DE368517C - System for conveying the overburden from the overburden excavator to the disposal site - Google Patents

System for conveying the overburden from the overburden excavator to the disposal site

Info

Publication number
DE368517C
DE368517C DEG53242D DEG0053242D DE368517C DE 368517 C DE368517 C DE 368517C DE G53242 D DEG53242 D DE G53242D DE G0053242 D DEG0053242 D DE G0053242D DE 368517 C DE368517 C DE 368517C
Authority
DE
Germany
Prior art keywords
overburden
excavator
scaffolding
conveyor belt
conveying
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
DEG53242D
Other languages
German (de)
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to DEG53242D priority Critical patent/DE368517C/en
Application granted granted Critical
Publication of DE368517C publication Critical patent/DE368517C/en
Expired legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65GTRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
    • B65G37/00Combinations of mechanical conveyors of the same kind, or of different kinds, of interest apart from their application in particular machines or use in particular manufacturing processes
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65GTRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
    • B65G2812/00Indexing codes relating to the kind or type of conveyors
    • B65G2812/01Conveyors composed of several types of conveyors
    • B65G2812/012Conveyors composed of several types of conveyors for conveying material successively by a series of conveyors
    • B65G2812/014Conveyors composed of several types of conveyors for conveying material successively by a series of conveyors with relative movement between conveyors
    • B65G2812/015Conveyors composed of several types of conveyors for conveying material successively by a series of conveyors with relative movement between conveyors the conveyors being movably linked

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Structure Of Belt Conveyors (AREA)

Description

Anlage zur Förderung des Abraums vom Abraumbagger zur Ablagerungsstelle. Die Erfin(dung betrifft eine: Anlage zur För- derung des Abraums vom Aibrau:mhagger zur Ahliageriu.ngsstelle, bei der ein Förderband parallel zum Biagger@gleis und unabhängig vom Bagger !angeordnet ist. B,ei solchen Aalalgen ist es zweckmäßig, .das Förderbamld in mehrere, von starren und fahr- baren Gerüsten getzagene endlose Bänder zu ,unterteilen. Gemäß edier Erfinldiung sind nun zwischen .den einziehen Gerüsten federnde Längskupplungen ,angeordri,et, während je ein Endre .der Gerüste mit einer Gabel versehen ist, die .das Niadhbargerüst zwecks -Qu-ereim- stellwng umlfaßt. Be)i diesier Au#sbi-fdhuvg des Fördexbanldes läßt sich das Föridezbandunter genauer M- pseunig .an die Förd-erstraBe leicht verlegen, ohne .daß der Zushmmenhang der Gerüste untereinander @unid das Zus(ammenwrkeu 4er Tei-lförder,bänider ,gestört wird. Zweckmäßig wird auch für ein günstiges Zusammenwirken zwischen Bagger und. TevI- förd,erbändern Sorge getragen, iddemeiner- seits am Bia@gger und anderseits an den Ge- rüsten der Teilförlderbändier Leitvorrichtun- gen anigeordnet sind, die eiine gen:a,ne Einstel- lung der Fördierblaüdachs,e unter die Schütt- trchteriachse ermöglichen: Auf der Zeichnung ist--der Gegenstand der Erfindung beispielsweise veranschaulicht, @unid zwiar steilten dar .Abt. i -das unterteilte Förider`band in Siei- tenansiicbt, . . Abb. a den Grunldmiß herzu, Abb.:3 einen- Querschnitt durch das Förder- band Aibb..4 eine Einzelheit der Unterstützung dies starren Gerüstes jedes: TeIlförderbandles, Abb. 5 -das Baggergleis sawie idie Unter- stützjung für @d'as Gerüst eines _T:eilföridier- b@andieis .Alb, 6 die Verbindung zweier Blandgerlüste in der-Längsriftung, Abb.7 die Vorrichtung zum EinsteMen der iBan.dgerüste in ider Querrichturiig undi Abb. 8 .dlie=Einzichtung zur Einstollüng,der Förderbandgerüste unterhalb des Schütttrichters .des Baggers.System for conveying the overburden from the overburden excavator to the disposal site. The invention relates to a: system for conveying modification of the spoil from the Aibrau: mhagger for Ahliageriu.ngsstelle where a conveyor belt parallel to the Biagger @ track and independent of the Excavator! Is arranged. B, with such eel algae it is useful to .that Förderbamld in several, from rigid and mobile getzagene endless belts to getzagene scaffolding , subdivide. According to the invention are now springy between the scaffolding Couplings, angeordri, et, while each one Attach a fork to the end of the scaffolding is the .the Niadhbar framework for the purpose of -Qu-erect- position included. Be) i this Au # sbi-fdhuvg of the Fördexbanldes can the Föridezband under more precisely M- pseunig. slightly relocated to the FörderstraBe, without the clinging of the scaffolding among each other @unid the Zus (ammenwrkeu 4er Partial conveyor, tethered, is disturbed. It will also be useful for a cheap one Interaction between excavator and. TevI- support, ribbons, iddemein- on the one hand at the Bia @ gger and on the other hand at the equip the partial conveyor belt guide device are arranged that have their own: a, ne setting ment of the Fördierblaüdachs, e under the bulk Trchteriachse enable: On the drawing is - the subject of For example, invention exemplifies @unid between .Dep. i -the divided Förider`band in Sie- tenansiicbt,. . Fig. A the basic misconception, A bb.:3 a cross-section through the conveyor tape Aibb..4 a detail of support this rigid structure of each: partial conveyor belt, Fig. 5 - the dredging track sawie i the lower support young for @ d'as framework of a _T: eilföridier- b @ andieis .Alb, 6 the connection of two Bland scaffolding in the longitudinal drift, Fig.7 the device for adjusting of the iBan.dgerüst in ider transverse direction and i Fig. 8 .dlie = arrangement for the entry, the Conveyor belt frames below the hopper of the excavator.

Das Färdierband ist in -seiner Längsrichtung in eine Reihe einzelner endloser Bänder a unterteilt. Diese Bänder sind in starren Gerüsten b angeordnet. Jedes Band wird von einem besonderen Elektromotor aus angetrieben. Jodes Gerüst b ist an zwei Punkten unterstützt. Zweckmäßig eHolgt die Unterstützung mit Hufe zweier Drehgestelle e, die entweder .mit Rädern oder gemäß Abb. q. mit Raupenketten d .ausgestattet sein können.The Färdierband is in its longitudinal direction in a row of individual endless ribbons a divided. These belts are arranged in rigid frames b. Each belt is driven by a special electric motor. Iode's scaffolding b is supported at two points. Appropriately, the support follows with hooves two bogies e, which either .with wheels or as shown in Fig. q. with caterpillars d. can be equipped.

Um das Förderband auch einem Gelände anpassen rau können, das Hebungen und Senkungen besitzt, können das eine oder beide Drehgestelle mit einer Hebevorrichtung versehen werden, mit deren Hilfe das Gerüst b an ,dem einen Ende emporgehoben werden kann. DieuAusbildüng der H@6beivorrichtungen kann in der verschiedensten Art erifolgen.In order to adapt the conveyor belt to rough terrain, the lifts and countersinks, one or both of the bogies can be lifted are provided, with the help of which the scaffold b at one end are lifted up can. The training of the lifting devices can be carried out in the most varied of ways.

Die Hebevorrlichtung kann auch zwischen den Drehgestellen angeordnet werden. Sie findet alsdann ihr Widerlager am Erdboden. Die Hebevorrichtung muß alsdann so ausgebildet sein, daß sie eine Drehbewegung des Gerüstes um die wagerechte Querachse ermöglicht.The lifting device can also be arranged between the bogies will. It then finds its abutment on the ground. The lifting device must then be designed so that it rotates the frame around the horizontal transverse axis enables.

Wie Alb. i erkennen läßt, sind die einzelnen Genäste derart ausgebildet, @daß die einzelnen Teilrförderbänder einander zum Teil überdecken, so daß das Gut von dem einen Förderb)and auf das andere Förlderb'and .niederfällt.How Alb. i shows that the individual branches are designed in such a way that @ that the individual conveyor belts partially cover each other, so that the good from one conveyor belt to the other conveyor belt.

Um eine sichere Längsverbindung zwischen den !Enden der Gerüste zu ermöglichen, ist eine federnde Stoßkupplung etwa gemäß Abb. 6 vorgesehen. Der Verbindgungsbolzen f besitzt zweckmäßig ein Kardangelenk g, um einte möglichst große Bewegungsdireiheit zweier benachbarter Gerüste gegendinander zu ermöglichen. Das einte Ende jedes Gerüstes trägt -eine Gähel h, die dass Ende des Nachbargerüstes umdaßt, so daß eine sorg fähige Einstellung in der Querrichtung ermöglicht w iTd.To ensure a secure longitudinal connection between the! Ends of the scaffolding enable, a resilient butt coupling is provided as shown in Fig. 6. The connecting bolt f has expediently a universal joint g in order to achieve the greatest possible degree of directness of movement to enable two neighboring scaffolds to be opposite each other. The one end of every scaffolding wears a Gähel h, which surrounds the end of the neighboring scaffolding, so that a care capable adjustment in the transverse direction enables w iTd.

Obwohl das Förderband, von dem Bagger und dem Bhggergleis vollkommen unabhängig ist, sinkt Vorkehriungen getroffen, um zu ermöglichen, daß die Längsachse des Föriiderbandes selbsttätig genau unter die Achse des Schütttrichtiers des Baggers ;gebracht werden kann. Zu diesem Zweck sind an .dem Gerüst des Baggers Leitvorrichtungen angeordnet, die entweder aus einfachen ,gekrümmten Schienen oder besser aus einer Rollengruppe i bestehen, die auf .einer Bogenlinie angeordnet sind. Diese Rollen i wirken mit entsprechenden Führungsschienen k an Ziem Förderbandgerüst zusammen. Sie bow"irken ein. selbsttätiges Zurechtrücken dies Förderhanldes,wenn dieses sich nicht in der rlichbigen Lage befinklen sollte.Although the conveyor belt, from the excavator and the Bhggergleis perfect is independent, precautions are taken to allow the longitudinal axis to decrease of the conveyor belt automatically exactly under the axis of the excavator's bulk hopper ; can be brought. For this purpose, there are guiding devices on the excavator's frame arranged, which either from simple, curved rails or better from a Role group i exist, which are arranged on a curved line. These roles i interact with corresponding guide rails k on Ziem conveyor belt frame. You bow "irken. Automatic adjustment of this promotional trade, if this occurs should not be in the red position.

Um neun .bei Schwenkungen des Förderbandes - vgl. Abib. a stnichpünktiierte Linien das volle Gelände mit dem, Bagger ,bestreichen zu können, kann am Ende der Baggerstraße ein ausziehbares Gerüst angeordnet sein, das sich der Oberfiäehenabm'essung des Geländes genau anzupassen vermag. Dieses Gerüst enthält zwei voneinander unabhüngiige und übereinanderliegende endlose Förderbänder. Durch Einschieben oder Ausziehen des einen Teilgerüstes läßt sich jede gewünschte Bandlänge herstellen.At nine when the conveyor belt swings - see Abib. a punctuated Lines the full area with the excavator, can be at the end of the Excavator road an extendable scaffold be arranged, which is the Oberfiäehenabm'essung able to adapt precisely to the terrain. This framework contains two independent ones and superimposed endless conveyor belts. By pushing in or pulling out of one part of the framework, any desired strip length can be produced.

Wenn der Bagger siele nach dem Gleisschwenkpunkte 'hin bewegt, so werden die links von dem Bagger liegenden Teile des Förderbundes für die Förderung nicht mehr geibraucht. -Sie würden also leer laufen. Um dies zu vermeiden, können an den Gerüsten Sternschalter L angeordnet werden, die von dein Baggerigerüst aus bewegt wenden. Sobald der eine Teil des Förderbandes :nicht mehr fier .die Förderung gebraucht wird, stößt das Baggergestell an -dem betreffenden Schalter l an und schaltet den Strom zu dem Moton aus.If the excavator moves towards the track pivot point, so the parts of the conveyor belt lying to the left of the excavator are used for the promotion no longer used. -So you'd run out of steam. To avoid this you can be arranged on the scaffolding star switch L from your excavator scaffold moving. As soon as one part of the conveyor belt: no longer fier. The promotion is needed, the excavator frame hits the relevant switch l and switches the power to the motor off.

Claims (2)

PATENTANSPRÜCHE: i. Anlage zur Förderung -des Abnaums vom Abraumibiagger zur Ablagerungsstelle, bestehend aus dinem Förderobande, das,aus mehreren, von fahrbaren Gerüsten getragenen endlosen Bändern besteht, daldiurah gekennzeichnet, daß zwischen den einzelnen Gerüsten federnde Längskupplungen (f, g) angeordnet sind, während j e ,ein Ende der Gerüste m'%t einer Gabel (h) versehen ist, .die das Nlachbargerüst zwecks Quereinstellurug umfaßt. PATENT CLAIMS: i. System for conveying the waste from the overburden conveyor to the deposit point, consisting of the conveyor belt, which consists of several endless belts carried by mobile scaffolding, daldiurah characterized in that elastic longitudinal couplings (f, g) are arranged between the individual scaffolding, while each, one end of the scaffolding is provided with a fork (h), which includes the neighboring scaffolding for the purpose of transverse adjustment. 2. Anlage nach Anspruch i, dadurch gekennzeichnet, üaß einerseits am Bagger ,und anderseits an den Förderbandgerüsten Leitvorrichtungen (i bzw. k) angeordnet sind, die eine .genaue Einstellung der Förderthandachse .unter die -Schüt'ttrichteraöhse ,ermöglichen..2. Plant according to claim i, characterized in that üass guiding devices on the one hand on the excavator and on the other hand on the conveyor belt frames (i or k) are arranged, the .precise adjustment of the conveyor hand axis .under the -schüt'ttrichteraöhse, enable ..
DEG53242D 1921-03-04 1921-03-04 System for conveying the overburden from the overburden excavator to the disposal site Expired DE368517C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DEG53242D DE368517C (en) 1921-03-04 1921-03-04 System for conveying the overburden from the overburden excavator to the disposal site

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DEG53242D DE368517C (en) 1921-03-04 1921-03-04 System for conveying the overburden from the overburden excavator to the disposal site

Publications (1)

Publication Number Publication Date
DE368517C true DE368517C (en) 1923-02-06

Family

ID=7130485

Family Applications (1)

Application Number Title Priority Date Filing Date
DEG53242D Expired DE368517C (en) 1921-03-04 1921-03-04 System for conveying the overburden from the overburden excavator to the disposal site

Country Status (1)

Country Link
DE (1) DE368517C (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE905476C (en) * 1950-02-23 1954-03-01 Friedrich Brennecke Conveyor system for overburden and coal in open-cast mining
DE931338C (en) * 1952-08-28 1955-08-04 Kloeckner Humboldt Deutz Ag Belt line with built-on back device
DE968419C (en) * 1950-01-10 1958-02-13 Eisen & Stahlind Ag Method and device for the removal of dredged material in opencast mines
DE976396C (en) * 1951-12-21 1963-08-01 Weserhuette Ag Eisenwerk Retractable belt conveyor
DE1183012B (en) * 1961-03-03 1964-12-03 Volker Siems Dipl Ing Device for position control of the transfer point between the discharge end of a feeder and the take-up end of a conveyor
DE977165C (en) * 1954-02-26 1965-05-06 Lauchhammer Maschb Drop trolley for conveyor belts

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE968419C (en) * 1950-01-10 1958-02-13 Eisen & Stahlind Ag Method and device for the removal of dredged material in opencast mines
DE905476C (en) * 1950-02-23 1954-03-01 Friedrich Brennecke Conveyor system for overburden and coal in open-cast mining
DE976396C (en) * 1951-12-21 1963-08-01 Weserhuette Ag Eisenwerk Retractable belt conveyor
DE931338C (en) * 1952-08-28 1955-08-04 Kloeckner Humboldt Deutz Ag Belt line with built-on back device
DE977165C (en) * 1954-02-26 1965-05-06 Lauchhammer Maschb Drop trolley for conveyor belts
DE1183012B (en) * 1961-03-03 1964-12-03 Volker Siems Dipl Ing Device for position control of the transfer point between the discharge end of a feeder and the take-up end of a conveyor

Similar Documents

Publication Publication Date Title
DE368517C (en) System for conveying the overburden from the overburden excavator to the disposal site
DE904397C (en) Conveyor equipment, especially for manure
DE819817C (en) Endless conveyor device
DE603291C (en) Universal movable apron conveyor on rails
DE882073C (en) Steel link conveyor belt
DE883122C (en) Device for driving conveyor belts or conveyor belt sections
DE616779C (en) Device for driving routes in underground pits
DE2513239C3 (en) Mobile deflection device
DE622718C (en) Mobile conveyor device for coal or similar materials with an endless belt
DE914478C (en) Apron conveyor
DE653869C (en) Overburden conveyor system
DE857602C (en) Endless conveyor and screening device consisting of two link chains and cross bars in between
DE27916C (en) snow plow
DE709755C (en) Belt conveyor device
DE685183C (en) Belt line
DE478375C (en) Chassis for an excavator movably connected to a conveyor bridge
DE971808C (en) Device to ensure the straight running of conveyor belt lines
AT237009B (en) Mobile device for clearing railway ballast
DE965209C (en) Steel link conveyor belt
DE1124424B (en) Soft for endless link conveyor belts
DE569478C (en) Device for guiding the scraper arms in scraper conveyors
AT212616B (en) Charger for hay, grass, etc. similar Crop
AT373938B (en) SNOWROOM UNIT
DE6605237U (en) CONVEYOR DEVICE FOR MANURE AND THE LIKE.
DE465478C (en) Machine for collecting and upward conveying coal by means of shovels