EP1337885A2 - Cable installation - Google Patents
Cable installationInfo
- Publication number
- EP1337885A2 EP1337885A2 EP01997876A EP01997876A EP1337885A2 EP 1337885 A2 EP1337885 A2 EP 1337885A2 EP 01997876 A EP01997876 A EP 01997876A EP 01997876 A EP01997876 A EP 01997876A EP 1337885 A2 EP1337885 A2 EP 1337885A2
- Authority
- EP
- European Patent Office
- Prior art keywords
- cable
- point
- cables
- pipe
- ducts
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L1/00—Laying or reclaiming pipes; Repairing or joining pipes on or under water
- F16L1/12—Laying or reclaiming pipes on or under water
- F16L1/123—Devices for the protection of pipes under water
-
- G—PHYSICS
- G02—OPTICS
- G02B—OPTICAL ELEMENTS, SYSTEMS OR APPARATUS
- G02B6/00—Light guides; Structural details of arrangements comprising light guides and other optical elements, e.g. couplings
- G02B6/46—Processes or apparatus adapted for installing or repairing optical fibres or optical cables
- G02B6/50—Underground or underwater installation; Installation through tubing, conduits or ducts
- G02B6/506—Underwater installation
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
- H02G1/06—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle
- H02G1/10—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle in or under water
Definitions
- the present invention relates to the installation of cables.
- the invention is primarily concerned with fibre optic communication cables but may be applied to other cables, for example co-axial or other communication or power cables.
- the invention is particularly concerned with providing a cable connection over an extended span, particularly over a sea or other water crossing and in a prefened application is concerned with providing a deep sea (for example transatlantic) cable crossing; however, aspects of the invention may be applied to land based or other applications.
- Provision of a cable link over an extended span, particularly a sea crossing, is a major undertaking and it is normal practice to plan each link to provide excess cable capacity at the time the link is constructed to accommodate future traffic for a given period until the next cable link is planned; this reduces repetition of the expensive time-consuming and hazardous work involved in installing a cable on the sea bed.
- the intention is normally that, once laid, the cable(s) will require minimal maintenance or disturbance underwater.
- the landing stations are well defined, growth in demand can be predicted, and it is likely that the cable will have a finite life so will need to replaced at some point. Therefore, despite the large cost of creating a link, it is usual to provide a link in the expectation that a new link will be needed in a few years. Indeed, because of the risk of damage to an individual link, it is considered desirable that new links over new routes are added over time.
- the present invention provides a method of facilitating provision of a point to point cable connection between first and second points separated by an extended span, the method comprising providing multiple ducting from the first point through a first region of the extended span to a termination point intermediate the first and second points.
- This aspect may enable a simplified cable installation, whereby for part of the connection, one or more cables may be subsequently introduced into an existing duct, without the expense or problems associated with installing individual cables afresh and without requiring multiple ducts across the entire span. Indeed, for an extended span, the provision of multiple initially empty ducts may not only be prohibitively expensive but counter productive as difficulties may be encountered in passing cables through such lengthy ducts.
- extended span as used herein, as will be understood by one skilled in the art, is intended to exclude short-range networks and preferably implies a distance of at least about 5km and/or including a region of troublesome tenain or water, typically a span of at least about 10km.
- This aspect offers particular advantages when the span is at least tens of kilometres, often at least about 100km or hundreds of kilometres or (for example in the case of a transatlantic crossing) even at least 1000km.
- advantages may be obtained when spans of the order of a few hundred metres are traversed, for example in the case of a river crossing, particularly in the case of a festoon as described herein.
- duct or "ducting” as used herein is intended to encompass any construction capable of directing a cable across a route; it will normally comprise a sealed (or substantially sealed) pipe through which the cable passes.
- the multiple ducting will comprise an outer duct having a plurality of sub-ducts defined therein.
- references to multiple ducts or multiple ducting may imply multiple independent ducts or a single duct which is capable of directing more than one cable (at separate installation times).
- the multiple duct may have sub-ducts within which separate cables can be laid, alternative embodiments are possible provided the duct is suitable for more than one cable passing operation.
- the setting up of a cable connection often involves installation across a region presenting a particular difficulty or delay.
- An example of one such region is an area of water to be traversed.
- connection points separated by an expanse of water, such as a lake, sea or ocean the first point being on or adjacent to the shore or at or near a cable landing station, the first region being in the shore area.
- a particular problem with installing cable across a region of water is that usually the cable will have to be laid on the bed below the water. At least a part of a new cable connection can be made without the need to repeat the underwater laying process in the vicinity of the shore, as the new cable(s) can be installed in the existing multiple ducts.
- An embodiment of this aspect provides the termination point at a distance relatively close to the first connection point. This may provide easy access to the termination point from the shore or bank of the water region.
- the termination point at a distance of preferably at least about 2 kilometres from the first point, more preferably at least about 5 km.
- a large amount of construction work is required in landing a cable, and, in the case of coastal installations, permits are required to land a cable and new cables must often be laid in place of old in the same route.
- the landing site area also suffers significant disruption, as the usual fishing, dredging and other shipping activities may have to be halted temporarily and the habitats of local marine life may be disturbed; even as close as 100m to the first point, the provision of a termination point coupled by multiple ducting can significantly reduce the overall technical effort required to provide a subsequent long distance cable link. Even for a route covering thousands of kilometres, analysis according to the invention has found that a surprising increase in efficiency of the overall process may be achieved by provision of multiple ducting over as little as 2 kilometres of route, in the vicinity of the shore end of the route.
- a termination or access point may be provided at an offshore platform, preferably a pre-existing offshore platform; this facilitates subsequent access and splicing of cables.
- the termination point, whether sub sea, ⁇ floating or on an offshore platform is preferably located out to sea (or otherwise away from the shore in the case of a lake) in the case of a route traversing water and the multiple ducting is preferably provided on or in the water bed.
- the distance may be less, in some cases for example the distance may only be of the order of a hundred metres or so although such embodiments may not offer the advantages associated with the considerably greater distances prefened (of the order of at least 2km) .
- the termination point at about 10 kilometres from the shore can provide a remarkable benefit in reduction of disruption when a subsequent cable is to be laid and it is surprising that, for example in the case of a cable crossing of many hundreds or even thousands of kilometres, provision of multiple ducting over a relatively small proportion of the distance can potentially significantly reduce expense and complication of subsequent cable installation operations.
- Benefits of having a relatively short distance to the termination point include reduced cost of multiple ducting and that the termination point remains relatively easily accessible.
- the termination point is placed at a greater distance, typically more than about 10 kilometres, typically tens of kilometres or even about 100km or more from the first point. At such great distances from the shore, the disruption associated with shoreline installation may be significantly reduced. Analysis pursuant to the invention shows a surprising advantage in terms of overall technical effort for a route and reliability of cable installation may be obtained with a termination point between 10km and 100km.
- termination point is of course not used in the mathematical sense but is intended to connote a region.
- the region will generally be relatively localised in comparison to the size of the extended span but may nonetheless have sub- features spread over an appreciable area.
- the termination point may comprise multiple cable exits spread over several hundred metres or even an area of the order of a square kilometer.
- the location of the termination point is preferably chosen based on the water depth (or, for example in the case of land based systems to which variants of the invention may be applied, based on other features of the tenain; for example, a cable across a rocky and desert region may have multiple ducts through the rocky region, where installation is more problematic than through the desert region).
- the termination point is preferably at a minimum depth of at least about 10m; at lesser depths the advantages diminish as subsequent installations will still require significant disruption, but this possibility is not excluded and may offer advantages in certain cases.
- the termination point is in a relatively shallow water region, preferably at a depth of about 300m or less, preferably 200m or less, more preferably of the order of about 100m.
- the termination point is located a substantial distance from the shore (for example many tens or even hundreds of kilometres, typically at least about 100km) on a continental shelf, preferably adjacent (for example at least half way to, typically within about 10km of, preferably within about 1km of) a transition to deeper water. Provision of a termination point adjacent the edge of a continental shelf may have the advantage that a cable leaving the termination point may not require burying in the shelf bed or at least not for an appreciable distance.
- repeaters or intermediate access points or intermediate termination points may be provided between the connection point and a final termination point, to facilitate cable installation and/or servicing and/or to enable signals to be transmitted reliably over longer distances. If repeaters are provided, these may be ananged to be upgradeable; this feature may be provided independently. In the case of a deep sea crossing, there may be a second termination point and a second region of multiple ducting from the second termination point to the second point.
- the invention may provide a method of facilitating provision of a point to point cable connection between first and second points separated by an extended span including a region of deep water, the method comprising providing first multiple ducting from the first point through a first relatively shallow water (for example continental shelf) region of the extended span to a first termination point intermediate the first and second points (preferably at least about 2 km from the first point, more preferably at least about 10km from the first point, preferably adjacent a transition to deep water), providing second multiple ducting from the second point through relatively shallow water (for example continental shelf) to a second termination point (preferably at least about 2 km from the second point, more preferably at least about 10km from the second point, preferably adjacent a transition to deep water), the first and second termination points being separated by said region of deep water.
- the first and second points are located in the US and UK or Europe respectively or vice versa and the first and second termination points are located in the respective continental shelves, the
- the ducting can be pre-fabricated onshore, and subsequently transported to the laying site by one or more vessels.
- the invention provides a method of facilitating provision of an underwater cable connection comprising fabricating a length of multiple ducting at a first point and transporting the length to a submerged lay site at a second underwater point. This allows for longer lengths of the ducting to be installed at one time. Typically, the section of ducting is towed between two vessels, and laid at the conect site.
- conduit for a plurality of underwater cables
- the conduit comprising an elongate (preferably substantially rigid) outer pipe having first and second ends and defining an inner space, a plurality of inner ducts positioned within the inner space and extending between the first and second ends, each inner duct defining a cable-directing inner channel extending substantially from the first end of the pipe to the second end of the pipe, wherein a seal is established at each of the first and second ends to trap a region of air in the inner space. This region of air can thus be partially or completely flooded to alter the buoyancy.
- the conduit has an inlet to facilitate flooding of the inner space.
- the invention provides a method of facilitating provision of a cable connection comprising fabricating a length of multiple ducting at a first point and transporting the length to a submerged lay site at a second underwater point, wherein the multiple ducting comprises a
- anangement comprising a plurality of ducts each adapted to receive a cable, wherein a seal is established between the outer pipe and the ducts at either end of the conduit to form a region of air trapped between the outer pipe, the insert and the seals, providing hydrostatic buoyancy, and comprising transporting the ducting to a submerged point above the lay site, breaking one or more of the seals, thereby flooding the region of trapped air, and laying the ducting at the lay site.
- the termination point will normally be provided on the sea bed. However, as an alternative, the termination point may be brought to the surface. Providing the termination point at the surface has the advantage that connection of cables is simplified, but requires suitable anchoring for the termination point, and provision of suitably robust ducting. In addition, the requirement for the cable to climb from the sea bed, which may be at a depth of 100m or more to the termination point may complicate installation of cable (although in such cases, the cable may be inserted from the termination point).
- the useful installation length may be extended.
- pull cords may be provided in the multiple ducting at installation and used to pull cable through the ducting.
- the cable may be unreeled from within the duct.
- a splicing point may be provided intermediate the first point and first termination point, for example at a depth of about 10m or less, under a beach.
- the splicing point may be coupled to a cable landing station by means of a multiple duct, optionally installed by means of a directional drill. Cables may be pulled through to this splicing point, which is relatively easily accessible and joined to a long distance cable which is propelled through further multiple ducting to the first termination point.
- estuary or channel such as the English Channel, for example up to 50km and particularly but not exclusively where unrepeated lengths are possible, multiple ducting may be provided across the whole route.
- the invention provides a method of facilitating a cable connection between first and second points separated by an expanse of water, the method comprising providing multiple ducting from the first point across the expanse of water, preferably buried in the bed of the expanse of water, to the second point.
- a plurality of cables can be installed from the first point to the second point, preferably in separate operations without having to repeat the "wet" work.
- the first and second points are located on shore and the multiple ducting provides multiple routes for cable to traverse from shore to shore.
- the invention further provides a method of providing multiple shore to shore cable connections across an expanse of water, the method comprising providing multiple ducting from the first point across the expanse of water, preferably buried in the bed of the expanse of water, to the second point and subsequently installing a plurality of cables from the first point to the second point.
- the duct dimensions and configuration may vary considerably depending on the environment and degree of resistance, the route length and the cable type and the invention is not limited to any particular duct configuration for the multiple ducting.
- the ducts need not be circular (although this is prefened for manufacture, duct installation and cable installation); references to diameter below should be construed as applying to the effective cross-sectional width in the case of polygonal or inegular shapes.
- a greatly prefened configuration is for the multiple ducting to comprise a relatively environmentally resistant and preferably relatively rigid outer shell, preferably of metal, preferably steel or reinforced with steel with a plurality, preferably at least four, most preferably at least eight sub-ducts of lesser environmental resistance through which cables can be inserted.
- the sub ducts are advantageously formed from plastics material and HDPE (high density poly ethene) has particularly advantageous properties for sub sea applications, particularly in terms of environmental resistance, extrudability and rigidity.
- the outer shell has a diameter of at least about 15cm, more preferably at least about 30cm often at least about 50cm and the inner sub-ducts preferably have an internal diameter of at least about 2.5cm, more preferably at least about 5cm. If the internal diameter is at least 10cm, preferably at least 15cm, particularly for longer lengths, installation of cables is greatly facilitated, although this of course requires a larger outer duct and increases the cost of installation.
- the diameter is preferably at least 15cm, more preferably at least 30cm and with ducts having an internal diameter of 50cm or more, a greatly increased number of cables can be accommodated.
- the duct preferably has a minimum internal diameter (or minimum dimension through which cable can pass in the case of a non-circular section duct) of at least about 10cm, more preferably at least about 20cm.
- passing the cable from the first termination point comprises providing cable between the first and second termination points and passing cable through the multiple ducting between the second point and second termination point.
- the cable passed through the ducting will be relatively thin lightweight cable, the ducting providing protection from the environment.
- the cable extending from the termination point (or between the first and second termination points) will normally be heavily armoured cable designed to be lain on the sea bed over the deep water region.
- the deepwater cable will normally be spliced at the termination points to the cable provided within the multiple ducting.
- the invention extends to provision of a cable link.
- the invention provides a method of providing a point to point cable connection between first and second points separated by an extended span, the method comprising passing a first cable through multiple ducting from the first point through a first region of the extended span to a termination point intermediate the first and second points and providing a second cable from the termination point to the second point.
- the multiple ducting is preferably provided according to the first aspect and prefened features of the first aspect apply to this aspect and vice versa.
- the first cable may comprise a relatively lightweight cable, preferably having a diameter of less than about 5cm, more preferably less than about 1cm.
- Providing the second cable may include providing an armoured section of cable on the sea bed of a deepwater region.
- the armoured section of cable preferably has an armour layer including metal, typically steel, preferably braid or wires if not a continuous layer and the armoured section may have a diameter of greater than 1cm.
- providing the second cable may comprise passing a section of second cable through multiple ducting
- the ducts according to the implementations above are buried, and where they are submerged, a trench is preferably dug (or jetted) in the underwater bed for this purpose. Thus damage to the ducts from either surface or waterborne hazards may be avoided.
- the ducts are provided in a channel drilled from a connection point to a termination point, protecting the ducts more effectively, as they can be laid further underground.
- An aspect of the invention provides a conduit installation comprising a connection point and multiple ducting between the connection point and a termination point in an at least partially submerged region.
- the termination point comprises multiple cable exits over an extended region so that cables can exit the multiple ducting at spaced apart locations.
- the termination point comprises a termination structure providing at least two cable exits spaced apart by at least 5m, more preferably at least 10m and in the case of a sea crossing preferably at least 50m. Analysis pursuant to the invention shows that a spacing of at least 50m in a sea-crossing cable can dramatically increase reliability of the multiple connections.
- the termination structure preferably provides protection, most preferably a protective duct or housing, between the cable exits and the (protective and/or suitably buried) multiple ducting. This is a particularly advantageous feature.
- the termination structure may be a branching sub-sea duct structure a part of which may optionally be recoverable to the surface to facilitate provision of new cables or repair or maintenance, an enlarged sea bed structure, a buoyant structure with protective cable risers or protective anchor chains or cables extending to the sea bed or an offshore platform structure with protective risers.
- the termination structure may include or be supplemented by protective elements such as concrete mattresses (as described herein) or other protective elements extending away from the multiple ducting and may be supplemented by or provided by excavations formed in the sea bed.
- the invention further provides a method of forming a subsea termination structure comprising providing a protective structure extending from a region of multiple ducting canying at least two cables to at least two spaced apart cable exits, the exits preferably being spaced apart at least 50m.
- a prefened spacing distance for the cables is of the order of at least about 1.5 times the water depth and the spacing is preferably at least equal to the water depth.
- Termination structures and methods of forming termination structures may be provided independently. Splicing
- a further aspect of the invention provides a cable splice box in an at least partially submerged region, comprising an enclosure and means for splicing cables. This allows for cables being laid in a submerged region to be spliced, thus avoiding, for example, shore line disruption caused by land based splice boxes.
- the box is buried, protecting it from possible damage.
- at least two cables run from the box to a cable landing station in a shore area.
- the invention provides a method of facilitating cable servicing and splicing, comprising providing a first cable splice box in an at least partially submerged region, passing one or more cables from a connection point to the box, and providing service access to the cables at the box. This may provide for an easily accessible serviceable cable installation.
- the present invention consists in a further aspect in a method of providing cable connections over an extended span comprising laying multiple ducts over a portion only of the extended span, passing at least one first cable having a first specification through a first duct to form a first cable connection, and subsequently after a period of time during which the first cable connection is operational passing at least one second cable, preferably having a second specification through a second duct to form a second cable connection.
- This aspect thus provides for a readily and cheaply upgradeable cable system.
- each duct is occupied by at least one cable, thereby maximising the data capacity of the set of conduits.
- one or more of the multiple ducts are left empty. This allows for ready upgrading when higher specification cable becomes economically viable.
- An aspect of the invention consists in a method of providing a cable connection between primary and secondary points, comprising installing a cable from the primary point through one of multiple ducts to at least a first primary termination point, passing the or a further cable across a substantial distance and installing the cable at the secondary point.
- long distance cable may be installed.
- a transatlantic cable installation may employ this method.
- one of the ends of the cable may be installed in an area where there are few restrictions, or where only a single cable connection is needed.
- the multiple ducts required at one end may not be required at the other, saving expense and time.
- the cable is passed across the substantial distance to at least a first secondary termination point, and installed through one of a multiple of ducts to the secondary point.
- a method of facilitating provision of a number of cable connections between a first point and a number of second points comprising providing multiple ducts from the first point to a termination point intermediate the first and second points, and providing at least one cable connection point at each of the second points.
- each of the multiple cables connected at the first connection may be connected to different connection points, for example a cable point in New York may be connected to the UK, to France and to Ireland.
- a method comprising installing cables from the first point through the multiple ducts to the termination point, and passing the cables or further cables to at least two of the second points.
- these methods are implemented in spanning a large expanse of water, such as a lake or ocean.
- the invention provides a cable installation comprising: first and second connection points; multiple ducts between the first connection point and a first termination point; and at least one cable installed through one of the multiple ducts to the first termination point, across a substantial distance and to the second connection point.
- cables are spliced at the first termination point.
- the cable is installed to a second termination point relatively close to the second connection point, through at least one duct to the second connection point, thus providing similar advantages at the other end of the connection.
- first and second (or further) connection points are separated by an expanse of water, such as a lake or ocean, thus providing, for example, a transatlantic cable installation.
- the invention may provide installing a cable inside an existing duct which is already occupied by one or more cables, and means for installing cables. Protection of cables
- the present invention consists in another aspect in a method of laying a submarine cable (or duct for canying cable) comprising using a variable burial depth profile based on anticipated hazards at differing depths.
- This aspect thus provides a method of cable laying which is less susceptible to damage, and thus can provide more reliable transmission.
- the method comprises a first burial depth in a shallow water area, a second burial depth in a deep water area and optionally an intermediate burial depth in an intermediate depth water area.
- the shallow water area is in an anchor zone
- the intermediate depth water area is in a dredging zone
- the deep water area includes a deep sea fishing zone.
- the method may include planning depths based on coastal outlines/activity and/or distances from shore in addition to or instead of based on water depth.
- This implementation provides for a cable laid to avoid the hazards most commonly found in the different regions, and save in expense in those areas where previous methods were excessive in burial depth.
- the invention provides, in a further aspect, a long distance cable installation between first and second coastal areas, comprising in the first area a cable landing station, at least one service point, multiple ducts through a first beach region between the landing station and a first splice box in a first shelf region, a second splice box at the boundary between the first shelf region and a deep water region, and a number of cables installed from the landing station, through the multiple ducts to the first splice box, through the shelf region to the second splice box and through the deep water region to the second, substantially distant coastal area.
- the second coastal area has a similar cable installation to the first coastal area.
- the cables are buried according to a particular variable depth profile, in order to avoid damage.
- the invention provides a method of facilitating transmission of data across a network spanning a large expanse of water, comprising installing a data transmission cable from a first connection point through a multiple of ducts in a first region to a first termination point, across a portion of the expanse of water to a second termination point, and through a multiple of ducts in a second region to a second connection point.
- the invention extends to installed networks, planning tools, computer software used in planning such methods , data packets transmitted by the installed cables and apparatus adapted for use in the methods of the invention.
- the invention is particularly suitable for building an upgradeable, particularly IP (Internet protocol) data network and the invention extends to an IP data packet transmitted across an expanse of water through a region of multiple ducting. Further independent aspects and/or prefened features are discussed below and/or set out in the claims.
- Figure 1 is a diagram illustrating a known anangement for laying a sub- sea cable
- Figure 2a is a diagram illustrating the anangement of the sub-sea cable according to an embodiment of the invention
- Figure 2b is a diagram illustrating an anangement for laying a sub-sea cable according to an embodiment of the invention
- Figure 3 is a diagram illustrating a method of providing a duct according to an embodiment of the invention
- Figure 4 is a diagram illustrating a method of laying a sub-sea cable according to an embodiment of the invention
- Figure 5 is a diagram illustrating another method of laying a sub-sea cable according to an embodiment of the invention.
- Figure 6 is a diagram illustrating another method of laying a sub-sea cable according to an embodiment of the invention.
- Figure 7 is a diagram illustrating details of Figure 6;
- Figure 8 is a diagram illustrating a stab-plate according to an embodiment of the invention.
- Figure 9 is a diagram illustrating another method of laying a sub-sea cable according to an embodiment of the invention.
- Figure 10 is a diagram illustrating a facet of the method of laying a sub- sea cable illustrated in Figure 9;
- Figure 11 is a diagram illustrating another method of laying a sub-sea cable according to an embodiment of the invention
- Figure 12 is a diagram illustrating another method of laying a sub-sea cable according to an embodiment of the invention
- Figure 13 is a diagram illustrating a termination point according to an embodiment of the invention.
- Figure 14 is a diagram illustrating a method of protection of ducting according to an embodiment
- Figure 15 is a diagram illustrating another method of protection of ducting according to an embodiment
- Figure 16 is a diagram illustrating a termination point according to an embodiment of the invention.
- Figures 17 to 19 are diagrams illustrating another termination point according to an embodiment of the invention.
- Figure 20 is a diagram illustrating a typical vessel for use in retrieving a termination point
- Figure 21 is a diagram illustrating a termination point according to an embodiment of the invention
- Figure 22 is a diagram illustrating another termination point according to an embodiment of the invention.
- Figure 23 is a diagram illustrating a method of deployment of a cable inside a duct according to an embodiment of the invention.
- Figure 24 is a diagram illustrating typical duct curvature in the region of an obstacle
- Figure 25 is a diagram illustrating an upgradeable repeater anangement
- Figure 26 is a diagram illustrating typical pressures associated with the installation of a cable into a duct according to an embodiment of the invention.
- Figure 27 is a diagram illustrating a further upgradeable repeater anangement
- Figure 28 is a graph illustrating a typical depth profile which would be encountered by a transatlantic cable
- Figure 29 is a graph illustrating a typical depth profile of the US continental shelf
- Figure 30 is a graph illustrating a typical depth profile of the UK continental shelf
- Figure 31 is a diagram illustrating the typical depths of penetration of various shipping activities, along with the usual burial depth of cables, and the burial depth according to an embodiment of the invention
- Figure 32 is a diagram illustrating a typical stockless type anchor
- Figure 33 is a graph illustrating typical anchor penetration for various vessel sizes
- Figure 34 is a diagram illustrating recent fault locations of existing sub- sea cables
- Figure 35 is a table illustrating the depths of recent faults in sub-sea cables, and their various causes;
- Figure 36 is a diagram illustrating the different types of fault typically encountered by transatlantic cables;
- Figure 37 is a diagram illustrating a repair strategy according to an embodiment of the invention.
- Figure 38 is a diagram illustrating repair procedures according to an embodiment of the invention.
- Figure 39 is a diagram illustrating a set of repair procedures according to an embodiment of the invention and including details of Figures 37 and 38;
- Figure 40 is a schematic overview of a transatlantic sub-sea cable system according to an embodiment of the invention
- Figure 41 is a diagram illustrating the typical make up and data capacity of the conduit according to an embodiment of the invention
- Figure 42 shows a pipeline repair clamp
- Figure 43 shows cutting out of a half shell
- Figure 44 illustrates traditional pipeline repair
- Figure 45 illustrates repair by bringing a damaged section to the surface
- Figure 46 shows a mechanical connector used for subsea repair
- Figure 47 shows schematically a combined tool including a pipe-end connector and a half-shell clamped aperture
- Figure 48 shows a pipe recovery tool
- Figure 49 illustrates repair of an HDPE conduit
- Figure 50 illustrates repair of an HDPE conduit outer duct
- Fig. 51 is a line diagram isometric of the "chain pipe” showing exploded view of horizontally and vertically split shells;
- Fig. 52 is an image of the "chain pipe” showing exploded view of horizontally and vertically split shells; and Fig. 53 is an image of the "chain pipe” showing exploded details of the connection.
- Figure 1 is a diagram illustrating an anangement for laying a sub-sea cable.
- a conduit 30 is laid from a cable landing station 240 to a service site
- a single channel 32 is bored a certain distance out into the continental shelf, typically to a water depth of 30 feet.
- the cable 320 is drawn through this and is then laid on the shelf.
- the cable is armour-plated, typically double armoured and usually buried deeply in the shelf.
- the cable is then laid across the ocean floor, often trenched, until the opposite continental shelf is met.
- Figure 2a is a diagram illustrating the anangement of the sub-sea cable according to an embodiment of the invention.
- Multiple ducting 300 is laid from the junction point 200 to the termination point 210.
- the same apparatus is set up at the opposite end of the cables with a termination point 220 and service point 230.
- the armoured cables may be laid metres or even kilometres.
- Figure 2b is a diagram illustrating an anangement for laying a sub-sea cable according to an embodiment of the invention.
- a conduit 30 is laid to the service point 250, but a bore hole 36 to the shelf is built to accommodate multiple ducting. Multiple cables can therefore be laid, and are either pulled or jetted to a junction box 200 at the top of the shelf. From here, multiple conduits 300 are laid in the same trench, and one or multiple cables 310 may be laid in a single conduit. These cables are then spliced at the splicing box 210 at the edge of the shelf, and the long distance ocean floor cable 320 is laid as usual. In other embodiments, the relative distances between the various stages are different.
- the splicing box 210 may only be halfway to the edge of the continental shelf , with the long distance cable 320 being laid to the edge of the shelf. It may only be necessary to splice the cable at distances of around 100 feet offshore.
- the distance from the service point 250 to the junction box 200 (or splicing box 210) may also vary, though particular embodiments of the invention, described below, allow for a longer distance to be traversed by the multiple conduits, typically of the order of 10 to 20 kilometers.
- the cables or conduits are laid directly from the service point 250 to the splicing box 210.
- a duct is drilled directly from the land station
- the continental shelf bed in certain embodiments, in the sections between stages, such as between junction box 200 and splicing box 210, there may be either a single conduit, capable of containing multiple cables, or multiple conduits or cables. These may be laid by a variety of methods, as described later. Many problems faced in installing cables across expanses of water, such as lakes or seas, are involved with the shore landing site 240. The land installation involves great expense, as a large amount of construction work is required. In the case of coastal installations, permits are required to land a cable in most areas. Several coastal region agencies also require that new cables must be laid in place of old in the same route.
- the landing site also suffers significant disruption, as the usual fishing, dredging and other shipping activities may have to be halted temporarily and the habitats of local wildlife and marine life may be disturbed. For example, blackout periods for shellfish harvests and marine life spawning season may be incuned. Also, as cable routes restrict fishing grounds for around a mile on either side, the containment of large numbers of cables in a single route is advantageous.
- This aspect of the invention when implemented for a coastal installation, may provide multiple pathways for cables without requiring a new installation each time. This may greatly reduce the amount of construction work required and the disruption caused to shipping and ecosystems. Cables usually have to be replaced due to simple wear and tear. Furthermore, the demand for increased bandwidth has increased rapidly in recent years along with the amount of traffic being handled by existing cable systems. Potential capacity of cables using new technological developments has also increased, but it is usually prohibitively expensive to replace cables regularly, due to the large costs involved. This aspect of the invention therefore allows simple and frequent replacement of the cables in the existing conduits, reducing costs and enabling greater bandwidth through more advanced cables.
- Typical shore-end installation time scales are of the order of 18 months, whereas deepwater work usually takes around two months even though the distance traversed is much greater. There is therefore an enormous time saving to be made, not just by reducing the number of land site installations, but also by canying out more of the work further out to sea, in deeper water regions.
- the conduits, ducts and cables may be laid onto the continental shelf and beach floor by several methods.
- the channel into which the conduit or cable is be laid may be trenched.
- a plough is dragged along the sea bed to establish a trench, and the cable is laid into it.
- the conduit or cable may be subsequently buried in the trench.
- Figure 3 illustrates one method of duct installation according to one embodiment of the invention.
- a channel is drilled directly from the land station to the sea-bed. This method of drilling may be used for only a first section of the anangement of Figure 2b, to the junction box 200, or also for the section to the splicing box 210.
- a cable may be introduced by several methods .
- One method according to an embodiment is to pull the cable through a conduit, simply by passing a drawing tether through the conduit, attaching this to the cable, and pulling it through the conduit.
- the cable may also be jetted, particularly using known flow methods as described later herein.
- FIG. 4 A first vessel 2 drags a plough 4 along the sea bed, and another lays the cable 320 into the resulting trench by paying it out from a reel 8 mounted on the vessel 6.
- the cable 320 is preferably flexible, to allow it to be reeled effectively.
- This method allows efficient laying of relatively long lengths of cable.
- Figure 5 Another method is illustrated in Figure 5.
- the pipe 10 containing the cable is fabricated on board the second ship 6, and is then laid in the trench.
- the cable need not necessarily be flexible.
- FIG. 6 A further method is illustrated in Figures 6 and 7, wherein a relatively long duct 302 is towed to the laying site by two vessels 12.
- the duct is preferably pre-fabricated on shore, to lengths of up to around 7.5 km.
- the complete duct would consist of a steel jacket 420 with a plastic pipe insert, containing the multiple conduits 300.
- the pre-installed ducts are typically separated inside the pipe by spacers 400.
- the insert 410 may be pulled through the steel pipe 420 onshore, typically using a winch and a series of pulling blocks on the plastic pipe, and the ends of the plastic pipe may be sealed to the steel jacket, providing a water tight seal.
- This method of laying may readily be used for depths of up to around 1000m, and greater depths can be achieved.
- the duct diameter will typically be approximately in the range 1-inch to 3 -inch over 5 to 10 km, or at least 6-inch and often 12-inch or more for longer lengths up to 100km.
- the factors to consider are that a larger pipe obviously increases cost per unit length but can accommodate more cables and simplifies installation of those cables.
- the number of cables that can be accommodated increases rapidly and non-linearly, with outer duct diameter and so a larger duct is prefened.
- a diameter of the order of 24 inches can accommodate of the order of 25000 fibres and a diameter of the order of at least about 30cm is prefened.
- each section of pipe 420 houses a multi-bore connection plate 500, mounted in the end of the plastic tube sealed inside the pipe. This is preferably a stab-plate 600, as shown in Figure 8, though other methods of connection of the sections of pipe may be employed.
- the ducting 302 may also be laid by a single vessel 14, with the multiple ducts 300 being introduced at a later stage.
- Figures 9 and 10 illustrate an implementation of this method.
- the vessel 14 pays out the pipeline 420 as it is fabricated on board.
- the ducts 300 are then pulled through the entire pipe 420 in a single operation, as shown in Figure 10.
- the pulling wire 520 may be attached to the ducts 300 at several points along its length, thereby distributing the tension load.
- the pulling wires 520 are preferably left inside the pipe after the installation.
- the pulling benefits from the buoyancy of the plastic ducts 300 inside the submerged pipe 420, allowing friction to be minimized.
- the pulling wire 520 is typically installed into the pipe 420 using a pig. This method would allow a particularly fast installation, but may be limited to the distances of pipe it may be used for.
- FIG. 11 Another method, as depicted in Figure 11, lays the pipe 420 in sections, installing each section of ducting 300 as each section is laid. This could either be employed using snap type connections 600 (as illusfrated in Figure 11) or welding to join the sections of pipe 420 and ducting 300. The advantage of this technique would be that there is theoretically no limit on the length of pipe which could be installed.
- the ducting 300 could also be installed into a pipeline 420 as it is laid, as illustrated in Figure 12. Difficulties arise here due to the pipe being flooded as it is laid, but provided these are overcome, installation can be relatively fast.
- Cables 310 could also be laid inside a pipeline 420 already laid without separation by multiple ducting 300, such as an oil or gas pipeline. However, there may be problems with this type of installation if objects or obstacles exist within the pipeline.
- the casing could be formed from other material, particularly thermoplastics, most preferably HDPE.
- thermoplastics most preferably HDPE.
- the outer duct would of course have to be substantially thicker than a steel duct to provide similar protection and there may be a requirement to add ballast to overcome buoyancy but advantages may include flexibility and cost. Reinforcement, such as metal braid or wires may be included to add weight and to provide protection.
- the joining or splicing of the cables at the splicing points may, according to embodiments of the invention, be carried out in several ways, and there are also various alternatives for the termination point(s) of the multiple ducting.
- One method according to an embodiment of the invention would employ a Fixed Pipeline End Manifold (PLEM)700, as shown in Figure 13.
- a sub-sea steel box structure is fixed to the seabed, and connected to the bundle of multiple ducts 300 with porches 710 around the periphery where outgoing cables 320 can be pulled in and connected to a central distribution module 720.
- the structure 700 is piled to the seabed for greater stability, and is typically sloped to allow trawl- gear to pass over it more easily. This option can be employed in deep waters, though the depth may be limited by the diver intervention required for connecting the cables.
- An alternative may employ a remote system to connect the cables, allowing greater depths.
- the armoured cables 320 connected to the PLEM 700 will typically be protected in the immediate vicinity by concrete mattresses or "dog kennels" 730, illustrated in Figures 14 and 15.
- the PLEM 700 can be a concrete structure, which may be cheaper than the above steel structure. It may also be a hyperbaric environment, which has the advantage of allowing dry cable connection rather than wet cable connection, which is often difficult and time-consuming. The installation of a hyperbaric chamber on the sea bed although expensive may offer advantages in terms of ease of repeat access.
- the PLEM 700 would be designed to be lifted from the sea bed by a connection vessel 16.
- the armoured cables 320 may be doubled back along the length of the duct bundle 302, so that the PLEM 700 supports them during lifting.
- the PLEM 700, the doubled- back cables and the cables 320 connected are all protected by concrete mattresses 730 or similar.
- the PLEMs 700 may be lifted using a DSV mounted crane or similar, in an similar procedure as that used for retrieving the end of an abandoned pipeline.
- the depths to which such a system could be laid may be limited to around 100m, by the lifting apparatus, though specialist vessels may be able to lift the PLEM from greater depths.
- This system would allow the surface connection of cables, which would be far more practical than undersea connection, though it may involve extra cost in hoisting the PLEM from the sea bed. It would also allow the PLEM to be retrieved at any time, in order to repair or replace cables, or to attach new connections simply and efficiently.
- the recoverable system of Figure 16 is adapted to provide a daisy-chain of connections, as shown in Figures 17, 18 and 19.
- the final length of the main pipeline 302 with multiple ducting 300 is fitted with a series of "wye" connections 740 and a final integral pipeline end manifold (PLEM) 700 mounted on the laid-down end of the pipeline.
- the "wyes” 740 and final PLEM 700 are separated by distances sufficient to allow intervention at each location without the risk of collateral damage to the adjacent cables.
- a series of side branch connections 750 (at 45 ° to 7 ° in the daisy chain layout are made to the "wyes" 710 in the main pipeline, one of which is illustrated in Figure 18.
- These branches consist of smaller diameter pipelines 304 (typically 12-inch diameter for a 30-inch main pipeline).
- each branch connection 750 one or two conduits 304 are routed from the main bundle, to exit from the main pipeline through a side aperture in the pipeline wall.
- the conduits 304 are typically given a constant (typically 4m) bend radius to minimize resistance/wear during the subsequent operation of installing the fibre-optics into the conduits.
- the exiting conduit ends are terminated in the multi-bore stab-plate 600 fashion described above on the outside of the main pipeline 302.
- these stab-plates 600 thus mate-up with opposite stab-plates in the branch connection pipelines 304.
- the side connection pipelines run for a straight length and are themselves terminated in PLEMs 700.
- Installation of the branch connections would typically employ the subsea mating of the stab-plates 600 on the main 302 and branch 304 pipelines. This would be performed using a system of docking and alignment devices mounted on both the main and branch pipelines. Typically, the installation would be achieved in two stages, an initial rough docking to structurally locate the branch pipeline onto the main pipeline followed by a closing operation where fine tolerance locating pins would engage and align both sides of the conduit stab-plates.
- PLEM i.e.
- the conduits terminate in structures designed to allow splicing of the fibre-optics between the pipeline and the incoming armoured cables.
- the PLEMs are lifted from the seabed to the surface as with the previous method, thereby allowing the operation to be performed under atmospheric conditions.
- PLEM is lifted to the surface where the suspended pipeline assumes a catenary shape down to its touchdown point on the seabed.
- the length of pipeline lifted would typically be 150% of the water depth at the PLEM.
- a substantially rigid section of multiple ducting may be provided with a plurality of relatively less rigid extending branches or risers from which one or more cables can be deployed.
- the branches are preferably of sufficient length and flexibility to facilitate raising to the surface to attach an extending armoured cable to a cable passed through the multiple ducting and into the branch.
- the armoured cables may extend away from the main conduit in a similar manner to that depicted in Fig. 17.
- the cables may extend directly from the ends of the flexible branches, without being doubled back along the branches. Similar distance considerations apply to the spacing of the extended cables in this embodiment and that of Fig. 17. Protection for example with concrete mattresses may be deployed.
- the following outline gives a possible procedure of the splicing operation for connecting an armoured cable to a 300m long branch pipeline in 100m of water depth:
- a Single Buoy Mooring (SBM 800), may be anchored in place with flexible risers 810 with distributed buoyancy 850 between the end of the multiple ducting 820 and the surface buoy 800, with one riser for each conduit.
- Dynamic armoured cable risers 830 designed for fatigue resistance under wave loading, are pulled-in to the SBM and surface-connected.
- the buoy 800 would be anchored to the sea bed using cables or chains 840, which also serve as protection for the enclosed cables and risers 320. This type of installation may be significantly cheaper than other types.
- FIG. 22 Another alternative would be to have a fixed surface termination point, as shown in Figure 22.
- a temporary or permanent platform 900 could be constructed, or an existing platform could be used.
- the cables 320 would be connected at the surface, again saving on complication and expense.
- the termination point may include a bundled conduit riser and J-tubes 910 for future pull-in of the armoured cables 320 for surface- connection.
- J-tubes 910 are commonly used for pull-in of power cables or control umbilicals. These could be retrofitted to an existing oil or gas platform. Retrofit risers are commonly installed offshore, sometimes as pre-fabricated bundles.
- conduits and cables could also be installed in empty well space.
- the conduits and cables may be protected by the structure of the platform itself, and exclusion zones could also be set up around the platform.
- the faces having complementary alignment components adapted to guide the sub- ducts of the conduit into connection with the sub-ducts of the multiple ducting may facilitate installation.
- Splicing or connecting the cables on board a vessel, facilitated by a recoverable or buoyant termination point may simplify installation.
- connection points at the termination point being spaced apart along the length of ducting, preferably at least 100m apart, more preferably at least 300m apart, ideally so that the long distance cables are at least 50m (ideally at least 250m apart) apart in a region at least 300m from the ducting can reduce the risk of multiple cable damage.
- FIG. 23 illustrates one of these methods, according to an embodiment.
- the cable 320 is propelled along the duct by flowing fluid, typically water, rather than simply being pulled through. This may allows it to negotiate curves and imperfections in the duct without getting jammed. It is of course possible simply to pull a cable through an existing duct. The problem usually encountered here is that the cable may get jammed inside the duct with no means for freeing it other than cutting the duct open. Pulling methods are essentially dependent on the tensile strength of the cable and the friction of the cable jacket; the effective distance for such a method may be increased by incorporating a reinforcement in the cable, such as a steel wire and by providing a low friction, for example PTFE jacket.
- Friction is often caused by curves in the duct, due to being laid on uneven ground, but can also be caused simply by excessive friction between the cable and the duct walls.
- Figure 24 illustrates the curvature which can arise in ducts 302 laid on the sea floor.
- Known flow methods may suffer less from excessive wall friction and allow a quicker and more efficient installation by preventing the cable from jamming.
- FIG. 26 shows the typical pressures which may be employed using water with known flow methods.
- the diameter of the duct 302 is preferably at least 0.25m.
- the pipes used may be able to withstand greater pressures, allowing a faster jetting of the cable.
- the cable is fitted with a head which provides a near seal with the walls of the duct, again allowing greater pressure to build, and pass the cable faster.
- the cable allows significant volumes of water to pass over it during transit, aiding the flow, and enabling an easier transit.
- US-A-4,756,510 discloses a method for installing a cable in a fluid transmission pipeline using a pig; such a method may be adapted to install a cable in the ducts provided by embodiments of the invention.
- the flow method becomes effectively a pulling method as the majority of the force is applied by the head and little is applied to the cable jacket.
- the duct is continually treated or flushed with water. This maintains clean conditions inside the duct, and allows for easier replacement of cables. If the duct is not straight, the friction may increase. The friction may also increase if impurities are present in the duct.
- the duct may be cleaned before introduction of a new cable by passing a cleaning head through the conduit, by similar flow methods. This may employ scraping or brushing action on the duct walls, and may be passed by any of the methods described, though particularly by pulling or by flow methods.
- the cable may be unreeled within the duct.
- sections of multiple ducting separated by intermediate access points which may advantageously comprise repeater stations may be provided.
- repeater or splicing stations may be provided at, for example, 12.5 km spacing, giving a total of 8 sections and the cable inserted in stages. Whilst provision of such stages may add to cost, it facilitates repair for example in the event of damage to a section and even in the (rare) event of catastrophic damage to a section it may only be necessary to replace a single section between splicing or repeater stations.
- Figure 25 shows a first embodiment of an upgradeable repeater. This may be provided independently and used in other applications, including single cable applications.
- an outer conduit 110 containing multiple (here 6 are shown but more or fewer may be employed) sub-ducts 112a...112f is coupled to one end of a repeater housing 120. Cables 114a...114f (preferably fibre-optic, but similar principles may be employed for co-axial or other electrical cables) are passed through the sub-ducts to connectors (not shown) on the outer wall of the housing 120. Each connector may couple multiple fibres. Not all cables need be present at the same time. Directing ducts (not shown) may be provided within the housing to direct an incoming cable to the connection point on the wall of the housing.
- continuation cables 118a...118f enter from respective sub-ducts in an opposed duct 130.
- Each set of cables 114a...ll4f and 118a...ll8f is coupled to a respective repeater 116a...ll6f mounted on the exterior of the housing by optical connectors and water-tight (at least for sub-sea applications; the embodiment is not so limited) fixings and contains repeater circuitry.
- the repeater circuitry will normally contain electronics which demodulate, shape, and re-form the signals carried optically and receive power via a water-tight connector (not shown) from the housing 120 which will normally receive power from a power cable contained within the duct 110.
- each fibre-optic cable 114a...114f may contain integrated power connections, for example carried in a shielding or reinforcing braid.
- the repeater may comprise an optical amplifier or optical circuitry which boosts the signal without converting it to electronic signals.
- the cables may be directly spliced onto the repeaters; this may be suitable for single deployment but may complicate or prevent replacement of repeaters.
- An advantageous feature, which may be provided independently, is the facility to upgrade repeaters, for example to increase bandwidth or signal quality or reduce power requirements as improved repeaters become commercially available.
- Fig. 25 which will typically be relatively small and may be ananged for the repeaters to be installed or replaced by a diver or a remote operated vehicle (RON) and in the case of splicing rather than using connectors, hyperbaric splicing equipment may be provided (in a sub-sea application).
- the apparatus may be ananged so that the repeaters can be accessed, added or replaced underwater or may be ananged to be recovered to the surface for the installation of new cables or the replacement or addition of a repeater.
- conduits with push-fit connectors are employed, for example as described with reference to Fig. 11, the repeater housing may push-fit onto such a conduit.
- the repeaters may be installed in a sealed chamber.
- FIG. 27 depicts schematically and not to scale such an anangement in which a sealed chamber 121 large enough for work to be performed within it and having an access airlock 123 is provided and the ducts 110, 130 coupled to the walls of the chamber.
- the chamber may be similar in construction to the PLEM of Figure 13.
- This embodiment may provide the following advantages in deployment of a long distance protected conduit fibre-optic system: - • to allow uninterrupted offshore installation of an unlimited length of a bundle comprising: empty conduits, fibre-optic cables and associated power cables within a protective steel pipe envelope.
- the embodiment provides for offshore termination of the conduit/fibre-optics and transitions or connections to traditional armoured cable by: • simple exiting and tie-in of individual fibre-optic cables which can either be preinstalled during the laying operation or post-installed using future flowing/pigging techniques.
- the key feature of the chain-pipe embodiment is to split the protective outer steel pipe envelope into discrete half shell units and install these over the internal conduit/cable bundle during the offshore lay operation.
- half shells are most convenient, it will be appreciated that the halves need not be exactly evenly sized nor symmetrical (and the shells may comprise complementary mating "halves"). More than two partial shells, for example three or even more may be used. However, two is preferable and use of larger numbers of partial shells, whilst reducing the size of the individual components and thereby offering some advantage, is likely to complicate installation significantly.
- each "half" has an opening at least about 90% of the internal diameter or subtends an angle in the range about 120 degrees to 240 degrees, preferably 150-210 degrees (or equivalent if the shells are not circular
- the shells are preferably shipped as individual pieces to the offshore lay vessel and subsequently assembled in a continuous lay operation which may be performed relatively rapidly.
- the half shell design preferably incorporates pin-jointed hinges 610 alternating by 90° at each joint between lengths of chain-pipe. These hinges inhibit bending moments developing during the laying process.
- the pin connections 620 effectively introduce continuous articulated "universal joints" along the length of pipe, with sufficient flexibility to allow the assembly to follow
- the shells may be assembled using a hydraulically operated handling cradle. Clamping of the half shells together may be performed using a metallic banding system, which will typically be hydraulically tensioned. Alternatively, the shells may be clamped using bolting. In certain cases, the shells may be welded; however that may introduce complications protecting the contents of the shells and also complicates repair.
- each half shell unit is identical and is fabricated from the following parts:
- a length of tubular half shell 630 The length of this may be selected as appropriate for the handling equipment and factors such as water depth, buoyancy from the internal conduits, lay tension, may be taken into account but is preferably at least 3m and preferably no more than 25m, typically in the range 5m to 15m. About 6m or 12m are convenient sizes for fabrication, handling and deployment in most conditions.
- a hole 640 for a locating pin, to be described is cut. This hole is ideally located half-way around the semi-circular section of the shell, and set back sufficiently to provide adequate pull-out strength when assembled with the following shells.
- At the opposite end is:
- An internal split sleeve connector 610 This is rolled to an external diameter which is about 10- 12mm less than that of the internal diameter of the half shells.
- An alternative configuration is also possible, with the internal diameter of the external sleeve about 10- 12mm larger than the outside diameter of the half shells.
- the connector is profiled to have an extension tab, here semi-circular but other appropriate shapes may be used, and matching recess 612. These engage with the opposite half shell sleeve connector.
- an extension tab In the extension tab is a hole with a protruding pin 620 welded into it. When assembled with the opposite shell the two pins align to form an articulating axle, or hinge.
- the connector is bonded, preferably welded to the half shell preferably using continuous fillet welds.
- Internal alignment split sleeves 640 These are spaced along the length of the half shells to provide longitudinal and transverse shearing resistance to the assembled pipe shells and maintain a circular cross-section. The number and location of these will depend on the length, thickness, material and deployment conditions of the pipe. The embodiment shown has three, one of which is near the "open" joining end and the others of which are spaced approximately evenly between this and the end split sleeve connector. It will be appreciated that any problems with integrity of the assembly can be alleviated by including more of these connectors, but at a cost.
- the alignment sleeves are profiled to have semi-circular extension tabs 622 and matching recesses 624 (or other appropriate shape). These engage with the opposite half shell alignment sleeves.
- the alignment sleeves are bonded, preferably welded to the half shell, preferably using discontinuous fillet welds.
- the assembled shell pairs are held together using a clamping system. This is either in the form of a hydraulically tensioned metallic banding system or by bolting.
- the bolting may be recessed through the half shells and into the internal tabs of the alignment sleeves.
- the duct should be suitable to protect the cables from sub-sea aggression, for example to provide a degree of protection from loose rocks, dragging anchor chains, marine life and the like. However it is not expected that the duct will provide complete protection and is unlikely to be sufficiently robust to withstand a direct impact from a ship's anchor.
- the duct shells may be ananged to form a substantially watertight seal but normally a degree of water flow will be permitted through the j oins , particularly where the duct is hinged between shells .
- the duct shells will be formed from steel, preferably having a thickness of at least about 2mm, more preferably at least about 5mm, sometimes at least about 10mm.
- the prefened method for offshore installation of the chain-pipe bundle is as follows:
- All internal materials are shipped to the lay vessel in predetermined coiled lengths on carousels and readied for un-spooling and assembling into a bundle.
- Preinstalled fibre-optic cables can be shipped separately and fed into designated conduits having continuous longitudinal splits prior to assembly with the remaining empty conduits.
- pre-assembled, protected, fibre-optic cables can be installed into the bundle individually.
- Power cables can be assembled and strapped together before assembly with the conduits or alternatively run individually, as required.
- the assembled conduit bundle is then fed over an assembly cradle bed where the half shells are readied.
- the half shell pairs are alternately split horizontally and vertically.
- a horizontally split pair the lower shell is placed on a mobile cradle located adjacent to the conduit bundle and the shell slid sideways and underneath the conduit bundle. The shell is then lifted up so that its pinhole locates onto the lower pin of the preceding shell pair.
- the upper shell is lowered over the conduit bundle to seat onto the lower shell, engaging its pinhole over the upper pin of the preceding shell pair.
- alignment aids are made to engage and align the two half shells together to form a circular cross-section.
- the clamping system is then installed. This can be either a tensioned band system or hand (or machine) installed bolting.
- the completed shell pair is paid out so that the next section of exposed conduit bundle comes over the cradle bed.
- the next shell pair will be split vertically.
- Both side shells are placed onto the mobile cradles.
- the cradles are then rotated through 90° and then slid sideways towards the conduit bundle.
- Both shells are manoeuvred so that their pinholes locate onto the horizontally orientated pins of the preceding shell pair.
- Alternative assembly methods are equally feasible including assembling four (or more) adjacent shells in one production step. Assembling two (or larger even number) adj acent pairs including both horizontally and vertically split shells . has the advantage that the shells are aligned the same way each time - that is one assembly station will always receive horizontally split shells and the other will always receive vertically split shells.
- the chain pipe half shells may be modified to provide branches at the termination point.
- a half shell may have an opening through which one or more sub conduits may pass and onto which a riser duct may be attached.
- the riser duct may be relatively more flexible than the chain pipe.
- the opening may be angled to form a branch for example in an analogous manner to Fig. 19.
- the invention extends to a duct half shell (or component) including an opening through which a conduit can pass to a branch duct or riser.
- branches may be inserted at joins between pairs of half shells, although this may compromise integrity of the join.
- a branch coupling may be provided at such joins.
- Figure 28 illustrates the typical depth of the sea bed for a transatlantic submarine cable.
- Figures 29 and 30 illustrate typical depth profiles in the region of the US and UK continental shelves respectively.
- Figure 31 illustrates the typical depths of penetration of various shipping activities, along with the usual burial depths 950, and the burial depth according to an embodiment of the invention 960.
- Previous installations have tended to choose a constant burial . depth of approximately two feet below the ocean floor. However, as can be seen from Figures 28 to 31, this is usually inappropriate. In shallow waters such as those on the continental shelves, it is insufficient to avoid anchor damage, which is the most significant factor in submarine cable faults.
- Figure 32 illustrates the stockless type anchor employed by most modern vessels. This type of anchor has greater sea-bed penetration characteristics than other types, as can be seen from
- Figure 33 a graph illustrating anchor penetration relative to vessel size.
- Cables which are buried at the usual depths are often unearthed eventually by tidal and storm waters, and when exposed, the cables can be cut despite the traditional armour plating employed. Damage is usually caused by shipping, for example, by dredging, trawler fishing, and, most commonly, ships' anchors. The subsequent losses of transmission can cause major disruption in communications networks which rely on the cables, and repairs are usually highly expensive and time-consuming. For these reasons, sub-sea cables are usually armour plated, and are also buried in shallow waters. The present invention prevents damage to the cable from the various hazards at the various different depths and sea areas, thus allowing a more reliable cable network.
- Figure 31 allows for the different penetration depths of different hazards, burying the conduit or cable on a variable depth trajectory, as shown. This is sufficient to avoid damage in shallow waters, where cables are particularly susceptible to anchor damage, as described. This trajectory also only requires relatively shallow burial in deeper waters, saving time and expense in the trenching process. Other hazards, such as dredging, which take place on the continental shelf but which penetrate the ocean floor to a lesser extent, are also avoided by this arrangement.
- the armour on the cables or conduits buried on the continental shelf is increased, so as to prevent damage should they be unearthed by, for example, bass storm waters.
- conduits or cables are buried to a depth of about 8 feet (typically at least about 2m, preferably about 2.5m, usually between 2-3m), in an anchor zone (typically in water up to a depth of about 500ft or in water up to a depth of at least about 100m, typically up to about 150m water depth) and to a shallower depth in water outside the anchor zone.
- the depth is preferably about 3 feet (at least about 3/4 m, typically about lm, usually between 3/4 and 1.5m or 2m) in a dredging zone (but outside the anchor zone), usually up to a water depth of about 1000 feet (typically in the region from the anchor zone to about 400m or 500m).
- the burial depth may be much less, for example about 1 to 2 feet or about 1.5 feet in deep water. More particularly, the burial depth may be, for example, less than 2m where the water depth is about 300m or more, typically less than lm where the water depth is about 400m or more, often about 0.5m where the depth is 400m or 500m or more.
- the burial for the embodiments employing the variable depth trajectory is implemented in the various ways outlined previously.
- the trench digging is supplemented by a second vessel which draws a tool to fill in the trench. This is implemented in one embodiment by a second plough, which simply churns the soil which was removed back into the trench.
- Damage due to conosion or material defect could occur in operation causing loss of integrity to the pipeline, resulting in a leak or mechanical weakness. Normally this type of damage would be prevented by quality control of materials, installation and operational maintenance. Nevertheless shortcomings in these areas could lead to conosion due to sea water seepage, loss of integrity, and the compromising of installation activities, such as passing pigs through the pipeline. This type of damage may be repaired by fitting clamps to seal leaks, and by providing structural reinforcement where required.
- Dropped objects could cause impact damage such as dents or crushing of a pipeline.
- Dropped objects are normally associated with locations near to existing offshore platforms. Although there is potential for objects to be dropped in open water, from any passing vessel, exposure to dropped objects is principally limited to vessels in transit in the vicinity of the pipeline. As heavy loads are not handled in transit it is highly unlikely for this type of incident to occur. Storm conditions may lead to vessel sinking or loss of cargo that could drop onto a pipeline. While this type of event has occuned in the past, the probability of such an occunence is incredibly small, and thus could not be predicted with any degree of accuracy. Fishing Activities
- the main hazards from fishing activities are from direct impact by trawling gear or snagging of nets and associated equipment.
- Fishing activity takes place principally in the near-shore regions, out of the shipping lanes.
- Trenching of the pipeline(s) may provide a high degree of protection from fishing activities. For pipelines trenched in sand, natural backfill is anticipated, and for pipelines trenched in clay the trench would generally be steep sided. Trenching may thus provide an efficient form of protection for the pipeline(s).
- the main concern with shipping is the possibility of anchors being dropped or dragged across the pipeline.
- the Channel has two busy shipping lanes passing across possible pipeline(s) routes. Unplanned or accidental incidents with anchors cannot be ruled out. It is impractical to protect a pipeline from direct impact of a dropped ships' anchor, in view of the high degree of seabed penetration that can occur and the relative infrequency of such an event.
- Trenching has been shown to provide reasonable protection from dragging anchors and chains, though there are shortcomings, which are examined in more detail is later sections. However, trenching to at least 0.5m below seabed should provide reasonable protection from dragging anchors and chains.
- Figure 37 illustrates a Repair Strategy. Repair procedures and standby repair equipment are also preferred as part of the contingency package.
- the repair system implemented in accordance with the invention may have an emergency response plan, maintain stocks of spare pipe, have to hand ancillary equipment such as clamps, and have pre-prepared procedures for commonly applied techniques such as concrete weight coating removal, pipe cutting, and hyperbaric welding. It is noted that repair may be greatly simplified in the case of a modular outer pipe such as the "chain pipe" mentioned above; in such a case repair may often involve replacing the damaged pipe segment with a new segment and repair clamps may not be required.
- Certain key long-delivery equipment, described in the preceding sections, are kept on standby for possible repairs. This equipment could be pooled by a number of pipeline operators to share the cost. Such emergency repair clubs may have standing emergency contracts with vessel operators to provide emergency repair vessels and tools.
- a preferable complete sequence of operations is as follows: Remove Concrete and coating [MOP 1]: a) Excavate around pipe b) Attach concrete disc cutter to cut circumferential slots c) Attach concrete disc cutter to cut longitudinal slots d) Use hydraulic tool to lever off concrete e) Use wire brushing tool to remove coating locally
- a standard mechanical repair clamp would preferably be used.
- the cable duct pipeline is a low- pressure system
- simple low-pressure clamps may be used for this type of repair.
- clamps are available, from, for example, PLIDCO, for repair of minor leaks in pipelines using gaskets to retain the fluid. These clamps re-establish the pressure holding capability of the pipeline.
- the simplest type uses a fully encircling bracelet to secure a cone-shaped seal over a small hole. Typically, once a bracelet is . secure the sealing cone is tightened into the defect, providing an effective seal.
- Larger mechanical clamps may comprise a flanged 430 and bolted pair of half shells 420, with sealing gaskets 440.
- the seal anangement will typically vary from simple clamps with a single seal, to high integrity clamps with twin seals, complete with packing bolts to energise the seals, and an annulus test port to allow the clamp seal integrity to be checked after installation.
- Figures 42 and 43 show suitable clamps.
- the soil around the pipe would be excavated to provide clearance for fitting the clamp, which would be bolted up around the pipe to make a seal.
- the structural clamp that has the capability to transmit forces adequately, for example, the structural clamps cunently produced by
- Install Repair Clamp [MOP 4]: a) Soil should already have been excavated from beneath the pipe to allow clamp to be fitted around the pipe b) Deploy clamp and centralise over pipe aperture c) Lower over pipe and close around pipe (hydraulic actuation or flange-pullers) d) Insert stud-bolts, nuts and fit bolt-tensioners e) Tension studs and tighten nuts f) Tighten end-studs by tension/torque to actuate seals g) Test seals using hot-stab Cut-out Panel Cable Repair
- the aperture in the pipe provides access for cable inspection and repair.
- the aperture cut-out is preferably covered and sealed by a repair clamp. This may avoid the need for welding which saves time and reduces the risk of cable damage during reassembly.
- the procedure takes place after an aperture has been cut in the pipe, through which the cable-ends can be accessed for repair.
- the method should will be applicable to three potential scenarios:
- Hyperbaric repair requires a dry pressurised chamber around the pipe and saturation-divers. Air-divers could only be used in shallow water (under 50m). Divers would be trained in cable repair tooling and equipment
- Purpose built tooling could employ a small dry chamber to carry out a repair, operated by a diver or semi-skilled technician.
- a compact cable-splicing tool that could automatically align and join individual fibres in a cable would be a significant advantage; such a tool can be based on existing fibre joining tools. Such a tool would greatly facilitate the deployment of a deepwater remotely operated tool. It is desirable to employ a cable joining method that results in a low profile junction, with a diameter not much larger than that of the parent cable. It is noted that a full hyperbaric chamber may be used in the procedures, if suitable compact cable-splicing tools are not readily available.
- Pipe-end connectors 580 are considerably more expensive but can save considerably on vessel time.
- Figure 46 shows mechanical pipe end connectors 580.
- a replacement pipe-spool will be prepared to fit between the severed ends. This spool will include cable jumpers with sufficient slack for a repair at each end. The spool will also include apertures close to each end. These apertures are used for access, to join the jumpers within the spool to the severed cables, using the cable repair method (above). The aperture is then closed by a half-shell clamp.
- FIG. 47 shows such a combined tool.
- This important construction which facilitates repair may be provided independently in accordance with a further aspect of the invention which provides a spool for use in repairing or replacing a length of cable- canying duct, the spool comprising a length of duct having at each end thereof means for mating with a cable-carrying duct to be repaired, the duct further having at least one opening or removable and resealable access panel providing access to the interior of the duct.
- the spool can be inserted in a duct in place of a damaged length of duct and cables can be spliced using the opening or removable access panel to gain access to the interior after the duct of the spool has been joined to the duct.
- the dimensions of the duct of the spool will generally conespond to the dimensions of the duct to be repaired, typically at least 30cm diameter.
- the means for mating may advantageously comprise a pipe end connector, particularly a sleeve ananged to slide over the duct to be joined.
- the opening may be ananged to receive a half shell clamp.
- the duct section will typically be at least 2 metres long, typically at least 10 metres long.
- Method of repair may also be provided independently as independent aspects.
- this aspect may provide a method of repairing a sub-sea duct carrying a plurality of cables comprising removing a damaged section of duct, inserting a repair spool comprising a length of duct (preferably having similar dimensions to the duct to be repaired) in place of the removed section, j oining the repair spool to the sub-sea duct, preferably by means of connectors pre-installed on the repair spool; accessing cables within the repair spool through an aperture in the repair spool to splice (or connect) the cables; and sealing the aperture.
- the cables are spliced using a hyperbaric splicing method, for example by enclosing the repair site in a hyperbaric chamber and/or by providing a hyperbaric splicing tool to create a hyperbaric region around the cables and splice the cables.
- This method may be modified to incorporate alternative features of the other repair methods disclosed herein and any such modified method may be provided independently.
- the invention further provides a sub-sea cable splicing tool comprising means for creating a hyperbaric or water-free region around at least one cable to be spliced and means for splicing the or each cable within said region.
- the cables may be formed to facilitate repair or splicing, for example as ribbon cables.
- the repair methodology is quite different from the case of a duct that contains individual cables. Principally the integrity of the outer pipe is not as critical.
- the outer duct pipe is there for protection, not as a piggable, pressure-containing pipe. In this case it is important to repair the conduits, maintaining the internal bore diameter constant as far as possible. While external protection does not have to be pressure containing, it must be reinstated.
- conduit-spools will include cable jumpers with sufficient slack for a cable repair at each end. If there is a cable, it is repaired using the cable repair method, described earlier. The conduit-spool is then joined to the conduit at each end using an HPDE repair sleeve Figure 49 schematically illustrates HDPE conduit 704 repair.
- These half-shell sleeves 702 are closed around half-shell packs 710 which are closed around each conduit 704 joint and held in place using high-tension straps 708.
- the outer shells include seals 712 to keep the conduits pressure tight. If necessary the ends to be joined can be chamfered 706 to provide a smoother bore for future cable installation.
- the outer duct-pipe can be repaired using an oversize sleeve to provide mechanical protection only.
- Figure 50 illustrates outer duct repair. This oversize sleeve will allow space for the conduit repair sleeves 802 to fit within the protection offered by this outer duct sleeve 804. The outline procedure for this repair is given below. This section goes through selected repair procedures using individual MOPS.
- MOPS are repeated a second time they are in italics.
- Replacement pipe-spool (a short length of replacement pipe with connection fittings at each end and aperture for cable repair) is prepared at surface to fit between the severed ends, b) Cable ' j umper s ' slightly longer than the spool are placed 30 within the pipe-spool with sufficient slack at each end, c) Pipe-spool will also include apertures for repair access, closed by a half-shell clamp, close to each end of the spool. Apertures will be closed by temporary straps, with cables prepared for joining inside. d) 'Pipe-end connector' at each end of the pipe-spool is prepared for activation with hydraulic tools or diver
- Subsea cable repair at each end [MOP 6] 30 a) Identify damaged cables for repair. b) Position test and splice tool equipment on the cable repair working platform c) Deploy working platform onto the pipe. d) Pull the cable-ends into the aperture. e) Install hyperbaric chamber f) Deploy diver-technicians g) Cable-ends are locked-off or held in temporary 5 restraints. h) Strip back cable to sound fibre and prepare
- an alternative aspect of the invention provides a method of providing a plurality of spaced apart cable connection points on a shore adjacent a body of water, the method comprising providing a plurality of sections of multiple ducting extending from each cable connection point on the shore into the body of water, passing a plurality of cables through each section of multiple ducting and connecting the cable connection points by means of the cables passed through each section of multiple ducting.
- Each section of multiple ducting preferably includes a termination point.
- the body of water may be a river or may be a sea and the shore may be an island or may border a relatively densely populated area; in such applications the technical problems associated with providing land based networks may be alleviated.
- the various embodiments described may possess one or more advantages although not all embodiments will possess such advantages.
- the cables may be laid and replaced quickly and efficiently; this will allow for faster upgrading of cable networks.
- the maintenance and upgrading costs may be low in comparison to known schemes.
- the cables laid may be more reliable, as they are less susceptible to damage from shipping and from maintenance and cable replacement. Any of the features described above which contribute to any advantages identified herein may be provided independently of other features and in other applications, unless otherwise stated.
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Mechanical Engineering (AREA)
- General Physics & Mathematics (AREA)
- Optics & Photonics (AREA)
- Laying Of Electric Cables Or Lines Outside (AREA)
Abstract
The invention facilitates provision of a point-to-point cable connection between first and second points separated by an extended span of water including a first region of shallow water and a second region of relatively deep water. A plurality of ducts are provided from the first point throught the first region of the extended span to an offshore termination point between the first and second points. Preferably, the ducts are buried in the seabed to prevent damage. At least one first cable is placed in one of the plurality of ducts to provide a connection between the first point and the offshore termination point. The first cable is connected to the second cable at the offshore termination point to create the point-to-point cable connection. In one embodiment, the offshore termination point is located on the continental shelf near the transition to deep water. Cable can be installed between the first point and the offshore termination point with relative ease by passing the cable through an available conduit. This eliminatesthe need for the time consuming and expensive permitting process typically associated with near-shore cable installation.
Description
CABLE INSTALLATION
Background of the Invention
Field of the Invention
The present invention relates to the installation of cables. The invention is primarily concerned with fibre optic communication cables but may be applied to other cables, for example co-axial or other communication or power cables. The invention is particularly concerned with providing a cable connection over an extended span, particularly over a sea or other water crossing and in a prefened application is concerned with providing a deep sea (for example transatlantic) cable crossing; however, aspects of the invention may be applied to land based or other applications.
Related Art
There are a variety of known techniques for laying cables, whether sub- sea or otherwise, each of which has associated problems. Long distance sea-crossing cables, for example cunent transatlantic sub- sea cables, are often deployed by unreeling armoured cable from a cable canying vessel. There are known techniques for suspending the cable at a distance below the surface, for burying cables in shallow waters and for armouring the cables to withstand various attacks. However, installation of such cables remains expensive and problematic and the cables are susceptible to damage.
Provision of a cable link over an extended span, particularly a sea crossing, is a major undertaking and it is normal practice to plan each link to provide excess cable capacity at the time the link is constructed to accommodate future traffic for a given period until the next cable link is planned; this reduces repetition of the expensive time-consuming and hazardous work involved in installing a cable on the sea bed. The intention is normally that, once laid, the cable(s) will require minimal maintenance or disturbance underwater. The
landing stations are well defined, growth in demand can be predicted, and it is likely that the cable will have a finite life so will need to replaced at some point. Therefore, despite the large cost of creating a link, it is usual to provide a link in the expectation that a new link will be needed in a few years. Indeed, because of the risk of damage to an individual link, it is considered desirable that new links over new routes are added over time.
By way of additional background, in urban cable networks, in contrast to point-to-point long-distance links, it is likely that new individual connections will be needed frequently, but the precise routing and connection points cannot necessarily be predicted. The urban environment is, of course, far more accessible and less hostile than the sea bed. It is therefore known to provide multiple empty ducts under roadways with regular access points, enabling new cables to be pulled through the relatively short distances between access points when a new connection is required. Installation of the ducts is, in comparison to installation of sub sea cables, a relatively straightforward task, involving merely digging up a section of roadway and is routinely performed by general road construction contractors; the techniques employed on such projects would not normally be considered applicable to the engineering challenges of a major sub sea link.
Summary of the Invention
In a first aspect, the present invention provides a method of facilitating provision of a point to point cable connection between first and second points separated by an extended span, the method comprising providing multiple ducting from the first point through a first region of the extended span to a termination point intermediate the first and second points.
This aspect may enable a simplified cable installation, whereby for part of the connection, one or more cables may be subsequently introduced into an existing duct, without the expense or problems associated with installing
individual cables afresh and without requiring multiple ducts across the entire span. Indeed, for an extended span, the provision of multiple initially empty ducts may not only be prohibitively expensive but counter productive as difficulties may be encountered in passing cables through such lengthy ducts. The term " extended span " as used herein, as will be understood by one skilled in the art, is intended to exclude short-range networks and preferably implies a distance of at least about 5km and/or including a region of troublesome tenain or water, typically a span of at least about 10km. This aspect offers particular advantages when the span is at least tens of kilometres, often at least about 100km or hundreds of kilometres or (for example in the case of a transatlantic crossing) even at least 1000km. However, in certain embodiments or modified implementations, which may be provided independently, advantages may be obtained when spans of the order of a few hundred metres are traversed, for example in the case of a river crossing, particularly in the case of a festoon as described herein.
The term "duct" or "ducting" as used herein is intended to encompass any construction capable of directing a cable across a route; it will normally comprise a sealed (or substantially sealed) pipe through which the cable passes. In prefened implementations, the multiple ducting will comprise an outer duct having a plurality of sub-ducts defined therein. However, in alternative embodiments, references to multiple ducts or multiple ducting may imply multiple independent ducts or a single duct which is capable of directing more than one cable (at separate installation times). Thus, whilst the multiple duct may have sub-ducts within which separate cables can be laid, alternative embodiments are possible provided the duct is suitable for more than one cable passing operation.
The setting up of a cable connection often involves installation across a region presenting a particular difficulty or delay. An example of one such region is an area of water to be traversed. Thus an implementation of this aspect is provided between connection points separated by an expanse of water, such as a
lake, sea or ocean, the first point being on or adjacent to the shore or at or near a cable landing station, the first region being in the shore area. A particular problem with installing cable across a region of water is that usually the cable will have to be laid on the bed below the water. At least a part of a new cable connection can be made without the need to repeat the underwater laying process in the vicinity of the shore, as the new cable(s) can be installed in the existing multiple ducts.
An embodiment of this aspect provides the termination point at a distance relatively close to the first connection point. This may provide easy access to the termination point from the shore or bank of the water region.
Location of termination points
Pursuant to the invention it has been appreciated that a large amount of disruption and expense can be avoided by providing, in the case of a lake or sea installation, the termination point at a distance of preferably at least about 2 kilometres from the first point, more preferably at least about 5 km. A large amount of construction work is required in landing a cable, and, in the case of coastal installations, permits are required to land a cable and new cables must often be laid in place of old in the same route. The landing site area also suffers significant disruption, as the usual fishing, dredging and other shipping activities may have to be halted temporarily and the habitats of local marine life may be disturbed; even as close as 100m to the first point, the provision of a termination point coupled by multiple ducting can significantly reduce the overall technical effort required to provide a subsequent long distance cable link. Even for a route covering thousands of kilometres, analysis according to the invention has found that a surprising increase in efficiency of the overall process may be achieved by provision of multiple ducting over as little as 2 kilometres of route, in the vicinity of the shore end of the route. Although the termination point will normally be subsea, a termination or access point may be provided at an offshore platform,
preferably a pre-existing offshore platform; this facilitates subsequent access and splicing of cables. The termination point, whether sub sea,~ floating or on an offshore platform is preferably located out to sea (or otherwise away from the shore in the case of a lake) in the case of a route traversing water and the multiple ducting is preferably provided on or in the water bed. In alternative embodiments, particularly in the case of a river crossing or festoon as described herein, the distance may be less, in some cases for example the distance may only be of the order of a hundred metres or so although such embodiments may not offer the advantages associated with the considerably greater distances prefened (of the order of at least 2km) .
Placing the termination point at about 10 kilometres from the shore can provide a remarkable benefit in reduction of disruption when a subsequent cable is to be laid and it is surprising that, for example in the case of a cable crossing of many hundreds or even thousands of kilometres, provision of multiple ducting over a relatively small proportion of the distance can potentially significantly reduce expense and complication of subsequent cable installation operations. Benefits of having a relatively short distance to the termination point include reduced cost of multiple ducting and that the termination point remains relatively easily accessible. However, in other embodiments, the termination point is placed at a greater distance, typically more than about 10 kilometres, typically tens of kilometres or even about 100km or more from the first point. At such great distances from the shore, the disruption associated with shoreline installation may be significantly reduced. Analysis pursuant to the invention shows a surprising advantage in terms of overall technical effort for a route and reliability of cable installation may be obtained with a termination point between 10km and 100km.
Although reference is made to termination "points" it will be appreciated that the term "point" is of course not used in the mathematical sense but is intended to connote a region. The region will generally be relatively localised in comparison to the size of the extended span but may nonetheless have sub-
features spread over an appreciable area. For example, the termination point may comprise multiple cable exits spread over several hundred metres or even an area of the order of a square kilometer.
The location of the termination point is preferably chosen based on the water depth (or, for example in the case of land based systems to which variants of the invention may be applied, based on other features of the tenain; for example, a cable across a rocky and desert region may have multiple ducts through the rocky region, where installation is more problematic than through the desert region). The termination point is preferably at a minimum depth of at least about 10m; at lesser depths the advantages diminish as subsequent installations will still require significant disruption, but this possibility is not excluded and may offer advantages in certain cases. However, to facilitate access, the termination point is in a relatively shallow water region, preferably at a depth of about 300m or less, preferably 200m or less, more preferably of the order of about 100m. This allows the termination point to be more accessible (for example by divers) allowing safer and more efficient installation of cables. In a most prefened embodiment, the termination point is located a substantial distance from the shore (for example many tens or even hundreds of kilometres, typically at least about 100km) on a continental shelf, preferably adjacent (for example at least half way to, typically within about 10km of, preferably within about 1km of) a transition to deeper water. Provision of a termination point adjacent the edge of a continental shelf may have the advantage that a cable leaving the termination point may not require burying in the shelf bed or at least not for an appreciable distance. Where the termination point is provided a substantial distance from the shore, repeaters or intermediate access points or intermediate termination points may be provided between the connection point and a final termination point, to facilitate cable installation and/or servicing and/or to enable signals to be transmitted reliably over longer distances. If repeaters are provided, these may be ananged to be upgradeable; this feature may be provided independently.
In the case of a deep sea crossing, there may be a second termination point and a second region of multiple ducting from the second termination point to the second point. For example, in the most prefened implementation, the invention may provide a method of facilitating provision of a point to point cable connection between first and second points separated by an extended span including a region of deep water, the method comprising providing first multiple ducting from the first point through a first relatively shallow water (for example continental shelf) region of the extended span to a first termination point intermediate the first and second points (preferably at least about 2 km from the first point, more preferably at least about 10km from the first point, preferably adjacent a transition to deep water), providing second multiple ducting from the second point through relatively shallow water (for example continental shelf) to a second termination point (preferably at least about 2 km from the second point, more preferably at least about 10km from the second point, preferably adjacent a transition to deep water), the first and second termination points being separated by said region of deep water. In the case of a method of facilitating a transatlantic cable crossing, the first and second points are located in the US and UK or Europe respectively or vice versa and the first and second termination points are located in the respective continental shelves, the Atlantic ocean comprising the region of deep water.
The ducting can be pre-fabricated onshore, and subsequently transported to the laying site by one or more vessels. In an aspect, the invention provides a method of facilitating provision of an underwater cable connection comprising fabricating a length of multiple ducting at a first point and transporting the length to a submerged lay site at a second underwater point. This allows for longer lengths of the ducting to be installed at one time. Typically, the section of ducting is towed between two vessels, and laid at the conect site.
Another aspect of the invention provides a section of conduit for a plurality of underwater cables, the conduit comprising an elongate (preferably substantially rigid) outer pipe having first and second ends and defining an inner
space, a plurality of inner ducts positioned within the inner space and extending between the first and second ends, each inner duct defining a cable-directing inner channel extending substantially from the first end of the pipe to the second end of the pipe, wherein a seal is established at each of the first and second ends to trap a region of air in the inner space. This region of air can thus be partially or completely flooded to alter the buoyancy. Preferably the conduit has an inlet to facilitate flooding of the inner space. Similarly the invention provides a method of facilitating provision of a cable connection comprising fabricating a length of multiple ducting at a first point and transporting the length to a submerged lay site at a second underwater point, wherein the multiple ducting comprises a
(preferably substantially rigid) sealed outer pipe and an anangement comprising a plurality of ducts each adapted to receive a cable, wherein a seal is established between the outer pipe and the ducts at either end of the conduit to form a region of air trapped between the outer pipe, the insert and the seals, providing hydrostatic buoyancy, and comprising transporting the ducting to a submerged point above the lay site, breaking one or more of the seals, thereby flooding the region of trapped air, and laying the ducting at the lay site.
The termination point will normally be provided on the sea bed. However, as an alternative, the termination point may be brought to the surface. Providing the termination point at the surface has the advantage that connection of cables is simplified, but requires suitable anchoring for the termination point, and provision of suitably robust ducting. In addition, the requirement for the cable to climb from the sea bed, which may be at a depth of 100m or more to the termination point may complicate installation of cable (although in such cases, the cable may be inserted from the termination point).
To install cables into ducts, flow methods are known, as discussed further herein, and these are suitable for installing cables into a continuous run of duct up to about 10km. Where the termination point is located substantially further than this from the first point, there are a number of options.
Intermediate access points may be provided at intervals at which the cable can be installed without problem and the cable may be installed in stages, for example propelled to a first access point, pulled through then propelled to the next access point or separate cables may be installed and spliced or coupled (optionally via a repeater) at the intermediate points.
Alternatively, by careful selection of parameters (for example cable jacket/duct friction coefficient, stiffness etc, duct and cable diameter, buoyancy), the useful installation length may be extended.
As a further alternative, pull cords may be provided in the multiple ducting at installation and used to pull cable through the ducting.
As a yet further alternative, to avoid having to drag the cable through the duct, particularly for larger ducts, the cable may be unreeled from within the duct.
A splicing point may be provided intermediate the first point and first termination point, for example at a depth of about 10m or less, under a beach. The splicing point may be coupled to a cable landing station by means of a multiple duct, optionally installed by means of a directional drill. Cables may be pulled through to this splicing point, which is relatively easily accessible and joined to a long distance cable which is propelled through further multiple ducting to the first termination point. For relatively short routes, for example across a river, estuary or channel, such as the English Channel, for example up to 50km and particularly but not exclusively where unrepeated lengths are possible, multiple ducting may be provided across the whole route. In a related aspect, the invention provides a method of facilitating a cable connection between first and second points separated by an expanse of water, the method comprising providing multiple ducting from the first point across the expanse of water, preferably buried in the bed of the expanse of water, to the second point. In this way, a plurality of cables can be installed from the first point to the second point, preferably in separate operations without having to repeat the "wet" work. Preferably the first and second points are located on shore and the multiple ducting provides multiple
routes for cable to traverse from shore to shore. The invention further provides a method of providing multiple shore to shore cable connections across an expanse of water, the method comprising providing multiple ducting from the first point across the expanse of water, preferably buried in the bed of the expanse of water, to the second point and subsequently installing a plurality of cables from the first point to the second point.
Duct dimensions
The duct dimensions and configuration may vary considerably depending on the environment and degree of resistance, the route length and the cable type and the invention is not limited to any particular duct configuration for the multiple ducting. The ducts need not be circular (although this is prefened for manufacture, duct installation and cable installation); references to diameter below should be construed as applying to the effective cross-sectional width in the case of polygonal or inegular shapes. A greatly prefened configuration is for the multiple ducting to comprise a relatively environmentally resistant and preferably relatively rigid outer shell, preferably of metal, preferably steel or reinforced with steel with a plurality, preferably at least four, most preferably at least eight sub-ducts of lesser environmental resistance through which cables can be inserted. The sub ducts are advantageously formed from plastics material and HDPE (high density poly ethene) has particularly advantageous properties for sub sea applications, particularly in terms of environmental resistance, extrudability and rigidity. In a most prefened anangement, the outer shell has a diameter of at least about 15cm, more preferably at least about 30cm often at least about 50cm and the inner sub-ducts preferably have an internal diameter of at least about 2.5cm, more preferably at least about 5cm. If the internal diameter is at least 10cm, preferably at least 15cm, particularly for longer lengths, installation of cables is greatly
facilitated, although this of course requires a larger outer duct and increases the cost of installation.
In the case of a single duct into which multiple cables are installed, the diameter is preferably at least 15cm, more preferably at least 30cm and with ducts having an internal diameter of 50cm or more, a greatly increased number of cables can be accommodated. The duct preferably has a minimum internal diameter (or minimum dimension through which cable can pass in the case of a non-circular section duct) of at least about 10cm, more preferably at least about 20cm.
Point to point installation overview and variants
To provide a cable connection, cable is passed through the multiple ducting to the first termination point (or alternatively but less preferably vice versa) and from the termination point to the second point. In the typical case where there is a second termination point, passing the cable from the first termination point comprises providing cable between the first and second termination points and passing cable through the multiple ducting between the second point and second termination point. Normally, the cable passed through the ducting will be relatively thin lightweight cable, the ducting providing protection from the environment. In contrast, the cable extending from the termination point (or between the first and second termination points) will normally be heavily armoured cable designed to be lain on the sea bed over the deep water region. Thus the deepwater cable will normally be spliced at the termination points to the cable provided within the multiple ducting. However, this need not necessarily be the case and a single cable of suitable constitution may be used. If one or more intermediate splicing points are provided, the cable will be spliced (or connected, optionally with a repeater) at such points and different cable types may be used for different sections. The invention extends to provision of a cable link.
In a second aspect, the invention provides a method of providing a point to point cable connection between first and second points separated by an extended span, the method comprising passing a first cable through multiple ducting from the first point through a first region of the extended span to a termination point intermediate the first and second points and providing a second cable from the termination point to the second point.
The multiple ducting is preferably provided according to the first aspect and prefened features of the first aspect apply to this aspect and vice versa.
The first cable may comprise a relatively lightweight cable, preferably having a diameter of less than about 5cm, more preferably less than about 1cm.
Providing the second cable may include providing an armoured section of cable on the sea bed of a deepwater region. The armoured section of cable preferably has an armour layer including metal, typically steel, preferably braid or wires if not a continuous layer and the armoured section may have a diameter of greater than 1cm. Where a second termination point is provided, providing the second cable may comprise passing a section of second cable through multiple ducting
■^from the second point to the second termination point and providing said armoured section of cable between the termination points.
Typically, the ducts according to the implementations above are buried, and where they are submerged, a trench is preferably dug (or jetted) in the underwater bed for this purpose. Thus damage to the ducts from either surface or waterborne hazards may be avoided.
In one implementation, the ducts are provided in a channel drilled from a connection point to a termination point, protecting the ducts more effectively, as they can be laid further underground.
An aspect of the invention provides a conduit installation comprising a connection point and multiple ducting between the connection point and a termination point in an at least partially submerged region.
This provides an infrastructure for multiple cable connections with less expense and disruption than a multiple of individual connections.
To minimise risk of catastrophic simultaneous damage to multiple cables, preferably the termination point comprises multiple cable exits over an extended region so that cables can exit the multiple ducting at spaced apart locations. Prefened implementations of this are discussed below. In a prefened implementation, the termination point comprises a termination structure providing at least two cable exits spaced apart by at least 5m, more preferably at least 10m and in the case of a sea crossing preferably at least 50m. Analysis pursuant to the invention shows that a spacing of at least 50m in a sea-crossing cable can dramatically increase reliability of the multiple connections. The termination structure preferably provides protection, most preferably a protective duct or housing, between the cable exits and the (protective and/or suitably buried) multiple ducting. This is a particularly advantageous feature. The termination structure may be a branching sub-sea duct structure a part of which may optionally be recoverable to the surface to facilitate provision of new cables or repair or maintenance, an enlarged sea bed structure, a buoyant structure with protective cable risers or protective anchor chains or cables extending to the sea bed or an offshore platform structure with protective risers. The termination structure may include or be supplemented by protective elements such as concrete mattresses (as described herein) or other protective elements extending away from the multiple ducting and may be supplemented by or provided by excavations formed in the sea bed. The invention further provides a method of forming a subsea termination structure comprising providing a protective structure extending from a region of multiple ducting canying at least two cables to at least two spaced apart cable exits, the exits preferably being spaced apart at least 50m. A prefened spacing distance for the cables is of the order of at least about 1.5 times the water depth and the spacing is preferably at least equal to the water depth. Termination structures and methods of forming termination structures may be provided independently.
Splicing
A further aspect of the invention provides a cable splice box in an at least partially submerged region, comprising an enclosure and means for splicing cables. This allows for cables being laid in a submerged region to be spliced, thus avoiding, for example, shore line disruption caused by land based splice boxes.
In an implementation, the box is buried, protecting it from possible damage. Typically, at least two cables run from the box to a cable landing station in a shore area.
In a further aspect, the invention provides a method of facilitating cable servicing and splicing, comprising providing a first cable splice box in an at least partially submerged region, passing one or more cables from a connection point to the box, and providing service access to the cables at the box. This may provide for an easily accessible serviceable cable installation.
Upgradeability
Another problem with cable installations is the large cost involved when cables are replaced or upgraded. The present invention consists in a further aspect in a method of providing cable connections over an extended span comprising laying multiple ducts over a portion only of the extended span, passing at least one first cable having a first specification through a first duct to form a first cable connection, and subsequently after a period of time during which the first cable connection is operational passing at least one second cable, preferably having a second specification through a second duct to form a second cable connection.
This aspect thus provides for a readily and cheaply upgradeable cable system.
Typically, each duct is occupied by at least one cable, thereby maximising the data capacity of the set of conduits. However, in an implementation, one or
more of the multiple ducts are left empty. This allows for ready upgrading when higher specification cable becomes economically viable.
Cable landing sites
An aspect of the invention consists in a method of providing a cable connection between primary and secondary points, comprising installing a cable from the primary point through one of multiple ducts to at least a first primary termination point, passing the or a further cable across a substantial distance and installing the cable at the secondary point.
In this manner, long distance cable may be installed. For example, a transatlantic cable installation may employ this method.
In an embodiment of the invention, one of the ends of the cable may be installed in an area where there are few restrictions, or where only a single cable connection is needed. Thus the multiple ducts required at one end, may not be required at the other, saving expense and time. In an implementation of this aspect, the cable is passed across the substantial distance to at least a first secondary termination point, and installed through one of a multiple of ducts to the secondary point.
In another aspect there is provided a method of facilitating provision of a number of cable connections between a first point and a number of second points, comprising providing multiple ducts from the first point to a termination point intermediate the first and second points, and providing at least one cable connection point at each of the second points.
This provides that each of the multiple cables connected at the first connection may be connected to different connection points, for example a cable point in New York may be connected to the UK, to France and to Ireland.
In an implementation, there is provided a method comprising installing cables from the first point through the multiple ducts to the termination point, and passing the cables or further cables to at least two of the second points.
Typically, these methods are implemented in spanning a large expanse of water, such as a lake or ocean.
In an aspect, the invention provides a cable installation comprising: first and second connection points; multiple ducts between the first connection point and a first termination point; and at least one cable installed through one of the multiple ducts to the first termination point, across a substantial distance and to the second connection point.
This provides an installation to which additional and replacement cables may more easily be added. In an implementation, cables are spliced at the first termination point.
In another implementation, the cable is installed to a second termination point relatively close to the second connection point, through at least one duct to the second connection point, thus providing similar advantages at the other end of the connection. Typically, there are multiple ducts between the second termination point and the second connection point.
Preferably, there are access or splicing points between the first termination point and the first connection point, and between the second termination point and the second connection point, allowing for service access to more areas of the installation. In other implementations, there may be further connection points, with at least one further cable being installed from the first connection point to one of the further connection points.
Typically, the first and second (or further) connection points are separated by an expanse of water, such as a lake or ocean, thus providing, for example, a transatlantic cable installation.
There are known methods of introduction of a cable into an existing duct. The invention may provide installing a cable inside an existing duct which is already occupied by one or more cables, and means for installing cables.
Protection of cables
A further problem faced is that of damage to the cable, which often results in failure of the transmission carried by it.
The present invention consists in another aspect in a method of laying a submarine cable (or duct for canying cable) comprising using a variable burial depth profile based on anticipated hazards at differing depths. This aspect thus provides a method of cable laying which is less susceptible to damage, and thus can provide more reliable transmission.
In an implementation, the method comprises a first burial depth in a shallow water area, a second burial depth in a deep water area and optionally an intermediate burial depth in an intermediate depth water area. Typically, the shallow water area is in an anchor zone, the intermediate depth water area is in a dredging zone and the deep water area includes a deep sea fishing zone. The method may include planning depths based on coastal outlines/activity and/or distances from shore in addition to or instead of based on water depth.
This implementation provides for a cable laid to avoid the hazards most commonly found in the different regions, and save in expense in those areas where previous methods were excessive in burial depth.
A typical installation
The invention provides, in a further aspect, a long distance cable installation between first and second coastal areas, comprising in the first area a cable landing station, at least one service point, multiple ducts through a first beach region between the landing station and a first splice box in a first shelf region, a second splice box at the boundary between the first shelf region and a deep water region, and a number of cables installed from the landing station, through the multiple ducts to the first splice box, through the shelf region to the
second splice box and through the deep water region to the second, substantially distant coastal area.
Typically, the second coastal area has a similar cable installation to the first coastal area. Preferably, in the shelf and deep water regions, the cables are buried according to a particular variable depth profile, in order to avoid damage.
In a still further aspect, the invention provides a method of facilitating transmission of data across a network spanning a large expanse of water, comprising installing a data transmission cable from a first connection point through a multiple of ducts in a first region to a first termination point, across a portion of the expanse of water to a second termination point, and through a multiple of ducts in a second region to a second connection point. This provides for a cheaper, more efficient, less disruptive and readily upgradeable data transmission system.
The invention extends to installed networks, planning tools, computer software used in planning such methods , data packets transmitted by the installed cables and apparatus adapted for use in the methods of the invention. The invention is particularly suitable for building an upgradeable, particularly IP (Internet protocol) data network and the invention extends to an IP data packet transmitted across an expanse of water through a region of multiple ducting. Further independent aspects and/or prefened features are discussed below and/or set out in the claims.
The invention will now be described in detail by way of example, with reference to the accompanying drawings, in which:
Brief Description of the Figures
Figure 1 is a diagram illustrating a known anangement for laying a sub- sea cable;
Figure 2a is a diagram illustrating the anangement of the sub-sea cable according to an embodiment of the invention;
Figure 2b is a diagram illustrating an anangement for laying a sub-sea cable according to an embodiment of the invention;
Figure 3 is a diagram illustrating a method of providing a duct according to an embodiment of the invention; Figure 4 is a diagram illustrating a method of laying a sub-sea cable according to an embodiment of the invention;
Figure 5 is a diagram illustrating another method of laying a sub-sea cable according to an embodiment of the invention;
Figure 6 is a diagram illustrating another method of laying a sub-sea cable according to an embodiment of the invention;
, Figure 7 is a diagram illustrating details of Figure 6;
Figure 8 is a diagram illustrating a stab-plate according to an embodiment of the invention;
Figure 9 is a diagram illustrating another method of laying a sub-sea cable according to an embodiment of the invention;
Figure 10 is a diagram illustrating a facet of the method of laying a sub- sea cable illustrated in Figure 9;
Figure 11 is a diagram illustrating another method of laying a sub-sea cable according to an embodiment of the invention; Figure 12 is a diagram illustrating another method of laying a sub-sea cable according to an embodiment of the invention;
Figure 13 is a diagram illustrating a termination point according to an embodiment of the invention;
Figure 14 is a diagram illustrating a method of protection of ducting according to an embodiment;
Figure 15 is a diagram illustrating another method of protection of ducting according to an embodiment;
Figure 16 is a diagram illustrating a termination point according to an embodiment of the invention;
Figures 17 to 19 are diagrams illustrating another termination point according to an embodiment of the invention;
Figure 20 is a diagram illustrating a typical vessel for use in retrieving a termination point; Figure 21 is a diagram illustrating a termination point according to an embodiment of the invention;
Figure 22 is a diagram illustrating another termination point according to an embodiment of the invention;
Figure 23 is a diagram illustrating a method of deployment of a cable inside a duct according to an embodiment of the invention;
Figure 24 is a diagram illustrating typical duct curvature in the region of an obstacle;
Figure 25 is a diagram illustrating an upgradeable repeater anangement;
Figure 26 is a diagram illustrating typical pressures associated with the installation of a cable into a duct according to an embodiment of the invention;
Figure 27 is a diagram illustrating a further upgradeable repeater anangement;
Figure 28 is a graph illustrating a typical depth profile which would be encountered by a transatlantic cable; Figure 29 is a graph illustrating a typical depth profile of the US continental shelf;
Figure 30 is a graph illustrating a typical depth profile of the UK continental shelf;
Figure 31 is a diagram illustrating the typical depths of penetration of various shipping activities, along with the usual burial depth of cables, and the burial depth according to an embodiment of the invention;
Figure 32 is a diagram illustrating a typical stockless type anchor;
Figure 33 is a graph illustrating typical anchor penetration for various vessel sizes;
Figure 34 is a diagram illustrating recent fault locations of existing sub- sea cables;
Figure 35 is a table illustrating the depths of recent faults in sub-sea cables, and their various causes; Figure 36 is a diagram illustrating the different types of fault typically encountered by transatlantic cables;
Figure 37 is a diagram illustrating a repair strategy according to an embodiment of the invention;
Figure 38 is a diagram illustrating repair procedures according to an embodiment of the invention;
Figure 39 is a diagram illustrating a set of repair procedures according to an embodiment of the invention and including details of Figures 37 and 38;
Figure 40 is a schematic overview of a transatlantic sub-sea cable system according to an embodiment of the invention; Figure 41 is a diagram illustrating the typical make up and data capacity of the conduit according to an embodiment of the invention;
Figure 42 shows a pipeline repair clamp;
Figure 43 shows cutting out of a half shell;
Figure 44 illustrates traditional pipeline repair; Figure 45 illustrates repair by bringing a damaged section to the surface;
Figure 46 shows a mechanical connector used for subsea repair;
Figure 47 shows schematically a combined tool including a pipe-end connector and a half-shell clamped aperture;
Figure 48 shows a pipe recovery tool; Figure 49 illustrates repair of an HDPE conduit;
Figure 50 illustrates repair of an HDPE conduit outer duct;
Fig. 51 is a line diagram isometric of the "chain pipe" showing exploded view of horizontally and vertically split shells;
Fig. 52 is an image of the "chain pipe" showing exploded view of horizontally and vertically split shells; and
Fig. 53 is an image of the "chain pipe" showing exploded details of the connection.
Detailed Description of the Preferred Embodiments
Figure 1 is a diagram illustrating an anangement for laying a sub-sea cable. Here, a conduit 30 is laid from a cable landing station 240 to a service site
250 at the beach front. From here, a single channel 32 is bored a certain distance out into the continental shelf, typically to a water depth of 30 feet. The cable 320 is drawn through this and is then laid on the shelf. The cable is armour-plated, typically double armoured and usually buried deeply in the shelf. At the end of the shelf, the cable is then laid across the ocean floor, often trenched, until the opposite continental shelf is met.
Figure 2a is a diagram illustrating the anangement of the sub-sea cable according to an embodiment of the invention. Multiple ducting 300 is laid from the junction point 200 to the termination point 210. The cables 310split up in termination point 210 and exit the splice box or termination point 210 via cable exits 212 as armoured cables 320. The same apparatus is set up at the opposite end of the cables with a termination point 220 and service point 230. The armoured cables may be laid metres or even kilometres.
Figure 2b is a diagram illustrating an anangement for laying a sub-sea cable according to an embodiment of the invention. A conduit 30 is laid to the service point 250, but a bore hole 36 to the shelf is built to accommodate multiple ducting. Multiple cables can therefore be laid, and are either pulled or jetted to a junction box 200 at the top of the shelf. From here, multiple conduits 300 are laid in the same trench, and one or multiple cables 310 may be laid in a single conduit. These cables are then spliced at the splicing box 210 at the edge of the shelf, and the long distance ocean floor cable 320 is laid as usual. In other embodiments, the relative distances between the various stages are different. For example, the splicing box 210 may only be halfway to the edge of the continental
shelf , with the long distance cable 320 being laid to the edge of the shelf. It may only be necessary to splice the cable at distances of around 100 feet offshore. The distance from the service point 250 to the junction box 200 (or splicing box 210) may also vary, though particular embodiments of the invention, described below, allow for a longer distance to be traversed by the multiple conduits, typically of the order of 10 to 20 kilometers.
In other embodiments, the cables or conduits are laid directly from the service point 250 to the splicing box 210. In further embodiments, there may be more service points, to enable easier access for repair or for insertion of repeaters. In one embodiment, described later, a duct is drilled directly from the land station
240 to the continental shelf bed. In certain embodiments, in the sections between stages, such as between junction box 200 and splicing box 210, there may be either a single conduit, capable of containing multiple cables, or multiple conduits or cables. These may be laid by a variety of methods, as described later. Many problems faced in installing cables across expanses of water, such as lakes or seas, are involved with the shore landing site 240. The land installation involves great expense, as a large amount of construction work is required. In the case of coastal installations, permits are required to land a cable in most areas. Several coastal region agencies also require that new cables must be laid in place of old in the same route. The landing site also suffers significant disruption, as the usual fishing, dredging and other shipping activities may have to be halted temporarily and the habitats of local wildlife and marine life may be disturbed. For example, blackout periods for shellfish harvests and marine life spawning season may be incuned. Also, as cable routes restrict fishing grounds for around a mile on either side, the containment of large numbers of cables in a single route is advantageous.
This aspect of the invention, when implemented for a coastal installation, may provide multiple pathways for cables without requiring a new installation each time. This may greatly reduce the amount of construction work required and the disruption caused to shipping and ecosystems.
Cables usually have to be replaced due to simple wear and tear. Furthermore, the demand for increased bandwidth has increased rapidly in recent years along with the amount of traffic being handled by existing cable systems. Potential capacity of cables using new technological developments has also increased, but it is usually prohibitively expensive to replace cables regularly, due to the large costs involved. This aspect of the invention therefore allows simple and frequent replacement of the cables in the existing conduits, reducing costs and enabling greater bandwidth through more advanced cables.
Typical shore-end installation time scales are of the order of 18 months, whereas deepwater work usually takes around two months even though the distance traversed is much greater. There is therefore an enormous time saving to be made, not just by reducing the number of land site installations, but also by canying out more of the work further out to sea, in deeper water regions.
Cable and duct laying methods
The conduits, ducts and cables may be laid onto the continental shelf and beach floor by several methods. The channel into which the conduit or cable is be laid may be trenched. Here, a plough is dragged along the sea bed to establish a trench, and the cable is laid into it. The conduit or cable may be subsequently buried in the trench. Figure 3 illustrates one method of duct installation according to one embodiment of the invention. A channel is drilled directly from the land station to the sea-bed. This method of drilling may be used for only a first section of the anangement of Figure 2b, to the junction box 200, or also for the section to the splicing box 210.
Once a conduit or duct has been established, a cable (or further conduits) may be introduced by several methods . One method according to an embodiment is to pull the cable through a conduit, simply by passing a drawing tether through the conduit, attaching this to the cable, and pulling it through the conduit. The
cable may also be jetted, particularly using known flow methods as described later herein.
There are several methods available for the installation of the longdistance cable on the ocean floor. One such method, according to an embodiment, . is illustrated in Figure 4. A first vessel 2 drags a plough 4 along the sea bed, and another lays the cable 320 into the resulting trench by paying it out from a reel 8 mounted on the vessel 6. For this anangement, the cable 320 is preferably flexible, to allow it to be reeled effectively. This method allows efficient laying of relatively long lengths of cable. Another method is illustrated in Figure 5. The pipe 10 containing the cable is fabricated on board the second ship 6, and is then laid in the trench. Here, the cable need not necessarily be flexible.
A further method is illustrated in Figures 6 and 7, wherein a relatively long duct 302 is towed to the laying site by two vessels 12. The duct is preferably pre-fabricated on shore, to lengths of up to around 7.5 km. The complete duct would consist of a steel jacket 420 with a plastic pipe insert, containing the multiple conduits 300. The pre-installed ducts are typically separated inside the pipe by spacers 400. The insert 410 may be pulled through the steel pipe 420 onshore, typically using a winch and a series of pulling blocks on the plastic pipe, and the ends of the plastic pipe may be sealed to the steel jacket, providing a water tight seal.
This would create a region of trapped air between the plastic pipe and the j acket, which would provide extra buoyancy while the duct is being towed. When the duct reaches the laying site, the air may be expelled, or the seal punctured, flooding the area between pipe and jacket, allowing the duct to sink to the shelf floor where it can be attached to the previously laid duct(s).
This method of laying may readily be used for depths of up to around 1000m, and greater depths can be achieved. The duct diameter will typically be approximately in the range 1-inch to 3 -inch over 5 to 10 km, or at least 6-inch and often 12-inch or more for longer lengths up to 100km. The factors to consider are
that a larger pipe obviously increases cost per unit length but can accommodate more cables and simplifies installation of those cables. The number of cables that can be accommodated increases rapidly and non-linearly, with outer duct diameter and so a larger duct is prefened. A diameter of the order of 24 inches can accommodate of the order of 25000 fibres and a diameter of the order of at least about 30cm is prefened.
The end of each section of pipe 420 houses a multi-bore connection plate 500, mounted in the end of the plastic tube sealed inside the pipe. This is preferably a stab-plate 600, as shown in Figure 8, though other methods of connection of the sections of pipe may be employed. The anay of alignment pins
510 allows the conduit ends to be married more easily.
The ducting 302 may also be laid by a single vessel 14, with the multiple ducts 300 being introduced at a later stage. Figures 9 and 10 illustrate an implementation of this method. The vessel 14 pays out the pipeline 420 as it is fabricated on board. The ducts 300 are then pulled through the entire pipe 420 in a single operation, as shown in Figure 10. To aid the pulling process, the pulling wire 520 may be attached to the ducts 300 at several points along its length, thereby distributing the tension load. The pulling wires 520 are preferably left inside the pipe after the installation. The pulling here benefits from the buoyancy of the plastic ducts 300 inside the submerged pipe 420, allowing friction to be minimized. The pulling wire 520 is typically installed into the pipe 420 using a pig. This method would allow a particularly fast installation, but may be limited to the distances of pipe it may be used for.
Another method, as depicted in Figure 11, lays the pipe 420 in sections, installing each section of ducting 300 as each section is laid. This could either be employed using snap type connections 600 (as illusfrated in Figure 11) or welding to join the sections of pipe 420 and ducting 300. The advantage of this technique would be that there is theoretically no limit on the length of pipe which could be installed.
The ducting 300 could also be installed into a pipeline 420 as it is laid, as illustrated in Figure 12. Difficulties arise here due to the pipe being flooded as it is laid, but provided these are overcome, installation can be relatively fast.
Cables 310 could also be laid inside a pipeline 420 already laid without separation by multiple ducting 300, such as an oil or gas pipeline. However, there may be problems with this type of installation if objects or obstacles exist within the pipeline.
As an alternative to a steel (or other metal - steel is prefened for cost and strength) for the outer casing 420, the casing could be formed from other material, particularly thermoplastics, most preferably HDPE. A major advantage of this is that the ducting can be formed by continuous extrusion, in particular an extrusion plant can be provided on a lay barge and raw material, such as resin or pellets supplied to the barge. The outer duct would of course have to be substantially thicker than a steel duct to provide similar protection and there may be a requirement to add ballast to overcome buoyancy but advantages may include flexibility and cost. Reinforcement, such as metal braid or wires may be included to add weight and to provide protection.
Termination point options
The joining or splicing of the cables at the splicing points may, according to embodiments of the invention, be carried out in several ways, and there are also various alternatives for the termination point(s) of the multiple ducting.
One method according to an embodiment of the invention would employ a Fixed Pipeline End Manifold (PLEM)700, as shown in Figure 13. A sub-sea steel box structure is fixed to the seabed, and connected to the bundle of multiple ducts 300 with porches 710 around the periphery where outgoing cables 320 can be pulled in and connected to a central distribution module 720. The structure 700 is piled to the seabed for greater stability, and is typically sloped to allow trawl- gear to pass over it more easily. This option can be employed in deep waters,
though the depth may be limited by the diver intervention required for connecting the cables. An alternative may employ a remote system to connect the cables, allowing greater depths. The armoured cables 320 connected to the PLEM 700 will typically be protected in the immediate vicinity by concrete mattresses or "dog kennels" 730, illustrated in Figures 14 and 15.
In alternatives, the PLEM 700 can be a concrete structure, which may be cheaper than the above steel structure. It may also be a hyperbaric environment, which has the advantage of allowing dry cable connection rather than wet cable connection, which is often difficult and time-consuming. The installation of a hyperbaric chamber on the sea bed although expensive may offer advantages in terms of ease of repeat access.
Another method is illustrated in Figure 16. The PLEM 700 would be designed to be lifted from the sea bed by a connection vessel 16. The armoured cables 320 may be doubled back along the length of the duct bundle 302, so that the PLEM 700 supports them during lifting. Here, the PLEM 700, the doubled- back cables and the cables 320 connected are all protected by concrete mattresses 730 or similar. The PLEMs 700 may be lifted using a DSV mounted crane or similar, in an similar procedure as that used for retrieving the end of an abandoned pipeline. The depths to which such a system could be laid may be limited to around 100m, by the lifting apparatus, though specialist vessels may be able to lift the PLEM from greater depths. This system would allow the surface connection of cables, which would be far more practical than undersea connection, though it may involve extra cost in hoisting the PLEM from the sea bed. It would also allow the PLEM to be retrieved at any time, in order to repair or replace cables, or to attach new connections simply and efficiently.
A possible disadvantage with the above methods is that the armoured cables 320 would typically fan out from a single connection point at the PLEM 700, and thus there may be a risk that if one is snagged by an anchor or trawler, the whole set will be dragged with it. Thus, in a prefened embodiment, the recoverable system of Figure 16 is adapted to provide a daisy-chain of
connections, as shown in Figures 17, 18 and 19. The final length of the main pipeline 302 with multiple ducting 300 is fitted with a series of "wye" connections 740 and a final integral pipeline end manifold (PLEM) 700 mounted on the laid-down end of the pipeline. The "wyes" 740 and final PLEM 700 are separated by distances sufficient to allow intervention at each location without the risk of collateral damage to the adjacent cables. After installation of the main pipeline 302 a series of side branch connections 750 (at 45 ° to 7 ° in the daisy chain layout are made to the "wyes" 710 in the main pipeline, one of which is illustrated in Figure 18. These branches consist of smaller diameter pipelines 304 (typically 12-inch diameter for a 30-inch main pipeline). Each branch pipeline
304 allows connection of a single or twin armoured cable 320 to the main trunk bundle 302. This daisy-chain connection system would thus provide branches sufficiently separated to eliminate the risk of a total loss of the system, as if one cable is snagged, the others may be avoided. At each branch connection 750 one or two conduits 304 are routed from the main bundle, to exit from the main pipeline through a side aperture in the pipeline wall. The conduits 304 are typically given a constant (typically 4m) bend radius to minimize resistance/wear during the subsequent operation of installing the fibre-optics into the conduits. The exiting conduit ends are terminated in the multi-bore stab-plate 600 fashion described above on the outside of the main pipeline 302. As shown in Figure 19, these stab-plates 600 thus mate-up with opposite stab-plates in the branch connection pipelines 304. The side connection pipelines run for a straight length and are themselves terminated in PLEMs 700. Installation of the branch connections would typically employ the subsea mating of the stab-plates 600 on the main 302 and branch 304 pipelines. This would be performed using a system of docking and alignment devices mounted on both the main and branch pipelines. Typically, the installation would be achieved in two stages, an initial rough docking to structurally locate the branch pipeline onto the main pipeline followed by a closing operation where fine tolerance locating pins would engage and align both sides of the conduit stab-plates. Within each PLEM,
i.e. at the end of the main pipeline and at the branches, the conduits terminate in structures designed to allow splicing of the fibre-optics between the pipeline and the incoming armoured cables. To perform the splicing operation the PLEMs are lifted from the seabed to the surface as with the previous method, thereby allowing the operation to be performed under atmospheric conditions. Each
PLEM is lifted to the surface where the suspended pipeline assumes a catenary shape down to its touchdown point on the seabed. The length of pipeline lifted would typically be 150% of the water depth at the PLEM.
As an alternative, a substantially rigid section of multiple ducting may be provided with a plurality of relatively less rigid extending branches or risers from which one or more cables can be deployed. The branches are preferably of sufficient length and flexibility to facilitate raising to the surface to attach an extending armoured cable to a cable passed through the multiple ducting and into the branch. The armoured cables may extend away from the main conduit in a similar manner to that depicted in Fig. 17. Alternatively, the cables may extend directly from the ends of the flexible branches, without being doubled back along the branches. Similar distance considerations apply to the spacing of the extended cables in this embodiment and that of Fig. 17. Protection for example with concrete mattresses may be deployed. For example, the following outline gives a possible procedure of the splicing operation for connecting an armoured cable to a 300m long branch pipeline in 100m of water depth:
(1) Attach the armoured cable start-up head to a point on the branch pipeline close to its "wye" connection using a haul-down winch and lay away the cable staying approximately 50m from the branch pipeline.
(2) Lay sufficient armoured cable on the seabed to allow the start-up head to be released by divers.
(3) Relocate the haul-down winch cable to the PLEM and haul the cable start-up head towards the PLEM, in effect doubling back the cable on itself for approximately 150m. Release the haul-down wire from the PLEM.
(4) Lock the start-up head into the PLEM and attach the doubled-back length of cable to the side of the branch pipeline using diver installed piggy-back clamps.
(5) Lift the PLEM to the surface, using a lifting line attached to a hard point on the PLEM structure. During this lifting operation the armoured cable would remain attached to the branch pipeline and be fully supported along its 150m long catenary shape.
(6) Perform the splicing operation between the armoured cable and pipeline fibre- optics and test the connection as necessary.
(7) Lower the PLEM to the seabed and release/recover the lifting line.
(8) Install flexible protection mattresses over the PLEM, branch pipeline and attached cable(s), untrenched regions of the armoured cables, and the "wye" branch connections at the main pipeline.
(9) Continue the cable laying and trenching operation.
Subsequent repair of the cable splice at the PLEM and/or connection of new cables to the branch connection would be performed using similar procedures. A typical lifting vessel employed in these embodiments is illustrated in
Figure 20.
An alternative form of termination point is illustrated in Figure 21. A Single Buoy Mooring (SBM 800), may be anchored in place with flexible risers
810 with distributed buoyancy 850 between the end of the multiple ducting 820 and the surface buoy 800, with one riser for each conduit. Dynamic armoured cable risers 830, designed for fatigue resistance under wave loading, are pulled-in to the SBM and surface-connected. The buoy 800 would be anchored to the sea bed using cables or chains 840, which also serve as protection for the enclosed cables and risers 320. This type of installation may be significantly cheaper than other types.
Another alternative would be to have a fixed surface termination point, as shown in Figure 22. Here, either a temporary or permanent platform 900 could be constructed, or an existing platform could be used. The cables 320 would be connected at the surface, again saving on complication and expense. For a permanent platform, the termination point may include a bundled conduit riser and J-tubes 910 for future pull-in of the armoured cables 320 for surface- connection. J-tubes 910 are commonly used for pull-in of power cables or control umbilicals. These could be retrofitted to an existing oil or gas platform. Retrofit risers are commonly installed offshore, sometimes as pre-fabricated bundles. The latter option would save on the cost of a new facility but capacity for additional risers and deck-space may be an issue, depending on the chosen platform. The conduits and cables could also be installed in empty well space. For each of these fixed surface options, the conduits and cables may be protected by the structure of the platform itself, and exclusion zones could also be set up around the platform.
In all cases it is preferable to provide protection for the armoured cables from the termination point out to where the cable is fully buried, or to a point far enough away to prevent common failure through external aggression of several cables tied-in to the same termination. This is provided typically by the described concrete mattresses, though other forms of protection are of course possible.
Certain advantageous features of termination points mentioned above are listed below:-
Providing a plurality of branch conduits each having at least two cable directing sub-ducts defined therein facilitates spreading out of cables.
Providing a mating face at the connection point and the branch conduit, the faces having complementary alignment components adapted to guide the sub- ducts of the conduit into connection with the sub-ducts of the multiple ducting may facilitate installation.
Splicing or connecting the cables on board a vessel, facilitated by a recoverable or buoyant termination point may simplify installation.
Providing the surface termination point at a substantially rigid platform secured to the underwater bed permits splicing the cables on board the platform.
Passing the long distance (armoured) cable to the splice point in substantially the same orientation as the duct, and splicing the cables, whereby for a distance comparable to the water depth at the termination point the cables are substantially parallel to each other and preferably securing the long distance cable to the ducted cable for at least a portion of the distance during which the cables are substantially parallel to each other may reduce disturbance to cables when access is required.
Providing multiple connection points at the termination point, the connection points being spaced apart along the length of ducting, preferably at least 100m apart, more preferably at least 300m apart, ideally so that the long distance cables are at least 50m (ideally at least 250m apart) apart in a region at least 300m from the ducting can reduce the risk of multiple cable damage.
Protecting termination points with one or more resistant structures greatly increases reliability without inhibiting maintenance (discussed below).
Insertion of cables into ducts
The installation of cables into the conduits laid can be undertaken by several methods.
Figure 23 illustrates one of these methods, according to an embodiment. The cable 320 is propelled along the duct by flowing fluid, typically water, rather than simply being pulled through. This may allows it to negotiate curves and imperfections in the duct without getting jammed. It is of course possible simply to pull a cable through an existing duct. The problem usually encountered here is that the cable may get jammed inside the duct with no means for freeing it other than cutting the duct open. Pulling methods are essentially dependent on the tensile strength of the cable and the friction of the cable jacket; the effective distance for such a method may be increased by incorporating a reinforcement in the cable, such as a steel wire and by providing a low friction, for example PTFE jacket. Friction is often caused by curves in the duct, due to being laid on uneven ground, but can also be caused simply by excessive friction between the cable and the duct walls. Figure 24 illustrates the curvature which can arise in ducts 302 laid on the sea floor. Known flow methods may suffer less from excessive wall friction and allow a quicker and more efficient installation by preventing the cable from jamming.
To effectively pass the cable through the duct using a known flow method, a high pressure is applied at the beginning of the duct, and the cable is carried through by the force of the water passing over it. Figure 26 shows the typical pressures which may be employed using water with known flow methods.
In this embodiment, taking typical maximum internal pressure of industrial water pipes to be 10 bar, the diameter of the duct 302 is preferably at least 0.25m. In other embodiments, the pipes used may be able to withstand greater pressures, allowing a faster jetting of the cable. In further embodiments, the cable is fitted with a head which provides a near seal with the walls of the duct, again allowing greater pressure to build, and pass the cable faster. In an alternative, the cable allows significant volumes of water to pass over it during transit, aiding the flow, and enabling an easier transit.
Flow methods have been successfully used to insert cables into ducts up to about 10 to 20 kilometres in length but longer may be possible with suitable
duct sizing and conditions. It becomes much easier to pass the cable with a flow method as the duct internal diameter increases as (1) the area and hence force available for a given pressure drop increases with the square of the duct diameter (2) the cable can be made larger and hence have a greater tensile strength (3) friction between the cable and duct wall may be reduced (3) leakage past the side of the drogue makes a relatively smaller difference to the working area so larger gaps and lower friction can be employed (4) flow losses in the pipe are reduced (this is more significant for high transit speeds). US-A-4,756,510 discloses a method for installing a cable in a fluid transmission pipeline using a pig; such a method may be adapted to install a cable in the ducts provided by embodiments of the invention. In the limiting case, as the head and duct become large in comparison to the cable diameter and the flow velocity decreases, the flow method becomes effectively a pulling method as the majority of the force is applied by the head and little is applied to the cable jacket. In general, according to embodiments in which flow methods are employed, the duct is continually treated or flushed with water. This maintains clean conditions inside the duct, and allows for easier replacement of cables. If the duct is not straight, the friction may increase. The friction may also increase if impurities are present in the duct. The duct may be cleaned before introduction of a new cable by passing a cleaning head through the conduit, by similar flow methods. This may employ scraping or brushing action on the duct walls, and may be passed by any of the methods described, though particularly by pulling or by flow methods.
There are other possible methods for cable installation. For example, if the duct is large enough, the cable may be unreeled within the duct. Where it is necessary to pass a cable through an extended length of duct and if problems are encountered, sections of multiple ducting separated by intermediate access points, which may advantageously comprise repeater stations may be provided. Thus, for example to span a 100km stretch, if the cable and duct properties are such that reliable insertion of the cable up to about 15km is possible using a
conventional flow method, repeater or splicing stations may be provided at, for example, 12.5 km spacing, giving a total of 8 sections and the cable inserted in stages. Whilst provision of such stages may add to cost, it facilitates repair for example in the event of damage to a section and even in the (rare) event of catastrophic damage to a section it may only be necessary to replace a single section between splicing or repeater stations.
Repeater options
It is possible with existing available technology to transmit signals through fibre up to 50-150km without undue difficulty without using repeaters. Experimental techniques have transmitted signals much further, and such techniques can be used practically, albeit at a greater cost than with off-the shelf equipment. If the termination point is at the surface within a suitable distance from the shore, for example on an offshore platform, it may be straightforward to have a run from the shore without any repeaters in the multiple ducting. It may even be possible to provide co-location facilities on the offshore platform (or at the termination point), provided a suitable power source is available. For the deep sea crossing, which may be a few thousand kilometers, conventional repeater technology may be used, inserted into lengths of armoured deep water cable which carries power for the repeater. Figure 25 shows a first embodiment of an upgradeable repeater. This may be provided independently and used in other applications, including single cable applications. In the embodiment shown, an outer conduit 110 containing multiple (here 6 are shown but more or fewer may be employed) sub-ducts 112a...112f is coupled to one end of a repeater housing 120. Cables 114a...114f (preferably fibre-optic, but similar principles may be employed for co-axial or other electrical cables) are passed through the sub-ducts to connectors (not shown) on the outer wall of the housing 120. Each connector may couple multiple fibres. Not all cables need be present at the same time. Directing ducts (not shown) may be
provided within the housing to direct an incoming cable to the connection point on the wall of the housing. Similarly, continuation cables 118a...118f enter from respective sub-ducts in an opposed duct 130. Each set of cables 114a...ll4f and 118a...ll8f is coupled to a respective repeater 116a...ll6f mounted on the exterior of the housing by optical connectors and water-tight (at least for sub-sea applications; the embodiment is not so limited) fixings and contains repeater circuitry. The repeater circuitry will normally contain electronics which demodulate, shape, and re-form the signals carried optically and receive power via a water-tight connector (not shown) from the housing 120 which will normally receive power from a power cable contained within the duct 110.
Alternatively or in addition, each fibre-optic cable 114a...114f may contain integrated power connections, for example carried in a shielding or reinforcing braid. The repeater may comprise an optical amplifier or optical circuitry which boosts the signal without converting it to electronic signals. In place of connectors, the cables may be directly spliced onto the repeaters; this may be suitable for single deployment but may complicate or prevent replacement of repeaters. An advantageous feature, which may be provided independently, is the facility to upgrade repeaters, for example to increase bandwidth or signal quality or reduce power requirements as improved repeaters become commercially available.
The embodiment of Fig. 25, which will typically be relatively small and may be ananged for the repeaters to be installed or replaced by a diver or a remote operated vehicle (RON) and in the case of splicing rather than using connectors, hyperbaric splicing equipment may be provided (in a sub-sea application). The apparatus may be ananged so that the repeaters can be accessed, added or replaced underwater or may be ananged to be recovered to the surface for the installation of new cables or the replacement or addition of a repeater. Where conduits with push-fit connectors are employed, for example as described with reference to Fig. 11, the repeater housing may push-fit onto such a conduit.
As an alternative, the repeaters may be installed in a sealed chamber. Fig.
27 depicts schematically and not to scale such an anangement in which a sealed chamber 121 large enough for work to be performed within it and having an access airlock 123 is provided and the ducts 110, 130 coupled to the walls of the chamber. The chamber may be similar in construction to the PLEM of Figure 13.
Chain-pipe Embodiment
This embodiment, to be described with reference to Figs. 51-53, may provide the following advantages in deployment of a long distance protected conduit fibre-optic system: - • to allow uninterrupted offshore installation of an unlimited length of a bundle comprising: empty conduits, fibre-optic cables and associated power cables within a protective steel pipe envelope.
• to allow for installation from any suitable vessel of opportunity in any water depth. - to allow for future extension or connections for expansion of the bundle system.
Offshore Termination of chain-pipe
The embodiment provides for offshore termination of the conduit/fibre-optics and transitions or connections to traditional armoured cable by: • simple exiting and tie-in of individual fibre-optic cables which can either be preinstalled during the laying operation or post-installed using future flowing/pigging techniques.
• the ability to be configured for distance-separated, or "daisy-chained" tie-in connections to deep water trans-ocean armoured cables, • fanned-out connections to the trans-ocean armoured cables at a single offshore location, including an fixed offshore surface, or subsea structure.
Features of chain-pipe
All of the features to be described may be provided independently of other features unless otherwise stated. The key feature of the chain-pipe embodiment is to split the protective outer steel pipe envelope into discrete half shell units and install these over the internal conduit/cable bundle during the offshore lay operation. Although half shells are most convenient, it will be appreciated that the halves need not be exactly evenly sized nor symmetrical (and the shells may comprise complementary mating "halves"). More than two partial shells, for example three or even more may be used. However, two is preferable and use of larger numbers of partial shells, whilst reducing the size of the individual components and thereby offering some advantage, is likely to complicate installation significantly. When two shells are used, it is preferable that these are at least similarly sized so that each "half" has an opening at least about 90% of the internal diameter or subtends an angle in the range about 120 degrees to 240 degrees, preferably 150-210 degrees (or equivalent if the shells are not circular
- polygonal (e.g. hexagonal) or inegular shapes are possible). Outside these limits installation will be hampered by the larger "half" having an unduly small opening to accommodate a bundle. The shells are preferably shipped as individual pieces to the offshore lay vessel and subsequently assembled in a continuous lay operation which may be performed relatively rapidly.
The half shell design preferably incorporates pin-jointed hinges 610 alternating by 90° at each joint between lengths of chain-pipe. These hinges inhibit bending moments developing during the laying process. The pin connections 620 effectively introduce continuous articulated "universal joints" along the length of pipe, with sufficient flexibility to allow the assembly to follow
(approximately) the shape of a natural catenary by small angular displacements at each hinge.
, The shells may be assembled using a hydraulically operated handling cradle. Clamping of the half shells together may be performed using a metallic
banding system, which will typically be hydraulically tensioned. Alternatively, the shells may be clamped using bolting. In certain cases, the shells may be welded; however that may introduce complications protecting the contents of the shells and also complicates repair. In the embodiment shown, each half shell unit is identical and is fabricated from the following parts:
• A length of tubular half shell 630. The length of this may be selected as appropriate for the handling equipment and factors such as water depth, buoyancy from the internal conduits, lay tension, may be taken into account but is preferably at least 3m and preferably no more than 25m, typically in the range 5m to 15m. About 6m or 12m are convenient sizes for fabrication, handling and deployment in most conditions. At one end of the shell a hole 640 for a locating pin, to be described, is cut. This hole is ideally located half-way around the semi-circular section of the shell, and set back sufficiently to provide adequate pull-out strength when assembled with the following shells. At the opposite end is:
• An internal split sleeve connector 610. This is rolled to an external diameter which is about 10- 12mm less than that of the internal diameter of the half shells. An alternative configuration is also possible, with the internal diameter of the external sleeve about 10- 12mm larger than the outside diameter of the half shells.
The connector is profiled to have an extension tab, here semi-circular but other appropriate shapes may be used, and matching recess 612. These engage with the opposite half shell sleeve connector. In the extension tab is a hole with a protruding pin 620 welded into it. When assembled with the opposite shell the two pins align to form an articulating axle, or hinge. The connector is bonded, preferably welded to the half shell preferably using continuous fillet welds.
• Internal alignment split sleeves 640. These are spaced along the length of the half shells to provide longitudinal and transverse shearing resistance to the assembled pipe shells and maintain a circular cross-section. The number and location of these will depend on the length, thickness, material and deployment
conditions of the pipe. The embodiment shown has three, one of which is near the "open" joining end and the others of which are spaced approximately evenly between this and the end split sleeve connector. It will be appreciated that any problems with integrity of the assembly can be alleviated by including more of these connectors, but at a cost. Again, the alignment sleeves are profiled to have semi-circular extension tabs 622 and matching recesses 624 (or other appropriate shape). These engage with the opposite half shell alignment sleeves. The alignment sleeves are bonded, preferably welded to the half shell, preferably using discontinuous fillet welds. The assembled shell pairs are held together using a clamping system. This is either in the form of a hydraulically tensioned metallic banding system or by bolting. The bolting may be recessed through the half shells and into the internal tabs of the alignment sleeves.
The duct should be suitable to protect the cables from sub-sea aggression, for example to provide a degree of protection from loose rocks, dragging anchor chains, marine life and the like. However it is not expected that the duct will provide complete protection and is unlikely to be sufficiently robust to withstand a direct impact from a ship's anchor. The duct shells may be ananged to form a substantially watertight seal but normally a degree of water flow will be permitted through the j oins , particularly where the duct is hinged between shells . Normally the duct shells will be formed from steel, preferably having a thickness of at least about 2mm, more preferably at least about 5mm, sometimes at least about 10mm.
Installation Method for chain-pipe
The prefened method for offshore installation of the chain-pipe bundle is as follows:
1. All internal materials (conduits, fibre-optic and power cables) are shipped to the lay vessel in predetermined coiled lengths on carousels and readied for un-spooling and assembling into a bundle. Preinstalled fibre-optic cables can be
shipped separately and fed into designated conduits having continuous longitudinal splits prior to assembly with the remaining empty conduits. Alternatively pre-assembled, protected, fibre-optic cables can be installed into the bundle individually. Power cables can be assembled and strapped together before assembly with the conduits or alternatively run individually, as required.
2. The assembled conduit bundle is then fed over an assembly cradle bed where the half shells are readied.
3. The half shell pairs are alternately split horizontally and vertically. For a horizontally split pair the lower shell is placed on a mobile cradle located adjacent to the conduit bundle and the shell slid sideways and underneath the conduit bundle. The shell is then lifted up so that its pinhole locates onto the lower pin of the preceding shell pair. The upper shell is lowered over the conduit bundle to seat onto the lower shell, engaging its pinhole over the upper pin of the preceding shell pair. During seating of the upper shell alignment aids are made to engage and align the two half shells together to form a circular cross-section.
4. The clamping system is then installed. This can be either a tensioned band system or hand (or machine) installed bolting.
5. The completed shell pair is paid out so that the next section of exposed conduit bundle comes over the cradle bed. The next shell pair will be split vertically. Both side shells are placed onto the mobile cradles. The cradles are then rotated through 90° and then slid sideways towards the conduit bundle. Both shells are manoeuvred so that their pinholes locate onto the horizontally orientated pins of the preceding shell pair.
6. Again the clamping system is then installed.
Alternative assembly methods are equally feasible including assembling four (or more) adjacent shells in one production step. Assembling two (or larger even number) adj acent pairs including both horizontally and vertically split shells . has the advantage that the shells are aligned the same way each time - that is one
assembly station will always receive horizontally split shells and the other will always receive vertically split shells.
The chain pipe half shells (or other portions) may be modified to provide branches at the termination point. For example, a half shell may have an opening through which one or more sub conduits may pass and onto which a riser duct may be attached. The riser duct may be relatively more flexible than the chain pipe. The opening may be angled to form a branch for example in an analogous manner to Fig. 19. The invention extends to a duct half shell (or component) including an opening through which a conduit can pass to a branch duct or riser. Alternatively, branches may be inserted at joins between pairs of half shells, although this may compromise integrity of the join. A branch coupling may be provided at such joins.
Burial of cables
As explained previously, cables buried on the ocean floor and in shallower areas are susceptible to damage, which can disrupt communications networks and introduce large repair expenses. However, the exact problems associated with the damage caused have remained largely unknown. Investigations pursuant to the invention have found that there are a number of different types of hazard which predominantly occur at different water depths. In contrast to the usual strategy of burying at an economically viable depth along the route, typically about 2 feet, it is considered preferable to employ a variable burial depth.
Figure 28 illustrates the typical depth of the sea bed for a transatlantic submarine cable. Figures 29 and 30 illustrate typical depth profiles in the region of the US and UK continental shelves respectively. Figure 31 illustrates the typical depths of penetration of various shipping activities, along with the usual burial depths 950, and the burial depth according to an embodiment of the invention 960. Previous installations have tended to choose a constant burial . depth of approximately two feet below the ocean floor. However, as can be seen
from Figures 28 to 31, this is usually inappropriate. In shallow waters such as those on the continental shelves, it is insufficient to avoid anchor damage, which is the most significant factor in submarine cable faults. Figure 32 illustrates the stockless type anchor employed by most modern vessels. This type of anchor has greater sea-bed penetration characteristics than other types, as can be seen from
Figure 33, a graph illustrating anchor penetration relative to vessel size. Cables which are buried at the usual depths are often unearthed eventually by tidal and storm waters, and when exposed, the cables can be cut despite the traditional armour plating employed. Damage is usually caused by shipping, for example, by dredging, trawler fishing, and, most commonly, ships' anchors. The subsequent losses of transmission can cause major disruption in communications networks which rely on the cables, and repairs are usually highly expensive and time-consuming. For these reasons, sub-sea cables are usually armour plated, and are also buried in shallow waters. The present invention prevents damage to the cable from the various hazards at the various different depths and sea areas, thus allowing a more reliable cable network.
The traditional burial depth chosen, as shown in Figure 31, is also excessive in the much deeper waters between the continental shelves, where fishing activity penetrates to a much more shallow extent. The anangement in
Figure 31 according to an embodiment of the invention allows for the different penetration depths of different hazards, burying the conduit or cable on a variable depth trajectory, as shown. This is sufficient to avoid damage in shallow waters, where cables are particularly susceptible to anchor damage, as described. This trajectory also only requires relatively shallow burial in deeper waters, saving time and expense in the trenching process. Other hazards, such as dredging, which take place on the continental shelf but which penetrate the ocean floor to a lesser extent, are also avoided by this arrangement. In one embodiment, the armour on the cables or conduits buried on the continental shelf is increased, so
as to prevent damage should they be unearthed by, for example, freak storm waters.
As may be seen from Figure 31, it is prefened that conduits or cables are buried to a depth of about 8 feet (typically at least about 2m, preferably about 2.5m, usually between 2-3m), in an anchor zone (typically in water up to a depth of about 500ft or in water up to a depth of at least about 100m, typically up to about 150m water depth) and to a shallower depth in water outside the anchor zone. The depth is preferably about 3 feet (at least about 3/4 m, typically about lm, usually between 3/4 and 1.5m or 2m) in a dredging zone (but outside the anchor zone), usually up to a water depth of about 1000 feet (typically in the region from the anchor zone to about 400m or 500m). Outside the anchor zone, and preferably outside the dredging zone, the burial depth may be much less, for example about 1 to 2 feet or about 1.5 feet in deep water. More particularly, the burial depth may be, for example, less than 2m where the water depth is about 300m or more, typically less than lm where the water depth is about 400m or more, often about 0.5m where the depth is 400m or 500m or more.
The burial for the embodiments employing the variable depth trajectory is implemented in the various ways outlined previously. In other embodiments, where trenching is used, the trench digging is supplemented by a second vessel which draws a tool to fill in the trench. This is implemented in one embodiment by a second plough, which simply churns the soil which was removed back into the trench.
As mentioned earlier, there are a number of alternatives available according to the invention when locating the splice box and other components of the system of Figure 2 on the continental shelf. A deciding factor for how far along the shelf to lay the conduits is the depth of water at the burial point. In particular, it is unlikely that cables laid on the continental shelf at depths greater than around 200 feet will be cut, according to cunent cable fault records (see Figures 34, 35, and 36). This may also dictate the plotting of the variable burial depth trajectory shown in one anangement in Figure 31.
Repair techniques
There are various potential sources of damage or external aggression for a pipeline including conosion or material defect, dropped objects, fishing activities, shipping and scour.
Conosion or material defect
Damage due to conosion or material defect could occur in operation causing loss of integrity to the pipeline, resulting in a leak or mechanical weakness. Normally this type of damage would be prevented by quality control of materials, installation and operational maintenance. Nevertheless shortcomings in these areas could lead to conosion due to sea water seepage, loss of integrity, and the compromising of installation activities, such as passing pigs through the pipeline. This type of damage may be repaired by fitting clamps to seal leaks, and by providing structural reinforcement where required.
Dropped Objects
Dropped objects could cause impact damage such as dents or crushing of a pipeline. Dropped objects are normally associated with locations near to existing offshore platforms. Although there is potential for objects to be dropped in open water, from any passing vessel, exposure to dropped objects is principally limited to vessels in transit in the vicinity of the pipeline. As heavy loads are not handled in transit it is highly unlikely for this type of incident to occur. Storm conditions may lead to vessel sinking or loss of cargo that could drop onto a pipeline. While this type of event has occuned in the past, the probability of such an occunence is incredibly small, and thus could not be predicted with any degree of accuracy.
Fishing Activities
The main hazards from fishing activities are from direct impact by trawling gear or snagging of nets and associated equipment. Fishing activity takes place principally in the near-shore regions, out of the shipping lanes. Trenching of the pipeline(s) may provide a high degree of protection from fishing activities. For pipelines trenched in sand, natural backfill is anticipated, and for pipelines trenched in clay the trench would generally be steep sided. Trenching may thus provide an efficient form of protection for the pipeline(s).
Shipping Activities
The main concern with shipping is the possibility of anchors being dropped or dragged across the pipeline. For example, The Channel has two busy shipping lanes passing across possible pipeline(s) routes. Unplanned or accidental incidents with anchors cannot be ruled out. It is impractical to protect a pipeline from direct impact of a dropped ships' anchor, in view of the high degree of seabed penetration that can occur and the relative infrequency of such an event.
Trenching has been shown to provide reasonable protection from dragging anchors and chains, though there are shortcomings, which are examined in more detail is later sections. However, trenching to at least 0.5m below seabed should provide reasonable protection from dragging anchors and chains.
Scour
Intermittent exposure and re-burial of the subsea pipeline(s) is possible in sections where there is loosely compacted sand back-fill. However in certain areas fast flowing water entail that deep, loose soil deposits are unlikely. A programme for monitoring the pipeline through regular inspections during the operational life may allow identification and remedial action in exposed areas,
should they occur, prior to any adverse consequences, such as fishing equipment impact. For sections where the soils are predominantly clay, scour is not expected to occur.
Such hazards may cause various types of damage which would typically be repaired in different ways. Medium sized dents in pipes may compromise pigging and therefore the installation of further cables, for example, unless the pig can be modified. With more major dents, cables may be crushed. Dents may be repaired by pulling them out, or in severe cases or even ruptures of the pipe, by cutting out the dent or rupture, repairing the cables if need be, and fitting a repair clamp. Snagging of the pipe can cause buckling, which impairs pigging and damages cables. For severe cases, the pipe would be cut back to either side of the buckle, the cables repaired, and a protective casing for the exposed cables fitted.
Summary
The following table summarises possible types of damage and repair. The problems mentioned below are particularly concerned with deployment of a cable using a pig, for example based on the technique disclosed in US-A-4,756,510 but apply similarly in the case of other cable deployment methods as obstructions will affect most methods similarly.
With the embodiments of the invention described and the possibilities for damage it is preferable that a repair system is implemented. Figure 37 illustrates a Repair Strategy. Repair procedures and standby repair equipment are also preferred as part of the contingency package. The repair system implemented in accordance with the invention may have an emergency response plan, maintain stocks of spare pipe, have to hand ancillary equipment such as clamps, and have pre-prepared procedures for commonly applied techniques such as concrete weight coating removal, pipe cutting, and hyperbaric welding. It is noted that repair may be greatly simplified in the case of a modular outer pipe such as the "chain pipe" mentioned above; in such a case repair may often involve replacing the damaged pipe segment with a new segment and repair clamps may not be required.
This combined with a complete database of operational and physical data for the pipeline system allows the emergency response team to be fully informed and able to make effective decisions. Once the location of the damage is confirmed the emergency response team would typically initiate the following course of action:
1. Limit or contain the pipeline leak, or potential leak, by reducing system pressure and containing any spillage.
2. Survey and assess damage and make engineering criticality assessment.
3. Select most appropriate repair method from those described
. Mobilise repair team with repair equipment to carry out the repair
5. Repair, inspect and record the operation
These procedures, and variations, are illustrated in Figure 38. This would be the typical scenario for an emergency repair but in some cases a repair may be planned well in advance. For example, if inspection reveals unexpected levels of corrosion or anode wastage that may compromise the design life of the pipeline but is not critical in the short term, a maintenance repair may be planned.
Certain key long-delivery equipment, described in the preceding sections, are kept on standby for possible repairs. This equipment could be pooled by a number of pipeline operators to share the cost. Such emergency repair clubs may have standing emergency contracts with vessel operators to provide emergency repair vessels and tools.
An outline of all procedures or MOPS is shown in Figure 39. Certain of these steps will now be described in greater detail.
It is to be noted that certain of these methods may be modified and in many cases simplified if the outer duct is constructed from partial (half) shells, for example as in the chain-pipe embodiment depicted in Figs. 51-53. In such a case, in many cases, it may be possible simply to remove the damaged half shell, or adjacent shells and replace them.
Span Correction [MOP 12 & 13]
There are various methods, according to embodiments, which may be employed for correcting spans:
1. Installation of grout bags, built up by divers under the pipe to form a secure support for the pipe. The pipe would then be protected by flexible concrete mattresses,
2. Installation of adjustable steel supports (possibly only effective if they cannot be undermined by scour);
3. Rock dumping, either over the entire span or in a heap close to the centre. The rock would be dumped to each side of the pipe to form a support and then over the top to provide protection.
4. Trenching, or jetting, to lower the ends of the span and partially shelter it within a trench. This may require large equipment to be mobilised.
Where there is a risk of snagging due to fishing activity, methods such as rock- dumping or mattresses covering a supported span, are prefened.
Pull-out a Dent [MOP 14]
If the serviceability of the cable duct pipeline is compromised by a dent, it may be possible to pull-out such a dent mechanically, particularly if it is in a relatively thin wall pipe. This procedure would preferably employ a specialist subsea tool to drill into the pipe and then insert a pulling tool to pull out the dent, without damaging the cables within. After pulling-out the dent a repair a clamp would be fitted to seal the drilled hole. If such a method could not be implemented then the cut-out method would typically be used.
A preferable complete sequence of operations is as follows: Remove Concrete and coating [MOP 1]: a) Excavate around pipe b) Attach concrete disc cutter to cut circumferential slots c) Attach concrete disc cutter to cut longitudinal slots d) Use hydraulic tool to lever off concrete e) Use wire brushing tool to remove coating locally
Pull out dent [MOP 2]: a) Deploy tooling onto pipe b) Drill hole just through pipe wall c) Insert hydraulic-puller through hole and engage internal grips d) Pull out dent to provide sufficient internal clearance for cables e) Disconnect and recover tool
Inhibit inside pipe [MOP 3]: a) Depending on size of hole either insert bag, or inject gel, containing slow- dissolving biocide into the pipeline, prior to sealing-up the hole.
Fit Repair Clamp [MOP 4] and protect [MOP 5]:
Repair Clamps [MOP 4]
For small apertures less than 1.5 diameters a standard mechanical repair clamp would preferably be used. Where, as will be typical, the cable duct pipeline is a low- pressure system, simple low-pressure clamps may be used for this type of repair.
Various types of clamps are available, from, for example, PLIDCO, for repair of minor leaks in pipelines using gaskets to retain the fluid. These clamps re-establish the pressure holding capability of the pipeline. The simplest type uses a fully encircling bracelet to secure a cone-shaped seal over a small hole. Typically, once a bracelet is . secure the sealing cone is tightened into the defect, providing an effective seal.
Larger mechanical clamps may comprise a flanged 430 and bolted pair of half shells 420, with sealing gaskets 440. The seal anangement will typically vary from simple clamps with a single seal, to high integrity clamps with twin seals, complete with packing bolts to energise the seals, and an annulus test port to allow the clamp seal integrity to be checked after installation. Figures 42 and 43 show suitable clamps.
Preferably, to install such a clamp, the soil around the pipe would be excavated to provide clearance for fitting the clamp, which would be bolted up around the pipe to make a seal. If the pipeline is experiencing high bending, or a large section of pipe wall has been cut away, it may be necessary to use a structural clamp that has the capability to transmit forces adequately, for example, the structural clamps cunently produced by
Hydrotech and Technomarine.
Preferable implementation of Install Repair Clamp [MOP 4]: a) Soil should already have been excavated from beneath the pipe to allow clamp to be fitted around the pipe b) Deploy clamp and centralise over pipe aperture c) Lower over pipe and close around pipe (hydraulic actuation or flange-pullers) d) Insert stud-bolts, nuts and fit bolt-tensioners e) Tension studs and tighten nuts f) Tighten end-studs by tension/torque to actuate seals g) Test seals using hot-stab
Cut-out Panel Cable Repair
This requires appropriate selection of tools to ensure that the pipe can be cut without damaging the cables within. Existing cold-cutting machines should be capable, preferably using shallow setting for the cut to minimise penetration into the pipeline. An additional low-pressure water jet may be employed to push cables clear of the cutting blade. The aim is to cut out a half shell aperture 422 to gain access to the cables within, as shown in Fig. 43.
Preferably, the aperture in the pipe provides access for cable inspection and repair. The aperture cut-out is preferably covered and sealed by a repair clamp. This may avoid the need for welding which saves time and reduces the risk of cable damage during reassembly.
For a typical cut-out panel repair:
1. Cut-out pipe dent: a) Deploy hydraulic cutting tool guides and clamp around pipe b) Deploy hydraulic cutting tool (Wachs type) and fit to guides c) Cut shallow circumferential slot through pipe wall, to about 2 way down pipe d) Apply restraining clamps to >half-shell= pipe-panel e) Cut shallow axial slot in pipe between circumferential slots f) Remove >half-shell= pipe-panel leaving aperture in the top half of the pipe.
2. Cut back pipe and repair cables
3. Install Repair Clamp
Pipe Aperture Cable Repair [MOP 6]
This procedure will be simplified by the use of pre fabricated customised tooling, to simplify and speed up the repair of fibre optic cables and it is preferred that tooling is prepared in advance of a repair. Such tooling should be straightforward to construct for a particular application based on the explanation presented below as to the
function of the tooling. A consideration is also to minimise the size (diameter) of the repaired section.
The procedure takes place after an aperture has been cut in the pipe, through which the cable-ends can be accessed for repair. The method should will be applicable to three potential scenarios:
- Surface repair by trained technicians. Technicians would be trained in cable repair tooling and equipment
- Subsea hyperbaric repair by trained divers. Hyperbaric repair requires a dry pressurised chamber around the pipe and saturation-divers. Air-divers could only be used in shallow water (under 50m). Divers would be trained in cable repair tooling and equipment
- Deep water repair by RON using specially developed cable repair tooling
hi all cases it is assumed that the repair is carried out in the dry. For a subsea repair this will require a hyperbaric habitat that can be located over the pipe aperture to cany out the repair. These habitats are large and expensive to deploy and operate.
Purpose built tooling could employ a small dry chamber to carry out a repair, operated by a diver or semi-skilled technician. A compact cable-splicing tool that could automatically align and join individual fibres in a cable would be a significant advantage; such a tool can be based on existing fibre joining tools. Such a tool would greatly facilitate the deployment of a deepwater remotely operated tool. It is desirable to employ a cable joining method that results in a low profile junction, with a diameter not much larger than that of the parent cable. It is noted that a full hyperbaric chamber may be used in the procedures, if suitable compact cable-splicing tools are not readily available.
Major Repair [MOP 9 or 10]
For major petrochemical pipelines, where damage is too severe for an external clamp, there are a number of existing methods for a cut-out type repair, however these may not be appropriate to a cable-duct pipe repair, where the damaged end of the pipe may still cany intact operating cables:
1) Surface repair by cutting out the damaged part of pipe 530 sub-sea, recovering ends to the surface, attaching flanges 430 (connectors) and assembling sub-sea using a flanged-end pipe-spool 520. Figure 44 illustrates traditional pipeline repair.
2) Surface repair by cutting the pipe sub-sea, recovering ends to the surface, welding the two ends together before laying over to one side. This will require an additional length of pipe welded in line for the ends to meet at the surface. Buoyancy aids 540 and Davit lines 550 keep the pipe from sinking, and the pipeline is clamped 560 to the barge prior to cutting. Figure 45 shows surface mid-line repair.
3) Sub-sea repair using mechanical connectors attached to the pipe ends 570. Pipe-end connectors 580 are considerably more expensive but can save considerably on vessel time. Figure 46 shows mechanical pipe end connectors 580.
4) Repair by sub-sea hyperbaric welding. This takes longer and requires considerably more equipment, including diving spread, welding habitat and pipe handling frames. This method is only used if mechanical connectors are not technically acceptable.
All these techniques involve cutting the pipe, which is a major challenge for pipe containing multiple cables, as the subsequent individual cable repairs will take a considerable time to perform. If at all possible the aim should be to repair the pipe without cutting it or the cables, unless the damage is such that all the cables are severed.
Two potential options are proposed: sub-sea repair and surface repair. For both types of repair the concrete coating is removed locally preferably using a commercially available concrete removal tool. The pipe is cut-back away from the damaged area while the cables are cut with extra length. The cable-ends are then pushed back and locked-off inside the end of the pipe. This lock-off anangement requires tool development. A replacement pipe-spool will be prepared to fit between the severed ends. This spool will include cable jumpers with sufficient slack for a repair at each end. The spool will also include apertures close to each end. These apertures are used for access, to join the jumpers within the spool to the severed cables, using the cable repair method (above). The aperture is then closed by a half-shell clamp. For the subsea repair a special 'pipe-end connector 580' and 'half-shell clamped aperture 420' would preferably be combined into one repair tool that is kept on standby to effect such a repair.
Figure 47 shows such a combined tool. This important construction which facilitates repair may be provided independently in accordance with a further aspect of the invention which provides a spool for use in repairing or replacing a length of cable- canying duct, the spool comprising a length of duct having at each end thereof means for mating with a cable-carrying duct to be repaired, the duct further having at least one opening or removable and resealable access panel providing access to the interior of the duct. In this way, the spool can be inserted in a duct in place of a damaged length of duct and cables can be spliced using the opening or removable access panel to gain access to the interior after the duct of the spool has been joined to the duct. The dimensions of the duct of the spool will generally conespond to the dimensions of the duct to be repaired, typically at least 30cm diameter. The means for mating may advantageously comprise a pipe end connector, particularly a sleeve ananged to slide over the duct to be joined. The opening may be ananged to receive a half shell clamp. The duct section will typically be at least 2 metres long, typically at least 10 metres long.
Method of repair may also be provided independently as independent aspects. For example, this aspect may provide a method of repairing a sub-sea duct carrying a plurality of cables comprising removing a damaged section of duct, inserting a repair spool comprising a length of duct (preferably having similar dimensions to the duct to be repaired) in place of the removed section, j oining the repair spool to the sub-sea duct, preferably by means of connectors pre-installed on the repair spool; accessing cables within the repair spool through an aperture in the repair spool to splice (or connect) the cables; and sealing the aperture. Preferably the cables are spliced using a hyperbaric splicing method, for example by enclosing the repair site in a hyperbaric chamber and/or by providing a hyperbaric splicing tool to create a hyperbaric region around the cables and splice the cables. This method may be modified to incorporate alternative features of the other repair methods disclosed herein and any such modified method may be provided independently. The invention further provides a sub-sea cable splicing tool comprising means for creating a hyperbaric or water-free region around at least one cable to be spliced and means for splicing the or each cable within said region. The cables may be formed to facilitate repair or splicing, for example as ribbon cables.
For a subsea repair final welding of the spool will be earned out on the surface achieve the conect dimensions for the gap between the pipe ends. The spool will also
be sufficiently flexible to allow the ends to be stabbed onto the pipe ends. This would be require bends within the spool to make a U configuration. Outline procedure for a subsea repair is given in section 4.3
For a surface repair the pipe is recovered to the surface using a pipe recovery tool (Figure 48). The spool is attached to this end of the pipe to extend it. Then, when the other pipe end is recovered to the surface there is sufficient length overall for the ends of the pipe to be suspended in a gentle catenary while they are joined together. This is a straight in-line connection as shown in Figure 45. Outline procedure for a subsea repair is given below
Major Subsea Repair to Pipe With Individual Conduits
For a duct-pipe which contains a number of HDPE conduits, that might contain a cable, the repair methodology is quite different from the case of a duct that contains individual cables. Principally the integrity of the outer pipe is not as critical. The outer duct pipe is there for protection, not as a piggable, pressure-containing pipe. In this case it is important to repair the conduits, maintaining the internal bore diameter constant as far as possible. While external protection does not have to be pressure containing, it must be reinstated.
Once again it will be necessary to cut the outer duct pipe back to an undamaged section. The subsequent individual conduit repairs will provide a path for new conduits to be run. If a cable is present in the conduit, then such a repair might take some time to perform. If at all possible the aim should be to repair the conduit without cutting the cable. If the cable is damaged, an in-situ repair may be necessary; unless the broken cable can be removed and reinstalled from scratch. The following procedure is proposed to cany out a subsea repair of the conduits. First the pipe is cut-back away from the damaged area while the conduits are cut with extra length. If cables are present, the ends are also cut with additional extra length and tied-back, temporarily.
Replacement lengths of conduit are prepared to fill the gap between the cut ends. These conduit-spools will include cable jumpers with sufficient slack for a cable repair at each end. If there is a cable, it is repaired using the cable repair method, described earlier. The conduit-spool is then joined to the conduit at each end using an
HPDE repair sleeve Figure 49 schematically illustrates HDPE conduit 704 repair. These half-shell sleeves 702 are closed around half-shell packs 710 which are closed around each conduit 704 joint and held in place using high-tension straps 708. The outer shells include seals 712 to keep the conduits pressure tight. If necessary the ends to be joined can be chamfered 706 to provide a smoother bore for future cable installation.
The outer duct-pipe can be repaired using an oversize sleeve to provide mechanical protection only. Figure 50 illustrates outer duct repair. This oversize sleeve will allow space for the conduit repair sleeves 802 to fit within the protection offered by this outer duct sleeve 804. The outline procedure for this repair is given below. This section goes through selected repair procedures using individual MOPS.
Where MOPS are repeated a second time they are in italics.
SEQUENCE OF OPERATIONS FOR CUT-OUT PANEL CABLE REPAIR (LOCAL CABLE DAMAGE)
(1) Survey pipe damage and select extent of damage to be cut-out
(2) Remove Concrete and coating [MOP 1] a) Excavate around pipe b) Attach concrete disc cutter to cut circumferential slots c) Attach concrete disc cutter to cut longitudinal slots d) Use hydraulic tool to lever off concrete e) Use wire brushing tool to remove coating locally Use high pressure jet to clean off surface coating
(3) Cut-out damaged pipe section [MOP 2] a) Deploy hydraulic cutting tool guides and clamp around pipe b) Deploy hydraulic cutting tool (Wachs type) and fit to guides c) Cut shallow circumferential slot through pipe wall, to about Vz way down pipe a) Apply restraining clamps to 'half-shell' pipe-panel b) Cut shallow axial slot in pipe between circumferential slots c) Remove 'half-shell' pipe-panel leaving aperture in the top half of the pipe. (Figure 3)
(4) Subsea cable repair [MOP 6] a) Identify damaged cables for repair. b) Position test and splice tool equipment on the cable repair working platform c) Deploy working platform into the pipe-aperture. d) Pull the cable-ends into the aperture. e) Install hyperbaric chamber f) Deploy diver-technicians g) Cable-ends are locked-off or held in temporary restraints, h) Strip back cable to sound fibre and prepare
i) Conduct OTDR and any other tests prior to splice j) Perform splicing operation k) Conduct OTDR and any other tests 1) Seal joints with low profile shrink sleeve/other m) Conduct final integrity test n) Lower cable back into pipe o) Repeat procedure on each severed cable p) Remove working platform q) Remove habitat (5) Inhibit inside pipe [MOP 3]
Depending on size of hole either insert bag, or inject gel, containing slow-dissolving biocide into the pipeline, prior to sealing-up the hole.
(6) Fit Repair Clamp [MOP 4] Soil should already have been excavated from beneath the pipe to allow clamp to befitted around the pipe Deploy clamp and centralise over pipe aperture Lower over pipe and close around pipe (using hydraulic actuators, or flange-pullers) Insert stud-bolts, nuts and fit bolt-tensioners
Tension studs and tighten nuts Tighten end-studs by tension/torque to actuate seals Test seals using hot-stab connection
(7) Protect [MOP 5] Deploy concrete protection mattresses over repair area and pipe to each side.
Butt each mattress against the last to leave no area exposed to impact or snagging. SEQUENCE OF OPERATIONS FOR MAJOR SUBSEA REPAIR (CUT PIPE AND REPAIR CABLES)
(8) Survey damage and select best location to cut-away pipe to each side of damage. Cut ends must he suitable for pipe end repair.
(9) Remove Concrete and coating [MOP 1] a) Excavate around pipe
. b) Attach concrete disc cutter to cut circumferential slots c) Attach concrete disc cutter to cut longitudinal slots 5 d) Use hydraulic tool to lever off concrete
Use wire brushing tool to remove coating locally Use high pressure jet to clean off surface coating
(10) Cut back pipe [MOP 7] a) Deploy and attach guides for hydraulic cutting tool 10 around pipe b) Deploy hydraulic cutting tool and cut though pipe to gain access to cables within. c) Cut around full circumference of pipe while protecting cables.
15 d) Cut away damaged cables leaving sufficient extra length for subsequent repair. e) Undamaged cables should remain un-cut, if at all possible. f) If cable ends are not long enough then pipe should be 20 cut back further. g) Cable-ends are locked-off or clamped in a temporary restraint that is pushed back inside the end of the pipe and fastened in position.
(11) Insert new pipe-spool [MOP 9]
25 a) Replacement pipe-spool (a short length of replacement pipe with connection fittings at each end and aperture for cable repair) is prepared at surface to fit between the severed ends, b) Cable ' j umper s ' slightly longer than the spool are placed 30 within the pipe-spool with sufficient slack at each end, c) Pipe-spool will also include apertures for repair access, closed by a half-shell clamp, close to each end of the
spool. Apertures will be closed by temporary straps, with cables prepared for joining inside. d) 'Pipe-end connector' at each end of the pipe-spool is prepared for activation with hydraulic tools or diver
5 tools e) Deploy the prepared pipe-spool and line up with the existing pipeline at each end. f) Pull ends of pipe-spool onto pipe ends g) Activate the pipe-end connectors.
10 h) Open up the half-shell clamps to expose apertures at each end i) Pull cable ends into apertures at each end of pipe-spool.
(12) Subsea cable repair at each end [MOP 6]: a) Identify damaged cables for repair.
15 b) Position test and splice tool equipment on the cable repair working platform c) Deploy working platform into the pipe-aperture. d) Pull the cable-ends into the aperture. e) Install hyperbaric chamber 20 /) Deploy diver-technicians g) Cable-ends are locked-off or held in temporary restraints. h) Strip back cable to sound fibre and prepare i) Conduct OTDR and any other tests prior to splice
25 j) Perform splicing operation k) Conduct OTDR and any other tests
I) Seal joints with low profile shrink sleeve/other m) Conduct final integrity test n) Lower cable back into pipe
30 o) Repeat procedure on each severed cable p) Remove working platform q) Remove habitat
(13) Seal Apertures [MOP 4]
a) Close the aperture half-shell clamps and bolt up to seal b) Test seals
(14) Protect [MOP 5]
Deploy concrete protection mattresses over repair area and pipe to each side.
Butt each mattress against the last to leave no area exposed to impact or snagging.
(15) Inhibit inside pipe [MOP 11]
Flush out uninhibited water by pumping in inhibited water from end of the pipeline or, depending on size of repair insert bag, or inject gel, containing slow-dissolving biocide, prior to sealing- up the hole. SEQUENCE OF OPERATIONS - SURFACE REPAIR [MOP 10]
(1) Survey damage and select best location to cut-away pipe to each side of damage.
(2) Remove Concrete and coating [MOP 1] a) Excavate around pipe b) Attach concrete disc cutter to cut circumferential slots c) Attach concrete disc cutter to cut longitudinal slots d) Use hydraulic tool to lever off concrete e) Use wire brushing tool to remove coating locally Use high pressure jet to clean off surface coating
(3) Cut back pipe [MOP 7] a) Deploy and attach guides for hydraulic cutting tool around pipe b) Deploy hydraulic cutting tool and cut though pipe to gain access to cables within. c) Cut around full circumference of pipe while protecting cables. d) Cut away damaged cables leaving sufficient extra length for subsequent repair, e) Undamaged cables should remain un-cut, if at all possible.
f) If cable ends are not long enough then pipe should be cut back further. g) Cable-ends are locked-off or clamped in a temporary restraint that is pushed back inside the end of the pipe
5 and fastened in position.
(4) Recover pipe ends and join [MOP 10] a) Deploy hydraulic recovery tool and locate inside end of pipe. b) Recover one pipe end to the surface using buoyancy and 10 davits on the vessel to support the pipe in a suitable configuration. c) Lock-off on side of vessel d) Align pipeline end with the prepared pipe-spool and line up
15 e) Connect end of pipe-spool to pipeline using welding or pipe-end connectors. f) Open up the half-shell clamps to expose apertures at each end g) Pull cable ends into apertures at the end of the pipe- 20 spool.
(5) Surface cable repair at each end [MOP 6] : a) Identify damaged cables for repair. b) Position test and splice tool equipment on the cable repair working platform in the pipe-aperture.
25 c) Pull the cable-ends into the aperture. d) Cable-ends are locked-off or held in temporary restraints. e) Strip back cable to sound fibre and prepare f) Conduct OTDR and any other tests prior to splice 30 g) Perform splicing operation h) Conduct OTDR and any other tests
I) Seal joints with low profile shrink sleeve/other j) Conduct final integrity test
k) Lower cable back into pipe
1) Repeat procedure on each severed cable
(6) Seal Apertures [MOP 4] a) Close the aperture half-shell clamps and bolt-up to seal. b) Test seals
(7) Lower and recover other pipe end and join [MOP 10] a) Lay down the pipeline end with additional (extension) pipe-spool now attached. b) Reconfigure the buoyancy and davit lift attachments c) Recover the other severed end of the pipe and the end of the pipe-spool using buoyancy and davits on the vessel to support the pipe in a suitable configuration. d) Align with the ends of pipeline and pipe-spool. e) Connect ends using welding or pipe-end connectors. f) Open the aperture clamp at the end of the pipe-spool g) Pull cable ends into apertures.
(8) Join cables to the cable jumpers, using the cable repair method [MOP 6] (above)
(9) Seal Apertures [MOP 4] (above) (10) Lay down the completed pipe in a smooth wave off the route centre-line. SEQUENCE OF OPERATIONS FOR MAJOR SUBSEA REPAIR TO PIPE WITH --NDIVIDUAL HDPE CONDUITS FOR EACH CABLE
(1) Survey damage and select best location to cut-away pipe to each side of damage. Cut ends must be suitable for pipe end repair.
(2) Remove Concrete and coating [MOP 1] a) Excavate around pipe b) Attach concrete disc cutter to cut circumferential slots c) Attach concrete disc cutter to cut longitudinal slots d) Use hydraulic tool to lever off concrete e) Use wire brushing tool to remove coating locally Use high pressure jet to clean off surface coating
(3) Cut back pipe [MOP 7] a) Deploy and attach guides for hydraulic cutting tool around pipe b) Deploy hydraulic cutting tool and cut though pipe to 5 gain access to cables within. c) Cut around full circumference of pipe while protecting conduits and cables within. d) Cut back damaged conduits and damaged cables within, leaving sufficient extra length for subsequent repair.
10 e) Undamaged cables should remain un-cut, if at all possible, f) If cable ends are not long enough then outer pipe and conduits should be cut back further.
(4) Insert new conduit sections
15 a) Replacement conduit-spools are prepared, comprising a short length of conduit pipe, cut to fit. b) If appropriate cable 'jumpers' are threaded into conduit- spools with sufficient slack at each end to join to existing cables,
20 c) For each end of each conduit-spool an HDPE half-sleeve repair clamp is prepared to join to the existing conduit d) Deploy the prepared conduit-spools and repair clamps. e) For each conduit (Figure 11):
I) Fit the lower half of the repair half-shell and strap 25 in place ii) Repair the cable, if present (as below) iii) Fit the upper half-shell iv) Tighten straps around repair to seal the conduit
(5) Subsea cable repair at each end [MOP 6] : 30 a) Identify damaged cables for repair. b) Position test and splice tool equipment on the cable repair working platform c) Deploy working platform onto the pipe.
d) Pull the cable-ends into the aperture. e) Install hyperbaric chamber f) Deploy diver-technicians g) Cable-ends are locked-off or held in temporary 5 restraints. h) Strip back cable to sound fibre and prepare
I) Conduct OTDR and any other tests prior to splice j) Perform splicing operation k) Conduct OTDR and any other tests
10 1) Seal joints with low profile shrink sleeve/other m) Conduct final integrity test n) Lower cable back into pipe o) Repeat procedure on each severed cable p) Remove working platform
15 q) Remove habitat
(6) Fit outer protection sleeve [MOP 21] a) After all the conduits and cables are repaired the conduits are strapped together b) A large diameter outer protection sleeve is fitted to 20 protect the repair area and contain the conduit repairs
(Figure 12) c) Protection sleeve flanges are bolted together.
(7) Inhibit inside pipe [MOP 11]
Protect against uninhibited water by inserting bags, or 25 injecting gel, containing slow-dissolving biocide, prior to sealing-up the hole.
(8) Protect [MOP 5]
Deploy concrete protection mattresses over repair area and pipe to each side. 30 Butt each mattress against the last to leave no area exposed to impact or snagging.
The embodiments described above are most advantageous for providing long distance deep-sea crossings. However, it will be appreciated that the techniques described may be applied to other applications. An alternative embodiment provides a festoon architecture on a coast or in a river. In such an embodiment, an alternative aspect of the invention provides a method of providing a plurality of spaced apart cable connection points on a shore adjacent a body of water, the method comprising providing a plurality of sections of multiple ducting extending from each cable connection point on the shore into the body of water, passing a plurality of cables through each section of multiple ducting and connecting the cable connection points by means of the cables passed through each section of multiple ducting. Each section of multiple ducting preferably includes a termination point. The body of water may be a river or may be a sea and the shore may be an island or may border a relatively densely populated area; in such applications the technical problems associated with providing land based networks may be alleviated.
The various embodiments described may possess one or more advantages although not all embodiments will possess such advantages. For example, the cables may be laid and replaced quickly and efficiently; this will allow for faster upgrading of cable networks. The maintenance and upgrading costs may be low in comparison to known schemes. The cables laid may be more reliable, as they are less susceptible to damage from shipping and from maintenance and cable replacement. Any of the features described above which contribute to any advantages identified herein may be provided independently of other features and in other applications, unless otherwise stated.
All of the above embodiments of the invention have been described by way of example only, and modifications and similar arrangements may occur to those skilled in the art. The applicant retains design right and copyright in all drawings and all material in this specification. Facsimile reproduction of the published version of this patent specification is permitted.
Claims
1. A method of facilitating provision of a point-to-point cable connection between first and second points separated by an extended span of water including a first region of shallow water and a second region of relatively deep water, the method comprising: providing a plurality of ducts from the first point through the first region of the extended span to an offshore termination point between the first and second points; placing a first cable in one of said plurality of ducts to provide a connection between the first point and said offshore termination point; receiving at said offshore termination point, a second cable from the second point; and connecting said first cable to said second cable at said offshore termination point to create the point-to-point cable connection.
2. The method of claim 1, wherein said first point is onshore and said providing step comprises: providing said plurality of ducts from the first point through the first region of the extended span to said offshore termination point between the first and second points, wherein said offshore termination point is at a distance of at least 2 kilometres from the first point.
3. The method of claim 1 , wherein said first point is onshore and wherein said providing step comprises: providing said plurality of ducts from the first point through the first region of the extended span to said offshore termination point between the first and second points, wherein said offshore termination point is at a distance of about 10 to 20 kilometres from the first point.
4. The method of claim 1 , wherein said first point is onshore and wherein said providing step comprises: providing said plurality of ducts from the first point through the first region of the extended span to said offshore termination point between the first and second points, wherein said offshore termination point is adjacent a transition the first and second regions.
5. The method of claim 4, wherein said first region is the Continental Shelf.
6. The method of claim 5, wherein said offshore termination point is positioned in water having a depth of less than about 200m.
7. The method of claim 1, wherein said placing step comprises placing the first cable in one of said plurality of ducts to provide a connection between the first point and said offshore termination point, wherein said first cable is a relatively thin, lightweight cable; and said receiving step comprises receiving at said offshore termination point, a second cable from the second point, wherein said second cable is an armoured cable.
8. The method of claim 1 , further comprising a step of: burying said plurality of ducts in the seabed.
9. The method of claim 8, further comprising the step of: burying said plurality of ducts in the seabed at a burial depth that decreases as a function of distance from said first point such that said plurality of ducts are buried deeper near said first point.
10. The method of claim 9, wherein said first point is onshore, adjacent a shoreline.
11. The method of claim 1 , wherein said providing step comprises: providing said plurality of ducts from the first point through the first region of the extended span to said offshore termination point between the first and second points, wherein said offshore termination point is an offshore platform.
12. The method of claim 11 , wherein said providing step further comprises: providing communication equipment on said offshore platform to receive and transmit signals via said first and second cables.
13. The method of claim 1, further comprising the step of: providing a plurality of spaced apart cable exits in the region of the offshore termination point.
14. The method of claim 13, wherein said step of providing a plurality of spaced apart cable exits comprises: providing said plurality of spaced apart cable exits in the region of the offshore termination point, wherein said spaced apart cable exits are preferably spaced apart by at least 50m.
15. The method of claim 13 , further comprising the step of: branching each of said plurality of ducts so that each duct leads to a conesponding cable exit.
16. A system for facilitating provision of a point-to-point cable connection between first and second points separated by an extended span of water including a first region of shallow water and a second region of relatively deep water, comprising: an offshore termination point located between the first and second points, for receiving at least one first cable from the first point and at least one second cable from the second point and providing signal communication between the first point and the second point; and a plurality of ducts extending from the first point through the first region of the extended span to said offshore termination point, each of said ducts being configured to receive at least one first cable.
17. The system of claim 16, wherein said offshore termination point is at a distance of at least 2 kilometres from the first point.
18. The system of claim 16, wherein said offshore termination point is at a distance of about 10 to 20 kilometres from the first point.
19. The system of claim 16, wherein said offshore termination point is adjacent a transition between the first and second regions.
20. The system of claim 19, wherein said first region is the Continental Shelf.
21. The system of claim 16, further comprising: a first cable extending through one of said plurality of ducts to provide a connection between the first point and said offshore termination point; and a second cable extending from the second point to said offshore termination point.
Applications Claiming Priority (5)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US25213000P | 2000-11-21 | 2000-11-21 | |
US252130P | 2000-11-21 | ||
GB0105403A GB2369728B (en) | 2000-11-21 | 2001-03-05 | Cable installation |
GB0105403 | 2001-03-05 | ||
PCT/US2001/043191 WO2002043214A2 (en) | 2000-11-21 | 2001-11-20 | Cable installation |
Publications (1)
Publication Number | Publication Date |
---|---|
EP1337885A2 true EP1337885A2 (en) | 2003-08-27 |
Family
ID=26245784
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP01997876A Withdrawn EP1337885A2 (en) | 2000-11-21 | 2001-11-20 | Cable installation |
Country Status (3)
Country | Link |
---|---|
EP (1) | EP1337885A2 (en) |
AU (1) | AU2002216663A1 (en) |
WO (1) | WO2002043214A2 (en) |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE102004058030A1 (en) * | 2004-11-26 | 2006-06-01 | Siemens Ag | Method for laying a gas-insulated electrical line |
DE102005007147A1 (en) * | 2005-02-11 | 2006-08-24 | Siemens Ag | Method for laying a gas-insulated electrical line and mass element for positioning a gas-insulated electrical line |
CN102278528A (en) * | 2011-06-15 | 2011-12-14 | 中国瑞林工程技术有限公司 | Arranging method of composite line pipe of copper and copper alloy plate strip job shop |
WO2018162103A1 (en) * | 2017-03-09 | 2018-09-13 | Siemens Wind Power A/S | Cable hang-off arrangement |
CN112178425A (en) * | 2020-09-14 | 2021-01-05 | 中国海洋大学 | Rapid fixing device and laying method for optical fiber sensor for deep-sea mixed transport vertical pipe |
CN113202141A (en) * | 2021-05-11 | 2021-08-03 | 西京学院 | Seabed vacuum pipeline test line capable of being extended to application line and implementation method thereof |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE1207465B (en) * | 1963-10-18 | 1965-12-23 | Felten & Guilleaume Carlswerk | Method for laying electrical cables, flexible pipelines or the like in lakes and rivers |
GB2122367B (en) * | 1982-05-06 | 1987-05-13 | Standard Telephones Cables Ltd | Laying cables |
JPS62225632A (en) * | 1986-03-27 | 1987-10-03 | Kokusai Denshin Denwa Co Ltd <Kdd> | Mobile layer for underwater bottom cable |
US4756510A (en) * | 1986-08-11 | 1988-07-12 | Atlantic Richfield Company | Method and system for installing fiber optic cable and the like in fluid transmission pipelines |
FR2704250B1 (en) * | 1993-04-21 | 1995-06-30 | Coflexip | Method and device for continuously laying and burying a flexible underwater pipe. |
-
2001
- 2001-11-20 WO PCT/US2001/043191 patent/WO2002043214A2/en not_active Application Discontinuation
- 2001-11-20 AU AU2002216663A patent/AU2002216663A1/en not_active Abandoned
- 2001-11-20 EP EP01997876A patent/EP1337885A2/en not_active Withdrawn
Non-Patent Citations (1)
Title |
---|
See references of WO0243214A3 * |
Also Published As
Publication number | Publication date |
---|---|
WO2002043214A9 (en) | 2003-05-01 |
AU2002216663A1 (en) | 2002-06-03 |
WO2002043214A3 (en) | 2002-10-10 |
WO2002043214A2 (en) | 2002-05-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US8668406B2 (en) | Subsea cable installation | |
AU681654B2 (en) | Method and device for continuously laying and burying a flexible submarine cable | |
US9121529B2 (en) | Method of laying a hybrid pipeline on the seabed | |
US8747025B2 (en) | Offshore cable laying method | |
KR20100020469A (en) | A tubing arrangement for an offshore facility | |
EP1337885A2 (en) | Cable installation | |
US20110142543A1 (en) | Method of Using Sacrificial Pipe String | |
WO2010018401A1 (en) | Installation tube | |
CN110573779B (en) | Method for laying a pipe bundle on the seabed | |
JP2009060710A (en) | Relocation construction method for underwater cable | |
GB2296957A (en) | A method of installing an underwater pipeline and/or cable | |
Costello et al. | Insulated pipelines between the underwater manifold centre and Cormorant a platform in the northern North Sea | |
Jeroense | Recommendations for Mechanical Testing of Submarine Cables (and Their Accessories) | |
Black et al. | Horizontal directional drilling cable shorelanding at san nicolas island, California | |
Mollison | Pipeline Installation by Bottom Tow Reduces Cost | |
JPH06109931A (en) | Direct embedding and laying method for optical fiber cable | |
Arkell et al. | Design, manufacture and installation of 150 kV submarine cable system for the Java–Madura interconnection | |
Behar et al. | The New Concept Of Flexible Pipes. Their Manufacture. Their Applications In The Offshore Oil Industry. Field Experiences. | |
Christiani | Ultra deepwater reel and flexible pipelay vessel for pre-salt field developments | |
DeJong et al. | Development and Utilization of a Deepwater Pipeline Connector | |
Nehme et al. | Oil Offloading Lines and Fiber Optic Cable Package | |
Galloway et al. | 150 kV Java-Madura submarine cable system interconnection | |
Green et al. | 3. The Design and Construction of Underwater Pipelines (USA) | |
Chen et al. | New Installation Method for Subsea Pipelines in South China Sea | |
Lallier et al. | A Technical Review of the Frigg Pipelines Constructions |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
17P | Request for examination filed |
Effective date: 20030605 |
|
AK | Designated contracting states |
Designated state(s): AT BE CH CY DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE TR |
|
AX | Request for extension of the european patent |
Extension state: AL LT LV MK RO SI |
|
17Q | First examination report despatched |
Effective date: 20050411 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN |
|
18D | Application deemed to be withdrawn |
Effective date: 20051024 |