EP2831343A2 - A pile grounded construction and a method for making such a construction - Google Patents

A pile grounded construction and a method for making such a construction

Info

Publication number
EP2831343A2
EP2831343A2 EP13712677.7A EP13712677A EP2831343A2 EP 2831343 A2 EP2831343 A2 EP 2831343A2 EP 13712677 A EP13712677 A EP 13712677A EP 2831343 A2 EP2831343 A2 EP 2831343A2
Authority
EP
European Patent Office
Prior art keywords
building structure
elements
compensation
ground
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
EP13712677.7A
Other languages
German (de)
French (fr)
Other versions
EP2831343B1 (en
Inventor
Lars Erik Hansen
Luis Jørgen NØRGAARD
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Rockwool AS
Original Assignee
Rockwool International AS
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Rockwool International AS filed Critical Rockwool International AS
Priority to EP13712677.7A priority Critical patent/EP2831343B1/en
Publication of EP2831343A2 publication Critical patent/EP2831343A2/en
Application granted granted Critical
Publication of EP2831343B1 publication Critical patent/EP2831343B1/en
Not-in-force legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations

Definitions

  • the present invention relates to a method for constructing a pile grounded building structure including the steps of arranging a plurality of piles in the ground, and constructing the building structure in a manner so that a fixed connection is achieved between it and at least some of the piles.
  • the invention further relates to a construction comprising a pile grounded building structure, where at least some of the piles are fixed in the building structure.
  • Pile grounding also known as a pile foundation, is used where the soil bearing capacity does not allow the use of simpler types of foundations or where an uplift on the construction is not equalized by its self-weight, the latter often being the case in wholly or partially submerged constructions.
  • the concrete When making the building structure from concrete by in situ casting, the concrete may be poured directly onto the compensation elements, thus minimizing the need for formwork.
  • the compensa- tion elements it is, however, also possible to arrange one or more cover elements) on top of the compensation elements to protect them from direct contact with the concrete.
  • cover elements may also contribute to the distribution of loads on the compensation elements.
  • the compensation elements to be used as a support for the building structure during construction thereof, the distance between the ground and the intended lowermost surface of the building structure must be compensated for. This means that the compensation elements together with any additional elements used in the space between the ground and the building structure must have a total height corresponding substantially to this distance.
  • the compressive strength o c of the compensation elements is to be understood as the yield strength, i.e. the maximum strength up to which deformation is still elastic.
  • the compensation elements should also be capa- ble of carrying the load of any traffic necessary for the construction of the building structure and that such loads is advantageously included in the calculation of the compressive force o D .
  • the compensation elements should preferably be capable of withstanding local loads, which may for ex- ample occur if a person steps on a compensation element.
  • the calculation of the breaking strength o B of the building deck structure should be based on the point in the construction, which will break first under the influence of a force from below caused by a soil uplift.
  • the location of this weakest point will depend on a number of fac- tors, not least relating to the use of reinforcement, and thus has to be determined for each individual construction.
  • the break may result from shearing forces, tensile forces, compressive forces or a combination of these depending on the structure in question and that all possible breakage patterns should take into consideration when making the calculations.
  • the construction includes several building structures, the calculation must include all of them.
  • the compensation elements may in principle be made from any suitable material and with any geometry, which is capable of carrying the loads of the building structure during its construction and any traffic associated with its construction, and of compensating for subsequent soil uplift.
  • lamella elements made from mineral wool, preferably having a density of 30-75 kg/m 3 , for stone wool 50-75 kg/m 3 , as compensation elements, these lamella elements being laid close to one another with the primary orientation of the mineral wool fibres of the lamella elements being approximately vertical.
  • the vertical orientation of the fibres means that each of them function as a small pillar, resulting in the load- bearing capacity being relatively high in comparison to traditional mineral wool batts or mats of the same density.
  • the vertical orientation of the fibres also means that the upper and lower surfaces of the lamella elements are of a relatively open structure, which may allow cement paste to penetrate between the fibres, when concrete is cast directly onto the compensation elements as described above. When the cement cures this may influence the bearing capacity of the lamella elements and hence potentially result in them not being able to serve their purpose as compensation elements.
  • This may be avoided by providing the lamella elements with a surface layer or by applying cover elements on top of the lamella elements as described above.
  • the cover elements are laid so that joints between them are not directly above parallel joints between compensation elements. Cover elements as well as compensation elements may be laid in a bond pattern to provide for a more homogeneous layer.
  • compensation elements are made from materials of a more homogeneous structure, such as expanded polystyrene or like foamed materials, and provided with weakening zones allowing them to collapse wholly or partially. Simple examples of such weakening zones are hollows in the material or sectors of a material of a lower density.
  • spheres filled with a solvent is embedded in the material and designed to burst and release the solvent when exposed to a pre-defined pressure, thereby dissolving the material of the compensation element and reducing its strength.
  • the solvent can be any suitable material depending on the material used for the compensation element, including organic solvents, but possible impacts of the environment and worker health should of course be taken into consideration.
  • Yet another type of compensation element comprises an outer shell and an inner lumen filled with a fluid, said outer shell allowing at least some of the fluid to escape when the compensation element is exposed to a pressure larger than the compressive force o D resulting from the weight of the building structure.
  • the fluid is preferably water or air, which are readily available and non-toxic, and the outer shell could be a textile material, allowing the fluid to escape through the weave under pressure.
  • An even simpler embodiment uses an outer shell where joints are made so sufficiently weak that they will burst when a pre-defined pressure is reached inside the compensation element.
  • spacers for holding reinforcement may be arranged on at least some of the compensation elements or cover elements if any. These spacers may be an integral part of the compensation elements or cover elements or may be arranged subsequent to step g) of the method.
  • Fig. 1 is a cross-sectional view of a pile grounded construction including a strip foundation and a ground deck in an initial state
  • Fig. 2 is a view of the detail marked II in Fig. 1 during a period of soil uplift
  • Fig. 4 is a view corresponding to that in Fig. 2, but in the initial state and showing a second embodiment of the compensation element
  • Fig. 6 is a view corresponding to that in Figs. 4 and 5, but showing a fourth embodiment of the compensation element.
  • the construction in Fig. 1 comprises foundation piles 10, 1 1 , 12, 13, 14 and two building structures in the form of a strip foundation 2 and a ground deck 3 arranged above a stripped ground surface 4'.
  • the space between the ground deck 3 and the stripped ground surface 4' and delimited by the strip foundation 2 is filled with one or more compensation elements 5, the function of which will be described below.
  • the piles 10,1 1 , 12,13, 14, which may be rammed into the ground 4, cast in situ in drilled holes or provided in any other expedient manner, are in direct contact with the strip foundation 2 and the ground deck 3, respectively, and are fixed therein as it is common practice.
  • This fixed connection may be achieved by embedding an upper end of a pile 12 projecting over the stripped ground surface 4' in the concrete, which are cast in situ, or by letting the con- crete penetrate into passages between the compensation elements 5 to reach a pile 1 1 , 13 ending at a lower level.
  • pre- made elements for the strip foundation and ground deck and to interconnect them to the piles. Methods for making these interconnections, both when using in situ cast building structures and pre-made elements, are known to the skilled person and will therefore not be described in detail here.
  • piles 10, 1 1 , 12, 13, 14 are distributed along the length of the strip foundation 2 and the ground deck 3, i.e. the direction into the plane of the drawing in Fig. 1 .
  • the distribution of the piles is not necessarily even as the need for piles is dictated by local soil conditions and it is even possible to have a construction, where one part of the construction is pile grounded, whereas the ground underneath other parts has sufficient bearing capacity to make piles superfluous.
  • the length of the piles depends on local soil condition and the expected loads on the building structure and will therefore normally vary over the construction as also illustrated in Fig. 1 .
  • the level 4' of the stripped ground surface on the inner side of the construction is lower than the level 4" of the ground surface on the outer side, which may be achieved either by excavating a construction pit or by arranging fill material on the outer side. It is, how- ever, to be understood that the stripped ground surface level 4' on the inner side may be the same as or higher than that 4" on the outer side. It is noted that the wording "stripped ground surface" is used to indicate that the ground surface has been prepared for the construction work, normally including the removal of top soil, and that this surface is therefore not necessarily at level with the original ground surface. It is, however, to be understood that in some cases the preparation may involve the addition of fill material to achieve an elevated ground surface and that the stripped ground surface is then higher than the original ground surface.
  • the strip foundation 2 and ground deck 3 may be regarded as two separate building structures or as one coherent building structure and it is to be understood that the construction may include further building structures.
  • the compensation members 5 are drawn with a signature normally used for insulating materials, since mineral wool is presently the preferred material, but other materials may also be used as will be explained later.
  • the insulating properties of the compensation elements are in principle of no consequence, but may be considered an added benefit.
  • the compensation elements 5 are drawn as a single homogeneous unit filling the spaces between piles 1 underneath the ground deck 3 entirely, but this need not be the case.
  • the compensation element will, however, often be smaller and hence several elements will be needed for filling the space.
  • cover elements not shown
  • the compensation elements 5 must fulfil three requirements: Firstly, they must have a compressive strength o c , which is larger than the compressive force o D resulting from the area weight of the ground deck 3, secondly, the compressive strength o c must be smaller than the breaking strength o s of the ground deck 3, and, thirdly, it must have a maximum strain E C , which is bigger than the expected maximum soil uplift E G of the ground 4.
  • the second and third requirement in combination means that if anything breaks as a consequence of soil uplift it is the compensation member 5, which will simply collapse and hence protect the ground deck 3 from damage.
  • This is illustrated in Fig. 2, where the initial level of the stripped ground surface is indicated by 4' and a subsequent level during a period of soil uplift by 4"'.
  • the compensation member 5 When the stripped ground surface rises, the compensation member 5 is simply compressed from its initial height hi to a reduced height h 2 , the change in height Ah corresponding to the magnitude of the soil uplift.
  • the compensation member is compressed to its maximum deformation and the stripped ground surface level continues to rise, it will eventually result in a higher pressure affecting the ground deck from below. It should therefore be ensured that the compensation elements are sufficiently high to be able to compensate for any soil uplift, which may reasonably be expected during the life time of the construction in question.
  • lamella elements of rock wool are well suited for use as compensation elements 5. These elements have a relatively homogeneous fibre orientation and when arranged with the majority of the fibres extending substantially in the direction of the forces applied, they have a high load bearing capacity compared to other mineral wool products of similar density and display a relatively low elastic deformation. In the context of the present invention this means that lamella elements arranged with a substantially vertical orientation of the fibres carry the loads of the building structure well.
  • the width of such lamella elements is 50-600 mm, preferably approximately 200-300 mm and the length is 1500-2500 mm, preferably approximately 2000 mm.
  • cover elements Due to the orientation of the fibres, not all lamella elements are suited for receiving concrete directly onto the upwards facing surface unless provided with some sort of surface covering and it may therefore be expedient to cover them with one or more cover elements as also explained above.
  • This may simply be a sheet of plastic, plywood plates or the like, but could also be mineral wool bats, preferably having a density of 120-220 kg/m 3 .
  • cover elements may also contribute to the distribution of loads and may function as a slip layer preventing the compensation elements 5 from sticking to the ground deck 3 as shown in Fig. 3.
  • a compensation elements made from a foam material such as expanded polystyrene
  • openings 51 serving as weakening zones.
  • the walls 52 between the openings collapse wholly or partially into the openings causing a reduction of the height of the compensation member.
  • the openings are shown as closed spaces, but they may also expend to a surface of the compensation member as indicated by the dotted lines.
  • Fig. 4 The embodiment in Fig. 4 is, however, presently less preferred as it involves a more abrupt reduction of the height of the compensation member than when using lamella elements of mineral wool and the material itself has less potential for compression.
  • spheres 53 filled with a solvent is embedded in the material and designed to burst and release the solvent when exposed to a pre-defined pressure.
  • the zone containing the spheres thus effectively becomes a weakening zone and it is possible to include spheres of different strength to provide a gradual release of the solvent.
  • the solvent would be an organic solvent, but other materials may entail the use of other solvents. This embodiment too is, however, presently less preferred as it is relatively expensive.
  • a third embodiment of the compensation element is shown in Fig. 6 and includes an outer shell 54 and an inner lumen 55 filled with a fluid, preferably water, air or a like cheap and non-polluting substance.
  • a fluid preferably water, air or a like cheap and non-polluting substance.
  • the outer shell is designed to allow at least some of the fluid to escape, either gradually via openings 56 in the outer shell, by the shell bursting or by a combination thereof.
  • the openings may simply be plugged holes in the outer shell, where the plugs are designed to be forced out of the opening, when a pre-defined pressure is reached, or valves open- ing and closing depending on the pressure.
  • spheres containing a solvent could be embedded in the material of the outer shell so that holes or weakenings are formed when the spheres burst.
  • the compensation member is simply made from a material, which becomes soft on exposure to water and will therefore loose its bearing capacity on contact with wet soil.
  • a compensation member could for example be made from paper or cardboard.

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

A construction according to the invention comprises a pile grounded building structure, where at least some of the piles are fixed in the building structure. Compensation elements, which are preferably lamella elements made from mineral wool, are arranged between the stripped ground surface and the building structure, so that they cover the area covered by the building structure substantially entirely. Said compensation elements have a compressive strength σC, which is larger than the compressive force σDresulting from the area weight of the building structure and smaller than the breaking strength σSof the building structure, and a maximum strain εC, which is bigger than the expected maximum soil uplift εG of the ground. The invention further relates to a method for making such a construction.

Description

The present invention relates to a method for constructing a pile grounded building structure including the steps of arranging a plurality of piles in the ground, and constructing the building structure in a manner so that a fixed connection is achieved between it and at least some of the piles. The invention further relates to a construction comprising a pile grounded building structure, where at least some of the piles are fixed in the building structure.
Pile grounding, also known as a pile foundation, is used where the soil bearing capacity does not allow the use of simpler types of foundations or where an uplift on the construction is not equalized by its self-weight, the latter often being the case in wholly or partially submerged constructions.
In constructions, which are of limited size and/or massive, such as for example a bridge pier, expansion of the soil underneath it can often be taken up by the neighbouring soil, possibly resulting in a soil uplift around the con- struction. Likewise, if the pile density is high, there will be little soil that can expand. If, on the other hand, the construction is hollow, involves fewer piles and/or covers a larger area, soil expansion have been known to course fractures in building structures, particularly in ground decks made from concrete and where horizontal expansion of the soil is hindered by a strip foundation.
It is therefore the object of the invention to provide a method for constructing a pile grounded building structure resulting in a construction, which is better capable of withstanding soil expansion.
This object is achieved with a method including the following steps to be performed before constructing the building structure:
c) calculating the expected area weight of the building structure and the resulting compressive force oD affecting material underneath of the building structure during construction thereof,
d) calculating the breaking strength oB of the building structure, e) calculating the expected maximum soil uplift EG of the ground, f) providing compensation elements having:
- a compressive strength oc, which is larger than the compressive force oD of the building structure and smaller than the breaking strength oB of the building structure, and - a maximum strain EC, which is bigger than the expected maximum soil uplift EG of the ground,
g) arranging the compensation elements on the ground , so that they cover the area to be covered by the building structure substantially entirely.
When such compensation elements are used as an intermediary layer between the building structure and the ground, any forces affecting the construction from below due to soil expansion will result in the compensation elements collapsing before the breaking strength of the building structure is reached. Due to the relatively large strain in the compensation elements, a direct transmission of forces from the ground to the building structure is prevented.
When making the building structure from concrete by in situ casting, the concrete may be poured directly onto the compensation elements, thus minimizing the need for formwork. Depending on the design of the compensa- tion elements it is, however, also possible to arrange one or more cover elements) on top of the compensation elements to protect them from direct contact with the concrete. Such cover elements may also contribute to the distribution of loads on the compensation elements.
It is to be understood that for the compensation elements to be used as a support for the building structure during construction thereof, the distance between the ground and the intended lowermost surface of the building structure must be compensated for. This means that the compensation elements together with any additional elements used in the space between the ground and the building structure must have a total height corresponding substantially to this distance.
With respect to step f) it is noted that the compressive strength oc of the compensation elements is to be understood as the yield strength, i.e. the maximum strength up to which deformation is still elastic. Once the building structure is finished, however, the need for the support of the compensation elements is considerably reduced or may no longer be needed at all and irreversible strain in the compensation element is thus often acceptable.
It is also noted that the compensation elements should also be capa- ble of carrying the load of any traffic necessary for the construction of the building structure and that such loads is advantageously included in the calculation of the compressive force oD. Likewise, the compensation elements should preferably be capable of withstanding local loads, which may for ex- ample occur if a person steps on a compensation element.
With respect to step d), the calculation of the breaking strength oB of the building deck structure should be based on the point in the construction, which will break first under the influence of a force from below caused by a soil uplift. The location of this weakest point will depend on a number of fac- tors, not least relating to the use of reinforcement, and thus has to be determined for each individual construction. It is also noted that the break may result from shearing forces, tensile forces, compressive forces or a combination of these depending on the structure in question and that all possible breakage patterns should take into consideration when making the calculations. Finally it is noted that if the construction includes several building structures, the calculation must include all of them.
Throughout this text reference is made to concrete, which is by far the most commonly used material for pile grounded building structures, but it is to be understood that the invention also applies to building structures made from other materials.
The compensation elements may in principle be made from any suitable material and with any geometry, which is capable of carrying the loads of the building structure during its construction and any traffic associated with its construction, and of compensating for subsequent soil uplift.
At present it is preferred to use lamella elements made from mineral wool, preferably having a density of 30-75 kg/m3, for stone wool 50-75 kg/m3, as compensation elements, these lamella elements being laid close to one another with the primary orientation of the mineral wool fibres of the lamella elements being approximately vertical. The vertical orientation of the fibres means that each of them function as a small pillar, resulting in the load- bearing capacity being relatively high in comparison to traditional mineral wool batts or mats of the same density. When a load is applied to such a la- mella element in a direction substantially in parallel to the orientation of the fibres, the element initially displays only very limited deformation, but when exceeding the maximum bearing capacity of the fibres, they buckle causing the element to yield with a considerable deformation.
The vertical orientation of the fibres, however, also means that the upper and lower surfaces of the lamella elements are of a relatively open structure, which may allow cement paste to penetrate between the fibres, when concrete is cast directly onto the compensation elements as described above. When the cement cures this may influence the bearing capacity of the lamella elements and hence potentially result in them not being able to serve their purpose as compensation elements. This may be avoided by providing the lamella elements with a surface layer or by applying cover elements on top of the lamella elements as described above. Advantageously, the cover elements are laid so that joints between them are not directly above parallel joints between compensation elements. Cover elements as well as compensation elements may be laid in a bond pattern to provide for a more homogeneous layer.
Other types of compensation elements are made from materials of a more homogeneous structure, such as expanded polystyrene or like foamed materials, and provided with weakening zones allowing them to collapse wholly or partially. Simple examples of such weakening zones are hollows in the material or sectors of a material of a lower density. In a more complex embodiment spheres filled with a solvent is embedded in the material and designed to burst and release the solvent when exposed to a pre-defined pressure, thereby dissolving the material of the compensation element and reducing its strength. The solvent can be any suitable material depending on the material used for the compensation element, including organic solvents, but possible impacts of the environment and worker health should of course be taken into consideration.
Yet another type of compensation element comprises an outer shell and an inner lumen filled with a fluid, said outer shell allowing at least some of the fluid to escape when the compensation element is exposed to a pressure larger than the compressive force oD resulting from the weight of the building structure. The fluid is preferably water or air, which are readily available and non-toxic, and the outer shell could be a textile material, allowing the fluid to escape through the weave under pressure. An even simpler embodiment, however, uses an outer shell where joints are made so sufficiently weak that they will burst when a pre-defined pressure is reached inside the compensation element.
For use when casting the building structure in situ, spacers for holding reinforcement may be arranged on at least some of the compensation elements or cover elements if any. These spacers may be an integral part of the compensation elements or cover elements or may be arranged subsequent to step g) of the method.
Moreover, the compensation elements and/or cover elements may be provided with a surface coating or additive, such as an adhesive, a mois- ture repellent, a fungicide or a primer, depending on demands.
In the following the invention will be described in closer detail with reference to examples shown in the schematic drawing where:
Fig. 1 is a cross-sectional view of a pile grounded construction including a strip foundation and a ground deck in an initial state,
Fig. 2 is a view of the detail marked II in Fig. 1 during a period of soil uplift,
Fig. 3 is a view corresponding to that in Fig. 2 at a later stage where the soil has reverted to its initial state,
Fig. 4 is a view corresponding to that in Fig. 2, but in the initial state and showing a second embodiment of the compensation element,
Fig. 5 is a view corresponding to that in Fig. 4, but showing a third embodiment of the compensation element, and
Fig. 6 is a view corresponding to that in Figs. 4 and 5, but showing a fourth embodiment of the compensation element.
The construction in Fig. 1 comprises foundation piles 10, 1 1 , 12, 13, 14 and two building structures in the form of a strip foundation 2 and a ground deck 3 arranged above a stripped ground surface 4'. The space between the ground deck 3 and the stripped ground surface 4' and delimited by the strip foundation 2 is filled with one or more compensation elements 5, the function of which will be described below.
The piles 10,1 1 , 12,13, 14, which may be rammed into the ground 4, cast in situ in drilled holes or provided in any other expedient manner, are in direct contact with the strip foundation 2 and the ground deck 3, respectively, and are fixed therein as it is common practice. This fixed connection may be achieved by embedding an upper end of a pile 12 projecting over the stripped ground surface 4' in the concrete, which are cast in situ, or by letting the con- crete penetrate into passages between the compensation elements 5 to reach a pile 1 1 , 13 ending at a lower level. It is, however also possible to use pre- made elements for the strip foundation and ground deck and to interconnect them to the piles. Methods for making these interconnections, both when using in situ cast building structures and pre-made elements, are known to the skilled person and will therefore not be described in detail here.
Though not visible in Fig. 1 , it is to be understood that piles 10, 1 1 , 12, 13, 14 are distributed along the length of the strip foundation 2 and the ground deck 3, i.e. the direction into the plane of the drawing in Fig. 1 . The distribution of the piles is not necessarily even as the need for piles is dictated by local soil conditions and it is even possible to have a construction, where one part of the construction is pile grounded, whereas the ground underneath other parts has sufficient bearing capacity to make piles superfluous. Likewise, the length of the piles depends on local soil condition and the expected loads on the building structure and will therefore normally vary over the construction as also illustrated in Fig. 1 .
In the constructions shown in Fig. 1 the level 4' of the stripped ground surface on the inner side of the construction is lower than the level 4" of the ground surface on the outer side, which may be achieved either by excavating a construction pit or by arranging fill material on the outer side. It is, how- ever, to be understood that the stripped ground surface level 4' on the inner side may be the same as or higher than that 4" on the outer side. It is noted that the wording "stripped ground surface" is used to indicate that the ground surface has been prepared for the construction work, normally including the removal of top soil, and that this surface is therefore not necessarily at level with the original ground surface. It is, however, to be understood that in some cases the preparation may involve the addition of fill material to achieve an elevated ground surface and that the stripped ground surface is then higher than the original ground surface.
Depending on the over-all construction, the strip foundation 2 and ground deck 3 may be regarded as two separate building structures or as one coherent building structure and it is to be understood that the construction may include further building structures.
In the drawing, the compensation members 5 are drawn with a signature normally used for insulating materials, since mineral wool is presently the preferred material, but other materials may also be used as will be explained later. In this context the insulating properties of the compensation elements are in principle of no consequence, but may be considered an added benefit.
Moreover, in Fig. 1 the compensation elements 5 are drawn as a single homogeneous unit filling the spaces between piles 1 underneath the ground deck 3 entirely, but this need not be the case. Depending on the material used, the compensation element will, however, often be smaller and hence several elements will be needed for filling the space. In that case, it may be advantageous to lay the compensation elements in a bond pattern and/or to provide cover elements (not shown) covering the joints between the compensation members. This will not only provide a better and more continuous load bearing capacity but will also reduce the risk of fresh concrete pene- trating into the joints. Likewise, it is possible to arrange two or more compensation members on top of each other so that they together form a stratified compensation layer (not shown).
Regardless of the material used and their dimensions, the compensation elements 5 must fulfil three requirements: Firstly, they must have a compressive strength oc, which is larger than the compressive force oD resulting from the area weight of the ground deck 3, secondly, the compressive strength oc must be smaller than the breaking strength os of the ground deck 3, and, thirdly, it must have a maximum strain EC, which is bigger than the expected maximum soil uplift EG of the ground 4.
The first requirement allows the compensation element 5 to serve as a support for the ground deck 3 during its construction, typically serving as a receiving surface for in-situ concrete and supporting the weight of the concrete and associated reinforcement until the concrete has cured. The compensation elements should preferably also be able to carry the weight of persons standing and walking on them and any other loads, which could reasonably be expected during the construction of the deck.
The second and third requirement in combination means that if anything breaks as a consequence of soil uplift it is the compensation member 5, which will simply collapse and hence protect the ground deck 3 from damage. This is illustrated in Fig. 2, where the initial level of the stripped ground surface is indicated by 4' and a subsequent level during a period of soil uplift by 4"'. When the stripped ground surface rises, the compensation member 5 is simply compressed from its initial height hi to a reduced height h2, the change in height Ah corresponding to the magnitude of the soil uplift. Of course, if the compensation member is compressed to its maximum deformation and the stripped ground surface level continues to rise, it will eventually result in a higher pressure affecting the ground deck from below. It should therefore be ensured that the compensation elements are sufficiently high to be able to compensate for any soil uplift, which may reasonably be expected during the life time of the construction in question.
In Fig. 3 the cause for the soil uplift is no longer present and the stripped ground surface has returned to its original level 4', but the compensation member 5 has been permanently deformed, as indicated by the modified signature, and therefore has not followed this movement, resulting in the formation of a space 6 between the ground deck 3 and the stripped ground surface. Such a permanent deformation is usually acceptable as the ground deck will normally be self-supporting once the concrete has cured.
In Fig. 3 the space is illustrated between the deformed compensation member 5 and the stripped ground surface 4'. This will typically be the result when concrete has been cast directly onto the upper surface of the compensation member, which consequently sticks to the concrete. In other cases, however, the compensation member may follow the stripped ground surface so that the space is formed between the compensation member 5 and the ground deck 3, or different layers of compensation members and/or associated elements may come apart and form one of more spaces between them.
Experiments have shown that so-called lamella elements of rock wool are well suited for use as compensation elements 5. These elements have a relatively homogeneous fibre orientation and when arranged with the majority of the fibres extending substantially in the direction of the forces applied, they have a high load bearing capacity compared to other mineral wool products of similar density and display a relatively low elastic deformation. In the context of the present invention this means that lamella elements arranged with a substantially vertical orientation of the fibres carry the loads of the building structure well.
When exceeding the yield strength of the lamella elements, however, the deformation is considerable as the fibres buckle successively and hence the lamella elements are able to compensate for considerable soil uplifts.
Lamella elements made from mineral wool with a density of 30-75 kg/m3, for stone wool 50-75 kg/m3, and a height of 50-500 mm, preferably 100-300 mm, will be well suited for most constructions. In case of extreme uplifts or extremely heavy building structures, the height or density, respectively, may, however, need to be even bigger.
Manual handling at the construction site will be possible if the width of such lamella elements is 50-600 mm, preferably approximately 200-300 mm and the length is 1500-2500 mm, preferably approximately 2000 mm.
Due to the orientation of the fibres, not all lamella elements are suited for receiving concrete directly onto the upwards facing surface unless provided with some sort of surface covering and it may therefore be expedient to cover them with one or more cover elements as also explained above. This may simply be a sheet of plastic, plywood plates or the like, but could also be mineral wool bats, preferably having a density of 120-220 kg/m3. Such cover elements may also contribute to the distribution of loads and may function as a slip layer preventing the compensation elements 5 from sticking to the ground deck 3 as shown in Fig. 3.
Many other materials apart from mineral wool will also be usable for the compensation members, as the balance between bearing capacity and the ability to yield may be achieved in many ways.
One example of such an alternative embodiment is shown in Fig. 4, where a compensation elements made from a foam material, such as expanded polystyrene, is provided with openings 51 serving as weakening zones. When a pre-determined load smaller than the breaking strength of the building structure is applied, the walls 52 between the openings collapse wholly or partially into the openings causing a reduction of the height of the compensation member. Here the openings are shown as closed spaces, but they may also expend to a surface of the compensation member as indicated by the dotted lines.
The embodiment in Fig. 4 is, however, presently less preferred as it involves a more abrupt reduction of the height of the compensation member than when using lamella elements of mineral wool and the material itself has less potential for compression.
Another alternative is shown in Fig. 5, where spheres 53 filled with a solvent is embedded in the material and designed to burst and release the solvent when exposed to a pre-defined pressure. The zone containing the spheres thus effectively becomes a weakening zone and it is possible to include spheres of different strength to provide a gradual release of the solvent. If using a compensation member made from expanded polystyrene, the solvent would be an organic solvent, but other materials may entail the use of other solvents. This embodiment too is, however, presently less preferred as it is relatively expensive.
A third embodiment of the compensation element is shown in Fig. 6 and includes an outer shell 54 and an inner lumen 55 filled with a fluid, preferably water, air or a like cheap and non-polluting substance. When a predefined pressure is reached, the outer shell is designed to allow at least some of the fluid to escape, either gradually via openings 56 in the outer shell, by the shell bursting or by a combination thereof. The openings may simply be plugged holes in the outer shell, where the plugs are designed to be forced out of the opening, when a pre-defined pressure is reached, or valves open- ing and closing depending on the pressure. In this case too, spheres containing a solvent could be embedded in the material of the outer shell so that holes or weakenings are formed when the spheres burst.
In a fourth embodiment (not shown) the compensation member is simply made from a material, which becomes soft on exposure to water and will therefore loose its bearing capacity on contact with wet soil. Such a compensation member could for example be made from paper or cardboard.
In the examples described above, the invention has been described with reference to a construction with a single building structure in the form of a ground deck 3, but it is to be understood that the construction may include more building structures and that it need not include a ground deck. Other examples of building structures, which might benefit from the use of compensation members are hollow elements, such as tunnel sections.
Moreover, it has been the assumption that the soil expands after construction of the building structure, but it may of course also contract, re- suiting in the ground level being lowered. This will result in a gap between the compensation elements and the ground, but as described with reference to the situation in Fig. 3 this is of no consequence, since the building structure then no longer depends on the support of the compensation elements.

Claims

C L A I M S
1 . A method for constructing a pile grounded building structure including the steps of:
a) arranging a plurality of piles in the ground, and
b) constructing the building structure in a manner so that a fixed connection is achieved between it and at least some of the piles,
c h a r a c t e r i z e d in that it further includes the following steps to be performed before step b):
c) calculating the expected area weight of the building structure and the resulting compressive force oD affecting material underneath the building structure during construction thereof,
d) calculating the breaking strength oB of the building structure, e) calculating the expected maximum soil uplift EG of the ground, f) providing compensation elements having:
- a compressive strength oc, which is larger than the compressive force oD of the building structure and smaller than the breaking strength oB of the building structure, and
- a maximum strain EC, which is bigger than the expected maximum soil uplift EG of the ground,
g) arranging the compensation elements on the ground , so that they cover the area to be covered by the building structure substantially entirely.
2. A method according to claim 1 , where the building structure is made from concrete by in situ casting.
3. A method according to claim 2, where step g) further includes ar- ranging one or more cover element(s) on top of the compensation elements.
4. A method according to any of the preceding claims, where the compensation elements are lamella elements made from mineral wool, which, in step g), are laid close to one another with the primary orientation of the mineral wool fibres of the lamella elements being approximately vertical.
5. A method according to any of the preceding claims, where the compensation elements are laid in a bond pattern and where the cover elements, if any, are laid so that at least some of the joints between them are not directly above parallel joints between compensation elements.
6. A method according to any of the preceding claims, where spacers for holding concrete reinforcement are arranged on at least some of the compensation elements or cover elements, if any.
7. A construction comprising a pile grounded building structure, where at least some of the piles are fixed in the building structure,
c h a r a c t e r i z e d in that
compensation elements are arranged between the ground and the building structure, so that they cover the area covered by the building struc- ture substantially entirely, and
that the compensation elements have a compressive strength oc, which is larger than the compressive force oD resulting from the area weight of the building structure and smaller than the breaking strength os of the building structure, and a maximum strain EC, which is bigger than the ex- pected maximum soil uplift EG of the ground.
8. A construction according to claim 7, where, in an initial state, the space present between the building structure and the ground is filled substantially entirely.
9. A construction according to claim 7 or 8, where the building struc- ture is made from in situ concrete.
10. A construction according to any of claims 7-9, where the building structure includes a ground deck and/or where upper parts of at least some of the piles project over the ground.
1 1 . A construction according to any of claims 7-10, further including one or more cover element(s) arranged on top of the compensation elements.
12. A construction according to any of claims 7-1 1 , where the compensation elements are lamella elements made from mineral wool, preferably having a density of 30-75 kg/m3, for stone wool 50-75 kg/m3, and arranged with a primary orientation of the mineral wool fibres approximately vertically.
13. A construction according to claim 12, where the height of the lamella elements is 50-500 mm, preferably 100-300 mm, the width of the lamella elements is 50-600 mm, and the length of the lamella elements is 1500- 2500 mm, the height being the dimension, which is substantially parallel to the primary orientation of the mineral wool fibres and substantially vertical in the laid out state.
14. A construction according to any of claims 7-13, where at least one compensation element includes a weakening zone allowing it to collapse wholly or partially.
15. A construction according to any of claims 7-14, where at least one compensation element comprises an outer shell and an inner lumen filled with a fluid, said outer shell allowing at least some of the fluid to escape when the compensation element is exposed to a pressure larger than the compressive force oD resulting from the weight of the building structure.
EP13712677.7A 2012-03-29 2013-03-22 A pile grounded construction and a method for making such a construction Not-in-force EP2831343B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
EP13712677.7A EP2831343B1 (en) 2012-03-29 2013-03-22 A pile grounded construction and a method for making such a construction

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
EP12162113 2012-03-29
PCT/DK2013/050084 WO2013143544A2 (en) 2012-03-29 2013-03-22 A pile grounded construction and a method for making such a construction
EP13712677.7A EP2831343B1 (en) 2012-03-29 2013-03-22 A pile grounded construction and a method for making such a construction

Publications (2)

Publication Number Publication Date
EP2831343A2 true EP2831343A2 (en) 2015-02-04
EP2831343B1 EP2831343B1 (en) 2016-12-21

Family

ID=48013687

Family Applications (1)

Application Number Title Priority Date Filing Date
EP13712677.7A Not-in-force EP2831343B1 (en) 2012-03-29 2013-03-22 A pile grounded construction and a method for making such a construction

Country Status (3)

Country Link
EP (1) EP2831343B1 (en)
DK (1) DK2831343T3 (en)
WO (1) WO2013143544A2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6217292B2 (en) * 2013-10-03 2017-10-25 新日鐵住金株式会社 Construction method and foundation structure of foundation structure of expansive ground
JP6402027B2 (en) * 2014-12-24 2018-10-10 鹿島建設株式会社 Sedimentation countermeasure structure and construction method of settlement countermeasure structure
JP6664697B2 (en) * 2016-01-08 2020-03-13 清水建設株式会社 Foundation structure using existing piles
JP6713294B2 (en) * 2016-02-09 2020-06-24 西武ポリマ化成株式会社 Himon structure substructure
JP6630616B2 (en) * 2016-04-07 2020-01-15 鹿島建設株式会社 Pile formation method, pile

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20100275526A1 (en) * 2006-07-11 2010-11-04 Yijing Sun Building-above-land for protection of vegetation and environment
US8056299B2 (en) * 2007-03-12 2011-11-15 Mack Industries, Inc. Foundation construction for superstructures

Also Published As

Publication number Publication date
EP2831343B1 (en) 2016-12-21
WO2013143544A3 (en) 2014-01-09
DK2831343T3 (en) 2017-04-03
WO2013143544A2 (en) 2013-10-03

Similar Documents

Publication Publication Date Title
EP2831343B1 (en) A pile grounded construction and a method for making such a construction
ITBO20060414A1 (en) METHOD FOR LIFTING A BUILDING AFT.
EP0183652A2 (en) Brick panel
CA3196584A1 (en) System and method for protection of under-slab utilities from changes in soil volume
JP3213990U (en) Bridge reinforcement structure
SE2100178A1 (en) Module for a load-bearing house foundation with integrated reinforcements
CN105421477A (en) Construction method for tower crane foundation
NZ624344A (en) A seismic isolation system
CN118390534A (en) Tunnel foundation pit upper unloading pit bottom reinforcement construction method and structure
US8807876B2 (en) Method and device for supporting lightly loaded structures and pavements on highly expansive soils
EP1605112B1 (en) Method for the production of a building construction as well as formwork therefor
CN111218938A (en) Excavation construction method for foundation pit above existing tunnel
CN103015463A (en) Foundation isolation construction method for built building and isolation structure used by same
KR101744083B1 (en) Interlocked cap concrete structure and method for interlocking cap concrete structure being already constructed
US20070151173A1 (en) Method of constructing structures with seismically-isolated base
CN116988456A (en) Anti-overcharging structure for cast-in-place pile in karst area and construction method
RU2633619C1 (en) Method of strengthening foundation at reconstruction
JP7008008B2 (en) How to build piers, piers
KR100436284B1 (en) A Method for Insulating an Underground Structure and An Underground Structure With an Insulation Panel for Draining Water
CN209891239U (en) Piston type foundation support structure
CN107142974A (en) A kind of assembly type internal model and its construction method
CN223017707U (en) A building foundation reinforcement structure in heterogeneous strata
CN222990796U (en) Basement pile head waterproof structure in heterogeneous stratum
JP2874860B2 (en) Soil floor structure and method of construction
JP5257210B2 (en) Ground excavation method

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

17P Request for examination filed

Effective date: 20141014

AK Designated contracting states

Kind code of ref document: A2

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

AX Request for extension of the european patent

Extension state: BA ME

DAX Request for extension of the european patent (deleted)
GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

INTG Intention to grant announced

Effective date: 20151119

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

INTG Intention to grant announced

Effective date: 20160406

GRAJ Information related to disapproval of communication of intention to grant by the applicant or resumption of examination proceedings by the epo deleted

Free format text: ORIGINAL CODE: EPIDOSDIGR1

INTC Intention to grant announced (deleted)
GRAR Information related to intention to grant a patent recorded

Free format text: ORIGINAL CODE: EPIDOSNIGR71

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

INTG Intention to grant announced

Effective date: 20161103

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: AT

Ref legal event code: REF

Ref document number: 855633

Country of ref document: AT

Kind code of ref document: T

Effective date: 20170115

REG Reference to a national code

Ref country code: DE

Ref legal event code: R096

Ref document number: 602013015573

Country of ref document: DE

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LV

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161221

REG Reference to a national code

Ref country code: DK

Ref legal event code: T3

Effective date: 20170328

REG Reference to a national code

Ref country code: LT

Ref legal event code: MG4D

REG Reference to a national code

Ref country code: NL

Ref legal event code: MP

Effective date: 20161221

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161221

Ref country code: LT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161221

Ref country code: NO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20170321

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20170322

REG Reference to a national code

Ref country code: AT

Ref legal event code: MK05

Ref document number: 855633

Country of ref document: AT

Kind code of ref document: T

Effective date: 20161221

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: FI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161221

Ref country code: HR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161221

Ref country code: RS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161221

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: NL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161221

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20170421

Ref country code: SK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161221

Ref country code: CZ

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161221

Ref country code: EE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161221

Ref country code: RO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161221

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: PT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20170421

Ref country code: BG

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20170321

Ref country code: PL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161221

Ref country code: AT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161221

Ref country code: IT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161221

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161221

Ref country code: BE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161221

Ref country code: SM

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161221

REG Reference to a national code

Ref country code: DE

Ref legal event code: R097

Ref document number: 602013015573

Country of ref document: DE

REG Reference to a national code

Ref country code: DE

Ref legal event code: R119

Ref document number: 602013015573

Country of ref document: DE

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

26N No opposition filed

Effective date: 20170922

GBPC Gb: european patent ceased through non-payment of renewal fee

Effective date: 20170322

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MC

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161221

REG Reference to a national code

Ref country code: IE

Ref legal event code: MM4A

REG Reference to a national code

Ref country code: FR

Ref legal event code: ST

Effective date: 20171130

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: FR

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20170331

Ref country code: LU

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20170322

Ref country code: DE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20171003

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20170322

Ref country code: SI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161221

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20170331

Ref country code: LI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20170331

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20170322

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DK

Payment date: 20180326

Year of fee payment: 6

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20170322

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: HU

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO

Effective date: 20130322

REG Reference to a national code

Ref country code: DK

Ref legal event code: EBP

Effective date: 20190331

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: CY

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161221

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161221

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: TR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161221

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: DK

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20190331

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: AL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20161221