EP2394018B1 - Landing string assembly - Google Patents
Landing string assembly Download PDFInfo
- Publication number
- EP2394018B1 EP2394018B1 EP10700891.4A EP10700891A EP2394018B1 EP 2394018 B1 EP2394018 B1 EP 2394018B1 EP 10700891 A EP10700891 A EP 10700891A EP 2394018 B1 EP2394018 B1 EP 2394018B1
- Authority
- EP
- European Patent Office
- Prior art keywords
- assembly
- landing string
- pump
- wellhead
- string assembly
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Not-in-force
Links
- 239000012530 fluid Substances 0.000 claims description 29
- 238000012360 testing method Methods 0.000 claims description 16
- 238000000034 method Methods 0.000 claims description 13
- 230000008878 coupling Effects 0.000 claims description 3
- 238000010168 coupling process Methods 0.000 claims description 3
- 238000005859 coupling reaction Methods 0.000 claims description 3
- 238000004519 manufacturing process Methods 0.000 description 14
- 238000005553 drilling Methods 0.000 description 9
- 238000005086 pumping Methods 0.000 description 9
- 230000015572 biosynthetic process Effects 0.000 description 8
- 238000005755 formation reaction Methods 0.000 description 8
- 229930195733 hydrocarbon Natural products 0.000 description 8
- 239000004215 Carbon black (E152) Substances 0.000 description 7
- 150000002430 hydrocarbons Chemical class 0.000 description 7
- 238000009434 installation Methods 0.000 description 4
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 4
- 238000004458 analytical method Methods 0.000 description 2
- 238000004891 communication Methods 0.000 description 2
- 238000010276 construction Methods 0.000 description 2
- 238000007667 floating Methods 0.000 description 2
- 230000002706 hydrostatic effect Effects 0.000 description 2
- 230000032683 aging Effects 0.000 description 1
- 238000009844 basic oxygen steelmaking Methods 0.000 description 1
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 238000007405 data analysis Methods 0.000 description 1
- 238000013480 data collection Methods 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 230000002349 favourable effect Effects 0.000 description 1
- 125000001183 hydrocarbyl group Chemical group 0.000 description 1
- 238000002347 injection Methods 0.000 description 1
- 239000007924 injection Substances 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012544 monitoring process Methods 0.000 description 1
- 230000008569 process Effects 0.000 description 1
- 230000000750 progressive effect Effects 0.000 description 1
- 230000008439 repair process Effects 0.000 description 1
- 238000005070 sampling Methods 0.000 description 1
- 238000007789 sealing Methods 0.000 description 1
- 230000000638 stimulation Effects 0.000 description 1
- 239000000725 suspension Substances 0.000 description 1
- 230000035899 viability Effects 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21B—EARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B33/00—Sealing or packing boreholes or wells
- E21B33/02—Surface sealing or packing
- E21B33/03—Well heads; Setting-up thereof
- E21B33/035—Well heads; Setting-up thereof specially adapted for underwater installations
- E21B33/038—Connectors used on well heads, e.g. for connecting blow-out preventer and riser
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21B—EARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B21/00—Methods or apparatus for flushing boreholes, e.g. by use of exhaust air from motor
- E21B21/001—Methods or apparatus for flushing boreholes, e.g. by use of exhaust air from motor specially adapted for underwater drilling
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21B—EARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B33/00—Sealing or packing boreholes or wells
- E21B33/02—Surface sealing or packing
- E21B33/03—Well heads; Setting-up thereof
- E21B33/035—Well heads; Setting-up thereof specially adapted for underwater installations
- E21B33/0355—Control systems, e.g. hydraulic, pneumatic, electric, acoustic, for submerged well heads
Definitions
- the present invention relates to a landing string assembly, and in particular, but not exclusively, to a landing string assembly for use in exploration and appraisal well operations.
- offshore wells are drilled from specialised platforms, such as floating or semi-submersible drilling rigs, into the earth to intercept hydrocarbon bearing formations or reservoirs.
- a marine riser is installed between the drilling platform and a subsea wellhead unit, and a drill string extends through the marine riser to drill the well from the wellhead and into the earth.
- casing As a wellbore is advanced into the earth it is supported and sealed, in stages, by strings of threaded tubulars known as casing. This is typically achieved by drilling to a first depth, retrieving the drill string, running in a casing string and cementing this in place, and then introducing the drill string back into the cased bore to advance the bore to a second depth. This process is repeated until the required total depth is achieved to intercept a hydrocarbon production zone.
- the resulting well consists of a number of concentric casing tubing strings cemented within the wellbore.
- BOP subsea blow out preventor
- well completion infrastructure and apparatus are installed, such as production tubing, production Xmas trees, manifolds and the like to fully commission the well and accommodate production of hydrocarbons.
- the early stages of wellbore construction, prior to installation of a completion, may form an exploration and appraisal stage, which focuses on data collection and analysis of, for example, pressure, temperature and flow data, and the proper sampling of fluids and their analysis to determine the characteristics and commercial viability of the well or reservoir. With the increased interest in proving oil and gas reserves, this area of appraisal well testing is receiving more focus and interest.
- Offshore exploration and appraisal wells are often flow tested by flowing reservoir fluid from the subterranean reservoir formation to the surface via a threaded tubing string which is run into the cased wellbore.
- This tubing string which is usually temporary, contains a number of elements or “tools” that allows the flow to be controlled and reservoir data to be collected.
- the element of this tubing string which extends from the seabed up to the drilling rig is conventionally known as the landing string.
- the landing string is contained within the marine riser and the drilling BOP, and the tubing through which the reservoir fluid will be produced as part of the well appraisal is landed in the wellhead using a locating device known as the tubing hanger.
- the tubing hanger typically represents the lowermost part of the subsea landing string.
- the landing string in the arrangement described above therefore provides a temporary flow path from the well for appraisal operations, prior to commissioning of the well for full production via a permanent completion.
- the appraisal operation does not present favourable results then the well may be abandoned.
- the landing string configuration described above can also be used to flow production wells until they have "cleaned-up" (i.e. reached close to their optimum flow performance) prior to suspension and then completion using, for example, a standard vertical-type subsea production Xmas tree.
- the flow rate from a newly constructed exploration and appraisal well is often quite low. This may result in, for example, the flow velocity in the tubing being too low to properly clean-up the wells, and/or the clean-up time being excessive resulting a significant rig time being expanded to achieve a reasonable flow performance.
- Gas lift techniques involve pumping hydrocarbon gas down the annulus between the tubing and the casing and through a tool in the tubing (called a gas lift valve) so that the low-density hydrocarbon gas is introduced into the denser oil flowing up the tubing. This results in a less dense flowing hydrocarbon column, and lower bottom hole pressure at the reservoir giving a higher flow rate from the reservoir.
- the main problems with the gas lift especially using non-permanent facilities such as those used on an exploration and appraisal rig, are establishing sufficient gas flow to deliver to the well, and getting enough gas compression capacity to inject the gas into the well at sufficient depth.
- the pumps installed within the well at the location of the reservoir may be electrically or hydraulically powered, with power being supplied from surface level via power cables or conduits and the like.
- These power cables and conduits etc. typically extend into the earth to the depth of the in-well pumps through the annulus formed between the tubing string and the casing. This can require significant lengths of cables/conduits, often necessitating multiple cable/conduit lengths to be connected together, which introduces possible failure points within the system. Also, there is a risk that the cables/conduits could be damaged when being run into the cased wellbore.
- the tubing string may be temporarily installed in the well, and it is a requirement for the landing string to be detachable from the in-well tubing string.
- the landing string is used as a conduit for flowing the well to "clean-up" (i.e. optimise) the performance of the production well prior to installation of the subsea Xmas tree, for example.
- This disconnect may be made in the event of bad weather, operational problems or operational requirements, and so if a pump is installed in the well as described above then it would be necessary to have a breakable power connector. This is a complex piece of equipment that results in lower reliability for landing string connection and for the installed pumps.
- landing string arrangements may also be used to assist in the deployment and installation of completion infrastructure and apparatus, either temporary or permanent.
- landing string arrangements may be used to perform intervention or workover operations on an ageing well. That is, once a well has been producing for some time it may be necessary to undertake some kind of intervention work, for example to perform well inspections, repairs, stimulation or the like. When such an intervention is required, production is suspended and the well disconnected from the existing permanent production facilities.
- a landing string may be used to deploy, accommodate or facilitate intervention operations, tooling and the like.
- a landing string assembly comprising:
- the first end When in normal use, the first end may define a lower end of the landing string assembly, and the second end may define an upper end of the landing string assembly.
- a pump when in normal use, a pump is provided in combination with the landing string assembly and thus located above the position of a wellhead assembly.
- the pump is not located downhole within the well. This arrangement therefore assists to eliminate problems associated with locating a pump within a well, and accommodating power delivery and the like.
- the pump may be configured to pump fluids from a well, such as hydrocarbon fluids, water or the like produced from a subterranean formation. Alternatively, or additionally, the pump may be configured to pump fluids into a well. For example, the pump may be configured to pump water, gas or the like, or any suitable combination thereof into a well.
- the landing string assembly may be configured for temporary use.
- the landing string assembly may be retrievable.
- the landing string assembly may be configured to define or form part of a permanent well infrastructure, such as a completion.
- the landing string assembly may be adapted for use in well testing operations, production operations, intervention operations, deployment operations, well kill and abandoning operations or the like, or any suitable combination thereof.
- the landing string assembly may be configured for use in an exploration and appraisal well.
- the pump may be adapted to pump well fluids from a well through the landing string assembly and towards a surface platform for subsequent testing, analysis and the like.
- the landing string assembly may be configured for use in a production well.
- the landing string assembly may be configured for use in an injection well.
- the landing string assembly may be configured for subsea use.
- the landing string assembly may be adapted to extend through a riser, such as a marine riser.
- the landing string assembly may comprise a plurality of tubular members secured together, for example by end-to-end threaded connections, welded connections or the like.
- the pump may be mounted within a tubular member. Alternatively, or additionally, the pump may be mounted intermediate two tubular members.
- the pump may comprise a centrifugal pump, progressive cavity pump or the like.
- the pump may comprise a submersible pump.
- the pump may be configured for pumping single and/or multiphase fluids.
- the pump may be located at any location along the length of the landing string assembly, between the first and second ends. In one embodiment, the pump may be located nearer to the first end than the second end. The pump may be located adjacent the first end of the landing string assembly. This arrangement may be particularly advantageous when used in marine environments, particularly deepwater marine environments. That is, when the pump is located towards the first end, and thus the lower end of the tubing string assembly, and is configured to pump fluids from the well, a discharge side of the pump will be exposed to the hydrostatic pressure of a column of fluid above the pump within the landing string assembly. Locating the pump towards the first end of the landing string assembly will therefore maximise the pressure on the discharge side of the pump. This advantageously minimises the pressure differential across the pump (i.e., the pressure differential between the downhole formation and at the discharge side of the pump).
- the landing string assembly may be configured for use in deep water.
- the pump may be located towards the first end of the landing string assembly.
- the pump may comprise a pumping portion and a drive portion.
- the pumping portion may comprise one or more blades, vanes or the like.
- the drive portion may comprise a motor, such as an electric motor, hydraulic motor or the like.
- the drive portion may comprise a turbine or the like.
- the pumping portion and drive portion may be located adjacent each other.
- the pumping portion and the drive portion may be located remotely of each other.
- the pump may be powered from surface level.
- the pump may be configured to receive power from a surface platform.
- the pump may be electrically operated, hydraulically operated, mechanically operated or the like, or any suitable combination thereof.
- a conduit may extend along the length of the landing string assembly, between the region of the second end and the pump.
- the conduit may be arranged to communicate power for operation of the pump.
- the conduit may comprise an electrical cable.
- the conduit may comprise a fluid passage, such as a hose. In this arrangement the conduit does not extend beyond the pump and the first end. This therefore eliminates the problems associated with transmitting power downhole into a well.
- the conduit may be configured to extend externally of the landing string assembly.
- the conduit may be secured to an outer surface of the landing string assembly.
- the conduit may be configured to extend internally of the landing string assembly.
- the pump may be operated by a mechanical connection from surface level, such as from a shaft or the like.
- the first end may be adapted to be directly coupled to a wellhead assembly.
- the first end may be adapted to be connected at the location of a wellhead assembly.
- the first end may be adapted to be indirectly coupled to a wellhead assembly.
- the first end may be adapted to be coupled to an intermediate assembly, such as a tubing string, which is connected to and extends from a wellhead assembly.
- the first end may comprise a connecting arrangement adapted to permit the landing string assembly to be coupled to a wellhead assembly, either directly or indirectly.
- the connecting arrangement may comprise a releasable connecting arrangement, permitting connection and disconnection of the landing string to and from a wellhead assembly.
- the connecting arrangement may comprise a latching arrangement.
- the entire landing string assembly may be configured to be releasable from a wellhead assembly.
- At least a portion of the landing string assembly may be configured to be releasable from a wellhead assembly.
- components of the landing string assembly may be arranged to remain secured to, or forming part of, a wellhead assembly following release and removal of other components of the landing string assembly.
- the wellhead assembly may comprise a subsea wellhead assembly.
- the wellhead assembly may comprise a wellhead unit located at ground level, for example at the level of the seabed.
- the wellhead assembly may comprise a fluid control assembly, such as a blow out preventor, a Xmas tree, such as a horizontal or vertical Xmas tree, a test tree or the like.
- a fluid control assembly such as a blow out preventor, a Xmas tree, such as a horizontal or vertical Xmas tree, a test tree or the like.
- the landing string assembly may comprise components arranged to form part of a wellhead assembly.
- the landing string assembly may comprise a subsea test tree.
- the subsea test tree may be located adjacent the first end of the landing string assembly.
- the subsea test tree may be releasably secured to the landing string assembly. This arrangement may permit the subsea tree to remain fixed to the wellhead assembly after the landing string assembly has been released.
- the landing string assembly may comprise a tubing hanger arranged to support a tubing string extending into an associated well.
- the tubing hanger may be releasable from the landing string such that the tubing hanger may remain within the wellhead assembly following removal of the landing string assembly.
- the wellhead assembly may comprise a manifold or the like.
- the landing string may comprise a valve assembly.
- the landing string may comprise a valve assembly located adjacent the first end of the valve assembly.
- the valve assembly may be configured to isolate the landing string assembly in the event of disconnection from the wellhead assembly. This arrangement may conveniently prevent release of well fluids into the environment.
- the valve assembly may be located below the pump.
- the landing string may comprise a retainer valve.
- the landing string may comprise a lubricator valve assembly configured to permit the passage of tooling and the like into the landing string.
- the lubricator valve may be located more towards the second end than the first end.
- the lubricator valve may be located adjacent the second end.
- the lubricator valve may be positioned within the landing string assembly to be located below a floor of a surface-platform, when in use.
- the landing string may be configured to be coupled to a wellhead assembly comprising a blow out Preventor (BOP).
- BOP blow out Preventor
- the pump may be positioned within the landing string assembly to be located above the BOP. This may prevent damage to the pump in the event of use of the BOP.
- the second end may be coupled at the location of a surface platform.
- the second end may be coupled to fluid handling equipment, such as a surface flow head or the like.
- the surface platform may comprise a floating vessel, anchored vessel or the like.
- the landing string assembly may be adapted to communicate with a downhole tubing string extending downhole from an associated wellhead assembly.
- the downhole tubing string may comprise a production tubing string or the like.
- a flow path between a wellhead assembly and a surface platform comprising the steps of:
- the method may comprise the step of operating the pump to pump fluids to and from a downhole location, that is, a location below the wellhead assembly.
- the method may comprise the step of providing power from surface level to operate the pump.
- the method may comprise the step of detaching the landing string assembly from the wellhead assembly at a location below the pump.
- the landing string assembly according to the method of the second aspect may be provided and used in accordance with the landing string assembly according to the first aspect.
- features of the first aspect may be also assumed in this second aspect.
- a well construction comprising:
- the landing string assembly may be provided in accordance with the first aspect.
- a deepwater landing string assembly comprising:
- the deepwater landing string assembly may be configured for use in water depths of greater than 300 m (1000 feet).
- a landing string assembly according to an embodiment of the present invention is diagrammatically shown in Figure 1 .
- the landing string assembly generally identified by reference numeral 10, includes a first or lower end 12 which is secured to a wellhead assembly 14, and a second or upper end 16 which is located relative to a surface platform 18, which in the embodiment shown is a semi-submersible drilling rig 18.
- the landing string assembly 10 in the embodiment shown may be configured for many operations. However, in the present exemplary embodiment the landing string assembly 10 is for use in an exploration and appraisal well operation.
- the landing string is in fluid communication with a downhole tubing string 20 which extends through casing 22, wherein fluids from a subterranean formation 24 are carried to surface through the downhole tubing string 20 and the landing string assembly 10 for testing prior to installation of a permanent completion.
- the upper end 16 of the landing string assembly 10 is secured to a surface flow head 26 which provides control of fluids from the landing string.
- FIG. 2 An enlarged view of the landing string assembly 10 is shown in Figure 2 , reference to which is additionally made.
- the wellhead assembly 14 includes a subsea wellhead 28 which supports a blow out preventor (BOP) 30. Only the left side of the BOP is shown in Figure 2 for clarity.
- a marine riser 32 extends from the BOP 30 to surface level, and the landing string assembly 10 extends through the marine riser 30.
- the landing string assembly 10 which is generally tubular in form, includes a pump 34 located intermediate the first and second ends 14, 16, and specifically towards the first end 12, above the wellhead assembly 14.
- the pump 34 functions to artificially lift fluids through the downhole tubing 20 from the formation 24, and ultimately to surface level. The pump 34 therefore improves the flow rate of produced fluids to be tested.
- the pump 34 is an electrical submersible pump and includes an electric motor 36 arranged to drive a pumping component 38.
- the pump 34 is configured to pump multiphase fluids.
- the pump 34 is located towards the first end 12 of the landing string assembly 10. This arrangement advantageously maximises the efficiency of the pump 34 in that a discharge side 40 of the pump will be exposed to the hydrostatic pressure of a column of fluid above the pump 34 within the landing string assembly 10, which advantageously minimises the pressure differential across the pump (i.e., the pressure differential between the downhole formation 24 and at the discharge side 40 of the pump 34). For this reason, the landing string assembly 10 has advantageous application in deepwater environments.
- An umbilical 42 extends from surface level through an annulus 44 formed between the landing string assembly 10 and the marine riser 32.
- the umbilical 42 is coupled to the pump 34 and is configured to communicate electrical power for operation of the pump 34.
- the umbilical 42 may also be configured to communicate signals or the like for control, monitoring or other purposes.
- Providing the umbilical 42 to extend only to the location of the pump 34, which is positioned above the wellhead assembly 14 is particularly advantageous in that the requirement to use specialised coupling arrangements and the like to ensure robust connection and passage of the umbilical past the wellhead is eliminated.
- the landing string assembly 10 further includes a connecting arrangement in the form of a latch 46 located below the pump 34.
- the latch 46 permits release of the upper portion of the landing string assembly 10, which may be required in an emergency situation, or other need. For example, extensive deviation of the drilling rig 18 may necessitate a quick-release of the landing string assembly 10.
- the latch 46 is positioned below the location of the pump 34 and the connection of the umbilical 42, which therefore eliminates the requirement to utilise complex and often unreliable latching arrangements for disconnection of an umbilical which extends below the location of the latch 46. This provides significant advantages over known systems, such as systems which locate a pump downhole, below the wellhead, and provide umbilical power connection across the wellhead.
- the latch 46 is configured to permit reconnection of the landing string assembly 10.
- a retainer valve 48 is located above the latch 46, and below the pump 34.
- the retainer valve 48 is configured to be selectively closed to isolate the sections of the landing string assembly 10 above and below the retainer valve 48.
- the retainer valve 48 is configured to be closed to isolate the upper portion of the landing string assembly 10 in the event of a requirement to disconnect at the latch 46. This therefore retains any fluids within the upper portion of the landing string assembly 10.
- a valve arrangement in the form of a subsea test tree 50 forms part of the landing string assembly 10 and is located below the latch 46.
- the subsea test tree 50 is formed of a tubular element containing a number of valves that allows the well to be safely shut in at the seabed. The large volume of hydrocarbon may therefore be contained some way below the rig floor, for example when disconnection at the latch 46 is required.
- the subsea test tree 50 may be locked into the drilling BOP 30 by closing the BOPs pressure sealing pipe rams or the like around the upper part of the subsea test tree 50.
- a lowermost portion of the landing string assembly 10 comprises a tubing hanger 52 which functions to support the downhole tubing string 20.
- the landing string assembly 10 also includes a lubricator valve 54 towards the upper end 16 thereof, and positioned below the platform 18.
- the lubricator valve 54 allows wireline and coiled tubing tools and the like (not shown) to be introduced safely into the well.
- Various elements of the landing string assembly 10 may be remotely controlled from surface via hydraulic or electro-hydraulic umbilicals, for example. These umbilicals (not shown) may be run with the landing string assembly 10 and may be contained within the annulus 44.
- the landing string assembly is described for use in an exploration and appraisal well operation.
- the landing string assembly may be used in many operations and types of well, such as in completion operations, well clean-up operations and the like.
Description
- The present invention relates to a landing string assembly, and in particular, but not exclusively, to a landing string assembly for use in exploration and appraisal well operations.
- In the oil and gas industry, offshore wells are drilled from specialised platforms, such as floating or semi-submersible drilling rigs, into the earth to intercept hydrocarbon bearing formations or reservoirs. Typically, a marine riser is installed between the drilling platform and a subsea wellhead unit, and a drill string extends through the marine riser to drill the well from the wellhead and into the earth.
- As a wellbore is advanced into the earth it is supported and sealed, in stages, by strings of threaded tubulars known as casing. This is typically achieved by drilling to a first depth, retrieving the drill string, running in a casing string and cementing this in place, and then introducing the drill string back into the cased bore to advance the bore to a second depth. This process is repeated until the required total depth is achieved to intercept a hydrocarbon production zone. The resulting well consists of a number of concentric casing tubing strings cemented within the wellbore.
- During drilling, well control is conventionally achieved by use of a subsea blow out preventor (BOP) which is mounted on the wellhead and includes a number of valves and cutting tools which can be used to isolate the wellbore if required.
- Once the wellbore is constructed and has been appropriately tested and appraised, well completion infrastructure and apparatus are installed, such as production tubing, production Xmas trees, manifolds and the like to fully commission the well and accommodate production of hydrocarbons.
- An example of a well completion structure is given in
US Patent 6,227,300 which discloses a slimbore riser connected through the bore of a BOP to a wellhead via a tubing spool and hanger mounted on a landing string and which provides fluid communication for production fluids from the wellhead to the surface. Although this document discusses the use of pumps where there is insufficient natural lift in the well, no disclosure is made as to nature or placement of the pump. - The early stages of wellbore construction, prior to installation of a completion, may form an exploration and appraisal stage, which focuses on data collection and analysis of, for example, pressure, temperature and flow data, and the proper sampling of fluids and their analysis to determine the characteristics and commercial viability of the well or reservoir. With the increased interest in proving oil and gas reserves, this area of appraisal well testing is receiving more focus and interest.
- Offshore exploration and appraisal wells are often flow tested by flowing reservoir fluid from the subterranean reservoir formation to the surface via a threaded tubing string which is run into the cased wellbore. This tubing string, which is usually temporary, contains a number of elements or "tools" that allows the flow to be controlled and reservoir data to be collected. The element of this tubing string which extends from the seabed up to the drilling rig is conventionally known as the landing string. The landing string is contained within the marine riser and the drilling BOP, and the tubing through which the reservoir fluid will be produced as part of the well appraisal is landed in the wellhead using a locating device known as the tubing hanger. The tubing hanger typically represents the lowermost part of the subsea landing string.
- The landing string in the arrangement described above therefore provides a temporary flow path from the well for appraisal operations, prior to commissioning of the well for full production via a permanent completion. Of course, if the appraisal operation does not present favourable results then the well may be abandoned.
- The landing string configuration described above can also be used to flow production wells until they have "cleaned-up" (i.e. reached close to their optimum flow performance) prior to suspension and then completion using, for example, a standard vertical-type subsea production Xmas tree.
- However, the flow rate from a newly constructed exploration and appraisal well is often quite low. This may result in, for example, the flow velocity in the tubing being too low to properly clean-up the wells, and/or the clean-up time being excessive resulting a significant rig time being expanded to achieve a reasonable flow performance.
- To address these issues it is known in the art to improve the well flow performance by artificial lift of the flowing wells by in-well techniques. These techniques may include, for example, gas lift, pumping or the like.
- Gas lift techniques involve pumping hydrocarbon gas down the annulus between the tubing and the casing and through a tool in the tubing (called a gas lift valve) so that the low-density hydrocarbon gas is introduced into the denser oil flowing up the tubing. This results in a less dense flowing hydrocarbon column, and lower bottom hole pressure at the reservoir giving a higher flow rate from the reservoir. The main problems with the gas lift, especially using non-permanent facilities such as those used on an exploration and appraisal rig, are establishing sufficient gas flow to deliver to the well, and getting enough gas compression capacity to inject the gas into the well at sufficient depth.
- Artificial lift by pumping is achieved by installing one or more pumps as part of the in-well tubing string to function to pump the reservoir fluids to surface and thus enhance flowing performance. It is well understood in the art that for maximum improved flow performance the pumps must be located close to the producing formation.
- The pumps installed within the well at the location of the reservoir may be electrically or hydraulically powered, with power being supplied from surface level via power cables or conduits and the like. These power cables and conduits etc. typically extend into the earth to the depth of the in-well pumps through the annulus formed between the tubing string and the casing. This can require significant lengths of cables/conduits, often necessitating multiple cable/conduit lengths to be connected together, which introduces possible failure points within the system. Also, there is a risk that the cables/conduits could be damaged when being run into the cased wellbore.
- Furthermore, and as noted above, in exploration and appraisal wells the tubing string may be temporarily installed in the well, and it is a requirement for the landing string to be detachable from the in-well tubing string. This is also true of well completions where the landing string is used as a conduit for flowing the well to "clean-up" (i.e. optimise) the performance of the production well prior to installation of the subsea Xmas tree, for example. This disconnect may be made in the event of bad weather, operational problems or operational requirements, and so if a pump is installed in the well as described above then it would be necessary to have a breakable power connector. This is a complex piece of equipment that results in lower reliability for landing string connection and for the installed pumps. Known power connectors are relatively large and cause design issues when other components, such as valves and the like, need to be accommodated within the marine riser, especially when the other components must also be powered or controlled from surface. Additionally, the running of the pumps into the well results in significant additional rig time being required to run and secure the power cable/conduit.
- The above discussion is focussed mainly on the use of a landing string in appraisal well testing. However, landing string arrangements may also be used to assist in the deployment and installation of completion infrastructure and apparatus, either temporary or permanent. Furthermore, landing string arrangements may be used to perform intervention or workover operations on an ageing well. That is, once a well has been producing for some time it may be necessary to undertake some kind of intervention work, for example to perform well inspections, repairs, stimulation or the like. When such an intervention is required, production is suspended and the well disconnected from the existing permanent production facilities. A landing string may be used to deploy, accommodate or facilitate intervention operations, tooling and the like.
- According to a first aspect of the present invention there is provided a landing string assembly comprising:
- a first end adapted to be coupled to a wellhead assembly;
- a second end adapted to be located relative to a surface platform; and
- a pump mounted intermediate the first and second ends.
- When in normal use, the first end may define a lower end of the landing string assembly, and the second end may define an upper end of the landing string assembly.
- In the present invention, when in normal use, a pump is provided in combination with the landing string assembly and thus located above the position of a wellhead assembly. Thus, the pump is not located downhole within the well. This arrangement therefore assists to eliminate problems associated with locating a pump within a well, and accommodating power delivery and the like.
- The pump may be configured to pump fluids from a well, such as hydrocarbon fluids, water or the like produced from a subterranean formation. Alternatively, or additionally, the pump may be configured to pump fluids into a well. For example, the pump may be configured to pump water, gas or the like, or any suitable combination thereof into a well.
- The landing string assembly may be configured for temporary use. The landing string assembly may be retrievable. The landing string assembly may be configured to define or form part of a permanent well infrastructure, such as a completion.
- The landing string assembly may be adapted for use in well testing operations, production operations, intervention operations, deployment operations, well kill and abandoning operations or the like, or any suitable combination thereof.
- The landing string assembly may be configured for use in an exploration and appraisal well. In such a configuration the pump may be adapted to pump well fluids from a well through the landing string assembly and towards a surface platform for subsequent testing, analysis and the like.
- The landing string assembly may be configured for use in a production well. The landing string assembly may be configured for use in an injection well.
- The landing string assembly may be configured for subsea use. The landing string assembly may be adapted to extend through a riser, such as a marine riser.
- The landing string assembly may comprise a plurality of tubular members secured together, for example by end-to-end threaded connections, welded connections or the like.
- The pump may be mounted within a tubular member. Alternatively, or additionally, the pump may be mounted intermediate two tubular members.
- The pump may comprise a centrifugal pump, progressive cavity pump or the like. The pump may comprise a submersible pump. The pump may be configured for pumping single and/or multiphase fluids.
- The pump may be located at any location along the length of the landing string assembly, between the first and second ends. In one embodiment, the pump may be located nearer to the first end than the second end. The pump may be located adjacent the first end of the landing string assembly. This arrangement may be particularly advantageous when used in marine environments, particularly deepwater marine environments. That is, when the pump is located towards the first end, and thus the lower end of the tubing string assembly, and is configured to pump fluids from the well, a discharge side of the pump will be exposed to the hydrostatic pressure of a column of fluid above the pump within the landing string assembly. Locating the pump towards the first end of the landing string assembly will therefore maximise the pressure on the discharge side of the pump. This advantageously minimises the pressure differential across the pump (i.e., the pressure differential between the downhole formation and at the discharge side of the pump).
- The landing string assembly may be configured for use in deep water. In this arrangement the pump may be located towards the first end of the landing string assembly.
- The pump may comprise a pumping portion and a drive portion. The pumping portion may comprise one or more blades, vanes or the like. The drive portion may comprise a motor, such as an electric motor, hydraulic motor or the like. The drive portion may comprise a turbine or the like. The pumping portion and drive portion may be located adjacent each other. The pumping portion and the drive portion may be located remotely of each other.
- The pump may be powered from surface level. For example, the pump may be configured to receive power from a surface platform. The pump may be electrically operated, hydraulically operated, mechanically operated or the like, or any suitable combination thereof. A conduit may extend along the length of the landing string assembly, between the region of the second end and the pump. The conduit may be arranged to communicate power for operation of the pump. The conduit may comprise an electrical cable. The conduit may comprise a fluid passage, such as a hose. In this arrangement the conduit does not extend beyond the pump and the first end. This therefore eliminates the problems associated with transmitting power downhole into a well.
- The conduit may be configured to extend externally of the landing string assembly. The conduit may be secured to an outer surface of the landing string assembly.
- The conduit may be configured to extend internally of the landing string assembly.
- The pump may be operated by a mechanical connection from surface level, such as from a shaft or the like.
- The first end may be adapted to be directly coupled to a wellhead assembly. In this arrangement the first end may be adapted to be connected at the location of a wellhead assembly. Alternatively, the first end may be adapted to be indirectly coupled to a wellhead assembly. For example, the first end may be adapted to be coupled to an intermediate assembly, such as a tubing string, which is connected to and extends from a wellhead assembly.
- The first end may comprise a connecting arrangement adapted to permit the landing string assembly to be coupled to a wellhead assembly, either directly or indirectly. The connecting arrangement may comprise a releasable connecting arrangement, permitting connection and disconnection of the landing string to and from a wellhead assembly. The connecting arrangement may comprise a latching arrangement.
- The entire landing string assembly may be configured to be releasable from a wellhead assembly.
- At least a portion of the landing string assembly may be configured to be releasable from a wellhead assembly. In this arrangement, components of the landing string assembly may be arranged to remain secured to, or forming part of, a wellhead assembly following release and removal of other components of the landing string assembly.
- The wellhead assembly may comprise a subsea wellhead assembly. The wellhead assembly may comprise a wellhead unit located at ground level, for example at the level of the seabed.
- The wellhead assembly may comprise a fluid control assembly, such as a blow out preventor, a Xmas tree, such as a horizontal or vertical Xmas tree, a test tree or the like.
- The landing string assembly may comprise components arranged to form part of a wellhead assembly. For example, in one arrangement the landing string assembly may comprise a subsea test tree. The subsea test tree may be located adjacent the first end of the landing string assembly. The subsea test tree may be releasably secured to the landing string assembly. This arrangement may permit the subsea tree to remain fixed to the wellhead assembly after the landing string assembly has been released.
- The landing string assembly may comprise a tubing hanger arranged to support a tubing string extending into an associated well. The tubing hanger may be releasable from the landing string such that the tubing hanger may remain within the wellhead assembly following removal of the landing string assembly.
- The wellhead assembly may comprise a manifold or the like.
- The landing string may comprise a valve assembly. The landing string may comprise a valve assembly located adjacent the first end of the valve assembly. The valve assembly may be configured to isolate the landing string assembly in the event of disconnection from the wellhead assembly. This arrangement may conveniently prevent release of well fluids into the environment. The valve assembly may be located below the pump. The landing string may comprise a retainer valve.
- The landing string may comprise a lubricator valve assembly configured to permit the passage of tooling and the like into the landing string. The lubricator valve may be located more towards the second end than the first end. The lubricator valve may be located adjacent the second end. The lubricator valve may be positioned within the landing string assembly to be located below a floor of a surface-platform, when in use.
- The landing string may be configured to be coupled to a wellhead assembly comprising a blow out Preventor (BOP). The pump may be positioned within the landing string assembly to be located above the BOP. This may prevent damage to the pump in the event of use of the BOP.
- The second end may be coupled at the location of a surface platform. The second end may be coupled to fluid handling equipment, such as a surface flow head or the like.
- The surface platform may comprise a floating vessel, anchored vessel or the like.
- The landing string assembly may be adapted to communicate with a downhole tubing string extending downhole from an associated wellhead assembly. The downhole tubing string may comprise a production tubing string or the like.
- According to a second aspect of the present invention there is provided a method of establishing a flow path between a wellhead assembly and a surface platform, said method comprising the steps of:
- incorporating a pump intermediate first and second ends of a landing string assembly;
- coupling the first end of the landing string assembly to a wellhead assembly; and
- locating the second end of the landing string assembly relative to a surface platform.
- The method may comprise the step of operating the pump to pump fluids to and from a downhole location, that is, a location below the wellhead assembly.
- The method may comprise the step of providing power from surface level to operate the pump.
- The method may comprise the step of detaching the landing string assembly from the wellhead assembly at a location below the pump.
- The landing string assembly according to the method of the second aspect may be provided and used in accordance with the landing string assembly according to the first aspect. Thus, features of the first aspect may be also assumed in this second aspect.
- According to a third aspect of the present invention there is provided a well construction comprising:
- a wellhead assembly; and
- a landing string having a first end coupled to the wellhead assembly and a second end secured relative to a surface platform, wherein the landing string comprises a pump located intermediate the first and second ends.
- The landing string assembly may be provided in accordance with the first aspect.
- According to a fourth aspect of the present invention there is provided a deepwater landing string assembly comprising:
- a first end adapted to be coupled to a wellhead assembly;
- a second end adapted to be located relative to a surface platform; and
- a pump mounted intermediate the first and second ends.
- The deepwater landing string assembly may be configured for use in water depths of greater than 300 m (1000 feet).
- Further aspects of the present invention relate to exploration and appraisal well apparatus and methods which use a landing string assembly according to the first aspect.
- These and other aspects of the present invention will now be described, by way of example only, with reference to the accompanying drawings, in which:
-
Figure 1 is a diagrammatic representation of a landing string assembly, shown in use, in accordance with an embodiment of the present invention; and -
Figure 2 is an enlarged diagrammatic representation of a lower end of the tubing string assembly ofFigure 1 , in the region of a wellhead. - A landing string assembly according to an embodiment of the present invention is diagrammatically shown in
Figure 1 . The landing string assembly, generally identified byreference numeral 10, includes a first orlower end 12 which is secured to awellhead assembly 14, and a second orupper end 16 which is located relative to asurface platform 18, which in the embodiment shown is asemi-submersible drilling rig 18. The landingstring assembly 10 in the embodiment shown may be configured for many operations. However, in the present exemplary embodiment thelanding string assembly 10 is for use in an exploration and appraisal well operation. That is, the landing string is in fluid communication with adownhole tubing string 20 which extends throughcasing 22, wherein fluids from asubterranean formation 24 are carried to surface through thedownhole tubing string 20 and thelanding string assembly 10 for testing prior to installation of a permanent completion. Theupper end 16 of thelanding string assembly 10 is secured to asurface flow head 26 which provides control of fluids from the landing string. - An enlarged view of the
landing string assembly 10 is shown inFigure 2 , reference to which is additionally made. - The
wellhead assembly 14 includes asubsea wellhead 28 which supports a blow out preventor (BOP) 30. Only the left side of the BOP is shown inFigure 2 for clarity. Amarine riser 32 extends from theBOP 30 to surface level, and thelanding string assembly 10 extends through themarine riser 30. - The landing
string assembly 10, which is generally tubular in form, includes apump 34 located intermediate the first and second ends 14, 16, and specifically towards thefirst end 12, above thewellhead assembly 14. Thepump 34 functions to artificially lift fluids through thedownhole tubing 20 from theformation 24, and ultimately to surface level. Thepump 34 therefore improves the flow rate of produced fluids to be tested. - In the embodiment shown the
pump 34 is an electrical submersible pump and includes anelectric motor 36 arranged to drive apumping component 38. Thepump 34 is configured to pump multiphase fluids. - As noted above, the
pump 34 is located towards thefirst end 12 of thelanding string assembly 10. This arrangement advantageously maximises the efficiency of thepump 34 in that adischarge side 40 of the pump will be exposed to the hydrostatic pressure of a column of fluid above thepump 34 within the landingstring assembly 10, which advantageously minimises the pressure differential across the pump (i.e., the pressure differential between thedownhole formation 24 and at thedischarge side 40 of the pump 34). For this reason, the landingstring assembly 10 has advantageous application in deepwater environments. - An umbilical 42 extends from surface level through an
annulus 44 formed between the landingstring assembly 10 and themarine riser 32. The umbilical 42 is coupled to thepump 34 and is configured to communicate electrical power for operation of thepump 34. The umbilical 42 may also be configured to communicate signals or the like for control, monitoring or other purposes. Providing the umbilical 42 to extend only to the location of thepump 34, which is positioned above thewellhead assembly 14 is particularly advantageous in that the requirement to use specialised coupling arrangements and the like to ensure robust connection and passage of the umbilical past the wellhead is eliminated. - The landing
string assembly 10 further includes a connecting arrangement in the form of alatch 46 located below thepump 34. Thelatch 46 permits release of the upper portion of thelanding string assembly 10, which may be required in an emergency situation, or other need. For example, extensive deviation of thedrilling rig 18 may necessitate a quick-release of thelanding string assembly 10. It should be noted that thelatch 46 is positioned below the location of thepump 34 and the connection of the umbilical 42, which therefore eliminates the requirement to utilise complex and often unreliable latching arrangements for disconnection of an umbilical which extends below the location of thelatch 46. This provides significant advantages over known systems, such as systems which locate a pump downhole, below the wellhead, and provide umbilical power connection across the wellhead. - The
latch 46 is configured to permit reconnection of thelanding string assembly 10. - A
retainer valve 48 is located above thelatch 46, and below thepump 34. Theretainer valve 48 is configured to be selectively closed to isolate the sections of thelanding string assembly 10 above and below theretainer valve 48. Specifically, theretainer valve 48 is configured to be closed to isolate the upper portion of thelanding string assembly 10 in the event of a requirement to disconnect at thelatch 46. This therefore retains any fluids within the upper portion of thelanding string assembly 10. - A valve arrangement in the form of a
subsea test tree 50 forms part of thelanding string assembly 10 and is located below thelatch 46. Thesubsea test tree 50 is formed of a tubular element containing a number of valves that allows the well to be safely shut in at the seabed. The large volume of hydrocarbon may therefore be contained some way below the rig floor, for example when disconnection at thelatch 46 is required. Thesubsea test tree 50 may be locked into thedrilling BOP 30 by closing the BOPs pressure sealing pipe rams or the like around the upper part of thesubsea test tree 50. - In the embodiment shown, a lowermost portion of the
landing string assembly 10 comprises atubing hanger 52 which functions to support thedownhole tubing string 20. - The landing
string assembly 10 also includes alubricator valve 54 towards theupper end 16 thereof, and positioned below theplatform 18. Thelubricator valve 54 allows wireline and coiled tubing tools and the like (not shown) to be introduced safely into the well. - Various elements of the
landing string assembly 10 may be remotely controlled from surface via hydraulic or electro-hydraulic umbilicals, for example. These umbilicals (not shown) may be run with the landingstring assembly 10 and may be contained within theannulus 44. - It should be understood that the embodiment described herein is exemplary and that various modifications may be made thereto without departing from the scope of the invention. For example, the landing string assembly is described for use in an exploration and appraisal well operation. However, the landing string assembly may be used in many operations and types of well, such as in completion operations, well clean-up operations and the like.
Claims (15)
- A tubular landing string assembly (10) comprising:a first end (12) adapted to be coupled to a wellhead assembly (14);a second end (16) adapted to be located relative to a surface platform (18);
anda pump (34) mounted intermediate the first and second ends to pump fluid through the landing string assembly (10) between the first and second ends (12, 16) to and/or from a well. - The assembly (10) according to any preceding claim, adapted to extend through a riser (32).
- The assembly (10) according to any preceding ciaim, comprising a plurality of tubular members secured together, and optionally wherein the pump (34) is mounted at least one of within a tubular member and intermediate two tubular members.
- The assembly (10) according to any preceding claim, wherein the pump (34) is located nearer to the first end (12) than the second end (16), and/or wherein the pump (34) is located adjacent the first end (12) of the landing string assembly (10), and or wherein the pump (34) is adapted to be powered from surface level by at least one of electrical power, hydraulic power, mechanical work and pneumatic power.
- The assembly (10) according to any preceding claim, wherein the first end (12) comprises a connecting arrangement (46) adapted to permit the landing string assembly (10) to be coupled to a wellhead assembly (14), either directly or indirectly, and optionally wherein the connecting arrangement (46) comprises a releasable connecting arrangement.
- The assembly (10) according to any preceding claim, wherein at least a portion of the landing string assembly (10) is configured to be releasable from a wellhead assembly (14), and/or wherein the entire landing string assembly (10) is configured to be releasable from a wellhead assembly (14).
- The assembly (10) according to any preceding claim, wherein the wellhead assembly (10) comprises a subsea wellhead assembly.
- The assembly (10) according to any preceding claim, wherein the wellhead assembly (10) comprises a fluid control assembly, such as at least one of a blow out preventor, a Xmas tree, such as a horizontal or vertical Xmas tree and a test tree.
- The assembly (10) according to any preceding claim, comprising components arranged to form part of a wellhead assembly (14), and optionally comprising a subsea test tree (50) located adjacent the first end (12) of the landing string assembly (10), and optionally wherein the subsea test tree (50) is configured to be releasably secured to the landing string assembly (10).
- The assembly (10) according to any preceding claim, comprising a tubing hanger (52) arranged to support a tubing string (20) extending into an associated well (22), and optionally wherein the tubing hanger (52) is configured to be releasable from the landing string (10).
- The assembly (10) according to any preceding claim, comprising a valve assembly (48), wherein the valve assembly (48) is optionally:located adjacent the first end (12) of the landing string assembly (10);configured to isolate the landing string assembly (10) in the event of disconnection from the wellhead assembly (14); and/orlocated below the pump (34).
- The assembly (10) according to any preceding claim, configured to be coupled to a wellhead assembly (14) comprising a blow out Preventor (BOP) (30), wherein the pump (34) is positioned within the landing string assembly (10) to be located above the BOP (30).
- The assembly (10) according to any preceding claim, wherein the second end (16) is adapted to be coupled at the location of a surface platform (18).
- The assembly (10) according to any preceding claim, adapted to communicate with a downhole tubing string (20) extending downhole from an associated wellhead assembly (14).
- A method of establishing a flow path between a wellhead assembly (14) and a surface platform (18), said method comprising the steps of:incorporating a pump (34) intermediate first and second ends (12, 16) of a tubular landing string assembly (10);coupling the first end (12) of the landing string assembly (10) to a wellhead assembly (14);locating the second end (16) of the landing string assembly (10) relative to a surface platform (18); andoperating the pump (34) to pump fluid through the landing string assembly (10) between the first and second ends (12, 16) to and/or from a well.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
GBGB0901807.8A GB0901807D0 (en) | 2009-02-04 | 2009-02-04 | Landing string assembly |
PCT/GB2010/000067 WO2010089525A1 (en) | 2009-02-04 | 2010-01-15 | Landing string assembly |
Publications (2)
Publication Number | Publication Date |
---|---|
EP2394018A1 EP2394018A1 (en) | 2011-12-14 |
EP2394018B1 true EP2394018B1 (en) | 2014-03-05 |
Family
ID=40469558
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP10700891.4A Not-in-force EP2394018B1 (en) | 2009-02-04 | 2010-01-15 | Landing string assembly |
Country Status (6)
Country | Link |
---|---|
US (1) | US20120061090A1 (en) |
EP (1) | EP2394018B1 (en) |
AU (1) | AU2010212164A1 (en) |
CA (1) | CA2751486A1 (en) |
GB (1) | GB0901807D0 (en) |
WO (1) | WO2010089525A1 (en) |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2493172A (en) * | 2011-07-27 | 2013-01-30 | Expro North Sea Ltd | A landing string including a separation assembly |
US20130153242A1 (en) * | 2011-12-16 | 2013-06-20 | Kirk W. Flight | In-riser power generation |
CA2866280C (en) | 2012-03-09 | 2017-01-24 | Halliburton Energy Services, Inc. | Method and assembly for conveying well logging tools |
EP2909424A1 (en) | 2012-12-26 | 2015-08-26 | Halliburton Energy Services, Inc. | Method and assembly for determining landing of logging tools in a wellbore |
BR112015017212A2 (en) * | 2013-02-19 | 2017-07-11 | Halliburton Energy Services Inc | fluid flow during bottoming of profiling tools |
MX2015011528A (en) | 2013-04-19 | 2016-05-31 | Halliburton Energy Services Inc | Fluid flow during landing of logging tools in bottom hole assembly. |
GB2544872B8 (en) * | 2015-10-12 | 2020-03-04 | Schlumberger Technology Bv | Debris tolerant flexible element valve |
Family Cites Families (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4658904A (en) * | 1985-05-31 | 1987-04-21 | Schlumberger Technology Corporation | Subsea master valve for use in well testing |
US4702320A (en) * | 1986-07-31 | 1987-10-27 | Otis Engineering Corporation | Method and system for attaching and removing equipment from a wellhead |
WO1999018329A1 (en) * | 1997-10-07 | 1999-04-15 | Fmc Corporation | Slimbore subsea completion system and method |
US6102673A (en) * | 1998-03-27 | 2000-08-15 | Hydril Company | Subsea mud pump with reduced pulsation |
US6325159B1 (en) * | 1998-03-27 | 2001-12-04 | Hydril Company | Offshore drilling system |
US6499540B2 (en) * | 2000-12-06 | 2002-12-31 | Conoco, Inc. | Method for detecting a leak in a drill string valve |
BR0202248B1 (en) * | 2001-04-23 | 2014-12-09 | Schlumberger Surenco Sa | Subsea communication system and method usable with a subsea well |
US7451822B2 (en) * | 2006-05-09 | 2008-11-18 | Noble Drilling Services Inc. | Method for retrieving riser for storm evacuation |
US20080202761A1 (en) * | 2006-09-20 | 2008-08-28 | Ross John Trewhella | Method of functioning and / or monitoring temporarily installed equipment through a Tubing Hanger. |
-
2009
- 2009-02-04 GB GBGB0901807.8A patent/GB0901807D0/en not_active Ceased
-
2010
- 2010-01-15 US US13/147,370 patent/US20120061090A1/en not_active Abandoned
- 2010-01-15 EP EP10700891.4A patent/EP2394018B1/en not_active Not-in-force
- 2010-01-15 WO PCT/GB2010/000067 patent/WO2010089525A1/en active Application Filing
- 2010-01-15 AU AU2010212164A patent/AU2010212164A1/en not_active Abandoned
- 2010-01-15 CA CA2751486A patent/CA2751486A1/en not_active Abandoned
Also Published As
Publication number | Publication date |
---|---|
CA2751486A1 (en) | 2010-08-12 |
EP2394018A1 (en) | 2011-12-14 |
GB0901807D0 (en) | 2009-03-11 |
AU2010212164A1 (en) | 2011-08-18 |
US20120061090A1 (en) | 2012-03-15 |
WO2010089525A1 (en) | 2010-08-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP1192331B1 (en) | Method of deploying an electrically driven fluid transducer system in a well | |
US7677320B2 (en) | Subsea well with electrical submersible pump above downhole safety valve | |
US8689879B2 (en) | Fluid displacement methods and apparatus for hydrocarbons in subsea production tubing | |
US7640993B2 (en) | Method of deploying and powering an electrically driven in a well | |
EP2394018B1 (en) | Landing string assembly | |
US8443899B2 (en) | Function spool | |
US10435993B2 (en) | Junction isolation tool for fracking of wells with multiple laterals | |
EP2287439A1 (en) | Method of completing a well | |
US20110011596A1 (en) | Wellbore drilled and equipped for in-well rigless intervention esp | |
WO2012045771A2 (en) | Well pump installation | |
NO20191012A1 (en) | An apparatus for forming at least a part of a production system for a wellbore, and a line for and a method of performing an operation to set a cement plug in a wellbore | |
US9874065B2 (en) | Dual stripper apparatus | |
US6672390B2 (en) | Systems and methods for constructing subsea production wells | |
GB2459023A (en) | Wellhead assembly with large bore vertical tree | |
EP3314085B1 (en) | Christmas tree | |
US20110162839A1 (en) | Retrofit wellbore fluid injection system | |
CA3199779A1 (en) | Systems and methods for plugging a well | |
NO20160019A1 (en) | Device for enabling removal or installation of a Christmas tree | |
WO2018143825A1 (en) | An apparatus for forming at least a part of a production system for a wellbore, and a line for an a method of performing an operation to set a cement plug in a wellbore | |
WO2017137622A1 (en) | Device and method for enabling removal or installation of a horizontal christmas tree | |
CN114856504B (en) | Well repair system for shallow water underwater horizontal christmas tree and operation method thereof | |
WO2016106267A1 (en) | Riserless subsea well abandonment system | |
WO2005005770A1 (en) | Systems and methods for constructing subsea production wells | |
Rigg et al. | A Subsea Completion System for Deep Water | |
Anastacio et al. | MOBO–AN ALTERNATIVE TYPE OF SUBSEA BOOSTING |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
17P | Request for examination filed |
Effective date: 20110727 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK SM TR |
|
DAX | Request for extension of the european patent (deleted) | ||
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
INTG | Intention to grant announced |
Effective date: 20130820 |
|
GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK SM TR |
|
REG | Reference to a national code |
Ref country code: GB Ref legal event code: FG4D |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: EP |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: REF Ref document number: 655023 Country of ref document: AT Kind code of ref document: T Effective date: 20140315 |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: FG4D |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R096 Ref document number: 602010013940 Country of ref document: DE Effective date: 20140417 |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: MK05 Ref document number: 655023 Country of ref document: AT Kind code of ref document: T Effective date: 20140305 |
|
REG | Reference to a national code |
Ref country code: NL Ref legal event code: VDEP Effective date: 20140305 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140305 |
|
REG | Reference to a national code |
Ref country code: NO Ref legal event code: T2 Effective date: 20140305 |
|
REG | Reference to a national code |
Ref country code: LT Ref legal event code: MG4D |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: CY Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140305 Ref country code: SE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140305 Ref country code: AT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140305 Ref country code: FI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140305 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: HR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140305 Ref country code: LV Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140305 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: BG Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140605 Ref country code: RO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140305 Ref country code: NL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140305 Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140705 Ref country code: CZ Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140305 Ref country code: EE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140305 Ref country code: BE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140305 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: PL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140305 Ref country code: ES Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140305 Ref country code: SK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140305 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R097 Ref document number: 602010013940 Country of ref document: DE |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: PT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140707 |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140305 |
|
26N | No opposition filed |
Effective date: 20141208 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R097 Ref document number: 602010013940 Country of ref document: DE Effective date: 20141208 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140305 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140305 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R119 Ref document number: 602010013940 Country of ref document: DE |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LU Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20150115 |
|
GBPC | Gb: european patent ceased through non-payment of renewal fee |
Effective date: 20150115 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MC Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140305 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20150131 Ref country code: LI Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20150131 Ref country code: DE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20150801 Ref country code: GB Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20150115 Ref country code: NO Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20150131 |
|
REG | Reference to a national code |
Ref country code: FR Ref legal event code: ST Effective date: 20150930 |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: MM4A |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: FR Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20150202 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20150115 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140606 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140305 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: HU Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO Effective date: 20100115 Ref country code: SM Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140305 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: TR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20140305 |
|