EP1536077B1 - Procédé de construction d'un bâtiment, ce bâtiment, et élément de mur pour ceux-ci - Google Patents

Procédé de construction d'un bâtiment, ce bâtiment, et élément de mur pour ceux-ci Download PDF

Info

Publication number
EP1536077B1
EP1536077B1 EP04105914A EP04105914A EP1536077B1 EP 1536077 B1 EP1536077 B1 EP 1536077B1 EP 04105914 A EP04105914 A EP 04105914A EP 04105914 A EP04105914 A EP 04105914A EP 1536077 B1 EP1536077 B1 EP 1536077B1
Authority
EP
European Patent Office
Prior art keywords
building
wall
elements
layer
floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
EP04105914A
Other languages
German (de)
English (en)
Other versions
EP1536077A1 (fr
Inventor
Albertus Theodorus Gerardus Veerman
Aije Jacob Simons
Bernardus Johannes Bos
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Veerhuis Beheer BV
Original Assignee
Veerhuis Beheer BV
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Veerhuis Beheer BV filed Critical Veerhuis Beheer BV
Priority to PL04105914T priority Critical patent/PL1536077T3/pl
Priority to SI200430984T priority patent/SI1536077T1/sl
Priority to EP04105914A priority patent/EP1536077B1/fr
Publication of EP1536077A1 publication Critical patent/EP1536077A1/fr
Application granted granted Critical
Publication of EP1536077B1 publication Critical patent/EP1536077B1/fr
Priority to CY20081101468T priority patent/CY1108683T1/el
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/16Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material
    • E04B1/161Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material with vertical and horizontal slabs, both being partially cast in situ
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/16Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material
    • E04B1/165Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material with elongated load-supporting parts, cast in situ
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/19Three-dimensional framework structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/02Load-carrying floor structures formed substantially of prefabricated units
    • E04B5/04Load-carrying floor structures formed substantially of prefabricated units with beams or slabs of concrete or other stone-like material, e.g. asbestos cement
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C2/00Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
    • E04C2/02Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials
    • E04C2/10Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials of wood, fibres, chips, vegetable stems, or the like; of plastics; of foamed products
    • E04C2/20Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials of wood, fibres, chips, vegetable stems, or the like; of plastics; of foamed products of plastics
    • E04C2/205Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials of wood, fibres, chips, vegetable stems, or the like; of plastics; of foamed products of plastics of foamed plastics, or of plastics and foamed plastics, optionally reinforced
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block

Definitions

  • the invention relates to a method of constructing a building, a building preferably constructed according to this method and wall and floor elements for use therein.
  • EP 0 727 535 A1 discloses a method of constructing a partition wall, which includes providing a plurality of columns or studs, securing basic face materials to both outer sides of the studs through sound insulation materials and fixing hard gypsum sheets to the outer sides of the corresponding basic face materials, thereby providing a wall structure having fire protecting properties.
  • US 5,765,333 discloses a united post and panel building system, in which a post is placed on a flooring system, a rigid foam panel, consisting of one or more layers of rigid foam bonded together using adhesives and having a shape to mate with the post, is placed next to the post, and is bonded to the post and the floor, whereafter the next post is put in place and bonded to the same panel etc.
  • Furring strips may be embedded in the surfaces of the panels to allow common attachment of plasterboard on the inside of the panel wall system or siding on the outside.
  • An object of the present invention is to provide an improved method of constructing a building.
  • the building wall according to the invention conforms to all basic requirements of building regulations, such as compressive strength, wind resistance etc, without costly additional measures.
  • large wall elements are used, such that a story high wall element completely fills the space between two adjacent upright building elements, such as columns or dividing walls. If the adjacent wall elements abut at the position of the upright building element, it is automatically covered.
  • the other, preferably inner, side of the column may be covered by a separate panel to close off the space around the column.
  • the wall surfaces on both sides of the building wall are flat, but for example at the position of the columns, the wall surface may be interrupted by protruding sections, or recessed sections.
  • the columns may be prefabricated from wood, steel, or concrete or any combination thereof, but it is also possible to cast columns in situ by closing the space around the desired columns and to use the wall elements and panel as shuttering to form the column from structural fill-material, such as concrete.
  • the walls may be formed in situ or may consist of prefab walls which are erected before the wall elements are placed.
  • the walls may be processed, preferably cut, to form openings and recesses in the walls to take up doors, windows, lines and pipes etc. Since the columns and/or dividing walls take up the majority of forces in the building, the openings in the wall elements may be created as desired without deteriorating the structural integrity of the building wall. As the wall elements are hardly loaded, they are not deformed and this obviates the need for frames around windows which are normally intended to protect the glass from forces in the wall. This reduces the building costs further. Frames are only necessary for supporting movable windows. Since there is a great freedom in making openings in the walls and since these openings could be made only after constructing the walls of the building, the design of the building may be changed in a late stage of the building process. This makes the building concept very flexible.
  • the wall elements can be prefabricated, with all windows, doors, lines and/or other accessories mounted in the production facility. It is even conceivable to prefabricate complete (one storey) facades or even the complete building before it is transported to the construction site.
  • the invention also includes a building in accordance with claim 8.
  • the covering layer includes a reinforcement layer, such as a woven mat, netting, mesh or the like, and preferably a fibre reinforced layer.
  • a reinforcement layer such as a woven mat, netting, mesh or the like, and preferably a fibre reinforced layer.
  • This reinforcement layer provides added strength to the wall elements in order to provide resistance against external forces, such as wind or the like.
  • a reinforcement layer on the inner side of the building may also provide added strength for mounting purposes inside the house, for example for hanging objects to the walls.
  • the invention also includes a wall element in accordance with claim 14.
  • the wall element will generally be plane, but it may also be curved around one or more axes.
  • Floors in the building are preferably made by placing and interconnecting lightweight, heat insulating floor elements, supporting them if necessary, and pouring structural fill-material, such as concrete or the like, onto the floor elements to form the floor.
  • structural fill-material such as concrete or the like
  • For interconnecting the floor elements use is preferably made of thin steel profile sections.
  • Fig. 1 - 3 show a part of a building wall in accordance with the present invention.
  • This building may be a house, but also buildings like offices or other utility buildings are conceivable.
  • Figs. 1 and 2 show that the building wall comprises a skeleton including upright building elements, in this case columns 1, and wall elements 2 filling the space between the columns 1.
  • the columns may consist of steel ( Fig. 1a ), wooden ( Fig. 1b ) or concrete ( Fig. 1c ) columns 1a, 1b, 1c.
  • the concrete columns may be prefab columns or may be poured in situ.
  • the wall elements 2 preferably have such dimensions, that they completely fill the space between the columns of one storey, so that there is only one wall element 2 between each adjacent pair of columns 1. This obviates the need for complicated (mechanical) connections between wall elements.
  • Figs. 5 - 7 show the shape of one wall element 2. From Fig. 5 it is clear that the wall element 2 is rectangular. In this embodiment, the width of wall element 2 is 2.5 m, the height 3.0 m and the thickness 0.3 m, but such dimensions may of course be varied in accordance with the particular application and requirements.
  • Figs. 6 and 7 show that only the part of the wall element 2 that is intended to be placed on the outside of the building wall has the dimensions as indicated above. The remainder of the wall element 2 is smaller. Due to these reduced dimensions, there is formed a rim 3 on all four edges of the wall element 2. This rim 3 is flush with the outside surface of the wall element 2 and may have a thickness of circa 60 mm. The length of the rim may for example be circa 90 mm.
  • a recess 4 Adjacent to the opposite surface, intended to form the inner wall surface of the building wall, there is formed a recess 4 having substantially the same dimensions as the rim 3. This recess 4 is also formed on all four sides of the wall element 2. In this way the edges of the wall elements 2 have a stepped configuration of which middle step has a height preferably corresponding to the thickness of the columns 1, while the depth of the first and last step preferably corresponds to half the width of the projected columns 1.
  • a recess having three sides of 200 mm, which is intended for accommodating the columns, as is shown in Fig. 1 .
  • inserts 5 which are placed against the particular columns 1 in order to substantially fill the recess between the wall elements 2.
  • a cover panel 6 may be positioned in the recesses 4 at the two adjacent edges of the wall elements 2 in order to close the recess between two wall elements, so that not only on the outside of the building wall, but also on the inside of the building wall a closed and continuous wall surface is formed.
  • These closed and plane wall surfaces may be covered by covering layers 7 and 8 on the outside and inside of the building wall.
  • columns which have larger dimensions, in particular a greater thickness
  • several situations may be created: first, wall elements having a greater thickness are used so that again completely plane wall surfaces can be obtained, furthermore, the column and/or a covering attached thereto may project on the inside and/or outside of the wall so that the wall surface has interruptions at the position of the columns.
  • Fig. 8 shows more a detailed section of the building wall at the position of a wall element 2.
  • This wall element 2 forms the core of the building wall and is formed of a lightweight, heat insulating and preferably fire retarding, non-shrinking and stabile material in order to give the proper quality to the building wall.
  • This material may for example be modified and pressed cardboard (e.g. as is disclosed in EP-A-1 180 564 ) or some expanded polymer, such as EPS (expanded polystyrene), for example that as offered by Unidek under the name Unidek EPS which is modified according to NEN 6065/6066 in order to obtain fire retarding properties.
  • EPS expanded polymer
  • the covering layer 7 on the outside of the building wall includes a first or base layer 9, preferably of modified resin mortar as is known in the art.
  • This base layer 9 is an adhesive layer in order to properly attach a second or top layer 10, which may be a layer of mineral mortar for example, which has properties to resist weather conditions and other influences which may exist on the outside of a building.
  • Such mineral mortar is also known in the art.
  • the covering layer 8 includes a first or base layer, preferably of modified resin mortar 11, and a second or top layer 12, for example formed by plaster mortar.
  • the total thickness of the covering layers 7 and 8 may be in the range of 20-30 mm, preferably 22-25 mm.
  • a reinforcement layer 13, 14, which may be a woven mat, netting, mesh or the like, for example a glass or carbon fibre reinforced mesh or non-woven material.
  • At least one of the reinforcement layers 13, 14, in this case the reinforcement layer 14 on the inside is positioned near the surface of the covering layer 8 in order to be at the maximum distance from the neutral bending line of the wall element 2 in order to give maximum bending resistance, for example when a wind force is exerted on a building wall.
  • Another advantage of this position of the reinforcement layer 14 is that it provides strength to this layer 8 so that the wall can be used to anchor fixing means, such as nails, screws, and the like in order to attach objects to the wall.
  • the expanded polystyrene material can be obtained in different qualities and in this embodiment, the wall element 2 may be formed of a standard quality, whereas the inserts 5 and cover panel 6 may be formed of higher compression material to provide additional heat insulation and strength around the columns 1 in order to obtain a substantially uniform heat-insulation quality through the entire wall.
  • Fig. 9 shows a variation on the building wall of Figs. 1 and 2 , in which the wall elements 2 are curved around a vertical axis to form a circular wall.
  • Fig. 2 shows a sectional side view of the building of Fig. 1 illustrating not only the structure of the building wall, but also the floors of the building. The floor structure is also shown in Fig. 4 .
  • Each floor comprises floor elements 18 which are interconnected and are formed from similar material as the wall elements 2, i.e. from lightweight, insulating and fire retarding material.
  • the floor elements 18 are interconnected by steel profiles 19 which may be formed from steel sheet, for example with a thickness of 1 mm.
  • Recesses 20 are formed in the sides of the floor elements 18 in order to enable engagement of protruding parts of the steel profiles 19 to ensure proper attachment of the profiles to the floor elements.
  • the floor elements 18 have lower rims 21 and these rims 21 of adjacent floor elements 18 are placed in abutting relationship to form a closed continuous lower surface of the floor.
  • the upper part of the floor element 18 is smaller and has a trapezoid cross section.
  • the floor elements 18 are connected and are supported by stays in order to resist the weight of structural fill-material, such as concrete 22, fibre reinforced resin or the like, which is poured onto the floor elements 18.
  • structural fill-material such as concrete 22, fibre reinforced resin or the like, which is poured onto the floor elements 18.
  • steel reinforcements 23 are placed on the floor elements 18. If necessary, inserts 25 placed in recesses that might still visible after constructing the floors 15-17.
  • a floor finishing 26, a ceiling finishing 27 and the covering layer 8 on the walls are provided, preferably in the final stage.
  • An embodiment of a method of constructing a building is as follows.
  • a foundation in and/or on the underground if necessary at all.
  • This foundation can be relatively light since the building will be much lighter than a traditional building. If a skeleton from steel or wood is used, the steel or wood columns 1 are placed on their foundation in the correct position. Inserts 5 are placed around the respective columns to create column dimensions to fit with the wall elements.
  • the wall elements 2 are then placed against the columns 1, such that the rims 3 are of the wall elements 2 are placed against the outside of the columns 1 and are positioned in abutting relationship with the next wall element 2.
  • Glue may be used to fix the wall elements 2 to the columns 1 and to each other, but other fixing means are conceivable.
  • a cover panel 6 is positioned in the recesses 4 of the wall elements 2 to cover the last side of the column 1. In the corners of the building inserts 28 are provided to fill any remaining gap.
  • the inserts 25 are mounted and the floor elements 18 are positioned on the lower inserts 25. Adjacent floor elements 18 are connected to each other by the profiles 19 and are supported on temporary supports.
  • the fill-material 22 is poured on the floor elements 18, on the profiles 19, on the upper side of the wall elements 2 and the columns positioned below.
  • the wall elements 2 are placed before the columns 1 are formed. Only a reinforcement for the concrete columns 1 is mounted within the recess formed by the adjacent wall elements 2.
  • the cover panels 6 are mounted to form a formwork or shuttering for the concrete which is then poured in the closed recess so that a column of concrete or other structural fill-material, is formed between the wall elements 2.
  • the invention provides a building method and a building that is cost effective.
  • the resulting building may be so light that it can be moved in its entirety, or storeys may be built on the ground and lifted to its position afterwards.
  • the energy- and maintenance cost are relatively low due to the high heat insulation and the low need for maintenance.
  • the flexibility of the building is high due to the light construction which makes it easy to rebuild or extend parts of the building.
  • openings may be closed again by closing or replacing a wall element and new openings may be created after completion of the building.
  • the building can be demounted again and the building materials can be reused. Therefore, the building method is also environmentally friendly.
  • the wall elements may be used in an burglary alarm by integrating parts thereof in the wall elements, for example light conducting fibres, or electrically conducting wires.
  • floors comprising floor elements and cast concrete
  • a floor from steel sections, wooden beams, an insulation layer and a cement finishing layer.
  • Figs. 12-16 show a further embodiment of the building and method according to the invention.
  • Fig. 12 shows a skeleton of a building, including separating or partition walls 29 and floors 30.
  • the dividing walls 29 function as a lightweight building element and separate in this case individual homes which are built in a row.
  • the ends of the dividing walls which are positioned at the outer side of the building more or less act as columns for the outer wall.
  • the wall element 2 forms a complete façade or outside wall between two adjacent dividing walls 29 and floors 30.
  • auxiliary columns 31 in this case in the form of steel sections, which are attached to the floor and ceiling 30.
  • These auxiliary columns 31 may be integrated in the wall elements 2 or may be installed in the skeleton before the wall elements 2 is mounted to the skeleton.
  • Figs. 13-16 show an embodiment of a wall element 2 which fits between two adjacent dividing walls 29. Therefore such wall element may be sized up to a length of 5 or 6 meters or more.
  • this wall element 2 has a laminate structure including layers 32, 33, 34 which are attached, for example glued together.
  • Each layer 32, 33, 34 may be formed of different parts.
  • the (relative) thickness of the various layers may be varied in accordance with the respective requirements.
  • the layers are each formed of different parts and the parts of the different layers being provided in an overlapping relationship so that they support each other.
  • Integrated in the central layer 33 are in this case two horizontal beams 35, 36 made from wood or another suitable material such as plastic or the like.
  • These horizontal beams are incorporated into the wall element 2 during the laminating process.
  • These beams 35, 36 provide rigidity to the large wall element 2 and provide a means for attaching the wall element 2 to the auxiliary columns 31 and any window to the wall element 2.
  • Fig. 14 it is shown that an opening 37 is already left open in the layers 32 and 34 so that after placement of the wall element 2 only layer 33 should be processed in order to finish the wall opening 37 to be able to mount the window.
  • the window or window frame can be mounted to both beams 35 and 36.
  • the beams 35 and 36 can also be used to attach the wall element 2 to one or more auxiliary columns 31.
  • the inner wall layer 34 is recessed at the position where an auxiliary column 31 should be mounted to the wall element 2.
  • the beams 35 and 36 are visible and the auxiliary column 31 can be mounted to the beams 35, 36 by means of self tapping screws or the like which are inserted through a hole in the auxiliary column 31.
  • Other types of attachments are conceivable.
  • the lower horizontal beam 36 has to be interrupted and cut off at the door opening.
  • the doorframe could be attached to the upper horizontal beam 35.
  • an auxiliary column 31 will be positioned next to a door opening in order to provide additional support for the wall element at the position of the door.
  • the door frame could also be attached to an adjacent auxiliary column 31.
  • the covering layer 7 or 8 on the outside or inside of the building may be provided on the wall elements 2 before the windows and/or doors are positioned in the respective openings in the wall element 2. This is advantageous as the windows and doors are preferably mounted in the wall elements 2 as late as possible in order to avoid damage to these parts. This covering layer 7 or 8 will be provided within the opening 37 up to the position where the window frame will be positioned.
  • Fig. 16 shows that the recess 38 is filled with an insert 39 to cover the auxiliary column 31 and to fill the recess 38 in order to create a flush inner wall which can be covered by a continuous covering layer 8.
  • the joint 40 between adjacent wall elements 2 will be filled with a filler material, preferably PUR glue which does not only fill the joint but also connects the adjacent wall elements 2 in a secure manner.
  • a filler material preferably PUR glue which does not only fill the joint but also connects the adjacent wall elements 2 in a secure manner.
  • the large joint 41 between the wall elements 2 and the dividing wall 29 (or between the wall elements 2 and the floor 30 as shown in Fig. 13 ) is filled with a sound insulating material forming a barrier against the transmittal of sound around the dividing walls 29 or floor 30.
  • the invention provides a wall element, in particular an outside wall element, which is durable, yet lightweight, fire resistant and easy to handle so that buildings may be constructed in an simple and quick manner. No extensive scaffolding is necessary, a light mobile device is sufficient to place wall elements above the ground floor.
  • the wall elements may be provided with (meandering) recesses to accommodate heating tubes of a wall and/or floor heating assembly.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Wood Science & Technology (AREA)
  • Building Environments (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Load-Bearing And Curtain Walls (AREA)
  • Finishing Walls (AREA)

Claims (14)

  1. Procédé de construction d'un bâtiment, comprenant les étapes suivantes consistant à :
    fournir une charpente pour le bâtiment, ladite charpente comprenant au moins des éléments (1 ; 29) montants de bâtiment, tels que des colonnes ou des cloisons de démarcation,
    placer au moins un élément (2) de paroi, léger, calorifuge et ignifuge entre chaque paire adjacente desdits éléments montants de bâtiment qui sont positionnés avant que les éléments de paroi ne soient placés, de sorte que les éléments de paroi remplissent complètement l'espace entre les éléments montants,
    fournir à l'intérieur et à l'extérieur des éléments (2) de paroi et au moins à l'extérieur des éléments (1 ; 29) montants de bâtiment une couche de revêtement (7, 8) pour fournir au moins une surface de paroi sensiblement fermée, ladite couche de revêtement ayant des propriétés pour à fournir au moins une résistance au feu à tout le mur.
  2. Procédé selon la revendication 1, dans lequel les éléments montants de bâtiment sont préfabriqués, tels que l'acier, le bois ou le béton préfabriqué, les colonnes (1) qui sont positionnées avant que les éléments de paroi ne soient placés, les éléments de paroi adjacents de préférence en appui pour former une surface de paroi fermée, en particulier à l'extérieur du bâtiment.
  3. Procédé selon la revendication 2, dans lequel des inserts (5) sont placés adjacents aux colonnes (1) pour remplir tout espace entre les colonnes et les éléments de paroi.
  4. Procédé selon l'une quelconque des revendications précédentes, dans lequel des éléments (18) de sol légers, calorifuges sont placés et reliés entre eux, et soutenus si nécessaire, et par la suite un matériau de remblayage structurel, tel que du béton, est versé sur les éléments de sol pour former un sol.
  5. Procédé selon l'une quelconque des revendications précédentes, dans lequel, après que les parois extérieures ont été construites, les parois sont travaillées, pour former des ouvertures et des cavités dans les parois pour élever des portes, des fenêtres, des galeries, etc.
  6. Procédé selon la revendication 1, dans lequel les éléments montants de bâtiment sont des cloisons de démarcation (29) entre des espaces de bâtiment adjacents, les éléments (2) de paroi légers remplissant l'espace entre les cloisons de démarcation.
  7. Procédé selon la revendication 6, dans lequel des colonnes auxiliaires (31) sont fixées à la charpente du bâtiment et sont intégrées dans les éléments (2) de paroi.
  8. Bâtiment comprenant :
    une charpente pour une paroi de bâtiment extérieure au bâtiment, ladite charpente comprenant au moins des éléments montants (1 ; 29) de bâtiment,
    au moins un élément (2) de paroi léger, calorifuge et ignifuge entre chaque paire adjacente desdits éléments montants de bâtiment, remplissant ainsi entièrement l'espace entre les éléments montants de bâtiment,
    une couche (7, 8) de revêtement fournie sur chaque face desdits éléments de paroi et au moins à l'extérieur des éléments montants de bâtiment pour fournir des surfaces de paroi sensiblement fermées, ladite couche de revêtement ayant des propriétés pour fournir au moins une résistance au feu à toute la paroi , la couche de revêtement sur la surface de paroi interne comprenant une couche de base en mortier de résine modifiée et de préférence une couche supérieure en mortier de plâtre, la couche de couverture sur la surface de paroi externe comprenant une couche de base en mortier de résine modifiée et de préférence une couche supérieure en mortier minéral.
  9. Bâtiment selon la revendication 8, dans lequel la couche de couverture comprend une couche de renforcement, telle qu'un tapis tissé, du grillage, du treillis ou similaire, et de préférence une couche renforcée de fibres.
  10. Bâtiment selon la revendication 8 ou 9, dans lequel la couche de revêtement sur la surface de paroi interne comprend une couche de base en mortier de résine modifiée, et de préférence une couche supérieure en mortier de plâtre, tandis que la couche de couverture sur la surface de paroi externe peut comprendre une couche de base en mortier de résine modifiée et de préférence une couche supérieure en mortier minéral.
  11. Bâtiment selon les revendications 9 et 10, dans lequel la couche de renforcement sur la surface de paroi interne est située sur la couche supérieure, tandis que la couche de renforcement sur la surface de paroi externe est située sur la couche de base.
  12. Bâtiment selon l'une quelconque des revendications 8 à 11, comprenant des ouvertures entre les éléments montants de bâtiment, lesdites ouvertures étant fermées par des portes, des fenêtres ou similaires.
  13. Bâtiment selon l'une quelconque des revendications 8 à 12, comprenant un sol, construit à partir d'éléments de sol légers, calorifuges et ignifuges reliés entre eux et du béton comme matériau de remblayage versé sur les éléments de sol, l'interconnexion étant de préférence effectuée au moyen de fines sections de profil en acier.
  14. Élément de paroi pour un bâtiment selon l'une quelconque des revendications 8 à 13, dans lequel l'élément de paroi est construit en matériau léger, calorifuge et ignifuge, tel que le polystyrène ou le carton modifié, l'élément de paroi ayant une épaisseur d'environ 200 à 400 mm, de préférence d'environ 300 mm, et étant sensiblement rectangulaire ayant une hauteur et une largeur de plus de 2 m, de préférence d'environ 3x2,5 m à 3x6 m, l'élément étant fourni sur tous les côtés avec un bord s'étendant latéralement depuis l'élément et affleurant d'un côté de l'élément, les côtés de l'élément de paroi ayant une configuration étagée comprenant au moins deux étapes.
EP04105914A 2003-11-21 2004-11-19 Procédé de construction d'un bâtiment, ce bâtiment, et élément de mur pour ceux-ci Active EP1536077B1 (fr)

Priority Applications (4)

Application Number Priority Date Filing Date Title
PL04105914T PL1536077T3 (pl) 2003-11-21 2004-11-19 Sposób konstrukcji budynku, ten budynek i element ścienny do zastosowania w tym budynku
SI200430984T SI1536077T1 (sl) 2003-11-21 2004-11-19 Postopek za gradnjo stavbe, tovrstna stavba in stenski element za uporabo v njej
EP04105914A EP1536077B1 (fr) 2003-11-21 2004-11-19 Procédé de construction d'un bâtiment, ce bâtiment, et élément de mur pour ceux-ci
CY20081101468T CY1108683T1 (el) 2003-11-21 2008-12-18 Μεθοδος κατασκευης κτιριου, τετοιο κτιριο, και στοιχειο τοιχωματος για χρηση σε αυτο

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
EP03104329 2003-11-21
EP03104329 2003-11-21
EP04105914A EP1536077B1 (fr) 2003-11-21 2004-11-19 Procédé de construction d'un bâtiment, ce bâtiment, et élément de mur pour ceux-ci

Publications (2)

Publication Number Publication Date
EP1536077A1 EP1536077A1 (fr) 2005-06-01
EP1536077B1 true EP1536077B1 (fr) 2008-10-08

Family

ID=34924132

Family Applications (1)

Application Number Title Priority Date Filing Date
EP04105914A Active EP1536077B1 (fr) 2003-11-21 2004-11-19 Procédé de construction d'un bâtiment, ce bâtiment, et élément de mur pour ceux-ci

Country Status (11)

Country Link
EP (1) EP1536077B1 (fr)
AT (1) ATE410565T1 (fr)
CY (1) CY1108683T1 (fr)
DE (1) DE602004016937D1 (fr)
DK (1) DK1536077T3 (fr)
ES (1) ES2315617T3 (fr)
HR (1) HRP20080681T3 (fr)
PL (1) PL1536077T3 (fr)
PT (1) PT1536077E (fr)
RS (1) RS51248B (fr)
SI (1) SI1536077T1 (fr)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GR1006023B (el) * 2005-06-27 2008-09-01 Κωνσταντινος Δημητριου Ζαβλιαρης Συστημα δομησης κτιριων με την χρηση δομικων στοιχειων απο παραμενοντα τυπο.
ITPG20090007A1 (it) * 2009-03-06 2009-06-05 Eros Pannacci Sistema di tamponatura irrigidente di strutture intelaiate.
CN102817426A (zh) * 2011-06-08 2012-12-12 吴淑环 一种建筑复合墙体
CN113027037A (zh) * 2021-03-11 2021-06-25 富思特新材料科技发展股份有限公司 一种外墙板、其加工方法及建筑物
CN113818592B (zh) * 2021-10-18 2022-11-01 福建金鼎建筑发展有限公司 一种装配式建筑中的t字型水平连接节点

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2225591B1 (fr) * 1973-04-12 1980-04-18 Pennecot Jean
US4193240A (en) * 1978-08-10 1980-03-18 Odoerfer Hans F Exterior wall composition
US4823534A (en) 1988-02-17 1989-04-25 Hebinck Carl L Method for constructing insulated foam homes
US5353562A (en) 1991-07-03 1994-10-11 Decker Wendell T Foam panel for construction
JPH0874358A (ja) 1994-09-02 1996-03-19 Yoshino Sekko Kk 間仕切り壁
US5617686A (en) 1995-06-07 1997-04-08 Gallagher, Jr.; Daniel P. Insulating polymer wall panels
US5765333A (en) 1996-04-03 1998-06-16 Cunningham; Dale W. Unitized post and panel building system
US6298622B1 (en) * 1996-10-15 2001-10-09 Plastedil, S.A. Self-supporting construction element of expanded plastics, in particular for manufacturing floor elements and walls of buildings in general
CA2441927C (fr) * 2001-03-27 2010-02-16 Owens Corning Gainage isolant structurel et procedes de gainage associes

Also Published As

Publication number Publication date
ATE410565T1 (de) 2008-10-15
SI1536077T1 (sl) 2009-02-28
PT1536077E (pt) 2009-01-09
PL1536077T3 (pl) 2009-05-29
EP1536077A1 (fr) 2005-06-01
CY1108683T1 (el) 2014-04-09
HRP20080681T3 (en) 2009-02-28
DK1536077T3 (da) 2009-02-02
RS51248B (sr) 2010-12-31
ES2315617T3 (es) 2009-04-01
DE602004016937D1 (de) 2008-11-20

Similar Documents

Publication Publication Date Title
US7946092B2 (en) Method of constructing a building, such building, and wall and floor elements for use therein
US4669240A (en) Precast reinforced concrete wall panels and method of erecting same
US20080196349A1 (en) Connected structural panels for buildings
EP2417308B1 (fr) Bâtiment et procédé de construction d'un bâtiment
CA2829321C (fr) Procede de construction utilisant des panneaux s'etendant sur plusieurs etages
US6247280B1 (en) Insulated wall construction and forms and method for making same
US8033062B2 (en) Type of building, method and means for erecting it
US6263628B1 (en) Load bearing building component and wall assembly method
US20070044426A1 (en) Lightweight Wall Structure For Building Construction
US20090113820A1 (en) Prefabricated wall panel system
US20090311932A1 (en) Structural insulated panel construction for building structures
US20070125042A1 (en) Structural insulated panel construction for building structures
AU2008286675A1 (en) Panel building system
IL221038A (en) Building board, building board structure and method of manufacture
WO2011154929A2 (fr) Module de panneau de paroi de remplissage structurel
MX2013014089A (es) Sistema de muro reforzado.
US3678638A (en) Building construction of modular units with settable material therebetween
EP1736609B1 (fr) Systeme de construction a partir de panneaux prefabriques et panneau prefabrique
EP1536077B1 (fr) Procédé de construction d'un bâtiment, ce bâtiment, et élément de mur pour ceux-ci
ZA200901736B (en) Improved construction system for buildings
EP2707550A1 (fr) Construction murale et bâtiment ayant une telle construction murale, procédé de construction d'un bâtiment
EP1164231A2 (fr) Améliorations relatives à des murs isolés
WO2010138993A1 (fr) Système de construction modulaire
WO2002020916A1 (fr) Panneau de construction modulaire
WO2002010529A1 (fr) Batiment prefabrique

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IS IT LI LU MC NL PL PT RO SE SI SK TR

AX Request for extension of the european patent

Extension state: AL HR LT LV MK YU

17P Request for examination filed

Effective date: 20051031

AKX Designation fees paid

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IS IT LI LU MC NL PL PT RO SE SI SK TR

AXX Extension fees paid

Extension state: LV

Payment date: 20051031

Extension state: YU

Payment date: 20051031

Extension state: MK

Payment date: 20051031

Extension state: HR

Payment date: 20051031

Extension state: LT

Payment date: 20051031

Extension state: AL

Payment date: 20051031

17Q First examination report despatched

Effective date: 20051208

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

RTI1 Title (correction)

Free format text: METHOD OF CONSTRUCTING A BUILDING, SUCH BUILDING, AND WALL ELEMENT FOR USE THEREIN

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IS IT LI LU MC NL PL PT RO SE SI SK TR

AX Request for extension of the european patent

Extension state: AL HR LT LV MK YU

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

REF Corresponds to:

Ref document number: 602004016937

Country of ref document: DE

Date of ref document: 20081120

Kind code of ref document: P

RAP2 Party data changed (patent owner data changed or rights of a patent transferred)

Owner name: VEERHUIS BEHEER B.V.

REG Reference to a national code

Ref country code: SE

Ref legal event code: TRGR

REG Reference to a national code

Ref country code: HR

Ref legal event code: TUEP

Ref document number: P20080681

Country of ref document: HR

REG Reference to a national code

Ref country code: RO

Ref legal event code: EPE

REG Reference to a national code

Ref country code: PT

Ref legal event code: SC4A

Free format text: AVAILABILITY OF NATIONAL TRANSLATION

Effective date: 20081223

REG Reference to a national code

Ref country code: GR

Ref legal event code: EP

Ref document number: 20080403535

Country of ref document: GR

REG Reference to a national code

Ref country code: DK

Ref legal event code: T3

REG Reference to a national code

Ref country code: HR

Ref legal event code: T1PR

Ref document number: P20080681

Country of ref document: HR

REG Reference to a national code

Ref country code: ES

Ref legal event code: FG2A

Ref document number: 2315617

Country of ref document: ES

Kind code of ref document: T3

REG Reference to a national code

Ref country code: PL

Ref legal event code: T3

REG Reference to a national code

Ref country code: HU

Ref legal event code: AG4A

Ref document number: E005025

Country of ref document: HU

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

26N No opposition filed

Effective date: 20090709

REG Reference to a national code

Ref country code: HR

Ref legal event code: ODRP

Ref document number: P20080681

Country of ref document: HR

Payment date: 20151109

Year of fee payment: 12

REG Reference to a national code

Ref country code: FR

Ref legal event code: PLFP

Year of fee payment: 12

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: BG

Payment date: 20151125

Year of fee payment: 12

Ref country code: FI

Payment date: 20151127

Year of fee payment: 12

Ref country code: GR

Payment date: 20151127

Year of fee payment: 12

Ref country code: IE

Payment date: 20151130

Year of fee payment: 12

Ref country code: DK

Payment date: 20151125

Year of fee payment: 12

Ref country code: CH

Payment date: 20151127

Year of fee payment: 12

Ref country code: EE

Payment date: 20151104

Year of fee payment: 12

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: MC

Payment date: 20151104

Year of fee payment: 12

Ref country code: RO

Payment date: 20151109

Year of fee payment: 12

Ref country code: LU

Payment date: 20151202

Year of fee payment: 12

Ref country code: SK

Payment date: 20151102

Year of fee payment: 12

Ref country code: SE

Payment date: 20151127

Year of fee payment: 12

Ref country code: CY

Payment date: 20151103

Year of fee payment: 12

Ref country code: HU

Payment date: 20151106

Year of fee payment: 12

Ref country code: CZ

Payment date: 20151111

Year of fee payment: 12

Ref country code: SI

Payment date: 20151102

Year of fee payment: 12

Ref country code: PT

Payment date: 20151104

Year of fee payment: 12

Ref country code: IS

Payment date: 20151102

Year of fee payment: 12

Ref country code: AT

Payment date: 20151103

Year of fee payment: 12

REG Reference to a national code

Ref country code: FR

Ref legal event code: PLFP

Year of fee payment: 13

REG Reference to a national code

Ref country code: HR

Ref legal event code: PBON

Ref document number: P20080681

Country of ref document: HR

Effective date: 20161119

REG Reference to a national code

Ref country code: LT

Ref legal event code: MM9D

Effective date: 20161119

REG Reference to a national code

Ref country code: EE

Ref legal event code: MM4A

Ref document number: E002988

Country of ref document: EE

Effective date: 20161130

REG Reference to a national code

Ref country code: DK

Ref legal event code: EBP

Effective date: 20161130

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

REG Reference to a national code

Ref country code: SE

Ref legal event code: EUG

REG Reference to a national code

Ref country code: AT

Ref legal event code: MM01

Ref document number: 410565

Country of ref document: AT

Kind code of ref document: T

Effective date: 20161119

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20170531

Ref country code: RO

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20161119

Ref country code: GR

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20170612

Ref country code: LI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20161130

Ref country code: CY

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20161119

Ref country code: EE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20161130

Ref country code: FI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20161119

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20161130

Ref country code: CZ

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20161119

Ref country code: SK

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20161119

REG Reference to a national code

Ref country code: SK

Ref legal event code: MM4A

Ref document number: E 4615

Country of ref document: SK

Effective date: 20161119

REG Reference to a national code

Ref country code: IE

Ref legal event code: MM4A

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: HU

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20161120

Ref country code: AT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20161119

Ref country code: SI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20161120

Ref country code: SE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20161120

Ref country code: PT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20170519

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LU

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20161130

REG Reference to a national code

Ref country code: SI

Ref legal event code: KO00

Effective date: 20170804

REG Reference to a national code

Ref country code: FR

Ref legal event code: PLFP

Year of fee payment: 14

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20161119

Ref country code: DK

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20161130

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20171129

Year of fee payment: 14

Ref country code: FR

Payment date: 20171127

Year of fee payment: 14

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: BE

Payment date: 20171127

Year of fee payment: 14

Ref country code: ES

Payment date: 20171201

Year of fee payment: 14

Ref country code: GB

Payment date: 20171127

Year of fee payment: 14

Ref country code: IT

Payment date: 20171123

Year of fee payment: 14

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MC

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20161130

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: BG

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20170808

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: PL

Payment date: 20181031

Year of fee payment: 15

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: TR

Payment date: 20181107

Year of fee payment: 15

REG Reference to a national code

Ref country code: DE

Ref legal event code: R119

Ref document number: 602004016937

Country of ref document: DE

GBPC Gb: european patent ceased through non-payment of renewal fee

Effective date: 20181119

REG Reference to a national code

Ref country code: BE

Ref legal event code: MM

Effective date: 20181130

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20181119

Ref country code: DE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20190601

Ref country code: FR

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20181130

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: BE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20181130

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20181119

REG Reference to a national code

Ref country code: ES

Ref legal event code: FD2A

Effective date: 20200103

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: ES

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20181120

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: PL

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20191119

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: TR

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20191119

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: NL

Payment date: 20231126

Year of fee payment: 20