EP2258810A1 - Method and device for controlling co concentration in coke dry-quenching equipment - Google Patents
Method and device for controlling co concentration in coke dry-quenching equipment Download PDFInfo
- Publication number
- EP2258810A1 EP2258810A1 EP09718422A EP09718422A EP2258810A1 EP 2258810 A1 EP2258810 A1 EP 2258810A1 EP 09718422 A EP09718422 A EP 09718422A EP 09718422 A EP09718422 A EP 09718422A EP 2258810 A1 EP2258810 A1 EP 2258810A1
- Authority
- EP
- European Patent Office
- Prior art keywords
- air
- flow rate
- charging
- coke
- cooling gas
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Images
Classifications
-
- C—CHEMISTRY; METALLURGY
- C10—PETROLEUM, GAS OR COKE INDUSTRIES; TECHNICAL GASES CONTAINING CARBON MONOXIDE; FUELS; LUBRICANTS; PEAT
- C10B—DESTRUCTIVE DISTILLATION OF CARBONACEOUS MATERIALS FOR PRODUCTION OF GAS, COKE, TAR, OR SIMILAR MATERIALS
- C10B39/00—Cooling or quenching coke
- C10B39/02—Dry cooling outside the oven
Definitions
- the present invention relates to a coke dry quenching facility for cooling hot coke taken out of a coke oven, by an inert circulation gas, and more specifically to a technique of adjusting an air-blowing amount during hot coke charging in such a manner that the air-blowing amount is adjusted during a period before the hot coke charging through until completion of the charging to control a CO concentration of the circulation gas during the hot coke charging to a predetermined value or less so as to suppress a rapid increase in the CO concentration.
- a coke dry quenching facility is used for cooling of hot coke taken out of a coke oven.
- the hot coke is charged into a prechamber from a top of a quenching tower of the coke dry quenching facility, and the charged coke is cooled while falling through a cooling chamber, by contact with an inert circulation gas blown from a lower side of the cooling chamber.
- the coke dry quenching facility is widely known, wherein the quenching tower comprises a prechamber, a cooling chamber, and a sloping flue between the prechamber and the cooling chamber.
- the cooling chamber has a lower portion provided with a cooling gas-blowing device for blowing a cooling gas consisting of an inert gas such as nitrogen, and a coke discharge port.
- a cooling gas-blowing device for blowing a cooling gas consisting of an inert gas such as nitrogen
- the hot coke conveyed from a coke oven is charged from a charging device into the prechamber, and the charged coke is cooled while falling through the cooling chamber, by contact with the cooling gas blown from the cooling gas-blowing device, and then discharged from the coke discharge port.
- the cooling gas heated to a high temperature and discharged from the quenching tower is introduced to a boiler to undergo heat exchange therein.
- the cooling gas discharged from the boiler is introduced to a heat exchanger and sent to the cooling gas-blowing device, by a circulation fan, so that it is blown into the cooling chamber in a circulating manner.
- Patent Document 1 discloses a technique of performing: a feedback control based on a PID (Proportional-Integral-Derivative algorithm) control process designed to compensate for a difference between preset and actual values of blowing-air flow rate, using a device for adjusting an amount of fresh air and bypass air to be blown from an air-blowing port provided between a sloping flue and a boiler; and a feedforward control based on a coke discharge amount and an actual gas concentration, in order to constantly maintain a burnable gas (CO) and an oxygen component in a circulation gas at a minimum level to maximize a sensible heat recovery amount.
- Patent Document 1 JP 2006-183058A
- the technique disclosed in the Patent Document 1 does not particularly consider the phenomenon that a CO concentration is rapidly increased after hot coke charging, and thereby it is still the case that an operator manually adjusts the CO concentration when it is rapidly increased after the coke charging, so as to reduce the CO concentration. Details thereof will be described with reference to FIG. 7 .
- FIG. 7 is a graph showing an influence of air blowing during the hot coke charging, on a CO concentration and a prechamber pressure, in the conventional technique.
- the CO concentration is a value measured at an outlet side of a heat exchanger.
- the CO concentration is increased after a short time from the coke charging.
- the amount of air to be blown from the air-blowing port provided between the sloping flue and the boiler is increased by a manual operation of an operator.
- the control is liable to lag behind an increase in the CO concentration caused by CO derived from hot coke and air entering from a charging port, just after the hot coke charging, resulting in failing to suppress an increase in the CO concentration.
- the present invention provides a CO concentration control method for a coke dry quenching facility designed to subject hot coke to heat exchange with a cooling gas consisting of an inert gas, in a quenching tower of the coke dry quenching facility, and blow CO-burning air into the cooling gas heated to a high temperature and discharged from the quenching tower, whereafter the cooling gas with the air is introduced to a boiler to recover heat therefrom, and the cooling gas cooled by and discharged from the boiler is circulated to the quenching tower.
- a cooling gas consisting of an inert gas
- the method is characterized in that it comprises: in advance of hot coke charging into the quenching tower, blowing the air at a flow rate which is increased by an air amount required for burning of CO to be increased after the coke charging, with respect to an air flow rate to be blown during a normal operation of the coke dry quenching facility; and during a subsequent period from initiation of the charging through until completion of the charging, blowing the air in the increased flow rate at an initiation timing of the charging.
- the method set forth in claim 1 is characterized in that it comprises, from 150 to 15 seconds before the initiation of the hot coke charging into the quenching tower, blowing the air at a flow rate which is increased at a rate of 10 to 95 Nm 3 /h per second with respect to the air flow rate to be blown during the normal operation.
- the present invention also provides a CO concentration control method for a coke dry quenching facility designed to subject hot coke to heat exchange with a cooling gas consisting of an inert gas, in a quenching tower of the coke dry quenching facility, and blow CO-burning air into the cooling gas heated to a high temperature and discharged from the quenching tower, whereafter the cooling gas with the air is introduced to a boiler to recover heat therefrom, and the cooling gas cooled by and discharged from the boiler is recirculated to the quenching tower.
- a cooling gas consisting of an inert gas
- the method is characterized in that it comprises: from 150 to 15 seconds before initiation of hot coke charging into the quenching tower, blowing the air at a flow rate which is increased at a rate of 10 to 95 Nm 3 /h per second with respect to an air flow rate to be blown during a normal operation of the coke dry quenching facility; and, during a subsequent period between the initiation and completion of the hot coke charging, blowing the air at a flow rate ranging from 0.7 ⁇ Q to 1.3 ⁇ Q, wherein Q is an air flow rate to be blown at an initiation timing of the hot coke charging.
- the present invention further provides a CO concentration control apparatus for a coke dry quenching facility designed to subject hot coke to heat exchange with a cooling gas consisting of an inert gas, in a quenching tower comprising a prechamber and a cooling chamber located beneath the prechamber, and blow CO-burning air into the cooling gas heated to a high temperature and discharged from the quenching tower to a gas duct, whereafter the cooling gas with the air is introduced to a boiler to recover heat therefrom, and the cooling gas cooled by and discharged from the boiler is circulated to the quenching tower.
- a cooling gas consisting of an inert gas
- the apparatus is characterized in that it comprises flow rate adjusting means operable, from 150 to 15 seconds before initiation of hot coke charging into the quenching tower, to blow the air at a flow rate which is increased at a rate of 10 to 95 Nm 3 /h per second with respect to an air flow rate to be blown during a normal operation of the coke dry quenching facility, and, during a subsequent period between the initiation and completion of the hot coke charging, to blow the air at a flow rate ranging from 0.7 ⁇ Q to 1.3 ⁇ Q, wherein Q is an air flow rate to be blown at an initiation timing of the hot coke charging.
- the CO-burning air in advance of the hot coke charging into the quenching tower, the CO-burning air is blown into the high-temperature cooling gas discharged from the quenching tower, at a flow rate which is increased by a given amount. Further, during the subsequent period from the initiation of the charging through until the completion of the charging, the air is blown at the flow rate at an initiation timing of the charging. This makes it possible to suppress an increase in CO concentration during the hot coke charging.
- a CO concentration control method and apparatus for a coke dry quenching facility of the present invention will be described based on an embodiment thereof.
- FIG. 1 is a schematic diagram showing one example of a coke dry quenching facility using the present invention.
- the coke dry quenching facility comprises a quenching tower 1 which has a prechamber 3 adapted to receive therein hot coke charged from a charging device 2 on a top of the quenching tower 1, and a cooling chamber 4 disposed beneath the prechamber 3 to cool the hot coke which is falling therethrough.
- An annular-shaped sloping flue 5 is provided between the prechamber 3 and the cooling chamber 4 to extract an after-mentioned cooling gas after being heated to a high temperature through heat exchange.
- the sloping flue 5 is connected to a gas duct 6.
- the cooling chamber 4 has a reverse conical-shaped lower portion provided with a cooling gas-blowing device 7 adapted to blow therefrom a cooling gas consisting of an inert gas such as nitrogen, and a coke discharge device 8.
- the cooling gas is supplied from a heat exchanger 9 to the cooling gas-blowing device 7.
- Hot coke conveyed from a coke oven is charged from the charging device 2 into the prechamber 3, and the charged coke is cooled while falling through the cooling chamber 4, by contact with the cooling gas blown from the cooling gas-blowing device 7, and then discharged from the coke discharge device 8. Meanwhile, the cooling gas heated to a high temperature by contact and heat exchange with the hot coke is subjected to dust removal through the gas duct 6, and then introduced into a boiler 10. In the boiler 10, the cooling gas is cooled through heat exchange. The cooling gas discharged from the boiler 10 is subjected to dust removal through a dust catcher 11 coupled to a gas outlet of the boiler 10. Then, the cooling gas is introduced to the heat exchanger 9 and sent to the cooling gas-blowing device 7, by a circulation fan 12, so that it is blown into the cooling chamber 4 in a circulating manner.
- a specific heat of the circulation gas will be lowered to cause a reduction in sensible heat recovery amount in the boiler in a subsequent stage.
- air is blown from an air-blowing port 13 into the cooling gas heated to a high temperature through the heat exchange and discharged from the quenching tower 1, on an upstream side of the boiler 10, to bum CO so as to reduce the CO concentration.
- a blowing-air flow rate is adjusted by a flow rate-adjusting valve serving as flow rate adjusting means 14.
- a rotation speed of a blower may be controllably adjusted, as shown in FIG. 6 .
- a blowing-air flow rate is adjusted before the hot coke charging into the quenching tower and during a subsequent period between initiation and completion of the hot coke charging, as described later. Then, after the completion of the charging, the blowing-air flow rate is adjusted by a feedback control based on a CO concentration,.
- FIG. 2 is a graph showing an influence of a rate of increase per second in a blowing-air flow rate, on a CO concentration and a prechamber pressure.
- the air is blown at a flow rate of ⁇ 30% with respect to an air flow rate Q to be blown at an initiation timing of the hot coke charging, i.e., at a flow rate ranging from 0.7 ⁇ Q to 1.3 ⁇ Q. This makes it possible to suppress an increase of CO concentration due to the increase in CO concentration during the hot coke charging.
- a time period of the increased blowing-air flow rate is set to an excessively large value (i.e., an initiation timing of increasing the blowing-air flow rate is set to be greater than 150 seconds before the initiation of the charging)
- a total blowing-air flow rate becomes excessively large, and O 2 in the blowing air causes burning of the coke in the prechamber to produce CO through a reduction reaction, so that the CO concentration cannot be controlled at a low level.
- FIGS. 3 to 5 illustrates an influence of the rate of increase per second in the blowing-air flow rate, on the CO concentration and the prechamber pressure
- FIG. 3 , FIG. 4 and FIG. 5 are a graph in case of setting the rate of increase per second in the blowing-air flow rate to 100 Nm 3 /h, a graph in case of setting the rate of increase per second in the blowing-air flow rate to 7 Nm 3 /h, and a graph in case of setting the rate of increase per second in the blowing-air flow rate to 10 to 95 Nm 3 /h, respectively.
- the air is blown at a flow rate ranging from 0.7 ⁇ Q to 1.3 ⁇ Q, wherein Q is an air flow rate of 10 to 95 Nm 3 /h per second to be blown before a timing of the initiation of the hot coke charging.
- Q is an air flow rate of 10 to 95 Nm 3 /h per second to be blown before a timing of the initiation of the hot coke charging.
- the blowing-air flow rate is greater than 1.3 ⁇ Q, hot gas will be blown out to an outside of the facility. This undesirably contaminates the environment and causes safety hazards.
- the blowing-air flow rate is less than 0.7 ⁇ Q, an internal pressure of the prechamber will be lowered, and thereby an outside air (ambient air) will enter from outside the facility.
Landscapes
- Chemical & Material Sciences (AREA)
- Engineering & Computer Science (AREA)
- Materials Engineering (AREA)
- Oil, Petroleum & Natural Gas (AREA)
- Organic Chemistry (AREA)
- Coke Industry (AREA)
Abstract
Description
- The present invention relates to a coke dry quenching facility for cooling hot coke taken out of a coke oven, by an inert circulation gas, and more specifically to a technique of adjusting an air-blowing amount during hot coke charging in such a manner that the air-blowing amount is adjusted during a period before the hot coke charging through until completion of the charging to control a CO concentration of the circulation gas during the hot coke charging to a predetermined value or less so as to suppress a rapid increase in the CO concentration.
- A coke dry quenching facility is used for cooling of hot coke taken out of a coke oven. The hot coke is charged into a prechamber from a top of a quenching tower of the coke dry quenching facility, and the charged coke is cooled while falling through a cooling chamber, by contact with an inert circulation gas blown from a lower side of the cooling chamber.
- The coke dry quenching facility is widely known, wherein the quenching tower comprises a prechamber, a cooling chamber, and a sloping flue between the prechamber and the cooling chamber.
- The cooling chamber has a lower portion provided with a cooling gas-blowing device for blowing a cooling gas consisting of an inert gas such as nitrogen, and a coke discharge port. The hot coke conveyed from a coke oven is charged from a charging device into the prechamber, and the charged coke is cooled while falling through the cooling chamber, by contact with the cooling gas blown from the cooling gas-blowing device, and then discharged from the coke discharge port.
The cooling gas heated to a high temperature and discharged from the quenching tower is introduced to a boiler to undergo heat exchange therein. The cooling gas discharged from the boiler is introduced to a heat exchanger and sent to the cooling gas-blowing device, by a circulation fan, so that it is blown into the cooling chamber in a circulating manner. - In an operation of the coke dry quenching facility, hot coke is charged from above the prechamber (several times per hour). Due to the hot coke charging, a CO concentration of the circulation gas (cooling gas), i.e., an internal atmosphere of the prechamber, is rapidly increased by a burnable gas (CO) generated during the hot coke charging and CO derived from the charged coke. If the operation is continued under the increased CO concentration, a specific heat of the circulation gas is lowered to cause a reduction in sensible heat recovery amount in the boiler in a subsequent stage. Thus, it is important to reduce the CO concentration. Therefore, there has been employed a technique of blowing air into the circulation gas at a position upstream of the boiler to bum CO to reduce the CO concentration.
- As a gas-concentration control method, the following
Patent Document 1 discloses a technique of performing: a feedback control based on a PID (Proportional-Integral-Derivative algorithm) control process designed to compensate for a difference between preset and actual values of blowing-air flow rate, using a device for adjusting an amount of fresh air and bypass air to be blown from an air-blowing port provided between a sloping flue and a boiler; and a feedforward control based on a coke discharge amount and an actual gas concentration, in order to constantly maintain a burnable gas (CO) and an oxygen component in a circulation gas at a minimum level to maximize a sensible heat recovery amount.
Patent Document 1:JP 2006-183058A - However, the technique disclosed in the
Patent Document 1 does not particularly consider the phenomenon that a CO concentration is rapidly increased after hot coke charging, and thereby it is still the case that an operator manually adjusts the CO concentration when it is rapidly increased after the coke charging, so as to reduce the CO concentration. Details thereof will be described with reference toFIG. 7 . -
FIG. 7 is a graph showing an influence of air blowing during the hot coke charging, on a CO concentration and a prechamber pressure, in the conventional technique. InFIG. 7 , the CO concentration is a value measured at an outlet side of a heat exchanger. - As shown in
FIG. 7 , the CO concentration is increased after a short time from the coke charging. Thus, the amount of air to be blown from the air-blowing port provided between the sloping flue and the boiler is increased by a manual operation of an operator. However, the control is liable to lag behind an increase in the CO concentration caused by CO derived from hot coke and air entering from a charging port, just after the hot coke charging, resulting in failing to suppress an increase in the CO concentration. - As above, it is extremely difficult for an operator to adjust the CO concentration to a stable and low value by adjusting a flow rate of air to be brown from the air-blowing port. Consequently, after the coke charging, a specific heat of the circulation gas is lowered due to the occurrence of an increase in the CO concentration of the circulation gas, which causes a problem a reduction in sensible heat (steam) recovery amount in the boiler provided in a subsequent stage.
- It is therefore an object of the present invention to provide a CO concentration control method and apparatus for a coke dry quenching facility, which is capable of suppressing a rapid increase in CO concentration during hot coke charging into the coke dry quenching facility.
- As set forth in the appended
claim 1, the present invention provides a CO concentration control method for a coke dry quenching facility designed to subject hot coke to heat exchange with a cooling gas consisting of an inert gas, in a quenching tower of the coke dry quenching facility, and blow CO-burning air into the cooling gas heated to a high temperature and discharged from the quenching tower, whereafter the cooling gas with the air is introduced to a boiler to recover heat therefrom, and the cooling gas cooled by and discharged from the boiler is circulated to the quenching tower. The method is characterized in that it comprises: in advance of hot coke charging into the quenching tower, blowing the air at a flow rate which is increased by an air amount required for burning of CO to be increased after the coke charging, with respect to an air flow rate to be blown during a normal operation of the coke dry quenching facility; and during a subsequent period from initiation of the charging through until completion of the charging, blowing the air in the increased flow rate at an initiation timing of the charging. - As set forth in
claim 2, the method set forth inclaim 1 is characterized in that it comprises, from 150 to 15 seconds before the initiation of the hot coke charging into the quenching tower, blowing the air at a flow rate which is increased at a rate of 10 to 95 Nm3/h per second with respect to the air flow rate to be blown during the normal operation. - As set forth in the appended
claim 3, the present invention also provides a CO concentration control method for a coke dry quenching facility designed to subject hot coke to heat exchange with a cooling gas consisting of an inert gas, in a quenching tower of the coke dry quenching facility, and blow CO-burning air into the cooling gas heated to a high temperature and discharged from the quenching tower, whereafter the cooling gas with the air is introduced to a boiler to recover heat therefrom, and the cooling gas cooled by and discharged from the boiler is recirculated to the quenching tower. The method is characterized in that it comprises: from 150 to 15 seconds before initiation of hot coke charging into the quenching tower, blowing the air at a flow rate which is increased at a rate of 10 to 95 Nm3/h per second with respect to an air flow rate to be blown during a normal operation of the coke dry quenching facility; and, during a subsequent period between the initiation and completion of the hot coke charging, blowing the air at a flow rate ranging from 0.7 × Q to 1.3 × Q, wherein Q is an air flow rate to be blown at an initiation timing of the hot coke charging. - As set forth in the appended
claim 4, the present invention further provides a CO concentration control apparatus for a coke dry quenching facility designed to subject hot coke to heat exchange with a cooling gas consisting of an inert gas, in a quenching tower comprising a prechamber and a cooling chamber located beneath the prechamber, and blow CO-burning air into the cooling gas heated to a high temperature and discharged from the quenching tower to a gas duct, whereafter the cooling gas with the air is introduced to a boiler to recover heat therefrom, and the cooling gas cooled by and discharged from the boiler is circulated to the quenching tower. The apparatus is characterized in that it comprises flow rate adjusting means operable, from 150 to 15 seconds before initiation of hot coke charging into the quenching tower, to blow the air at a flow rate which is increased at a rate of 10 to 95 Nm3/h per second with respect to an air flow rate to be blown during a normal operation of the coke dry quenching facility, and, during a subsequent period between the initiation and completion of the hot coke charging, to blow the air at a flow rate ranging from 0.7 × Q to 1.3 × Q, wherein Q is an air flow rate to be blown at an initiation timing of the hot coke charging. - In the present invention, in advance of the hot coke charging into the quenching tower, the CO-burning air is blown into the high-temperature cooling gas discharged from the quenching tower, at a flow rate which is increased by a given amount. Further, during the subsequent period from the initiation of the charging through until the completion of the charging, the air is blown at the flow rate at an initiation timing of the charging. This makes it possible to suppress an increase in CO concentration during the hot coke charging.
- A CO concentration control method and apparatus for a coke dry quenching facility of the present invention will be described based on an embodiment thereof.
-
FIG. 1 is a schematic diagram showing one example of a coke dry quenching facility using the present invention. - In
FIG. 1 , the coke dry quenching facility comprises aquenching tower 1 which has aprechamber 3 adapted to receive therein hot coke charged from acharging device 2 on a top of thequenching tower 1, and acooling chamber 4 disposed beneath theprechamber 3 to cool the hot coke which is falling therethrough. An annular-shaped sloping flue 5 is provided between theprechamber 3 and thecooling chamber 4 to extract an after-mentioned cooling gas after being heated to a high temperature through heat exchange. The slopingflue 5 is connected to agas duct 6. - The
cooling chamber 4 has a reverse conical-shaped lower portion provided with a cooling gas-blowing device 7 adapted to blow therefrom a cooling gas consisting of an inert gas such as nitrogen, and acoke discharge device 8. The cooling gas is supplied from aheat exchanger 9 to the cooling gas-blowing device 7. - Hot coke conveyed from a coke oven is charged from the
charging device 2 into theprechamber 3, and the charged coke is cooled while falling through thecooling chamber 4, by contact with the cooling gas blown from the cooling gas-blowing device 7, and then discharged from thecoke discharge device 8.
Meanwhile, the cooling gas heated to a high temperature by contact and heat exchange with the hot coke is subjected to dust removal through thegas duct 6, and then introduced into aboiler 10. In theboiler 10, the cooling gas is cooled through heat exchange. The cooling gas discharged from theboiler 10 is subjected to dust removal through adust catcher 11 coupled to a gas outlet of theboiler 10. Then, the cooling gas is introduced to theheat exchanger 9 and sent to the cooling gas-blowing device 7, by acirculation fan 12, so that it is blown into thecooling chamber 4 in a circulating manner. - In an operation of the coke dry quenching facility, if the operation is performed under a condition that a CO concentration of the circulation gas (cooling gas) is excessively increased, a specific heat of the circulation gas will be lowered to cause a reduction in sensible heat recovery amount in the boiler in a subsequent stage. Thus, in order to reduce the CO concentration, air is blown from an air-blowing
port 13 into the cooling gas heated to a high temperature through the heat exchange and discharged from thequenching tower 1, on an upstream side of theboiler 10, to bum CO so as to reduce the CO concentration. A blowing-air flow rate is adjusted by a flow rate-adjusting valve serving as flow rate adjusting means 14. In place of the flow rate-adjusting value serving as the flow rate adjusting means 14, a rotation speed of a blower may be controllably adjusted, as shown inFIG. 6 . - In the present invention, in order to suppress the rapid increase in CO concentration during the hot coke charging, a blowing-air flow rate is adjusted before the hot coke charging into the quenching tower and during a subsequent period between initiation and completion of the hot coke charging, as described later. Then, after the completion of the charging, the blowing-air flow rate is adjusted by a feedback control based on a CO concentration,.
-
FIG. 2 is a graph showing an influence of a rate of increase per second in a blowing-air flow rate, on a CO concentration and a prechamber pressure. - In
FIG. 2 , from 150 to 15 seconds before initiation of the hot coke charging into the quenching tower, air is blown at a flow rate which is increased at a rate ranging from 10 Nm3/h per second (broken line) to 95 Nm3/h per second (two-dot chain line) with respect to an air flow rate to be blown during a normal cooling operation (about 7000 to 10000 Nm3/h). - Then, when the hot coke charging is initiated after opening a cover of the prechamber, the air is blown at a flow rate of ± 30% with respect to an air flow rate Q to be blown at an initiation timing of the hot coke charging, i.e., at a flow rate ranging from 0.7 × Q to 1.3 × Q. This makes it possible to suppress an increase of CO concentration due to the increase in CO concentration during the hot coke charging.
- An initiation timing of the air blowing was analyzed by a test performed on condition that it is variously changed with respect to the initiation timing of the hot coke charging, while setting the rate of increase in the blowing-air flow rate, to a constant value (range of 10 to 95 Nm3/h per second). As a result, the following knowledge was obtained.
- If a time period of the increased blowing-air flow rate is set to an excessively large value (i.e., an initiation timing of increasing the blowing-air flow rate is set to be greater than 150 seconds before the initiation of the charging), a total blowing-air flow rate becomes excessively large, and O2 in the blowing air causes burning of the coke in the prechamber to produce CO through a reduction reaction, so that the CO concentration cannot be controlled at a low level. It was also proven that, if the time period of the increased blowing-air flow rate is set to an excessively small value (i.e., the initiation timing of increasing the blowing-air flow rate is set to be less than 15 seconds before the initiation of the charging), an amount of O2 required for burning of CO becomes deficient to preclude a possibility to control the CO concentration.
- From the above results, it has become clear that it is adequate to initiate increasing the blowing-air flow rate, from 150 to 15 seconds before the initiation of the hot coke charging.
- Further, a test was performed on condition that the rate of increase per second in the blowing-air flow rate is variously changed while increasing the blowing-air flow rate from the adequate timing (150 to 15 seconds) before the initiation of the hot coke charging.
-
FIGS. 3 to 5 illustrates an influence of the rate of increase per second in the blowing-air flow rate, on the CO concentration and the prechamber pressure, whereinFIG. 3 ,FIG. 4 andFIG. 5 are a graph in case of setting the rate of increase per second in the blowing-air flow rate to 100 Nm3/h, a graph in case of setting the rate of increase per second in the blowing-air flow rate to 7 Nm3/h, and a graph in case of setting the rate of increase per second in the blowing-air flow rate to 10 to 95 Nm3/h, respectively. - As shown in
FIG. 3 , if the blowing-air flow rate is sharply increased at a rate of 100 Nm3/h per second, a pressure fluctuation occurs in the prechamber to cause a change in pressure balancing of the entire CDQ (coke dry quenching) facility, which leads to fluctuation in amount of the circulation gas and in steam recovery amount in the boiler provided in the subsequent stage. - As shown in
FIG. 4 , conversely, if the blowing-air flow rate is gently increased at a rate of 7 Nm3/h per second, air becomes deficient with respect to CO derived from charged coke and air entering from a charging port during hot coke charging in the next cycle, which precludes a possibility to reduce the CO concentration. - A test was further performed on condition that the rate of increase per second in the blowing-air flow rate is variously changed in the range between the rates in
FIGS. 3 and4 . As a result, a stable CO concentration and a stable prechamber pressure were obtained at a rate of 10 to 95 Nm3/h per second, as shown inFIG. 5 . - During a period between initiation and completion of the hot coke charging, the air is blown at a flow rate ranging from 0.7 × Q to 1.3 × Q, wherein Q is an air flow rate of 10 to 95 Nm3/h per second to be blown before a timing of the initiation of the hot coke charging. If the blowing-air flow rate is greater than 1.3 × Q, hot gas will be blown out to an outside of the facility. This undesirably contaminates the environment and causes safety hazards. If the blowing-air flow rate is less than 0.7 × Q, an internal pressure of the prechamber will be lowered, and thereby an outside air (ambient air) will enter from outside the facility. Consequently, the entered air causes burning of coke inside the facility to produce CO through a reduction reaction, which precludes a possibility to reduce the CO concentration of the circulation gas. Therefore, it has become clear that an adequate blowing-air flow rate is in the range of 0.7 × Q to 1.3 × Q.
-
-
FIG. 1 is a schematic diagram showing one example of a coke dry quenching facility using the present invention. -
FIG. 2 is a graph showing an influence of a rate of increase per second in a blowing-air flow rate, on a CO concentration and a prechamber pressure, in the present invention. -
FIG. 3 is a graph showing an influence of the rate of increase per second in the blowing-air flow rate, on the CO concentration and the prechamber pressure, in case of setting the rate to 100 Nm3/h. -
FIG. 4 is a graph showing an influence of the rate of increase per second in the blowing-air flow rate, on the CO concentration and the prechamber pressure, in case of setting the rate to 7 Nm3/h. -
FIG. 5 is a graph showing an influence of the rate of increase per second in the blowing-air flow rate, on the CO concentration and the prechamber pressure, in case of setting the rate to 10 to 95 Nm3/h. -
FIG. 6 is a schematic diagram showing another example of the coke dry quenching facility using the present invention. -
FIG. 7 is a graph showing an influence of air blowing during the hot coke charging, on a CO concentration and a prechamber pressure, in a conventional technique. -
- 1:
- quenching tower
- 2:
- charging device
- 3:
- prechamber (PC)
- 4:
- cooling chamber
- 5:
- sloping flue
- 6:
- gas duct
- 7:
- cooling gas-blowing device
- 8:
- coke discharge device
- 9:
- heat exchanger
- 10:
- boiler
- 11:
- dust catcher
- 12:
- circulation fan
- 13:
- air-blowing port
- 14:
- flow rate adjusting means (flow rate-adjusting valve, blower)
Claims (4)
- A CO concentration control method for a coke dry quenching facility designed to subject hot coke to heat exchange with a cooling gas consisting of an inert gas, in a quenching tower of the coke dry quenching facility, and blow CO-burning air into the cooling gas heated to a high temperature and discharged from the quenching tower, whereafter the cooling gas with the air is introduced to a boiler to recover heat therefrom, and the cooling gas cooled by and discharged from the boiler is recirculated to the quenching tower, the CO concentration control method being characterized in that it comprises: in advance of hot coke charging into the quenching tower, blowing the air at a flow rate which is increased by an air amount required for burning of CO to be increased after the coke charging, with respect to an air flow rate to be blown during a normal operation of the coke dry quenching facility; and, during a subsequent period from initiation of the charging through until completion of the charging, blowing the air in the increased flow rate at an initiation timing of the charging.
- The CO concentration control method as defined in claim 1, characterized in that it comprises, from 150 to 15 seconds before the initiation of the hot coke charging into the quenching tower, blowing the air at a flow rate which is increased at a rate of 10 to 95 Nm3/h per second with respect to the air flow rate to be blown during the normal operation.
- A CO concentration control method for a coke dry quenching facility designed to subject hot coke to heat exchange with a cooling gas consisting of an inert gas, in a quenching tower of the coke dry quenching facility, and blow CO-burning air into the cooling gas heated to a high temperature and discharged from the quenching tower, whereafter the cooling gas with the air is introduced to a boiler to recover heat therefrom, and the cooling gas cooled by and discharged from the boiler is recirculated to the quenching tower, the CO concentration control method being characterized in that it comprises: from 150 to 15 seconds before initiation of hot coke charging into the quenching tower, blowing the air at a flow rate which is increased at a rate of 10 to 95 Nm3/h per second with respect to an air flow rate to be blown during a normal operation of the coke dry quenching facility; and, during a subsequent period between the initiation and completion of the hot coke charging, blowing the air at a flow rate ranging from 0.7 × Q to 1.3 × Q, wherein Q is an air flow rate to be blown at an initiation timing of the hot coke charging.
- A CO concentration control apparatus for a coke dry quenching facility designed to subject hot coke to heat exchange with a cooling gas consisting of an inert gas, in a quenching tower comprising a prechamber and a cooling chamber located beneath the prechamber, and blow CO-burning air into the cooling gas heated to a high temperature and discharged from the quenching tower to a gas duct, whereafter the cooling gas with the air is introduced to a boiler to recover heat therefrom, and the cooling gas cooled by and discharged from the boiler is circulated to the quenching tower, the CO concentration control apparatus being characterized in that it comprises flow rate adjusting means operable, from 150 to 15 seconds before initiation of hot coke charging into the quenching tower, to blow the air at a flow rate which is increased at a rate of 10 to 95 Nm3/h per second with respect to an air flow rate to be blown during a normal operation of the coke dry quenching facility, and, during a subsequent period between the initiation and completion of the hot coke charging, to blow the air at a flow rate ranging from 0.7 × Q to 1.3 × Q, wherein Q is an air flow rate to be blown at an initiation timing of the hot coke charging.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2008058217 | 2008-03-07 | ||
PCT/JP2009/054133 WO2009110535A1 (en) | 2008-03-07 | 2009-03-05 | Method and device for controlling co concentration in coke dry-quenching equipment |
Publications (2)
Publication Number | Publication Date |
---|---|
EP2258810A1 true EP2258810A1 (en) | 2010-12-08 |
EP2258810A4 EP2258810A4 (en) | 2017-02-22 |
Family
ID=41056087
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP09718422.0A Withdrawn EP2258810A4 (en) | 2008-03-07 | 2009-03-05 | Method and device for controlling co concentration in coke dry-quenching equipment |
Country Status (4)
Country | Link |
---|---|
EP (1) | EP2258810A4 (en) |
JP (1) | JP5166320B2 (en) |
TW (1) | TWI408218B (en) |
WO (1) | WO2009110535A1 (en) |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH02120392A (en) * | 1988-10-28 | 1990-05-08 | Kawasaki Steel Corp | Method for adjusting combustible component content of gas in coke dry quenching equipment |
JPH039988A (en) * | 1989-06-08 | 1991-01-17 | Nippon Steel Chem Co Ltd | Operation of coke dry quencher |
JPH03157485A (en) * | 1989-11-14 | 1991-07-05 | Sumitomo Metal Ind Ltd | Operation of dry quenching facility for coke |
JP2821985B2 (en) * | 1994-03-31 | 1998-11-05 | 住友金属工業株式会社 | Combustible gas combustion control method for coke dry fire extinguishing equipment |
JP4299841B2 (en) | 2006-03-03 | 2009-07-22 | 新日本製鐵株式会社 | Coke dry fire extinguishing method and apparatus |
-
2009
- 2009-02-26 JP JP2009044359A patent/JP5166320B2/en active Active
- 2009-03-05 EP EP09718422.0A patent/EP2258810A4/en not_active Withdrawn
- 2009-03-05 TW TW98107131A patent/TWI408218B/en active
- 2009-03-05 WO PCT/JP2009/054133 patent/WO2009110535A1/en active Application Filing
Non-Patent Citations (1)
Title |
---|
See references of WO2009110535A1 * |
Also Published As
Publication number | Publication date |
---|---|
TW201000618A (en) | 2010-01-01 |
JP5166320B2 (en) | 2013-03-21 |
TWI408218B (en) | 2013-09-11 |
JP2009235390A (en) | 2009-10-15 |
EP2258810A4 (en) | 2017-02-22 |
WO2009110535A1 (en) | 2009-09-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101513857B1 (en) | Device for securing a furnace provided with a rapid cooling and heating system operating under controlled atmosphere | |
EP2300562B1 (en) | Method for producing pulverized coal | |
US20090000267A1 (en) | System and methods for heat recovery steam generators hot purging | |
EP2586850B1 (en) | Coke dry quenching plant and method for operating same | |
JP2013525598A (en) | A method of preheating an object to be annealed in a cover-type annealing facility | |
WO2019204444A1 (en) | Roasting system having self-aligning agitator and door bearing assembly | |
CA2731885C (en) | Method for producing pulverized coal | |
EP2258810A1 (en) | Method and device for controlling co concentration in coke dry-quenching equipment | |
CN112066736B (en) | Method for baking double-hearth tubular heating furnace | |
JP4133372B2 (en) | Coke dry fire extinguishing method | |
JP3285259B2 (en) | Coke production method | |
KR100784138B1 (en) | Device for preventing dew in coke dry quenching facilities | |
JPH03157485A (en) | Operation of dry quenching facility for coke | |
CN114956513B (en) | Emergency furnace pressure control device and control method for TFT glass kiln | |
JPS61168690A (en) | Method of blowing air in dry coke quenching installation | |
CN212320442U (en) | Flue gas temperature regulating device | |
CN218646064U (en) | Preheating one-section stepped air supply system of chain grate machine | |
JPH10197160A (en) | Operating method for sintering machine | |
WO2024108840A1 (en) | Cascade air supply system for first preheating section of grate and air supply method | |
CN115584384A (en) | Method and system for processing high-temperature test incompatibility of bell-type furnace | |
JP2885072B2 (en) | Heating furnace control method | |
JP2002220591A (en) | Coke dry quenching facility and method for operating the same | |
CN116694340A (en) | Process control method for online dynamic balance adjustment of coke dry quenching circulating fan | |
KR101193751B1 (en) | Method for keeping heat of hot stove | |
JPH07188667A (en) | Removing method for soot and controlling method for soot removal in heating passage of high-temperature carbonization gas in formed coke production apparatus |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
17P | Request for examination filed |
Effective date: 20101007 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK TR |
|
AX | Request for extension of the european patent |
Extension state: AL BA RS |
|
DAX | Request for extension of the european patent (deleted) | ||
RA4 | Supplementary search report drawn up and despatched (corrected) |
Effective date: 20170119 |
|
RIC1 | Information provided on ipc code assigned before grant |
Ipc: C10B 39/02 20060101AFI20170113BHEP |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN |
|
18D | Application deemed to be withdrawn |
Effective date: 20170818 |