EP1383985B1 - Wellhead product testing system - Google Patents
Wellhead product testing system Download PDFInfo
- Publication number
- EP1383985B1 EP1383985B1 EP02718397A EP02718397A EP1383985B1 EP 1383985 B1 EP1383985 B1 EP 1383985B1 EP 02718397 A EP02718397 A EP 02718397A EP 02718397 A EP02718397 A EP 02718397A EP 1383985 B1 EP1383985 B1 EP 1383985B1
- Authority
- EP
- European Patent Office
- Prior art keywords
- wellhead
- test
- trees
- manifold
- tree
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000012360 testing method Methods 0.000 title claims abstract description 158
- 238000004519 manufacturing process Methods 0.000 claims abstract description 76
- 238000000034 method Methods 0.000 claims abstract description 52
- 238000000605 extraction Methods 0.000 claims abstract description 15
- 229930195733 hydrocarbon Natural products 0.000 claims abstract description 9
- 150000002430 hydrocarbons Chemical class 0.000 claims abstract description 9
- 239000004215 Carbon black (E152) Substances 0.000 claims abstract description 8
- 238000003032 molecular docking Methods 0.000 claims description 29
- 239000000470 constituent Substances 0.000 claims description 3
- 239000012530 fluid Substances 0.000 description 14
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 12
- 238000004458 analytical method Methods 0.000 description 5
- 238000010348 incorporation Methods 0.000 description 2
- 238000002347 injection Methods 0.000 description 2
- 239000007924 injection Substances 0.000 description 2
- 238000002955 isolation Methods 0.000 description 2
- 238000012423 maintenance Methods 0.000 description 2
- 239000000126 substance Substances 0.000 description 2
- 241000237858 Gastropoda Species 0.000 description 1
- 238000004873 anchoring Methods 0.000 description 1
- 230000000295 complement effect Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000007257 malfunction Effects 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000013011 mating Effects 0.000 description 1
- -1 oil and gas Chemical class 0.000 description 1
- 230000000737 periodic effect Effects 0.000 description 1
- 238000005191 phase separation Methods 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
- 239000000243 solution Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B43/00—Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
- E21B43/01—Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells specially adapted for obtaining from underwater installations
- E21B43/017—Production satellite stations, i.e. underwater installations comprising a plurality of satellite well heads connected to a central station
- E21B43/0175—Hydraulic schemes for production manifolds
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B34/00—Valve arrangements for boreholes or wells
- E21B34/02—Valve arrangements for boreholes or wells in well heads
- E21B34/04—Valve arrangements for boreholes or wells in well heads in underwater well heads
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B43/00—Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
- E21B43/34—Arrangements for separating materials produced by the well
- E21B43/36—Underwater separating arrangements
Definitions
- the present invention relates to a method and apparatus for diverting the fluid flow from a wellhead tree or trees in a hydrocarbon extraction system to a testing means for analysing its content.
- the invention is described in the context of a system for extracting hydrocarbons, such as oil and gas, from a sub-sea location, but-is equally applicable to extraction from other locations, particularly those in which access creates a problem for example in swampy areas.
- References to wellhead trees can alternatively be taken as references to wellheads per se.
- FIG. 1 A typical prior art system is shown in Figure 1.
- Such a system generally includes plural wellhead trees 2, 4, 6 and 8 on the seabed through which a combination of oil, gas and water flow from a deposit below the seabed.
- the trees are generally connected to a manifold system 10 including valves which are operable to selectively divert flows from the trees into a production pipeline 12 leading to a host facility 14 which may be tens of kilometres away and a test pipeline 16 also leading to the host facility.
- the valves in the manifold system generally include a main valve 18 for each tree, which is typically diver or remote vehicle operable and not regularly opened and closed during normal operation of the system, and a pair of diverter valves including a production valve 20 (opened when flow from the associated tree is to enter the production pipeline) and a test valve 22 (which is opened instead of the production valve 20 when flow is to enter the test pipeline). It is necessary to regularly analyse the flow from each tree in turn to ascertain that optimum extraction is occurring. When, for example output from tree 2 is to be tested, its associated production valve 20 is closed and test valve 22 is opened. While flow from the trees 4, 6 and 8 continues to flow into the production pipeline, that from tree 2 flows into the test pipeline.
- the output of tree 2 can be collected at the host facility for analysis. Once the valves are returned to the states shown in Figure 1, the operation can be repeated for the other trees.
- they are generally remotely actuable and controlled by means of signals sent to the manifold system from the host facility by an integrated service umbilical 24 which enters the manifold system at an umbilical termination assembly 26 from where the signals and power are directed to a sub-sea control module 28 and on to the trees and diverter valves (signal and power connections 30, shown by dotted lines are only shown for tree 8, the other connections having been omitted for clarity).
- Another prior art system is known from for instance GB-A-2 028 400.
- one object of the invention is to eliminate such remotely actuable diverter valves and their associated actuators from the manifold system.
- a sub-sea control module 28 When a sub-sea control module 28 is installed in the manifold system, it involves the mating of hydraulic, electrical and possibly chemical injection lines. The making and breaking of such connections in deep water poses potential problems and accordingly it is a further preferred object of the invention to eliminate, when possible, the requirement for such a control module in the manifold system.
- the inventors have recognised that, because the wellhead trees by necessity include remotely actuable valves with associated actuators (usually hydraulic) and a sub-sea control module for effecting actuation of the valves, the overall reliability of the trees is not significantly reduced by the incorporation of additional remotely actuable valves and associated actuators.
- FIG. 2 An alternative prior system for analysing flow from a particular tree is shown in Figure 2 in which parts corresponding to those shown in Figure 1 are designated with the same numerals.
- each test valve 22 is connected to a multi-phase flow meter 40 rather than to a test pipeline 16.
- This arrangement avoids the problem of having to flush fluid from a possibly very long pipeline between the testing of the flow from each tree and the problem associated with phase separation and other changes which tend to occur as the test flow travels along the pipeline.
- Such multiphase flow meters are however very expensive, prone to malfunction and are not particularly accurate.
- a method of controlling flows from plural hydrocarbon extraction wellhead trees in an extraction system including plural wellhead trees connected by a pipeline network to a host facility via a manifold system situated remotely from the host facility, the method involving selective opening and closing of valves controlling the flows through the pipeline network to enable selective delivery of output from a selected wellhead tree to testing means for analysing the content of the output from the selected wellhead tree
- the method includes the steps of providing each wellhead tree with a production flow outlet, a test flow outlet and valve means operable to selectively divert the output from the wellhead tree through one of the outlets and operating the valve means to divert the output of one wellhead tree only to the testing means.
- the manifold assembly simply routes flows into the production and test pipelines, the need for a sub-sea control module in the part of the manifold assembly permanently connected to the seabed can be avoided.
- the manifold assembly comprises a docking manifold in which insert retrievable system modules are located, since such system modules can each contain their own system power and control modules.
- the method involves the step of providing each wellhead tree with a production flow valve and a test flow valve for respectively controlling output through the production and test flow outlets which valves constitute the valves means of the wellhead tree.
- the method includes the step of connecting the test flow outlets of two or more wellhead trees with each other by a test conduit to form a wellhead tree group and connecting the test conduit to the manifold system. More preferably two or more wellhead trees of the group are connected in parallel to the test conduit.
- the method includes the step of opening the test flow valve of a selected one of the wellhead trees of the group only while maintaining the others closed and passing output from the selected wellhead tree to the testing means via the test conduit.
- the output from the selected wellhead tree may pass through a portion of the test conduit connecting two wellhead trees prior to passing through a different part of the test conduit for delivery to the manifold system.
- the method includes the step of connecting the test flow outlet of each wellhead tree to the manifold system by an individual test conduit.
- the method involves the step of opening the test flow valve of a selected one of the wellhead trees only while maintaining the others closed and passing output from the selected wellhead tree to the testing means via the corresponding individual test conduit.
- the manifold system comprises a docking manifold for receiving one or more system modules for acting on wellhead tree outputs flowing through the manifold system and the method includes docking at least one such system module in the docking manifold.
- the use of such system modules permits different production phases of an oil field to be catered for by substituting appropriately configured system modules as explained more fully below.
- At least one system module docked in the docking manifold may simply provide throughflow connection firstly between the production flow outlets of the wellhead trees and a production pipeline connecting the docking manifold and the host facility and secondly between the test flow outlets of the wellhead trees and a test pipeline connecting the docking manifold and the testing means which is situated at the host facility, the method including the step of conveying output from a selected one the wellhead trees to the testing means via the system module.
- Such a method is appropriate in the early production phase of the oil field when oil with relatively little water and/or gas issues from the wellhead trees under high pressure.
- At least one system module docked in the docking manifold includes the testing means and separating means for separating constituent components of the flows from the wellhead trees, the method including the step of operating the valve means of the wellhead trees to divert the output from one selected wellhead tree test flow outlet only to the separating means and measuring and/or analysing its content with the testing means.
- the separating means may also constitute the testing means.
- At least one system module docked in the docking manifold firstly provides simple through-flow connection between the production flow outlets and a production pipeline connecting the docking manifold and the host facility and secondly includes the testing means, the method including the step of conveying output from a selected one of the wellhead trees to the testing means of the system module and analysing its content.
- control signals are routed to the wellhead trees via the manifold system but without passing through any control means forming part of the manifold system.
- the invention also provides a method of operating a hydrocarbon extraction system including the above method and including the step of conveying mainstream production fluid (such as gas) from the separating means through the test pipeline used during an earlier phase of production to convey wellhead output to the test facility for testing.
- mainstream production fluid such as gas
- the invention also provides apparatus for controlling flows from plural hydrocarbon extraction wellhead trees in an extraction system including plural wellhead trees connected by a pipeline network to a host facility via a manifold system situated remotely from a host facility characterised by each wellhead tree having a production flow outlet, a test flow outlet and valve means operable to selectively divert output from the wellhead tree through one of the outlets and an interconnecting pipeline network for delivering the output from one of the test flow outlets to the testing means.
- a wellhead tree including a production flow outlet and a test flow outlet and valve means operable to selectively divert output from the wellhead tree.
- a first system for putting the inventive method into practice is shown in Figures 3 and 4.
- the system includes four wellhead trees 50, 52, 54 and 56 mounted on the seabed and connected by pipes to a seabed manifold system 58 which is connected by a production pipeline 60 and a test pipeline 62 to a host facility 64 (shown in Figure 3 as a floating production unit).
- the test pipeline 62 may be used in later production phases for the conveyance of a production fluid such as gas.
- An integrated service umbilical 68 containing electrical, hydraulic and also possibly chemical injection line(s) leads from the host facility 64 to an umbilical termination assembly 66 which may conveniently be mounted on the manifold system 58 to provide a secure anchoring location but may be situated elsewhere.
- the wellhead tree 50 is shown in greater detail in Figure 4. Fluid flowing out of the tree is divertable at a junction 70 towards a production flow outlet 72 through a production flow valve 74 or towards a test flow outlet 76 through a test flow valve 78. These two valves are respectively controlled by actuators 80 and 82 which are controlled by a sub-sea control module 84 connected by a power and signal carrying control line 86 to the umbilical termination assembly 66.
- the production flow outlet 72 is connected by a production conduit 88 to a production feeder pipe 90 in the manifold system which leads into an inlet production header pipe 92.
- the production feeder pipe 90 has a main valve 96 which is operable by a diver or remotely operated vehicle.
- the inlet production header pipe 92 is linked by a further valve 112 to the production pipeline 60.
- test flow outlet 76 of the tree 50 is connected by a branch pipe 110 to a junction 98 in a test conduit 104 (which interconnects the wellhead trees) via an isolation valve 100 which is diver or remotely operated vehicle actuable.
- test flow outlet 76 of tree 50 is connected via the test conduit 104 to a test feeder pipe 106 in the manifold system 58 which leads into an inlet test header pipe 108 which is in turn connected by a valve 114 to the test pipeline 62.
- the test feeder pipe 106 contains a main valve 97 similar to main valve 96.
- test flow outlets 76 of trees 52, 54 and 56 are respectively connected by branch pipes 110 to interconnecting sections of the test conduit 104. Serially adjacent trees are accordingly interconnected in series. While four trees are depicted in Figure 3, other numbers of trees could be connected in a like manner.
- valves 96, 97 and valves 112 and 114 will remain open at all times.
- test flow valves 78 of the trees are closed and the production flow valves 74 will be open. Production fluid will accordingly flow through the production conduits 88 and production feeder pipes 90 into the inlet production header pipe 92 from where it is routed via the production pipeline 60 to the host facility 64.
- test flow will travel directly into the test conduit 104, through the test feeder pipe 106 and into the inlet test header pipe 108 from where it is routed to the host facility 64 via the test pipeline 62. If the tree concerned is one of the trees 52, 54 or 56, the test flow from the tree will pass through one or more of the interconnecting portions of the test conduit 104 before entering the main part of the test conduit 104.
- test flow valve 78 and production flow valve 74 are closed and opened respectively to return to the normal production mode and testing of the flow from another well can commence.
- the loop of pipe 116 interconnecting the production and test header pipes 92 and 108 is a so-called "pigging loop" and used for clearing the pipes in a manner which is well known in the art and not of direct relevance to the present invention.
- the valves 118 are used when pigging occurs.
- the manifold system of Figure 3 is replaced by a docking manifold 130 containing the pipes shown and adapted to receive two system modules 132. It may be designed to accommodate more than two such modules. Different modules, such as those shown in Figures 8 and 10 may be employed instead depending on what functions the modules are to perform.
- each system module 132 includes a first part 134 of a multi-pipe connector 138 which is engageable with complementary second part 136 of the multi-pipe connector 138.
- Pipes in the second part 136 are connected to the inlet production header 92 and the inlet test header 108 for routing fluid(s) from the trees 50, 52, 54 and 56 into the system module 132 and to an outlet production header 140, an outlet test header 142 and an outlet water header 144 for routing fluid(s) away from the system module 132.
- the umbilical termination assembly 66 is shown separated from the docking manifold 130 but could be mounted thereon and divides the integrated service umbilical 68 into two module umbilicals 146 each of which terminates in a wet mateable connection 147 for connection to a system power and control module 148 of the system module when it engages the docking manifold (connection not shown in Figure 6).
- the system module shown in Figure 6 is for use during an early production phase of the oil field, at which stage oil flows from the trees at a sufficiently high pressure that gas does not tend to break out of solution and form gas slugs in the production pipeline.
- the system modules accordingly include a production loop 150 which connects the inlet production header 92 to the outlet production header 140 and a test loop 152 which connects the inlet test header 108 to the outlet test header 142.
- the outlet water header 144 is not used with this particular system module 132.
- Control lines which route signals from the wet mateable connection 147 to the trees, are only partially shown for reasons of clarity.
- the trees and the interconnections therebetween and between the trees and the docking manifold 130 will be as described with reference to Figures 3 and 4.
- the method of routing the flow from one particular tree to the host facility will only differ in that production flow will pass into one of the two system modules 132 and pass around one of the production loops 150 and any test flow entering the docking manifold 130 via the test conduit 104 will pass into one of the system modules and around one of the test loops 152.
- FIG. 7 A third system which can be used to perform the method according to the invention is shown in Figures 7 and 8. Components of the system which correspond to those shown in Figures 3 to 6 are designated with the same numerals and will not be described in detail below.
- the system shown in Figures 7 and 8 differs from that shown in Figures 5 and 6 in that it does not include a test pipeline 62 and it includes a different system module 158 having a single loop 160 containing a multi-phase flow meter 162 for analysing the content of fluid(s) passing therethrough.
- the pigging valves 118 in the docking manifold 130 are open and the valve 114 is closed so that all fluid flowing out of the system modules 158 is routed through the production pipeline 60.
- first feed pipe 164 connected to the inlet production header 92 is controlled by a first feed valve 166 and flow through a second feed pipe 168 connected to the inlet test header 108 is controlled by a second feed valve 170.
- the configuration shown in Figure 8 corresponds to normal production (i.e. testing not taking place).
- a test flow diverted from a particular tree into the test header 108 in the manner described above, can be routed through the meter 162 and analysed. Test flows from the different trees can be diverted through the meter 162 for this purpose before valves 166 and 170 are opened and closed respectively so that normal production can be resumed.
- Information from the meter 162 can be processed locally by the control module 148 and used to control the trees or relayed to the host facility 64 for processing.
- FIG. 9 A fourth system which can be used to perform the method according to the invention is shown in Figures 9 and 10. Components of the system which correspond to those shown in Figures 3 to 8 are designated with the same numerals and are not described in detail below.
- the system shown in Figures 9 and 10 differs from that shown in Figures 5 and 6 in that it includes two system modules 180 for separating flows received from the trees via the inlet production header 92 into its oil, gas and water constituent parts and delivers these separately to separate ports 182, 184 and 186 of the first part 134 of the multi-pipe connector 138.
- the multi-pipe connector connects: (i) the oil port 182 to the outlet production header 140 (as in Figure 5); (ii) the gas port 184 to an outlet gas header 188; and the water port 186 to outlet water header 144. Since separation and analysis of the flows can occur within the system module 180, there is no need to route tree flows back to the host facility 64 for analysis.
- the outlet test header 142 and test pipeline 62 are respectively redesignated as an outlet gas manifold 188 and a gas pipeline 190 for delivering gas from the system module 180 to the host facility.
- This double use of the pipeline 62/190 obviates the need to provide three separate pipelines (for oil, gas and test flows) from the docking manifold 130 to the host facility 64.
- the outlet water header 144 is connected to a water disposal well 192.
- a separator chamber 194 in the system module 180 is supplied with flows from the trees either via a first feed pipe 164 connected to the inlet production header 92 or via a second feed pipe 168 connected to the inlet test header 108.
- First and second feed valves 166 and 170 in these pipes respectively are operable as described with reference to Figure 8 to divert production flow from all of the wells into the separator chamber or merely divert a test flow from one of the trees thereinto, also as described above.
- the manner in which components of the system module 180 act on fluids flowing therethrough will not be described in detail since it is not strictly relevant to the present invention.
- the components included in the system module 180 are labelled as follows: fluid interface level sensor 196; pressure sensor 198; modulating valves 200; flow meters 202; pumps 204; failsafe valve 206; and non-return valves 208.
- the system power and control module 148 receives signals from and controls the operation of most these components and others in the system modules 180.
- an intermediate system module (not shown) may be used which includes a two-phase separator for separating the flows into oil and gas or water components only.
- FIG. 11 A fifth system which can be used to perform a method according to the invention is shown in Figures 11 and 12. Components of the system which correspond to those shown in Figures 3 to 10 are designated with like numerals and not described in detail below.
- system modules 132 shown in Figure 11 correspond to that shown in Figure 6. As subsequent production phases of the oil field are entered, different system modules can be substituted for the system modules 132 as described above.
- test flow outlet 76 of each tree 212 is connected by an individual test conduit 210 to the inlet test header 108. Furthermore, no interconnecting pipes are provided to link the test flow outlets 76 of the trees 212 and the trees 212 do not include isolation valves 100 or branch pipes 110.
- valve means forming part of the wellhead trees has been described, the production and test flow valves 74 and 78 may be closely associated with the associated tree rather than forming part thereof.
- the integrated service umbilical 68 described may be replaced by one or more leading directly from the host facility to the wellhead trees.
- header pipe referred to above could be described as an individual sub manifold within the associated manifold system or docking manifold.
Landscapes
- Life Sciences & Earth Sciences (AREA)
- Engineering & Computer Science (AREA)
- Geology (AREA)
- Mining & Mineral Resources (AREA)
- Physics & Mathematics (AREA)
- Environmental & Geological Engineering (AREA)
- Fluid Mechanics (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Pipeline Systems (AREA)
- Paper (AREA)
- Telephone Function (AREA)
- Production Of Liquid Hydrocarbon Mixture For Refining Petroleum (AREA)
- Flow Control (AREA)
- Testing Or Calibration Of Command Recording Devices (AREA)
- Control And Other Processes For Unpacking Of Materials (AREA)
- Perforating, Stamping-Out Or Severing By Means Other Than Cutting (AREA)
- Diaphragms For Electromechanical Transducers (AREA)
- Manufacture Of Iron (AREA)
- Treatment Of Sludge (AREA)
- Pressure Welding/Diffusion-Bonding (AREA)
- Holo Graphy (AREA)
- Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
Description
- Figure 1
- shows a typical prior art system for diverting wellhead tree output flows to a host facility for testing
- Figure 2
- shows a prior art system for diverting wellhead tree output flows to a testing device associated with a sub-sea manifold system
- Figure 3
- shows a system according to the invention for diverting wellhead tree output flows to a host facility for testing
- Figure 4
- shows a detail of flow diverting valves situated at each wellhead tree according to the invention
- Figure 5
- shows a second system according to the invention with a docking manifold in which two retrievable system modules are installable
- Figure 6
- shows the type of system module for use in the system shown in Figure 5
- Figure 7
- shows a variant of the system shown in Figure 5 for use with alternative system modules
- Figure 8
- shows the type of system module for use in the system shown in Figure 7
- Figure 9
- shows a further variant of the system shown in Figure 5 for use with a further alternative system module
- Figure 10
- shows the type of system module for use in the system shown in Figure 9
- Figure 11
- shows a further variant of the system shown in Figure 5 including alternative connections to the wellhead trees; and
- Figure 12
- shows details of flow diverting valves situated at each wellhead tree of the system shown in Figure 11.
Claims (18)
- A method of controlling flows from plural hydrocarbon extraction wellhead trees (50, 52, 54, 56) in an extraction system including plural wellhead trees (50 ...) connected by a pipeline network (60, 62, 88, 104) to a host facility (64) via a manifold system (58) situated remotely from the host facility (64), the method involving selective opening and closing of valves (74, 78) controlling the flows through the pipeline network to enable selective delivery of output from a selected wellhead tree (50...) to testing means for analysing the content of the output from the selected wellhead tree wherein the method includes the steps of providing each wellhead tree (50...) with a production flow outlet (72), a test flow outlet (76) and valve means (74, 78) operable to selectively divert the output from the wellhead tree (50...) through one of the outlets (72, 76) and operating the valve means (74, 78) to divert the output of one wellhead tree only to the testing means.
- The method of according to claim 1 including the step of providing each wellhead tree (50 ...) with a production flow valve (74) and a test flow valve (78) for respectively controlling output through the production and test flow outlets (72, 76) which valves (74, 78) constitute the valve means of the wellhead tree (50...).
- The method according to claim 1 or 2 including the step of connecting the test flow outlets (76) of two or more wellhead trees (50 ...) with each other by a test conduit (104) to form a wellhead tree group and connecting the test conduit (104) to the manifold system (58).
- The method of claim 3 wherein two or more wellhead trees (50...) of the group are connected in parallel to the test conduit (104).
- The method of claims 2 and 3 including the step of opening the test flow valve (78) of a selected one of the wellhead trees (50 ...) of the group only while maintaining the or each other test flow valve (78) closed and passing output from the selected wellhead tree (50...) to the testing means via the test conduit (104).
- The method of claim 5 wherein output from the selected wellhead tree (52, 54, 56) passes through a portion of the test conduit (104) connecting two wellhead trees (50, 52, 54, 56) prior to passing through a different part of the test conduit (104) for delivery to the manifold system (58).
- The method according to any preceding claim including the step of connecting the test flow outlet (76) of each wellhead tree (212) to the manifold system (130) by an individual test conduit (210).
- The method according to claims 2 and 7 including the step of opening the test flow valve (76) of a selected one of the wellhead trees (212) only while maintaining the others closed and passing output from the selected wellhead tree (212) to the testing means via the corresponding individual test conduit (210).
- The method according to any preceding claim wherein the manifold system comprises a docking manifold (130) for receiving one or more system modules (132, 158, 180) for acting on wellhead tree outputs flowing through the manifold system and the method includes docking at least one such system module (132, 158, 180) in the docking manifold (130).
- The method according to claim 9 wherein at least one said system module (132) docked in the docking manifold (130) simply provides through connection firstly (150) between the production flow outlets (72) of the wellhead trees (50...) and a production pipeline (60) connecting the docking manifold (130) and the host facility (64) and secondly (152) between the test flow outlets (76) of the wellhead trees (50...) and a test pipeline (62) connecting the docking manifold (130) and the testing means which is situated at the host facility (64), the method including the step of conveying output from a selected one of the wellhead trees (50...) to the testing means via the system module (132).
- The method according to claim 9 wherein at least one said system module (158) docked in the docking manifold (130) firstly (164, 160) provides simple throughflow connection between the production flow outlets (72) of the wellhead trees (50...) and a production pipeline (60) connecting the docking manifold (130) and the host facility (64) and secondly (168, 160) includes the testing means (162), the method including the step of conveying output from a selected one of the wellhead trees (50...) to the testing means (162) of the system module (158) and analysing its contents.
- The method according to claim 9 wherein at least one said system module (180) docked in the docking manifold (130) includes the testing means (202) and separating means (194) for separating constituent components of the flows from the wellhead trees (50...), the method including the step of operating the valve means (74, 78) of the wellhead trees (50...) to divert the output from one selected wellhead tree test flow outlet (76) only to the separating means (194) and measuring and/or analysing its contents with the testing means (202).
- The method according to any preceding claim wherein control signals for controlling the valve means (74, 78) of each wellhead tree (50...) are provided from the host facility (64).
- The method according to claim 13 wherein the control signals are routed to the wellhead trees (50...) via the manifold system (58) but without passing through any control means forming part of the manifold system (58).
- The method according to claim 13 wherein the control signals are routed to the wellhead trees (50...) without passing through the manifold system.
- The method according to claim 9 wherein at least one of the system modules (158, 180) includes the testing means (162, 202), the method including the step of conveying output from a selected one of the wellhead trees (50...) to the testing means (162, 194) of the system module (158, 202).
- A method of operating a hydrocarbon extraction system including the steps of employing the method of claim 10 involving conveying output from a selected one of the wellhead trees (50...) to the testing means via the system module (132) and the test pipeline (62) and subsequently employing the method of claim 12 and conveying one of the constitute components from the separating means (194) to the host facility (64) via the pipeline (190) previously used as the test pipeline (62).
- Apparatus for controlling flows from plural hydrocarbon extraction wellhead trees (50...) in an extraction system including plural wellhead trees (50...) connected by a pipeline network (60, 62, 88, 104) to a host facility (64) via a manifold (58) situated remotely from the host facility (64) characterised by each wellhead tree (50...) having a production flow outlet (72), a test flow outlet (76) and valve means (74, 78) operable to selectively divert output from the wellhead tree (50...) through one of the outlets (72, 76) and the interconnecting pipeline network for delivering the output from one of the test flow outlets (76) to the testing means.
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
GBGB0110398.5A GB0110398D0 (en) | 2001-04-27 | 2001-04-27 | Wellhead product testing system |
GB0110398 | 2001-04-27 | ||
PCT/GB2002/001924 WO2002088519A1 (en) | 2001-04-27 | 2002-04-26 | Wellhead product testing system |
Publications (2)
Publication Number | Publication Date |
---|---|
EP1383985A1 EP1383985A1 (en) | 2004-01-28 |
EP1383985B1 true EP1383985B1 (en) | 2004-12-08 |
Family
ID=9913617
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP02718397A Expired - Lifetime EP1383985B1 (en) | 2001-04-27 | 2002-04-26 | Wellhead product testing system |
Country Status (8)
Country | Link |
---|---|
US (1) | US20040144543A1 (en) |
EP (1) | EP1383985B1 (en) |
AT (1) | ATE284479T1 (en) |
BR (1) | BR0209335A (en) |
DE (1) | DE60202202D1 (en) |
GB (1) | GB0110398D0 (en) |
NO (1) | NO20034764L (en) |
WO (1) | WO2002088519A1 (en) |
Families Citing this family (37)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1352679A1 (en) | 2002-04-08 | 2003-10-15 | Cooper Cameron Corporation | Separator |
WO2005047646A1 (en) * | 2003-05-31 | 2005-05-26 | Des Enhanced Recovery Limited | Apparatus and method for recovering fluids from a well and/or injecting fluids into a well |
GB2393981B (en) * | 2002-10-10 | 2006-02-15 | Abb Offshore Systems Ltd | Controlling and/or testing a hydrocarbon production system |
EP2283905A3 (en) * | 2003-09-24 | 2011-04-13 | Cameron International Corporation | Subsea well production flow and separation system |
EP1721058B1 (en) | 2004-02-26 | 2009-03-25 | Cameron Systems (Ireland) Limited | Connection system for subsea flow interface equipment |
GB2421524B (en) * | 2004-12-22 | 2009-06-24 | Vetco Gray Controls Ltd | Hydraulic control system |
MY140159A (en) * | 2005-08-29 | 2009-11-30 | Alpha Perisai Sdn Bhd | Control system for seabed processing system |
GB2437304B (en) * | 2006-04-18 | 2008-08-20 | Riverside Projects Ltd | Apparatus and method for a hydrocarbon production facility |
GB2443843B (en) | 2006-11-14 | 2011-05-25 | Statoil Asa | Seafloor-following streamer |
US7798233B2 (en) | 2006-12-06 | 2010-09-21 | Chevron U.S.A. Inc. | Overpressure protection device |
US7793726B2 (en) * | 2006-12-06 | 2010-09-14 | Chevron U.S.A. Inc. | Marine riser system |
US7793724B2 (en) * | 2006-12-06 | 2010-09-14 | Chevron U.S.A Inc. | Subsea manifold system |
US7793725B2 (en) * | 2006-12-06 | 2010-09-14 | Chevron U.S.A. Inc. | Method for preventing overpressure |
GB0625526D0 (en) | 2006-12-18 | 2007-01-31 | Des Enhanced Recovery Ltd | Apparatus and method |
US9145979B2 (en) * | 2007-06-12 | 2015-09-29 | Cameron International Corporation | Gate valve rotary actuator |
US8201624B2 (en) * | 2007-10-23 | 2012-06-19 | Saudi Arabian Oil Company | Clustered wellhead trunkline protection and testing system with ESP speed controller and emergency isolation valve |
GB0722469D0 (en) * | 2007-11-16 | 2007-12-27 | Statoil Asa | Forming a geological model |
GB0724847D0 (en) * | 2007-12-20 | 2008-01-30 | Statoilhydro | Method of and apparatus for exploring a region below a surface of the earth |
GB2479200A (en) | 2010-04-01 | 2011-10-05 | Statoil Asa | Interpolating pressure and/or vertical particle velocity data from multi-component marine seismic data including horizontal derivatives |
AU2011245498B2 (en) * | 2010-04-27 | 2015-09-17 | Shell Internationale Research Maatschappij B.V. | Method of retrofitting subsea equipment with separation and boosting |
US8757270B2 (en) * | 2010-05-28 | 2014-06-24 | Statoil Petroleum As | Subsea hydrocarbon production system |
EA024606B1 (en) * | 2010-10-21 | 2016-10-31 | Сауди Арабиан Ойл Компани | Clustered wellhead trunkline protection and testing system with esp speed controller and emergency isolation valve |
EP3289319B1 (en) | 2015-04-30 | 2021-12-29 | Services Pétroliers Schlumberger | Multiphase flow meters and related methods |
US9963956B2 (en) | 2015-07-07 | 2018-05-08 | Schlumberger Technology Corporation | Modular mobile flow meter system |
US20180283148A1 (en) * | 2015-10-30 | 2018-10-04 | Halliburton Energy Services, Inc. | Automated lift-gas balancing in oil production |
GB2549102A (en) * | 2016-04-04 | 2017-10-11 | Forsys Subsea Ltd | Pipeline integrated manifold |
US10416015B2 (en) | 2016-07-07 | 2019-09-17 | Schlumberger Technology Corporation | Representative sampling of multiphase fluids |
US10670575B2 (en) | 2017-03-24 | 2020-06-02 | Schlumberger Technology Corporation | Multiphase flow meters and related methods having asymmetrical flow therethrough |
CN107871040A (en) * | 2017-11-06 | 2018-04-03 | 中煤航测遥感集团有限公司 | Pipe network connectivity analysis methods and device |
NO20180820A1 (en) | 2018-06-13 | 2019-12-16 | Vetco Gray Scandinavia As | A hydrocarbon production field layout |
GB2585724B (en) * | 2018-12-11 | 2022-04-20 | Enpro Subsea Ltd | Apparatus, Systems and Methods for Oil and Gas Operations |
NO345115B1 (en) * | 2019-01-28 | 2020-10-05 | Seabed Separation As | Well testing under full field production |
GB201901257D0 (en) * | 2019-01-30 | 2019-03-20 | Enpro Subsea Ltd | Apparatus, systems and methods for oil and gas operations |
US11274550B2 (en) | 2020-07-08 | 2022-03-15 | Fmc Technologies, Inc. | Well test module |
NO347166B1 (en) * | 2020-12-15 | 2023-06-19 | Vetco Gray Scandinavia As | Compact dual header manifold layout |
US11944920B2 (en) * | 2021-06-29 | 2024-04-02 | Saudi Arabian Oil Company | Modified gathering manifold, a production system, and a method of use |
US12084949B2 (en) * | 2021-08-26 | 2024-09-10 | Baker Hughes Energy Technology UK Limited | Intervention system and method using well slot path selector valve |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2028400B (en) * | 1978-08-16 | 1982-08-11 | Otis Eng Corp | Production from and servicing of wells |
FR2617233B1 (en) * | 1987-06-29 | 1989-11-17 | Elf Aquitaine | MODULAR SUBMARINE STATION ON MONOPOD CHASSIS |
GB2281925B (en) * | 1993-09-17 | 1997-01-22 | Consafe Eng Uk Ltd | Production manifold |
GB9919024D0 (en) * | 1999-08-13 | 1999-10-13 | Coflexip | Methods and apparatus for the emergency actuation of control systems |
GB9921373D0 (en) * | 1999-09-10 | 1999-11-10 | Alpha Thames Limited | Modular sea-bed system |
NO313767B1 (en) * | 2000-03-20 | 2002-11-25 | Kvaerner Oilfield Prod As | Process for obtaining simultaneous supply of propellant fluid to multiple subsea wells and subsea petroleum production arrangement for simultaneous production of hydrocarbons from multi-subsea wells and supply of propellant fluid to the s. |
-
2001
- 2001-04-27 GB GBGB0110398.5A patent/GB0110398D0/en not_active Ceased
-
2002
- 2002-04-26 US US10/475,932 patent/US20040144543A1/en not_active Abandoned
- 2002-04-26 AT AT02718397T patent/ATE284479T1/en not_active IP Right Cessation
- 2002-04-26 EP EP02718397A patent/EP1383985B1/en not_active Expired - Lifetime
- 2002-04-26 DE DE2002602202 patent/DE60202202D1/en not_active Expired - Lifetime
- 2002-04-26 BR BR0209335-9A patent/BR0209335A/en not_active IP Right Cessation
- 2002-04-26 WO PCT/GB2002/001924 patent/WO2002088519A1/en not_active Application Discontinuation
-
2003
- 2003-10-24 NO NO20034764A patent/NO20034764L/en not_active Application Discontinuation
Also Published As
Publication number | Publication date |
---|---|
EP1383985A1 (en) | 2004-01-28 |
ATE284479T1 (en) | 2004-12-15 |
US20040144543A1 (en) | 2004-07-29 |
WO2002088519A1 (en) | 2002-11-07 |
GB0110398D0 (en) | 2001-06-20 |
BR0209335A (en) | 2004-06-15 |
NO20034764D0 (en) | 2003-10-24 |
NO20034764L (en) | 2003-12-22 |
DE60202202D1 (en) | 2005-01-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP1383985B1 (en) | Wellhead product testing system | |
US6640901B1 (en) | Retrievable module and operating method suitable for a seabed processing system | |
EP2233688B1 (en) | Apparatus and method for recovering fluids from a well and/or injecting fluids into a well | |
US11486217B2 (en) | Flow control module | |
EP2100003B1 (en) | Apparatus and method for processing fluids from a well | |
EP2673466B1 (en) | Well testing and production apparatus and method | |
US20040251030A1 (en) | Single well development system | |
WO2007027080A2 (en) | Control system for seabed processing system | |
AU2021206804B2 (en) | Solid particle separation in oil and/or gas production | |
US20100044038A1 (en) | Apparatus and method for processing fluids from a well | |
WO2018164657A1 (en) | Compact flow control module |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
17P | Request for examination filed |
Effective date: 20031119 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AT BE CH CY DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE TR |
|
AX | Request for extension of the european patent |
Extension state: AL LT LV MK RO SI |
|
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AT BE CH CY DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE TR |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: TR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20041208 Ref country code: NL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20041208 Ref country code: LI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20041208 Ref country code: IT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT;WARNING: LAPSES OF ITALIAN PATENTS WITH EFFECTIVE DATE BEFORE 2007 MAY HAVE OCCURRED AT ANY TIME BEFORE 2007. THE CORRECT EFFECTIVE DATE MAY BE DIFFERENT FROM THE ONE RECORDED. Effective date: 20041208 Ref country code: FR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20041208 Ref country code: FI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20041208 Ref country code: ES Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20041208 Ref country code: CH Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20041208 Ref country code: BE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20041208 Ref country code: AT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20041208 |
|
REG | Reference to a national code |
Ref country code: GB Ref legal event code: FG4D |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: EP |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: FG4D |
|
REF | Corresponds to: |
Ref document number: 60202202 Country of ref document: DE Date of ref document: 20050113 Kind code of ref document: P |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20050308 Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20050308 Ref country code: DK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20050308 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20050309 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LU Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20050426 Ref country code: IE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20050426 Ref country code: CY Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20050426 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MC Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20050430 |
|
NLV1 | Nl: lapsed or annulled due to failure to fulfill the requirements of art. 29p and 29m of the patents act | ||
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
26N | No opposition filed |
Effective date: 20050909 |
|
EN | Fr: translation not filed | ||
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GB Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20060426 |
|
GBPC | Gb: european patent ceased through non-payment of renewal fee |
Effective date: 20060426 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: PT Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20050508 |