EP3000944B1 - A material handling machine - Google Patents

A material handling machine Download PDF

Info

Publication number
EP3000944B1
EP3000944B1 EP15170945.8A EP15170945A EP3000944B1 EP 3000944 B1 EP3000944 B1 EP 3000944B1 EP 15170945 A EP15170945 A EP 15170945A EP 3000944 B1 EP3000944 B1 EP 3000944B1
Authority
EP
European Patent Office
Prior art keywords
region
material handling
implement
bucket
control system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
EP15170945.8A
Other languages
German (de)
French (fr)
Other versions
EP3000944A1 (en
EP3000944C0 (en
Inventor
Lee HARPER
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JC Bamford Excavators Ltd
Original Assignee
JC Bamford Excavators Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JC Bamford Excavators Ltd filed Critical JC Bamford Excavators Ltd
Publication of EP3000944A1 publication Critical patent/EP3000944A1/en
Application granted granted Critical
Publication of EP3000944B1 publication Critical patent/EP3000944B1/en
Publication of EP3000944C0 publication Critical patent/EP3000944C0/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/28Dredgers; Soil-shifting machines mechanically-driven with digging tools mounted on a dipper- or bucket-arm, i.e. there is either one arm or a pair of arms, e.g. dippers, buckets
    • E02F3/36Component parts
    • E02F3/42Drives for dippers, buckets, dipper-arms or bucket-arms
    • E02F3/43Control of dipper or bucket position; Control of sequence of drive operations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/28Dredgers; Soil-shifting machines mechanically-driven with digging tools mounted on a dipper- or bucket-arm, i.e. there is either one arm or a pair of arms, e.g. dippers, buckets
    • E02F3/36Component parts
    • E02F3/42Drives for dippers, buckets, dipper-arms or bucket-arms
    • E02F3/43Control of dipper or bucket position; Control of sequence of drive operations
    • E02F3/435Control of dipper or bucket position; Control of sequence of drive operations for dipper-arms, backhoes or the like
    • E02F3/439Automatic repositioning of the implement, e.g. automatic dumping, auto-return
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/28Dredgers; Soil-shifting machines mechanically-driven with digging tools mounted on a dipper- or bucket-arm, i.e. there is either one arm or a pair of arms, e.g. dippers, buckets
    • E02F3/36Component parts
    • E02F3/42Drives for dippers, buckets, dipper-arms or bucket-arms
    • E02F3/43Control of dipper or bucket position; Control of sequence of drive operations
    • E02F3/431Control of dipper or bucket position; Control of sequence of drive operations for bucket-arms, front-end loaders, dumpers or the like
    • E02F3/434Control of dipper or bucket position; Control of sequence of drive operations for bucket-arms, front-end loaders, dumpers or the like providing automatic sequences of movements, e.g. automatic dumping or loading, automatic return-to-dig
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/28Dredgers; Soil-shifting machines mechanically-driven with digging tools mounted on a dipper- or bucket-arm, i.e. there is either one arm or a pair of arms, e.g. dippers, buckets
    • E02F3/36Component parts
    • E02F3/42Drives for dippers, buckets, dipper-arms or bucket-arms
    • E02F3/43Control of dipper or bucket position; Control of sequence of drive operations
    • E02F3/435Control of dipper or bucket position; Control of sequence of drive operations for dipper-arms, backhoes or the like
    • E02F3/437Control of dipper or bucket position; Control of sequence of drive operations for dipper-arms, backhoes or the like providing automatic sequences of movements, e.g. linear excavation, keeping dipper angle constant
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/28Dredgers; Soil-shifting machines mechanically-driven with digging tools mounted on a dipper- or bucket-arm, i.e. there is either one arm or a pair of arms, e.g. dippers, buckets
    • E02F3/36Component parts
    • E02F3/42Drives for dippers, buckets, dipper-arms or bucket-arms
    • E02F3/43Control of dipper or bucket position; Control of sequence of drive operations
    • E02F3/435Control of dipper or bucket position; Control of sequence of drive operations for dipper-arms, backhoes or the like
    • E02F3/438Memorising movements for repetition, e.g. play-back capability
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/20Drives; Control devices
    • E02F9/2025Particular purposes of control systems not otherwise provided for
    • E02F9/2029Controlling the position of implements in function of its load, e.g. modifying the attitude of implements in accordance to vehicle speed
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/20Drives; Control devices
    • E02F9/2025Particular purposes of control systems not otherwise provided for
    • E02F9/2041Automatic repositioning of implements, i.e. memorising determined positions of the implement

Definitions

  • the present invention relates to a material handling machine.
  • Known material handling machines such as excavators have a material handling arm assembly.
  • the arm assembly may have an arm, known as a boom, pivotally mounted about a generally horizontal axis relative to a chassis of the machine.
  • a further arm known as a dipper, may be attached to an end of the boom remote from the chassis and may be pivotable about a generally horizontal axis.
  • a material handling implement such as a bucket may be pivotably mounted on an end of the dipper.
  • the boom may be raised and lowered by operation of a first hydraulic ram.
  • the dipper may be moveable relative to the boom by operation of a second hydraulic ram, the bucket may be moveable relative to the dipper by operation of a third hydraulic ram.
  • a skilful operator In order to handle material, for example dig a trench, a machine operator must simultaneously operate all three hydraulic actuators and this is a skilful process.
  • a skilful operator when digging a trench, will quickly be able to fill the bucket with material, lift bucket out of the trench and empty the bucket to one or other side of the vehicle.
  • This excavation cycle time or loading cycle time is markedly affected by the initial penetration of the bucket into the ground. If the bucket penetrates too far into the ground then the bucket cannot be drawn through the ground to be filled. Conversely if the bucket does not penetrate far enough into the ground, then the bucket only half fills. Less well trained operators tend to operate at lower excavation/ loading cycle times.
  • a method of operating a material handling machine having a material handling implement moveable relative to a chassis of the machine including the steps of
  • the first region may be a region where it is desired to dig a trench.
  • the second region may be a region where it desired to deposit spoil from the trench.
  • step a) positions the implement in the first region, for example in the region where it is desired to dig a trench but step c) positions the material handling implement at a different position in the first region than step a).
  • the control system automatically positions the material handing implement at an incrementally different position in the trench, thereby assisting digging of the trench as it is incrementally extended.
  • the material handling implement is automatically placed directly at the next sequential position in the trench as the length of the trench is progressively extended.
  • the different positions in the trench to which the material handling implement is directly positioned as the trench is incrementally extended may successively progress towards the machine or away from the machine.
  • the direct positioning of the material handling implement to the required position within the trench i.e. the material handling implement is not moved via a previous digging position) saves time and facilitates more efficient digging.
  • a material handling machine 10 including a chassis 12 and an operator cab 14.
  • the operator cab is mounted on the chassis 12.
  • Ground engaging transport means in the form of a pair of tracks 16 are provided on the chassis to move the machine over the ground.
  • Attached to a frame of the cab 14 is an arm assembly 18, the arm assembly includes a first arm in the form of a boom 20, a second arm in the form of a dipper 22 and a ground engaging implement in the form of a bucket 24.
  • the boom 20 is pivotally mounted by pivot 26 to link 12A at a first end 20A of the boom.
  • Link 12A is pivotally mounted at a generally vertical axis relative to the frame.
  • Pivot 26 is orientated horizontally.
  • the dipper is pivotally mounted via pivot 28 to a second end 20B of the boom 20.
  • Pivot 28 is orientated horizontally.
  • the bucket is pivotally mounted via pivot 30 to an end 22B of dipper 22 remote from end 22A of dipper 22. Pivot 30 is orientated horizontally.
  • a first hydraulic actuator in the form of a first hydraulic ram 32 has a first end 32A pivotally attached to the frame and a second end 32B pivotally attached to the boom part way between the first and second ends of the boom.
  • a second hydraulic actuator in the form of a second hydraulic ram 34 has a first end 34A pivotally attached to the boom part way between the first and second ends of the boom and a second end 34B pivotally attached to the dipper proximate the first end 22A of the dipper.
  • a third hydraulic actuator in the form of a third hydraulic ram 36 has a first end 36A pivotally attached to the dipper proximate the first end 22A of the dipper and a second end 36B pivotally attached to a linkage mechanism 38 proximate the second end of the dipper.
  • the linkage mechanism 38 per se is known and simply converts extension and retraction movement of the third hydraulic ram 36 into rotary movement of the bucket 24 about pivot 30.
  • Extension of the first hydraulic ram causes the boom to raise, and contraction of the first hydraulic ram causes lowering of the boom.
  • Extension of the second ram causes the dipper to pivot in a clockwise direction (when viewing figure 1 ) about pivot 28, i.e. causes the boom to move in a "dipper in” direction, and retraction of the second hydraulic ram 34 causes the dipper to move in an anticlockwise direction when viewing figure 1 about pivot 28, i.e. in a "dipper out” direction.
  • Extension of the third hydraulic ram 36 causes the bucket 24 to move in a clockwise direction about pivot 30, i.e. in a "crowd” direction, and retraction of the third hydraulic ram 36 causes the bucket to move in an anticlockwise direction about pivot 30, i.e. in a "dump" direction.
  • the first, second and third hydraulic rams are all double acting hydraulic rams.
  • Double acting hydraulic rams are known per se. They include a piston within a cylinder. The piston is attached to a rod which extends beyond the end of the cylinder. The end of the rod remote from the piston defines one end of the hydraulic ram. The end of the cylinder remote from the rod defines an opposite end of hydraulic ram.
  • a "head side chamber” is defined between the piston and the end of the cylinder remote from the rod.
  • a “rod side chamber” is defined between the piston and the end of the cylinder proximate the end of the rod. Pressurisation of the head side pressure chamber extends the ram and pressurisation of the rod side chamber causes the ram to retract.
  • the machine includes a system for operating the first, second and third hydraulic rams, as described below.
  • a hydraulic pump (not shown) is driven by a prime mover.
  • Prime mover may be an internal combustion engine, though other prime movers are suitable.
  • a boom spool valve (not shown) can be operated by an operator manipulating boom control (not shown) to extend or retract hydraulic ram 32.
  • a dipper spool valve (not shown) can be controlled via a dipper control (not shown) to extend or retract hydraulic ram 34.
  • a bucket spool valve (not shown) can be controlled by a bucket control (not shown) to extend or retract hydraulic ram 36.
  • the operator can manually manipulate the boom control, dipper control and bucket control in order to manoeuvre and handle material.
  • the material handling machine also includes a control system 52.
  • the control system 52 can be selectively enabled or disabled at the option of the operator. In order to enable the control system 52 the operator actuates a switch, button or other operator input device (not shown). In order to disable the control system 52 the operator actuates the button, switch or other operator input device.
  • the operator can manually manipulate the boom control, dipper control and bucket control, as described above, in order to manoeuvre and handle material.
  • the control system 52 allows a pre-programmed sequence of manoeuvres to be carried out automatically.
  • control system 52 controls movement of the boom, dipper and bucket in a pre-programmed sequence of manoeuvres.
  • sequence of movements of the arm assembly is as follows:
  • the control system 52 lowers the boom and the dipper is moved in a "dipper out” direction thereby moving the bucket teeth 25 of the bucket 24 away from the chassis 12.
  • the boom is then further lowered such that the bucket teeth 25 engage the ground.
  • the bucket is then crowded slightly so as to start to move the bucket teeth through the ground.
  • the dipper, boom and bucket are then simultaneously operated by the control system 52 to progressively move the dipper in a "dipper in” direction and to move the boom in a "boom raised” direction and to move the bucket in a "crowd” direction such that the bucket teeth move generally towards the chassis to fill the bucket with ground material.
  • the boom is raised, the arm assembly is swung laterally relative to the machine and the ground material is then dumped by moving the bucket to a dumped position.
  • the sequence is then generally repeated. However, as the bucket is returned to the trench it is not positioned in the same position as when the first bucket load of ground material was removed, rather it is positioned at an incrementally different position ready to take the second bucket load of ground material.
  • the cutting edge 24B of the bucket in order to dig the trench the cutting edge 24B of the bucket must first be positioned on the ground surface G at point 101.
  • the control system then moves the boom, dipper and bucket so as to draw the leading edge 24B to point 102.
  • the control system then crowds the bucket to draw the cutting edge 24B to point 103 following which the boom is raised to move the bucket out of the ground. This results in the removal of portion A of the ground shown cross-hatched in figure 3 .
  • the frame is then swung clockwise relative to the chassis (when viewing figure 2 ) so as to move the bucket towards a second region 60, where it is intended to dump the spoil from the trench.
  • the bucket 24 is then "dumped” thereby depositing spoil A on the ground at region 60.
  • the frame is then swung anticlockwise and the cutting edge 24B is returned to the trench.
  • the leading edge 24B of the bucket 24 needs to be positioned at position 102 by the control system rather than at position 101.
  • the cutting edge is positioned at position 102, moved to position 104 and then moved to position 105 in order to collect ground material B shown cross-hatched in figure 3 .
  • the boom is then raised to lift the bucket out of the ground, the frame is swung clockwise and the spoil B is deposited at the second region 60 thereby forming a spoil pile.
  • the cutting edge is initially positioned at position 104 by the control system and then moved to position 106 and 107.
  • the cutting edge is positioned at position 106 by the control system and then moved to position 108 and 109.
  • the fifth bucket load is positioned at position 108 by the control system and then moved to position 110 and then 111.
  • the sixth bucket load is positioned at position 110 by the control system and then moved to position 112 and 113.
  • the desired position of the trench represents a first region 59 (see figure 2 ).
  • the spoil pile of the trench represents second region 60 (see figure 2 ).
  • the invention provides for moving the material handling implement (in this example the bucket 24) repeatedly between the first and second regions. However, the implement is not moved to the same position when at the first region, rather it is moved automatically to an incrementally different position of the first region. In this way a trench or the like can progressively be dug.
  • the movement of the boom, dipper and bucket alone may be sufficient to dig the short trench, in other words it may not be necessary to move the vehicle via tracks 16.
  • the first part of the trench may be dug (for example by removing ground material A, B and C whilst the chassis is positioned at position 1 of figure 1 .
  • the chassis In order to remove ground material D, E and F it may be necessary to move the chassis to position 2 as shown in figure 2 .
  • the bucket nevertheless returns to the first region, i.e. returns to the trench in order to remove ground material D, E and F.
  • the system allows automatic digging of a trench or the like, and as such there is no need for an operator to be physically present in the machine, rather the operator can be remote from the machine. This is particularly advantageous in dangerous environments where the operator can be remote from the machine in a safe location.
  • the operator When in a remote location, the operator need not control all aspects of the machine. In one example all that the operator needs to define is the first position of the first region and the second region. Once this has been done the control system can automatically cause a sequence of predefined movements to occur thereby handling material in a desired manner, for example digging a trench or a hole at the first region and depositing the spoil at the second region.
  • only certain steps may be controlled by the controller.
  • the step of returning the material handling implement to the first region by positioning it at a second position of the first region different to the first position of the first region be carried out automatically.
  • This enables the implement to be quickly returned to an appropriate position (for example in a trench) different from the previous position of implement (for example in the trench).
  • the control system therefore can quickly return the implement to an incrementally different position.
  • This then enables the operator to control movement of the implement, for example to handle material, until such time as it is required to return the implement to another incrementally different position. This is advantageous when the material being handled is not uniform, for example where the ground includes occasional large rocks or other such material.
  • the first three bucket loads may contain loose material such as soil. Pickling up of this soil requires a particular implement manoeuvre. However, a fourth load may require the digging up of a rock or the like which will require a slightly different implement manoeuvre. The operator will be able to determine the required implement manoeuvre required to pick-up the soil or rock, as appropriate, but nevertheless once the earth/rock has been deposited on the spoil heap, the machine can nevertheless return the implement to an appropriate incrementally different position ready for a further material handling implement manoeuvre to pick-up further soil or a further rock as appropriate and as will be seen by the operator.
  • the leading edge 24B of the bucket starts at position 101.
  • positions 102, 104, 106, 108 and 110 are positioned at positions 102, 104, 106, 108 and 110.
  • These incrementally different starting positions generally progress towards the machine.
  • the incrementally different positions need not progress towards the machine, rather they can progress in any direction.
  • certain of the incrementally different position may be directly below a previous position.
  • the control system may be pre-programmed at the manufacturing factory with a sequence of manoeuvres to be carried out.
  • the control system may be pre-programmed in the field.
  • the control system may be pre-programmed in the field by recording a sequence of material handling manoeuvres and then arranging for those manoeuvres to be repeated with an offset. For example, an alternative way of digging the trench of figure 3 is with the control system disabled, the operator removes soil A and B.
  • sequence of recorded manoeuvres becomes the pre-programmed sequence of manoeuvres in order to remove soil E and F except with an offset.
  • sequence of manoeuvres used to remove soil D and E are repeated to remove soil E and F except they are repeated with an offset according to the distance between position 104 and 108.
  • additional sensors can be provided to provide a feedback loop for the positional control of the implement.
  • no sensors or the like are required and accordingly no positional feedback loop.
  • Such an arrangement is therefore relatively inexpensive (since no feedback sensors are required) and is relatively easy to maintain (since there are no sensors which require maintenance.
  • the material handling machine is an excavator.
  • the present invention is not limited to excavators and other material handling machines could be used, for example a back hoe loader, a telescopic handler, a fork lift truck etc.
  • the implement used is a bucket.
  • the step of positioning the material handling implement in a first position of a first region and the step of returning the material handling implement to the first region by positioning it at a second position of the first region different to the first position of the first region are carried out with the machine stationary, either with the machine stationary in the same position, or with the machine stationary in different positions. In further embodiments it is impossible to carry out one or both of these steps whilst the machine is in motion, i.e. whilst the machine is travelling over the ground.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Operation Control Of Excavators (AREA)
  • Replacement Of Web Rolls (AREA)

Description

  • The present invention relates to a material handling machine.
  • Known material handling machines such as excavators have a material handling arm assembly. The arm assembly may have an arm, known as a boom, pivotally mounted about a generally horizontal axis relative to a chassis of the machine. A further arm, known as a dipper, may be attached to an end of the boom remote from the chassis and may be pivotable about a generally horizontal axis. A material handling implement such as a bucket may be pivotably mounted on an end of the dipper. The boom may be raised and lowered by operation of a first hydraulic ram. The dipper may be moveable relative to the boom by operation of a second hydraulic ram, the bucket may be moveable relative to the dipper by operation of a third hydraulic ram.
  • In order to handle material, for example dig a trench, a machine operator must simultaneously operate all three hydraulic actuators and this is a skilful process. A skilful operator, when digging a trench, will quickly be able to fill the bucket with material, lift bucket out of the trench and empty the bucket to one or other side of the vehicle. This excavation cycle time or loading cycle time is markedly affected by the initial penetration of the bucket into the ground. If the bucket penetrates too far into the ground then the bucket cannot be drawn through the ground to be filled. Conversely if the bucket does not penetrate far enough into the ground, then the bucket only half fills. Less well trained operators tend to operate at lower excavation/ loading cycle times.
  • Examples of material handling machines having control systems for controlling the arm assembly are described in US5446980A , US2004/267404 A1 and WO 97/46769 A1 .
  • Accordingly, there is a need for an improved material handling machine.
  • Thus, according to the present invention there is provided a method of operating a material handling machine having a material handling implement moveable relative to a chassis of the machine, the method including the steps of
    1. a) manually positioning the material handling implement in a first position of a first region of a trench, the first region being a region where it is desired to manually dig the trench,
    2. b) manually moving the material handling implement to a second region, the second region being a region where it is desired to deposit spoil,
    3. c) providing a control system and enabling the control system to automatically return the material handling implement to the first region by directly positioning the material handling implement at a second position of the first region, the second position being a next sequential position where it is desired to manually dig the trench,
    4. d) manually returning the material handling implement to the second region.
  • The first region may be a region where it is desired to dig a trench. The second region may be a region where it desired to deposit spoil from the trench. Advantageously step a) positions the implement in the first region, for example in the region where it is desired to dig a trench but step c) positions the material handling implement at a different position in the first region than step a). Advantageously the control system automatically positions the material handing implement at an incrementally different position in the trench, thereby assisting digging of the trench as it is incrementally extended. The material handling implement is automatically placed directly at the next sequential position in the trench as the length of the trench is progressively extended. The different positions in the trench to which the material handling implement is directly positioned as the trench is incrementally extended may successively progress towards the machine or away from the machine. The direct positioning of the material handling implement to the required position within the trench (i.e. the material handling implement is not moved via a previous digging position) saves time and facilitates more efficient digging.
  • The invention will now be described, by way of example only, with reference to the accompanying drawings in which:-
    • Figure 1 is a schematic side view of a material handling machine according to the present invention,
    • Figure 2 is a schematic plan view of part of the material handling machine of figure 1, and
    • Figure 3 is a schematic side cross-section view of a trench dug by the machine of figure 1 according to the method of the present invention.
  • With reference to figures 1 and 2 there is shown a material handling machine 10 including a chassis 12 and an operator cab 14. The operator cab is mounted on the chassis 12. Ground engaging transport means in the form of a pair of tracks 16 are provided on the chassis to move the machine over the ground.
  • Attached to a frame of the cab 14 is an arm assembly 18, the arm assembly includes a first arm in the form of a boom 20, a second arm in the form of a dipper 22 and a ground engaging implement in the form of a bucket 24. The boom 20 is pivotally mounted by pivot 26 to link 12A at a first end 20A of the boom. Link 12A is pivotally mounted at a generally vertical axis relative to the frame. Pivot 26 is orientated horizontally. The dipper is pivotally mounted via pivot 28 to a second end 20B of the boom 20. Pivot 28 is orientated horizontally. The bucket is pivotally mounted via pivot 30 to an end 22B of dipper 22 remote from end 22A of dipper 22. Pivot 30 is orientated horizontally.
  • A first hydraulic actuator in the form of a first hydraulic ram 32 has a first end 32A pivotally attached to the frame and a second end 32B pivotally attached to the boom part way between the first and second ends of the boom. A second hydraulic actuator in the form of a second hydraulic ram 34 has a first end 34A pivotally attached to the boom part way between the first and second ends of the boom and a second end 34B pivotally attached to the dipper proximate the first end 22A of the dipper. A third hydraulic actuator in the form of a third hydraulic ram 36 has a first end 36A pivotally attached to the dipper proximate the first end 22A of the dipper and a second end 36B pivotally attached to a linkage mechanism 38 proximate the second end of the dipper. The linkage mechanism 38 per se is known and simply converts extension and retraction movement of the third hydraulic ram 36 into rotary movement of the bucket 24 about pivot 30.
  • Extension of the first hydraulic ram causes the boom to raise, and contraction of the first hydraulic ram causes lowering of the boom. Extension of the second ram causes the dipper to pivot in a clockwise direction (when viewing figure 1) about pivot 28, i.e. causes the boom to move in a "dipper in" direction, and retraction of the second hydraulic ram 34 causes the dipper to move in an anticlockwise direction when viewing figure 1 about pivot 28, i.e. in a "dipper out" direction. Extension of the third hydraulic ram 36 causes the bucket 24 to move in a clockwise direction about pivot 30, i.e. in a "crowd" direction, and retraction of the third hydraulic ram 36 causes the bucket to move in an anticlockwise direction about pivot 30, i.e. in a "dump" direction.
  • The first, second and third hydraulic rams are all double acting hydraulic rams. Double acting hydraulic rams are known per se. They include a piston within a cylinder. The piston is attached to a rod which extends beyond the end of the cylinder. The end of the rod remote from the piston defines one end of the hydraulic ram. The end of the cylinder remote from the rod defines an opposite end of hydraulic ram. A "head side chamber" is defined between the piston and the end of the cylinder remote from the rod. A "rod side chamber" is defined between the piston and the end of the cylinder proximate the end of the rod. Pressurisation of the head side pressure chamber extends the ram and pressurisation of the rod side chamber causes the ram to retract.
  • The machine includes a system for operating the first, second and third hydraulic rams, as described below.
  • A hydraulic pump (not shown) is driven by a prime mover. Prime mover may be an internal combustion engine, though other prime movers are suitable. A boom spool valve (not shown) can be operated by an operator manipulating boom control (not shown) to extend or retract hydraulic ram 32. A dipper spool valve (not shown) can be controlled via a dipper control (not shown) to extend or retract hydraulic ram 34. A bucket spool valve (not shown) can be controlled by a bucket control (not shown) to extend or retract hydraulic ram 36. Thus, the operator can manually manipulate the boom control, dipper control and bucket control in order to manoeuvre and handle material.
  • The material handling machine also includes a control system 52.
  • The control system 52 can be selectively enabled or disabled at the option of the operator. In order to enable the control system 52 the operator actuates a switch, button or other operator input device (not shown). In order to disable the control system 52 the operator actuates the button, switch or other operator input device.
  • When the control system is disabled, the operator can manually manipulate the boom control, dipper control and bucket control, as described above, in order to manoeuvre and handle material.
  • With the control system enabled, operation is as follows:-
  • The control system 52 allows a pre-programmed sequence of manoeuvres to be carried out automatically.
  • Thus, by way of example when it is required to dig a trench the operator enables the control system 52. The control system 52 then controls movement of the boom, dipper and bucket in a pre-programmed sequence of manoeuvres. In a typical sequence of movements of the arm assembly is as follows:-
  • Firstly, the control system 52 lowers the boom and the dipper is moved in a "dipper out" direction thereby moving the bucket teeth 25 of the bucket 24 away from the chassis 12. The boom is then further lowered such that the bucket teeth 25 engage the ground. The bucket is then crowded slightly so as to start to move the bucket teeth through the ground. The dipper, boom and bucket are then simultaneously operated by the control system 52 to progressively move the dipper in a "dipper in" direction and to move the boom in a "boom raised" direction and to move the bucket in a "crowd" direction such that the bucket teeth move generally towards the chassis to fill the bucket with ground material. Once the bucket is full, the boom is raised, the arm assembly is swung laterally relative to the machine and the ground material is then dumped by moving the bucket to a dumped position. The sequence is then generally repeated. However, as the bucket is returned to the trench it is not positioned in the same position as when the first bucket load of ground material was removed, rather it is positioned at an incrementally different position ready to take the second bucket load of ground material.
  • Thus, with regard to figures 2 and 3, in order to dig the trench the cutting edge 24B of the bucket must first be positioned on the ground surface G at point 101. The control system then moves the boom, dipper and bucket so as to draw the leading edge 24B to point 102. The control system then crowds the bucket to draw the cutting edge 24B to point 103 following which the boom is raised to move the bucket out of the ground. This results in the removal of portion A of the ground shown cross-hatched in figure 3. The frame is then swung clockwise relative to the chassis (when viewing figure 2) so as to move the bucket towards a second region 60, where it is intended to dump the spoil from the trench. Once the bucket 24 is above second region 60 the bucket is then "dumped" thereby depositing spoil A on the ground at region 60. The frame is then swung anticlockwise and the cutting edge 24B is returned to the trench. However, since ground material A has been moved, the leading edge 24B of the bucket 24 needs to be positioned at position 102 by the control system rather than at position 101. In order to fill the bucket for the second time the cutting edge is positioned at position 102, moved to position 104 and then moved to position 105 in order to collect ground material B shown cross-hatched in figure 3. The boom is then raised to lift the bucket out of the ground, the frame is swung clockwise and the spoil B is deposited at the second region 60 thereby forming a spoil pile. For the third bucket load the cutting edge is initially positioned at position 104 by the control system and then moved to position 106 and 107. For the fourth bucket load the cutting edge is positioned at position 106 by the control system and then moved to position 108 and 109. The fifth bucket load is positioned at position 108 by the control system and then moved to position 110 and then 111. The sixth bucket load is positioned at position 110 by the control system and then moved to position 112 and 113. Thus, each time the bucket is returned to the trench, the cutting edge is positioned by the control system incrementally differently from the previous occasion.
  • The desired position of the trench represents a first region 59 (see figure 2). The spoil pile of the trench represents second region 60 (see figure 2). The invention provides for moving the material handling implement (in this example the bucket 24) repeatedly between the first and second regions. However, the implement is not moved to the same position when at the first region, rather it is moved automatically to an incrementally different position of the first region. In this way a trench or the like can progressively be dug.
  • Where short trenches are required to be dug, then the movement of the boom, dipper and bucket alone may be sufficient to dig the short trench, in other words it may not be necessary to move the vehicle via tracks 16. However, in other circumstances where a longer trench is required then the first part of the trench may be dug (for example by removing ground material A, B and C whilst the chassis is positioned at position 1 of figure 1. In order to remove ground material D, E and F it may be necessary to move the chassis to position 2 as shown in figure 2. In spite of movement of the chassis the bucket nevertheless returns to the first region, i.e. returns to the trench in order to remove ground material D, E and F.
  • In one embodiment the system allows automatic digging of a trench or the like, and as such there is no need for an operator to be physically present in the machine, rather the operator can be remote from the machine. This is particularly advantageous in dangerous environments where the operator can be remote from the machine in a safe location.
  • When in a remote location, the operator need not control all aspects of the machine. In one example all that the operator needs to define is the first position of the first region and the second region. Once this has been done the control system can automatically cause a sequence of predefined movements to occur thereby handling material in a desired manner, for example digging a trench or a hole at the first region and depositing the spoil at the second region.
  • Alternatively, in another embodiment only certain steps may be controlled by the controller. For example, it is only necessary for the step of returning the material handling implement to the first region by positioning it at a second position of the first region different to the first position of the first region be carried out automatically. This enables the implement to be quickly returned to an appropriate position (for example in a trench) different from the previous position of implement (for example in the trench). The control system therefore can quickly return the implement to an incrementally different position. This then enables the operator to control movement of the implement, for example to handle material, until such time as it is required to return the implement to another incrementally different position. This is advantageous when the material being handled is not uniform, for example where the ground includes occasional large rocks or other such material. For example, when digging a trench the first three bucket loads may contain loose material such as soil. Pickling up of this soil requires a particular implement manoeuvre. However, a fourth load may require the digging up of a rock or the like which will require a slightly different implement manoeuvre. The operator will be able to determine the required implement manoeuvre required to pick-up the soil or rock, as appropriate, but nevertheless once the earth/rock has been deposited on the spoil heap, the machine can nevertheless return the implement to an appropriate incrementally different position ready for a further material handling implement manoeuvre to pick-up further soil or a further rock as appropriate and as will be seen by the operator.
  • As described above, and as shown in figure 3, the leading edge 24B of the bucket starts at position 101. For each successive bucket load it is positioned at positions 102, 104, 106, 108 and 110. These incrementally different starting positions generally progress towards the machine. However, in further embodiments the incrementally different positions need not progress towards the machine, rather they can progress in any direction. In particular, when digging a deep hole, or a deep trench, certain of the incrementally different position may be directly below a previous position.
  • The control system may be pre-programmed at the manufacturing factory with a sequence of manoeuvres to be carried out. Alternatively, the control system may be pre-programmed in the field. In particular the control system may be pre-programmed in the field by recording a sequence of material handling manoeuvres and then arranging for those manoeuvres to be repeated with an offset. For example, an alternative way of digging the trench of figure 3 is with the control system disabled, the operator removes soil A and B.
  • With the control system still disabled, the operator enables a recording system which then records the sequence of manual manipulations of the boom control, dipper control and bucket control used to remove soil C and D. That sequence of recorded manoeuvres becomes the pre-programmed sequence of manoeuvres in order to remove soil E and F except with an offset. In other words sequence of manoeuvres used to remove soil D and E are repeated to remove soil E and F except they are repeated with an offset according to the distance between position 104 and 108.
  • In an embodiment additional sensors can be provided to provide a feedback loop for the positional control of the implement. However, in an embodiment no sensors or the like are required and accordingly no positional feedback loop. Such an arrangement is therefore relatively inexpensive (since no feedback sensors are required) and is relatively easy to maintain (since there are no sensors which require maintenance.
  • As described above, the material handling machine is an excavator. However, the present invention is not limited to excavators and other material handling machines could be used, for example a back hoe loader, a telescopic handler, a fork lift truck etc. As described above, the implement used is a bucket. However, in further embodiments it is not necessary to use a bucket and other implements should be used, for example fork lift truck or telescopic handler forks could be used etc.
  • As described above, the step of positioning the material handling implement in a first position of a first region and the step of returning the material handling implement to the first region by positioning it at a second position of the first region different to the first position of the first region are carried out with the machine stationary, either with the machine stationary in the same position, or with the machine stationary in different positions. In further embodiments it is impossible to carry out one or both of these steps whilst the machine is in motion, i.e. whilst the machine is travelling over the ground.

Claims (15)

  1. A method of operating a material handling machine (10) having a material handling implement moveable relative to a chassis of the machine (10), the method including the steps of
    a) manually positioning the material handling implement in a first position (101) of a first region (59) of a trench, the first region (59) being a region where it is desired to manually dig the trench,
    b) manually moving the material handling implement to a second region (60), the second region (60) being a region where it is desired to deposit spoil,
    c) providing a control system (52) and enabling the control system (52) to automatically return the material handling implement to the first region (59) by directly positioning the material handling implement at a second position (102) of the first region (59), the second position (102) being a next sequential position where it is desired to manually dig the trench,
    d) manually returning the material handling implement to the second region (60).
  2. A method as defined in claim 1 wherein step a) includes carrying out a material handling manoeuvre with the implement, preferably the manoeuvre picks up material.
  3. A method as defined in either of claims 1 or 2 wherein step b) includes moving material carried by the implement to the second region (60).
  4. A method as defined in any preceding claim wherein step b) includes carrying out a material handling manoeuvre with the implement at the second region (60), preferably the manoeuvre deposits material.
  5. A method as defined in any preceding claim wherein step c) includes returning the material handling implement to the first region (59) absent any material.
  6. A method as defined in any preceding claim wherein step c) includes carrying out a material handling manoeuvre with the implement, preferably carrying out a material handling manoeuvre of claim 2.
  7. A method as defined in any preceding claim wherein step d) includes moving material carried by the implement to the second region (60).
  8. A method as defined in any preceding claim wherein step d) includes carrying out a material handling manoeuvre with the implement at the second region (60), preferably carrying out the material handling manoeuvre of claim 4.
  9. A method as defined in any preceding claim wherein step b) includes moving the material handling implement to a first position of the second region, wherein step d) includes returning the material handling implement to a second position of the second region (60) different from the first position of the second region.
  10. A method as defined in any preceding claim wherein the material is frangible material and/or loose material, for example wherein the method is used to transfer the frangible and/or loose material from the first region (59) to the second region (60).
  11. A method as defined in any preceding claim wherein the material handling implement is a bucket (24) or a shovel, and/or wherein steps a), b), c) and d) are carried out whilst the chassis (12) of the machine (10) is stationary.
  12. A method as defined in any preceding claim including:-
    e) arranging a control system (52) to automatically return the material handling implement to the first region (59) by positioning it at a third position (104) of the first region different to the first (101) and second (102) positions of the first region (59), the second position (102) of the first region (59) being intermediate, the first position (101) of the first region (59) and the third position (104) of the first region (59),
    f) returning the material handling implement to the second region (60).
  13. A method as defined in claim 12 wherein step f) is carried out automatically by the control system (52).
  14. The method as defined in claim 12 wherein steps a), b), c), d), e) and f) are carried out whilst the chassis of the machine (10) is stationary, preferably prior to carrying out steps e) and f) the chassis (12) of the machine (10) is moved to a different and/or adjacent location.
  15. A material handling machine comprising a material handling implement and a control system, wherein the control system is configured to control the material handling implement to carry out a method according to any of claims 1-14.
EP15170945.8A 2014-07-02 2015-06-08 A material handling machine Active EP3000944B1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
GB1411808.7A GB2527795B (en) 2014-07-02 2014-07-02 Automation of a material handling machine digging cycle

Publications (3)

Publication Number Publication Date
EP3000944A1 EP3000944A1 (en) 2016-03-30
EP3000944B1 true EP3000944B1 (en) 2024-01-17
EP3000944C0 EP3000944C0 (en) 2024-01-17

Family

ID=51410528

Family Applications (1)

Application Number Title Priority Date Filing Date
EP15170945.8A Active EP3000944B1 (en) 2014-07-02 2015-06-08 A material handling machine

Country Status (9)

Country Link
US (1) US20160002878A1 (en)
EP (1) EP3000944B1 (en)
JP (1) JP2016014314A (en)
CN (1) CN105317071A (en)
AU (2) AU2015203391A1 (en)
BR (1) BR102015016056B1 (en)
GB (1) GB2527795B (en)
MX (1) MX2015008174A (en)
RU (2) RU2015125592A (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2574444A (en) 2018-06-06 2019-12-11 Caterpillar Global Mining Llc Face shovel and method of operation
US11372405B2 (en) 2018-08-06 2022-06-28 Clark Equipment Company Augmented loader controls
US11738643B2 (en) 2019-02-27 2023-08-29 Clark Equipment Company Display integrated into door
CN109680740A (en) * 2018-12-28 2019-04-26 山东临工工程机械有限公司 Excavate machine automatic drive system and control method
CA3139501C (en) * 2019-05-07 2024-04-23 Clark Equipment Company Localized navigation system controller for power machine
CN114391056A (en) 2019-11-12 2022-04-22 克拉克设备公司 Display integrated into door
CN117627084A (en) * 2023-12-09 2024-03-01 爱克斯维智能科技(苏州)有限公司 Excavator base material removing method and device, material shaking control system and excavator

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080127531A1 (en) * 2006-11-30 2008-06-05 Daniel Stanek Automated machine repositioning in an excavating operation
US7753132B2 (en) * 2006-11-30 2010-07-13 Caterpillar Inc Preparation for machine repositioning in an excavating operation

Family Cites Families (31)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3643828A (en) * 1969-07-09 1972-02-22 James H Elliott Automatic control system for front end loader
JPS5423001A (en) * 1977-07-22 1979-02-21 Mitsubishi Mining & Cement Co Opencut mining method and apparatus
US4288196A (en) * 1979-06-14 1981-09-08 Sutton Ii James O Computer controlled backhoe
JPS59150837A (en) * 1983-02-17 1984-08-29 Hitachi Constr Mach Co Ltd Action regenerator of working machine
SU1641953A1 (en) * 1988-03-31 1991-04-15 Производственное объединение "Уралмаш" Device for automatic control of hydraulic shovel
US5065326A (en) * 1989-08-17 1991-11-12 Caterpillar, Inc. Automatic excavation control system and method
RU2032029C1 (en) * 1992-07-27 1995-03-27 Хрусталев Евгений Николаевич Method and apparatus of ground excavation by single bucket excavator
US5446980A (en) * 1994-03-23 1995-09-05 Caterpillar Inc. Automatic excavation control system and method
US5438771A (en) * 1994-05-10 1995-08-08 Caterpillar Inc. Method and apparatus for determining the location and orientation of a work machine
WO1997046763A1 (en) * 1996-06-03 1997-12-11 Siemens Aktiengesellschaft Process and arrangement for controlling a sequence of movements in a moving construction machine
US6523765B1 (en) * 1998-03-18 2003-02-25 Hitachi Construction Machinery Co., Ltd. Automatically operated shovel and stone crushing system comprising the same
US6167336A (en) * 1998-05-18 2000-12-26 Carnegie Mellon University Method and apparatus for determining an excavation strategy for a front-end loader
US6363632B1 (en) * 1998-10-09 2002-04-02 Carnegie Mellon University System for autonomous excavation and truck loading
US6371214B1 (en) * 1999-06-11 2002-04-16 Caterpillar Inc. Methods for automating work machine functions
JP2001123478A (en) * 1999-10-28 2001-05-08 Hitachi Constr Mach Co Ltd Automatically operating excavator
JP2001182091A (en) * 1999-12-28 2001-07-03 Hitachi Constr Mach Co Ltd Automatic operating shovel, and automatic shovel operating method
AU2002331786A1 (en) * 2001-08-31 2003-03-18 The Board Of Regents Of The University And Community College System, On Behalf Of The University Of Coordinated joint motion control system
CA2682256C (en) * 2007-03-21 2017-01-03 Commonwealth Scientific And Industrial Research Organisation Method for planning and executing obstacle-free paths for rotating excavation machinery
US7934329B2 (en) * 2008-02-29 2011-05-03 Caterpillar Inc. Semi-autonomous excavation control system
CN102042098A (en) * 2009-10-14 2011-05-04 北汽福田汽车股份有限公司 Method and system for controlling engine gears of excavator
US8527158B2 (en) * 2010-11-18 2013-09-03 Caterpillar Inc. Control system for a machine
US8239128B2 (en) * 2010-11-30 2012-08-07 Caterpillar Inc. Electric cable management for a mobile machine
CN102071717B (en) * 2010-12-16 2012-07-04 重庆航天工业公司 Adaptive control method for excavator
US9206587B2 (en) * 2012-03-16 2015-12-08 Harnischfeger Technologies, Inc. Automated control of dipper swing for a shovel
US9598836B2 (en) * 2012-03-29 2017-03-21 Harnischfeger Technologies, Inc. Overhead view system for a shovel
RU2496303C1 (en) * 2012-05-03 2013-10-27 Лев Николаевич Шобанов Method of machine control
US8700272B2 (en) * 2012-07-30 2014-04-15 Caterpillar Inc. System and method for detecting a crest
US20140064897A1 (en) * 2012-08-29 2014-03-06 Deere And Company Single stick operation of a work tool
US9580883B2 (en) * 2014-08-25 2017-02-28 Cnh Industrial America Llc System and method for automatically controlling a lift assembly of a work vehicle
US20170073935A1 (en) * 2015-09-11 2017-03-16 Caterpillar Inc. Control System for a Rotating Machine
US20170073925A1 (en) * 2015-09-11 2017-03-16 Caterpillar Inc. Control System for a Rotating Machine

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080127531A1 (en) * 2006-11-30 2008-06-05 Daniel Stanek Automated machine repositioning in an excavating operation
US7753132B2 (en) * 2006-11-30 2010-07-13 Caterpillar Inc Preparation for machine repositioning in an excavating operation

Also Published As

Publication number Publication date
EP3000944A1 (en) 2016-03-30
GB2527795B (en) 2019-11-13
MX2015008174A (en) 2016-04-22
AU2015203391A1 (en) 2016-01-21
AU2020200774A1 (en) 2020-02-20
RU2015125592A3 (en) 2018-06-19
CN105317071A (en) 2016-02-10
US20160002878A1 (en) 2016-01-07
BR102015016056B1 (en) 2022-06-14
GB2527795A (en) 2016-01-06
JP2016014314A (en) 2016-01-28
RU2745144C1 (en) 2021-03-22
RU2015125592A (en) 2017-01-10
BR102015016056A2 (en) 2016-05-24
EP3000944C0 (en) 2024-01-17
GB201411808D0 (en) 2014-08-13

Similar Documents

Publication Publication Date Title
EP3000944B1 (en) A material handling machine
US7726048B2 (en) Automated machine repositioning in an excavating operation
US10246855B2 (en) Material handling machine with bucket shake control system and method
US7753132B2 (en) Preparation for machine repositioning in an excavating operation
WO2008066648A2 (en) Repositioning assist for an excavating operation
KR20190110583A (en) Working machine
EP3088611B1 (en) A method of mounting an attachment
US20080127529A1 (en) Recommending a machine repositioning distance in an excavating operation
US9051944B2 (en) Hydraulic system and control logic for collection and recovery of energy in a double actuator arrangement
AU2018101149A4 (en) An Improved Bucket
EP4108836B1 (en) System and method for automatically controlling a work vehicle during the performance of an earthmoving operation
EP2955285B1 (en) A material handling machine
US20150345103A1 (en) Linkage assembly for machine
GB2527598A (en) A material handling machine
JP4395286B2 (en) Method and apparatus for lifting a work implement attached to a work machine
US11920322B2 (en) Systems and methods for coupling an implement to a work vehicle
US20180171577A1 (en) Debris gripper and extractor for hydraulic equipment
US20170121934A1 (en) Accessory for excavation of a ditch and related methods
US11613871B2 (en) Systems and methods for coupling an implement to a work vehicle
US20080022564A1 (en) Off-fall control for a trenching operation
KR101936329B1 (en) Construction equipment
AU2018200283A1 (en) Bucket-orientation-maintaining device for tractor loader
JPH04302620A (en) Front loader

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

AX Request for extension of the european patent

Extension state: BA ME

17P Request for examination filed

Effective date: 20160930

RBV Designated contracting states (corrected)

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: EXAMINATION IS IN PROGRESS

17Q First examination report despatched

Effective date: 20200423

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: EXAMINATION IS IN PROGRESS

RAP3 Party data changed (applicant data changed or rights of an application transferred)

Owner name: J.C. BAMFORD EXCAVATORS LIMITED

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: GRANT OF PATENT IS INTENDED

INTG Intention to grant announced

Effective date: 20220317

GRAJ Information related to disapproval of communication of intention to grant by the applicant or resumption of examination proceedings by the epo deleted

Free format text: ORIGINAL CODE: EPIDOSDIGR1

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: EXAMINATION IS IN PROGRESS

INTC Intention to grant announced (deleted)
GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: GRANT OF PATENT IS INTENDED

INTG Intention to grant announced

Effective date: 20230822

RIN1 Information on inventor provided before grant (corrected)

Inventor name: HARPER, LEE

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE PATENT HAS BEEN GRANTED

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: DE

Ref legal event code: R096

Ref document number: 602015087289

Country of ref document: DE

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

U01 Request for unitary effect filed

Effective date: 20240123

U07 Unitary effect registered

Designated state(s): AT BE BG DE DK EE FI FR IT LT LU LV MT NL PT SE SI

Effective date: 20240130

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240517

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: GB

Payment date: 20240614

Year of fee payment: 10

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240418

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: HR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240117

Ref country code: RS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240417

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240117

U20 Renewal fee paid [unitary effect]

Year of fee payment: 10

Effective date: 20240614

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: RS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240417

Ref country code: NO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240417

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240517

Ref country code: HR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240117

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240418

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240117

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: PL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240117

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: PL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240117

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SM

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20240117