EP0154208A1 - Shield driving method for making concrete lining cast "in situ" and device therefor - Google Patents
Shield driving method for making concrete lining cast "in situ" and device therefor Download PDFInfo
- Publication number
- EP0154208A1 EP0154208A1 EP85101461A EP85101461A EP0154208A1 EP 0154208 A1 EP0154208 A1 EP 0154208A1 EP 85101461 A EP85101461 A EP 85101461A EP 85101461 A EP85101461 A EP 85101461A EP 0154208 A1 EP0154208 A1 EP 0154208A1
- Authority
- EP
- European Patent Office
- Prior art keywords
- formwork
- shield
- concrete
- annular
- presses
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/06—Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
- E21D9/0621—Shield advancing devices
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/06—Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
- E21D9/0607—Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield being provided with devices for lining the tunnel, e.g. shuttering
Definitions
- the invention relates to a shield driving method for producing an in-situ concrete tube according to the preamble of patent claim 1.
- a shield driving method is known in which the driving shield is provided with an open cutting wheel studded with chisels, which breaks down the ground on the face.
- a concreteite suspension which is kept in the excavation space of the tunnel shield by a compressed air cushion under constant pressure, takes over the constant support of the face.
- the jacking plate is provided with a trailing plate, behind which the in-situ concrete removal is continuously introduced at the same time as the soil is being removed and the driving plate is being advanced.
- a concrete coated with steel fibers is pumped through a sliding front formwork into the circular ring space, the outside of the existing floor, inside a steel moving formwork and the front end, the movable front formwork. If the floor is not stable, the concrete pumped into the annulus under excess pressure supports the floor in its liquid state. The amount of concrete extruded into the formwork is the same Volume increase resulting from pulling the forehead circuit forward.
- the concrete back pressure is controlled by a control system using pressure transducers. Feed presses are provided for advancing the advance shield with a trailing shield, which are supported on the one hand on the feed shield and on the other hand via a pressure ring on the inner casing.
- the forehead formwork is preferred over forehead formwork cylinders, which are connected on the one hand to the forehead formwork and on the other hand to the tunneling shield.
- This known method does not allow reinforcement to be introduced.
- the steel fibers mixed into the concrete instead of the reinforcement are not permitted as real reinforcement and only have the character of an additional surcharge.
- the steel fibers cannot absorb larger tensions, which weakens the concrete produced by the known method in particular because it is produced without joints, that is to say not in sections. Because of the long setting time, an extended internal formwork must be provided, which is also necessary because it has to absorb the pressure of the feed presses supported on it.
- the object of the invention is to provide a method of the type specified at the outset, according to which in-situ concrete pipes consisting of sections and provided with reinforcements can be produced.
- the pressure exerted on the forehead formwork by the feed presses is the last concreted section dewatered, so that the concrete produced by the method according to the invention has great strength even before it hardens because of the low water-cement factor. In the method according to the invention, it is therefore not necessary to wait for the concrete to harden before the face formwork is brought forward and the next section is started to be concreted.
- the concrete can be introduced into the interconnected sections in a simple manner because the concrete can be pumped.
- the shield driving method according to the invention is particularly suitable for reasons in which it is not possible to work with compressed air, for example for highly permeable gravel with little overlap and low water pressure.
- the method according to the invention can also be carried out in soils above the water level.
- the forehead formwork is expediently set in vibration during the pressure drainage.
- the drainage process can be improved and accelerated and the amount of water extracted can be increased.
- the inner formwork it is equipped with conventional vibrators.
- the dewatering process can also be supported in that a vacuum is applied to the concrete to be pressed or pressed.
- a vacuum is applied to the water drain opening in a conventional manner, the openings being closed by filters.
- the formwork shield that forms the outer formwork can also be pulled out during pressing and dewatering. Concrete is expediently pumped into the freed annular space while the formwork shield is being pulled forward. This pumped-in concrete then fills the annular space between the concrete pipe and the surrounding floor as well as any voids that may still be present.
- the lower limit of the compression pressure for the concrete can be about 3 bar or even lower. The pressure of the pumped concrete is chosen according to the local conditions.
- a suspension or other suitable hardening support compound can be injected into the annular space between the concrete tube and the surrounding concrete, which prevent the soil from falling down.
- a first embodiment of a device for carrying out the method according to the invention is the subject of claim 8.
- the pressure drainage is carried out, if necessary, by advancing the tunneling shield, so that the entire compressive force required to advance the tunneling shield is introduced into the concrete tube.
- the tunneling shield has been driven a distance that the concrete If a new section is permitted, the front formwork is retightened.
- the reinforcement is installed and the formwork is closed by moving the ring-shaped formwork elements of the last formwork ring to the front and attaching the face formwork.
- the concrete is then pumped in and there is a renewed pressure drainage by advancing the tunneling shield. Concrete can be pressed in during the shield driving, which fills the annular space between the concrete pipe and the surrounding floor after pulling the shield tail forming the formwork shield.
- a second embodiment of a device for carrying out the method according to the invention is the subject of claim 9.
- the propulsion shield is propelled by the presses arranged between it and the support ring, the support force being introduced into the face formwork ring via the second group of presses, so that this acts on the concrete pipe.
- the support ring can be retightened with the formwork shield through the first presses, whereby the required dewatering pressure can still be exerted on the concrete tube via the second presses.
- the front formwork ring is also pulled over the second presses, so that a section to be newly concreted can be formed.
- the length of the tail of the formwork shield depends on the local conditions.
- the formwork sign should be made longer. If the length of the formwork shield is shorter, the annular space formed by tightening the formwork shield can be filled by pumping concrete under pressure.
- This second embodiment of the device has the advantage over the first that the required drainage pressure on the face formwork can be maintained even when the formwork shield is being tightened. If necessary, the jacking plate can also be driven independently of having to retighten the formwork plate. However, no advance can take place during the installation of the reinforcement and during the conversion of the formwork elements from the back to the front.
- a third embodiment of a device for carrying out the method according to the invention is the subject of claim 10.
- the pressure required for drainage is exerted on the concreted tube via the face formwork.
- the additional pressure required for the feed is introduced via the parallel group of presses into the formwork elements forming the inner formwork, which are to be anchored accordingly.
- the inner formwork elements can be made lighter because they no longer have to absorb the full hydrostatic internal pressure of the pressed concrete resulting from the feed pressure forces.
- the second, parallel-connected group of hydraulic presses can also be provided with an inner formwork forming a sliding formwork ring are connected, so that concreting the concrete tube in the slipform process is possible if special reinforcement of the concrete tube is not required.
- the formwork elements can be provided with a large number of small bores or openings. It is also possible to provide drainage openings that are secured by filters.
- the end formwork ring is provided with axial bores through which rod-shaped longitudinal reinforcing steel can be inserted. This gives the concrete pipe, which is concreted in sections, greater shear strength in the joints.
- Vacuum lances for additional suction of water can also be inserted through the axial openings in the front formwork.
- the resulting holes are then pegged with reinforcing steel.
- the driving shield 1 shown in FIG. 1 has a cutting edge 2 serving as a guide at its front end.
- the shield tail of the tunneling shield is integrally connected to the formwork shield 3, which forms its extension, as it were.
- the formwork shield 3 forms the outer formwork for the tunnel tube concreted in sections 4.
- the inner formwork 5 consists of ring-shaped formwork elements, of which each formwork ring has a length corresponding to the section to be concreted. A large number of formwork rings are provided so that the concrete tunnel tube is supported by them until they have hardened sufficiently.
- the piston rods are distributed over the inner circumference of the formwork shield 1; ten presses 6 hinged to the front area of the formwork shield 1.
- the rear ends of the cylinders of the hydraulic presses 6 are supported on the end formwork 7 via an articulated connection, which consists of a ring, the width of which corresponds to the thickness of the wall of the tunnel tube.
- the presses 6 are supported via the front formwork 7 on the last section 4 of the concreted tunnel tube.
- the formworks are provided with suitable openings or holes so that the last concrete section is drained in a relatively short time.
- the time required to drive the driving shield 1 is in any case longer than the time of the pressure drainage of the last concreted section 4, by means of which this section is so strong that the front formwork can be removed for concreting the next section.
- the front formwork ring 7 is retightened by the press 6. The reinforcement is then installed and the formwork elements of the last formwork ring are moved forward. As soon as the formwork is closed by the front formwork ring 7, concrete can be pumped into it for concreting the prepared section through the nozzle 8 of the front inner formwork ring.
- the annular space 9 between the concrete sections and the surrounding floor must be filled with concrete or a suspension after the tail of the formwork shield has been pulled free.
- the annular space can be filled with pumped-in concrete, if necessary, while pushing the formwork tail forward.
- the tail of the driving shield 1 extends telescopically over the front area of the formwork shield 3.
- the formwork shield 3 is connected to a front support ring 9. Between the support ring 9 and the front area of the tunneling shield 1 on the one hand and the support ring 9 and the front formwork 7 on the other hand, groups of presses 10, 11 are arranged in the manner shown.
- the propulsion shield 1 is propelled via the hydraulic presses 10, the supporting force being introduced into the last concreted section 4 via the support ring 9, the hydraulic presses 11 and the front formwork ring 7.
- the support ring 9 is advanced by a section length in the manner evident from the lower half of FIG. 2 by the press 10, whereby by the Hydraulic presses 10 the pressure required for pressure drainage is exerted on the end formwork ring 7: Subsequently, the end formwork ring 7 is pulled forward by a section length by the presses 11, so that the formwork for the new one is brought in by inserting the reinforcement and moving the last formwork ring concrete section can be prepared.
- FIG. 3 differs from that of FIG Fig. 2 essentially only in that a further group of parallel presses 13 is mounted on the support ring 9 on an inner ring surface concentric to the presses 11, the other ends of which are supported in the manner shown on the end face of the annular formwork elements 5.
- This device has the advantage that all the pressure required for advancing the tunneling shield does not have to be introduced into the last concreted section via the face formwork 7. If large feed forces are required, a large hydrostatic pressure builds up in the last concreted section, which causes strong and oversized formwork elements of the inner formwork for normal requirements.
- the pressure resulting from the advancing force of the jacking plate can be divided so that the presses 11th exert only the pressure required for pressure drainage on the face formwork ring 7, while the remaining pressure is introduced into the inner formwork rings, which have great rigidity in the axial direction.
- the formwork elements 5 of the ring-shaped inner formwork must be anchored so that they can absorb the feed pressure.
- the formwork elements can be provided on their inner side with rib-like or ring-like projections 14, with which they engage in a toothed manner in the concrete sections 4.
- This type of positive connection of the inner formwork rings with the concreted sections 4 also has the additional advantage that tensile forces can be transmitted to the inner formwork via the presses 13, which is necessary, for example, if this is required for advancing the jacking plate Pressure is less than the pressure on the forehead formwork required for the pressure drainage of the last concreted section.
Abstract
Description
Die Erfindung betrifft ein Schildvortriebsverfahren zur Herstellung einer Ortbetonröhre nach dem Oberbegriff des Patentanspruchs 1.The invention relates to a shield driving method for producing an in-situ concrete tube according to the preamble of
Auf Seite 37 der Veröffentlichung "Saubere Gewässer erfordern Milliarden" von Rolf Bielecki ist ein Schildvortrieb unter Druckluft mit Ortbetonröhre aus Colcrete-Beton beschrieben worden, bei dem der Vortriebsschild mit einem Schildschwanz versehen ist und bei dem ein zwischen dem äußeren dünnen Stahlblechmantel des Schildschwanzes und einer inneren Stahlübbingschalung eingebrachtes Grobkorngerüst nachträglich mit Zement vermörtelt wird. Bei diesem bekannten Verfahren erfolgen wegen des porösen Grobkorngerüsts sämtliche Arbeitsvorgänge, auch die Herstellung des Betons, unter Druckluft. Bei diesem bekannten Verfahren bereitet insbesondere wegen der zuvor eingebrachten Bewehrung das Einfüllen des Grobkorngerüsts Schwierigkeiten. Dieses muß überwiegend manuell zwischen den Schildschwanz und die Innenschalung eingebracht und durch zusätzliche Maßnahmen verdichtet werden, bevor der Ringraum durch die Stirnschalung geschlossen und das Grobkorngerüst durch die auf diese abgestützten Vorschubpressen endgültig verdichtet wird. Wegen des großen Anteils an manueller Arbeit bleibt das bekannte Verfahren auf lichte Durchmesser bis etwa 2,50 m beschränkt und es lassen sich nur mittlere Rohbauleistungen von 3 m/Tag im Mehrschichtenbetrieb erreichen.On page 37 of the publication "Clean waters require billions" by Rolf Bielecki a shield drive under compressed air with in-situ concrete tube made of Colcrete-concrete was described, in which the drive shield is provided with a shield tail and in which one between the outer thin sheet steel jacket of the shield tail and one the coarse-grained scaffold in the inner steel lining formwork is subsequently mortared with cement. In this known method, because of the porous coarse grain structure, all work processes, including the production of the Concrete, under compressed air. In this known method, the filling of the coarse grain structure is particularly difficult because of the reinforcement previously introduced. This must predominantly be manually inserted between the shield tail and the inner formwork and compacted by additional measures before the annular space is closed by the face formwork and the coarse grain structure is finally compacted by the feed presses supported on it. Because of the large proportion of manual work, the known method is limited to clear diameters of up to approximately 2.50 m and only average shell work of 3 m / day can be achieved in multi-shift operation.
Aus der Veröffentlichung der Firma HOCHTIEF "Extrudierter Ort- - betonausbau-mit Zusatz von Stahlfasern hinter einem Betonitschild" ist ein Schildvortriebsverfahren bekannt, bei dem der Vortriebsschild mit einem mit Meißeln besetzten offenen Schneidrad versehen ist, das an der Ortsbrust den Boden abbaut. Dabei übernimmt eine Betonitsuspension, die im Abbauraum des Vortriebsschildes durch ein Druckluftpolster unter konstantem Druck gehalten wird, die ständige Stützung der Ortsbrust. Der Vortriebsschild ist mit einem Nachlaufschild versehen, hinter dem gleichzeitig mit dem Abbau des Bodens und dem Vorschub des Vortriebsschildes der Ortbetonausbau kontinuierlich eingebracht wird. Da dieses Verfahren das Einbringen einer Bewehrung nicht ermöglicht, wird ein mit Stahlfasern gemichter Beton durch eine gleitende Stirnschalung in den kreisförmigen Ringraum gepumpt, den außen der anstehende Boden, innen eine stählerne Umsetzschalung und als vorderer Abschluß die bewegliche Stirnschalung begrenzt. Bei nicht standfestem Boden stützt der unter Überdruck in den Ringraum gepumpteBeton bereits im flüssigen Zustand den Boden ab. Dabei gleicht die in die Schalung extrudierte Betonmenge den Volumenzuwachs aus, der durch das Vorziehen der Stirnschaltung entsteht. Der Betond-r-uck wird durch ein Regelsystem mittels Druckmeßdosen gesteuert. Zum Vorschub des Vortriebsschildes mit Nachlaufschild sind Vorschubspressen vorgesehen, die sich einerseits auf dem Vorschubschild und andererseits über einen Druckring auf der Innenverschalung abstützen. Die Stirnschalung wird über Stirnschalungszylinder vorgezogen, die einerseits mit der Stirnschalung und andererseits mit dem Vortriebsschild verbunden sind. Dieses bekannte Verfahren gestattet es nicht, eine Bewehrung einzubringen. Die statt der Bewehrung dem Beton zugemischten Stahlfasern sind als echte Bewehrung nicht zugelassen und haben lediglich den Charakter eines zusätzlichen Zuschlags. Die Stahlfasern können größere Spannungen nicht aufnehmen, was den nach dem bekannten Verfahren hergestellten Beton besonders deshalb schwächt, weil dieser ohne Fugen, also nicht abschnittweise, hergestellt ist. Wegen der langen Abbindungszeit muß eine verlängerte Innenschalung vorgesehen werden, die auch deshalb erforderlich ist, weil sie den Druck der auf dieser abgestützten Vorschubpressen aufnehmen muß.From the publication of the HOCHTIEF company "Extruded site - - concrete lining - with the addition of steel fibers behind a concrete shield" a shield driving method is known in which the driving shield is provided with an open cutting wheel studded with chisels, which breaks down the ground on the face. A concreteite suspension, which is kept in the excavation space of the tunnel shield by a compressed air cushion under constant pressure, takes over the constant support of the face. The jacking plate is provided with a trailing plate, behind which the in-situ concrete removal is continuously introduced at the same time as the soil is being removed and the driving plate is being advanced. Since this method does not allow the introduction of reinforcement, a concrete coated with steel fibers is pumped through a sliding front formwork into the circular ring space, the outside of the existing floor, inside a steel moving formwork and the front end, the movable front formwork. If the floor is not stable, the concrete pumped into the annulus under excess pressure supports the floor in its liquid state. The amount of concrete extruded into the formwork is the same Volume increase resulting from pulling the forehead circuit forward. The concrete back pressure is controlled by a control system using pressure transducers. Feed presses are provided for advancing the advance shield with a trailing shield, which are supported on the one hand on the feed shield and on the other hand via a pressure ring on the inner casing. The forehead formwork is preferred over forehead formwork cylinders, which are connected on the one hand to the forehead formwork and on the other hand to the tunneling shield. This known method does not allow reinforcement to be introduced. The steel fibers mixed into the concrete instead of the reinforcement are not permitted as real reinforcement and only have the character of an additional surcharge. The steel fibers cannot absorb larger tensions, which weakens the concrete produced by the known method in particular because it is produced without joints, that is to say not in sections. Because of the long setting time, an extended internal formwork must be provided, which is also necessary because it has to absorb the pressure of the feed presses supported on it.
Aufgabe der Erfindung ist es, ein Verfahren der eingangs angegebenen Art zu schaffen, nach dem sich in wirtschaftlicher Weise aus Abschnitten bestehende und mit Bewehrungen versehene Ortbetonröhren herstellen lassen.The object of the invention is to provide a method of the type specified at the outset, according to which in-situ concrete pipes consisting of sections and provided with reinforcements can be produced.
Erfindungsgemäß wird diese Aufgabe bei einem Verfahren der gattungsgemäßen Art durch die kennzeichnenden Merkmale des Patentanspruchs 1 gelöst.According to the invention, this object is achieved in a method of the generic type by the characterizing features of
Bei dem erfindungsgemäßen Verfahren wird durch den durch die Vorschubpressen auf die Stirnschalung ausgeübten Druck der zuletzt betonierte Abschnitt entwässert, so daß der nach dem erfindungsgemäßen Verfahren hergestellte Beton wegen des niedrigen Wasser-Zement-Faktors eine große Festigkeit bereits auch vor seinem Aushärten aufweist. Bei dem erfindungsgemäßen Verfahren muß also nicht das Aushärten des Betons abgewartet werden, bevor die Stirnschalung vorgezogen und mit dem Betonieren des nächsten Abschnitts begonnen wird.In the method according to the invention, the pressure exerted on the forehead formwork by the feed presses is the last concreted section dewatered, so that the concrete produced by the method according to the invention has great strength even before it hardens because of the low water-cement factor. In the method according to the invention, it is therefore not necessary to wait for the concrete to harden before the face formwork is brought forward and the next section is started to be concreted.
Das Einbringen des Betons in die verschalten Abschnitte läßt sich in einfacher Weise durchführen, weil der Beton gepumpt werden kann.The concrete can be introduced into the interconnected sections in a simple manner because the concrete can be pumped.
Das erfindungsgemäße Schildvortriebsverfahren eignet sich besonders für Gründe, in denen nicht mit Druckluft gearbeitet werden kann, beispielsweise für stark durchlässige Kiese mit geringer Überdeckung und geringem Wasserdruck. Das erfindungsgemäße Verfahren kann auch in Böden oberhalb des Wasserspiegels durchgefährt werden.The shield driving method according to the invention is particularly suitable for reasons in which it is not possible to work with compressed air, for example for highly permeable gravel with little overlap and low water pressure. The method according to the invention can also be carried out in soils above the water level.
Zweckmäßigerweise wird die Stirnschalung während der Druckentwässerung in Vibration versetzt. Durch dieses Vibrieren der Innenschalung läßt sich der Entwässerungsvorgang verbessern und beschleunigen und die entzogene Wassermenge erhöhen. Zum Zwecke des Vibrierens der Innenschalung wird diese mit üblichen Vibratoren ausgerüstet.The forehead formwork is expediently set in vibration during the pressure drainage. By vibrating the inner formwork, the drainage process can be improved and accelerated and the amount of water extracted can be increased. For the purpose of vibrating the inner formwork, it is equipped with conventional vibrators.
Der Entwässerungsvorgang kann auch dadurch unterstützt werden, daß an den zu verpressenden oder verpreßten Beton ein Unterdruck angelegt wird. Zum Erzeugen-des Unterdrucks wird an die Wasserabzugsöffnung in üblicher Weise ein Vakuum angelegt, wobei die Öffnungen durch Filter geschlossen werden.The dewatering process can also be supported in that a vacuum is applied to the concrete to be pressed or pressed. In order to generate the negative pressure, a vacuum is applied to the water drain opening in a conventional manner, the openings being closed by filters.
Der die Außenschalung bildende Schalungsschild kann auch während des Verpressens und Entwässerns vorgezogen werden. Dabei wird zweckmäßigerweise während des Vorzeihens des Schalungsschildes gleichzeitig Beton in den freiwerdenden Ringraum eingepumpt. Dieser eingepumpte Beton füllt sodann den Ringraum zwischen der betonierten Röhre und dem umgebenden Boden sowie eventuell noch vorhandene Hohlräume aus. Die Untergrenze des Preßdrucks für den Beton kann etwa 3 bar betragen oder noch niedriger sein. Der Druck des eingepumpten Betons wird entsprechend den örtlichen Gegebenheiten gewählt.The formwork shield that forms the outer formwork can also be pulled out during pressing and dewatering. Concrete is expediently pumped into the freed annular space while the formwork shield is being pulled forward. This pumped-in concrete then fills the annular space between the concrete pipe and the surrounding floor as well as any voids that may still be present. The lower limit of the compression pressure for the concrete can be about 3 bar or even lower. The pressure of the pumped concrete is chosen according to the local conditions.
Es ist auch möglich, eine Entwässerung nur im Bereich der Stirnschalung vorzunehmen. Versuche haben gezeigt, daß eine ausreichende Grünstandfestigkeit des Betons auch dann erreicht wird, wenn nur der vordere Bereich entwässert wird. Beispielsweise ist es möglich, bei betonierten Abschnittlängen von 3 bis 4 Meter nur die ersten 1 bis 2 Meter zu entwässern.It is also possible to drain only in the area of the forehead formwork. Tests have shown that the concrete has sufficient green stability even if only the front area is drained. For example, with concrete section lengths of 3 to 4 meters, it is possible to drain only the first 1 to 2 meters.
Nach dem Vorziehen des Schalungsschildes kann in den Ringraum zwischen der Betonröhre und den umgebenden Beton eine Suspension oder eine andere geeignete aushärtende Stützmasse eingespritzt werden, die ein Nachfallen des Erdreichs verhindern.After the formwork shield has been pulled forward, a suspension or other suitable hardening support compound can be injected into the annular space between the concrete tube and the surrounding concrete, which prevent the soil from falling down.
Eine erste Ausführungsform einer Vorrichtung zur Durchführung des erfindungsgemäßen Verfahrens ist Gegenstand des Patentanspruchs 8. Bei dieser Vorrichtung erfolgt die Druckentwässerung gegebenenfalls unter Vorschub des Vortriebsschildes, so daß die gesamte zum Vorschub des Vortriebsschildes erforderliche Druckkraft in die Betonröhre eingeleitet wird. Nachdem der Vortriebsschild um eine Strecke vorgetrieben worden ist, die die Betonierung eines neuen Abschnitts erlaubt, wird die Stirnschalung nachgezogen. Anschließend wird die Armierung eingebaut und die Schalung durch Umsetzen der ringförmigen Schalungselemente des letzten Schalungsringes nach vorn und Aufsetzen der Stirnschalung geschlossen. Sodann wird der Beton eingepumpt und es erfolgt eine erneute Druckentwässerung durch Vorschieben des Vortriebsschildes. Während des Schildvortriebs kann Beton nachgepreßt werden, der den Ringraum zwischen der betonierten Röhre und den umgebenden Boden nach Vorziehen des den Schalungsschild bildenden Schildschwanzes ausfüllt.A first embodiment of a device for carrying out the method according to the invention is the subject of
Eine zweite Ausführungsform einer Vorrichtung zur Durchführung des erfindungsgemäßen Verfahrens ist Gegenstand des Patentanspruchs 9. Mit dieser Vorrichtung erfolgt der Vortrieb des Vortriebsschildes durch die zwischen diesem und dem Stützring angeordneten Pressen, wobei die Stützkraft über die zweite Gruppe von Pressen in den Stirnschalungsring eingeleitet wird, so daß diese auf die betonierte Betonröhre wirkt. Der Stützring läßt sich mit dem Schalungsschild durch die ersten Pressen nachziehen, wobei über die zweiten Pressen noch immer der erforderliche Entwässerungsdruck auf die Betonröhre ausgeübt werden kann. Nach dem Nachziehen des Stützringes wird über die zweiten Pressen auch der Stirnschalungsring nachgezogen, so daß ein neu zu betonierender Abschnitt eingeschalt werden kann. Die Länge des Schwanzes des Schalungsschildes hängt von den örtlichen Bedingungen ab. Besteht die Gefahr, daß der grünfeste Beton durch Grundwasserströmungen ausgespült werden könnte, ist der Schalungsschild länger auszubilden. Ist die Länge des Schalungsschildes kürzer, kann der durch Nachziehen des Schalungsschildes gebildete Ringraum durch Nachpumpen von Beton unter Druck gefüllt werden.A second embodiment of a device for carrying out the method according to the invention is the subject of
Diese zweite Ausführungsform der Vorrichtung weist gegenüber der ersten den Vorteil auf, daß auch während des Nachziehens des Schalungsschildes der erforderliche Entwässerungsdruck auf der Stirnschalung aufrechterhalten werden kann. Gegebenenfalls ist auch ein Vortrieb des Vortriebsschildes unabhängig von dem Nachziehen des Schalungsschildes möglich. Allerdings kann kein Vortrieb während des Einbaus der Armierung und während des Umbaus der Schalungselemente von hinten nach vorne erfolgen.This second embodiment of the device has the advantage over the first that the required drainage pressure on the face formwork can be maintained even when the formwork shield is being tightened. If necessary, the jacking plate can also be driven independently of having to retighten the formwork plate. However, no advance can take place during the installation of the reinforcement and during the conversion of the formwork elements from the back to the front.
Eine dritte Ausführungsform einer Vorrichtung zur Durchführung des erfindungsgemäßen Verfahrens ist Gegenstand des Patentanspruchs 10. Bei dieser Ausführungsform wird der zur Entwässerung benötigte Druck über die Stirnschalung auf die betonierte Röhre ausgeübt. Der darüber hinausgehende, für den Vorschub benötigte Druck wird über die parallelgeschaltete Gruppe von Pressen in die die Innenschalung bildenden Schalungselemente eingeleitet, die entsprechend zu verankern sind. Die Innenschalungselemente können dadurch leichter ausgestaltet werden, weil sie nicht mehr den vollen, aus den Vorschubdruckkräften resultierenden hydrostatischen Innendruck des verpreßten Betons aufnehmen müssen. Mit der Vorrichtung ist weiterhin während des Vortriebs des Vortriebsschildes eine Armierung des folgenden zu betonierenden Abschnitts nach Vorziehen der Stirnschalung möglich, so daß anschließend der Vortrieb nur für die Zeit unterbrochen werden muß, die für das Umsetzen der Schalung benötigt wird. Die Armierung eines Abschnitts ist zeitaufwendiger als das Umsetzen der Schalung, so daß eine beträchtliche Zeitersparnis möglich ist.A third embodiment of a device for carrying out the method according to the invention is the subject of
Die zweite, parallelgeschaltete Gruppe von hydraulischen Pressen kann auch mit einem eine Gleitschalung bildenden Innenschalungsring verbunden werden, so daß ein Betonieren der Betonröhre im Gleitschalungsverfahren möglich ist, wenn eine besondere Armierung der Betonröhre nicht erforderlich ist.The second, parallel-connected group of hydraulic presses can also be provided with an inner formwork forming a sliding formwork ring are connected, so that concreting the concrete tube in the slipform process is possible if special reinforcement of the concrete tube is not required.
Zur Entwässerung des betonierten Abschnitts können die Schalungselemente mit einer Vielzahl kleiner Bohrungen oder Öffnungen versehen sein. Es ist auch möglich, Entwässerungsöffnungen vorzusehen, die durch Filter gesichert sind.To drain the concrete section, the formwork elements can be provided with a large number of small bores or openings. It is also possible to provide drainage openings that are secured by filters.
In weiterer Ausgestaltung der Erfindung ist vorgesehen, daß der Stirnschalungsring mit axialen Bohrungen versehen ist, durch die stangenförmiger Längsarmierungsstahl eingeführt werden kann. Die abschnittweise betonierte Betonröhre erhält dadurch eine größere Scherfestigkeit in den Fugen.In a further embodiment of the invention it is provided that the end formwork ring is provided with axial bores through which rod-shaped longitudinal reinforcing steel can be inserted. This gives the concrete pipe, which is concreted in sections, greater shear strength in the joints.
Durch die axialen Öffnungen der Stirnschalung können auch Vakuumlanzen zum zusätzlichen Absaugen von Wasser eingeschoben werden. Die sich daraus ergebenden Löcher werden anschließend mit Armierungsstahl verdübelt.Vacuum lances for additional suction of water can also be inserted through the axial openings in the front formwork. The resulting holes are then pegged with reinforcing steel.
Ausführungsbeispiele der Erfindung werden nachstehend anhand der Zeichnung näher erläutert. In dieser zeigt
- Fig. 1 einen Längsschnitt durch den Vortriebsschild mit einstückig mit diesem verbundenen Schalungsschild in schematischer Darstellung während der Druckentwässerung des zuletzt betonierten Tunnelabschnitts,
- Fig. 2 einen Längsschnitt durch eine zweite Ausführungsform eines Vortriebsschildes, der den von diesem getrennt beweglichen Schalungsschild teleskopartig einfaßt, in schematischer Darstellung und
- Fig. 3 einen Längsschnitt einer dritten Ausführungsform eines Vortriebsschildes, bei der der teleskopartig von dem Schwanz des Vortriebsschildes eingefaßte Schaltungs schild über zusätzliche Pressen auf der Innenschalung abstützbar ist.
- 1 shows a longitudinal section through the tunneling shield with a formwork shield integrally connected to it in a schematic representation during the pressure drainage of the last concreted tunnel section,
- Fig. 2 shows a longitudinal section through a second embodiment of a tunneling shield, which telescopically surrounds the formwork shield, which is movable separately therefrom, in a schematic representation and
- Fig. 3 is a longitudinal section of a third embodiment of a jacking shield, in which the telescopically enclosed by the tail of the jacking shield circuit board can be supported by additional presses on the inner formwork.
Der in Fig. 1 dargestellte Vortriebsschild 1 weist an seinem vorderen Ende eine der Führung dienende Schneide 2 auf. Der Schildschwanz des Vortriebsschildes ist einstückig mit dem Schalungsschild 3 verbunden, der gleichsam dessen Verlängerung bildet.The driving
Der Schalungsschild 3 bildet die Außenschalung für die in Abschnitten 4 betonierte Tunnelröhre. Die Innenschalung 5 besteht aus ringförmigen.Schalungselementen, von denen jeder Schalungsring eine dem jeweils zu betonierenden Abschnitt entsprechende Länge aufweist. Dabei ist eine so große Anzahl von Schalungsringen vorgesehen, daß die betonierte Tunnelröhre von diesen bis zu ihrer ausreichenden Erhärtung gestützt wird.The
Bei der in Fig. 1 dargestellten Vorrichtung sind die Kolbenstangen der über den inneren Umfang des Schalungsschildes 1 verteil- ; ten Pressen 6 an den vorderen Bereich des Schalungsschildes 1 angelenkt. Die hinteren Enden der Zylinder der hydraulischen Pressen 6 stützen sich über eine gelenkige Verbindung auf die Stirnschalung 7 ab, die aus einem Ring besteht, dessen Breite der Dicke der Wandung der Tunnelröhre entspricht.In the device shown in FIG. 1, the piston rods are distributed over the inner circumference of the
Zum Vorschub des Vortriebsschildes 1 stützen sich die Pressen 6 über die Stirnschalung 7 auf den letzten Abschnitt 4 der betonierten Tunnelröhre ab. Die Schalungen sind mit geeigneten Öffnungen oder Löchern versehen, so daß der zuletzt betonierte Abschnitt dadurch in verhältnismäßig kurzer Zeit entwässert wird. Die zum Vortrieb des Vortriebsschildes 1 benötigte Zeit ist in jedem Falle länger als die Zeit der Druckentwässerung des zuletzt betonierten Abschnitts 4, durch die dieser eine so große Festigkeit erhält, daß die Stirnschalung zum Betonieren des nächsten Abschnitts abgenommen werden kann.In order to advance the
Nachdem der Vortriebsschild 1 um eine Abschnittlänge vorgetrieben worden ist, wird durch die Presse 6 der Stirnschalungsring 7 nachgezogen. Anschließend wird die Bewehrung eingebaut und die Schalungselemente des letzten Schalungsringes werden nach vorne versetzt. Sobald die Schalung durch den Stirnschalungsring 7 geschlossen ist, kann in diese zur Betonierung des vorbereiteten Abschnitts durch den Stutzen 8 des vorderen Innenschalungsrin--ges Beton eingepumpt werden.After the
Überdeckt der Schwanz des Schalungsschildes 3 den letzten Abschnitt oder auch vorherige betonierte Abschnitte, mußn der Ringraum 9 zwischen den betonierten Abschnitten und dem umgebenden Boden nach Freiziehen des Schwanzes des Schalungsschildes mit Beton oder einer Suspension verfüllt werden.If the tail of the
Ist der Schwanz des Schalungsschildes relativ kurz, kann der Ringraum gegebenenfalls unter gleichzeitigem Vorschieben des Schalungsschwanzes durch nachgepumpten Beton verfüllt werden.If the tail of the formwork shield is relatively short, the annular space can be filled with pumped-in concrete, if necessary, while pushing the formwork tail forward.
Bei der Vorrichtung nach Fig. 2 übergreift der Schwanz des Vortriebsschildes 1 teleskopartig den vorderen Bereich des Schalungsschildes 3. Der Schalungsschild 3 ist mit einem vorderen Stützring 9 verbunden. Zwischen dem Stützring 9 und dem vorderen Bereich des Vortriebsschildes 1 einerseits und dem Stützring 9 und der Stirnschalung 7 andererseits sind in der dargestellten Weise ringförmig Gruppen von Pressen 10, 11 angeordnet.In the device according to FIG. 2, the tail of the driving
Der Vortrieb des Vortriebsschildes 1 erfolgt über die hydraulischen Pressen 10, wobei die Stützkraft über den Stützring 9, die hydraulischen Pressen 11 und den Stirnschalungsring 7 in den zuletzt betonierten Abschnitt 4 eingeleitet wird.The
Nachdem der Vortriebsschild in der aus der oberen Hälfte der Fig. 2 ersichtlichen Weise um eine Abschnittlänge vorgetrieben worden ist, wird durch die Presse 10 der Stützring 9 in der aus der unteren Hälfte der Fig. 2 ersichtlichen Weise um eine Abschnittlänge vorgezogen, wobei durch die hydraulischen Pressen 10 der zur Druckentwässerung erforderliche Druck auf den Stirnschalungsring 7 ausgeübt wird: Anschließend werden durch die Pressen 11 der Stirnschalungsring 7 um eine Abschnittlänge vorgezogen, so daß in der beschriebenen Weise durch Einbringen der Bewehrung und Umsetzen des letzten Schalungsringes die Schalung für den neu zu betonierenden Abschnitt vorbereitet werden kann.After the tunneling shield has been advanced by a section length in the manner evident from the upper half of FIG. 2, the
Die Vorrichtung nach Fig. 3 unterscheidet sich von der nach Fig. 2 im wesentlichen nur dadurch, daß an dem Stützring 9 auf einer inneren zu den Pressen 11 konzentrischen Ringfläche eine weitere Gruppe paralleler Pressen 13 gelagert ist, deren anderen Enden sich in der dargestellten Weise auf der Stirnfläche der ringförmigen Schalungselemente 5 abstützen. Diese Vorrichtung hat den Vorteil, daß der ganze für den Vorschub des Vortriebsschildes benötigte Druck nicht über die Stirnschalung 7 in den zuletzt betonierten Abschnitt eingeleitet werden muß. Werden nämlich große Vorschubkräfte benötigt, baut sich in dem letzten betonierten Abschnitt ein großer hydrostatischer Druck auf, der starke und für die normalen Anforderungen überdimensionierte Schalungselemente der Innenschalung bedingt. Durch die Parallelschaltung der beiden Gruppen von Pressen 11, 13, von denen sich die äußere Gruppe auf die Stirnschalung 7 und die innere Gruppe auf die Schalungselemente 5 abstützt, kann der sich aus der Vorschubkraft des Vortriebsschildes ergebende Druck so aufgeteilt werden, daß die Pressen 11 auf den Stirnschalungsring 7 nur den zur Druckentwässerung erforderlichen Druck ausüben, während der restliche Druck in die Innenschalungsringe eingeleitet wird, die in axialer Richtung eine große Steifigkeit besitzen.3 differs from that of FIG Fig. 2 essentially only in that a further group of
Die Schalungselemente 5 der ringförmigen Innenschalung müssen verankert werden, damit diese den Vorschubdruck aufnehmen können. Hierzu können die Schalungselemente auf ihrer Innenseite mit rippen- oder ringartigen Vorsprüngen 14 versehen sein, mit denen sie verzahnend in die betonierten Abschnitte 4 greifen. Diese Art der formschlüssigen Verbindung der Innenschalungsringe mit den betonierten Abschnitten 4 hat zusätzlich auch den Vorteil, daß über die Pressen 13 auf die Innenschalung Zugkräfte übertragen werden können, was beispielsweise dann erforderlich ist, wenn der für den Vorschub des Vortriebsschildes benötigte Druck geringer ist als der für die Druckentwässerung des letzten betonierten Abschnitts erforderliche Druck auf die Stirnschalung.The
Claims (18)
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE19843404839 DE3404839A1 (en) | 1984-02-10 | 1984-02-10 | SHIELD DRIVING METHOD FOR PRODUCING A LOCAL CONCRETE PIPE AND DEVICE FOR CARRYING OUT THE METHOD |
DE3404839 | 1984-02-10 |
Publications (1)
Publication Number | Publication Date |
---|---|
EP0154208A1 true EP0154208A1 (en) | 1985-09-11 |
Family
ID=6227406
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP85101461A Withdrawn EP0154208A1 (en) | 1984-02-10 | 1985-02-11 | Shield driving method for making concrete lining cast "in situ" and device therefor |
Country Status (2)
Country | Link |
---|---|
EP (1) | EP0154208A1 (en) |
DE (1) | DE3404839A1 (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2592091A1 (en) * | 1985-12-25 | 1987-06-26 | Shimizu Construction Co Ltd | METHOD OF HORIZONTAL ROUTING USING A SHIELD AND APPARATUS FOR ASSEMBLING AND DISASSEMBLING TUBULAR ASSEMBLIES FOR EXCAVATING GALLERIES |
EP0253051A1 (en) * | 1986-07-08 | 1988-01-20 | Minoru Yamamoto | Method for constructing a tunnel |
EP0483445A1 (en) * | 1989-05-11 | 1992-05-06 | VOEST-ALPINE Bergtechnik Gesellschaft m.b.H | Driving shield |
CN106907156A (en) * | 2017-04-06 | 2017-06-30 | 济南中铁重工轨道装备有限公司 | Multiple edge body tail shield structural member and its group point preparation method |
CN113236264A (en) * | 2021-04-28 | 2021-08-10 | 中铁六局集团有限公司交通工程分公司 | Split starting construction method for shield of small clearance, upper soft and lower hard stratum |
CN116044442A (en) * | 2023-03-31 | 2023-05-02 | 中建交通建设集团有限公司 | Butt joint section structure in shield ground and construction method thereof |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2154463A1 (en) * | 1971-09-27 | 1973-05-11 | Gewerk Eisenhuette Westfalia | |
FR2295218A1 (en) * | 1974-12-19 | 1976-07-16 | Gewerk Eisenhuette Westfalia | METHOD AND DEVICE FOR CONCRETING TUNNELS |
FR2320416A1 (en) * | 1975-08-05 | 1977-03-04 | Gaillard Rene | Tunnelling machine with three telescopic cylinders behind cutting head - has sequentially operated jacks advancing cylinders and head after concrete injection |
FR2330850A1 (en) * | 1975-11-07 | 1977-06-03 | Gewerk Eisenhuette Westfalia | DEVICE AND METHOD FOR DRILLING TUNNELS OR SIMILAR CAVITES BY MEANS OF A SUPPORT SHIELD WITH LAYING OF A CONCRETE COATING |
FR2380413A1 (en) * | 1977-02-15 | 1978-09-08 | Gewerk Eisenhuette Westfalia | PROCESS AND DEVICE FOR DIGGING TUNNELS, GALLERIES AND SIMILAR CELLARS, WITH SIMULTANEOUS LAYING OF A CONCRETE COATING |
FR2443567A1 (en) * | 1978-12-06 | 1980-07-04 | Gewerk Eisenhuette Westfalia | KNIFE SHIELD |
DE2913091A1 (en) * | 1979-04-02 | 1980-10-16 | Gewerk Eisenhuette Westfalia | Tunnel driving and concrete lining system - absorbs driving reaction forces by inner concrete shuttering |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE1206938B (en) * | 1963-04-25 | 1965-12-16 | Hochtief Ag Hoch Tiefbauten | Controllable propulsion shield for driving tunnels, routes or the like, and method for producing an in-situ concrete lining with such a propulsion shield |
DE7614295U1 (en) * | 1976-01-29 | 1978-03-16 | (Belgien) | SHIELD MACHINE WITH A DEVICE FOR PRODUCING A TUNNEL LINING IN IN-SITE CONCRETE |
DE3218643A1 (en) * | 1982-05-18 | 1983-11-24 | Philipp Holzmann AG, Hauptniederlassung Düsseldorf, 4000 Düsseldorf | Method of producing an underground tunnel structure |
-
1984
- 1984-02-10 DE DE19843404839 patent/DE3404839A1/en not_active Ceased
-
1985
- 1985-02-11 EP EP85101461A patent/EP0154208A1/en not_active Withdrawn
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2154463A1 (en) * | 1971-09-27 | 1973-05-11 | Gewerk Eisenhuette Westfalia | |
FR2295218A1 (en) * | 1974-12-19 | 1976-07-16 | Gewerk Eisenhuette Westfalia | METHOD AND DEVICE FOR CONCRETING TUNNELS |
FR2320416A1 (en) * | 1975-08-05 | 1977-03-04 | Gaillard Rene | Tunnelling machine with three telescopic cylinders behind cutting head - has sequentially operated jacks advancing cylinders and head after concrete injection |
FR2330850A1 (en) * | 1975-11-07 | 1977-06-03 | Gewerk Eisenhuette Westfalia | DEVICE AND METHOD FOR DRILLING TUNNELS OR SIMILAR CAVITES BY MEANS OF A SUPPORT SHIELD WITH LAYING OF A CONCRETE COATING |
FR2380413A1 (en) * | 1977-02-15 | 1978-09-08 | Gewerk Eisenhuette Westfalia | PROCESS AND DEVICE FOR DIGGING TUNNELS, GALLERIES AND SIMILAR CELLARS, WITH SIMULTANEOUS LAYING OF A CONCRETE COATING |
FR2443567A1 (en) * | 1978-12-06 | 1980-07-04 | Gewerk Eisenhuette Westfalia | KNIFE SHIELD |
DE2913091A1 (en) * | 1979-04-02 | 1980-10-16 | Gewerk Eisenhuette Westfalia | Tunnel driving and concrete lining system - absorbs driving reaction forces by inner concrete shuttering |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2592091A1 (en) * | 1985-12-25 | 1987-06-26 | Shimizu Construction Co Ltd | METHOD OF HORIZONTAL ROUTING USING A SHIELD AND APPARATUS FOR ASSEMBLING AND DISASSEMBLING TUBULAR ASSEMBLIES FOR EXCAVATING GALLERIES |
EP0253051A1 (en) * | 1986-07-08 | 1988-01-20 | Minoru Yamamoto | Method for constructing a tunnel |
EP0483445A1 (en) * | 1989-05-11 | 1992-05-06 | VOEST-ALPINE Bergtechnik Gesellschaft m.b.H | Driving shield |
CN106907156A (en) * | 2017-04-06 | 2017-06-30 | 济南中铁重工轨道装备有限公司 | Multiple edge body tail shield structural member and its group point preparation method |
CN106907156B (en) * | 2017-04-06 | 2023-11-03 | 济南中铁重工轨道装备有限公司 | Multi-edge tail shield structural member assembly point manufacturing method |
CN113236264A (en) * | 2021-04-28 | 2021-08-10 | 中铁六局集团有限公司交通工程分公司 | Split starting construction method for shield of small clearance, upper soft and lower hard stratum |
CN116044442A (en) * | 2023-03-31 | 2023-05-02 | 中建交通建设集团有限公司 | Butt joint section structure in shield ground and construction method thereof |
CN116044442B (en) * | 2023-03-31 | 2023-06-02 | 中建交通建设集团有限公司 | Butt joint section structure in shield ground and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
DE3404839A1 (en) | 1985-09-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE2240091C2 (en) | Concreting process in connection with the jacking shield or cutting shoe supported on the in-situ concrete and equipment for carrying out the process | |
DE2550050C2 (en) | Device for driving tunnels or the like. by means of a shoring sign with the introduction of an in-situ concrete lining | |
DE3043312A1 (en) | METHOD AND DEVICE FOR DRIVING A SLIDE SHUTTER | |
EP0154208A1 (en) | Shield driving method for making concrete lining cast "in situ" and device therefor | |
DE1206938B (en) | Controllable propulsion shield for driving tunnels, routes or the like, and method for producing an in-situ concrete lining with such a propulsion shield | |
DE2921907A1 (en) | METHOD AND DEVICE FOR LINING A TUNNEL, AN UNDERGROUND DISTANCE OR THE LIKE. WITH CONCRETE | |
DE3521888C2 (en) | ||
DE2544834B2 (en) | PROCEDURE FOR BOLTING DAMPS IN UNSTILL MOUNTAINS AND SHIELD DRIVING DEVICE FOR CARRYING OUT THE PROCEDURE | |
DE2857475C1 (en) | Device and method for the expansion of a tunnel driven in the shield drive | |
DE3407384A1 (en) | Method of producing a tubular underground hollow space, e.g. a traffic tunnel, and apparatus for carrying out the method | |
DE2706244A1 (en) | Tunnel driving system with simultaneous concreting - has segments formed in succession in peripheral direction using internal shuttering only | |
AT522502B1 (en) | Method for placing concrete with a horizontal sliding construction in in-situ concrete construction, device for the production of a horizontal concrete element | |
DE3435724C2 (en) | ||
DE3131559A1 (en) | Method of producing cast-in-situ piles | |
DE2555524C2 (en) | Jacking knife for a shoring shield | |
DE2109384C3 (en) | Method and apparatus for producing tubular tunnels, galleries or the like. in shield driving with a lining made of in-situ concrete | |
DE3520092A1 (en) | Method of producing a tubular underground hollow space, e.g. a traffic tunnel, and apparatus for carrying out the method | |
DE2758489B2 (en) | Process for the production of a pre-stressed ground pile as well as a ground pile manufactured according to the process | |
DE3126651C1 (en) | End formwork for a tunnel-driving machine | |
DE102004040191B4 (en) | Method for the production of guide elements | |
EP0381665A2 (en) | Process and apparatus for forming a strand of single elements under water | |
DE1902971C (en) | Formwork construction for the section have production of the lining of tunnels, tunnels, channels, shafts or the like | |
DE10207126A1 (en) | Trench digging and lining machine for preparing foundations for buildings has chain scraping up soil from bottom of trench and carrying it up to surface | |
DE7418388U (en) | Device for producing tunnels, canals or galleries, in particular underground tunnels | |
EP0465755A2 (en) | Process for making reinforced concrete beams, slide-casting apparatus therefor, and reinforced concrete beams obtained thereby |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
AK | Designated contracting states |
Designated state(s): AT BE CH DE FR GB IT LI LU NL SE |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN |
|
18D | Application deemed to be withdrawn |
Effective date: 19860512 |
|
RIN1 | Information on inventor provided before grant (corrected) |
Inventor name: DIE ERFINDER HABEN AUF IHRE NENNUNG VERZICHTET. |