EP3132550B1 - Detecting traffic load for a telecommunications system using narrowband signal monitoring - Google Patents
Detecting traffic load for a telecommunications system using narrowband signal monitoring Download PDFInfo
- Publication number
- EP3132550B1 EP3132550B1 EP15780462.6A EP15780462A EP3132550B1 EP 3132550 B1 EP3132550 B1 EP 3132550B1 EP 15780462 A EP15780462 A EP 15780462A EP 3132550 B1 EP3132550 B1 EP 3132550B1
- Authority
- EP
- European Patent Office
- Prior art keywords
- narrowband signals
- profile
- resource utilization
- remote units
- traffic load
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000012544 monitoring process Methods 0.000 title claims description 17
- 238000000034 method Methods 0.000 claims description 16
- 238000013468 resource allocation Methods 0.000 claims description 7
- 238000005070 sampling Methods 0.000 claims description 3
- 238000001914 filtration Methods 0.000 claims 1
- 238000010295 mobile communication Methods 0.000 description 7
- 238000010586 diagram Methods 0.000 description 5
- 238000005259 measurement Methods 0.000 description 4
- 238000005457 optimization Methods 0.000 description 3
- 230000002776 aggregation Effects 0.000 description 2
- 238000004220 aggregation Methods 0.000 description 2
- 230000005540 biological transmission Effects 0.000 description 2
- 239000000969 carrier Substances 0.000 description 2
- 239000002131 composite material Substances 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 230000007774 longterm Effects 0.000 description 2
- 230000003595 spectral effect Effects 0.000 description 2
- 238000012935 Averaging Methods 0.000 description 1
- RYGMFSIKBFXOCR-UHFFFAOYSA-N Copper Chemical compound [Cu] RYGMFSIKBFXOCR-UHFFFAOYSA-N 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 229910052802 copper Inorganic materials 0.000 description 1
- 239000010949 copper Substances 0.000 description 1
- 230000005574 cross-species transmission Effects 0.000 description 1
- 239000000835 fiber Substances 0.000 description 1
- 238000009432 framing Methods 0.000 description 1
- 230000003287 optical effect Effects 0.000 description 1
- 230000008520 organization Effects 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 230000001960 triggered effect Effects 0.000 description 1
Images
Classifications
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04B—TRANSMISSION
- H04B17/00—Monitoring; Testing
- H04B17/30—Monitoring; Testing of propagation channels
- H04B17/309—Measuring or estimating channel quality parameters
- H04B17/318—Received signal strength
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04W—WIRELESS COMMUNICATION NETWORKS
- H04W72/00—Local resource management
- H04W72/50—Allocation or scheduling criteria for wireless resources
- H04W72/52—Allocation or scheduling criteria for wireless resources based on load
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04W—WIRELESS COMMUNICATION NETWORKS
- H04W24/00—Supervisory, monitoring or testing arrangements
- H04W24/08—Testing, supervising or monitoring using real traffic
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04W—WIRELESS COMMUNICATION NETWORKS
- H04W72/00—Local resource management
- H04W72/50—Allocation or scheduling criteria for wireless resources
- H04W72/51—Allocation or scheduling criteria for wireless resources based on terminal or device properties
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04W—WIRELESS COMMUNICATION NETWORKS
- H04W72/00—Local resource management
- H04W72/04—Wireless resource allocation
- H04W72/044—Wireless resource allocation based on the type of the allocated resource
- H04W72/0446—Resources in time domain, e.g. slots or frames
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04W—WIRELESS COMMUNICATION NETWORKS
- H04W72/00—Local resource management
- H04W72/04—Wireless resource allocation
- H04W72/044—Wireless resource allocation based on the type of the allocated resource
- H04W72/0453—Resources in frequency domain, e.g. a carrier in FDMA
Definitions
- the present disclosure generally relates to telecommunications systems and more particularly (though not necessarily exclusively) to detecting traffic loads using narrowband signal monitoring.
- a distributed antenna system can provide a signal transport network for communicating signals between a base transceiver station and mobile communication devices.
- the DAS can include one or more master units and remote units.
- the master unit can be coupled to a base transceiver station using radio frequency cables.
- the base transceiver station can send downlink signals for receipt by the mobile communication devices.
- the master unit can receive downlink signals from the base transceiver station and distribute the downlink signals to one or more remote units.
- the remote units can transmit downlink signals to mobile communication devices within the coverage area that each remote unit services.
- the mobile communication devices can send uplink signals to the base transceiver station.
- the remote units can receive uplink signals from the mobile communication devices within respective coverage areas.
- the remote units can combine the uplink signals and transmit the combined uplink signals to the master unit.
- the master unit can transmit the uplink signals to the base transceiver station.
- a base transceiver station can allocate time and frequency channel resources in a given cell in a coverage area, but no information may be available to the base transceiver station about the utilization of channel resources at the individual remote unit level.
- WO 2014/022211 A2 (Dali Systems Co Ltd) published 6 February 2014 discloses a system for dynamically routing signals in a distributed antenna.
- the system includes a plurality of digital access units (DAUs).
- the DAUs are coupled and operable to route signals between the plurality of DAUs.
- the system also includes a plurality of digital remote units (DRUs) coupled to the plurality of DAUs and operable to transport signals between the DRUs, the DAUs, and a plurality of base transceiver stations (BTSs).
- DRUs digital remote units
- BTSs base transceiver stations
- the system further includes a plurality of traffic monitoring modules and a network optimization goal an optimization algorithm.
- IDAS Intelligent Distributed Antenna System
- BTS Base Transceiver Station
- SON Self-Optimized Network
- Monitoring the traffic on the DAS network is required in order to plan, configure and optimize the SON.
- a method is disclosed to monitor the required SON information in order to properly configure the remote antenna allocation.
- An LTE SON system is described using a particular method for traffic monitoring.
- a system comprising one or more remote units and a monitoring unit, as defined in the appended claims.
- Certain aspects and features relate to detecting a traffic load by monitoring one or more narrowband signals.
- a wideband uplink signal can be decomposed into one or more narrowband signals.
- a resource utilization profile comprising time and frequency resource utilization information of the used uplink radio channel can be estimated at each remote unit based on information extracted from and associated with the narrowband signals generated from a wideband uplink signal. Based on the resource utilization profile, a traffic load can be determined at each remote unit.
- a repeater can include a device that receives a digital signal on an electromagnetic or optical transmission medium and regenerates the signal along a next segment of the medium.
- a distributed antenna system can include a type of digital repeater that can use mediums such as fiber optic or copper cables.
- a DAS will be used throughout as an example of a digital repeater suitable for detecting traffic load by monitoring one or more narrowband signals, but other types of telecommunication systems can be used.
- a remote unit can include circuitry that can be coupled to an antenna element. Alternatively, the remote unit can include an antenna element.
- the remote units can transmit uplink signals to the master unit.
- the master unit can combine uplink signals received from remote units for transmission to the base transceiver station.
- a base transceiver station can be configured to reallocate resources optimally based on the spatial distribution of the traffic load for each remote unit in the DAS. For example, the organization of remote units and cells can be adjusted based on the detected traffic load for each remote unit.
- the simulcast factor can be reduced for high-load cells and the simulcast factor can be increased for low-load cells.
- additional cells associated with different radio frequency (“RF") carriers can be designated to be associated with high-load remote units.
- RF radio frequency
- Optimizing the traffic load based on measured power spectral density profiles of narrowband signals can reduce or improve the efficiency of radio link budgets. Because remote units with a low load can use less frequency resources, the available composite transmit power can be used on a narrower bandwidth and the transmitted power spectral density can be increased.
- FIG. 1 illustrates a telecommunications system suitable for implementing an aspect of the present disclosure.
- the system can include a DAS 100 coupled to a base transceiver station 102.
- the DAS 100 can include a master unit 104 and remote units 106, 108.
- Each remote unit 106, 108 can transmit information to and receive information from mobile communication devices 110, 112 within the respective coverage area 114, 116 of each remote unit 106, 108.
- two remote units are shown, any number of remote units, including one, can be used.
- one master unit is shown, any number of master units can be used.
- the DAS 100 can be communicatively coupled to the base transceiver station 102 using, for example, radio frequency cables between the base transceiver station 102 and master unit 104 in the DAS 100. In other examples, the DAS 100 is communicatively coupled to the base transceiver station 102 by a wireless link.
- the channel resource utilization profile can be the same for each remote unit in the DAS due to a downlink single simulcast.
- the DAS master unit 104 can split the RF signals for each RF carrier associated with a given cell supported by the base transceiver station.
- the same RF signal of a given cell can be split into multiple signal copies that can be distributed to multiple remote units.
- the signal copies can be distributed according to a simulcast factor.
- the simulcast factor can be defined, for example, by the number of remote units radiating the same cell signals.
- the base transceiver station can allocate time and frequency channel resources in a given cell.
- the channel resource utilization profile can vary substantially across different remote units.
- channel resource utilization can vary as a function of the distribution of active mobile communication devices transmitting uplink signals throughout the coverage areas served by the remote units.
- the DAS can monitor the resource utilization profile for each remote unit to determine the traffic load of a given cell in the coverage area served by the respective remote units.
- the resource utilization profile can be monitored anywhere in the DAS (e.g., at the remote unit level, at the master unit level, at the base station, etc.).
- FIG. 2 is a flow chart showing examples of a process for detecting traffic load for a telecommunications system using narrowband signal monitoring.
- a wideband uplink signal can be decomposed into one or more complex narrowband signals (e.g., I/Q samples, where "I” and “Q” can correspond to the real and imaginary parts of the signal, respectively).
- the sample rate of each complex narrowband signals is decimated to the minimum acceptable value.
- the multiple narrowband signals are generated using filter banks.
- each carrier can be processed by a filter bank having a specific narrowband filters grid.
- the frequency resolution of the filter bank can be dimensioned according to the carrier format of the specific uplink signal (e.g., LTE, GSM, etc.).
- narrowband signals can be generated, for example, by sampling signal information from the uplink signal and performing off-channel-path processing.
- the per-user frequency resource allocation can be 180 kHz, which can correspond to a single physical resource block (PRB).
- PRB physical resource block
- the individual bandwidth of each narrowband signal can be in the same order to reduce the effects of energy spillover from user devices operating adjacent in frequency.
- GSM uplink signals TDMA can scheme over a single 200 kHz carrier and FDMA can scheme over different carriers using frequency hopping. Each GSM carrier of 200 kHz bandwidth can be accommodated with a filter bank having this frequency resolution.
- the nominal channel bandwidth can be 5MHz (e.g., 3.84MHz + roll-off).
- a higher frequency resolution can be used to estimate resources assigned to each user.
- a power profile is determined for the narrowband signals.
- the power profile for each carrier can include determining the square of the momentary power of each narrowband signal (e.g., adding the square of the I and Q samples of the complex narrowband signals).
- a resource utilization profile is estimated.
- the estimation can be based on a resource allocation map over time and frequency.
- Time and frequency resource utilization information includes information extracted from the narrowband signals and information defined by a signal format associated with the narrowband signals.
- the power profile for samples of the narrowband profiles can be stored in a database. The power profile of the samples versus the frequency of the carrier and the sample time can yield a resource allocation map of the remote units over time and frequency.
- the square of the I and Q samples of the complex narrowband signals can be added together.
- the result can be the square of the power of the signal over a particular time and frequency bin.
- the collections of square power values can represent the resource utilization profile over the time and the frequency with a time resolution equal to the sample time and a frequency resolution equal to the narrowband filters grid.
- the calculated square power values can be averaged over the time and frequency domain according to the signal format known by the system.
- a traffic load is determined based on the estimated resource utilization profile.
- Active resources whether in the frequency domain, time domain, or both, can indicate whether a user signal is being transported by a remote unit in the DAS. All of the narrowband signals having an estimated resource utilization profile at or above a predetermined threshold are assumed to carry traffic load and are marked as active. All of the narrowband signals having an estimated resource utilization profile lower than a predetermined threshold are assumed to carry only noise, so are marked as inactive.
- the predetermined threshold for determining whether narrowband signals are active or inactive is based on the power profile of the noise floor measured at non-loaded traffic conditions when no traffic is being transmitted through the DAS (e.g., at the commissioning of the system).
- a RUM can measure narrowband signals which are not transporting traffic load at a given point in time.
- the noise floor calibration can be applied to the signal formats processed by the RUM of each remote unit.
- the noise floor is a reference for discriminating between "active" and "inactive" resources during a given time period. The start of the time period can be triggered when the first narrow band signal is detected as "active.”
- the traffic activity can be measured as a percentage of resource usage versus the total available resources.
- the frequency resources that are in use per remote unit can be determined over time and frequency. Using the specific frequency resources that are in use per remote unit over time and frequency can provide more precise measurement results than using a long-term power measurement because imperfections in power control for the user device may not affect the power measurement. Long-term power measurements can be available, for example, in UMTS embodiments.
- the composite power profile generated by active user devices in the cell can be estimated.
- the admission/congestion control procedure of the base transceiver station can be configured to ensure that a maximum received total wideband power ("RTWP") is not exceeded.
- RCWP maximum received total wideband power
- configuring the base transceiver station to ensure that a maximum RTWP is not exceeded can include limiting the maximum number of user devices attached to the cell.
- the percentage of resource usage versus full load condition can be estimated.
- the number of active user devices per time slot can be estimated by measuring the number of active physical resource blocks over the total number of physical resource blocks determined to be "active". Assuming a non-adjacent frequency allocation for the users, different groups of active physical resource blocks allocated to a specific user can be identified. The number of user devices per time slot can be computed by dividing the total number of "active" physical resource blocks by the number of identified physical resource block groups.
- a physical resource block can be a minimum resource assigned to a user.
- traffic load optimization policies can be applied by the base transceiver station. For example, the simulcast factor of the cells distributed through the DAS can be modified and more carrier frequencies can be allocated to remote units reporting high traffic load. By allocating more carrier frequencies to high-load remote units, the traffic load per carrier for a given remote unit can be reduced.
- a base transceiver station can allocate all resources to a user device if that user device is the only one communicating in the DAS. Rather than measuring the number of user devices directly, the system can measure the load and optimize accordingly.
- FIG. 3 is a diagram illustrating a DAS suitable for detecting traffic load by monitoring narrowband signals.
- One or more DAS remote units 300 labeled RU #0 through RU #N, can communicate multi-carrier RF uplink signals.
- the uplink signals are decomposed into multiple narrowband complex signals (I/Q samples) using filter banks 302.
- Separate filter banks can be configured to decompose uplink signals having like signal formats.
- LTE SC-FDMA uplink signals received by the remote unit can be decomposed by a multi-carrier LTE filter bank (e.g., LTE Filter Bank #0 for RU #0, LTE Filter Bank #N for DAS RU #N).
- UMTS uplink signals received by the remote unit can be decomposed by a multi-carrier UMTS filter bank (e.g., UMTS Filter Bank #0 for RU #0, UMTS Filter Bank #N for remote unit RU #N).
- GSM uplink signals received by the remote unit can be decomposed by a multi-carrier GSM filter bank (e.g., GSM Filter Bank #0 for RU #0, GSM Filter Bank #N for RU #N).
- each carrier signal can, alternatively, be processed by a filter bank having a narrowband filter grid designed for a specified carrier.
- the narrowband signals that are outputted by the filter bank(s) may not need to be grouped by format.
- the narrowband signals used to determine a power profile can be ungrouped (e.g., one signal per power profile) or can be grouped based on other characteristics (e.g., grouped by carrier).
- each master unit can include a resource utilization monitor ("RUM"), RUM #0 through RUM #N, that is configured to receive, monitor (or process), and transmit the narrowband complex signals generated from the uplink signals.
- RUM resource utilization monitor
- a RUM is configured to receive the narrowband complex signals and determine a power profile for each of the narrowband complex signals.
- narrowband signals of the same carrier or carrier signal format can, alternatively, be processed together to determine the respective power profile for each carrier or format.
- the RUM is further configured to estimate time and frequency channel resource utilization information of the radio channel at the remote units.
- a resource utilization profile of the radio channel is determined based on the measured power profiles associated with the narrowband signals and the time and frequency for each carrier.
- the RUM determines a traffic load based on the resource utilization profile.
- This information can be fed into a multistage, aggregation, transport and distribution block 306.
- the signal carrying the information can be routed to the antenna ports 308 servicing the base transceiver stations BTS #0 through BTS #N.
- a RUM can be located anywhere in the DAS.
- the functionality of the RUM can be integrated into a remote unit, a master unit, or an expansion unit.
- the RUM integrated into a master unit.
- the receiver and transmitter functions can, in some aspects, utilize the receiving and transmitting means of the unit into which it is integrated.
- the functionality of the RUM can be distributed throughout the DAS without departing from the scope of the subject matter described herein.
- FIG. 4 is a functional block diagram of a RUM according to one example.
- the RUM 400 can include a receiver 402 and a processor 404 to receive and process, respectively, narrowband signals (e.g., I/Q samples) generated from uplink signals.
- the processor 404 can process common signal formats (e.g., LTE, UMTS, GSM) together.
- a power profile 406 can be determined for each grouping of I/Q samples.
- the processor 404 can determine an LTE Power Profile 406a for the LTE narrowband signals received, a UMTS Power Profile 406b for the UMTS narrowband signals received, and a GSM Power Profile 406c for the GSM narrowband signals received.
- each power profile 406 can be stored in a database 408 in the RUM.
- a resource utilization profile 410 is estimated for each remote unit based on the power profiles 406.
- a traffic load is determined from the resource utilization profile 410. The traffic load information is transmitted by a transmitter 414 to the base transceiver station of the DAS through the transport network as a part of control messaging.
- resources utilization monitor RUM #0 can process the narrowband I/Q samples generated from the uplink signals received from remote unit RU #0.
- RUM #0 can estimate the resource utilization profile for RU #0 based on a power profile of the narrowband I/Q samples from remote unit RU #0.
- RUM #0 can determine a traffic load based on the estimated resource utilization profile and transmit the traffic load information to one or more of the BTS antenna ports 308.
- the traffic load information is transmitted to an antenna port 308 of a base transceiver station that can optimize the traffic load by reallocating resources within the DAS.
- a RUM 400 can determine a power profile 406 per sample time and in the time domain.
- the RUM 400 can apply a different monitoring function to power profiles 406 related to different signal formats, depending on the time domain characteristics of the received signal frame.
- Power profiles 406 calculated at each sample time can be averaged over a time window that is equal to the time resolution in order to correspond to changes in the resource allocation applied to each specific carrier format.
- the frequency resolution of the power profile 406 can be defined by the filter bank resolution.
- a burst period can be defined to be 0.577 msec.
- a time division multiple access (“TDMA") frame includes eight burst periods.
- the GSM frequency-hopping rate corresponds to the TDMA framing.
- One TDMA frame can be 4.615 msec.
- the time resolution of the power profile can be at least equal to the GSM burst.
- the frame duration is 10 msec, but the shortest time transmit interval (TTI) for resource scheduling can be 2 msec.
- Time slot resolution of the power profile can be at least equal to the TTI duration for each UMTS carrier.
- the physical resource block duration can be equal to a time slot of 0.5 msec.
- Time slot resolution of the power profile can be at least equal to the physical resource block duration for each LTE carrier.
Landscapes
- Engineering & Computer Science (AREA)
- Computer Networks & Wireless Communication (AREA)
- Signal Processing (AREA)
- Quality & Reliability (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Mobile Radio Communication Systems (AREA)
Description
- The present disclosure generally relates to telecommunications systems and more particularly (though not necessarily exclusively) to detecting traffic loads using narrowband signal monitoring.
- A distributed antenna system ("DAS") can provide a signal transport network for communicating signals between a base transceiver station and mobile communication devices. The DAS can include one or more master units and remote units. The master unit can be coupled to a base transceiver station using radio frequency cables. The base transceiver station can send downlink signals for receipt by the mobile communication devices. The master unit can receive downlink signals from the base transceiver station and distribute the downlink signals to one or more remote units. The remote units can transmit downlink signals to mobile communication devices within the coverage area that each remote unit services. The mobile communication devices can send uplink signals to the base transceiver station. The remote units can receive uplink signals from the mobile communication devices within respective coverage areas. The remote units can combine the uplink signals and transmit the combined uplink signals to the master unit. The master unit can transmit the uplink signals to the base transceiver station.
- A base transceiver station can allocate time and frequency channel resources in a given cell in a coverage area, but no information may be available to the base transceiver station about the utilization of channel resources at the individual remote unit level.
-
WO 2014/022211 A2 (Dali Systems Co Ltd) published 6 February 2014 discloses a system for dynamically routing signals in a distributed antenna. The system includes a plurality of digital access units (DAUs). The DAUs are coupled and operable to route signals between the plurality of DAUs. The system also includes a plurality of digital remote units (DRUs) coupled to the plurality of DAUs and operable to transport signals between the DRUs, the DAUs, and a plurality of base transceiver stations (BTSs). The system further includes a plurality of traffic monitoring modules and a network optimization goal an optimization algorithm. - Seyed Amin Hejazi et al: "Traffic Monitoring in a LTE distributed antenna system", published 1 May 2013, discloses an Intelligent Distributed Antenna System (IDAS) fed by a multiple Base Transceiver Station (BTS) which has the ability to distribute the radio resources over a given geographic area. To enable an efficient distribution of radio resources amongst the antenna modules, a server is utilized to dynamically allocate the remote antenna modules to the BTSs using a Self-Optimized Network (SON) algorithm. Monitoring the traffic on the DAS network is required in order to plan, configure and optimize the SON. A method is disclosed to monitor the required SON information in order to properly configure the remote antenna allocation. An LTE SON system is described using a particular method for traffic monitoring.
- In accordance with a first aspect of the invention there is provided a method, as defined in the appended claims.
- In accordance with a second aspect of the invention there is provided a system comprising one or more remote units and a monitoring unit, as defined in the appended claims.
-
-
FIG. 1 is a block diagram depicting a telecommunications system according to one example of the present disclosure. -
FIG. 2 is a flow chart depicting a process for detecting traffic load for a telecommunications system using narrowband signal monitoring according to one example of the present disclosure. -
FIG. 3 is a functional block diagram depicting a distributed antenna system for detecting traffic load using narrowband signal monitoring according to one example of the present disclosure. -
FIG. 4 is a functional block diagram depicting a resource utilization monitor according to one example of the present disclosure. - Certain aspects and features relate to detecting a traffic load by monitoring one or more narrowband signals. In some aspects, a wideband uplink signal can be decomposed into one or more narrowband signals. A resource utilization profile comprising time and frequency resource utilization information of the used uplink radio channel can be estimated at each remote unit based on information extracted from and associated with the narrowband signals generated from a wideband uplink signal. Based on the resource utilization profile, a traffic load can be determined at each remote unit.
- In digital communications systems, a repeater can include a device that receives a digital signal on an electromagnetic or optical transmission medium and regenerates the signal along a next segment of the medium. A distributed antenna system (DAS) can include a type of digital repeater that can use mediums such as fiber optic or copper cables. For purposes of illustration, a DAS will be used throughout as an example of a digital repeater suitable for detecting traffic load by monitoring one or more narrowband signals, but other types of telecommunication systems can be used.
- A remote unit can include circuitry that can be coupled to an antenna element. Alternatively, the remote unit can include an antenna element. The remote units can transmit uplink signals to the master unit. The master unit can combine uplink signals received from remote units for transmission to the base transceiver station. A base transceiver station can be configured to reallocate resources optimally based on the spatial distribution of the traffic load for each remote unit in the DAS. For example, the organization of remote units and cells can be adjusted based on the detected traffic load for each remote unit. The simulcast factor can be reduced for high-load cells and the simulcast factor can be increased for low-load cells. In another example, additional cells associated with different radio frequency ("RF") carriers can be designated to be associated with high-load remote units. Optimizing the traffic load based on measured power spectral density profiles of narrowband signals can reduce or improve the efficiency of radio link budgets. Because remote units with a low load can use less frequency resources, the available composite transmit power can be used on a narrower bandwidth and the transmitted power spectral density can be increased.
- These illustrative examples are given to introduce the reader to the general subject matter discussed here and are not intended to limit the scope of the disclosed concepts. The following sections describe various additional features and examples with reference to the drawings, but, like the illustrative examples, should not be used to limit the present disclosure.
-
FIG. 1 illustrates a telecommunications system suitable for implementing an aspect of the present disclosure. The system can include aDAS 100 coupled to abase transceiver station 102. The DAS 100 can include amaster unit 104 andremote units remote unit mobile communication devices respective coverage area remote unit DAS 100 can be communicatively coupled to thebase transceiver station 102 using, for example, radio frequency cables between thebase transceiver station 102 andmaster unit 104 in theDAS 100. In other examples, the DAS 100 is communicatively coupled to thebase transceiver station 102 by a wireless link. - In the downlink path, the channel resource utilization profile can be the same for each remote unit in the DAS due to a downlink single simulcast. For example, the
DAS master unit 104 can split the RF signals for each RF carrier associated with a given cell supported by the base transceiver station. The same RF signal of a given cell can be split into multiple signal copies that can be distributed to multiple remote units. In one aspect, the signal copies can be distributed according to a simulcast factor. The simulcast factor can be defined, for example, by the number of remote units radiating the same cell signals. The base transceiver station can allocate time and frequency channel resources in a given cell. - In the uplink path, the channel resource utilization profile can vary substantially across different remote units. For example, channel resource utilization can vary as a function of the distribution of active mobile communication devices transmitting uplink signals throughout the coverage areas served by the remote units. The DAS can monitor the resource utilization profile for each remote unit to determine the traffic load of a given cell in the coverage area served by the respective remote units. The resource utilization profile can be monitored anywhere in the DAS (e.g., at the remote unit level, at the master unit level, at the base station, etc.).
-
FIG. 2 is a flow chart showing examples of a process for detecting traffic load for a telecommunications system using narrowband signal monitoring. Atblock 200, a wideband uplink signal can be decomposed into one or more complex narrowband signals (e.g., I/Q samples, where "I" and "Q" can correspond to the real and imaginary parts of the signal, respectively). The sample rate of each complex narrowband signals is decimated to the minimum acceptable value. In some aspects, the multiple narrowband signals are generated using filter banks. For example, each carrier can be processed by a filter bank having a specific narrowband filters grid. The frequency resolution of the filter bank can be dimensioned according to the carrier format of the specific uplink signal (e.g., LTE, GSM, etc.). In other aspects, where filter banks may not be used for decomposing the uplink signal, narrowband signals can be generated, for example, by sampling signal information from the uplink signal and performing off-channel-path processing. - Information regarding the number of carrier frequencies, channel bandwidth and format served by each remote unit in the DAS can be available during the system configuration phase. For example, with respect to LTE SC-FDMA uplink signals, the per-user frequency resource allocation can be 180 kHz, which can correspond to a single physical resource block (PRB). The individual bandwidth of each narrowband signal can be in the same order to reduce the effects of energy spillover from user devices operating adjacent in frequency. With respect to GSM uplink signals, TDMA can scheme over a single 200 kHz carrier and FDMA can scheme over different carriers using frequency hopping. Each GSM carrier of 200 kHz bandwidth can be accommodated with a filter bank having this frequency resolution. With respect to UMTS uplink signals, the nominal channel bandwidth can be 5MHz (e.g., 3.84MHz + roll-off). When a CDMA scheme for user-resource allocation is used over the entire channel bandwidth, a higher frequency resolution can be used to estimate resources assigned to each user.
- At
block 202, a power profile is determined for the narrowband signals. In some aspects, the power profile for each carrier can include determining the square of the momentary power of each narrowband signal (e.g., adding the square of the I and Q samples of the complex narrowband signals). - At
block 204, a resource utilization profile is estimated. The estimation can be based on a resource allocation map over time and frequency. Time and frequency resource utilization information includes information extracted from the narrowband signals and information defined by a signal format associated with the narrowband signals. For example, the power profile for samples of the narrowband profiles can be stored in a database. The power profile of the samples versus the frequency of the carrier and the sample time can yield a resource allocation map of the remote units over time and frequency. - For each sample time, the square of the I and Q samples of the complex narrowband signals can be added together. The result can be the square of the power of the signal over a particular time and frequency bin. The collections of square power values can represent the resource utilization profile over the time and the frequency with a time resolution equal to the sample time and a frequency resolution equal to the narrowband filters grid. The calculated square power values can be averaged over the time and frequency domain according to the signal format known by the system.
- At
block 206, a traffic load is determined based on the estimated resource utilization profile. Active resources, whether in the frequency domain, time domain, or both, can indicate whether a user signal is being transported by a remote unit in the DAS. All of the narrowband signals having an estimated resource utilization profile at or above a predetermined threshold are assumed to carry traffic load and are marked as active. All of the narrowband signals having an estimated resource utilization profile lower than a predetermined threshold are assumed to carry only noise, so are marked as inactive. - In some aspects, the predetermined threshold for determining whether narrowband signals are active or inactive is based on the power profile of the noise floor measured at non-loaded traffic conditions when no traffic is being transmitted through the DAS (e.g., at the commissioning of the system). Alternatively, a RUM can measure narrowband signals which are not transporting traffic load at a given point in time. The noise floor calibration can be applied to the signal formats processed by the RUM of each remote unit. The noise floor is a reference for discriminating between "active" and "inactive" resources during a given time period. The start of the time period can be triggered when the first narrow band signal is detected as "active." The traffic activity can be measured as a percentage of resource usage versus the total available resources. In LTE and GSM, the frequency resources that are in use per remote unit can be determined over time and frequency. Using the specific frequency resources that are in use per remote unit over time and frequency can provide more precise measurement results than using a long-term power measurement because imperfections in power control for the user device may not affect the power measurement. Long-term power measurements can be available, for example, in UMTS embodiments.
- In UMTS, the composite power profile generated by active user devices in the cell can be estimated. The admission/congestion control procedure of the base transceiver station can be configured to ensure that a maximum received total wideband power ("RTWP") is not exceeded. For example, configuring the base transceiver station to ensure that a maximum RTWP is not exceeded can include limiting the maximum number of user devices attached to the cell. After determining values for the maximum RTWP level (e.g., defined by the base transceiver station at full load), the measured noise floor calibration level, and the measured power density (e.g., as rise over thermal noise power), the percentage of resource usage versus full load condition can be estimated.
- For LTE, the number of active user devices per time slot can be estimated by measuring the number of active physical resource blocks over the total number of physical resource blocks determined to be "active". Assuming a non-adjacent frequency allocation for the users, different groups of active physical resource blocks allocated to a specific user can be identified. The number of user devices per time slot can be computed by dividing the total number of "active" physical resource blocks by the number of identified physical resource block groups. A physical resource block can be a minimum resource assigned to a user.
- Once the traffic load on the remote units is detected, traffic load optimization policies can be applied by the base transceiver station. For example, the simulcast factor of the cells distributed through the DAS can be modified and more carrier frequencies can be allocated to remote units reporting high traffic load. By allocating more carrier frequencies to high-load remote units, the traffic load per carrier for a given remote unit can be reduced. A base transceiver station can allocate all resources to a user device if that user device is the only one communicating in the DAS. Rather than measuring the number of user devices directly, the system can measure the load and optimize accordingly.
-
FIG. 3 is a diagram illustrating a DAS suitable for detecting traffic load by monitoring narrowband signals. One or more DASremote units 300, labeledRU # 0 through RU #N, can communicate multi-carrier RF uplink signals. The uplink signals are decomposed into multiple narrowband complex signals (I/Q samples) usingfilter banks 302. Separate filter banks can be configured to decompose uplink signals having like signal formats. For example, LTE SC-FDMA uplink signals received by the remote unit can be decomposed by a multi-carrier LTE filter bank (e.g., LTEFilter Bank # 0 forRU # 0, LTE Filter Bank #N for DAS RU #N). UMTS uplink signals received by the remote unit can be decomposed by a multi-carrier UMTS filter bank (e.g., UMTSFilter Bank # 0 forRU # 0, UMTS Filter Bank #N for remote unit RU #N). GSM uplink signals received by the remote unit can be decomposed by a multi-carrier GSM filter bank (e.g., GSMFilter Bank # 0 forRU # 0, GSM Filter Bank #N for RU #N). - The process of decomposing multicarrier RF uplink signals into multiple narrowband complex signals can be applied to any uplink carrier format and frequency. In some aspects, each carrier signal can, alternatively, be processed by a filter bank having a narrowband filter grid designed for a specified carrier. In some aspects, the narrowband signals that are outputted by the filter bank(s) may not need to be grouped by format. For example, the narrowband signals used to determine a power profile can be ungrouped (e.g., one signal per power profile) or can be grouped based on other characteristics (e.g., grouped by carrier).
- The collection of I/Q samples generated by the
filter banks 302 can be sent to one ormore master units 304. In some aspects, each master unit,MU # 0 through MU #N, can include a resource utilization monitor ("RUM"),RUM # 0 through RUM #N, that is configured to receive, monitor (or process), and transmit the narrowband complex signals generated from the uplink signals. Specifically, a RUM is configured to receive the narrowband complex signals and determine a power profile for each of the narrowband complex signals. In some configurations, narrowband signals of the same carrier or carrier signal format can, alternatively, be processed together to determine the respective power profile for each carrier or format. The RUM is further configured to estimate time and frequency channel resource utilization information of the radio channel at the remote units. A resource utilization profile of the radio channel is determined based on the measured power profiles associated with the narrowband signals and the time and frequency for each carrier. The RUM determines a traffic load based on the resource utilization profile. This information can be fed into a multistage, aggregation, transport anddistribution block 306. At the output of the multistage, aggregation, transport anddistribution block 306, the signal carrying the information can be routed to theantenna ports 308 servicing the base transceiverstations BTS # 0 through BTS #N. - A RUM can be located anywhere in the DAS. For example, the functionality of the RUM can be integrated into a remote unit, a master unit, or an expansion unit. For example, as illustrated above, the RUM integrated into a master unit. The receiver and transmitter functions can, in some aspects, utilize the receiving and transmitting means of the unit into which it is integrated. In some aspects, the functionality of the RUM can be distributed throughout the DAS without departing from the scope of the subject matter described herein.
-
FIG. 4 is a functional block diagram of a RUM according to one example. TheRUM 400 can include areceiver 402 and aprocessor 404 to receive and process, respectively, narrowband signals (e.g., I/Q samples) generated from uplink signals. In some aspects, theprocessor 404 can process common signal formats (e.g., LTE, UMTS, GSM) together. Apower profile 406 can be determined for each grouping of I/Q samples. For example, theprocessor 404 can determine an LTE Power Profile 406a for the LTE narrowband signals received, a UMTS Power Profile 406b for the UMTS narrowband signals received, and aGSM Power Profile 406c for the GSM narrowband signals received. In some aspects, eachpower profile 406 can be stored in adatabase 408 in the RUM. Aresource utilization profile 410 is estimated for each remote unit based on the power profiles 406. A traffic load is determined from theresource utilization profile 410. The traffic load information is transmitted by atransmitter 414 to the base transceiver station of the DAS through the transport network as a part of control messaging. - Returning to
FIG. 3 to illustrate how aRUM 400 may operate within the DAS, resources utilizationmonitor RUM # 0 can process the narrowband I/Q samples generated from the uplink signals received from remoteunit RU # 0.RUM # 0 can estimate the resource utilization profile forRU # 0 based on a power profile of the narrowband I/Q samples from remoteunit RU # 0.RUM # 0 can determine a traffic load based on the estimated resource utilization profile and transmit the traffic load information to one or more of theBTS antenna ports 308. The traffic load information is transmitted to anantenna port 308 of a base transceiver station that can optimize the traffic load by reallocating resources within the DAS. - Resources for a given carrier can be assigned in the frequency and time domains. A
RUM 400 can determine apower profile 406 per sample time and in the time domain. TheRUM 400 can apply a different monitoring function topower profiles 406 related to different signal formats, depending on the time domain characteristics of the received signal frame. Power profiles 406 calculated at each sample time can be averaged over a time window that is equal to the time resolution in order to correspond to changes in the resource allocation applied to each specific carrier format. In some aspects, the frequency resolution of thepower profile 406 can be defined by the filter bank resolution. By calculatingpower profiles 406 at each sample time and averaging over a time window, thepower profile 406 of each carrier can be estimated in the either or both of the frequency and time domains. - For example, in GSM, a burst period can be defined to be 0.577 msec. A time division multiple access ("TDMA") frame includes eight burst periods. The GSM frequency-hopping rate corresponds to the TDMA framing. One TDMA frame can be 4.615 msec. The time resolution of the power profile can be at least equal to the GSM burst. For UMTS, the frame duration is 10 msec, but the shortest time transmit interval (TTI) for resource scheduling can be 2 msec. Time slot resolution of the power profile can be at least equal to the TTI duration for each UMTS carrier. For LTE, the physical resource block duration can be equal to a time slot of 0.5 msec. Time slot resolution of the power profile can be at least equal to the physical resource block duration for each LTE carrier.
- The foregoing description of the examples, including illustrated examples, of the invention has been presented only for the purpose of illustration and description and is not intended to be exhaustive or to limit the invention to the precise forms disclosed. The illustrative examples described above are given to introduce the reader to the general subject matter discussed here and are not intended to limit the scope of the disclosed concepts.
Claims (10)
- A method, comprising:decomposing, with one or more filter banks (302), a wideband uplink signal, received by one or more remote units (106, 108) of a distributed antenna system, into one or more narrowband signals (200), wherein each of the one or more filter banks (302) is uniquely coupled to a remote unit;determining a power profile for each of the one or more narrowband signals (202);estimating a resource utilization profile for each of the one or more narrowband signals for each of the one or more remote units based, at least in part, on the power profile for each of the one or more narrowband signals (204); anddetermining a traffic load at each of the one or more remote units based on the resource utilization profile (206), by:comparing the resource utilization profile for each of the one or more narrowband signals of a remote unit to a predetermined threshold that is based on a power profile of a noise floor for the remote unit measured when no traffic is transmitted;designating as active narrowband signals of the remote unit having the estimated resource utilization profile at or above the predetermined threshold; anddesignating as inactive narrowband signals of the remote unit having the estimated resource utilization profile below the predetermined threshold.
- The method of claim 1, further comprising:generating digital samples of the one or more narrowband signals; andfiltering the digital samples based on a signal format associated with the one or more narrowband signals.
- The method of claim 1, wherein determining the power profile for each of the one or more narrowband signals includes:sampling the one or more narrowband signals; anddetermining a square of a momentary power for the one or more narrowband signals at each sample time.
- The method of claim 1, wherein estimating the resource utilization profile for each of the one or more remote units (106, 108) comprises:storing the power profile for samples of each of the one or more narrowband signals in a database; andderiving a resource allocation map from the power profile for the samples for each of the one or more narrowband signals, frequency characteristics of the samples for each of the one or more narrowband signals, and a sample time of the samples for each of the one or more narrowband signals.
- The method of claim 1, further comprising optimizing the traffic load by:allocating greater frequency or time resources to each of the one or more remote units (106, 108) having the resource utilization profile at or above the predetermined threshold; andallocating fewer frequency or time resources to each of the one or more remote units having the resource utilization profile below the predetermined threshold.
- A distributed antenna system comprising:one or more remote units (106, 108, 300);one or more filter banks (302) configured for decomposing a widebank uplink signal into one or more narrowband signals, wherein each filter bank is uniquely communicatively coupled to a remote unit (106, 108) and further configured to communicatively couple the one or more narrowband signals to at least one base transceiver station; anda monitoring unit (400) comprising:a receiver (402) configured for receiving one or more narrowband signals generated from a wideband uplink signal received by at least one of the one or more remote units; anda processor (404), coupled to the receiver, configured for determining a power profile for each of the one or more narrowband signals (202),wherein the processor (404) is further configured for estimating a resource utilization profile for each of the one or more narrowband signals for each of the one or more remote units (204) based, at least in part, on the power profile for each of the one or more narrowband signals, andwherein the processor (404) is further configured for determining a traffic load at each of the one or more remote units based on the resource utilization profile (206) by:comparing the resource utilization profile for each of the one or more narrowband signals of a remote unit to a predetermined threshold that is based on a power profile of a noise floor for the remote unit measured when no traffic is transmitted;designating as active narrowband signals of the remote unit having the estimated resource utilization profile at or above the predetermined threshold; anddesignating as inactive narrowband signals of the remote unit having the estimated resource utilization profile below the predetermined threshold.
- The distributed antenna system of claim 6, wherein the monitoring unit further comprises a transmitter configured for transmitting information based on the traffic load at each of the one or more remote units (106, 108, 300) to a base transceiver station.
- The distributed antenna system of claim 6, further comprising a database (408) configured for storing the power profile for samples of each of the one or more narrowband signals, and
wherein the processor (404) is further configured to derive a resource allocation map, at least in part, from information stored in the database. - The distributed antenna system of claim 6, wherein the processor (404) is further configured to determine the power profile for each of the one or more narrowband signals by sampling the one or more narrowband signals and determining a square of a momentary power for the one or more narrowband signals at each sample time.
- The distributed antenna system of claim 6, wherein the monitoring unit (400) further comprises a transmitter (414) configured to transmit traffic load information to a base transceiver station configured to optimize the traffic load based, at least in part, on the traffic load information, the traffic load information being measured as a percentage of resource usage to at least one of the one or more remote units (106, 108, 300) versus a total of available resources to the at least one of the one or more remote units.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US201461980728P | 2014-04-17 | 2014-04-17 | |
PCT/US2015/025771 WO2015160821A1 (en) | 2014-04-17 | 2015-04-14 | Detecting traffic load for a telecommunications system using narrowband signal monitoring |
Publications (3)
Publication Number | Publication Date |
---|---|
EP3132550A1 EP3132550A1 (en) | 2017-02-22 |
EP3132550A4 EP3132550A4 (en) | 2017-11-22 |
EP3132550B1 true EP3132550B1 (en) | 2022-06-08 |
Family
ID=54324498
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP15780462.6A Active EP3132550B1 (en) | 2014-04-17 | 2015-04-14 | Detecting traffic load for a telecommunications system using narrowband signal monitoring |
Country Status (4)
Country | Link |
---|---|
US (1) | US11291010B2 (en) |
EP (1) | EP3132550B1 (en) |
AU (1) | AU2015247794B2 (en) |
WO (1) | WO2015160821A1 (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US9794155B2 (en) * | 2014-12-19 | 2017-10-17 | Tube Incorporated | System and method for coordinating client-side inference of mobile network loading and capacity |
US10251121B2 (en) * | 2016-09-30 | 2019-04-02 | Intel IP Corporation | Apparatus, system and method of detecting one or more active wireless communication channels |
EP3949581A1 (en) * | 2019-04-02 | 2022-02-09 | FRAUNHOFER-GESELLSCHAFT zur Förderung der angewandten Forschung e.V. | Transceivers and methods for operating the same |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP3243085A1 (en) * | 2015-01-09 | 2017-11-15 | CommScope Technologies LLC | System and method for location of mobile devices in confined environments |
Family Cites Families (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1126734B1 (en) * | 2000-02-15 | 2004-12-01 | Lucent Technologies Inc. | Method and mobile radio telecommunication system with improved uplink resource allocation |
US8670390B2 (en) * | 2000-11-22 | 2014-03-11 | Genghiscomm Holdings, LLC | Cooperative beam-forming in wireless networks |
US6996197B2 (en) * | 2003-09-17 | 2006-02-07 | Motorola, Inc. | Method and apparatus for reducing interference within a communication system |
US7463871B2 (en) * | 2005-12-09 | 2008-12-09 | Broadcom Corporation | Processing received digital data signals based on a received digital data format |
CN101536496B (en) * | 2006-11-01 | 2011-11-09 | 汤姆森特许公司 | A co-channel interference remover |
DE112008001994T5 (en) * | 2007-08-08 | 2010-06-10 | Advantest Corp. | Meter and program |
FI20085375A0 (en) | 2008-04-25 | 2008-04-25 | Nokia Siemens Networks Oy | Distributed antenna system in a telecommunications network |
US8244268B2 (en) * | 2009-09-30 | 2012-08-14 | The United States Of America As Represented By The Secretary Of The Navy | System and method for communicating with a plurality of remote communication units |
US9401784B2 (en) * | 2009-10-21 | 2016-07-26 | Qualcomm Incorporated | Time and frequency acquisition and tracking for OFDMA wireless systems |
EP2583503B1 (en) * | 2010-06-16 | 2014-06-18 | Nokia Solutions and Networks Oy | Power saving procedure in communication network |
US8842909B2 (en) * | 2011-06-30 | 2014-09-23 | Qualcomm Incorporated | Efficient blending methods for AR applications |
US9179363B2 (en) * | 2011-08-12 | 2015-11-03 | Telefonaktiebolaget Lm Ericsson (Publ) | Systems and methods for determining a coupling characteristic in a radio communications network |
US8254848B1 (en) * | 2011-12-09 | 2012-08-28 | At&T Intellectual Property I, Lp | Monitoring system for distributed antenna systems |
US9256983B2 (en) * | 2012-06-28 | 2016-02-09 | Here Global B.V. | On demand image overlay |
US9306682B2 (en) * | 2012-07-20 | 2016-04-05 | Commscope Technologies Llc | Systems and methods for a self-optimizing distributed antenna system |
US10506454B2 (en) | 2012-07-31 | 2019-12-10 | Dali Systems Co., Ltd. | Optimization of traffic load in a distributed antenna system |
-
2015
- 2015-04-14 EP EP15780462.6A patent/EP3132550B1/en active Active
- 2015-04-14 US US15/304,047 patent/US11291010B2/en active Active
- 2015-04-14 WO PCT/US2015/025771 patent/WO2015160821A1/en active Application Filing
- 2015-04-14 AU AU2015247794A patent/AU2015247794B2/en active Active
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP3243085A1 (en) * | 2015-01-09 | 2017-11-15 | CommScope Technologies LLC | System and method for location of mobile devices in confined environments |
Non-Patent Citations (1)
Title |
---|
SEYED AMIN HEJAZI ET AL: "Traffic Monitoring in a LTE Distributed Antenna System", 1 May 2013 (2013-05-01), XP055280101, Retrieved from the Internet <URL:http://www.cyberjournals.com/Papers/May2013/03.pdf> [retrieved on 20160613] * |
Also Published As
Publication number | Publication date |
---|---|
US11291010B2 (en) | 2022-03-29 |
EP3132550A1 (en) | 2017-02-22 |
AU2015247794B2 (en) | 2019-02-28 |
AU2015247794A1 (en) | 2016-10-27 |
US20170041936A1 (en) | 2017-02-09 |
WO2015160821A1 (en) | 2015-10-22 |
EP3132550A4 (en) | 2017-11-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US10938450B2 (en) | Base station router for distributed antenna systems | |
CN106465149B (en) | Wireless spectrum monitoring and analysis system and method | |
Ghassemi et al. | Cognitive radio for smart grid communications | |
CN101036313B (en) | Power line communication methods and devices | |
CN1943263B (en) | Dynamic allocation of radio resources | |
US8630636B2 (en) | Radio base station and radio communication method | |
CN104885547B (en) | Multi channel Multiple Access scheme for the network with finite link budget | |
CN110383905A (en) | The Poewr control method of uplink transmission | |
US20110201277A1 (en) | Radio communication system, radio base station, and radio communication method | |
EP2628338B1 (en) | Method and apparatus for selecting cell to increase transmission capacity in wireless communication system | |
JP5650326B2 (en) | Radio frequency detection method, radio frequency detection device, and radio frequency detection system | |
CN101409931B (en) | Combined communications system, prohibiting-signal transmitting apparatus, wireless base station, and method | |
EP3108598B1 (en) | Optimizing network resources in a telecommunications system | |
WO2009049535A1 (en) | Method and device for allocating wireless resource in wireless communication system | |
US8488568B2 (en) | Method and system of interferer signal detection | |
US20150163008A1 (en) | Method and apparatus for cell discovery | |
EP3011773B1 (en) | Method and apparatus in a base station for controlling communication resources to a plurality of antenna sites of the base station | |
KR20120048863A (en) | Apparatus and method for cluster based opportunistic power control in wireless communicatoin system | |
EP3132550B1 (en) | Detecting traffic load for a telecommunications system using narrowband signal monitoring | |
CN103155627A (en) | A wireless station, an interference estimation method, a wireless communication system and a computer program | |
EP3087684A1 (en) | Systems and methods for capacity management for a distributed antenna system | |
CN103416099A (en) | A radio base station and a method therein for scheduling radio resources | |
KR20130091511A (en) | Apparatus and method for controlling power to mitigate interference in wierelss communication system | |
CN101803421A (en) | Improved uplink scheduling in a cellular system | |
CN102415167B (en) | The method of allocation of downlink through-put power and corresponding device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE INTERNATIONAL PUBLICATION HAS BEEN MADE |
|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE |
|
17P | Request for examination filed |
Effective date: 20161011 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
AX | Request for extension of the european patent |
Extension state: BA ME |
|
DAV | Request for validation of the european patent (deleted) | ||
DAX | Request for extension of the european patent (deleted) | ||
A4 | Supplementary search report drawn up and despatched |
Effective date: 20171025 |
|
RIC1 | Information provided on ipc code assigned before grant |
Ipc: H04B 17/20 20150101AFI20171019BHEP Ipc: H04B 17/382 20150101ALI20171019BHEP Ipc: H04B 17/318 20150101ALI20171019BHEP Ipc: H04W 24/08 20090101ALI20171019BHEP Ipc: H04W 72/04 20090101ALI20171019BHEP |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: EXAMINATION IS IN PROGRESS |
|
17Q | First examination report despatched |
Effective date: 20181207 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: EXAMINATION IS IN PROGRESS |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: EXAMINATION IS IN PROGRESS |
|
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: GRANT OF PATENT IS INTENDED |
|
INTG | Intention to grant announced |
Effective date: 20211213 |
|
GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE PATENT HAS BEEN GRANTED |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR |
|
REG | Reference to a national code |
Ref country code: GB Ref legal event code: FG4D |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: REF Ref document number: 1497646 Country of ref document: AT Kind code of ref document: T Effective date: 20220615 Ref country code: CH Ref legal event code: EP |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R096 Ref document number: 602015079364 Country of ref document: DE |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: FG4D |
|
REG | Reference to a national code |
Ref country code: LT Ref legal event code: MG9D |
|
REG | Reference to a national code |
Ref country code: NL Ref legal event code: MP Effective date: 20220608 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220608 Ref country code: NO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220908 Ref country code: LT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220608 Ref country code: HR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220608 Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220909 Ref country code: FI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220608 Ref country code: ES Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220608 Ref country code: BG Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220908 |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: MK05 Ref document number: 1497646 Country of ref document: AT Kind code of ref document: T Effective date: 20220608 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: RS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220608 Ref country code: LV Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220608 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220608 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SM Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220608 Ref country code: SK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220608 Ref country code: RO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220608 Ref country code: PT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20221010 Ref country code: EE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220608 Ref country code: CZ Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220608 Ref country code: AT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220608 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: PL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220608 Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20221008 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R097 Ref document number: 602015079364 Country of ref document: DE |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: AL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220608 |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220608 |
|
26N | No opposition filed |
Effective date: 20230310 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220608 |
|
P01 | Opt-out of the competence of the unified patent court (upc) registered |
Effective date: 20230530 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: DE Payment date: 20230427 Year of fee payment: 9 |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
GBPC | Gb: european patent ceased through non-payment of renewal fee |
Effective date: 20230414 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LU Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20230414 |
|
REG | Reference to a national code |
Ref country code: BE Ref legal event code: MM Effective date: 20230430 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MC Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220608 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GB Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20230414 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MC Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220608 Ref country code: LI Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20230430 Ref country code: IT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20220608 Ref country code: GB Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20230414 Ref country code: FR Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20230430 Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20230430 |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: MM4A |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: BE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20230430 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20230414 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20230414 |