EP2201788B1 - Communications network - Google Patents

Communications network Download PDF

Info

Publication number
EP2201788B1
EP2201788B1 EP08838910.1A EP08838910A EP2201788B1 EP 2201788 B1 EP2201788 B1 EP 2201788B1 EP 08838910 A EP08838910 A EP 08838910A EP 2201788 B1 EP2201788 B1 EP 2201788B1
Authority
EP
European Patent Office
Prior art keywords
network
connection
optical
terminals
communications
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
EP08838910.1A
Other languages
German (de)
French (fr)
Other versions
EP2201788A1 (en
Inventor
Derek Nesset
Justin Kang
Mark Wilkinson
Kevin Smith
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
British Telecommunications PLC
Original Assignee
British Telecommunications PLC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by British Telecommunications PLC filed Critical British Telecommunications PLC
Publication of EP2201788A1 publication Critical patent/EP2201788A1/en
Application granted granted Critical
Publication of EP2201788B1 publication Critical patent/EP2201788B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04QSELECTING
    • H04Q11/00Selecting arrangements for multiplex systems
    • H04Q11/0001Selecting arrangements for multiplex systems using optical switching
    • H04Q11/0062Network aspects
    • H04Q11/0067Provisions for optical access or distribution networks, e.g. Gigabit Ethernet Passive Optical Network (GE-PON), ATM-based Passive Optical Network (A-PON), PON-Ring
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L12/00Data switching networks
    • H04L12/28Data switching networks characterised by path configuration, e.g. LAN [Local Area Networks] or WAN [Wide Area Networks]
    • H04L12/46Interconnection of networks
    • H04L12/4641Virtual LANs, VLANs, e.g. virtual private networks [VPN]
    • H04L12/467Arrangements for supporting untagged frames, e.g. port-based VLANs
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04QSELECTING
    • H04Q11/00Selecting arrangements for multiplex systems
    • H04Q11/0001Selecting arrangements for multiplex systems using optical switching
    • H04Q11/0062Network aspects
    • H04Q2011/0079Operation or maintenance aspects
    • H04Q2011/0081Fault tolerance; Redundancy; Recovery; Reconfigurability

Definitions

  • the present invention relates to optical communications networks, and in particular to resilient optical communications networks.
  • Broadband services are commonly supplied over legacy telephony networks using digital subscriber line (DSL) technology.
  • DSL digital subscriber line
  • One of the limitations of DSL is that the maximum data rate is not that high (for example, the maximum bit-rate is around 20 Mb s -1 ) and that the available bit rate decreases as the distance between the customer and the telephone exchange increases.
  • PON passive optical network
  • EP-A 1 784 045 discloses a network architecture in which each terminal is provided with two PON units, each of which are connected to different PONs. Traffic will be sent over both the first and second PONs by the terminals, with traffic sent over the second PON being blocked by a level 2 switch in the network. In the event that the first PON is damaged then the level 2 switch will allow some or all of the traffic from the second PON to be passed through.
  • a communications network comprising first and second optical line terminals and one or more optical network terminals wherein: i) the first optical line terminal has a first network connection to the one or more optical network terminals and the second optical line terminal has a second network connection to the one or more optical network terminals; ii) a first virtual LAN connection is made to each of the one or more optical network terminals via the first network connection; and ii) a second virtual LAN connection is made to each of the one or more optical network terminals via the second network connection; characterised in that, in use, the network is configured such that: a) the first network connection and the second network connection are both routed to the one or more optical network terminals via shared network infrastructure; b) the first network connection is an active connection used to transmit data to and/or receive data from the one or more optical network terminals; c) the second network connection is a standby connection; and d) a decision is made to switch from the active first network connection to the standby second network connection
  • the present invention provides a network structure that enables dual homing protection with a standard GPON product and also a mechanism for the higher layers to react when there has been a traffic switch to a protection OLT.
  • the solution proposed here for the provision of resilient services over a dual-homed GPON infrastructure involves protection at two levels: the physical layer protection of the PON itself and protection switching of services at the Ethernet layer.
  • the physical layer protection of the PON is handled by the GPON management system and the service protection switching relies on recently ratified Ethernet Operations, Administration and Maintenance (OAM) standards for Connectivity Fault Management (IEEE 802.1ag/ITU-T Y.1731).
  • OAM Ethernet Operations, Administration and Maintenance
  • FIG. 1 shows a schematic depiction of a conventional network architecture that is used to increase the resilience of PONs.
  • a PON 100 comprises a first plurality of optical network terminals (ONTs) 10 and a second plurality of optical network terminals (ONTs) 15.
  • the first plurality of optical network terminals (ONTs) 10 are connected to a first optical line terminal (OLT) at network node 20a via optical fibres and a passive optical splitter.
  • the first OLT 16a is then connected on to a core network 40 for the subsequent routing of traffic.
  • the first plurality of ONTs is also connected to a second OLT 16b at network node 20b, which is also connected to the core network 40.
  • the second plurality of ONTs 15 are connected to a first OLT 16c, which is located at the second network node 20b and to a second OLT 16d which is located at a third network node 20d.
  • the first plurality of ONTs will communicate with the first OLT but in the event of a network fault, or other contingency, then the first plurality of ONTs will switch to the second OLT.
  • This architecture is commonly referred to as a dual-homed PON (see D. Hunter and T. Gilfedder, "Routing and fast protection in networks of long-reach PONs", BTTJ, Vol. 24-2, p.p. 26-32 (2006 )).
  • the second plurality of ONTs are dual homed to OLTs at network nodes 20b & 20c. All of the OLTs at the various network nodes 20a, 20 & 20c are connected to a PON management system 30.
  • FIG. 2 shows a schematic depiction of a network according to the present invention.
  • ONT 10 is in communication with first and second OLTs 22, 24 via a PON comprising an optical splitter 28 and optical fibre links 23 & 26.
  • a first optical fibre 23 connects the ONT to first OLT 22 and a second optical fibre 26 connect the ONT to the second OLT 24..
  • Both the first and the second OLTs are connected to a PON management system 30.
  • Both the first and the second OLTs are connected to communications server 35, via first and second communications links 32 & 34.
  • First and second communications links 32 & 34 should be routed separately otherwise the benefits of providing separate firs and second optical fibre links will be lost.
  • the communications server 35 is in communications with one or more core networks 40.
  • FIG. 2 shows only a single ONT 10 but it will be understood that in practice a PON will comprise many ONTs, possibly in excess of 100.
  • the PON management system 30 In the event that the PON management system 30 detects the failure of the active OLT (for example, first OLT 22) then it will cause the backup OLT (second OLT 24) to initiate communications with the ONT. Similarly, if a fault in the PON infrastructure is detected, (for example a break in one of the optical fibre links 26) then the PON management system can switch all the affected ONTs across to the backup OLT.
  • the active OLT for example, first OLT 22
  • the backup OLT second OLT 24
  • Figure 2 also shows that resilient connections may be formed at the application level, with first and second Ethernet VLANs (Virtual Local Area Networks) 25 & 27 being formed between the communications server 35 and the ONT, with the first VLAN 25 being routed via the first OLT 22 and first optical fibre link 23. Similarly, the second VLAN 27 is routed via the second OLT 24 and second optical fibre link 26.
  • first and second Ethernet VLANs Virtual Local Area Networks
  • Ethernet continuity check messages are sent between the ONT and the communications server, with the same VLAN being used for the customer traffic and the CCMs.
  • the CCMs are defined in the Ethernet Operations, Administration and Maintenance (OAM) standards for Connectivity Fault Management (see IEEE 802.1ag, "OAM Functions and Mechanism for Ethernet based networks-Amendment 5: CFM", Feb. 8, 2007 ).
  • a series of CCMs are transmitted from the OLT to each of the ONTs, with each ONT sending an acknowledgement that the CCM was received from the OLT.
  • the continuity messages are lost and this causes the PON management system to switch from the active VLAN to the backup VLAN (i.e. from the first VLAN to the second VLAN or vice versa ), which is carried via the back-up OLT.
  • the backup OLT Once the backup OLT has successfully restored connectivity to the ONT the Ethernet service can resume over the backup VLAN. Customer traffic and continuity check messages can now be sent over the backup VLAN until the original fault has been repaired and the network operator is ready to revert to the original active VLAN.
  • the communications server can take advantage of the PON architecture to provide information regarding the state of the network or of the active OLT. For example, if the active OLT where to fail, or if there were to be a break in the optical fibre in between the OLT and the splitter, then none of the ONTs connected to the PON would be able to receive, or respond to, a CCM.
  • the communications server may send a CCM only to selected subsets of the ONTs.
  • the communications server may send the CCMs to ONTs at random, or alternatively the communications server may hold a list of ONTs and sequentially cycle through the ONTs to select ONTs which are to receive a CCM.
  • the results of which ONTs respond with an acknowledgement to a CCM can be stored to build up a map of working ONTs.
  • the communications server may take further action to determine if any other ONTs are not responding. For example, the communications server may send further CCMs to a non-responsive ONT: if, for example, an ONT does not respond to three consecutive CCMs then it may be assumed that connection has been lost to that ONT (it will be understood that a different threshold value for CCMs may be selected).
  • the communications server then may send CCMs to selected ONTs to obtain information that may be used to determine where the network fault(s) may be.
  • CCMs may be sent to other ONTs that share some part of the PON infrastructure with the non-responsive ONT then it is possible to diagnose where the network failure has occurred and how many ONTs have been effected by the fault.
  • CCMs may be sent to all of the other ONTs that are connected to the same secondary optical splitter; if the other ONTs respond then it is most likely that the fault is in the non-responsive ONT or the connection between the non-responsive ONT and the secondary optical splitter. If non of the ONTs respond then it is likely that there is a fault in the network infrastructure. If ONTs connected to other secondary optical splitters are responsive then it is likely that there is a fault with one of the secondary optical splitter.
  • the information derived from the analysis of CCMs can be used to initiate a switch to the backup VLAN in the event that no responses are received from any ONTs or to cause further investigations and/or repair work to be made in the event that only a subset of ONTs are non responsive.
  • the sequential transmission method of CCMs according to the present invention causes less network bandwidth is lost to management overheads when compared to sending CCMs to all ONTs. Furthermore, the present invention requires less of a processing overhead from a communications server in transmitting CCMs, tracking the acknowledgments received from ONTs and then initiating further actions when acknowledgements are not received.
  • Figure 2 shows only a single communications server 35. It should be understood that the main and back-up OLTs may be connected to a plurality of communications servers with each of the communications servers being associated with a different communications provider, in the event that the regulatory regime mandates that a number of communications providers are allowed to provide services over a communications network owned by a different network operator (although the same entity may operate the communications network as well as a communications server).
  • FIG. 3 shows a schematic depiction of a dual-homed GPON Ethernet service demonstrator which can be operated in accordance with the present invention.
  • the demonstrator 300 comprises two Siemens GPON OLTs (hiX 5750) 320 & 322 a number of GPON ONTs (hiX57XX) 310, two Ethernet Network Termination Equipment (NTE) devices (RAD ETX102) 330, an IP video server 340 and a PC 350 to receive and play video streams.
  • the NTEs provide the required Ethernet OAM functionality which is not supported currently on the other equipment (it is expected that this functionality will be implemented in the OLT/ONT and Ethernet switches in the near future).
  • the ONTs are dual-homed to two OLTs through a splitter 370.
  • the two OLTs should be located at different geographical locations to provide resilience.
  • Each ONT is then registered on both the primary and secondary OLTs. To avoid physical interference through the optical splitter, only one of the OLTs can be active at any one time
  • the ONT When either of the OLTs is switched on, the ONT automatically ranges to it and the configured service profile is applied.
  • the same service profile is configured in both OLTs via the Element Management System (EMS) 360.
  • EMS Element Management System
  • a second PC is used to run software to monitor the alarms of the GPON and control the GPON via the EMS 360.
  • the primary OLT fails or the fibre is broken, the alarms are detected, leading to the primary OLT being disabled and the secondary OLT being enabled.
  • the ONT is now connected to the secondary OLT and ranges to it automatically. Ethernet and higher layer services are restored after the ranging finishes. Both ONT and OLT use Ethernet ports to provide services.
  • the NTEs have two types of Ethernet ports: user ports and net ports.
  • User ports are connected to end users or communications servers (in the demonstrator, the IP video server 340 takes the role of the communications server).
  • Net ports are connected to ONT or OLT Ethernet ports and support Maintenance association End Points (MEP) per port per VLAN.
  • MEP Maintenance association End Points
  • the end-to-end Continuity Check Messages (CCM) are only transmitted between the net ports of the NTEs.
  • GPON provides 1:1 VLAN connections.
  • the primary OLT uplink Ethernet port is connected to an NTE 330b of the IP video server using a first VLAN.
  • the secondary OLT is connected to the same IP video server NTE 330b using a second VLAN.
  • the IP video server uses the first VLAN and monitors the connectivity of the VLAN using CCMs. Following the loss of three consecutive CCMs, the NTEs switch to send customer data and CCMs on the second VLAN, so that traffic is directed towards the secondary OLT.
  • the CCMs always use the same VLAN as customer data.
  • the interval between CCMs can be configured according to different failure response time and overhead requirements; for example it may be 25 ms.
  • a fault can be simulated by disconnecting the primary OLT fibre, which causes a loss of signal alarm to be detected by the EMS. According to the alarm, the primary OLT port is disabled and the secondary OLT port is enables via the EMS. The video traffic is disrupted and the picture is frozen when the fibre is disconnected.
  • the IP video server will detect an increase in CCMs and thus switch from the first VLAN to the second VLAN. When the connectivity is restored using the secondary VLAN, the video will resume playing.
  • the service disruption time consists of the software overhead ( ⁇ 9s), the ONT re-ranging time and the Ethernet restoration time. The average service disruption time is 26 seconds. It is thought that with improvements to the process it is possible to reduce the service disruption to less than 1 second.
  • the present invention is also capable of use with other network structures, for example Fibre to the Cabinet (FTTCab) or Fibre to the Kerb (FTTK) in which the portion of the network that is not optical fibre comprises a wireless link or a twisted pair or coaxial cable connection.
  • FTTCab Fibre to the Cabinet
  • FTTK Fibre to the Kerb
  • the present invention to provide additional duplication at the service level.
  • other performance indicators may be used as an alternative to the Ethernet continuity check messages or in addition to CCMs.
  • a composite performance indicator may be generated based on the values of a number of different parameters.

Description

  • The present invention relates to optical communications networks, and in particular to resilient optical communications networks.
  • Broadband services are commonly supplied over legacy telephony networks using digital subscriber line (DSL) technology. One of the limitations of DSL is that the maximum data rate is not that high (for example, the maximum bit-rate is around 20 Mb s-1) and that the available bit rate decreases as the distance between the customer and the telephone exchange increases. It is believed that future broadband services are increasingly likely to be offered over optical fibre infrastructure using passive optical network (PON) architectures (D. B. Payne and R. P. Davey, "The future of fibre access systems", BTTJ, Vol. 20-4, pp 104-114, (2002)). There are a number of large scale PON deployments currently underway around the world using either IEEE EPON technology or FSAN/ITU BPON and GPON. There is an emerging trend from network operators to consolidate network nodes and to reduce the amount of real estate used, leading to reductions in operational costs. A consequence of centralising network equipment into a smaller number of network nodes is that the network is more vulnerable to large scale outages in the event that a node is rendered out of service due to some catastrophic fault (fire, earthquake etc.). EP-A 1 784 045 discloses a network architecture in which each terminal is provided with two PON units, each of which are connected to different PONs. Traffic will be sent over both the first and second PONs by the terminals, with traffic sent over the second PON being blocked by a level 2 switch in the network. In the event that the first PON is damaged then the level 2 switch will allow some or all of the traffic from the second PON to be passed through.
  • According to an aspect of the present invention there is provided a communications network comprising first and second optical line terminals and one or more optical network terminals wherein: i) the first optical line terminal has a first network connection to the one or more optical network terminals and the second optical line terminal has a second network connection to the one or more optical network terminals; ii) a first virtual LAN connection is made to each of the one or more optical network terminals via the first network connection; and ii) a second virtual LAN connection is made to each of the one or more optical network terminals via the second network connection; characterised in that, in use, the network is configured such that: a) the first network connection and the second network connection are both routed to the one or more optical network terminals via shared network infrastructure; b) the first network connection is an active connection used to transmit data to and/or receive data from the one or more optical network terminals; c) the second network connection is a standby connection; and d) a decision is made to switch from the active first network connection to the standby second network connection for one or more of the optical network terminals, the decision being made in response to network performance indicators associated with the first virtual LAN connection. Furthermore, in use, if the network switches from the active connection to the standby connection for a non-responsive optical network terminal, continuity check messages may be sent to one or more selected optical network terminals which are connected to the same network infrastructure as the responsive optical network terminal.
  • There are protection mechanisms already defined in PON standards e.g. G.984 series, but these assume that the standby OLT resides at the same central office location, which is not acceptable when protecting against catastrophic failures. Hence new mechanisms need to be defined for this network architecture. Furthermore, higher network layers (Ethernet, IP...) need to be able to switch traffic to the correct OLT in the event of a failure. The responsibility for the management and operation of these layers may reside with independent service providers, with no direct access to the PON management system. The present invention provides a network structure that enables dual homing protection with a standard GPON product and also a mechanism for the higher layers to react when there has been a traffic switch to a protection OLT.
  • The solution proposed here for the provision of resilient services over a dual-homed GPON infrastructure involves protection at two levels: the physical layer protection of the PON itself and protection switching of services at the Ethernet layer. The physical layer protection of the PON is handled by the GPON management system and the service protection switching relies on recently ratified Ethernet Operations, Administration and Maintenance (OAM) standards for Connectivity Fault Management (IEEE 802.1ag/ITU-T Y.1731).
  • The invention will now be described with reference to the following Figures, which are provided by way of example only, in which:
    • Figure 1 shows a schematic depiction of a network architecture that is used to increase the resilience of PONs;
    • Figure 2 shows a schematic depiction of a network according to the present invention; and
    • Figure 3 shows a schematic depiction of a dual-homed GPON Ethernet service demonstrator.
  • Figure 1 shows a schematic depiction of a conventional network architecture that is used to increase the resilience of PONs. A PON 100 comprises a first plurality of optical network terminals (ONTs) 10 and a second plurality of optical network terminals (ONTs) 15. The first plurality of optical network terminals (ONTs) 10 are connected to a first optical line terminal (OLT) at network node 20a via optical fibres and a passive optical splitter. The first OLT 16a is then connected on to a core network 40 for the subsequent routing of traffic. To provide resilience, the first plurality of ONTs is also connected to a second OLT 16b at network node 20b, which is also connected to the core network 40. Similarly, the second plurality of ONTs 15 are connected to a first OLT 16c, which is located at the second network node 20b and to a second OLT 16d which is located at a third network node 20d.
  • Conventionally, the first plurality of ONTs will communicate with the first OLT but in the event of a network fault, or other contingency, then the first plurality of ONTs will switch to the second OLT. This architecture is commonly referred to as a dual-homed PON (see D. Hunter and T. Gilfedder, "Routing and fast protection in networks of long-reach PONs", BTTJ, Vol. 24-2, p.p. 26-32 (2006)). Similarly, the second plurality of ONTs are dual homed to OLTs at network nodes 20b & 20c. All of the OLTs at the various network nodes 20a, 20 & 20c are connected to a PON management system 30.
  • Figure 2 shows a schematic depiction of a network according to the present invention. ONT 10 is in communication with first and second OLTs 22, 24 via a PON comprising an optical splitter 28 and optical fibre links 23 & 26. A first optical fibre 23 connects the ONT to first OLT 22 and a second optical fibre 26 connect the ONT to the second OLT 24.. Both the first and the second OLTs are connected to a PON management system 30. Both the first and the second OLTs are connected to communications server 35, via first and second communications links 32 & 34. First and second communications links 32 & 34 should be routed separately otherwise the benefits of providing separate firs and second optical fibre links will be lost. The communications server 35 is in communications with one or more core networks 40.
  • For the sake of simplicity Figure 2 shows only a single ONT 10 but it will be understood that in practice a PON will comprise many ONTs, possibly in excess of 100.
  • In the event that the PON management system 30 detects the failure of the active OLT (for example, first OLT 22) then it will cause the backup OLT (second OLT 24) to initiate communications with the ONT. Similarly, if a fault in the PON infrastructure is detected, (for example a break in one of the optical fibre links 26) then the PON management system can switch all the affected ONTs across to the backup OLT.
  • Figure 2 also shows that resilient connections may be formed at the application level, with first and second Ethernet VLANs (Virtual Local Area Networks) 25 & 27 being formed between the communications server 35 and the ONT, with the first VLAN 25 being routed via the first OLT 22 and first optical fibre link 23. Similarly, the second VLAN 27 is routed via the second OLT 24 and second optical fibre link 26.
  • In addition to the traffic sent to the ONT in response to customer actions or requests, Ethernet continuity check messages (CCMs) are sent between the ONT and the communications server, with the same VLAN being used for the customer traffic and the CCMs. The CCMs are defined in the Ethernet Operations, Administration and Maintenance (OAM) standards for Connectivity Fault Management (see IEEE 802.1ag, "OAM Functions and Mechanism for Ethernet based networks-Amendment 5: CFM", Feb. 8, 2007).
  • Under normal operation, a series of CCMs are transmitted from the OLT to each of the ONTs, with each ONT sending an acknowledgement that the CCM was received from the OLT. In the event of an OLT failure, or a fibre break, the continuity messages are lost and this causes the PON management system to switch from the active VLAN to the backup VLAN (i.e. from the first VLAN to the second VLAN or vice versa), which is carried via the back-up OLT. Once the backup OLT has successfully restored connectivity to the ONT the Ethernet service can resume over the backup VLAN. Customer traffic and continuity check messages can now be sent over the backup VLAN until the original fault has been repaired and the network operator is ready to revert to the original active VLAN.
  • In a particular embodiment of the present invention, the communications server can take advantage of the PON architecture to provide information regarding the state of the network or of the active OLT. For example, if the active OLT where to fail, or if there were to be a break in the optical fibre in between the OLT and the splitter, then none of the ONTs connected to the PON would be able to receive, or respond to, a CCM. Similarly, for a PON with 64 ONTs, in which the optical splitter is formed from a 2x8 splitter to which each of the outputs is connected to a 1 x8 splitter, if one of the 1 x8 splitters were to fail then all eight of the ONTs connected to that splitter would not be able to receive, or respond to, a CCM. Furthermore, if there were to be a failure of the optical fibre between the optical splitter and the customer premises then it is likely that this mean that only a single ONT would not be able to receive, or respond to, a CCM. Thus, by analysing the distribution of received CCMs it is possible to infer the status of the active OLT, the network infrastructure and the ONTs without the service provider operating the communications server having access to the PON management system 30.
  • It will be understood that sending CCMs to all ONTs will increase the proportion of network traffic that is used by network management overhead. Thus, rather than sending CCMs to all ONTs, the communications server may send a CCM only to selected subsets of the ONTs. For example, the communications server may send the CCMs to ONTs at random, or alternatively the communications server may hold a list of ONTs and sequentially cycle through the ONTs to select ONTs which are to receive a CCM.
  • The results of which ONTs respond with an acknowledgement to a CCM can be stored to build up a map of working ONTs. In the event that an ONT does not respond then the communications server may take further action to determine if any other ONTs are not responding. For example, the communications server may send further CCMs to a non-responsive ONT: if, for example, an ONT does not respond to three consecutive CCMs then it may be assumed that connection has been lost to that ONT (it will be understood that a different threshold value for CCMs may be selected).
  • The communications server then may send CCMs to selected ONTs to obtain information that may be used to determine where the network fault(s) may be. By sending CCMs to other ONTs that share some part of the PON infrastructure with the non-responsive ONT then it is possible to diagnose where the network failure has occurred and how many ONTs have been effected by the fault.
  • For example, if one ONT becomes non-responsive then CCMs may be sent to all of the other ONTs that are connected to the same secondary optical splitter; if the other ONTs respond then it is most likely that the fault is in the non-responsive ONT or the connection between the non-responsive ONT and the secondary optical splitter. If non of the ONTs respond then it is likely that there is a fault in the network infrastructure. If ONTs connected to other secondary optical splitters are responsive then it is likely that there is a fault with one of the secondary optical splitter. The information derived from the analysis of CCMs can be used to initiate a switch to the backup VLAN in the event that no responses are received from any ONTs or to cause further investigations and/or repair work to be made in the event that only a subset of ONTs are non responsive.
  • The sequential transmission method of CCMs according to the present invention causes less network bandwidth is lost to management overheads when compared to sending CCMs to all ONTs. Furthermore, the present invention requires less of a processing overhead from a communications server in transmitting CCMs, tracking the acknowledgments received from ONTs and then initiating further actions when acknowledgements are not received.
  • Figure 2 shows only a single communications server 35. It should be understood that the main and back-up OLTs may be connected to a plurality of communications servers with each of the communications servers being associated with a different communications provider, in the event that the regulatory regime mandates that a number of communications providers are allowed to provide services over a communications network owned by a different network operator (although the same entity may operate the communications network as well as a communications server).
  • Figure 3 shows a schematic depiction of a dual-homed GPON Ethernet service demonstrator which can be operated in accordance with the present invention. The demonstrator 300 comprises two Siemens GPON OLTs (hiX 5750) 320 & 322 a number of GPON ONTs (hiX57XX) 310, two Ethernet Network Termination Equipment (NTE) devices (RAD ETX102) 330, an IP video server 340 and a PC 350 to receive and play video streams. The NTEs provide the required Ethernet OAM functionality which is not supported currently on the other equipment (it is expected that this functionality will be implemented in the OLT/ONT and Ethernet switches in the near future). The ONTs are dual-homed to two OLTs through a splitter 370. The two OLTs should be located at different geographical locations to provide resilience. Each ONT is then registered on both the primary and secondary OLTs. To avoid physical interference through the optical splitter, only one of the OLTs can be active at any one time.
  • When either of the OLTs is switched on, the ONT automatically ranges to it and the configured service profile is applied. The same service profile is configured in both OLTs via the Element Management System (EMS) 360. A second PC is used to run software to monitor the alarms of the GPON and control the GPON via the EMS 360. When the primary OLT fails or the fibre is broken, the alarms are detected, leading to the primary OLT being disabled and the secondary OLT being enabled. The ONT is now connected to the secondary OLT and ranges to it automatically. Ethernet and higher layer services are restored after the ranging finishes. Both ONT and OLT use Ethernet ports to provide services.
  • The NTEs have two types of Ethernet ports: user ports and net ports. User ports are connected to end users or communications servers (in the demonstrator, the IP video server 340 takes the role of the communications server). Net ports are connected to ONT or OLT Ethernet ports and support Maintenance association End Points (MEP) per port per VLAN. The end-to-end Continuity Check Messages (CCM) are only transmitted between the net ports of the NTEs. GPON provides 1:1 VLAN connections. The primary OLT uplink Ethernet port is connected to an NTE 330b of the IP video server using a first VLAN. The secondary OLT is connected to the same IP video server NTE 330b using a second VLAN. In normal operation, the IP video server uses the first VLAN and monitors the connectivity of the VLAN using CCMs. Following the loss of three consecutive CCMs, the NTEs switch to send customer data and CCMs on the second VLAN, so that traffic is directed towards the secondary OLT. The CCMs always use the same VLAN as customer data.
  • The interval between CCMs can be configured according to different failure response time and overhead requirements; for example it may be 25 ms. A fault can be simulated by disconnecting the primary OLT fibre, which causes a loss of signal alarm to be detected by the EMS. According to the alarm, the primary OLT port is disabled and the secondary OLT port is enables via the EMS. The video traffic is disrupted and the picture is frozen when the fibre is disconnected. The IP video server will detect an increase in CCMs and thus switch from the first VLAN to the second VLAN. When the connectivity is restored using the secondary VLAN, the video will resume playing. The service disruption time consists of the software overhead (∼9s), the ONT re-ranging time and the Ethernet restoration time. The average service disruption time is 26 seconds. It is thought that with improvements to the process it is possible to reduce the service disruption to less than 1 second.
  • Although the preceding discussion has focused on PONs it will be readily understood that the present invention is also capable of use with other network structures, for example Fibre to the Cabinet (FTTCab) or Fibre to the Kerb (FTTK) in which the portion of the network that is not optical fibre comprises a wireless link or a twisted pair or coaxial cable connection. In general, if there is some degree of physical separation in the network path between the service provider (or the hardware of the network provider) then it is possible to utilise the present invention to provide additional duplication at the service level. It will be understood that other performance indicators may be used as an alternative to the Ethernet continuity check messages or in addition to CCMs. A composite performance indicator may be generated based on the values of a number of different parameters.

Claims (7)

  1. A communications network comprising first and second optical line terminals and one or more optical network terminals wherein:
    i) the first optical line terminal (22) has a first network connection (23) to the one or more optical network terminals (10) and the second optical line terminal (24) has a second network connection (26) to the one or more optical network terminals;
    ii) a first virtual LAN connection (25) is made to each of the one or more optical network terminals via the first network connection; and
    ii) a second virtual LAN connection is made (27) to each of the one or more optical network terminals via the second network connection;
    characterised in that, in use, the network is configured such that:
    a) the first network connection and the second network connection are both routed to the one or more optical network terminals via shared network infrastructure (28);
    b) the first network connection (23) is an active connection used to transmit data to and/or receive data from the one or more optical network terminals;
    c) the second network connection (26) is a standby connection; and
    d) a decision is made to switch from the active first network connection to the standby second network connection for one or more of the optical network terminals, the decision being made in response to network performance indicators associated with the first virtual LAN connection (25).
  2. A communications network according to claim 1, wherein the network is connected to one or more communications servers (35), wherein the virtual LAN connections established in steps ii) and iii) are extended to the one or more communications servers.
  3. A communications network according to claim 1, wherein the virtual LAN connection comprises an Ethernet VLAN and the network performance indicators comprise one or more Ethernet continuity check messages.
  4. A communications network according to claim 3, wherein continuity check messages are sent to a random selection of optical network terminals.
  5. A communications network according to claim 3, wherein continuity check messages are sent to ONTs that are sequentially selected from the one or more random selection of optical network terminals.
  6. A communications network according to any of claims 3 to 5, wherein, in use, the network switches from the active connection to the standby connection when three consecutive Ethernet continuity check messages are not received from one of the optical network terminals.
  7. A communications network according to claim 3, wherein, in use, if the network switches from the active connection to the standby connection for a non-responsive optical network terminal, continuity check messages are sent to one or more selected optical network terminals which are connected to the same network infrastructure as the responsive optical network terminal.
EP08838910.1A 2007-10-15 2008-10-15 Communications network Active EP2201788B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
GBGB0720094.2A GB0720094D0 (en) 2007-10-15 2007-10-15 Optical network
PCT/GB2008/003499 WO2009050459A1 (en) 2007-10-15 2008-10-15 Communications network

Publications (2)

Publication Number Publication Date
EP2201788A1 EP2201788A1 (en) 2010-06-30
EP2201788B1 true EP2201788B1 (en) 2014-11-12

Family

ID=38788179

Family Applications (1)

Application Number Title Priority Date Filing Date
EP08838910.1A Active EP2201788B1 (en) 2007-10-15 2008-10-15 Communications network

Country Status (5)

Country Link
US (1) US8433194B2 (en)
EP (1) EP2201788B1 (en)
CN (1) CN101822070B (en)
GB (1) GB0720094D0 (en)
WO (1) WO2009050459A1 (en)

Families Citing this family (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101998191A (en) * 2009-08-27 2011-03-30 华为技术有限公司 Sink node linkage switching method, sink node and system
WO2011126416A1 (en) * 2010-04-08 2011-10-13 Telefonaktiebolaget Lm Ericsson (Publ) Method and arrangements for protection in an optical network
US8805922B2 (en) * 2010-05-14 2014-08-12 Stephen Ball System and method for negotiating a network connection
JP5226900B2 (en) * 2010-11-25 2013-07-03 三菱電機株式会社 Communication line switching method, communication apparatus, station side communication apparatus, communication system, and control apparatus
US8699326B2 (en) * 2011-01-31 2014-04-15 Telefonaktiebolaget L M Ericsson (Publ) Optical network automatic protection switching
CN102215124B (en) 2011-06-08 2013-06-05 华为技术有限公司 Fault processing method, sink node and optical network protection system
CN103178971B (en) * 2011-12-20 2015-12-16 华为技术有限公司 PON guard method and device
WO2014094268A1 (en) * 2012-12-20 2014-06-26 华为技术有限公司 Service protection method, optical line terminal and system in passive optical network
EP2775733A1 (en) 2013-03-05 2014-09-10 British Telecommunications public limited company Communications network
US9209925B2 (en) * 2013-03-12 2015-12-08 Tellabs Bedford, Inc. Passive optical networking redundancy via two or more auto sensing optical line terminals
CN103281131A (en) * 2013-06-05 2013-09-04 杜和青 Method for designing optical fiber bus based on Ethernet passive optical network
CN103441793B (en) * 2013-08-30 2017-01-25 上海斐讯数据通信技术有限公司 Method for realizing reliable communication between optical links
WO2015070427A1 (en) * 2013-11-15 2015-05-21 华为技术有限公司 Method, device, and system for configuring maintenance association (ma)
WO2015101763A1 (en) 2013-12-31 2015-07-09 British Telecommunications Public Limited Company Operationally resilient optical network
US11107039B2 (en) 2015-02-03 2021-08-31 PEOZZLE Corporation Multimedia human resource distribution system
US20160234582A1 (en) * 2015-02-10 2016-08-11 Daniel Ronald Method and system for redundancy in a passive optical network
JP6743494B2 (en) * 2016-06-03 2020-08-19 富士通株式会社 Transmission system, communication device, and path switching method
ES2946957T3 (en) * 2020-08-24 2023-07-28 Deutsche Telekom Ag Procedure for the operation of a broadband access network of a telecommunications network comprising a plurality of central office delivery points, broadband access networks or telecommunications networks, clusters of central office delivery points, systems , programs and computer-readable media
US11936435B2 (en) * 2022-03-23 2024-03-19 Aleksandar MILOJKOVIC Systems and methods for combination telecommunications and power networks

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1746857A1 (en) * 2005-07-20 2007-01-24 Siemens Aktiengesellschaft Method and apparatus enabling end-to-end resilience in PONs
US7821949B2 (en) * 2005-09-12 2010-10-26 Nortel Networks Limited Forwarding plane data communications channel for ethernet transport networks
US7756018B2 (en) 2005-11-03 2010-07-13 Alcatel Lucent System and method for implementing fast layer 2 protection in passive optical networks
US20070201872A1 (en) * 2006-01-19 2007-08-30 Allied Telesis Holdings K.K. IP triple play over Gigabit Ethernet passive optical network
CN1859811B (en) * 2006-03-15 2011-02-02 华为技术有限公司 Passive optical network system and its service protective method
CN100555949C (en) * 2006-03-22 2009-10-28 华为技术有限公司 A kind of to GPON system configuration Native VLAN and processing Ethernet method of message

Also Published As

Publication number Publication date
WO2009050459A9 (en) 2010-06-03
GB0720094D0 (en) 2007-11-21
EP2201788A1 (en) 2010-06-30
US20100247098A1 (en) 2010-09-30
WO2009050459A1 (en) 2009-04-23
CN101822070B (en) 2013-03-20
CN101822070A (en) 2010-09-01
US8433194B2 (en) 2013-04-30

Similar Documents

Publication Publication Date Title
EP2201788B1 (en) Communications network
EP2622872B1 (en) Communications network
JP6367246B2 (en) Communication network
KR100833504B1 (en) A apparatus and method for partial duplex protection switching by using single splitter in pon
EP2393237B1 (en) Passive optical network protection method, master-standby switch control device and system
US10129617B2 (en) Link switching method, device, and system
US20120134664A1 (en) Joint switching method for an aggregation node, aggregation node and system
US20080298803A1 (en) System and method for protection of point to multipoint passive optical network
US6798991B1 (en) Optical communication systems, optical communication system terminal facilities, optical communication methods, and methods of communicating within an optical network
US20140178067A1 (en) Data communication method in optical network system, optical network unit and system
US20120251097A1 (en) Passive architectural optical distribution network
JP2002057685A (en) Access network from one point to multiple points
Hajduczenia et al. Resilience and service protection for Ethernet passive optical networks in SIEPON
Kang et al. Restoration of ethernet services over a dual-homed GPON system-operator requirements and practical demonstration
JP2017175177A (en) Optical line terminal, redundant terminal changeover method, and redundant terminal changeover program
KR100452887B1 (en) Protection device and method of Optical network unit in passive optical network
EP2056619A1 (en) Passive optical network
Hossain et al. A simple self-healing ring-based local access PON architecture for supporting private networking capability
TWI403102B (en) A structure for passive optical network and protecting method
Ab-Rahman et al. Access Control System: An architecture approach for monitoring, survivability and scalability in FTTH-PON application
WO2021069113A1 (en) Optical communications network and method for continuous service provision thereon
Premadi et al. Protection Access Network: An Architecture Approach to Remote Monitor and Control
Ng et al. Hardware Architecture of Protection Switching Device (PSD)

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

17P Request for examination filed

Effective date: 20100419

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MT NL NO PL PT RO SE SI SK TR

AX Request for extension of the european patent

Extension state: AL BA MK RS

DAX Request for extension of the european patent (deleted)
GRAJ Information related to disapproval of communication of intention to grant by the applicant or resumption of examination proceedings by the epo deleted

Free format text: ORIGINAL CODE: EPIDOSDIGR1

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

INTG Intention to grant announced

Effective date: 20140428

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MT NL NO PL PT RO SE SI SK TR

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

REG Reference to a national code

Ref country code: AT

Ref legal event code: REF

Ref document number: 696378

Country of ref document: AT

Kind code of ref document: T

Effective date: 20141115

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: DE

Ref legal event code: R096

Ref document number: 602008035374

Country of ref document: DE

Effective date: 20141224

REG Reference to a national code

Ref country code: NL

Ref legal event code: VDEP

Effective date: 20141112

REG Reference to a national code

Ref country code: AT

Ref legal event code: MK05

Ref document number: 696378

Country of ref document: AT

Kind code of ref document: T

Effective date: 20141112

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150312

Ref country code: FI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141112

Ref country code: NL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141112

Ref country code: LT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141112

Ref country code: PT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150312

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141112

Ref country code: NO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150212

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: CY

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141112

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150213

Ref country code: PL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141112

Ref country code: SE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141112

Ref country code: LV

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141112

Ref country code: HR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141112

Ref country code: AT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141112

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141112

Ref country code: RO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141112

Ref country code: DK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141112

Ref country code: EE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141112

Ref country code: CZ

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141112

REG Reference to a national code

Ref country code: DE

Ref legal event code: R097

Ref document number: 602008035374

Country of ref document: DE

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

26N No opposition filed

Effective date: 20150813

REG Reference to a national code

Ref country code: FR

Ref legal event code: PLFP

Year of fee payment: 8

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141112

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141112

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LU

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20151015

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MC

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141112

REG Reference to a national code

Ref country code: IE

Ref legal event code: MM4A

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20151031

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20151031

REG Reference to a national code

Ref country code: FR

Ref legal event code: PLFP

Year of fee payment: 9

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20151015

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: BG

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141112

Ref country code: HU

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO

Effective date: 20081015

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: TR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141112

Ref country code: MT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141112

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: BE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141112

REG Reference to a national code

Ref country code: FR

Ref legal event code: PLFP

Year of fee payment: 10

REG Reference to a national code

Ref country code: FR

Ref legal event code: PLFP

Year of fee payment: 11

P01 Opt-out of the competence of the unified patent court (upc) registered

Effective date: 20230623

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: GB

Payment date: 20230920

Year of fee payment: 16

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: FR

Payment date: 20230920

Year of fee payment: 16

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20230920

Year of fee payment: 16