DE740381C - Tariff establishment - Google Patents

Tariff establishment

Info

Publication number
DE740381C
DE740381C DES130266D DES0130266D DE740381C DE 740381 C DE740381 C DE 740381C DE S130266 D DES130266 D DE S130266D DE S0130266 D DES0130266 D DE S0130266D DE 740381 C DE740381 C DE 740381C
Authority
DE
Germany
Prior art keywords
load
network
individual
peak
customers
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
DES130266D
Other languages
German (de)
Inventor
Dipl-Ing Hans Guenther
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Siemens AG
Original Assignee
Siemens AG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Siemens AG filed Critical Siemens AG
Priority to DES130266D priority Critical patent/DE740381C/en
Application granted granted Critical
Publication of DE740381C publication Critical patent/DE740381C/en
Expired legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R11/00Electromechanical arrangements for measuring time integral of electric power or current, e.g. of consumption
    • G01R11/56Special tariff meters

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Description

Tarifeinrichtung Bekanntlich ist es für eine gerechte und den ElSel tätsabsatz: rdernde geldliche Belastung der einzelnen Abnehmer eines Elektrizi:tätsnetzes nützlich, wenn der Verbraucher einerseits dafür belastet wird, in welch hohem Maße er die Leistung der im Elektrizitätsnetz installierten Maschinen und Verteilungsvorrichtungen in Anspruch nimmt (Leistungspreis), andererseits auch dafür, wieviel Kilowattstunden er aus dem Netze entnommen hat (Arbeitspreis). Während nun die Verrechnung der-Leis'tungskosten bei den für die Industrieabnehmer geltenden Ilochspannungstarifen in bester tJbereinstimmung mit den Forderungen der Praxis einheitlich auf Grund der bemessenen Abnehmerhöchstlast erfolgt, müssen bei den für die Kleinahnehmer geltenden Niederspannungstarifen allein schon mit Rücksicht auf die Unwirtschaftlichkeit des Einbaues der kostspieligen Höchstlastzähler bei den vielen Kleinabnehmen andere Wege beschritten werden.Tariff establishment As is well known, it is for a fair and the ElSel Sales of electricity: increasing monetary burden on the individual consumers of an electricity network useful if on the one hand the consumer is burdened to what extent he the performance of the machines and distribution devices installed in the electricity network takes (performance price), on the other hand also for how many kilowatt hours he has taken from the network (energy price). While now the settlement of the service costs in the best agreement with the ilochet voltage tariffs applicable to industrial customers with the requirements of practice uniformly due to the measured maximum customer load takes place, must with the low-voltage tariffs applicable to the small workers alone considering the inefficiency of installing the expensive ones High load counter with the many small weight loss counters take other paths.

Man bedient sich hierzu vorwiegend der Form des Grundpreistarifes, bei welcher die Messung der Leistungsanteile und deren Verrechnung durch Einschaltung miltelbarer fester Bezugsgrößen für die Grundpreise (Zahl der installierten Lampen, Steckdosen oder ITaushaltsgeräte beim Kleinabuehmer oder Zahl der Wohnzimmer) ersetzt wird.For this purpose, one mainly uses the form of the basic price tariff, in which the measurement of the performance shares and their offsetting through involvement Miltable fixed reference values for the basic prices (number of installed lamps, Sockets or IT household appliances at the small business owner or number of living rooms) will.

Diese Umgehung !der Leistungsmessung bringt aber leider den Verzicht auf die sachlich gegebene Eindeutigkeit in der Bestimmung und Verrechnung der Leistungskosten mit sich, denn die unterschiedliche Zusammensetzung der Abnehmerschaft einerseits und die verschiedenartigen Verwendungszwecke der elektrischen Energie andererseits bedingen jeweils zweckmäßig angepaßte und gut abgestufte Bezugsgrößen und Grundpreise, deren Formbestimmung jedoch letzten Endes von einem persönlichen Werturteil abhängt. Durch die Einfügung derartiger fester Bezugsgrößen wird also erreicht, daß der daron abhängige Grundpreis nicht mehr genügend mit dem an sich gerechtfertigten I elstungspreis übereinstimmt.Unfortunately, this bypassing of the power measurement leads to the waiver on the factual clarity in the determination and offsetting of the service costs with itself, because the different composition of the customer base on the one hand and the various uses of electrical energy on the other hand require appropriately adapted and well-graded reference values and basic prices, whose form determination, however, ultimately depends on a personal value judgment. By inserting such fixed reference values, it is achieved that the daron dependent The basic price is no longer sufficient with the justified service price matches.

Grundsätzlich neue Möglichkeiten für die Tarifgestaltung können erst nach Ausschaltung der willkürlichen Bezugsgrößen, also bei unmittelbarer Bezugnahme des Grundpreises auf die Leistungskosten selbst, erwartet wer den. Geht man davon aus, daß die jährlichen Leistungskosten eines Werkes von der Jahresspitze der Werksbelastung abhängen, dann ergeben die Leistungsanteile aller Abnehmer an der Werksspitze sofort die eindeutige Aufteilung der gesamten Leistungskosten auf die Einzelabnel!mer. Ein gemessener Spitzenanteil ist demzufolge nichts anderes als der Verbrauch an Spitzenleistung in Kilowatt oder Watt, der ebenso unmittelbar mit dem l.eistungspreis für die Einheit der Leistung zu verrechnen ist, wie der in kWh gemessene Energieverbrauch mit dem Arbeitspreis für die Einheit der Arbeit. Fundamentally new options for tariff structuring can only be achieved after elimination of the arbitrary reference values, i.e. with direct reference of the basic price on the service costs themselves. One assumes from the fact that the annual output costs of a work depend on the annual peak of the workload depend, then the performance shares of all customers at the top of the factory result immediately the clear allocation of the total service costs to the individual customers. A measured peak share is therefore nothing other than the consumption of Peak power in kilowatts or watts, which is also directly linked to the oil price for the unit of power is to be charged like the energy consumption measured in kWh with the labor price for the unit of labor.

Die Erfindung betrifft nun eine Tarifeinrichtung zur Feststellung des Anteiles der einzelnen Abnehmer eines Elektrizitätsnetzes an der Spitzenbelastung des Netzes, das sich in einfacher Weise und mit einfachen Mitteln auch bei Kleinahnehmern durchführen läßt und das die Festsetzung des Grundpreises in unmittelbarer Abhängigkeit von den Leistungskosten gestattet. Erfindungsgemäß wird bei Überschreitung einer bestimmten, in der Nähe der Spitzenlast gelegenen Belastung des Netzes von einer Zentralstelle aus bei den einzelnen Abnehmern eine die clektrische Arbeit zählende Vorrichtung (Snnderzählwerk), zweckmäßig unter Auslösung einer Anzeige-oder Nieldevorrichtung, eingeschaltet und bei Unterschreitung einer bestimmten, in der Nähe der Spitzenleistung gelegenen Netzbelastung nieder ausgeschaltet. Ferner wird in der Zentralstelle die Gesamtdauer aller Einzelheiten, während denen bei den Abnehmern die Sonderzählwerke eingeschaltet sind, jeweils für eine Meßperiode gemessen. The invention now relates to a tariff device for determination the share of the individual consumers of an electricity network in the peak load of the network, which is easy and simple, even for small business owners can be carried out and the setting of the basic price in direct dependence Allowed by the performance costs. According to the invention, when a certain load on the grid located near the peak load of a Central office from the individual buyers one that counts the clever work Device (sniffer counter), expediently by triggering a display or indicator device, switched on and when falling below a certain level, close to the peak power network load is switched off. Furthermore, the Total duration of all details during which the special counters were used by the customers are switched on, each measured for one measuring period.

Man hat bei der Tarifgestaltung von Elektrizitätsnetzen bereits erkannt. daß zweckmäßig Preise zu verrechnen sind, die sich mit der augenblicklichen Gesamtleistung nach Maßgabe etwa der Kostenkurve ändern. Als Meßaufgabe sah man dabei an die Bestimmung von Größen, die außer von der Abnehmerleistung auch von der Gesamtleistung abhängen, also zunächst aus dieser zu ermitteln sind. Um diese Aufgabe durchzuführen, wurde vorgeschlagen, einen Bereitstellungspreis zu verrechnen, der sich auf das größte, in einer Viertelstunde erreichte Produkt aus Gesamtleistung und Abnehmerleistung abstellt. Die Messung sollte dabei mit überlagerten Hochfrequenzimpulsen erfolgen. One has already recognized in the tariff structure of electricity networks. that appropriate prices are to be charged that are based on the current overall performance change according to the cost curve. Determination was the task of measurement of sizes that depend not only on the customer's performance but also on the overall performance, therefore must first be determined from this. To accomplish this task was made proposed to charge a provision price based on the largest, The product of total performance and customer performance achieved in a quarter of an hour turns off. The measurement should be carried out with superimposed high-frequency pulses.

Diese bekannte Tarifeinrichtung hat aber gegenüber der nach der Erfindung den sehr wesentlichen Nachteil, daß sie sehr kostspielig ist, da bei der bekannten Einrichtung mittels der überlagerten Hochfrequenzimpulse Meßwerte zwischen dem Verbraucher und der Zentrale übertragen werden müssen, während bei der Erfindung nicht Meßwerte übertragen werden, sondern nur Impulse zur Ein- oder Ausschaltung des Zählwerkes bei den einzelnen Abnehmern. Dies ist eine technisch weitaus einfacher und wirtschaftlicher durchzuführende Maßnahme als die Übertragung von quantitativen Meßwerten.This known tariff facility has however compared to that according to the invention the very significant disadvantage that it is very expensive, since the known Device by means of the superimposed high-frequency pulses measured values between the consumer and the control center must be transmitted, while with the invention not measured values are transmitted, but only pulses for switching the counter on or off with the individual customers. This is technically far simpler and more economical action to be taken as the transfer of quantitative measured values.

Jedesmal, wenn die ansteigende Gesamtbelastung eines Netzes oder Kraftwerkes etwa 90 % der Jahresspitze erreicht, wird bei allen Abnehmern gleichzeitig ein je Zähler vorgesehenes Sonderzählwerk durch Fernsteuerung selbsttätig eingerückt. Alle diese Sonderzahiwerke messen dann so lange den gesamten Stromverbrauch, bis die Werksbelastung wieder auf den Betrag gesunken ist, den sie im Augenblick des Einrückens der Zählwerke hatte. Beim weiteren Sinken der Werksbelastung werden alle diese Zähl werke gleichzeitig wieder ausgerückt und damit bis zum nächsten Lastanstieg stillgesetzt. Every time the increasing total load on a network or Power plant reaches around 90% of the annual peak is achieved by all customers at the same time a special register provided for each meter is automatically engaged by remote control. All of these special meters then measure the total electricity consumption until the factory load has fallen back to the amount that it was at the moment of Indenting the counters. If the plant load continues to fall, all will these counters are disengaged again at the same time and thus until the next load increase shut down.

Abb. 1 zeigt anschaulich die Wirkungsweise des Meßverfahrens an Hand der Jahresdauerkurve I einer Kraftwerksbelastung (Werksbelastung in Prozent der Spitze und Zahl der Stunden im Jahr, in denen diese Werksbelastung vorhanden war), bei welcher als Einsatzhöhe für die Spitzenanteilmesstingen eine Belastung von go °/0 der Spitze gewählt wurde. Eine Parallele 2 zur Zeitachse in dieser Höhe schneidet die Dauerkurve in einem Punkt, der die jährliche Gesamtdauerll aller Einzeleinschaltzeiten, also die Benutzungsdauer von go 0/, der Höchstspitze, festlegt. Das Integral der,Dauerkurve von O bis 11, dargestellt durch die schraffierte Fläche, ist aber ein Maß für die kWh-Summe aus den Leistungsmessungen aller Zähler, da ja während dieser Zeit der Gesamtverbrauch aller Abnehmer mittels der Leistungszählwerke gesondert gemessen wurde. Fig. 1 clearly shows how the measuring method works the annual duration curve I of a power plant load (plant load in percent of Peak and number of hours in the year in which this workload was present), at which a load of go ° / 0 of the tip was chosen. A parallel 2 to the time axis intersects at this height the duration curve at one point that represents the total annual duration of all individual switch-on times, that is, defines the duration of use of go 0 /, the maximum peak. The integral of, duration curve from O to 11, represented by the hatched area, is a measure of the kWh sum from the power measurements of all meters, since during this time the Total consumption of all consumers measured separately by means of the performance counters became.

Teilt rnan jetzt sowohl alle diese Einzelmessungen als auch deren Summe durch die im Werk selbsttätig gemessene und für alle Abnehmer genau gleiche jährliche Einschaltdauer h, dann erhält man sowohl die mittlere L.eistungsentnahme jedes Einzelabnehmers als auch, bei Hinzurechnung der Verluste, die mittlere Werksbelastnng (3 in I) für diese Zeitdauer. Damit kennt man zunächst den .\enteil jeder Einzelabnahme an der mittleren ATerkshöchstbelastung der Dauerkurve. Da diese aber laut Voraussetzung stets nur wenige Prozent kleiner sein kann als die Höchstspitze, darf. die so gemessene mittlere Werkshöchstbelastung der kurzzeitigen Höchstspitze praktisch verhältnisgleich gesetzt werden, und zwar bei jeder beliebigen jährlichen Gesamtdauer h der Einzeleinschaltzeiten. Now share all of these individual measurements as well as theirs Sum by the automatically measured in the factory and exactly the same for all customers annual duty cycle h, then you get both the mean power consumption of each individual customer as well as the mean factory load, if the losses are added (3 in I) for this period. So you first know the part of each individual acceptance at the mean maximum load of the continuous curve. Since this, however, according to the prerequisite can always be only a few percent smaller than that Peak, allowed. the mean maximum factory load measured in this way for the short-term maximum peak be set practically proportionately, at any given annual Total duration h of the individual switch-on times.

Die zeitliche Ausdehnung der Spitzenanteilmessung, die somit praktisch keinen Einfluß auf die einwandfreie Aufteilung der Jahresspitze hat, ist jedoch von großer Wichtigkeit für die tarifliche Brauchbarkeit des Meßverfahrens. Während nämlich die Beschränkung der Spitzenanteiltnessung auf den Augenblick der Jahreshöchstspitze für den Einzel anteil einen gänzlich von zufålligen Einflüssen bestimmten Wert ergäbe, bringt das neue Meßverfahren neben der reinen Spitzenabhängigkeit zwangsläufig auch den zeitlichen Verlauf der Belastung mit in die Leistungskostenverteilung. The temporal expansion of the peak proportion measurement, which is therefore practical has no influence on the correct distribution of the annual peak, however of great importance for the tariff usability of the measurement method. While namely the limitation of the peak proportion to the moment of the annual peak the individual part would have a value determined entirely by random influences, In addition to the pure peak dependency, the new measuring method inevitably also brings it the temporal course of the load in the service cost distribution.

Da die Jahres spitzen in den einzelnen Anlageteilen in Richtung des Energieflusses zum Niederspannungsnetz, vor allem bei größeren Werken, selten am gleichen Tage und fast nie zur selben Stunde, auftreten, würde die einfache Summierung der bezogenen Leistungskosten dieser Anlageteile den Niederspannungsverbrauch zu hoch belasten; es würde alsö, wie Abb. 2 an Hand eines Beispiels zeigt, der Belastungsausgleich in den vorgeschalteten Fortleitungsnetzen und im Kraftwerk nicht berücksichtigt werden. Die Kurven der Abb. 2 zeigen den Belastungsverlauf in den Erzeugungs- und Fortleitungsanlagen während eines Tages. Die Kurve, stellt den Pelastungsverlauf im Kraftwerk (Gesamtbelastung), die Kurve L1 den Belastungsverlauf des Hochspannungsnetzes (Industrieabnehmer und Abspannstationen für Niederspannungsnetz), die Kurve N den Eelastungsverlauf des Niederspannungsuetzes jeweils am Tage der Jahresspitze dieser Anlagerteile und die Kurven Nt und N2 den Belastungsverlauf im Niederspannungsnetz am Tage der Jahresspitze von L1 bzw. L2, dar. Since the annual peaks in the individual parts of the system in the direction of the Energy flow to the low-voltage network, especially in larger plants, rarely on the same days and almost never at the same hour, the simple summation would occur the related performance costs of these system parts to the low-voltage consumption load heavily; as shown in Fig. 2 using an example, it would be the load compensation not taken into account in the upstream transmission networks and in the power plant will. The curves in Fig. 2 show the load profile in the generation and Forwarding systems during one day. The curve represents the course of the load in the power plant (total load), curve L1 shows the load profile of the high-voltage network (Industrial customers and substations for low-voltage networks), the curve N den Load curve of the low voltage usage on the day of the annual peak of this Plant parts and the curves Nt and N2 show the load profile in the low-voltage network on the day of the annual peak of L1 or L2.

Die den einzelnen Kurven zugeordneten Ordinaten S1, S2 und SN geben die Jahresspitzen der einzelnen Kurven an, die nach vorstehendem in der Regel nicht alle am gleichen Tage auftreten. Die Teilstücke sSlJ Ssn der Ordinaten S1 und S2 geben den Spitzenanteil der Niederspannungsnetzbelastung an der Spitzenbelastung des HochspannungsretzesSl bzw. an der, Spitzenbelastung des gesamten Kraftwerkes S2 wieder. In solchen Fällen müßte daher eine Herabsetzung des Leistungspreises, der mit den Spitzenanteilen an der Höchsfbelastung im Niederspannungsnetz verrechnet wird, stattfinden. Dieser herabgesetzte Leistungspreis kann nach einer einfachen Formel berechnet werden, die sich bei sinngemäßer Anwendung des Spitzenanteilprinzips auf die vorgeschalteten Kostenstellen wie folgt ergibt: Der Leistungspreis PLX der mit den an der N iederspannungsspitze gemessenen Spitzenanteilen zu verrechnen ist, setzt sich also zusammen aus dem Leistungspreis pilr für das Niederspannungsnetz allein und aus der Summe der jeweiligen Leistungspreise PL?, für die vorgeschalteten Anlageteile, je verkleinert ss, um das Verhältnis S 8, wobei SSn = Spitzenanteil der Gesamtbelastung im Niederspannungsnetz an der Jahreshöchstspitze eines vorgeschalteten Anlageteiles, SN = Jahreshöchstspitze im Niederspannungsnetz und SNI= Summe aller gemessenen Spitzenanteile an der Niedersp annungshö chstbelastung.The ordinates S1, S2 and SN assigned to the individual curves indicate the annual peaks of the individual curves which, according to the above, generally do not all occur on the same day. The sections sSlJ Ssn of the ordinates S1 and S2 reflect the peak proportion of the low-voltage network load in the peak load of the high-voltage network S1 or in the peak load of the entire power plant S2. In such cases, a reduction in the power price, which is offset against the peak proportions of the maximum load in the low-voltage network, would have to take place. This reduced service price can be calculated using a simple formula which, if the principle of peak shares is applied to the upstream cost centers, results as follows: The performance price PLX, which is offset against the peak proportions measured at the low voltage peak, is thus composed of the performance price pilr for the low-voltage network alone and the sum of the respective performance prices PL? For the upstream system components, each reduced by the ratio S 8, where SSn = peak share of the total load in the low-voltage network at the annual peak of an upstream part of the system, SN = annual peak in the low-voltage network and SNI = sum of all measured peak shares in the maximum low-voltage load.

Da obige Formel mit beliebiger Genauigkeit die Aufteilung der leistungsabhängigen Kosten in bezug auf die Gesamtabgabe in Niederspannung liefert, kann auf eine mehrfache Spitzenanteilmessung bezüglich der zeitlich auseinanderfallenden Jahres spitzen in den vorgeschalteten Fortleitungsnetzen und sonstigen Anlageteilen verzichtet werden. Because the above formula shows the division of the performance-dependent Costs in relation to the total charge in low voltage supplies can be multiple Peak proportion measurement with regard to the annual peaks that coincide with each other waived in the upstream transmission networks and other parts of the system will.

Damit bleibt die spitzenbekämpfende Wirkung im Niederspannungsverteilnetz voll erhalten, ohne hier durch zusätzliche Messungen beeinträchtigt und abgeschwächt zu werden. Eine mehrfache Spitzenanteilmessung würde außerdem die Vorteile der Einfachheit und Übersichtlichkeit des Verfahrens wesentlich herabsetzen und zudem noch die meßtechnischen Aufwendungen beträchtlich erhöhen.This means that the anti-peak effect remains in the low-voltage distribution network fully preserved without being impaired and weakened here by additional measurements to become. Multiple peak fraction measurements would also have the advantages of simplicity and the clarity of the procedure, and also the metrological Increase expenses considerably.

Dank der immer weiter fortschreitenden Einführung vollvermaschter Netze mit ihrem guten Belastungsausgleich wird schließlich bei den meisten Werken ein Zustand geschaffen sein, der die einwandfreie Erfassung der für den Netzausbau maßgebenden Höchstbelastung stets mit Sicherheit gewährleistet. Thanks to the ever-advancing introduction of fully meshed Networks with their good load balancing will eventually work at most a state must be created that allows for the proper recording of the network expansion relevant maximum load is always guaranteed with certainty.

Die Fernsteuerung der Zählwerke kann dann zweckmäßigerweise von einem im Speiseschwerpunkt des Verteilnetzes liegenden Umspannwerk aus erfolgen, dessen Belastungsverlauf der mittleren Netzbelastung am besten entspricht.The remote control of the counters can then expediently from one the substation located in the feed focus of the distribution network, whose The course of the load corresponds best to the average network load.

Eine genügend genaue Abschätzung der Jahres spitze der kommenden Meßperiode zwecks richtiger Einstellung des Gebers für die Steuerung der Zählwerke wird bei geeigneter Überwachung und statistischer Erfassung der sich stetig ändernden Belastungsverhältnisse im Verteilnetz immer möglich sein. Für die Einstellung der Einsatzhöhe steht ja, wie Abb. 1 zeigt, ein reichlicher Spielraum zwischen etwa 75 und 95 01o der Höchstspitze zur Verfügung, dessen obere und untere Grenze lediglich von praktischen Gesichtspunkten, wie ausreichende Gesamtdauer der Messungen bzw. Vermeidung etwaigen Ubergreifens der Messungen auf die Mittelbelastung, bestimmt werden. A sufficiently accurate estimate of the peak of the coming year Measuring period for the purpose of correct setting of the encoder for controlling the counters will be appropriate Monitoring and statistical recording of the constantly changing load conditions in the distribution network should always be possible. For the setting of the bet height there is, as Fig. 1 shows, an ample amount Range of between about 75 and 95 01o of the maximum peak is available, its upper and lower limit only from a practical point of view, such as sufficient total duration the measurements or avoidance of any overlapping of the measurements on the mean exposure, to be determined.

Um die absatzhemmende Wirkung des Meßvorganges möglichst auf die Dauer der Spitzenanteilmessung selbst zu beschränken, ist eine sichtbare Anzeige der Meßzeiten, zweckmäßigerweise an den Zählern, erforderlich, damit jeder Abnehmer stets rasch feststellen kann, ob gerade eine Spitzenmessung stattfindet oder nicht, und dadurch in die Lage versetzt wird, seine Ausgaben für den Leistungspreis durch geringere Stromabnahme während der Spitzenzeit entsprechend zu senken. Diese sichtbare Anzeige der WIeßzeit der Spitzenmessung kann beispielsweise in einer Signalscheibe bestehen, die während dieser Zeit vor ein Fenster des Zählers tritt. To the sales-inhibiting effect of the measuring process as possible on the Limiting the duration of the peak fraction measurement itself is a visible indication of the measuring times, expediently at the meters, required so that every customer can always quickly determine whether a peak measurement is taking place or not, and thereby is in a position to reduce its expenses for the price of the service lower power consumption during the peak period accordingly. This visible The white time of the peak measurement can be displayed, for example, in a signal disk exist, which occurs during this time in front of a window of the counter.

Man könnte aber auch eine Glühlampe aufleuchten lassen oder ein akustisches Signal betätigen.But you could also let a light bulb light up or an acoustic one Activate the signal.

Die für die Durchführung des Leistungspreismeßverfahrens der Erfindung erforderlichen zusätzlichen Vorrichtungen sind sehr einfach. In einer Zentralstelle, also im Kraftwerk oder in einem Unterwerli, ist ein als Wattmeter ausgebildetes Schaltgerät vorgesehen, das diejenige Netzbelastung mißt, deren Spitzenanteile bei den einzelnen Abnehmer bestimmt werden sollen. Dieses Schaltgerät nimmt dann mittels Fernsteuerung bei den einzelnen Abnehmern die Umschaltung vor. Bei diesen Abnehmern wird zur Messung des Arl)eits- und des Leistungspreises grundsätzlich nur ein kWh-Zähler je Abnehmer benötigt. Der Zähler besitzt zwei Zählwerlse, davon steht das eine mit dem Laufwerk dauernd in Eingriff und mißt die gesamte Arbeit, während das andere zur gesonderten Messung der in der Spitzeneinschaltzeit verbrauchten kWh von dem in der Zentrale angeordneten wattmetri schen Schaltgerät ein- und ausgerückt wird. Beim Vergleich mit einem normalen Doppeltarifzähler taucht also bei der Anordnung nach der Erwindung nur eines dieser beiden Zählwerke gesteuert zu werden. The one for performing the power price measurement method of the invention required additional devices are very simple. In a central office, So in the power plant or in a Unterwerli, a wattmeter is designed Switching device is provided that measures the network load whose peak proportions to be determined by the individual customer. This switching device then takes by means of Remote control for the individual customers. With these customers In principle, only one kWh meter is used to measure the work and service price required per customer. The counter has two counters, one of which is with the drive is constantly engaged and measures all the work while the other for separate measurement of the kWh consumed during the peak switch-on time of the Wattmetri switching device arranged in the control center is engaged and disengaged. When comparing it with a normal double-tariff meter, the arrangement appears to be controlled after the development of only one of these two counters.

Für die Durchbildung des in der Zentralstelle angeordneten wattmetrischen Schaltgerätes sind folgende Gesichtspunkte maßgebend: Erstens müssen die Kontakte, mit denen das wattinetrische Schaltgerät in Abhängigkeit von der in der Zentralstelle vorhandenen Gesamtlast gesteuert wird, nach der Höhe dieser Belastung einstellbar sein, zweitens soll ein ausreichender toter Bereich zwischen den Ein- und Ausschaltkontakten, mit lenden die Ein- und Ausschaltung der Spitzenzählwerke bei den einzelnen Abnehmer durchgeführt wird, vorhanden sein. Ferner ist der Einbau einer Verzögerungsvorriclltullg an dem wattmetrischen Schaltgerät der Zentrale zweckmäßig, die den Einfluß kurzzeitiger Relastungsschwankungen in der Nähe der Einsatzhöhe des Schaltgerätes unwirksam macht. Das wattmetrische Schaltgerät steuert ferner in der Zentrale gleichzeitig mit der Steuerung der Zählwerk bei den einzelnen bnehmern einen Zeitzähler zur Messung der jährlichen Gesamtdauer der Einzeleinschaltzeiten. For the development of the wattmetric arranged in the central office Switchgear, the following aspects are decisive: First, the contacts, with which the wattinetric switching device depends on the in the central office existing total load is controlled, adjustable according to the level of this load Second, there should be a sufficient dead area between the switch-on and switch-off contacts, with lenden the switching on and off of the peak counters for the individual customers is carried out. Furthermore, the installation of a delay device is possible on the wattmetric switching device of the control center expediently, the influence of short-term Makes load fluctuations in the vicinity of the operating altitude of the switching device ineffective. The wattmetric switching device also controls in the control center at the same time as the Control of the counter at the individual recipients a time counter to measure the annual total duration of the individual switch-on times.

Für die Fernsteuerung der einzelnen Zählwerke von dem in der Zentrale untergebrach ten wattmetrischen Schaltgerät kann man an sich bekannte Ferustenerungsverfahren benutzen. Bei der sog. Schaltdrahtsteuerung sind zwischen der Zentrale und den einzelnen Abnehmer dünne Hilfsleitungen verlegt, über die der Schaltapparat der Zentrale die Umschaltung der einzelnen Zähler durchführt. For remote control of the individual counters from the one in the control center Untergebrach th wattmetric switching device can be known Ferustenerungsverfahren use. With the so-called jumper wire control, there are between the control center and the individual Customer laid thin auxiliary lines through which the switchgear of the control center Switches the individual counters.

Es kann dazu ein einpoliges Schaltdrahtnetz auf dem Gestänge von Freileitungsortsnetzen benutzt werden. Bei der Neuverlegung von Kabelnetzen kann gleichzeitig ein schwacher Leiter mitverlegt werden, etwa nach Art des üblichen Meßdrahtes für Prüfzweclie, was bei genügender Ahnehmerdichte in den meisten ställen wirtschaftlich durchführbar ist.For this purpose, a single-pole jumper wire network on the rods of overhead line networks can be used to be used. When laying new cable networks, a weak Conductors are also laid, for example in the manner of the usual measuring wire for test purposes, which is economically feasible in most stables if there is a sufficient number of recipients is.

In Netzen, in denen die Verlegung von Hilfsleitungen unwirtschaftlich teuer würde, kann man das ebenfalls bekannte Überlagerungsverfahren benutzen. Bei diesem werden dem Netz beispielsweise Spannungen hoher Frequenz überlagert, die bei dem einzelnen Abnehmer Relais steuern. Dieses Verfahren arbeitet um so wirtschaftlicher, je größer die Zahl der zu steuernden Meßgeräte und die Ausdehnung des Netzes ist. Es kommt daher hauptsächlich für größere und mittlere Städte, ferner für geeignete ländliche Versorgungsgebiete mit gut vermaschten WIittelspannungsvertei lungsuetzen in Betracht. In networks in which the laying of auxiliary lines is uneconomical would be expensive, one can use the also known overlay method. at for example, high-frequency voltages are superimposed on the network Control relays at the individual consumer. This process works all the more economically, the greater the number of measuring devices to be controlled and the expansion of the network. It is therefore mainly used for larger and medium-sized cities, and also for suitable ones Rural supply areas with well-meshed medium-voltage distributions into consideration.

Das Üb erl agerungsverfahren erfordert beim Abnehmer ein Relais, das auf die Ein- und Nusrüelsimpulse eines in der Zentralstelle befudlichen Impulssenders, der seinerseits wieder von dem wattmetrischen Schaltgerät gesteuert wird, anspricht und das das Lei stungszählwerl; ein- und ausschaltet. Die Gesamtzahl der dabei erforderlichen Relais läßt sich dadurch wesentlich herabsetzen, daß man für mehrere Abnehmer ein gemeinsames Relais vorsieht, das seinerseits über Hilfsleitungen zu den einzelnen Zählern die Umschaltung vornimmt. Beispielsweise ist für Mehrfamilienwohnungen, für größere Mietshäuser, für eng bebaute Straßen ein gemeinsames Relais vorgesehen, das mittels Uberlagerungsimpulse gesteuert wird, das aber die einzelnen Zähler über Schaltdrahtanschlüsse steuert. The transfer procedure requires a relay from the customer, that on the input and nutritious impulses of an impulse transmitter located in the central office, which in turn is controlled by the wattmetric switching device, responds and that the performance counter; turns on and off. The total number of required Relay can be significantly reduced by having one for several customers provides a common relay, which in turn via auxiliary lines to makes the switchover for the individual counters. For example, for multi-family apartments, for larger apartment buildings, a shared relay is provided for narrowly built-up streets, which is controlled by means of superimposition pulses, but which the individual counters via Jumper connections controls.

Claims (7)

PATENTANSPRÜCHE: I. Tarifeinrichtung zur Feststellung des Anteils der einzelnen Abnehmer eines Elektrizitätsnetzes an der Spitzenbelastung des Netzes, dadurch gekennzeichnet, daß bei Überschreitung einer bestimmten, in der Nähe der Spitzenlast gelegenen Belastung des Netzes von einer ZentraIstelle aus bei den einzelnen Abnehmern eine die elektrische Arbeit zählende Vorrichtung (Sonderzählwerk), zweckmäßig unter Auslösung einer Anzeige- oder Meldevorrichtung, eingeschaltet und bei Unterschreitung einer bestimmten, in der Nähe der Spitzenlast gelegenen Netzbelastung wieder ausgeschaltet wird dnd daß in der Zentralstelle die Gesamtdauer aller Einzelzeiten, während denen bei den Abnehmern die Sonderzählwerke, eingeschaltet sind, jeweils für eine Meßperiode gemessen wird. PATENT CLAIMS: I. Tariff system for determining the share the individual consumers of an electricity network at the peak load of the network, characterized in that when a certain limit is exceeded, close to the Peak load on the network from a central point at the individual A device that counts the electrical work (special counter) is expedient for customers when a display or signaling device is triggered, switched on and if the value falls below the limit a certain grid load near the peak load is switched off again becomes dnd that in the central office the total duration of all individual times during which at the customers the special counters are switched on, each for one measuring period is measured. 2. Anordnung nach Anspruch 1, dadurch gekennzeichnet, daß der Elektrizitätszähler bei den Abnehmern während der Spitzenbelastung auf das Sonderzählwerk geschaltet wird. 2. Arrangement according to claim 1, characterized in that the electricity meter switched to the special register for customers during peak loads will. 3. Anordnung nach Anspruch 1, dadurch gekennzeichnet, daß der Elektrizitätszähler während der Spitzenbelastung auch ein Sonderzählwerk antreibt. 3. Arrangement according to claim 1, characterized in that the electricity meter a special counter also drives during peak loads. 4. Anordnung nach Anspruch 1, dadurch gekennzeichnet, daß in der Zentralstelle ein als Wattmeter ausgebildetes Schaltgerät vorgesehen ist, das entweder mit Hilfe von Hilfsleitungen (Schaltdrahtsteuerung) oder mit Hilfe einer dem Netze überlagerten, zweckmäßig höhere Frequenz aufweisenden Steuerspannung bei den einzelnen Abnehmern das Sonderzählwerk ein- und ausschaltet. 4. Arrangement according to claim 1, characterized in that in the Central unit designed as a wattmeter switching device is provided that either with the help of auxiliary lines (jumper wire control) or with the help of one of the networks superimposed, expediently higher frequency having control voltage for the individual Switches the special counter on and off. 5. Anordnung nach Anspruch 4, bei der eine dem Netz überlagerte Spannung beim Verbraucher ein Relais ein- und ausschaltet, dadurch gekennzeichnet, daß das Relais für eine Gruppe von Abnehmern vorvorgesehen ist und die Sonderzählwerke der Abnehmer mittels Hilfsleitungen ein-und ausschaltet. 5. Arrangement according to claim 4, wherein a voltage superimposed on the network when the consumer switches a relay on and off, characterized in that the Relay is provided for a group of customers and the special counters Switches consumer on and off by means of auxiliary lines. 6. Anordnung nach Anspruch 1, dadurch gekennzeichnet, daß zweckmäßig in der Zentralstelle eine Verzögerungsvorrichtung vorgesehen ist, die den Einfluß kurzzeitiger Belastungsschwankungen auf die Einschaltung oder Ausschaltung der bei den einzelnen Abnehmern vorgesehenen Sonderzählwerke unwirksam macht. 6. Arrangement according to claim 1, characterized in that expedient a delay device is provided in the central office, the influence short-term load fluctuations on the activation or deactivation of the makes the special counters intended for the individual customers ineffective. 7. Anordnung nach Anspruch 1, dadurch gekennzeichnet, daß die Fernsteuerung der Sonderzählwerke von einem im Speiseschwerpunkt des Netzes liegenden Umspannwerk aus erfolgt, dessen Belastungsverlauf der mittleren Netzbelastung entspricht. 7. Arrangement according to claim 1, characterized in that the remote control the special counters from a substation located in the main supply point of the network takes place, the load curve of which corresponds to the mean network load. Zur Abgrenzung des Anmeldungsgegenstandes vom Stand der Technik sind im Erteilungsverfahren in Betracht gezogen worden: deutsche Patentschrift Nr. 410 796 446 I27, 99021; »EleEtrische Energwewirtschaft« von R. Schneider (Verlag Julius Springer, Berlin) 1936 S. 246 und S. 343 bis 352. To distinguish the subject of the application from the state of the art are Considered in the grant procedure: German patent specification No. 410 796 446 I27, 99021; "EleEtrische Energwewirtschaft" by R. Schneider (Verlag Julius Springer, Berlin) 1936 p. 246 and p. 343 to 352.
DES130266D 1938-01-01 1938-01-01 Tariff establishment Expired DE740381C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DES130266D DE740381C (en) 1938-01-01 1938-01-01 Tariff establishment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DES130266D DE740381C (en) 1938-01-01 1938-01-01 Tariff establishment

Publications (1)

Publication Number Publication Date
DE740381C true DE740381C (en) 1943-10-25

Family

ID=7538393

Family Applications (1)

Application Number Title Priority Date Filing Date
DES130266D Expired DE740381C (en) 1938-01-01 1938-01-01 Tariff establishment

Country Status (1)

Country Link
DE (1) DE740381C (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE410796C (en) * 1924-06-15 1925-03-07 Aeg Over-consumption counter
DE446127C (en) * 1927-06-24 Stanislaus Walloschek Point counter with differential gear for electrical counters with double counter arranged next to each other

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE446127C (en) * 1927-06-24 Stanislaus Walloschek Point counter with differential gear for electrical counters with double counter arranged next to each other
DE410796C (en) * 1924-06-15 1925-03-07 Aeg Over-consumption counter

Similar Documents

Publication Publication Date Title
WO2010018197A2 (en) Apparatus for measuring power output and/or consumption parameters in a low voltage network
DE102017121457B4 (en) System and method for detecting amounts of energy
EP3167412A1 (en) Method and apparatus for forecasting the temporal trend in a power requirement for a residential complex
DE102007063513B4 (en) Production energy data collection and analysis system
DE102007044166B4 (en) Arrangement for measuring current yield and / or consumption variables in a low-voltage network, together with the associated method
EP2237212A1 (en) Method for itemising the electrical consumption of a number of electrical consumers and device for same
DE740381C (en) Tariff establishment
DE3426542C2 (en)
EP2527850A1 (en) Voltage-dependent meter
DE2316341A1 (en) PROCESS FOR CONTINUOUSLY DISTRIBUTING ELECTRIC ENERGY
DE702275C (en) Process and device for monitoring work that has been performed with varying degrees of intensity over time
EP2618458B1 (en) Method for determining circuit states in energy supply networks and system for performing the method
DE102011113376A1 (en) Method for providing physical origin of generated electric current from e.g. atomic power plant to information system for power consumers, involves transferring information about actual current-mix based on physical origin of current
EP3477262B1 (en) Method for the load dependent consumption detection for different power sources in the end consumer area
DE755600C (en) Device for monitoring electricity consumption
CH711189A2 (en) A system for current rate control and power supply for a building, a method for controlling the current rate for a building and billing procedures for the power supply of a building.
DE202012011695U1 (en) electric circuit for consumption of self-generated electric power with devices of different tariff position
DE703235C (en) Fault indicator for the voltage circuit of power measuring devices in three-phase three-wire systems
EP0505526B1 (en) Maximum monitor, especially for rate calculation
EP3700042B1 (en) System for operating of an energy storage
DE2150948A1 (en) DEVICE FOR LIMITING THE CURRENT DRAWN FROM AN ELECTRICAL SUPPLY NETWORK
DE926021C (en) Method for analyzing the consumption taken from an energy distribution network
AT405585B (en) Electricity tariff-dependent load profile optimization system
DE917380C (en) Circuit arrangement for the arbitrary additional supply of pantographs with cheaper load compensation current and counting of the same
WO2016005451A1 (en) Energy management method and energy management device for a residential complex with one or more residential units or for a city area