DE8227251U1 - DEVICE FOR PRODUCING VERTICAL DRAINAGE BY MEANS OF A RAMM TUBE WITH A DRILL HEAD CONNECTED TO A RUETTEL DEVICE - Google Patents

DEVICE FOR PRODUCING VERTICAL DRAINAGE BY MEANS OF A RAMM TUBE WITH A DRILL HEAD CONNECTED TO A RUETTEL DEVICE

Info

Publication number
DE8227251U1
DE8227251U1 DE19828227251 DE8227251U DE8227251U1 DE 8227251 U1 DE8227251 U1 DE 8227251U1 DE 19828227251 DE19828227251 DE 19828227251 DE 8227251 U DE8227251 U DE 8227251U DE 8227251 U1 DE8227251 U1 DE 8227251U1
Authority
DE
Germany
Prior art keywords
drill bit
ram
pipe
section
vibrating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
DE19828227251
Other languages
German (de)
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wentzel Hanno Dipl-Ing 2082 Uetersen De
Original Assignee
Wentzel Hanno Dipl-Ing 2082 Uetersen De
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wentzel Hanno Dipl-Ing 2082 Uetersen De filed Critical Wentzel Hanno Dipl-Ing 2082 Uetersen De
Priority to DE19828227251 priority Critical patent/DE8227251U1/en
Publication of DE8227251U1 publication Critical patent/DE8227251U1/en
Expired legal-status Critical Current

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Description

Die Erfindung betrifft eine Vorrichtung zur Herstellung von Vertikaldrainagen mittels eines mit einer Rütteleinrichtung verbundenen Rammrohres mit Bohrkopf.The invention relates to a device for producing vertical drainage by means of a device with a vibrating device connected ram pipe with drill head.

Es ist bekannt, bindige Böden, wie vornehmlich solche organischer Herkunft durch Abbau des Porenwasserüberdruckes nach Aufbringen von Zusatzlasten zu konsolidieren. Hierzu können die Böden mit einer größeren Belastung beaufschlagt werden, als die normale Gebrauchslast beträgt. Es ist ferner möglich, Vertikaldrainagen aus kunststoffarmierten Vlies in Schlitze von Hohlkonstruktionen in einem vorgegebenen Raster einzurammen, einzurütteln oder einzudrücken. Hierbei besteht der Nachteil, daß der Durchlässigkeitsbeiwert des Vlieses stark von den ihn zusammendrückenden Kräften aus Erdlast abhängt und daher in seiner Höhe variiert. Aus diesem Grunde werden häufig Vertikaldrainagen dadurch hergestellt, daß in das zu drainierende Erdreich eng fraktionierte,dem vorhandenen Boden nach den Filterregeln angepaßter Sand in einem vorgegebenen Raster eingebaut wird. Hierzu ist es bekannt, Rammrohre mit einer dreischaligen Spitze auszurüsten, in das Erdreich einzurütteln und dann von oben Sand einzufüllen, wobei das Rohr dann rüttelnd wieder herausgezogen wird. Während des Ziehvorganges öffnet sich die Spitze durch die eigene Schwerkraft. Die Durchlässigkeit des so eingebrachten Sandes wird durch äußere Kräfte nur geringfügig verändert.It is known to have cohesive soils, such as primarily organic ones Consolidate origin by reducing the excess pore water pressure after applying additional loads. You can do this the floors are subjected to a greater load than the normal working load. It is also possible Ramming vertical drainages made of plastic-reinforced fleece into slots of hollow structures in a predetermined grid, shake or push in. The disadvantage here is that the permeability coefficient of the fleece is high depends on the compressive forces from the earth's load and therefore varies in height. Because of this, will often vertical drainage produced by the fact that in the soil to be drained closely fractionated, the existing soil sand adapted to the filter rules is installed in a given grid. For this purpose it is known to have ram pipes equip a three-shell tip, shake it into the ground and then pour in sand from above, with the pipe is then pulled out again with a shake. During the pulling process, the tip opens due to its own gravity. The permeability of the sand introduced in this way is only slightly changed by external forces.

Die Aufgabe der Erfindung besteht darin, die gattungsgemäße Vorrichtung so zu verbessern, daß bei Erhöhung der Handhabungssicherheit der Zeitaufwand zur Herstellung einer Vertikaldrainage im Erdreich verringert wird.The object of the invention is to improve the generic device so that while increasing the handling safety the time required to produce a vertical drainage in the ground is reduced.

Erfindungsgemäß erfolgt die Lösung der Aufgabe dadurch, daß die Bohrspitze einen rechteckigen Querschnitt aufweist, deren schwenkbaren Schneidenplatten 8 mittels einer Schließeinrichtung beim Eintreiben der Bohrspitze in das Erdreich inAccording to the invention, the object is achieved in that the drill bit has a rectangular cross-section, the pivotable cutting plates 8 of which by means of a locking device when driving the drill bit into the ground in

-A--A-

Schließstellung gehalten werden, und einen an dem der Bohrspitze abgewandten Abschnitt des Rammrohres angeordneten Einfülltrichter für Drainagematerial.Are held in the closed position, and a funnel arranged on the section of the ram pipe facing away from the drill bit for drainage material.

Weitere Merkmale der Erfindung werden in den Unteransprüchen beschrieben. Ausführungsbeispiele der Erfindung sind in den Zeichnungen dargestellt. Es zeigtFurther features of the invention are described in the subclaims. Embodiments of the invention are shown in Drawings shown. It shows

Fig. 1 eine erfindungsgemäße Vorrichtung in einer schematischftn Seitenansicht,1 shows a device according to the invention in a schematic side view,

Fig. 2 die Bohrspitze der Vorrichtung nach Fig. 1FIG. 2 shows the drill bit of the device according to FIG. 1

in einer schematischen Seitenansicht im Schnitt,in a schematic side view in section,

Fig. 3 die Bohrspitze in einer Ansicht von unten, Fig. 4 die Bohrspitze in einer Teilansicht im Schnitt.3 shows the drill bit in a view from below, FIG. 4 shows the drill bit in a partial view in section.

Die in Fig. 1 dargestellte Vorrichtung 1 zur Herstellung einer Vertikaldrainage ist mit einem nur angedeuteten Bagger 3 antriebsseitig verbunden. An dem Bagger 3 ist ein Mäkler 2 befestigt, der eine Mäklerführung 4 aufweist, die zur Führung eines Rüttelbärs 5 und der Vorrichtung 1 dient. Die Vorrichtung 1 besteht aus einem Rammrohr 7 an dessen unteren Endabschnitt eine Bohrspitze 6 ausgebildet ist. An dem der Bohrspitze 6 abgewandten Abschnitt 10 befindet sich eine Halteeinrichtung 22, an der der Rüttelkopf 19 des Rüttelbärs 5 zugewandt befestigt ist. In dem Rammrohr 7 ist eine Förderschnecke 18 ausgebildet, die vorzugsweise eine Steigung von 45° aufweist. Die Förderschnecke 18 wird mittels eines Hydraulikmotors 20 angetrieben, der in der Halteeinrichtung 22 gelagert ist. Die Beaufschlagung des Hydraulikmotors 20 mit Hydraulikflüssigkeit kann durch eine am Bagger 3 ausgebildete hydraulische Energieversorgungseinrichtung erfolgen. Sowohl der Hydraulikmotor 20 wie auch die Förderschnecke 18 sind auf Schwingelementen 21,26The device 1 shown in Fig. 1 for producing a vertical drainage is with an only indicated excavator 3 on the drive side tied together. A leader 2 is attached to the excavator 3, which has a leader guide 4 which is used for guidance a jogger 5 and the device 1 is used. The device 1 consists of a ram pipe 7 at its lower end portion a drill bit 6 is formed. A holding device is located on the section 10 facing away from the drill bit 6 22, on which the vibrating head 19 of the vibrating bear 5 is attached facing. In the ram pipe 7 is a screw conveyor 18 formed, which preferably has a slope of 45 °. The screw conveyor 18 is driven by a hydraulic motor 20 driven, which is mounted in the holding device 22. The application of hydraulic fluid to the hydraulic motor 20 can by means of a hydraulic energy supply device formed on the excavator 3 take place. Both the hydraulic motor 20 and the screw conveyor 18 are on vibrating elements 21, 26

gelagert und so gegen Beschädigungen aufgrund von Erschütterungen durch den Rüttelbär 5 geschützt.stored and thus protected against damage due to vibrations by the jogger 5.

An dem Abschnitt 10 des Rammrohrs 7 ist endabschnittseitig ein Rohrverbinder 17 ausgebildet, an dem ein Rohrabschnitt 23 befestigt ist. Der Rohrverbinder 17 kann als Flansch oder ähnliches Verbindungsteil ausgebildet sein und dient dazu, gegebe nenfalls auch Verlängerungsstücke an das Rammrohr 7 anbauen zu können.Der Rohrabschnitt 23 ist integraler Bestandteil eines Einfülltrichters 11 und mit der Halteeinrichtung 22 verbunden. Der Einfülltrichter 11 wird vorzugsweise so dimensioniert, daß sein Volumen dem Volumen des als Vertikaldrainage einzubringenden Drainagematerials entspricht. Als Drainagematerial wird regelmäßig entsprechend fraktionierter Sand verwendet. Um die Verdichtung des Sandes im Erdreich zu erhöhen, ist es zweckmäßig, dem Sand Wasser zuzugeben, so daß der Sand in fließfähigem Zustand in das Erdreich eingebracht werden kann. Es ist zweckmäßig, an dem Einfülltrichter 11 einen Wasseranschlußstutzen 12 vorzusehen, an den beispielsweise mittels eines Schnellverschlusses ein Wasserschlauch angeschlossen werden kann. Der Sand kann aber auch trocken eingebracht werden.On the section 10 of the ram pipe 7, a pipe connector 17 is formed on the end section side, to which a pipe section 23 is attached is. The pipe connector 17 can be used as a flange or the like Be formed connecting part and is used to build extension pieces to the ram pipe 7, if necessary The pipe section 23 is an integral part of a filling funnel 11 and is connected to the holding device 22. The funnel 11 is preferably dimensioned so that its volume corresponds to the volume of the drainage material to be introduced as vertical drainage. As a drainage material is used regularly appropriately fractionated sand is used. In order to increase the compaction of the sand in the ground, it is advisable to to add water to the sand so that the sand can be poured into the ground in a flowable state. It is appropriate to the funnel 11 to provide a water connection piece 12 to which a water hose, for example by means of a quick release can be connected. The sand can also be brought in dry.

Die Bohrspitze 6 ist in Fig. 2 bis 4 näher dargestellt. An dem dem bohrspitzenseitigen Endabschnitt des Rammrohres 7 zugewandten Abschnitt der Bohrspitze 6 ist in deren inneren Querschnitt eine Traverse 27 angeordnet, in der sich mittig das Wellenlager '25 der Schneckenwelle 24 der Förderschnecke 18 befindet. Das Wellenlager 25 ist auf einem Schwingungsdämpfer 26 abgestützt. Die Bohrspitze 6 besteht aus einem Bohrspitzenrahmen 28, der aus je zwei Seitenflächen 29, 30 gebildet ist. Die Seitenflächen weisen einen dreieckförmigen vorragenden Endabschnitt auf, dessen Querschnitt dem Querschnitt der Bohrspitze 6 im Schließzustand enspricht. Zwischen den kürzeren Seitenflächen 29 sind die Schneidenplatten 8 angeordnet, die um Lager 13, 14 schwenkbar sind. Jedes Lager 13, 14 besteht aus einem Zapfen 32, derThe drill bit 6 is shown in more detail in FIGS. To the the portion of the drill bit 6 facing the end portion of the ram pipe 7 on the side of the drill bit is in its inner cross section a Traverse 27 is arranged, in which the shaft bearing '25 of the screw shaft 24 of the screw conveyor 18 is located in the middle. The shaft bearing 25 is supported on a vibration damper 26. The drill bit 6 consists of a drill bit frame 28, which consists of two side surfaces 29, 30 each are formed. The side faces have a triangular protruding end section, the cross section of which corresponds to the cross section of the drill bit 6 in the closed state corresponds. The cutting plates 8, which can pivot about bearings 13, 14, are arranged between the shorter side surfaces 29 are. Each bearing 13, 14 consists of a pin 32, the

mit einer Seitenfläche 30 ζ. B. durch Schweißung verbunden ist. Die Endabschnitte der Zapfen 32 sind in Lagerbügeln 31 gelagert, die mit den Schneidenplatten 8 z.B. durch Schweißung verbunden sind. Die beim Einrütteln der Vorrichtung auf die Schneidenplatten 8 einwirkenden vertikalen Kräfte werden auf die Seitenflächen 29 übertragen. Sandpartikel, die die Funktion der Lager 13, 14 beeinträchtigen, können im Regelfall durch kurze Betätigung des Rüttelbärs 5 entfernt werden.with a side face 30 ζ. B. is connected by welding. The end sections of the journals 32 are mounted in bearing brackets 31 which are connected to the cutting inserts 8, for example by welding are. The vertical forces acting on the cutting inserts 8 when the device is vibrated are applied to the side surfaces 29 transfer. Sand particles that impair the function of the bearings 13, 14 can usually be removed by briefly pressing the Jogging Bear 5 can be removed.

Um die Schneidenplatten 8 in Schließstellung zu halten, ist jede Schneidenplatte 8 mit mindestens einer Feder 16 verbunden, die an dem Bohrspitzenrahmen 28 befestigt ist. Um eine Beeinträchtigung der Funktion der Federn 16 zu verhindern, werden diese vorzugsweise mit einem elastischen Balg umgeben.In order to keep the cutting plates 8 in the closed position, each cutting plate 8 is connected to at least one spring 16 which is attached to the bit frame 28. To an impairment To prevent the function of the springs 16, they are preferably surrounded by an elastic bellows.

Um den porenschließenden Reibeinfluß des Erdreichs 9 durch das Rammrohr 7 bei dessen Hochziehen entgegenzuwirken, ist der Querschnitt der Bohrspitze 6 größer, als der des Rammrohrs 7 (Fig. 3).In order to counteract the pore-closing frictional influence of the soil 9 through the ram pipe 7 when it is pulled up, the cross-section is the drill bit 6 larger than that of the ram pipe 7 (Fig. 3).

Es ist auch möglich, die Bohrspitze 6 vor dem Einbringen in das Erdreich mit einem Gummiring zu versehen, der die Schneidenplatten 8 in Schließstellung hält. Beim Eindringen in das Erdreich 9 wird der Gummiring zerstört, während die Schneidenplatten 8 weiterhin in Schließstellung bleiben, Sie öffnen sich erst beim Hochziehen des Rammrohres 7 aufgrund eigener Schwerkraft sowie den Druck des in das Erdreich durch das Rammrohr 7 einzubringenden Sandes.It is also possible to provide the drill bit 6 with a rubber ring, which the cutting plates 8 holds in the closed position. When penetrating into the soil 9, the rubber ring is destroyed, while the cutting plates 8 continue stay in the closed position, they only open when pulling up the ram pipe 7 due to its own gravity as well the pressure of the sand to be introduced into the ground through the ram pipe 7.

Bei Verwendung der Förderschnecke 18 in dem Rammrohr 7 wird das von dem Hydraulikmotor 20 aufgebrachte Drehmoment zum überwiegenden Teil zum Einbringen des Drainagesandes in das Bohrloch benötigt. Lediglich ein geringer Teil der auf die Förderschnecke einwirkenden Energie dient zum Öffnen der Schneidenplatten 8. Die Verwendung der Förderschnecke 18 ermöglicht eine relativ hohe Verdichtung von in das Erdreich 9 eingebrachten Sand.When using the screw conveyor 18 in the ram pipe 7, the The torque applied by the hydraulic motor 20 is required for the most part to introduce the drainage sand into the borehole. Only a small part of the energy acting on the screw conveyor is used to open the cutting inserts 8. Die Use of the screw conveyor 18 enables a relatively high compression of sand introduced into the ground 9.

Die Förderschnecke 18 kann auch auf wenige Windungen beschränkt sein, in dem ein als Achsmotor ausgebildeter schlanker Motor
als Antriebseinrichtung verwendet wird, der auf einer weiteren Traverse ähnlich dem Schneckenunterteil innerhalb des Rammrohres 7 gelagert ist. Das Rammrohr 7 kann nicht nur für Vertikalbohrungen sondern auch für Horizontalbohrungen verwendet
werden.
The screw conveyor 18 can also be limited to a few turns, in which a slim motor designed as an axis motor
is used as a drive device, which is mounted on a further traverse similar to the screw lower part within the ram pipe 7. The ram pipe 7 can be used not only for vertical bores but also for horizontal bores
will.

Claims (1)

SCHÜTZ ANSPRÜCHESCHÜTZ CLAIMS Vorrichtung zur Herstellung von Vertikaldrainagen mittels eines mit einer Rütteleinrichtung verbundenen Rammrohres mit Bohrkopf, dadurch gekennzeichnet, daß die Bohrspitze einen rechteckigen Querschnitt aufweist, deren schwenkbare Schneidenplatten (8) mittels einer Schließeinrichtung beim Eintreiben dei Bohrspitze (6) in das Erdreich (9) in Schließstellung gehalten werden, und einen an dem der Bohrspitze (6) abgewandten Abschnitt (10) des Rammrohres (7) angeordneten Einfülltrichter (11) für Drainagematerial.An apparatus for producing vertical drainage by means of a connected to a vibrating Rammrohres with the drill head, characterized net gekennzeich that the drill bit has a rectangular cross-section, the swiveling cutting plates (8) by means of a closing device during the driving dei drill bit (6) into the ground (9) in Are held in the closed position, and a funnel (11) for drainage material arranged on the section (10) of the ram pipe (7) facing away from the drill bit (6). Vorrichtung nach Anspruch 1, dadurch gekennzeichnet, daß die Bohrspitze (6) aus zwei um jeweils ein Lager (13, 14) schwenkbare Schneidenplatten (8) besteht.Device according to Claim 1, characterized in that the drill bit (6) consists of two bearings (13, 14) each around one pivotable cutting plates (8) consists. Vorrichtung nach Anspruch 2, dadurch gekennzeichnet, daß die Lager (13, 14) im Innenraum der Bohrspitze (6) angeordnet und die Schneidenplatten (8) mittels balggeschützter Federn (16) od.dgl. zum Verschließen schwenkbar sind.Device according to Claim 2, characterized in that the bearings (13, 14) are arranged in the interior of the drill bit (6) and the cutting plates (8) by means of bellows-protected springs (16) or the like. are pivotable to close. Vorrichtung nach Anspruch 1 bis 3, dadurch gekennzeichnet, daß das Rammrohr (7) mit dem Rüttelbär (5) mit einem zur Baggerbefestigung ausgebildeten Mäkler (2) verbunden ist.Device according to Claims 1 to 3, characterized in that the ram pipe (7) with the vibrating ram (5) is connected to one another Excavator attachment trained leader (2) is connected. 5. Vorrichtung nach Anspruch 1 bis 4, dadurch gekennzeichnet, daß der Einfülltrichter (11) mittels einer Halteeinrichtung (22) mit dem Rüttelbär (5) und seinem Rüttelkopf (19) verbunden ist.5. Apparatus according to claim 1 to 4, characterized in that that the filling funnel (11) is connected to the vibrating bear (5) and its vibrating head (19) by means of a holding device (22) is. 6. Vorrichtung nach Anspruch 1 bis 5, dadurch gekennzeichnet, daß an dem der Bohrspitze (6) abgewandten Abschnitt (10) des Rammrohres (7) ein Rohrverbinder (17) ausgebildet ist.6. Apparatus according to claim 1 to 5, characterized in that on the section (10) facing away from the drill bit (6) of the ram pipe (7) a pipe connector (17) is formed. 7. Vorrichtung nach Anspruch 1 bis 6, dadurch gekennzeichnet, daß in dem Rammrohr (7) eine Förderschnecke (18) gelagert ist, die mit einer Antriebseinrichtung verbunden ist.7. Apparatus according to claim 1 to 6, characterized in that a screw conveyor (18) is mounted in the ram pipe (7) which is connected to a drive device. 8. Vorrichtung nach Anspruch 7, dadurch gekennzeichnet, daß die Antriebseinrichtung als in der Halteeinrichtung (22) angeordneter Hydraulikmotor (20) ausgebildet ist.8. Apparatus according to claim 7, characterized in that the drive device than in the holding device (22) arranged hydraulic motor (20) is formed. 9. Vorrichtung nach Anspruch 7 und 8, dadurch gekennzeichnet, daß die Förderschnecke (18) und der Hydraulikmotor (20) auf Schwingelementen (21, 26) gelagert sind.9. Apparatus according to claim 7 and 8, characterized in that the screw conveyor (18) and the hydraulic motor (20) Oscillating elements (21, 26) are mounted. 10. Vorrichtung nach Anspruch 1 bis 9, dadurch gekennzeichnet, daß an dem Einfülltrichter (11) ein Wasseranschlußstutzen (12) ausgebildet ist.10. Apparatus according to claim 1 to 9, characterized in that a water connection piece (12) on the filling funnel (11) is trained.
DE19828227251 1982-09-29 1982-09-29 DEVICE FOR PRODUCING VERTICAL DRAINAGE BY MEANS OF A RAMM TUBE WITH A DRILL HEAD CONNECTED TO A RUETTEL DEVICE Expired DE8227251U1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DE19828227251 DE8227251U1 (en) 1982-09-29 1982-09-29 DEVICE FOR PRODUCING VERTICAL DRAINAGE BY MEANS OF A RAMM TUBE WITH A DRILL HEAD CONNECTED TO A RUETTEL DEVICE

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE19828227251 DE8227251U1 (en) 1982-09-29 1982-09-29 DEVICE FOR PRODUCING VERTICAL DRAINAGE BY MEANS OF A RAMM TUBE WITH A DRILL HEAD CONNECTED TO A RUETTEL DEVICE

Publications (1)

Publication Number Publication Date
DE8227251U1 true DE8227251U1 (en) 1983-01-20

Family

ID=6744088

Family Applications (1)

Application Number Title Priority Date Filing Date
DE19828227251 Expired DE8227251U1 (en) 1982-09-29 1982-09-29 DEVICE FOR PRODUCING VERTICAL DRAINAGE BY MEANS OF A RAMM TUBE WITH A DRILL HEAD CONNECTED TO A RUETTEL DEVICE

Country Status (1)

Country Link
DE (1) DE8227251U1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102005019168B4 (en) * 2005-04-25 2014-06-26 Friedr. Ischebeck Gmbh Use and method using a drilling injection anchor for drainage

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102005019168B4 (en) * 2005-04-25 2014-06-26 Friedr. Ischebeck Gmbh Use and method using a drilling injection anchor for drainage

Similar Documents

Publication Publication Date Title
DE69836769T2 (en) Building treatment
DE2534341B2 (en) Grouting anchor
EP3485097A2 (en) Vibrofloatation device
EP3112535A1 (en) Filling tube for creating a filler column in the soil and device and method therefor
DE1292586B (en) Method and device for producing a concrete casing pipe
EP1134319B1 (en) Method and apparatus for obtaining a cast in situ concrete pile
DE4005032C2 (en) Device for applying a force between a base plate and a foundation element
EP0543320B1 (en) Device for producing concrete piles in the ground
DE4224042A1 (en) Method and device for pile foundation
DE8227251U1 (en) DEVICE FOR PRODUCING VERTICAL DRAINAGE BY MEANS OF A RAMM TUBE WITH A DRILL HEAD CONNECTED TO A RUETTEL DEVICE
DE2550595C3 (en) A ram and a pipe having device for the production of earth bores and in these arranged piles made of poured or compacted concrete
DE2229383A1 (en) METHOD AND DEVICE FOR CONSOLIDATING THE SOIL, IN PARTICULAR FOR THE FOUNDATION OF PILES OR SIMILAR FOUNDATION STRUCTURES
DE102005008679A1 (en) Pile driving by head-, internal-, or vibration driving of pile tube, employs double-walled pile tube with filling of sand in annulus between walls
DE10025966C2 (en) Support tube columns
DE3021558C2 (en) Method for piping of liquid-filled wells, boreholes or the like. using individual pipe sections
DE10351956B3 (en) Device for extracting earth material from pipe driven into soil has flaps held by cable extending from one end of gripper pipe to other connected to actuator so this lowers cable and flaps drop to outlet position under pressure of soil
DE19942016B4 (en) Apparatus and method for producing a soil column of viable granular filler material
DE4303518C2 (en) Method and device for solidifying a landfill of pre-compacted waste with the development of additional capacity for fresh waste
DE19509088A1 (en) Method of producing recoverable jacket for use in pile driving
AT217200B (en) Climbing device for sliding formwork for concrete structures
DE2851619A1 (en) Concrete post foundation hole prodn. - involves lowering pipe into ground using vibrator and core is removed using differential air pressure
AT282887B (en) Support of structures to protect them if their foundations are shaken
DE1212899B (en) Method and device for the production of in-situ concrete piles
CH360349A (en) Process for carrying out vibration work using internal vibrators and internal vibrators for carrying out the process
DE1409608C (en) Procedure for the foundation of a floating tank with driven piles