DE4120112C1 - Symmetrising PWM transformer feeding inverter bridges - involves force switching off electronic switches of bridge branch pairs independently of control - Google Patents

Symmetrising PWM transformer feeding inverter bridges - involves force switching off electronic switches of bridge branch pairs independently of control

Info

Publication number
DE4120112C1
DE4120112C1 DE19914120112 DE4120112A DE4120112C1 DE 4120112 C1 DE4120112 C1 DE 4120112C1 DE 19914120112 DE19914120112 DE 19914120112 DE 4120112 A DE4120112 A DE 4120112A DE 4120112 C1 DE4120112 C1 DE 4120112C1
Authority
DE
Germany
Prior art keywords
counter
switch
clock
switched
time
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
DE19914120112
Other languages
German (de)
Inventor
Thomas Dipl.-Ing. Dihlmann
Jacek Dipl.-Ing. 1000 Berlin De Pawlak
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Bombardier Transportation GmbH
Original Assignee
AEG Westinghouse Transport Systeme GmbH
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by AEG Westinghouse Transport Systeme GmbH filed Critical AEG Westinghouse Transport Systeme GmbH
Priority to DE19914120112 priority Critical patent/DE4120112C1/en
Application granted granted Critical
Publication of DE4120112C1 publication Critical patent/DE4120112C1/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02MAPPARATUS FOR CONVERSION BETWEEN AC AND AC, BETWEEN AC AND DC, OR BETWEEN DC AND DC, AND FOR USE WITH MAINS OR SIMILAR POWER SUPPLY SYSTEMS; CONVERSION OF DC OR AC INPUT POWER INTO SURGE OUTPUT POWER; CONTROL OR REGULATION THEREOF
    • H02M1/00Details of apparatus for conversion
    • H02M1/32Means for protecting converters other than automatic disconnection
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02MAPPARATUS FOR CONVERSION BETWEEN AC AND AC, BETWEEN AC AND DC, OR BETWEEN DC AND DC, AND FOR USE WITH MAINS OR SIMILAR POWER SUPPLY SYSTEMS; CONVERSION OF DC OR AC INPUT POWER INTO SURGE OUTPUT POWER; CONTROL OR REGULATION THEREOF
    • H02M7/00Conversion of ac power input into dc power output; Conversion of dc power input into ac power output
    • H02M7/42Conversion of dc power input into ac power output without possibility of reversal
    • H02M7/44Conversion of dc power input into ac power output without possibility of reversal by static converters
    • H02M7/48Conversion of dc power input into ac power output without possibility of reversal by static converters using discharge tubes with control electrode or semiconductor devices with control electrode

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Inverter Devices (AREA)

Abstract

Single phase inverter bridges feeding transformers and PWM controlled are symmetrised by switching-off, electronic switches (4.1,4.2) of the branch pairs of the inverter bridge (1), conducting the overcurrent independently of the control. The established switched-on duration (T) of the electronic switch (e.g. 4.1), conducting during the last half cycle and now switched-off, is evaluated in the bridge branch pair. The basic initial time, which increases for a selected additional time (deltaT) as a measure for the switched on duration of the other current conducting switch (e.g. 4.2), is valid in the following half cycle in the bridge branch. The switched-on duration for the electronic switches with subsequent release, is increased across the further cycles in steps, for respectively a further additional time, up to the desired value specified by the control. USE/ADVANTAGE - For DC converters, with rapid attainment of the rated control value.

Description

Die Erfindung bezieht sich nach dem Oberbegriff des Anspruches 1 zunächst auf ein Verfahren zur Symmetrierung von über Regelungen impulsbreitenmoduliert be­ triebene, auf Transformatoren arbeitende Wechselrichterbrücken, insbesondere Einphasen-Wechselrichterbrücken. (siehe hierzu die unten genannte "Electronic" 5 (März 1982) S. 55-58).According to the preamble of claim 1, the invention initially relates to a method for the symmetrization of pulse width modulated via controls driven inverter bridges working on transformers, in particular Single-phase inverter bridges. (See the "Electronic" 5 (March 1982) pp. 55-58 below).

Anwendungsgebiet sind z. B. Gleichspannungs­ wandler. Verschiedene Arten bekannter Gleichspannungswandler sind in den Fig. 2 bis 4 dargestellt. Die Gleichspannungswandler können mit Halbbrücken-Wechsel­ richtern (vgl. Fig. 2) oder mit Vollbrücken-Wechselrichtern (vgl. Fig. 3) oder auch (vgl. Fig. 4) als Gegentaktwandler mit deren Varianten arbeiten. Generell wird dabei eine Eingangsgleichspannung Ue periodisch mittels eines Wechsel­ richters 1 in Gleichspannungsimpulse umgesetzt, die einen Transformator 2 in wechselnder Richtung durchfluten. Die ausgangsseitig abnehmbare transformierte Impulsspannung wird in einem Gleichrichter 3 gleichgerichtet und steht als ge­ wandelte Ausgangsgleichspannung Ua zur Verfügung. Allgemein wird die Ausgangs­ spannung Ua oder der Ausgangsstrom geregelt, indem die Einschaltzeit bzw. -dauer T der einander abwechselnd stromführenden elektronischen Schalter bzw. Halbleiterventile (z. B. 4.1, 4.2) den jeweiligen Brückenzweigen des Wechsel­ richters 1 durch einen Regler vorgegeben wird. Zusätzlich werden meist - be­ trieblich bedingt - Überwachungsschaltungen, z. B. Überstromüberwachungen vorge­ sehen, die in bestimmten Fällen (z. B. bei zu starker Belastung der Ausgangs­ spannung Ua) die durch den Regler erzwungene verkürzte Einschaltzeit zusätzlich reduzieren können. Das kann zu einer stark asymmetrischen Aussteuerung des Trans­ formators 2 in diesen Betriebszuständen führen und bedeutet physikalisch ein Betrieb des Transformators 2 mit stark unterschiedlichen Spannungszeitflächen von Halbperiode zu Halbperiode. Dadurch baut sich im Transformator 2 ein mag­ netischer Fluß mit Gleichanteil auf, der in der Lage ist, über mehrere Perioden der Taktfrequenz das Magnetmaterial durch Vormagnetisierung in die Sättigung zu treiben. Das wiederum führt zu unerwünschten zusätzlichen, nicht durch die ausgangsseitige Belastung verursachten Überströmen in den elektronischen Schal­ tern 4, die sich durch die konträren Einschaltzeitvorgaben von Regler und Über­ wachung von Zyklus zu Zyklus verstärken. Ferner sind Fälle denkbar, wo bei durch Transformatorsättigung bedingter großer Stromanstiegsgeschwindigkeit di/dt in den Schaltern 4 - wegen der begrenzten Reaktionsgeschwindigkeit der Überstrom­ begrenzung sowie des Stellgliedes - ein rechtzeitiger schützender Eingriff un­ möglich ist und deshalb Schäden durch Zerstörung der Schalter 4 drohen.Field of application are e.g. B. DC converter. Different types of known DC-DC converters are shown in FIGS. 2 to 4. The DC-DC converters can work with half-bridge inverters (see FIG. 2) or with full-bridge inverters (see FIG. 3) or also (see FIG. 4) as push-pull converters with their variants. In general, an input DC voltage U e is periodically converted into DC voltage pulses by means of an alternating converter 1 which flood a transformer 2 in an alternating direction. The transformable voltage which can be removed on the output side is rectified in a rectifier 3 and is available as a converted output direct voltage U a . In general, the output voltage U a or the output current is regulated by the switch-on time or duration T of the alternating current-carrying electronic switches or semiconductor valves (e.g. 4.1 , 4.2 ), the respective bridge branches of the inverter 1 is predetermined by a controller . In addition, monitoring circuits, e.g. B. Overcurrent monitors can be seen, which in certain cases (e.g. when the output voltage U a is too heavily loaded) can additionally reduce the shortened switch-on time enforced by the controller. This can lead to a highly asymmetrical modulation of the transformer 2 in these operating states and means physically an operation of the transformer 2 with greatly different voltage time areas from half period to half period. As a result, a magnetic flux with a DC component builds up in the transformer 2 , which is able to drive the magnetic material into saturation by premagnetization over several periods of the clock frequency. This, in turn, leads to undesired additional overcurrents in the electronic switches 4 , not caused by the load on the output side, which are amplified by the contrary switch-on times of the controller and monitoring from cycle to cycle. Furthermore, cases are conceivable where, due to transformer saturation, a high current rise rate di / dt in the switches 4 - due to the limited reaction speed of the overcurrent limitation and the actuator - a timely protective intervention is impossible and therefore damage through destruction of the switches 4 is impending.

Insbesondere in Halbbrückenschaltungen (vgl. Fig. 2) führen die vorgenannten Er­ scheinungen besonders schnell zu Asymmetrien mit den beschriebenen negativen Auswirkungen, weil der Transformator 2 einseitig an einen kapazitiven Mittel­ punkt angeschlossen ist und sich dieser Mittelpunkt durch den von der Asymmetrie verursachten Gleichanteil aus der Mitte verlagert, womit sich die Asymmetrie noch mehr verstärkt.Particularly in half-bridge circuits (see FIG. 2), the above-mentioned phenomena lead particularly quickly to asymmetries with the negative effects described, because the transformer 2 is unilaterally connected to a capacitive center and this center point is due to the constant component caused by the asymmetry Center shifted, which increases the asymmetry even more.

Zur Abhilfe wird bei bestimmten ausgeführten Lösungen der Wechselrichter nach dem Erreichen der Stromgrenze vorübergehend gesperrt, um den Transformator zu entmagnetisieren und dieser wird dann mit Sanftanlauf wieder gestartet. Die Be­ triebsunterbrechungen beim Eingreifen des Schutzes sind für die angeschlossenen Verbraucher oft nachteilig, so daß ein solcher Betrieb daher nur bedingt ver­ tretbar ist.To remedy this, the inverter is used for certain implemented solutions temporarily blocked when the current limit is reached in order to close the transformer Demagnetize and this is then started again with a soft start. The Be Drive interruptions when the protection intervenes are for the connected Consumers often disadvantageous, so that such an operation is therefore limited is pedalable.

Zur Symmetrierung von Gegentaktwandlern und auch Brückenwandlern ist ein Ver­ fahren bekanntgeworden, das durch eine Hilfsschaltung Unsymmetrien in der Gleich­ stromvormagnetisierung der Wandler feststellt und auswertet (Electronic 5 (März 1982), S. 55-58). Es werden dazu dort die Primärstromimpulse zweier im Primär­ stromkreis liegender Schalttransistoren verglichen und Unsymmetrien durch Korrek­ turimpulse auf Symmetriereingänge einer zusätzlichen Steuerschaltung ausgeglichen. Die Steuerschaltung bewirkt eine gegenläufige Tastzeitkorrektur für die Schalt­ transistoren. Der Aufwand ist nicht unbeträchtlich, der Regelsollwert wird nur langsam erreicht.For balancing push-pull converters and also bridge converters, a Ver drive became known through an auxiliary circuit asymmetries in the same current pre-magnetization of the converter is determined and evaluated (Electronic 5 (March 1982), pp. 55-58). There are two primary currents in the primary circuit switching transistors compared and asymmetries by correction door impulses balanced on balancing inputs of an additional control circuit. The control circuit effects a counteracting duty time correction for the switching transistors. The effort is not insignificant, the standard setpoint only becomes slowly reached.

Aufgabe der Erfindung ist es, eine verbesserte Symmetriereinrichtung zu schaffen, mit der unter Anwendung eines veränderten Prinzips der Regelsollwert schneller erreichbar ist.The object of the invention is to provide an improved balancing device, with the control setpoint faster using a modified principle is achievable.

Diese Aufgabe wird gemäß den kennzeichnenden Merkmalen des Anspruches 1 gelöst. Eine vorteilhafte Ausgestaltung des Verfahrens ist Anspruch 2 entnehmbar. Die weiteren Ansprüche beziehen sich auf Anordnungen zur Durchführung des Verfahrens.This object is achieved in accordance with the characterizing features of claim 1. An advantageous embodiment of the method can be found in claim 2. The  further claims relate to arrangements for performing the method.

Anhand eines schematischen Ausführungsbeispieles für eine Anordnung wird die Er­ findung im nachstehenden näher erläutert.Using a schematic embodiment for an arrangement, the Er invention explained in more detail below.

Es zeigen:Show it:

Fig. 1 das Prinzip einer Überstrombegrenzung mit symmetrierenden Eigenschaften für einen einphasigen Wechselrichter Fig. 2 bis 4 zur Anwendung geeignete verschiedene Ausführungsformen bekannter schon be­ sprochener Gleichspannungswandler. Fig. 1 shows the principle of an overcurrent limitation with symmetrizing properties for a single-phase inverter . Fig. 2 to 4 suitable various embodiments of known DC voltage converters already known.

Wie bereits zu den Fig. 2 und 4 beschrieben, werden die elektronischen Schalter (z. B. 4.1, 4.2) in den Brückenzweigen eines einphasigen Wechselrichters 1 bei asymmetrischer Aussteuerung des nachgeschalteten Transformators 2 stark belastet. Als Schutzmaßnahme wird deshalb nach der Erfindung der betroffene Schalter (z. B. 4.1) nach Erreichen seiner maximal zulässigen Stromgrenze sofort abgeschaltet. Die Einschaltdauer wird jedoch festgehalten, und um den Wechselrichter 1 wieder zu symmetrieren, dann in der nächsten Halbperiode der andere elektronische Schalter (z. B. 4.2) im anderen Wechselrichterzweig nur für eine Einschaltdauer T wie der vorher zwangsabgeschaltete Schalter 4.1, jedoch zuzüglich einer Zusatzzeit ΔT angesteuert. Dies geschieht auch dann, wenn die vom Regler vorgegebene Einschalt­ dauer an sich länger sein sollte, bzw. der Strom in diesem elektronischen Schal­ ter 4.2 zur Abschaltzeit die Abschaltgrenze noch nicht erreicht hat. Anschließend wird über weitere Perioden die Einschaltdauer der elektronischen Schalter 4.1 und 4.2 in den Wechselrichterzweigen schrittweise um diese Zusatzzeit ΔT weiter er­ höht, bis die vom Regler vorgegebene Größe erreicht wird. Tritt während dieses Symmetrierungsvorganges erneut Überstrom auf, dann wiederholt sich der Vorgang; eine neue Symmetrierung mit einer neuen Grundanfangszeit wird vorgenommen.As already described for FIGS. 2 and 4, the electronic switches (for example 4.1 , 4.2 ) in the bridge branches of a single-phase inverter 1 are subjected to high loads when the downstream transformer 2 is driven asymmetrically. As a protective measure, the switch concerned (for example 4.1 ) is therefore switched off immediately after reaching its maximum permissible current limit. However, the on-time is recorded, and in order to symmetrize the inverter 1 again, then in the next half-period the other electronic switch (e.g. 4.2 ) in the other inverter branch only for an on-time T like the previously switched off switch 4.1 , but plus an additional time ΔT controlled. This also happens if the switch-on duration specified by the controller should itself be longer, or the current in this electronic switch ter 4.2 has not yet reached the switch-off limit at the switch-off time. Then the duty cycle of the electronic switches 4.1 and 4.2 in the inverter branches is increased step by step by this additional time ΔT over further periods until the size specified by the controller is reached. If overcurrent occurs again during this balancing process, the process is repeated; a new symmetry with a new start time is made.

Zur Realisierung dieses Prinzips besteht die Schaltung nach Fig. 1 im wesentlichen aus drei Zählern A, B, C und einem digitalen Komparator 5. Die Zähler werden mittels eines Steuerwerkes 6 angesteuert. Zur Zeitvorgabe dient ein Taktgenerator 7. To implement this principle, the circuit according to FIG. 1 essentially consists of three counters A, B, C and a digital comparator 5 . The counters are controlled by a control unit 6 . A clock generator 7 serves to set the time.

Der 1. Zähler A ist ständig aktiv und mißt die Einschaltdauer eines elek­ tronischen Schalters (z. B. 4.1) mit Hilfe des Taktgenerators 7. Tritt ein Überstrom im Schalter 4.1 auf, dann wird der Inhalt QA des 1. Zählers A in den 2. Zähler B geladen. Das Zwangsabschalten jedes elektronischen Schalters 4, hier z. B. 4.1, aktiviert die Funktionen des 2. und 3. Zählers B und C. Zähler A wird über RA (= Reset A) zurückgesetzt.The 1st Counter A is constantly active and measures the duty cycle of an electronic switch (z. B. 4.1 ) using the clock generator 7th If an overcurrent occurs in switch 4.1 , the content QA of the 1st counter A is loaded into the 2nd counter B. The forced shutdown of each electronic switch 4 , here z. B. 4.1 , activates the functions of the 2nd and 3rd counters B and C. Counter A is reset via RA (= Reset A).

Zu Beginn der nächsten Halbperiode wird dem 2. Zähler B zusätzlich die Zu­ satzzeit ΔT zuaddiert. Gleichzeitig wird der 3. Zähler C zur Messung der Einschaltdauer des anderen elektronischen Zweigschalters, z. B. 4.2, frei­ gegeben. Ist der Inhalt QC des 3. Zählers C gleich dem Inhalt QB des 2. Zählers - die Einschaltdauer ist gleich der in der Vorperiode +ΔT - dann wird der gerade leitende elektronische Schalter, z. B. 4.2, über den Ausgang des Komparators 5 abgeschaltet.At the beginning of the next half-period, the additional counter time ΔT is added to the second counter B. At the same time the 3rd counter C for measuring the duty cycle of the other electronic branch switch, z. B. 4.2 , released. If the content QC of the 3rd counter C is equal to the content QB of the 2nd counter - the duty cycle is the same as in the previous period + ΔT - then the currently conductive electronic switch, e.g. B. 4.2 , switched off via the output of the comparator 5 .

Anschließend wird der Inhalt QB des 2. Zählers B wieder um ΔT erhöht. Der 3. Zähler C wird (über RC = Reset B) zurückgesetzt und kann in der nächsten Halbperiode wieder die Einschaltdauer des dann leitenden elektronischen Zweigschalters, z. B. 4.1, bestimmen. Überschreitet die über die Zähler bestimmte Einschaltzeit die Zeitdauer, die vom Regler vorgegeben ist, dann wird die Symmetrierung beendet. Zähler B wird über RB (= Reset B) zurückgesetzt.The content QB of the second counter B is then increased again by ΔT. The 3rd counter C is reset (via RC = Reset B) and can in the next half period again the duty cycle of the then conductive electronic branch switch, for. B. 4.1 , determine. If the switch-on time determined by the counter exceeds the time specified by the controller, the balancing is ended. Counter B is reset via RB (= Reset B).

Sollte während der Symmetrierungsphase erneut Überstrom auftreten, dann wird die Einschaltdauer des jeweils abgeschalteten elektronischen Schal­ ters 4 erneut im 1. Zähler A festgehalten und in den 2. Zähler B über­ tragen. Die Symmetrierung beginnt mit der neuen Zeit von Anfang an zu arbeiten.Should overcurrent occur again during the balancing phase, then the duty cycle of the electronic switch 4 that is switched off is again recorded in the first counter A and transferred to the second counter B. The symmetrization starts working from the beginning with the new time.

Durch die Erfindung ergeben sich insbesondere folgende Vorteile:The following advantages result in particular from the invention:

  • - Schutz des Umrichters: Die Schaltung begrenzt das Auftreten eines Überstroms.- Protection of the converter: The circuit limits the occurrence of a Overcurrent.
  • - Durch die Schaltung wird die Verstärkung der asymmetrischen Aus­ steuerung des Transformators 2 verhindert.- The circuit prevents the gain from the asymmetrical control of the transformer 2 .
  • - Über die Einschaltdauer wird die Strombelastung der Halbleiter­ schalter 4 ohne Betriebsunterbrechung symmetriert.- Over the duty cycle, the current load of the semiconductor switch 4 is symmetrized without interrupting operation.
  • - Das dynamische Verhalten des Umrichters wird verbessert. Ohne diese Symmetrierungsschaltung war bislang das Zuschalten von starken Lasten (große Motoren, Lüfter, Kompressoren) in bestimmten Fällen nur mit Betriebsunterbrechung möglich.- The dynamic behavior of the converter is improved. Without these Up until now, balancing circuit has been the connection of heavy loads (large motors, fans, compressors) in certain cases only with Business interruption possible.
  • - Die magnetischen Bauteile können besser ausgenutzt werden. Damit geht in der Regel eine Reduzierung der Baugröße und des Gewichtes in Verbindung mit geringeren Kosten einher.- The magnetic components can be better used. In order to is usually a reduction in size and weight combined with lower costs.
  • - Der Stromregler wird entlastet. Da er keine Schutzfunktionen mehr wahrnehmen muß, kann seine I-Zeitkonstante auf die Lastregelung im Wechselrichter 1 optimiert werden. (Zeitkonstante größer).- The current controller is relieved. Since he no longer has to perform any protective functions, his I-time constant can be optimized for the load control in inverter 1 . (Time constant larger).

Claims (9)

1. Verfahren zur Symmetrierung von über Regelungen impulsbreitenmoduliert betriebene, auf Transformatoren arbeitende Wechselrichterbrücken, ins­ besonder Einphasen-Wechselrichterbrücken, dadurch gekennzeichnet, daß unabhängig von der Regelung die elektronischen Schalter (4.1, 4.2) der Zweigpaare der Wechselrichterbrücke (1), die Überstrom führen, zwangs­ abgeschaltet werden, wobei die festgestellte Einschaltdauer (T) des während der letzten Halbperiode stromführenden und jetzt abgeschalteten elektro­ nischen Schalters (z. B. 4.1) im Brückenzweigpaar als eine Grundanfangszeit gewertet wird, die um eine definierte Zusatzzeit (ΔT) erhöht als Maß für die Einschaltdauer des während der folgenden Halbperiode stromführenden anderen Schalters (z. B. 4.2) im Brückenzweigpaar gültig ist und daß sich die Einschaltdauer für die einander ablösenden elektronischen Schalter (4.1, 4.2, 4.1 usw.) über die weiteren Perioden schrittweise um jeweils eine weitere Zu­ satzzeit (ΔT) bis zum vom Regler vorgegebenen Sollwert erhöht. 1. A method for symmetrizing inverter bridges operating on transformers, operated in a pulse-width-modulated manner on controls, in particular single-phase inverter bridges, characterized in that, independently of the control, the electronic switches ( 4.1 , 4.2 ) of the branch pairs of the inverter bridge ( 1 ) which carry overcurrent, are forcibly switched off, whereby the determined duty cycle (T) of the current-carrying and now switched-off electronic switch (e.g. 4.1 ) in the pair of bridges is rated as a basic start time, which is increased by a defined additional time (ΔT) as a measure of the duty cycle of the other switch (e.g. 4.2 ) carrying current during the following half-cycle is valid in the pair of bridges and that the duty cycle for the electronic switches ( 4.1 , 4.2 , 4.1 , etc.) that are replacing each other gradually increases over the other periods At set time ( ΔT) up to the setpoint specified by the controller. 2. Verfahren nach Anspruch 1, dadurch gekennzeichnet, daß bei einem erneuten überstromabhängigen Abschalten eines elektro­ nischen Schalters (z. B. 4.1) während des Symmetrierungsvorganges der Vorgang mit einer dabei neu festgestellten Grundanfangszeit wiederholt wird. 2. The method according to claim 1, characterized in that with a renewed overcurrent-dependent switching off of an electronic switch (z. B. 4.1 ) during the balancing process, the process is repeated with a newly determined basic start time. 3. Anordnung zur Durchführung des Verfahrens nach Anspruch 1, dadurch gekennzeichnet,
daß ein 1. Zähler (A) vorgesehen ist, der die Einschaltdauer des jewei­ ligen stromführenden Schalters (z. B. 4.1) in der einen Halbperiode über die Taktimpulse (clock A) eines Taktgenerators (7) mißt,
daß ein 2. Zähler (B) vorgesehen ist, der bei einer Zwangsabschaltung dieses Schalters (4.1) das Zählergebnis vom 1. Zähler (A) übernimmt und ein um eine definierte Zusatzzeit (ΔT) vergrößertes Ergebnis (QB) an einen Komparator (5) ausgibt,
daß ein 3. Zähler (C) vorgesehen ist, der die Einschaltdauer des anderen, in der Folgeperiode nun stromführenden Schalters (z. B. 4.2) über die Taktimpulse (clock C) des Taktgenerators (7) mißt und sein Zähler­ gebnis (QC) an den Komparator (5) ausgibt, der bei Gleichheit der Zählergebnisse beider Zähler (B und C) ein Schaltersperrsignal (c) für den gerade stromführenden anderen Schalter (4.2) abgibt.
3. Arrangement for performing the method according to claim 1, characterized in that
that a 1st counter (A) is provided which measures the on-time of the respective current-carrying switch (z. B. 4.1 ) in one half period via the clock pulses (clock A) of a clock generator ( 7 ),
that a second counter (B) is provided, which takes over the counting result from the first counter (A) when this switch ( 4.1 ) is switched off and a result (QB) increased by a defined additional time (ΔT) to a comparator ( 5 ) issues
that a third counter (C) is provided, which measures the duty cycle of the other switch, which is now current-carrying in the following period (e.g. 4.2 ) via the clock pulses (clock C) of the clock generator ( 7 ), and its counter result (QC) outputs to the comparator ( 5 ) which, if the count results of both counters (B and C) are the same, outputs a switch inhibit signal (c) for the other switch ( 4.2 ) which is currently carrying current.
4. Anordnung nach Anspruch 3, dadurch gekennzeichnet, daß ein Steuerwerk (6) für die Zähler (A, B, C) vorgesehen ist, daß die Taktimpulse (clock A, clock B, clock C) zu den Zählern (A, B, C) durchschaltet, diese startet und zurücksetzt.4. Arrangement according to claim 3, characterized in that a control unit ( 6 ) for the counter (A, B, C) is provided that the clock pulses (clock A, clock B, clock C) to the counters (A, B, C) switches through, this starts and resets. 5. Anordnung nach den Ansprüchen 3 und 4, dadurch gekennzeichnet, daß das Steuerwerk (6) eingangsseitig von Signalen für Zwangsabschal­ tung (b), Schaltersperre (c) und Beginn der Halbperiode (a) beauf­ schlagt wird.5. Arrangement according to claims 3 and 4, characterized in that the control unit ( 6 ) on the input side of signals for Zwangsabschal device (b), switch lock (c) and the beginning of the half-period (a) is beaten. 6. Anordnung nach den Ansprüchen 3 bis 5, dadurch gekennzeichnet, daß mit dem Signal "Zwangsabschaltung" (b) über das Steuerwerk (6) der 1. Zähler (A) zur Übergabe seines Zählergebnisses (QA) an den 2. Zähler (B) veranlaßt und selbst rückgesetzt (RA) wird, das übernommene Zählergebnis im 2. Zähler (B) um die definierte Zusatzzeit (ΔT) er­ höht und der 3. Zähler (C) gestartet wird. 6. Arrangement according to claims 3 to 5, characterized in that with the signal "forced shutdown" (b) via the control unit ( 6 ) of the 1st counter (A) for transferring its counting result (QA) to the 2nd counter (B ) is initiated and reset itself (RA), the counting result in the second counter (B) is increased by the defined additional time (ΔT) and the third counter (C) is started. 7. Anordnung nach den Ansprüchen 3 bis 5, dadurch gekennzeichnet, daß mit dem Signal "Schaltersperre" (c) der stromführende elektro­ nische Schalter (z. B. 4.2) ausgeschaltet und über das Steuerwerk (6) der 3. Zähler (C) angehalten und rückgesetzt (RC) wird.7. Arrangement according to claims 3 to 5, characterized in that with the signal "switch lock" (c) the current-carrying electronic switch (z. B. 4.2 ) is switched off and the control unit ( 6 ) of the 3rd counter (C) stopped and reset (RC). 8. Anordnung nach den Ansprüchen 3 bis 5, dadurch gekennzeichnet, daß mit dem Signal "Anfang der Halbperiode" (a) über das Steuerwerk (6) das im 2. Zähler (B) gespeicherte Zählergebnis (QB) um eine weitere definierte Zusatzzeit (ΔT) erhöht und der 3. Zähler (C) erneut für eine definierte Einschaltzeit des jeweils anderen elek­ tronischen Schalters (jetzt z. B. wieder 4.1) innerhalb der nächsten Halbperiode gestartet wird.8. Arrangement according to claims 3 to 5, characterized in that with the signal "beginning of the half period" (a) via the control unit ( 6 ) the counting result (QB) stored in the second counter (B) by a further defined additional time ( ΔT) increased and the 3rd counter (C) is started again for a defined switch-on time of the other electronic switch (now e.g. again 4.1 ) within the next half period. 9. Anordnung nach einem der vorhergehenden Ansprüche, dadurch gekennzeichnet, daß mit Erreichen des Sollwertes der Regelung ohne einen Überstrom alle Zähler zurückgesetzt werden (RA, RB, RC) und nur der 1. Zähler (A) wirksam bleibt, dessen Zählergebnis jeweils mit dem Signal "An­ fang einer Halbperiode" (a) über das Steuerwerk (6) auf 0 zurückge­ setzt wird (RA).9. Arrangement according to one of the preceding claims, characterized in that upon reaching the setpoint of the control without an overcurrent, all counters are reset (RA, RB, RC) and only the 1st counter (A) remains effective, the counting result of which is in each case with the Signal "At the beginning of a half period" (a) is reset to 0 via the control unit ( 6 ) (RA).
DE19914120112 1991-06-15 1991-06-15 Symmetrising PWM transformer feeding inverter bridges - involves force switching off electronic switches of bridge branch pairs independently of control Expired - Lifetime DE4120112C1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DE19914120112 DE4120112C1 (en) 1991-06-15 1991-06-15 Symmetrising PWM transformer feeding inverter bridges - involves force switching off electronic switches of bridge branch pairs independently of control

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE19914120112 DE4120112C1 (en) 1991-06-15 1991-06-15 Symmetrising PWM transformer feeding inverter bridges - involves force switching off electronic switches of bridge branch pairs independently of control

Publications (1)

Publication Number Publication Date
DE4120112C1 true DE4120112C1 (en) 1992-08-13

Family

ID=6434223

Family Applications (1)

Application Number Title Priority Date Filing Date
DE19914120112 Expired - Lifetime DE4120112C1 (en) 1991-06-15 1991-06-15 Symmetrising PWM transformer feeding inverter bridges - involves force switching off electronic switches of bridge branch pairs independently of control

Country Status (1)

Country Link
DE (1) DE4120112C1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4426721C1 (en) * 1994-07-22 1995-11-23 Burmester Audiosysteme Gmbh Circuit for correcting DC voltage component in AC supply voltage
AT511298A1 (en) * 2011-03-28 2012-10-15 Lutz Erhartt DYNAMIC PWM CONTROL FOR TRANSFORMER-COUPLED COUNTER-TERM INVERTERS

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
MACEK, Otto: Symmetrierung von Gegentakt- wandlern in: Electronic, H.5 (1982) S.55-58 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4426721C1 (en) * 1994-07-22 1995-11-23 Burmester Audiosysteme Gmbh Circuit for correcting DC voltage component in AC supply voltage
AT511298A1 (en) * 2011-03-28 2012-10-15 Lutz Erhartt DYNAMIC PWM CONTROL FOR TRANSFORMER-COUPLED COUNTER-TERM INVERTERS
AT511298B1 (en) * 2011-03-28 2014-06-15 Lutz Erhartt DYNAMIC PWM CONTROL FOR TRANSFORMER-COUPLED COUNTER-TERM INVERTERS

Similar Documents

Publication Publication Date Title
DE3007597C2 (en) Protective circuit arrangement for semiconductor switches
EP3523873B1 (en) Direct current converter and method for its operation
EP3028377B1 (en) Direct current converter
AT403865B (en) VOLTAGE CONVERSION DEVICE FOR A DC VOLTAGE CONSUMER
DE112011103585T5 (en) The power conversion
DE69733679T2 (en) Switching Power Supply
DE102020214013A1 (en) POWER CONVERTER, CONTROL PROCEDURE AND CONTROL PROGRAM
EP0208065B1 (en) Circuit arrangement for driving high-voltage power transistors
DE69210940T2 (en) Power converter
DE2524367A1 (en) CIRCUIT FOR THE CONVERSION OF AC VOLTAGES INTO A DC VOLTAGE OF CONSTANT SIZE
DE2546826A1 (en) CONTROL SWITCH FOR INVERTER
EP0203571B1 (en) Static inverter including a circuit to increase the current in case of a short circuit
EP0078252B1 (en) Electronic welding device
DE3429488A1 (en) ELECTRONIC SWITCHING DEVICE
EP0419727B1 (en) Circuit arrangement for a regulated flyback switching power supply
DE69310328T2 (en) Power supply with resonant load for arc welding
DE4120112C1 (en) Symmetrising PWM transformer feeding inverter bridges - involves force switching off electronic switches of bridge branch pairs independently of control
DE1169030B (en) Current limiting device
DE3215009C2 (en)
EP3931953A1 (en) Method for current limitation in the event of transient voltage variations at an ac output of a multi-level inverter and multi-level inverter
DE2849575C2 (en) Clocked power supply
DE3833700C2 (en)
DE2738838A1 (en) DC converter with single smoothing filter - has at least three transformers whose primaries are connected to source by controlled rectifiers to reduce voltage rating requirement
DE4342414A1 (en) Bi-directional power converter
EP0458055A2 (en) Pulse width modulation method for a convertor

Legal Events

Date Code Title Description
8100 Publication of the examined application without publication of unexamined application
D1 Grant (no unexamined application published) patent law 81
8364 No opposition during term of opposition
8327 Change in the person/name/address of the patent owner

Owner name: DAIMLERCHRYSLER RAIL SYSTEMS GMBH, 13627 BERLIN, D

8339 Ceased/non-payment of the annual fee