- EP0867272A2 EP0867272A2 EP97115067A EP97115067A EP0867272A2 EP 0867272 A2 EP0867272 A2 EP 0867272A2 EP 97115067 A EP97115067 A EP 97115067A EP 97115067 A EP97115067 A EP 97115067A EP 0867272 A2 EP0867272 A2 EP 0867272A2
- Authority
- EP
- European Patent Office
- Prior art keywords
- station
- press
- floors
- press according
- loading
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B30—PRESSES
- B30B—PRESSES IN GENERAL
- B30B7/00—Presses characterised by a particular arrangement of the pressing members
- B30B7/02—Presses characterised by a particular arrangement of the pressing members having several platens arranged one above the other
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B27—WORKING OR PRESERVING WOOD OR SIMILAR MATERIAL; NAILING OR STAPLING MACHINES IN GENERAL
- B27D—WORKING VENEER OR PLYWOOD
- B27D3/00—Veneer presses; Press plates; Plywood presses
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B27—WORKING OR PRESERVING WOOD OR SIMILAR MATERIAL; NAILING OR STAPLING MACHINES IN GENERAL
- B27N—MANUFACTURE BY DRY PROCESSES OF ARTICLES, WITH OR WITHOUT ORGANIC BINDING AGENTS, MADE FROM PARTICLES OR FIBRES CONSISTING OF WOOD OR OTHER LIGNOCELLULOSIC OR LIKE ORGANIC MATERIAL
- B27N3/00—Manufacture of substantially flat articles, e.g. boards, from particles or fibres
- B27N3/08—Moulding or pressing
- B27N3/20—Moulding or pressing characterised by using platen-presses
Definitions
- the invention relates to a continuous press with the features the preamble of claim 1.
- the invention is therefore based on the object of a press for creating veneer material that stands out through a high Throughput with a compact design and more economical Operating possibility and thus high efficiency overall distinguished.
- Is a loading station for loading the press station with too processing veneer material is provided and is the Loading station designed so that it has at least two has superposed floors, and is at least one of the floors at least partially by at least one Swivel axis is pivotally arranged, so is a System chosen that with a small footprint and high throughput and thus high efficiency, through which simple design of the swiveling floors easy loading of the loading station with processing veneer material guaranteed.
- the loading station has one of the number of floors in the Press station on identical number of floors and everyone is Press station floor assigned a loading station floor, so thereby chosen a system with which simple but failure-prone way as fast as possible Load the press station with material to be pressed is made possible.
- the loading station has two levels one above the other on, and is at least partially the top of the two floors about at least one pivot axis between a lower one Material delivery position and an upper maximum position arranged pivotably, and is the lower of the two Levels at least partially around at least one pivot axis between an upper material delivery position and a lower maximum position is pivotally arranged thereby choosing a facility with which a simple and easy assembly of the lower floor with too processing material is made possible.
- the first is to expose the material to pressure and heat treating press station is present and is a second, with the first press station in a row lying press station is present and is the second press station for cooling the Designed to serve materials under pressure, so an arrangement is hereby selected, which at the same time high throughput of veneer material to be pressed Minimum machine life of the two press stations guaranteed, because a time-consuming and therefore cost-intensive transport of the veneer material to be processed between the Press stations are eliminated.
- the press station has at least two on top of each other arranged, a pressure and heat treatment of the material serving floors and has the second press station at least two superimposed cooling the Material pressurized floors on, and each have at least two floors of the first and second press station at least one, the feed and / or removal of the material from or into the press station serving conveyor belts, so it becomes an arrangement chosen that with the largest possible throughput and the smallest possible space requirement, a simple but failure-prone shipment of the goods to be processed Guaranteed veneer material from or in the pressing stations.
- the unloading station has one of the number of floors Press station on identical number of floors and everyone is Press station floor assigned an unloading station floor, so thereby chosen a system with which simple but trouble-free way of unloading as quickly as possible of the finished pressed material from the pressing station becomes.
- the unloading station has two levels arranged one above the other on, and is at least partially the top of the two floors about at least one pivot axis between a lower one Material removal position and an upper maximum position arranged pivotably and is the lower of the two floors at least partially between at least one pivot axis an upper material removal position and a lower one Maximum position is arranged so that it can pivot chosen a facility with which a simple and easy unloading of the pressed material from the lower floor is made possible.
- each of the at least two superimposed ones Floors of the unloading device each have at least one Removal of the processed material from the press station serving conveyor belt, an arrangement is thereby selected, with which a large one with the smallest space requirement Amount of veneer material processed from the press station can be removed.
- each other assigned conveyor belts of the loading station, the pressing station and the unloading station in flight i.e. in a vertical plane can be brought, so it becomes a Arrangement chosen to ensure a smooth continuous Production process guaranteed because the veneer batches to everyone Edited at the same time at the production process become, i.e. a time-consuming and therefore costly lifting or lowering the veneer batches.
- the continuous press 1 according to the invention from FIG this embodiment of four arranged in series Work stations, a heating press 2 and a cooling press 3, continue from a right next to the heating press 2 arranged loading station 4 and one to the left of the Unloading station 5 arranged in the cooling press 3.
- the loading station 4 consists of two superimposed conveyor floors 6.7, each about a pivot axis 8.9 in the directions of arrow 12 Fig.1 are pivotally mounted.
- the pivot axes 8.9 of the conveyor floors 6.7 are in this Embodiment, as can be seen in Fig.1a, in the Centers of the pulleys 13, 14 each to the Funding days 6,7 belonging conveyor belt 10,11 placed on the side of the loading station 4 are attached to the Connect heating press 2.
- a swiveling of the conveyor floors 6,7 around another, one Opening of the conveyor floors 6,7 guaranteeing swivel axis 8,9 is just as conceivable as possible, as is pivoting the funding days 6.7 about a pivot axis 8.9 on the Side of the loading station 4 is facing away from the heating press is.
- the promotion days are 6.7 around their respective Swivel axis 8.9 in the directions of arrow 12 Fig.1 pivots that between the funding levels 6.7 Opening angle arises.
- the opening angle to be achieved between the two Funding days 6,7 should be chosen so large that all points of the lower funding level 7 are easily accessible are, i.e. equipping the lower funding level 7 can be done easily.
- the lower conveyor floor 7 is included Veneer batches 15 loaded, then both conveyor floors pivoted back into their horizontal starting position, so that now the upper conveyor floor 6 also with veneer batches 15 can be equipped.
- the batches of veneer 15 to be pressed are to e.g. 12 to 24 sheets arranged one above the other, e.g. arranged in about 4 to 6 rows next to each other are.
- the heating press 2 is on opened the conventional way.
- the batches of veneer 15 to be pressed are now so in Move horizontally in the direction of arrow 16 from FIG on the upper conveyor belt 10 of the loading station 4 lying veneer batches 15 on that, now with it in one Upper conveyor belt 17 of the heating press 2 in alignment arrive, and on the lower conveyor belt 11 of the Loading station 4 lying veneer batches 15 on that, now with him also lower conveyor belt lying in alignment 18 of the heating press 2 are spent.
- the hot pressed veneer batches 15a can now be in the cooling press 3 connected to the heating press 2 in the direction of arrow 16 from FIG. 1.
- the heating press 2 is set to that described above Way from the loading station 4, with others too pressing pressing veneer batches 15, so that both Pressing processes in the heating press 2 and in the cooling press 3 can be started at the same time.
- the loading station 4 can now also again during the now running pressing operations, in the manner already described and Refilled with veneer batches to be pressed will.
- the design of the unloading station 5 is that of the loading station 4 the same, in this embodiment it is a mirror image arranged to the loading station 4.
- the unloading station 5 is in this embodiment from two superposed conveyor floors 21, 22 each about a pivot axis 27, 28 in the directions of the Arrow 29 from Figure 2 are pivotally mounted.
- the pivot axis 27, 28 of the conveyor floors 21, 22 are in this Embodiment, the centers of the pulleys 30,31 one belonging to each of the funding days 21, 22 Conveyor belt 32,33 on the side of the unloading station 5 are arranged, which connect to the cooling press 3.
- the opening angle to be achieved between the two Funding days 21,22 should be chosen so large that everyone Points of the lower funding level 22 are easily accessible, i.e. that unloading the lower conveyor floor 22 easily can be done.
- the unloading station 5 is opened in this exemplary embodiment manual type unloading, first those on the upper conveyor floor 21 lying pressed Unload veneer batches 15c, then after swiveling the Funding days 21, 22 are those on the lower funding level 22 unload lying veneer batches 15c.
- Such a continuous feed can be such be made that in the presses 2.3 batches to be imported first into the loading station 4 be introduced, then, as described above, in the first workstation, i.e. Press station 2, spent too will.
- the loading station 4 can now again charged with batches to be brought into the press station 2 will.
- the batch located in the press station 2 After completion of the pressing process in the pressing station 2 then the batch located in the press station 2, according to a given length, e.g. corresponding the length of those located in the loading station 4 processed materials, this e.g. can be made such that the already in the Press station 2 spent batch there in whole or in part remains, while that existing in the loading station 4 Batch is already brought into press station 2, i.e. it are then in the press station 2 two to be processed Batches, whereby the batch introduced first is still in its entirety or only partially present in the first press station 2 can be.
- a given length e.g. corresponding the length of those located in the loading station 4 processed materials
- the press station 2 After the pressing process is completed, the press station 2 existing batches or those available in the press station Batches transported and new material in the Press station 2 spent from the loading station 4, the to processing batches arranged one behind the other will.
- the first one arrives of the batches introduced into the pressing station 2 into the second Press station 3, it is quite conceivable that a part of the material to be processed with his, the first Press station 2 facing end remains in this.
- the loading station 4 of the first pressing station 2 of the second Press station 3 and the removal station 5 is one continuous processing of the material to be pressed, e.g. guaranteed regardless of the length of the individual batches.
- the arrangement i.e. Position of the material during the Pressing process depends on the length of the press stations and the length of the material to be processed.
Landscapes
- Life Sciences & Earth Sciences (AREA)
- Engineering & Computer Science (AREA)
- Wood Science & Technology (AREA)
- Forests & Forestry (AREA)
- Mechanical Engineering (AREA)
- Manufacturing & Machinery (AREA)
- Veneer Processing And Manufacture Of Plywood (AREA)
- Press Drives And Press Lines (AREA)
Abstract
Description
Die Erfindung betrifft eine Durchlaufpresse mit den Merkmalen des Oberbegriffs des Patentanspruchs 1.The invention relates to a continuous press with the features the preamble of claim 1.
Bei bekannten Furnierpressen ist es üblich, daß das zu verarbeitende Furniermaterial zunächst in eine Heizpresse verbracht wurde, wo es unter Wärmeeinwirkung und Druckbeaufschlagung in einem ersten Arbeitsschritt gepreßt wurde.In known veneer presses, it is common for this to be the case processing veneer material first in a heating press was where it was exposed to heat and Pressurization pressed in a first step has been.
Danach wurden die so warmgepreßten Furnierchargen in eine Kühlpresse verbracht, in der sie in einem zweiten Arbeitsschritt unter Druckeinwirkung abgekühlt wurden.Then the hot-pressed veneer batches were put into one Cooling press spent in a second Work step were cooled under pressure.
Eine derartige Behandlung bzw. ein derartiger Aufbau der Anlage, machte es erforderlich, sowohl für die Heizpresse als auch für die Kühlpresse Bedienungspersonal bereitzustellen, die nicht nur für eine ordnungsgemäße Verbringung des Furniermaterials in die einzelnen Fressen zu sorgen hatten, sondern auch für den Transport des Furniermaterials zwischen den Pressen zuständig waren.Such treatment or structure of the Facility, made it necessary for both the heating press as well to provide operating personnel for the cooling press, which is not only for a proper shipment of the Veneer material had to take care of the individual faces, but also for the transport of the veneer material between the presses were responsible.
Die durch diesen Aufbau der Anlage resultierenden, relativ hohen Maschinenstandzeiten, in Zusammenwirkung mit der relativ geringen Durchsatzmenge an zu bearbeitenden Furniermaterial, hatten zur Folge, daß eine solche Anlage mit hohen Arbeits- und Maschinenkosten einhergeht, die zu einer Verteuerung des Arbeitsprozesses insgesamt führten.The resulting from this construction of the plant, relative long machine service life, in cooperation with the relatively low throughput to be processed Veneer material had the result that such a system with high labor and machine costs, which leads to a Overall increase in the cost of the work process.
Der Erfindung liegt daher die Aufgabe zugrunde, eine Presse für Furniermaterial zu schaffen, die sich durch einen hohen Durchsatz bei kompakter Bauweise und wirtschaftlicher Betriebsmöglichkeit und damit hoher Wirtschaftlichkeit insgesamt auszeichnet.The invention is therefore based on the object of a press for creating veneer material that stands out through a high Throughput with a compact design and more economical Operating possibility and thus high efficiency overall distinguished.
Diese Aufgabe wird bei einer Durchlaufpresse der eingangsgenannten Gattung mit den Merkmalen des kennzeichnenden Teils des Patentanspruchs 1 gelöst.This task is carried out in a continuous press genus with the characteristics of characterizing part of claim 1 solved.
Weitere vorteilhafte Ausgestaltungen der Erfindung sind Gegenstand der Unteransprüche.Further advantageous embodiments of the invention are Subject of the subclaims.
Ist eine Beladestation zur Beschickung der Preßstation mit zu verarbeitenden Furniermaterial vorgesehen und ist die Beladestation dermaßen ausgestaltet, daß sie wenigstens zwei übereinander angeordnete Etagen aufweist, und ist wenigstens eine der Etagen wenigstens teilweise um wenigstens einen Schwenkachse verschwenkbar angeordnet, so wird dadurch ein System gewählt, daß bei gleichzeitig geringem Platzbedarf und hohem Durchsatz und damit hoher Wirtschaftlichkeit, durch die einfache konstruktive Ausgestaltung der verschwenkbar Etagen ein problemloses Bestücken der Beladestation mit zu bearbeitenden Furniermaterial gewährleistet.Is a loading station for loading the press station with too processing veneer material is provided and is the Loading station designed so that it has at least two has superposed floors, and is at least one of the floors at least partially by at least one Swivel axis is pivotally arranged, so is a System chosen that with a small footprint and high throughput and thus high efficiency, through which simple design of the swiveling floors easy loading of the loading station with processing veneer material guaranteed.
Weist die Beladestation eine der Anzahl der Etagen der Preßstation identische Anzahl an Etagen auf und ist jeder Preßstationetage eine Beladestationetage zugeordnet, so wird dadurch ein System gewählt, mit dem auf einfache aber störunanfällige Art und Weise ein schnellstmögliches Bestücken der Preßstation mit zu pressenden Material ermöglicht wird. If the loading station has one of the number of floors in the Press station on identical number of floors and everyone is Press station floor assigned a loading station floor, so thereby chosen a system with which simple but failure-prone way as fast as possible Load the press station with material to be pressed is made possible.
Weist die Beladestation zwei übereinander angeordnete Etagen auf, und ist die obere der beiden Etagen wenigstens teilweise um wenigstens eine Schwenkachse zwischen einer unteren Materialabgabeposition und einer oberen Maximalposition verschwenkbar angeordnet, und ist die untere der beiden Etagen wenigstens teilweise um wenigstens eine Schwenkachse zwischen einer oberen Materialabgabeposition und einer unteren Maximalposition verschwenkbar angeordnet, so wird dadurch eine Einrichtung gewählt, mit der ein einfaches und problemloses Bestücken der unteren Etage mit zu verarbeitenden Material ermöglicht wird.If the loading station has two levels one above the other on, and is at least partially the top of the two floors about at least one pivot axis between a lower one Material delivery position and an upper maximum position arranged pivotably, and is the lower of the two Levels at least partially around at least one pivot axis between an upper material delivery position and a lower maximum position is pivotally arranged thereby choosing a facility with which a simple and easy assembly of the lower floor with too processing material is made possible.
Weist jede der Etagen der Beladestation jeweils wenigstens ein der Beschickung der Preßstation mit Furniermaterial dienendes Förderband auf, so wird dadurch eine Anordnung gewählt, mit der auf einfache aber störunanfällige Weise gleichzeitig eine große Menge an zu verarbeitenden Furniermaterial in die Preßstation verbracht werden kann.At least assign each of the floors of the loading station one of the loading of the press station with veneer material serving conveyor belt, so it becomes an arrangement chosen with the simple but not susceptible to interference at the same time a large amount of to be processed Veneer material can be brought into the press station.
Ist eine erste, das Material druck- und wärmeaussetzend behandelnde Preßstation vorhanden und ist eine zweite, mit der ersten Preßstation in eine Reihe liegende Preßstation vorhanden und ist die zweite Preßstation der Abkühlung des Materials unter Druckbeaufschlagung dienend ausgestaltet, so wird hiermit eine Anordnung gewählt, die bei gleichzeitig hoher Druchsatzmenge an zu pressenden Furniermaterial eine möglichst geringe Maschinenstandzeit der beiden Preßstationen garantiert, da ein zeit- und damit kostenintensiver Transport des zu verarbeitenden Furniermaterials zwischen den Preßstationen entfällt.The first is to expose the material to pressure and heat treating press station is present and is a second, with the first press station in a row lying press station is present and is the second press station for cooling the Designed to serve materials under pressure, so an arrangement is hereby selected, which at the same time high throughput of veneer material to be pressed Minimum machine life of the two press stations guaranteed, because a time-consuming and therefore cost-intensive transport of the veneer material to be processed between the Press stations are eliminated.
Weist die Preßstation wenigstens zwei übereinander angeordnete, einer Druck- und Wärmebehandlung des Materials dienende Etagen auf und weist die zweite Preßstation wenigstens zwei übereinander angeordnete der Abkühlung des Materials unter Druckbeaufschlagung dienende Etagen auf, und weisen die jeweils wenigstens zwei Etagen der ersten und zweiten Preßstation jeweils wenigstens ein, der Beschickung und/oder Entnahme des Materials aus oder in die Preßstation dienende Förderbänder auf, so wird dadurch eine Anordnung gewählt, daß bei gleichzeitig größtmöglicher Durchsatzmenge und geringst möglichem Platzbedarf, eine einfache aber störunanfällige Verbringung des zu verarbeitenden Furniermaterials aus oder in die Preßstationen gewährleistet.If the press station has at least two on top of each other arranged, a pressure and heat treatment of the material serving floors and has the second press station at least two superimposed cooling the Material pressurized floors on, and each have at least two floors of the first and second press station at least one, the feed and / or removal of the material from or into the press station serving conveyor belts, so it becomes an arrangement chosen that with the largest possible throughput and the smallest possible space requirement, a simple but failure-prone shipment of the goods to be processed Guaranteed veneer material from or in the pressing stations.
Ist eine Entladestation vorgesehen, und ist die Entladestation auf der, der Beladestation gegenüberliegenden Seite der Preßstationen vorgesehen und weist die Entladestation wenigstens zwei übereinander angeordnete Etagen auf, und ist wenigstens eine der Etagen wenigstens teilweise um wenigstens eine Schwenkachse verschwenkbar angeordnet, so wird hierdurch ein System gewählt, mit dem bei gleichzeitig geringstem Platzbedarf und hohem Durchsatz und damit hoher Wirtschaftlichkeit insgesamt ein mühe- und problemloses Entladen der Entladevorrichtung gewährleistet ist.Is an unloading station provided and is the Unloading station on the opposite of the loading station Provided side of the press stations and has the Unloading station at least two superimposed Floors, and is at least one of the floors at least partially pivotable about at least one pivot axis arranged, a system is thereby selected with which at the same time minimum space requirement and high throughput and thus a high level of cost-effectiveness guaranteed unloading of the unloading device is.
Weist die Entladestation eine der Anzahl der Etagen der Preßstation identische Anzahl an Etagen auf und ist jeder Preßstationetage eine Entladestationetage zugeordnet, so wird dadurch ein System gewählt, mit dem auf einfache aber störunanfällige Art und Weise ein schnellstmögliches Entladen des fertiggepreßten Materials aus der Preßstation ermöglicht wird.If the unloading station has one of the number of floors Press station on identical number of floors and everyone is Press station floor assigned an unloading station floor, so thereby chosen a system with which simple but trouble-free way of unloading as quickly as possible of the finished pressed material from the pressing station becomes.
Weist die Entladestation zwei übereinander angeordnete Etagen auf, und ist die obere der beiden Etagen wenigstens teilweise um wenigstens eine Schwenkachse zwischen einer unteren Materialentnahmeposition und einer oberen Maximalposition verschwenkbar angeordnet und ist die untere der beiden Etagen wenigstens teilweise um wenigstens eine Schwenkachse zwischen einer oberen Materialentnahmeposition und einer unteren Maximalposition verschwenkbar angeordnet, so wird dadurch eine Einrichtung gewählt, mit der ein einfaches und problemloses Entladen des fertiggepreßten Materials von der unteren Etage ermöglicht wird.The unloading station has two levels arranged one above the other on, and is at least partially the top of the two floors about at least one pivot axis between a lower one Material removal position and an upper maximum position arranged pivotably and is the lower of the two floors at least partially between at least one pivot axis an upper material removal position and a lower one Maximum position is arranged so that it can pivot chosen a facility with which a simple and easy unloading of the pressed material from the lower floor is made possible.
Weist jede der wenigstens zwei übereinander angeordneten Etagen der Entladevorrichtung jeweils wenigstens ein, der Entnahme des verarbeiteten Materials aus der Preßstation dienendes Förderband, so wird dadurch eine Anordnung gewählt, mit der bei gleichzeitig geringstem Platzbedarf eine große Menge an verarbeiteten Furniermaterial aus der Preßstation entnommen werden kann.Assigns each of the at least two superimposed ones Floors of the unloading device each have at least one Removal of the processed material from the press station serving conveyor belt, an arrangement is thereby selected, with which a large one with the smallest space requirement Amount of veneer material processed from the press station can be removed.
Sind die Beladestationen, die Entladestation und die Preßstationen hintereinander in einer Reihe liegend angeordnet, so wird hierdurch eine Anordnung gewählt, in der auf einfachste konstruktive Art große und damit kostenintensive Transportwege zwischen den einzelnen Arbeitsstationen vermieden werden, wodurch ein reibungsloser und damit kostengünstiger Produktionsablauf gewährleistet ist.Are the loading stations, the unloading station and the Press stations lying in a row one after the other arranged, an arrangement is hereby selected in which in the simplest constructive way large and therefore costly transport routes between the individual Workstations can be avoided, which makes it smoother and thus guarantees cost-effective production processes is.
Sind die jeweils zwei übereinander angeordneten, einander zugeordneten Förderbänder der Beladestation, der Preßstation und der Entladestation in einer Flucht, d.h. in eine vertikale Ebene bringbar angeordnet, so wird damit eine Anordnung gewählt, die einen reibungslosen kontinuierlichen Produktionsablauf garantiert, da die Furnierchargen zu jedem Zeitpunkt des Produktionsablaufs auf einer Höhe bearbeitet werden, d.h. ein zeit- und damit kostenintensives Anheben oder Absenken der Furnierchargen entfällt.Are the two superimposed, each other assigned conveyor belts of the loading station, the pressing station and the unloading station in flight, i.e. in a vertical plane can be brought, so it becomes a Arrangement chosen to ensure a smooth continuous Production process guaranteed because the veneer batches to everyone Edited at the same time at the production process become, i.e. a time-consuming and therefore costly lifting or lowering the veneer batches.
In der Zeichnung ist ein Ausführungsbeispiel einer erfindungsgemäßen Durchlaufpresse schematisch dargestellt und zwar zeigt
- Fig.1
- eine erfindungsgemäße Durchlaufpresse in einer ersten Arbeitsposition in Seitenansicht,
- Fig.1a
- einen vergrößerten Teilausschnitt der erfindungsgemäßen Durchlaufpresse aus Fig.1,
- Fig.2
- die erfindungsgemäße Durchlaufpresse aus Fig.1 in einer zweiten Arbeitsposition in Seitenansicht,
- Fig.3
- die erfindungsgemäße Durchlaufpresse aus den Figuren 1 und 2 in Draufsicht.
- Fig. 1
- a continuous press according to the invention in a first working position in side view,
- Fig.1a
- 2 shows an enlarged partial section of the continuous press according to the invention from FIG. 1,
- Fig. 2
- the continuous press according to the invention from Figure 1 in a second working position in side view,
- Fig. 3
- the continuous press according to the invention from Figures 1 and 2 in plan view.
Die erfindungsgemäße Durchlaufpresse 1 aus Fig.1 besteht in
diesem Ausführungsbeispiel aus vier in Reihe angeordneten
Arbeitsstationen, einer Heizpresse 2 und einer Kühlpresse 3,
weiterhin aus einer rechts neben der Heizpresse 2
angeordneten Beladestation 4 sowie einer links neben der
Kühlpresse 3 angeordneten Entladestation 5.The continuous press 1 according to the invention from FIG
this embodiment of four arranged in series
Work stations, a
Die Beladestation 4 besteht in diesem Ausführungsbeispiel aus
zwei übereinander angeordneten Förderetagen 6,7, die jeweils
um eine Schwenkachse 8,9 in den Richtungen des Pfeils 12 aus
Fig.1 schwenkbar gelagert sind.In this exemplary embodiment, the
Die Schwenkachsen 8,9 der Förderetagen 6,7 sind in diesem
Ausführungsbeispiel, wie in Fig.1a ersichtlich, in die
Mittelpunkte der Umlenkrollen 13,14 eines jeweils zu den
Förderetagen 6,7 gehörigen Förderbands 10,11 gelegt, die an
der Seite der Beladestation 4 angebracht sind, die an die
Heizpresse 2 anschließen.The pivot axes 8.9 of the conveyor floors 6.7 are in this
Embodiment, as can be seen in Fig.1a, in the
Centers of the
Ein Verschwenken der Föderetagen 6,7 um eine andere, eine
Öffnung der Förderetagen 6,7 garantierende Schwenkachse 8,9
ist aber genauso denkbar wie möglich, ebenso ein Verschwenken
der Förderetagen 6,7 um eine Schwenkachse 8,9 die auf der
Seite der Beladestation 4 liegt, der der Heizpresse abgewandt
ist. A swiveling of the
Es wäre aber genauso denkbar, gemäß eines hier nicht
dargestellten Ausführungsbeispiels, nur eine der Förderetagen
6,7 um eine Schwenkachse 8 schwenkbar zu gestalten.But it would also be conceivable, according to one not here
illustrated embodiment, only one of the funding floors
6.7 to make a
Zum Bestücken der Beladestation 4 mit zu pressenden
Furnierchargen 15, die in Fig.2 strichpunktiert angedeutet
sind, werden die Förderetagen 6,7 um ihre jeweilige
Schwenkachse 8,9 derart in den Richtungen des Pfeils 12 aus
Fig.1 verschwenkt, daß zwischen den Förderetagen 6,7 ein
Öffnungswinkel entsteht.To load the
Der zu erreichende Öffnungswinkel zwischen den beiden
Förderetagen 6,7 ist dabei jeweils so groß zu wählen, daß
alle Punkte der unteren Förderetage 7 problemlos erreichbar
sind, d.h. das ein Bestücken der unteren Förderetage 7
problemlos erfolgen kann.The opening angle to be achieved between the two
Das Bestücken der Beladestation 4 mit zu pressenden
Furnierchargen 15 erfolgt, in diesem Ausführungsbeispiel,
durch manuelle Verbringung der Furnierchargen 15 auf die
Förderetagen 6,7.The loading of the
Dabei wird zunächst die untere Förderetage 7 mit
Furnierchargen 15 bestückt, danach werden beide Förderetagen
in ihre horizontale Ausgangslage zurückgeschwenkt, so daß
jetzt die obere Förderetage 6 ebenfalls mit Furnierchargen 15
bestückt werden kann.First, the
Eine der oben beschriebenen, umgekehrte Vorgehensweise ist aber genauso denkbar, wie ein gleichzeitiges Bestücken beider Förderetagen 6,7 im ausgeschwenkten Zustand.One of the reverse procedures described above is but just as conceivable as equipping both at the same time Funding days 6.7 in the swung-out state.
Bei den zu pressenden Furnierchargen 15 handelt es sich dabei
um z.B. 12 bis 24 übereinander angeordnete Blätter, die z.B.
in etwa 4 bis 6 nebeneinanderliegenden Reihen angeordnet
sind. The batches of
Nach Bestücken der Beladestation 4 mit zu pressenden
Furnierchargen 15 und Zurückschwenken der Förderetagen 6,7 in
ihre horizontale Ausgangslage, wird die Heizpresse 2 auf
herkömmliche Art geöffnet.After
Die zu pressenden Furnierchargen 15 werden jetzt derart in
Richtung des Pfeils 16 aus Fig.1 horizontal verfahren, daß
die auf dem oberen Förderband 10 der Beladestation 4
liegenden Furnierchargen 15 auf das, jetzt mit ihm in einer
Flucht liegende obere Förderband 17 der Heizpresse 2
gelangen, und die auf dem unteren Förderband 11 der
Beladestation 4 liegenden Furnierchargen 15 auf das, jetzt
mit ihm ebenfalls in einer Flucht liegende untere Förderband
18 der Heizpresse 2 verbracht werden.The batches of
Nach dem die Heizpresse 2 mit den Furnierchargen 15 beladen
ist, wird diese auf herkömmliche Art geschlossen. Der
Preßvorgang kann nun durch Wärmezuführung und
Druckbeaufschlagung auf beiden Etagen 23,24 der Heizpresse 2
gestartet werden.After loading the
Während des Preßvorganges ist es denkbar und gewollt, daß die
Beladestation 4 erneut mit zu pressenden Furnierchargen 15
bestückt wird, wodurch gewährleistet ist, daß nach Beendigung
des Preßvorganges in der Heizpresse 2, die Furnierchargen 15a
in die Kühlpresse 3 überführt werden und die Heizpresse 2
erneut befüllt werden kann.During the pressing process, it is conceivable and wanted that the
Loading
Eine hohe und damit kostenintensive Standzeit der Heizpresse
2 wird somit vermieden.A long and therefore costly service life of the
Nach Beendigung des Preßvorganges in der Heizpresse 2 wird
diese auf herkömmliche Art wieder geöffnet.After completion of the pressing process in the
Die heißgepreßten Furnierchargen 15a können jetzt in die sich
an die Heizpresse 2 anschließende Kühlpresse 3 in Richtung
des Pfeils 16 aus Fig. 1 verbracht werden. The hot pressed veneer batches 15a can now be in the
Die auf dem oberen Förderband 17 der Heizpresse 2 liegenden
Furnierchargen 15a werden dabei auf das, mit ihm geöffneten
Zustand der Heizpresse 2 und Kühlpresse 3 auf einer
vertikalen Ebene liegende obere Förderband 19 der Kühlpresse
3 verbracht, gleichfalls werden die auf dem unteren
Förderband 18 der Heizpresse 2 liegenden Furnierchargen 15a
auf das mit ihm jetzt ebenfalls in einer vertikalen Ebene
liegende untere Förderband 20 der Kühlpresse 3 verbracht.Those lying on the
Gleichzeitig wird die Heizpresse 2 auf die oben beschriebene
Art und Weise von der Beladestation 4 aus, mit weiteren zu
pressenden Furnierchargen 15 beschickt, so daß beide
Preßvorgänge in der Heizpresse 2 und in der Kühlpresse 3
gleichzeitig gestartet werden können.At the same time, the
Dabei werden die in die Heizpresse 2 verbrachten
Furnierchargen 15 auf schon beschriebene Art und Weise unter
Wärmezuführung und Druckbeaufschlagung gepreßt, die in die
Kühlpresse 3 verbrachten Furnierchargen 15a gleichzeitig
abgekühlt und gepreßt.The are brought into the
Die Beladestation 4 kann jetzt ebenfalls wieder, während der
nun ablaufenden Preßvorgänge, auf schon beschriebene Art und
Weise erneut mit zu pressenden Furnierchargen bestückt
werden.The
Nach Beendigung der beiden Preßvorgänge in der Heizpresse 2
und in der Kühlpresse 3 werden beide Preßstationen 2,3 auf
herkömmliche Art wieder geöffnet.After completing the two pressing processes in the
Die in der Kühlpresse 3 liegenden, nun fertig gepreßten
Furnierchargen 15b werden jetzt auf die sich an die
Kühlpresse 3 anschließende Entladestation 5 in Richtung des
Pfeils 16 aus Fig.1 verbracht. The lying in the
Die auf dem oberen Förderband 19 der Kühlpresse 3 liegenden
Furnierchargen 15b werden dabei auf die mit ihr im geöffneten
Zustand der Kühlpresse 3 in einer Flucht liegende obere
Förderetage 21 der Entladestation 5 verbracht, die auf dem
unteren Förderband 20 der Kühlpresse 3 liegenden
Furnierchargen 15b auf die mit ihr jetzt ebenfalls in einer
Flucht liegende untere Förderetage 22 der Entladestation 5.The lying on the upper conveyor belt 19 of the
Mit dem Entladen der fertiggepreßten Furnierchargen 15b aus
der Kühlpresse 3 in die Entladestation 5, wird diese erneut
mit heißgepreßten Furnierchargen 15a aus der Heizpresse 2 auf
schon beschriebene Art und Weise bestückt, ebenso wird die
Heizpresse 2 erneut mit zu pressenden Furnierchargen 15 von
der Beladestation 4 aus beschickt. Ein erneutes Bestücken der
Beladestation 4 mit weiteren zu pressenden Furnierchargen 15
kann jetzt ebenfalls erfolgen.With the discharge of the finished pressed veneer batches 15b
the
Die Entladestation 5 ist in ihrer Bauart der Beladestation 4
gleich, in diesem Ausführungsbeispiel ist sie spiegelbildlich
zur Beladestation 4 angeordnet.The design of the unloading
Die Entladestation 5 besteht in diesem Ausführungsbeispiel
aus zwei übereinander angeordneten Förderetagen 21,22 die
jeweils um eine Schwenkachse 27,28 in den Richtungen des
Pfeils 29 aus Fig.2 schwenkbar gelagert sind.The unloading
Die Schwenkachse 27,28 der Förderetagen 21,22 sind in diesem
Ausführungsbeispiel die Mittelpunkte der Umlenkrollen 30,31
eines jeweils zu den Förderetagen 21,22 gehörigen
Förderbandes 32,33, die an der Seite der Entladestation 5
angeordnet sind, die an die Kühlpresse 3 anschließen.The
Ein Verschwenken der Förderetagen 21,22 der Entladestation 5
um eine andere, eine Öffnung der Förderetagen 21,22
gewährleistende Schwenkachse 27,28, ist aber ebenso denkbar
wie möglich, gleichfalls ein Verschwenken der Förderetagen
21,22 um eine Schwenkachse 27,28 die auf der Seite der
Entladestation 5 liegt, die der Kühlpresse 3 abgewandt ist.A pivoting of the
Es wäre aber genauso möglich, gemäß eines hier nicht
dargestellten Ausführungsbeispiels, nur die obere Förderetage
21 um eine Schwenkachse 27 schwenkbar zu gestalten.But it would be just as possible, according to one not here
illustrated embodiment, only the
Zum Entladen der nun fertiggepreßten Furnierchargen 15c aus
der Entladestation 5 werden die Förderetagen 21,22 derart um
ihren jeweilige Schwenkachse 27,28 in den Richtungen des
Pfeils 29 aus Fig.2 verschwenkt, das zwischen den
Förderetagen 21,22 ein Öffnungswinkel entsteht.To unload the now finished pressed
Der zu erreichende Öffnungswinkel zwischen den beiden
Förderetagen 21,22 ist dabei so groß zu wählen, daß alle
Punkte der unteren Förderetage 22 problemlos erreichbar sind,
d.h. daß ein Entladen der unteren Förderetage 22 problemlos
erfolgen kann.The opening angle to be achieved between the two
Die Entladestation 5 wird in diesem Ausführungsbeispiel auf
manuelle Art entladen, dabei werden zunächst die auf der
oberen Förderetage 21 liegenden fertiggepreßten
Furnierchargen 15c entladen, dann nach Verschwenken der
Förderetagen 21,22 werden die auf der unteren Förderetage 22
liegenden Furnierchargen 15c entladen.The unloading
Eine der oben beschriebenen, umgekehrte Vorgehensweise ist
aber genauso denkbar, wie ein gleichzeitiges Entladen beider
Förderetagen 21,22, im ausgeschwenkten Zustand.One of the reverse procedures described above is
but just as conceivable as unloading both at the same
Da sowohl die Förderetagen 6,7 der Beladestation 4 sowie die
Etagen 23,24,25,26 der Preßstationen 2,3 stets gefüllt sind,
d.h. nicht leer stehen, ist ein kontinuierlicher
Produktionsablauf der erfindungsgemäßen Durchlaufpresse 1
sichergestellt, eine vernachlässigbar geringe
Maschinenstandzeit der Preßstation 2,3 ist somit zu jeder
Zeit gegeben, ein hoher Durchsatz an zu verarbeitenden
Furnierchargen 15 ist ebenfalls durch den Einsatz der
erfindungsgemäßen Durchlaufpresse gewährleistet.Since both the funding days 6.7 of the
Eine Weiterentwicklung der erfindungsgemäßen Durchlaufpresse
1 durch Aufstocken von einem bzw. mehreren Förderetagen an
der Beladestation 4 und an der Entladestation 5 sowie
Aufstocken von einem bzw. mehreren Förderbändern und
Preßetagen an den Preßstationen 2,3 ist aber genauso denkbar
wie möglich.A further development of the continuous press according to the invention
1 by increasing one or more funding days
the
Aufgrund der erfindungsgemäßen Ausgestaltung ist es bei der
erfindungsgemäßen Durchlaufpresse 1 möglich, die einzelnen
Stationen, insbesondere die Preßstationen 2 und 3
kontinuierlich zu beschicken.Because of the configuration according to the invention, it is in the
Continuous press 1 according to the invention possible, the individual
Stations, in particular the
Ein derartige kontinuierliche Beschickung kann derart
vorgenommen werden, daß die, in die Pressen 2,3
einzuführenden Chargen zunächst einmal in die Beladestation 4
eingebracht werden, um dann, wie zuvor beschrieben, in die
erste Arbeitsstation, d.h. Preßstation 2, verbracht zu
werden.Such a continuous feed can be such
be made that in the presses 2.3
batches to be imported first into the
Während des Preßvorganges kann nun die Beladestation 4 erneut
mit, in die Preßstation 2 zu verbringenden Chargen beschickt
werden.During the pressing process, the
Nach Beendigung des Preßvorganges in der Preßstation 2 wird
dann die, in der Preßstation 2 befindliche Charge,
entsprechend einer vorgegebenen Länge wie z.B. entsprechend
der Länge der in der Beladestation 4 befindlichen zu
bearbeitenden Materialen weitertransportiert, wobei dies z.B.
derart vorgenommen werden kann, daß die bereits in die
Preßstation 2 verbrachte Charge dort ganz oder teilweise
verbleibt, während die, in der Beladestation 4 vorhandene
Charge bereits in die Preßstation 2 verbracht wird, d.h. es
befinden sich dann in der Preßstation 2 zwei zu bearbeitende
Chargen, wobei die zuerst eingebrachte Charge noch in Gänze
oder auch nur teilweise in der ersten Preßstation 2 vorhanden
sein kann.After completion of the pressing process in the
Nunmehr werden die in der Preßstation 2 befindlichen Chargen
erneut bzw. einem ersten Preßvorgang unterzogen.Now the batches located in the
Nach Beendigung des Preßvorganges wird die in der Preßstation
2 vorhandene Charge bzw. die in der Preßstation vorhandenen
Chargen weitertransportiert und erneutes Material in die
Preßstation 2 aus der Beladestation 4 verbracht, wobei die zu
bearbeitenden Chargen unmittelbar hintereinander angeordnet
werden.After the pressing process is completed, the
Bei entsprechender Weiterverbringung gelangt nun die erste
der, in die Preßstation 2 eingebrachten Chargen in die zweite
Preßstation 3, wobei es durchaus denkbar ist, daß ein Teil
des zu bearbeitenden Materials noch mit seinem, der ersten
Preßstation 2 zugewandten Ende in dieser verbleibt.If it is forwarded appropriately, the first one arrives
of the batches introduced into the
Durch die zuvor beschriebene Arbeitsweise ist eine
kontinuierliche Pressung der Materialien möglich, d.h. es
durchläuft ständig unmittelbar aneinander angrenzendes
Material die Preßstationen 2 und 3, wobei es dabei durchaus
denkbar ist, daß das zu bearbeitende Material sowohl bereits
teilweise in der ersten Preßstation 2 als auch noch in der
Beladestation 4 während des Preßvorganges angeordnet ist,
ebenso ist es denkbar, daß die zweite Preßstation 3
verlassendes Material bereits teilweise in der
Entnahmestation 5 wie auch in der zweiten Preßstation 3
während des Preßvorganges der Preßstation 3 verbleibend
angeordnet ist.Due to the way of working described above is a
continuous pressing of the materials possible, i.e. it
continuously runs directly adjacent to one another
Material the
Durch die erfindungsgemäße Ausgestaltung der Gesamtanlage mit
der Beladestation 4 der ersten Preßstation 2 der zweiten
Preßstation 3 und der Entnahmestation 5, ist eine
kontinuierliche Bearbeitung des zu pressenden Materials, z.B.
unabhängig von der Länge der einzelnen Chargen gewährleistet. Due to the inventive design of the entire system
the
Die Anordnung, d.h. Stellung des Materials, während des Preßvorganges hängt dabei von der Länge der Preßstationen und der Länge des zu bearbeitenden Materials ab.The arrangement, i.e. Position of the material during the Pressing process depends on the length of the press stations and the length of the material to be processed.
Aufgrund der Ausgestaltung der Be- und Entladestation 4,5 ist
es möglich, Material in den Preßstationen 2,3 zu bearbeiten,
während es noch teilweise in der Belade- oder teilweise
bereits in der Entnahmestation 4,5 angeordnet ist.Due to the design of the loading and unloading station 4.5
it is possible to process material in the
Claims (18)
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE19712319 | 1997-03-24 | ||
DE1997112319 DE19712319A1 (en) | 1997-03-24 | 1997-03-24 | Continuous press |
Publications (2)
Publication Number | Publication Date |
---|---|
EP0867272A2 true EP0867272A2 (en) | 1998-09-30 |
EP0867272A3 EP0867272A3 (en) | 1998-12-09 |
Family
ID=7824445
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP97115067A Withdrawn EP0867272A3 (en) | 1997-03-24 | 1997-08-30 | Continuous press |
Country Status (2)
Country | Link |
---|---|
EP (1) | EP0867272A3 (en) |
DE (1) | DE19712319A1 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US8915278B2 (en) | 2011-05-04 | 2014-12-23 | Raute Oyj | Press apparatus for wood products |
DE102017007327A1 (en) * | 2017-08-04 | 2019-02-07 | Hanse Haus Gmbh & Co. Kg | Apparatus and method for producing a component to be glued, in particular a component of a prefabricated house |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE102019113686B4 (en) * | 2019-02-22 | 2024-04-25 | Wooden-3D-Tubing UG (haftungsbeschränkt) | Method and device for producing a wooden profile |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE1230544B (en) * | 1960-04-25 | 1966-12-15 | Heinrich Wemhoener K G Maschin | Loading device with support tables arranged one above the other on its chassis and provided with pushing elements for the preferably wooden workpieces |
FR2309330A1 (en) * | 1975-04-28 | 1976-11-26 | Fahrni Peter | LIFTING AND LOWERING DEVICE FOR RAW FEEDING A MULTI-STAGE PRESS AND FOR UNLOADING SUPPORTS FOR FEEDING THIS PRESS |
DE2634563B1 (en) * | 1976-07-31 | 1978-02-02 | Siempelkamp Gmbh & Co | Device for charging multi-level units in the course of the production of wood-based panels |
FR2511217A1 (en) * | 1981-08-07 | 1983-02-11 | Darragon Cie Ets E | AUTOMATIC TOOL LOADING AND UNLOADING SYSTEM FOR A MULTI-STAGE PRESS, IN PARTICULAR A MULTI-LAYER PRINTED LAMINATE PRESS |
-
1997
- 1997-03-24 DE DE1997112319 patent/DE19712319A1/en not_active Withdrawn
- 1997-08-30 EP EP97115067A patent/EP0867272A3/en not_active Withdrawn
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE1230544B (en) * | 1960-04-25 | 1966-12-15 | Heinrich Wemhoener K G Maschin | Loading device with support tables arranged one above the other on its chassis and provided with pushing elements for the preferably wooden workpieces |
FR2309330A1 (en) * | 1975-04-28 | 1976-11-26 | Fahrni Peter | LIFTING AND LOWERING DEVICE FOR RAW FEEDING A MULTI-STAGE PRESS AND FOR UNLOADING SUPPORTS FOR FEEDING THIS PRESS |
DE2634563B1 (en) * | 1976-07-31 | 1978-02-02 | Siempelkamp Gmbh & Co | Device for charging multi-level units in the course of the production of wood-based panels |
FR2511217A1 (en) * | 1981-08-07 | 1983-02-11 | Darragon Cie Ets E | AUTOMATIC TOOL LOADING AND UNLOADING SYSTEM FOR A MULTI-STAGE PRESS, IN PARTICULAR A MULTI-LAYER PRINTED LAMINATE PRESS |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US8915278B2 (en) | 2011-05-04 | 2014-12-23 | Raute Oyj | Press apparatus for wood products |
DE102017007327A1 (en) * | 2017-08-04 | 2019-02-07 | Hanse Haus Gmbh & Co. Kg | Apparatus and method for producing a component to be glued, in particular a component of a prefabricated house |
Also Published As
Publication number | Publication date |
---|---|
DE19712319A1 (en) | 1998-10-01 |
EP0867272A3 (en) | 1998-12-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE2527035B2 (en) | Device for stacking boards made of cardboard or the like | |
DE4320863B4 (en) | Plant in a parcel-forming center for stacking several bundles of sheets or similar flat units, e.g. Books, packages | |
DE2612206C2 (en) | Liftable and lowerable molding loading and emptying device for press supports for a multi-daylight press | |
DE69107828T2 (en) | Assembling device. | |
DE2547149B2 (en) | Stacking device for loading a multi-stage press | |
DE69210703T2 (en) | Fluid-using device for performing nested alignment of objects with a round cross-section | |
DE69921268T2 (en) | Device and method for automatic stacking of products on pallets | |
DE2547803B2 (en) | Method and device for removing workpieces from a cutting press | |
EP0867272A2 (en) | Continuous press | |
DE69621886T2 (en) | DEVICE AND METHOD FOR PRODUCING WORKPIECES | |
DE3934030A1 (en) | CONVEYOR DEVICE FOR LARGE WORKPIECES | |
DE4301569A1 (en) | Workpiece transporting jig changeover system for press - has robot mounted on press and inclined hoist moving box of jigs into path of workpiece and fixing device on end of robot for transporting jigs | |
AT377495B (en) | DEVICE FOR DISTRIBUTING AND STACKING CUTS IN COLORING PLANTS | |
DE3105237C2 (en) | Plant for the production of tempered chipboard, fiberboard and the like. | |
DE2852456C2 (en) | Device for on and off panels in the manufacture of laminated panels | |
DE2619156C2 (en) | Device for unloading pallets in layers | |
EP0822739B1 (en) | Automated apparatus for printed circuit board inspection | |
DE1729441C3 (en) | Drying chamber with stackable item carriers for drying elongated, layered items made of wood | |
EP3397435A1 (en) | Method and device for laying veneer panels | |
DE3635134C2 (en) | ||
DE2046054B2 (en) | Device for feeding plate blanks | |
DE2226897C3 (en) | Forming and pressing line for the manufacture of chipboard | |
DE4124291A1 (en) | Loading/unloading feed for machine processing station - operates from only one side using single conveyor with upper and lower runs | |
DE19832754A1 (en) | Kiln installation for ceramic goods includes a shunt line which runs parallel to the kiln wagon line between the loading and unloading stations, and is provided with transport and transfer facilities for ceramic goods | |
DE3401233C2 (en) |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
AK | Designated contracting states |
Kind code of ref document: A2 Designated state(s): AT BE CH DE DK ES FI FR GB IE IT LI NL PT SE |
|
AX | Request for extension of the european patent |
Free format text: AL;LT PAYMENT 980307;LV PAYMENT 980307;RO;SI PAYMENT 980307 |
|
PUAL | Search report despatched |
Free format text: ORIGINAL CODE: 0009013 |
|
AK | Designated contracting states |
Kind code of ref document: A3 Designated state(s): AT BE CH DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE |
|
AX | Request for extension of the european patent |
Free format text: AL;LT PAYMENT 980307;LV PAYMENT 980307;RO;SI PAYMENT 980307 |
|
17P | Request for examination filed |
Effective date: 19990223 |
|
AKX | Designation fees paid |
Free format text: AT BE CH DE DK ES FI FR GB IE IT LI NL PT SE |
|
AXX | Extension fees paid |
Free format text: LT PAYMENT 19980307;LV PAYMENT 19980307;SI PAYMENT 19980307 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN |
|
18D | Application deemed to be withdrawn |
Effective date: 20020301 |