EP2309063A1 - Apparatus, system and method of extending piles into a seabed - Google Patents

Apparatus, system and method of extending piles into a seabed Download PDF

Info

Publication number
EP2309063A1
EP2309063A1 EP10180777A EP10180777A EP2309063A1 EP 2309063 A1 EP2309063 A1 EP 2309063A1 EP 10180777 A EP10180777 A EP 10180777A EP 10180777 A EP10180777 A EP 10180777A EP 2309063 A1 EP2309063 A1 EP 2309063A1
Authority
EP
European Patent Office
Prior art keywords
guiding
seabed
pile
guiding apparatus
elements
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
EP10180777A
Other languages
German (de)
French (fr)
Inventor
Torstein Alm
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kvaerner Jacket Technology AS
Original Assignee
Aker Jacket Technology AS
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Aker Jacket Technology AS filed Critical Aker Jacket Technology AS
Priority to EP11153383A priority Critical patent/EP2325398A1/en
Publication of EP2309063A1 publication Critical patent/EP2309063A1/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/04Guide devices; Guide frames

Definitions

  • the invention concerns installation of piles. More specifically, the invention concerns an apparatus and a system for installation of piles, a method of installing the apparatus and a method of installing piles into the ground.
  • the invention is of particular use for subsea applications and for installing piles into the seabed in connection with the erection offshore wind-energy power plants.
  • the state of the art includes various structures, such as slender circular columns, for supporting wind powered plants for generating electricity. When installed at sea, such plants are commonly supported by a lower truss structure, also referred to as a "jacket”, fixed to the seabed via piles or similar devices known in the art.
  • a lower truss structure also referred to as a "jacket”
  • piles or similar devices known in the art.
  • FIG 1 An example of a wind-powered plant for generating electricity is illustrated schematically in figure 1 , where a truss structure 4, commonly referred to as a "jacket", is installed on a seabed B below a body of water W via foundation piles 12, in a manner well known in the art.
  • the jacket 4 is in figure 1 shown as having main supports - or legs - 5a and diagonal struts 5b, and extends a distance above the water surface S.
  • the jacket 4 supports a circular column or tower 2, for example via a load transferring element 10, and the tower carries a wind turbine 6 having at least one turbine blade 6a.
  • the action of the wind both directly and via the rotation of the turbine, generates considerable torsion in the tower, as well as bending moments in the transition between the tower and the jacket. It is therefore of great importance that the jacket is properly and sufficiently supported on the seabed, and consequently that the piles 12 are set with the required precision and verticality.
  • piles used for this purpose may have a length of 45m, a diameter of 1.5m and a weight in air of approximately 60 tonnes.
  • the piles are extended 40m into the seabed.
  • Jackets for use in wind farms are often placed in comparatively shallow waters (e.g. 15 - 25m), and subsea operations give poor or non-existent visibility in the water. This makes the use of ROVs and divers difficult.
  • a guiding apparatus for piles to be extended into a seabed comprising a plurality of pile guiding elements interconnected by connection elements, each guiding element having respective guiding means and respective support elements for supporting the apparatus on the seabed, characterised in that the guiding means is supported by the support element via articulation means, each articulation means having a first end connected to the guiding means and a second end connected to the support element and being individually adjustable, whereby the articulation means of each guiding element are operable to ensure that the guiding apparatus may brought into a level state on an inclined or uneven seabed.
  • the guiding means may comprise a tubular element having a first central axis and the support element may comprise a frusto-conical tubular element having a second central axis, and a portion of the guiding means is adjustably extendible inside the frusto-conical tubular element by said adjustment of the articulation means.
  • the articulation means are individually and selectively adjustable, whereby the guiding means and the frusto-conical tubular element are movable with respect to one another, both in an axial direction where the first and second central axes coincide and in an articulated manner where the first and second central axes do not coincide.
  • the extent of articulation is substantially determined by the conical angle of the frusto-conical tubular element.
  • the articulation means are arranged with even spacing around the guiding element perimeter.
  • the articulation means comprise a hydraulic cylinder having a rod selectively adjustable between a retracted position and an extended position.
  • the articulation means of each guiding element are functionally interconnected, whereby each support element will adapt itself to the inclination of the seabed on which they are resting.
  • the invention comprises a rectangular pile installation frame having four pile guiding elements rigidly interconnected by connection elements.
  • a system for installation of piles to be extended into a seabed comprising a guiding apparatus having a plurality of pile guiding elements interconnected by connection elements, each guiding element having respective guiding means and respective support elements for supporting the apparatus on the seabed, said system also comprising control- and power means for connection to the guiding apparatus, characterised in that the guiding apparatus further comprises position-sensing means and inclination-sensing means operably connected via control means to the guiding elements, whereby the guiding apparatuses' horizontal and vertical positions may be adjusted and the guiding apparatus may brought into a level state on the seabed.
  • the guiding apparatus further comprises hydro-acoustic sensing means connected to a control unit, for sensing the movement and position of a pile being extended into the guiding element.
  • the guiding apparatus further comprises visual sensing means connected to a control unit, for sensing the movement and position of a pile being extended into the guiding element.
  • Each guiding apparatus preferably comprises guiding means having a longitudinal opening for monitoring the position of the pile inside the guiding apparatus.
  • the guiding apparatus preferably comprises a distance sensor for sensing the distance between a piling tool and an upper region of the guiding apparatus.
  • the pile vertical position is measured using hydro-acoustic sensing means. In one embodiment, the pile vertical position is measured using visual sensing means. In one embodiment, the distance between a piling tool and an upper region of the guiding apparatus is measured simultaneously with step c). With the invention, a large number of piles may be pre-installed in a precise and efficient manner.
  • a pile installation frame 20 comprises in this embodiment four guiding elements 24, spaced apart with equal distance to form a square structure, and interconnected by truss structures 22 and diagonal bracing 19.
  • This installation frame thus serves as an installation template, ensuring that the four piles for a given jacket are installed with the required spacing.
  • the installation frame may have a footprint of approximately 18x18m 2 and a vertical extension of about 7m.
  • a typical weight (in air) is 150 tonnes.
  • FIG 3 is an enlargement of a portion of figure 2 , showing one of the guiding elements 24.
  • Each guiding element 24 comprises a pile receptacle 25 connected to a guide funnel 27, and an adjustable support element 32.
  • the support element 32 is connected to the guide funnel 27 via a plurality of actuators 23, in the described embodiment hydraulic cylinders 23. This arrangement is shown in more detail in figure 4 , illustrating the lower portion of the guiding element 24.
  • the actuators 23 connect the support element 32 to the guide funnel 27.
  • the actuators 23 thus provide an adjustable, articulated connection between the guide funnel and the support element.
  • the support element 32 comprises a foot plate, or mud mat, 26 for placement on the seabed, and a frusto-conical (i.e. truncated cone) element 28.
  • FIG. 5a it can be seen (e.g. figure 5a ) how the guide funnel 27 extends a distance into the frusto-conical element 28, having a cone angle ⁇ C and being adjustably supported by the actuators 23.
  • the actuators which in this embodiment are hydraulic cylinders, have a first end 21 connected to the guide funnel 27 and a second end 30 connected to the support element 32, preferably the mud mat 26.
  • Figure 5b and 5c illustrate various relative vertical positions between the support element 32 and the guide funnel 27, all actuators 23 having the same the degree of actuation and the guide funnel central axis C 27 coinciding with the support element central axis C 32 .
  • the actuator 23 on the left-hand side is extended more than the actuator 23 on the left-hand side, whereby the support element and the guide funnel are pivoted (or deflected) with respect to one another, i.e. such that the central axes C 27 and C 32 are not coinciding.
  • the cone angle ⁇ C determines the maximum deflection between the central axes, i.e., in principle, ⁇ M ⁇ 2 ⁇ C .
  • the maximum deflection may be somewhat greater, due to necessary tolerances between the frusto-conical element and the guide funnel. It is apparent from the figures, however, that the maximum deflection is limited by the abutment of the guide funnel against the inner wall of the frustro-conical element.
  • the actuators serve as an articulated joint between the support element and the guide funnel
  • the support element 32 and the guide funnel 27 may be adjusted such that the support element is resting against the somewhat inclined seabed, while the guide funnel 27 extends substantially vertically.
  • the actuators on all of the guiding elements 24 in this fashion the pile installation frame 20 may be adjusted to a substantially level state on the seabed, its guide funnels 27 thereby having a vertical orientation.
  • the guiding elements may accommodate a seabed inclination of 10° and the actuators may have maximum stroke of 1.5m.
  • the actuators 23 may be hydraulic cylinders, interconnected via a subsea control unit 49 (see figure 7 ).
  • the individual actuators 23 are selectively fluidly interconnected via fluid lines 52 and a remote control unit 49 (see figure 7 ).
  • An operator may thus - based on measurements of the applicable seabed conditions, etc. - set a certain pressure in the fluid lines, common for all actuators on a given guiding element 24, whereby the respective support element 32 will be permitted to bear against the seabed surface S (having an inclination ⁇ with respect to the horizontal; see e.g. figure 5d ), while ensuring that the guide funnel 27 is substantially vertical.
  • This operation may be repeated for each guiding element, until the pile installation frame 20 has assumed a substantially level orientation.
  • each support element will automatically adapt itself to the inclination ⁇ of the seabed on which it is resting.
  • the pressures in the hydraulic lines for each guiding element 24 may be equalized in order to ensuring that all four guiding elements bear against the seabed with the substantially same force.
  • Figure 6 is a top view of the installation frame 20, showing some of the applicable instrumentation.
  • Positioning data for the pile installation frame e.g. in relation to an installation vessel, are provided by transponders 36, attached to the truss structure 22.
  • the transponders may also be provided with inclinometers.
  • a gyro 46, placed on an instrumentation platform 34, provides for high-accuracy measurement of heading and tilt data. Examples of applicable gyros are laser ring gyro and fibre-optic gyro.
  • cameras 42 and lights 42a, pan-and-tilt cameras 42', a sonar 38, and echo sounders 40 are also fitted to the guide frame.
  • the sonar may be a digital multi-frequency scanning sonar, having a 360° operations range.
  • a convenient camera configuration may be two cameras in each corner of the frame, for example having pan-and-tilt capabilities for 360° monitoring.
  • the lights may preferably be of the LED type.
  • the instrumentation platform also comprises a valve assembly, termed a Remote Control Unit (RCU) 49, the connection of which is schematically illustrated in figure 7 .
  • the RCU 49 is connected via individual lines 52 to respective hydraulic actuators 23.
  • the actuators (hydraulic cylinders) 23 around each guiding element 24 are operated through two independent systems, and the system is fully operational with one faulty system for each guiding element.
  • the RCU 49 is supplied from an umbilical 50 from a Hydraulic Power Unit (HPU) 54 on the topsides vessel 57 (see figure 8a ), platform, or similar, and is operated by electrical signals routed through a Subsea Electronic Module (SEM) 48 on the installation frame.
  • HPU Hydraulic Power Unit
  • SEM Subsea Electronic Module
  • the aforementioned gyro 46, sonar 38, echo sounder 40 and cameras and light 42, 42', are also connected to the SEM 48.
  • the topsides HPU 54 is included as an integral part of the overall control system, included in a operation container located at the installation vessel, also comprising known elements such as e.g. an umbilical reel 56.
  • the umbilical 50 may be a conventional bundle of hydraulic hoses 55a, power cables and signal cables 47.
  • Figure 15 shows an alternative embodiment of the monitoring and control system, where hydraulic lines 55a (dotted lines) connects the topsides oil reservoir 55 and HPU 54a with the subsea installation frame.
  • Power and signal lines 47 (solid lines) are via a connection plate 47a connected to matrices 70, which in turn are connected to the actuators via valve pack 69 and lines 52, as described above.
  • Figure 15 also identifies accelerometer 71, pan-and-tilt camera 42', as well as cameras 42, 42a,d, and gyro 46, sonar 38 and distance measuring units 62.
  • FIG. 11 An alternative embodiment of the instrumentation platform 34 is illustrated in figures 11 - 14 .
  • One instrumentation platform is positioned substantially in the centre of the installation frame, and one instrumentation platform is placed on or in the vicinity of each guiding element 24 (see figure 11 ), i.e. for monitoring the setting of each respective pile.
  • Each instrumentation platform 24 is in this embodiment provided with - in addition to the aforementioned instruments - multiplexer 68, a distance-measuring unit 62 (described below) and cameras 42 and lights 42a, as well as a vertical measurement camera 42b underneath the platform 34.
  • FIGs 8a and 8b are schematic representations of the installation of a pile 12 into the seabed, using the apparatus and system described above.
  • the pile 12 is lowered by a crane 58 on a surface vessel 57, while the approaching pile and its distance from the guiding element 24 is being monitored bye means of the sonar 38 or the echo sounder 40.
  • a platform e.g. a jack-up platform or similar topsides structure, may be used instead of the floating vessel 57. It is also possible to monitor the introduction of the pile into the guiding funnel 27 by visual means, such as the cameras 42, 42' (not shown in figure 8a ).
  • the operator can monitor the length of pile remaining (see figure 8b ) and thus determine the penetration depth.
  • the central sonar will observe the hammer 64 as this approaches the height for target penetration. This will give indication to when observations from other systems should be started.
  • Figures 9 and 10 illustrate further means for controlling the pile installation, more specifically the vertical position of the top of the pile.
  • a distance sensor 62 is mounted on the guide funnel 27, and through an opening 63 in the pile receptacle 25 being able to measure the distance to a defined point on the hammer 64 or follower, e.g. up to the flange 65 on the hammer (see also figures 12 and 14 ).

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

A guiding apparatus (20), system and method for piles (12) to be extended into a seabed, comprising a plurality of pile guiding elements (24) interconnected by connection elements (19, 22), each guiding element (24) having respective guiding means (27) and respective support elements (32) for supporting the apparatus on the seabed (B). The guiding means (27) is supported by the support element (32) via articulation means (23), each articulation means (23) having a first end (21) connected to the guiding means (27) and a second end (30) connected to the support element and being individually adjustable, whereby the articulation means (23) of each guiding element (24) are operable to ensure that the guiding apparatus (20) may brought into a level state on an inclined or uneven seabed.

Description

    Field of the invention
  • The invention concerns installation of piles. More specifically, the invention concerns an apparatus and a system for installation of piles, a method of installing the apparatus and a method of installing piles into the ground. The invention is of particular use for subsea applications and for installing piles into the seabed in connection with the erection offshore wind-energy power plants.
  • Background of the invention
  • The state of the art includes various structures, such as slender circular columns, for supporting wind powered plants for generating electricity. When installed at sea, such plants are commonly supported by a lower truss structure, also referred to as a "jacket", fixed to the seabed via piles or similar devices known in the art.
  • An example of a wind-powered plant for generating electricity is illustrated schematically in figure 1, where a truss structure 4, commonly referred to as a "jacket", is installed on a seabed B below a body of water W via foundation piles 12, in a manner well known in the art. The jacket 4 is in figure 1 shown as having main supports - or legs - 5a and diagonal struts 5b, and extends a distance above the water surface S.
  • The jacket 4 supports a circular column or tower 2, for example via a load transferring element 10, and the tower carries a wind turbine 6 having at least one turbine blade 6a. The action of the wind, both directly and via the rotation of the turbine, generates considerable torsion in the tower, as well as bending moments in the transition between the tower and the jacket. It is therefore of great importance that the jacket is properly and sufficiently supported on the seabed, and consequently that the piles 12 are set with the required precision and verticality.
  • It is known in the art to first install the piles in the seabed and the install the jacket on the pre-installed piles. Such pre-installation requires very high precision in order to for the jacket legs to fit precisely onto the piles. In order to ensuring that the piles are set in the correct position and inclination, it is known in the art to use various guide structures, operated either from a vessel or platform on the surface or via a subsea ROV. When the piles have been installed in the seabed, the structure (jacket) is placed on the piles, in a manner known in the art.
  • As an example, piles used for this purpose may have a length of 45m, a diameter of 1.5m and a weight in air of approximately 60 tonnes. Typically, the piles are extended 40m into the seabed. Jackets for use in wind farms are often placed in comparatively shallow waters (e.g. 15 - 25m), and subsea operations give poor or non-existent visibility in the water. This makes the use of ROVs and divers difficult.
  • It is therefore a need for a device and a method for ensuring accurate pre-installation of foundation piles, both in horizontal and vertical positions and orientations. It is also an object to provide an efficient and re-usable pile installation tool, whereby the installation time may be reduced.
  • Summary of the invention
  • It is thus according to the invention provided a guiding apparatus for piles to be extended into a seabed, comprising a plurality of pile guiding elements interconnected by connection elements, each guiding element having respective guiding means and respective support elements for supporting the apparatus on the seabed, characterised in that the guiding means is supported by the support element via articulation means, each articulation means having a first end connected to the guiding means and a second end connected to the support element and being individually adjustable, whereby the articulation means of each guiding element are operable to ensure that the guiding apparatus may brought into a level state on an inclined or uneven seabed.
  • The guiding means may comprise a tubular element having a first central axis and the support element may comprise a frusto-conical tubular element having a second central axis, and a portion of the guiding means is adjustably extendible inside the frusto-conical tubular element by said adjustment of the articulation means.
  • Preferably, the articulation means are individually and selectively adjustable, whereby the guiding means and the frusto-conical tubular element are movable with respect to one another, both in an axial direction where the first and second central axes coincide and in an articulated manner where the first and second central axes do not coincide. The extent of articulation is substantially determined by the conical angle of the frusto-conical tubular element.
  • In one embodiment, the articulation means are arranged with even spacing around the guiding element perimeter. In one embodiment, the articulation means comprise a hydraulic cylinder having a rod selectively adjustable between a retracted position and an extended position. Preferably, the articulation means of each guiding element are functionally interconnected, whereby each support element will adapt itself to the inclination of the seabed on which they are resting.
  • In one embodiment, the invention comprises a rectangular pile installation frame having four pile guiding elements rigidly interconnected by connection elements.
  • It is also according to the invention provided a system for installation of piles to be extended into a seabed, comprising a guiding apparatus having a plurality of pile guiding elements interconnected by connection elements, each guiding element having respective guiding means and respective support elements for supporting the apparatus on the seabed, said system also comprising control- and power means for connection to the guiding apparatus, characterised in that the guiding apparatus further comprises position-sensing means and inclination-sensing means operably connected via control means to the guiding elements, whereby the guiding apparatuses' horizontal and vertical positions may be adjusted and the guiding apparatus may brought into a level state on the seabed.
  • Preferably, the guiding apparatus further comprises hydro-acoustic sensing means connected to a control unit, for sensing the movement and position of a pile being extended into the guiding element. In one embodiment, the guiding apparatus further comprises visual sensing means connected to a control unit, for sensing the movement and position of a pile being extended into the guiding element.
  • Each guiding apparatus preferably comprises guiding means having a longitudinal opening for monitoring the position of the pile inside the guiding apparatus.
  • The guiding apparatus preferably comprises a distance sensor for sensing the distance between a piling tool and an upper region of the guiding apparatus.
  • It is also according to the invention provided a method of installing the guiding apparatus according to the invention, characterized by the steps of:
    1. a) deploying the guiding apparatus to the seabed below a body of water;
    2. b) sensing the inclination of said guiding apparatus on the seabed, by means of inclination-sensing means;
    3. c) selectively operating the individual articulation means on each guiding means until the guiding apparatus has reached a desired inclination with respect to the seabed.
  • It is also according to the invention provided a method of extending a pile into a seabed by means of the system according to the invention, characterized by the steps of:
    1. a) deploying the guiding apparatus to the seabed below a body of water;
    2. b) lowering the pile towards a guiding element while monitoring the distance between the pile and the guiding element;
    3. c) extending the pile into the seabed while monitoring the length of the pile rising above guiding element, until the pile has reached the desired depth in the seabed.
  • In one embodiment, the pile vertical position is measured using hydro-acoustic sensing means. In one embodiment, the pile vertical position is measured using visual sensing means. In one embodiment, the distance between a piling tool and an upper region of the guiding apparatus is measured simultaneously with step c). With the invention, a large number of piles may be pre-installed in a precise and efficient manner.
  • Brief description of the drawings
  • These and other characteristics of the invention will be clear from the following description of a preferential embodiment, given as a non-restrictive example, with reference to the attached drawings wherein:
    • Figure 1 is a schematic illustration of a wind turbine installation, comprising a jacket structure connected to piles driven into a seabed.
    • Figure 2 is a perspective view of an embodiment of the installation frame according to the invention;
    • Figure 3 is an enlargement of a portion of figure 2, showing an embodiment of the guide funnel according to the invention;
    • Figure 4 is a perspective view of a lower portion of the guide funnel according to the invention;
    • Figures 5a - 5e are schematic illustrations of the adjustable support element in various positions and orientations with respect to a guiding element of the guide funnel;
    • Figure 6 is a top view of an embodiment of the installation frame according to the invention;
    • Figure 7 is a schematic illustration of a system for monitoring the levelling of an installation frame and the installation of piles;
    • Figures 8a and 8b are schematic illustrations of an installation procedure for a pile, using an installation frame;
    • Figure 9 is a schematic illustration of a distance-measuring apparatus;
    • Figure 10 is a perspective view of a detail on an embodiment of the guide funnel;
    • Figure 11 a perspective view of an embodiment of the installation frame according to the invention;
    • Figure 12 is a top view of an embodiment of the installation frame shown in figure 11, identifying monitoring devices;
    • Figures 13 and 14 are perspective views of embodiments of an instrumentation platform; and
    • Figure 15 is a schematic illustration of a system for monitoring the levelling of an installation frame and the installation of piles.
    Detailed description of a preferential embodiment
  • An embodiment of the guiding apparatus according to the invention is illustrated in figure 2. A pile installation frame 20 comprises in this embodiment four guiding elements 24, spaced apart with equal distance to form a square structure, and interconnected by truss structures 22 and diagonal bracing 19. This installation frame thus serves as an installation template, ensuring that the four piles for a given jacket are installed with the required spacing. In a practical example, the installation frame may have a footprint of approximately 18x18m2 and a vertical extension of about 7m. A typical weight (in air) is 150 tonnes.
  • Figure 3 is an enlargement of a portion of figure 2, showing one of the guiding elements 24. Each guiding element 24 comprises a pile receptacle 25 connected to a guide funnel 27, and an adjustable support element 32. The support element 32 is connected to the guide funnel 27 via a plurality of actuators 23, in the described embodiment hydraulic cylinders 23. This arrangement is shown in more detail in figure 4, illustrating the lower portion of the guiding element 24.
  • In the illustrated embodiment, six actuators 23 (only four shown) connect the support element 32 to the guide funnel 27. The actuators 23 thus provide an adjustable, articulated connection between the guide funnel and the support element. The support element 32 comprises a foot plate, or mud mat, 26 for placement on the seabed, and a frusto-conical (i.e. truncated cone) element 28.
  • Turning now to the sectional principle sketches in figures 5a - 5e, it can be seen (e.g. figure 5a) how the guide funnel 27 extends a distance into the frusto-conical element 28, having a cone angle αC and being adjustably supported by the actuators 23. The actuators which in this embodiment are hydraulic cylinders, have a first end 21 connected to the guide funnel 27 and a second end 30 connected to the support element 32, preferably the mud mat 26.
  • Figure 5b and 5c illustrate various relative vertical positions between the support element 32 and the guide funnel 27, all actuators 23 having the same the degree of actuation and the guide funnel central axis C27 coinciding with the support element central axis C32.
  • In figures 5d and 5e, the actuator 23 on the left-hand side is extended more than the actuator 23 on the left-hand side, whereby the support element and the guide funnel are pivoted (or deflected) with respect to one another, i.e. such that the central axes C27 and C32 are not coinciding. It will be appreciated that the cone angle αC determines the maximum deflection between the central axes, i.e., in principle, αM ∼ 2αC. In a practical application the maximum deflection may be somewhat greater, due to necessary tolerances between the frusto-conical element and the guide funnel. It is apparent from the figures, however, that the maximum deflection is limited by the abutment of the guide funnel against the inner wall of the frustro-conical element.
  • Therefore, the actuators serve as an articulated joint between the support element and the guide funnel By selectively varying the stroke of the individual actuators 23 on the individual guiding element 24, the support element 32 and the guide funnel 27 may be adjusted such that the support element is resting against the somewhat inclined seabed, while the guide funnel 27 extends substantially vertically. By adjusting the actuators on all of the guiding elements 24 in this fashion, the pile installation frame 20 may be adjusted to a substantially level state on the seabed, its guide funnels 27 thereby having a vertical orientation.
  • In a practical application, the guiding elements may accommodate a seabed inclination of 10° and the actuators may have maximum stroke of 1.5m. The actuators 23 may be hydraulic cylinders, interconnected via a subsea control unit 49 (see figure 7).
  • In one embodiment, the individual actuators 23 are selectively fluidly interconnected via fluid lines 52 and a remote control unit 49 (see figure 7). An operator may thus - based on measurements of the applicable seabed conditions, etc. - set a certain pressure in the fluid lines, common for all actuators on a given guiding element 24, whereby the respective support element 32 will be permitted to bear against the seabed surface S (having an inclination β with respect to the horizontal; see e.g. figure 5d), while ensuring that the guide funnel 27 is substantially vertical. This operation may be repeated for each guiding element, until the pile installation frame 20 has assumed a substantially level orientation. Thus, each support element will automatically adapt itself to the inclination β of the seabed on which it is resting. Then, the pressures in the hydraulic lines for each guiding element 24 may be equalized in order to ensuring that all four guiding elements bear against the seabed with the substantially same force.
  • The system for installing the pile installation frame 20 and for installing the piles, will now be described with reference to figures 6 to 10.
  • Figure 6 is a top view of the installation frame 20, showing some of the applicable instrumentation. Positioning data for the pile installation frame, e.g. in relation to an installation vessel, are provided by transponders 36, attached to the truss structure 22. The transponders may also be provided with inclinometers. A gyro 46, placed on an instrumentation platform 34, provides for high-accuracy measurement of heading and tilt data. Examples of applicable gyros are laser ring gyro and fibre-optic gyro.
  • For use during the pile installation, cameras 42 and lights 42a, pan-and-tilt cameras 42', a sonar 38, and echo sounders 40 are also fitted to the guide frame. The sonar may be a digital multi-frequency scanning sonar, having a 360° operations range. A convenient camera configuration may be two cameras in each corner of the frame, for example having pan-and-tilt capabilities for 360° monitoring. The lights may preferably be of the LED type.
  • The instrumentation platform also comprises a valve assembly, termed a Remote Control Unit (RCU) 49, the connection of which is schematically illustrated in figure 7. The RCU 49 is connected via individual lines 52 to respective hydraulic actuators 23. As mentioned above, the actuators (hydraulic cylinders) 23 around each guiding element 24 are operated through two independent systems, and the system is fully operational with one faulty system for each guiding element. The RCU 49 is supplied from an umbilical 50 from a Hydraulic Power Unit (HPU) 54 on the topsides vessel 57 (see figure 8a), platform, or similar, and is operated by electrical signals routed through a Subsea Electronic Module (SEM) 48 on the installation frame. The aforementioned gyro 46, sonar 38, echo sounder 40 and cameras and light 42, 42', are also connected to the SEM 48. The topsides HPU 54 is included as an integral part of the overall control system, included in a operation container located at the installation vessel, also comprising known elements such as e.g. an umbilical reel 56. The umbilical 50 may be a conventional bundle of hydraulic hoses 55a, power cables and signal cables 47.
  • Figure 15 shows an alternative embodiment of the monitoring and control system, where hydraulic lines 55a (dotted lines) connects the topsides oil reservoir 55 and HPU 54a with the subsea installation frame. Power and signal lines 47 (solid lines) are via a connection plate 47a connected to matrices 70, which in turn are connected to the actuators via valve pack 69 and lines 52, as described above. Figure 15 also identifies accelerometer 71, pan-and-tilt camera 42', as well as cameras 42, 42a,d, and gyro 46, sonar 38 and distance measuring units 62.
  • An alternative embodiment of the instrumentation platform 34 is illustrated in figures 11 - 14. One instrumentation platform is positioned substantially in the centre of the installation frame, and one instrumentation platform is placed on or in the vicinity of each guiding element 24 (see figure 11), i.e. for monitoring the setting of each respective pile. Each instrumentation platform 24 is in this embodiment provided with - in addition to the aforementioned instruments - multiplexer 68, a distance-measuring unit 62 (described below) and cameras 42 and lights 42a, as well as a vertical measurement camera 42b underneath the platform 34.
  • With the system described above, an operator is able to:
    • Verify that the installation frame is placed on the correct position with correct heading on the seabed;
    • Monitor and verify horizontal leveling of the frame on the seabed;
    • Assist in guiding the piles into the frame funnels by monitoring the location of the pile during stabbing; and
    • Monitor and verify vertical position of the piles.
  • Using the apparatus and system described above, the typical operation sequence is thus:
    1. 1. Placing the installation frame 20 on the seabed in the correct position and orientation;
    2. 2. Adjusting the installation frame to horizontal alignment (level) through individual leveling of each guiding element 24 (i.e. each corner of the frame) and verifying horizontal position;
    3. 3. Guiding the piles 12 into the respective pile receptacle 25 on each guiding element 24;
    4. 4. Driving the foundation piles 12 using a hydraulic hammer 64 (optionally supplemented by a follower on top of the pile);
    5. 5. Observing the pile driving towards target penetration, by either visual or hydro-acoustic means;
    6. 6. Measuring the vertical position of each pile top, by either visual or hydro-acoustic means;
    7. 7. Guiding soil removal tool into the piles, and,
    8. 8. When the piles are cleaned to specified depth, retrieving the installation frame 20 to the surface.
  • Figures 8a and 8b are schematic representations of the installation of a pile 12 into the seabed, using the apparatus and system described above. In figure 8a, the pile 12 is lowered by a crane 58 on a surface vessel 57, while the approaching pile and its distance from the guiding element 24 is being monitored bye means of the sonar 38 or the echo sounder 40. A platform, e.g. a jack-up platform or similar topsides structure, may be used instead of the floating vessel 57. It is also possible to monitor the introduction of the pile into the guiding funnel 27 by visual means, such as the cameras 42, 42' (not shown in figure 8a). Using these hydro-acoustic or visual means, the operator can monitor the length of pile remaining (see figure 8b) and thus determine the penetration depth. The central sonar will observe the hammer 64 as this approaches the height for target penetration. This will give indication to when observations from other systems should be started.
  • Figures 9 and 10 illustrate further means for controlling the pile installation, more specifically the vertical position of the top of the pile.
  • In figure 9, a distance sensor 62 is mounted on the guide funnel 27, and through an opening 63 in the pile receptacle 25 being able to measure the distance to a defined point on the hammer 64 or follower, e.g. up to the flange 65 on the hammer (see also figures 12 and 14).
  • In figure 10, visual confirmation via the cameras 42, 42' is possible by a slot 67 in the guide funnel 27, combined with markings on the pile top or pile follower (indicated by horizontal stripes in the slot 67 in figure 10).

Claims (20)

  1. A guiding apparatus (20) for piles (12) to be extended into a seabed, comprising a plurality of pile guiding elements (24) interconnected by connection elements (19, 22), each guiding element (24) having respective guiding means (27) and respective support elements (32) for supporting the apparatus on the seabed (B), characterised in that
    the guiding means (27) is supported by the support element (32) via articulation means (23), each articulation means (23) having a first end (21) connected to the guiding means (27) and a second end (30) connected to the support element and being individually adjustable,
    whereby the articulation means (23) of each guiding element (24) are operable to ensure that the guiding apparatus (20) may brought into a level state on an inclined or uneven seabed.
  2. The guiding apparatus of claim 1, wherein the guiding means (27) comprises a tubular element having a first central axis (C27) and the support element (32) comprises a frusto-conical tubular element (28) having a second central axis (C32), and a portion of the guiding means (27) is adjustably extendible inside the frusto-conical tubular element (28) by said adjustment of the articulation means (23).
  3. The guiding apparatus of claim 2, wherein the articulation means (23) are individually and selectively adjustable, whereby the guiding means (27) and the frusto-conical tubular element (28) are movable with respect to one another, both in an axial direction where the first (C27) and second (C32) central axes coincide and in an articulated manner where the first (C27) and second (C32) central axes do not coincide.
  4. The guiding apparatus of claim 2 or claim 3, wherein the extent of articulation is substantially determined by the conical angle (αC) of the frusto-conical tubular element (28).
  5. The guiding apparatus of any one of claims 1 - 4, wherein the articulation means (23) are arranged with even spacing around the guiding element (24) perimeter.
  6. The guiding apparatus of any one of claims 1 - 5, wherein the articulation means (23) comprise a hydraulic cylinder having a rod selectively adjustable between a retracted position and an extended position.
  7. The guiding apparatus of any one of claims 1 - 6, wherein the articulation means (23) of each guiding element (24) are functionally interconnected, whereby each support element will adapt itself to the inclination of the seabed on which they are resting.
  8. The guiding apparatus of any one of claims 1 - 7, comprising a rectangular pile installation frame having four pile guiding elements (24) rigidly interconnected by connection elements (19, 22).
  9. A system for installation of piles (12) to be extended into a seabed (B), comprising a guiding apparatus (20) having a plurality of pile guiding elements (24) interconnected by connection elements (19, 22), each guiding element (24) having respective guiding means (27) and respective support elements (32) for supporting the apparatus on the seabed (B), said system also comprising control- and power means (54, 56) for connection to the guiding apparatus (20), characterised in that the guiding apparatus (20) further comprises position-sensing means (36) and inclination-sensing means (46) operably connected via control means (49) to the guiding elements (24), whereby the guiding elements' (24) horizontal and vertical positions may be adjusted and the guiding apparatus (20) may brought into a level state on the seabed.
  10. The system of claim 9, wherein the guiding apparatus (20) further comprises hydro-acoustic sensing means (38; 40) connected to a control unit (48), for sensing the movement and position of a pile (12) being extended into the guiding element (24).
  11. The system of claim 9 or claim 10, wherein the guiding apparatus (20) further comprises visual sensing means (42; 42') connected to a control unit (48), for sensing the movement and position of a pile (12) being extended into the guiding element (24).
  12. The system of any one of claims 9 - 11, wherein each guiding element (24) comprises guiding means (27) having a longitudinal opening (67) for monitoring the position of the pile (12) inside the guiding elements (24).
  13. The system of any one of claims 9 - 12, wherein the guiding element (24) comprises a distance sensor (62) for sensing the distance between a piling tool (64) and an upper region (25) of the guiding element (24).
  14. The system of any one of claims 9 - 13, wherein the guiding apparatus (20) comprises the guiding apparatus according to claims 1 - 7.
  15. A method of installing the guiding apparatus according to claims 1 - 8, characterized by the steps of:
    a) deploying the guiding apparatus (20) to the seabed (B) below a body of water (W);
    b) sensing the inclination of said guiding apparatus on the seabed, by means of inclination-sensing means (46);
    c) selectively operating the individual articulation means (23) on each guiding means (27) until the guiding apparatus (20) has reached a desired inclination with respect to the seabed.
  16. A method of extending a pile (12) into a seabed (B) by means of the system of claims 9 - 14, characterized by the steps of:
    a) deploying the guiding apparatus (20) to the seabed (B) below a body of water (W);
    b) lowering the pile (12) towards a guiding element (24) while monitoring the distance between the pile and the guiding element;
    c) extending the pile into the seabed while monitoring the length of the pile rising above guiding element (24), until the pile has reached the desired depth in the seabed.
  17. The method of claim 16, wherein the pile vertical position is measured using hydro-acoustic sensing means (38, 40).
  18. The method of claim 16 or claim 17, wherein the pile vertical position is measured using visual sensing means (42, 42').
  19. The method of any one of claims 16 - 18, wherein the distance between a piling tool (64) and an upper region (25) of the guiding element (24) is measured simultaneously with step c).
  20. The method of any one of claims 16 - 19, wherein the method of claim 14 is executed after step a) and before step b).
EP10180777A 2009-10-01 2010-09-28 Apparatus, system and method of extending piles into a seabed Withdrawn EP2309063A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
EP11153383A EP2325398A1 (en) 2009-10-01 2010-09-28 A system and method of extending piles into a seabed

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
NO20093082A NO20093082A1 (en) 2009-10-01 2009-10-01 Device, system and method for lining piles in a seabed

Related Child Applications (1)

Application Number Title Priority Date Filing Date
EP11153383.2 Division-Into 2011-02-04

Publications (1)

Publication Number Publication Date
EP2309063A1 true EP2309063A1 (en) 2011-04-13

Family

ID=43332821

Family Applications (2)

Application Number Title Priority Date Filing Date
EP10180777A Withdrawn EP2309063A1 (en) 2009-10-01 2010-09-28 Apparatus, system and method of extending piles into a seabed
EP11153383A Withdrawn EP2325398A1 (en) 2009-10-01 2010-09-28 A system and method of extending piles into a seabed

Family Applications After (1)

Application Number Title Priority Date Filing Date
EP11153383A Withdrawn EP2325398A1 (en) 2009-10-01 2010-09-28 A system and method of extending piles into a seabed

Country Status (2)

Country Link
EP (2) EP2309063A1 (en)
NO (1) NO20093082A1 (en)

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2492401A1 (en) * 2011-02-22 2012-08-29 GeoSea NV Device for manufacturing a foundation for a mass located at height, associated method and assembly of the device and a jack-up platform
WO2011147481A3 (en) * 2010-05-28 2012-10-18 Siemens Aktiengesellschaft Offshore foundation structure, offshore foundation and method of establishing the same
NL2007166C2 (en) * 2011-07-22 2013-01-24 Ballast Nedam Offshore B V Re-usable guiding frame.
DE102011112026A1 (en) 2011-08-31 2013-02-28 Strabag Offshore Wind Gmbh Method for installing a steel jacket foundation on a seabed by means of a pile, drilling or screw template and screw or ram template for the installation of steel jacket foundations
WO2013043055A1 (en) 2011-09-23 2013-03-28 Installer As Norwind Template
US8926226B2 (en) 2011-02-22 2015-01-06 GeoSea N.V. Device for manufacturing a foundation for a mass located at height, associated method and assembly of the device and a jack-up platform
CN104563155A (en) * 2013-10-18 2015-04-29 中国海洋石油总公司 Offshore jacket with spread foundation
WO2016005617A1 (en) * 2014-07-10 2016-01-14 Drace Infraestructuras, S.A. Autonomous anchoring method and system for foundations of offshore structures
WO2016144185A1 (en) * 2015-03-09 2016-09-15 Owec Tower As Apparatus and methods for installing a substructure
CN107119686A (en) * 2017-04-19 2017-09-01 合肥学院 A kind of basic pile sinking position-limited rack of marine intertidal wind power generating and its construction method
WO2019057827A1 (en) 2017-09-22 2019-03-28 Jan De Nul N.V. Reusable offshore installation template and use thereof
CN110832143A (en) * 2017-06-14 2020-02-21 Ihc荷兰Ie有限公司 A template and method of using the template
CN112411603A (en) * 2020-11-21 2021-02-26 南通泰胜蓝岛海洋工程有限公司 Installation and construction process of offshore wind power booster station
US20210246623A1 (en) * 2018-06-18 2021-08-12 Vallourec Deutschland Gmbh Device for verifying the bearing capacity of a pile of an offshore foundation construction
NL2025753A (en) * 2020-04-08 2021-10-27 Heerema Marine Contractors Nl Devices and methods for installing piles into the ground or seabed
CN115233679A (en) * 2022-07-19 2022-10-25 张家港江苏科技大学产业技术研究院 Underwater guide frame with high structural strength
CN116289936A (en) * 2023-02-22 2023-06-23 交通运输部广州打捞局 Offshore pile inserting construction device and construction process

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL2010375C2 (en) * 2013-02-28 2014-09-01 Ihc Sea Steel Ltd Pile driving guide.
NL2017560B1 (en) 2016-09-30 2018-04-10 Ihc Iqip Uk Ltd Pile guide comprising a base frame and a guide member
CN106695614B (en) * 2016-12-28 2019-01-11 山东大学 A kind of apparatus and method for the vertical straightening of round steel
KR102457037B1 (en) * 2021-04-21 2022-10-21 최병렬 Template structure for beforehand pile penetration and method for installation of marine substructure using it

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2054710A (en) * 1979-05-25 1981-02-18 Cjb Bearl & Wright Ltd Levelling seabed templates
NL1029056C1 (en) * 2005-05-17 2005-10-03 Pieter Den Breejen Partition wall assembly apparatus for e.g. dam or harbour wall, comprises pile post with anchor device and grip mechanism for holding wall plank or panel
GB2460172A (en) * 2008-05-24 2009-11-25 Marine Current Turbines Ltd Installation of a pile in the seabed using a guide structure
GB2467842A (en) * 2009-02-12 2010-08-18 Marine Current Turbines Ltd A submerged support structure with adjustable feet secured by piling

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2054710A (en) * 1979-05-25 1981-02-18 Cjb Bearl & Wright Ltd Levelling seabed templates
NL1029056C1 (en) * 2005-05-17 2005-10-03 Pieter Den Breejen Partition wall assembly apparatus for e.g. dam or harbour wall, comprises pile post with anchor device and grip mechanism for holding wall plank or panel
GB2460172A (en) * 2008-05-24 2009-11-25 Marine Current Turbines Ltd Installation of a pile in the seabed using a guide structure
GB2467842A (en) * 2009-02-12 2010-08-18 Marine Current Turbines Ltd A submerged support structure with adjustable feet secured by piling

Cited By (26)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2011147481A3 (en) * 2010-05-28 2012-10-18 Siemens Aktiengesellschaft Offshore foundation structure, offshore foundation and method of establishing the same
US8834071B2 (en) 2011-02-22 2014-09-16 GeoSea N.V. Device for manufacturing a foundation for a mass located at height, associated method and assembly of the device and a jack-up platform
BE1019832A4 (en) * 2011-02-22 2013-01-08 Geosea N V DEVICE FOR MANUFACTURING A FOUNDATION FOR A HIGH-FIXED MASS, RELATED METHOD AND COMPOSITION OF THE DEVICE AND A LIFTING PLATFORM.
EP2492401A1 (en) * 2011-02-22 2012-08-29 GeoSea NV Device for manufacturing a foundation for a mass located at height, associated method and assembly of the device and a jack-up platform
US8926226B2 (en) 2011-02-22 2015-01-06 GeoSea N.V. Device for manufacturing a foundation for a mass located at height, associated method and assembly of the device and a jack-up platform
NL2007166C2 (en) * 2011-07-22 2013-01-24 Ballast Nedam Offshore B V Re-usable guiding frame.
EP2565329A3 (en) * 2011-08-31 2013-05-29 STRABAG Offshore Wind GmbH Driving template for installation of steel jacket foundations on the sea bed
EP2565329A2 (en) 2011-08-31 2013-03-06 STRABAG Offshore Wind GmbH Driving template for installation of steel jacket foundations on the sea bed
DE102011112026A1 (en) 2011-08-31 2013-02-28 Strabag Offshore Wind Gmbh Method for installing a steel jacket foundation on a seabed by means of a pile, drilling or screw template and screw or ram template for the installation of steel jacket foundations
WO2013043055A1 (en) 2011-09-23 2013-03-28 Installer As Norwind Template
CN104563155A (en) * 2013-10-18 2015-04-29 中国海洋石油总公司 Offshore jacket with spread foundation
WO2016005617A1 (en) * 2014-07-10 2016-01-14 Drace Infraestructuras, S.A. Autonomous anchoring method and system for foundations of offshore structures
US10400416B2 (en) 2014-07-10 2019-09-03 Drace Infraestructuras, S.A. Autonomous anchoring method and system for foundations of offshore structures
WO2016144185A1 (en) * 2015-03-09 2016-09-15 Owec Tower As Apparatus and methods for installing a substructure
CN107636234A (en) * 2015-03-09 2018-01-26 欧威克高塔公司 The apparatus and method for installing minor structure
CN107119686A (en) * 2017-04-19 2017-09-01 合肥学院 A kind of basic pile sinking position-limited rack of marine intertidal wind power generating and its construction method
CN110832143A (en) * 2017-06-14 2020-02-21 Ihc荷兰Ie有限公司 A template and method of using the template
CN110832143B (en) * 2017-06-14 2022-04-15 Ihc荷兰Ie有限公司 Template and method for using same
WO2019057827A1 (en) 2017-09-22 2019-03-28 Jan De Nul N.V. Reusable offshore installation template and use thereof
US20210246623A1 (en) * 2018-06-18 2021-08-12 Vallourec Deutschland Gmbh Device for verifying the bearing capacity of a pile of an offshore foundation construction
NL2025753A (en) * 2020-04-08 2021-10-27 Heerema Marine Contractors Nl Devices and methods for installing piles into the ground or seabed
NL2025754A (en) * 2020-04-08 2021-10-27 Heerema Marine Contractors Nl Devices and methods for installing piles into the ground or seabed
CN112411603A (en) * 2020-11-21 2021-02-26 南通泰胜蓝岛海洋工程有限公司 Installation and construction process of offshore wind power booster station
CN115233679A (en) * 2022-07-19 2022-10-25 张家港江苏科技大学产业技术研究院 Underwater guide frame with high structural strength
CN115233679B (en) * 2022-07-19 2024-04-02 张家港江苏科技大学产业技术研究院 Underwater guide frame with high structural strength
CN116289936A (en) * 2023-02-22 2023-06-23 交通运输部广州打捞局 Offshore pile inserting construction device and construction process

Also Published As

Publication number Publication date
EP2325398A1 (en) 2011-05-25
NO20093082A1 (en) 2011-04-04

Similar Documents

Publication Publication Date Title
EP2309063A1 (en) Apparatus, system and method of extending piles into a seabed
US10100482B2 (en) Method of installing an offshore foundation and template for use in installing an offshore foundation
AU2012204091B2 (en) Method for providing a foundation for a mass located at height, and a positioning frame for performing the method
CN110709602B (en) Offshore wind turbine installation
EP2354321B1 (en) Method of providing a foundation for an elevated mass, and assembly of a jack-up platform and a framed template for carrying out the method.
JP5774158B2 (en) Installation of submerged support structure
US8834071B2 (en) Device for manufacturing a foundation for a mass located at height, associated method and assembly of the device and a jack-up platform
EP1499778B1 (en) Method and vessel for manipulating an offshore construction
AU2012202883B2 (en) Method for producing an underwater foundation element, adjustment head for an underwater foundation element and underwater working arrangement
CN111373101B (en) Coupling system, assembly of coupling system and vessel, and assembly of coupling system, sheathing pile and foundation pile
EP2766528B1 (en) Template
KR20190109748A (en) System used in crane of ship
EP3483342B1 (en) Device and method for arranging a secondary construction on an offshore primary construction
EP2574698B1 (en) Method and device for driving a multiplicity of piles into a seabed
US5988949A (en) Offshore jacket installation
EP2913439B1 (en) Device and method for arranging foundation piles in an underwater bottom
JP3790452B2 (en) Jacket structure
JP2025532311A (en) Underwater pile settlement positioning system for four-pile jacket foundation steel pipe piles in deep sea
EP3792486B1 (en) Method of offshore mounting a wind turbine
CN206873514U (en) Steel-pipe pile testing apparatus for verticality
NO20101229A1 (en) System and method of lining piles into a seabed, and method of installing the system
EP2697455B1 (en) A method of obtaining vertical alignment of a tower
KR102692391B1 (en) Modular pre-piling underwater template with independent leg structure
GB2401387A (en) Adjustable offshore wind tower foundation

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK SM TR

AX Request for extension of the european patent

Extension state: BA ME RS

17P Request for examination filed

Effective date: 20111013

RAP1 Party data changed (applicant data changed or rights of an application transferred)

Owner name: KVAERNER JACKET TECHNOLOGY AS

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN

18D Application deemed to be withdrawn

Effective date: 20130418