamber 1, to inhibit (e.g. substantially prevent) the open end of such a pipe from contacting and therefore being closed off by contacting a surface of thechamber 1. Accordingly, the pipe may remain open. - Optionally,
multiple spacers 5 may be provided. Thespacer 5 may extend across a width of thechamber 1. - The
chamber 1 may comprise a fixing 12 for fitting theair inlet chamber 1 to a sealed-air boiler. As shown inFigs 1 to 4 , the fixing 12 may be located on anouter rim 11 of the chamber. - The
outer rim 11 may be continuous around the perimeter of the casing of thechamber 1, as shown infigures 1 to 4 . Additionally or alternatively, theouter rim 11 may be a continuation of thewalls 10, e.g. the top of thewalls 10 may be shaped to form theouter rim 11. - The
outer rim 11 may define a plane which may be substantially perpendicular to that of thewalls 10 of thechamber 1. The fixing 12 may be a cut-out, for use with a further means of fixing thechamber 1 in place. The cut-out may be of dimensions to fit a screw or another fixing. Theouter rim 11 may not define cut-outs 12 and may instead be designed to fit in any other way, as will be apparent to the skilled person. For example, theouter rim 11 may further include hooks or another type of fixing means. For example, rails or another receiving means for thechamber 1 may be positioned in a boiler to allow thechamber 1 to be fixed in place. - The
chamber 1 may be fixed in place within a boiler using an adhesive, e.g. a sealing adhesive or a sealant. For example, an adhesive may be applied to theouter rim 11. Thechamber 1 may be removably fixable to a boiler, for example to facilitate servicing of the boiler including removal of thechamber 1. - As shown in
Figs 5 and6 , there is also provided aboiler 6 including an air-inlet chamber 1 as described above. - The
boiler 6 may be a sealedair boiler 6. Inclusion of theair inlet chamber 1 in a sealedair boiler 6, may be particularly advantageous as it can help to provide a sealed air boiler which is sealed both when the housing of the boiler is open (e.g. during adjustment) and whilst the housing of the boiler is closed (e.g. during normal use). Accordingly, a sealedair boiler 6 which is more easily correctly commissioned can be provided. - The
chamber 1 may be positioned at the top of theboiler 6, as shown. - A surface of the
boiler 6 may close-off a top of thechamber 1 that is open when not installed within theboiler 6. Alternatively, thechamber 1 may be closed-off or contained in some other way, as would be apparent to the skilled person. - The
chamber 1 is for use between the air and water inlet (for example the air and water inlet aperture 101) of aboiler 6 and the rest of the boiler system. - The
boiler 6 may include an air and water inlet pipe. The air andwater inlet aperture 101 of thechamber 1 may receive an air and water inlet pipe in use. Accordingly, water may drip from the air and water inlet pipe. Any water admitted to theinlet chamber 1, is admitted in thefirst region 30 of the casing, accordingly, the water can exit thefirst outlet 3. The air andwater inlet aperture 101 should not open directly into thesecond region 40 of the casing, as thebarrier 2 would not then be able to fulfil its function of substantially preventing or inhibiting water from entering thesecond region 40 of the casing and exiting thesecond outlet 4. - Air from the air and
water inlet aperture 101 is passable over thebarrier 2 into thesecond region 40 of the casing, such that air may exit thechamber 1 via thesecond outlet 4 and may be drawn beyond thechamber 1 further into theboiler 6 for combustion. - As will be appreciated, air is the useful part of the intake into the
chamber 1 and may be drawn into theboiler 6 from thesecond outlet 4 in any suitable way. The sealed air boilerair inlet chamber 1 can be suitable for use with any suitable suction means known in the art of boilers. The term 'drawn' does not exclude the free flow of air into theboiler 6 without the use of any particular suction means or other means of inciting air flow. - With reference to
Figs 5 and6 in particular, afirst pipe 302 is shown, which can connect thefirst outlet 3 of thechamber 1, for example using afirst connector 301, to part of theboiler 6. For example thefirst outlet 3 may be connected to adrain 303. - The
drain 303 may be external to theboiler 6 such that thefirst pipe 302 traverses theboiler 6. Thedrain 303 may be external to theboiler 6 such that water from thefirst outlet 3 does not interact with any other part of the interior of theboiler 6 except for thefirst pipe 302. Thedrain 303 may otherwise be a drainage component inside theboiler 6 that includes a reservoir or a similar water collecting receptacle. In some embodiments, where theboiler 6 is a condensing boiler, thedrain 303 may be the same drain as is used for condensate from the boiler. - With reference to
Figs 5 and6 in particular, asecond pipe 402 is shown, which connects thechamber 1 at thesecond outlet 4, by thesecond connector 401, to a further part of theboiler 6. In particular, thesecond outlet 4 may be connected directly or indirectly to a furnace. Thesecond pipe 402 may have a diameter corresponding to that of thesecond outlet 4. - The
second pipe 402 may be connected in an air-tight manner to thesecond outlet 4. An air tight connection may be advantageous as it can allow the boiler to be air sealed even when a cover of the boiler is not in place. - The
chamber 1 may be shaped to fit to the shape of part of theboiler 6. - As shown in
Fig. 7 , there is also provided aheating system 8, comprising aboiler 6 as described above, including theinlet 1 described above. - The
heating system 8 may be a central heating system. Additionally or alternatively, theheating system 8 may be a water heating system. - The
heating system 8 may comprise a heating element 7, which is in communication with theboiler 6. The heating element 7 may be a wall-mounted radiator. The heating element 7 may be a water heater. - A
single heating system 8 may comprise multiple heating elements 7 and may comprise different types of heating elements 7. - The
heating system 8 may include asingle boiler 6. Theheating system 8 may includemultiple boilers 6 if theheating system 8 is large-scale. Theheating system 8 may include one ormore boilers 6 that include a sealed air boilerair inlet chamber 1 and one ormore boilers 6 without achamber 1, i.e. theheating system 8 may comprise a combination of sealed air boilers and open boilers. - Accordingly, the passage of water, which is a waste product in an air and water intake, into the parts of a
boiler 6 that use air and that work more efficiently with drier air, is satisfactorily prevented by the sealed air boilerair inlet chamber 1 provided. - When used in this specification and claims, the terms "comprises" and "comprising" and variations thereof mean that the specified features, steps or integers are included. The terms are not to be interpreted to exclude the presence of other features, steps or components.
- The features disclosed in the foregoing description, or the following claims, or the accompanying drawings, expressed in their specific forms or in terms of a means for performing the disclosed function, or a method or process for attaining the disclosed result, as appropriate, may, separately, or in any combination of such features, be utilised for realising the invention in diverse forms thereof.
Claims (15)
- A sealed air boiler air inlet chamber, comprising:a casing, defining a volume, an air and water inlet aperture, a first outlet for water, and a second outlet for air; anda barrier, spaced from the second outlet, demarking a first region of the casing including the first outlet and a second region of the casing including the second outlet,wherein the barrier is configured to inhibit the flow of water from the first region to the second region and to permit the flow of air from the first region to the second region.
- A sealed air boiler air inlet chamber according to claim 1, wherein the barrier extends a height from a plane of the casing including the second outlet.
- A sealed air boiler air inlet chamber according to claim 1 or claim 2, wherein the barrier extends between a first surface and a second surface of the casing.
- A sealed air boiler air inlet chamber according to claim 1, claim 2 or claim 3, wherein a surface of the casing is inclined towards the first outlet in use.
- A sealed air boiler air inlet chamber according to any preceding claim, further comprising a connector for connecting the first outlet to a drain.
- A sealed air boiler air inlet chamber according to any preceding claim, further comprising a connector for connecting the second outlet to a furnace.
- A sealed air boiler air inlet chamber according to any preceding claim, wherein the first outlet and the second outlet are of different sizes.
- A sealed air boiler air inlet according to claim 7, wherein the first outlet is smaller than the second outlet.
- A sealed air boiler air inlet chamber according to any preceding claim, further comprising a spacer.
- A sealed air boiler air inlet chamber according to claim 9, wherein the spacer is for inhibiting an object within the chamber from contacting a surface of the chamber.
- A sealed air boiler air inlet chamber according to claim 10, wherein the object is an air inlet pipe, and wherein the spacer is for inhibiting an open end of the pipe from contacting a surface of the chamber, such that the pipe remains open.
- A sealed air boiler air inlet chamber according to any preceding claim, wherein the chamber comprises a fixing for fitting the air inlet chamber to a sealed-air boiler.
- A sealed air boiler air inlet chamber according to claim 12, comprising an outer rim such that the fixing is located on the outer rim of the chamber.
- A boiler, comprising an air-inlet chamber according to any preceding claim.
- A heating system, comprising a boiler according to claim 14.
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
GB1611266.6A GB2551749B (en) | 2016-06-29 | 2016-06-29 | Sealed air boiler air inlet chamber |
Publications (2)
Publication Number | Publication Date |
---|---|
EP3264005A1 true EP3264005A1 (en) | 2018-01-03 |
EP3264005B1 EP3264005B1 (en) | 2019-11-06 |
Family
ID=56891634
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP17178153.7A Active EP3264005B1 (en) | 2016-06-29 | 2017-06-27 | Sealed air boiler air inlet chamber |
Country Status (2)
Country | Link |
---|---|
EP (1) | EP3264005B1 (en) |
GB (1) | GB2551749B (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US11512872B2 (en) * | 2020-10-20 | 2022-11-29 | Rheem Manufacturing Company | Tankless water heater connector |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0036364A1 (en) * | 1980-03-13 | 1981-09-23 | SAUNIER DUVAL EAU CHAUDE CHAUFFAGE S.D.E.C.C. - Société anonyme | Method of connecting a gas fired heater of the sealed and forced draught type to a conventional chimney |
JP2003287287A (en) * | 2002-03-27 | 2003-10-10 | Noritz Corp | Combustion apparatus |
JP2005061792A (en) * | 2003-08-20 | 2005-03-10 | Paloma Ind Ltd | Water heater |
US20150176862A1 (en) * | 2013-12-25 | 2015-06-25 | Noritz Corporation | Water heater |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10205746A (en) * | 1997-01-20 | 1998-08-04 | Fujitsu General Ltd | Intake and exhaust device |
KR101020858B1 (en) * | 2010-02-17 | 2011-03-09 | 주식회사종합건축사사무소가람건축 | Outer cap of hole for natural ventilation |
-
2016
- 2016-06-29 GB GB1611266.6A patent/GB2551749B/en not_active Expired - Fee Related
-
2017
- 2017-06-27 EP EP17178153.7A patent/EP3264005B1/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0036364A1 (en) * | 1980-03-13 | 1981-09-23 | SAUNIER DUVAL EAU CHAUDE CHAUFFAGE S.D.E.C.C. - Société anonyme | Method of connecting a gas fired heater of the sealed and forced draught type to a conventional chimney |
JP2003287287A (en) * | 2002-03-27 | 2003-10-10 | Noritz Corp | Combustion apparatus |
JP2005061792A (en) * | 2003-08-20 | 2005-03-10 | Paloma Ind Ltd | Water heater |
US20150176862A1 (en) * | 2013-12-25 | 2015-06-25 | Noritz Corporation | Water heater |
Also Published As
Publication number | Publication date |
---|---|
GB2551749B (en) | 2020-06-17 |
GB201611266D0 (en) | 2016-08-10 |
EP3264005B1 (en) | 2019-11-06 |
GB2551749A (en) | 2018-01-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US10145581B2 (en) | Condensate pan with condensate trap | |
US5313930A (en) | Air intake for furnace | |
JP6099925B2 (en) | Air conditioner outdoor unit | |
US3028843A (en) | Gas water heater for trailers and houses | |
JPH10253099A (en) | Outdoor unit for separate type air conditioner | |
CN105485883B (en) | Vertical air conditioner | |
EP3264005B1 (en) | Sealed air boiler air inlet chamber | |
CN106288038B (en) | Shell assembly of air conditioner outdoor unit and air conditioner outdoor unit | |
CN207830657U (en) | The Anti-splash automatic exhaust steam valve of adjustable pressure | |
US4564142A (en) | Hydronic system with circulators connected to a header | |
JP2010281461A (en) | Outdoor unit for air conditioner | |
CN203349381U (en) | Embedded type air conditioner | |
US8104634B2 (en) | Drain pan for mounted water equipment | |
US9464816B1 (en) | Attic ventilation system | |
US4373472A (en) | Water heater | |
JP6489312B2 (en) | Air conditioner | |
US6886756B2 (en) | Method and apparatus for controlling and providing electrical connections for a boiler | |
US6772713B2 (en) | Method and apparatus for providing and utilizing outside air for boiler combustion | |
US7097210B2 (en) | Method and apparatus for providing a transition connector to introduce outside air and vent flue for boiler combustion | |
JP2016223666A (en) | Air conditioner | |
US11725888B2 (en) | Multi-position condensation kit and bracket | |
JP7138371B2 (en) | Filter equipment and water heater | |
JPH0422176Y2 (en) | ||
CN113614466B (en) | Indoor unit of air conditioner | |
JP2016223667A (en) | Air conditioner |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE APPLICATION HAS BEEN PUBLISHED |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
AX | Request for extension of the european patent |
Extension state: BA ME |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE |
|
17P | Request for examination filed |
Effective date: 20180703 |
|
RBV | Designated contracting states (corrected) |
Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
RIC1 | Information provided on ipc code assigned before grant |
Ipc: F24H 9/00 20060101AFI20190329BHEP Ipc: F23L 17/14 20060101ALI20190329BHEP Ipc: F24D 19/08 20060101ALI20190329BHEP Ipc: F23L 1/00 20060101ALI20190329BHEP Ipc: F24H 9/12 20060101ALI20190329BHEP |
|
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: GRANT OF PATENT IS INTENDED |
|
INTG | Intention to grant announced |
Effective date: 20190529 |
|
GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE PATENT HAS BEEN GRANTED |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
REG | Reference to a national code |
Ref country code: GB Ref legal event code: FG4D |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: EP Ref country code: AT Ref legal event code: REF Ref document number: 1199272 Country of ref document: AT Kind code of ref document: T Effective date: 20191115 |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: FG4D |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R096 Ref document number: 602017008360 Country of ref document: DE |
|
REG | Reference to a national code |
Ref country code: NL Ref legal event code: MP Effective date: 20191106 |
|
REG | Reference to a national code |
Ref country code: LT Ref legal event code: MG4D |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: PT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20200306 Ref country code: NO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20200206 Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20200207 Ref country code: PL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191106 Ref country code: LT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191106 Ref country code: NL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191106 Ref country code: SE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191106 Ref country code: LV Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191106 Ref country code: BG Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20200206 Ref country code: FI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191106 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: RS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191106 Ref country code: HR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191106 Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20200306 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: AL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191106 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191106 Ref country code: EE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191106 Ref country code: RO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191106 Ref country code: ES Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191106 Ref country code: CZ Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191106 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R097 Ref document number: 602017008360 Country of ref document: DE |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: MK05 Ref document number: 1199272 Country of ref document: AT Kind code of ref document: T Effective date: 20191106 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SM Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191106 Ref country code: SK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191106 |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
26N | No opposition filed |
Effective date: 20200807 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191106 Ref country code: AT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191106 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MC Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191106 Ref country code: IT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191106 |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LU Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20200627 |
|
REG | Reference to a national code |
Ref country code: BE Ref legal event code: MM Effective date: 20200630 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20200627 Ref country code: FR Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20200630 Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20200630 Ref country code: LI Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20200630 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: BE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20200630 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R082 Ref document number: 602017008360 Country of ref document: DE Representative=s name: DEHNS, DE Ref country code: DE Ref legal event code: R082 Ref document number: 602017008360 Country of ref document: DE Representative=s name: DEHNS PATENT AND TRADEMARK ATTORNEYS, DE |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: TR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191106 Ref country code: MT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191106 Ref country code: CY Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191106 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20191106 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: GB Payment date: 20230829 Year of fee payment: 7 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: DE Payment date: 20230821 Year of fee payment: 7 |