DE3309046A1 - Track rebuilding method without rail removal, characterised in that, in short track sections, the sleepers are displaced and the remaining ballast is conveyed to the displaced sleepers - Google Patents
Track rebuilding method without rail removal, characterised in that, in short track sections, the sleepers are displaced and the remaining ballast is conveyed to the displaced sleepersInfo
- Publication number
- DE3309046A1 DE3309046A1 DE19833309046 DE3309046A DE3309046A1 DE 3309046 A1 DE3309046 A1 DE 3309046A1 DE 19833309046 DE19833309046 DE 19833309046 DE 3309046 A DE3309046 A DE 3309046A DE 3309046 A1 DE3309046 A1 DE 3309046A1
- Authority
- DE
- Germany
- Prior art keywords
- sleepers
- track
- displaced
- ballast
- rails
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B27/00—Placing, renewing, working, cleaning, or taking-up the ballast, with or without concurrent work on the track; Devices therefor; Packing sleepers
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B29/00—Laying, rebuilding, or taking-up tracks; Tools or machines therefor
- E01B29/06—Transporting, laying, removing or renewing sleepers
- E01B29/09—Transporting, laying, removing or renewing sleepers under, or from under, installed rails
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B2203/00—Devices for working the railway-superstructure
- E01B2203/01—Devices for working the railway-superstructure with track
- E01B2203/012—Devices for working the railway-superstructure with track present, i.e. in its normal position
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Machines For Laying And Maintaining Railways (AREA)
Abstract
Description
Das technische Gebiet ist der Gleisbau bei der Deutschen Bundesbahn,Ver-The technical field is track construction at the Deutsche Bundesbahn, Ver
kehrsbetrieben und Privatgleisanschlüssen, Die Erfindung betrifft ein Umbauverfahren, wobei die eingebauten Gleisschienen belassen werden; speziell bei beengten Platzverhältnissen und kurzen Sperrpausen Bei dem heutigen Stand der Technik werden diese Arbeiten entweder durch reine Handarbeit oder durch den Ausbau des umzubauenden Gleisstückes ausgeführt, Die Kritik am Stand der heutigen Technik ist die Gefahr einer Sperrzeitenüberschreitung und die geringere Fahrsicherheit, sowie eine Reduzierung des Fahrkomforts durch das Schneiden der Schienen und eine entsprechend geringe Leistung in der kurzen Sperrpause, die für die Arbeiten zur Verfügung steht.Sweeping operations and private sidings, The invention relates a remodeling process, whereby the built-in track rails are left; special in the case of cramped space conditions and short breaks Technique, this work is either done by hand or by expansion of the track section to be rebuilt, the criticism of the current state of technology is the risk of exceeding the blocking times and the lower driving safety, as well as a reduction in driving comfort by cutting the rails and a correspondingly low performance in the short lockout period required for work on Available.
Der Erfindung liegt die Aufgabe zugrunde, einen sicheren und wirtschaftlichen Gleisumbau in Sperrpausen durchzuführen. Diese Aufgabe wird erfindungsgemäß dadurch ausgelöst, daß die Schienen nicht ausgebaut werden. Die Schwellen werden entweder nur verschoben oder ausgewechselt. Der Schotter wird umgeschichtet, kann dabei auch gereinigt werden. Auch ist es möglich den Schotter zu verladen. Bei entsprechend ungeeignetem Untergrund unter dem Schotter ist es möglich, dieses Material auszubauen und zu verladen.The invention is based on the object of a safe and economical Track renewal to be carried out during closed breaks. This object is achieved according to the invention triggered that the rails are not removed. The sleepers will either only postponed or replaced. The gravel is shifted, it can also getting cleaned. It is also possible to load the ballast. With accordingly unsuitable subsoil under the gravel, it is possible to develop this material and to load.
Ein Ausführungsbeispiel für die Erfindung ist der Einbau von Unterschottermatten (Schallschutzmatten) in der S-Bahnröhre (Tunnel), um den geforderten Schallschutz im nahe gelegenen Kulturzentrum (Konzertsaal) der Stadt München am " Gasteig " zu erreichen. Da der S-Bahnbetrieb nicht eingestellt werden konnte, mußten die Arbeiten in nächtlichen Sperrpausen durchgeführt werden.One embodiment of the invention is the installation of sub-ballast mats (Noise protection mats) in the S-Bahn tube (tunnel) to achieve the required noise protection in the nearby cultural center (concert hall) of the city of Munich on "Gasteig" reach. Since the S-Bahn could not be stopped, the work had to be done can be carried out during nightly closed breaks.
-1 1. Abschnitt ( 1. Umbautt ) Bei Umbaubeginn werden 8 Schwellen ausgebaut und für den späteren Wiedereinbau gelagert. Der unter den ausgebauten Schwellen nun freiliegende Schotter wird auf eine Länge von 5 m mit einem auf den Schienen fahrenden Bagger auf einem Schottertransportwagen verladen. Nach dem Reinigen der zu isolierenden Tunnelsohle von Schotterabrieb und dem Ausgleich von Betonunebenheiten werden die Schallisoliermatten verlegt bzw. auf der Tunnelsohle verklebt.-1 1st section (1st conversion) At the start of the renovation, 8 sleepers will be removed and stored for later reinstallation. The one under the dismantled sleepers now exposed ballast is laid to a length of 5 m with one on the rails loaded moving excavator on a gravel transport wagon. After cleaning the tunnel floor to be isolated from gravel abrasion and to compensate for uneven concrete the sound insulation mats are laid or glued to the tunnel sole.
2. Abschnitt und weitere: Abschnitte Nunmehr beginnt der zweite Umbautakt.2nd section and others: sections Now the second renovation cycle begins.
Die noch im Schotter liegende erste Schwelle wird mit einem am gleisfahrbaren Bagger angebrachten an jeweils einer Schwelle angesetzten Verschiebegerät (in Richtung bereits mit Matten ausgelegten Abschnitt) aus dem Schotterbett ca. 1 m weit verschoben. Die zu verschiebende Schwelle ist an einem auf den Schienen rollenden Schwellentransportwagen in der Rippenplatte aufgehängt und wird bis zu der neuen Montagestelle (ca. 5 m ) von Hand weitergeschoben.The first sleeper, which is still in the gravel, is fitted with a track-driven one Excavator attached to one sleeper each shifting device (in direction section already covered with mats) moved approx. 1 m from the gravel bed. The sleeper to be moved is on a sleeper transport trolley that rolls on the rails suspended in the ribbed plate and is moved up to the new assembly point (approx. 5 m ) pushed further by hand.
An der mit Schwelleneinteilung versehenen Stelle wird die Schwelle mit einer Montagevorrichtung, welche am Schwellentransportwagen angebracht ist bis zum Schienenfuß angehoben und in ihrer endgültigen Lage montiert.The threshold is at the point provided with the threshold division with a mounting device which is attached to the sleeper transport trolley up to raised to the rail foot and mounted in their final position.
Die zweite und dritte Schwelle wird wie eben beschrieben mit dem Bagger aus dem Schotterbett geschoben und an der vorgesehenen Stelle montiert.The second and third threshold are as just described with the excavator pushed out of the ballast bed and mounted in the intended place.
Der nun freiliegende Schotter (auf ca. 1.80 m Länge ) wird mit dem Bagger aufgenommen, bis zu den 3 neu montierten Schwellen verfahren und hier wieder eingebaut.The now exposed gravel (approx. 1.80 m long) is covered with the Excavator picked up, move up to the 3 newly installed sleepers and here again built-in.
Dieser Arbeitsablauf wiederholt sich bis im Bereich von 8 Schwellen ( 5 m) die Tunnelsohle wieder freiliegt und die Schallisoliermatten eingebaut werden können.This workflow is repeated up to a range of 8 thresholds (5 m) the tunnel floor is exposed again and the sound insulation mats are installed can.
Alle weiteren Abschnitte verlaufen wie im Abschnitt 2, .1 3. Abschnitt, letzter Aschnitt in einer Sperrpuse In den vom vorhergehenden Arbbitstakt freiliegenden ca. 5 m Abschnitt werden nach dem Einlegen der Isoliermatten die im 1. Umbautakt ausgebauten Schwellen wieder eingebaut und der ebenfalls im 1. Umbautakt verladene Schotter an dieser Stelle entladen.All other sections proceed as in section 2, .1 3rd section, last section in a blocking puse In the from the previous Arbbitstakt exposed approx. 5 m section are after inserting the insulating mats the im 1st conversion cycle removed sleepers and reinstalled in the 1st conversion cycle unload loaded ballast at this point.
Der Arbeitsablauf für eine Sperrpause für dieses zum Patent angemeldeten Umbauverfahren ist damit abgeschlossen. Es folgen noch wie üblich die restlichen Stopfarbeiten und das Räumen der Baustelle für die fahrplanmäßige Wiederaufnahme des Eisenbahnbetriebes.The workflow for a lockout for this patent pending The conversion process is now complete. The rest of them follow as usual Tamping work and the clearing of the construction site for the scheduled resumption of the railway company.
Die vom Auftraggeber geforderte Leistung in der nächtlichen Sperrzeit betrug 12 Meter, die durch die Erfindung erzielte Leistung konnte auf 30 Meter gesteigert werden.The service required by the client during the nightly blocking period was 12 meters, the performance achieved by the invention could be increased to 30 meters will.
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE19833309046 DE3309046A1 (en) | 1983-03-14 | 1983-03-14 | Track rebuilding method without rail removal, characterised in that, in short track sections, the sleepers are displaced and the remaining ballast is conveyed to the displaced sleepers |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE19833309046 DE3309046A1 (en) | 1983-03-14 | 1983-03-14 | Track rebuilding method without rail removal, characterised in that, in short track sections, the sleepers are displaced and the remaining ballast is conveyed to the displaced sleepers |
Publications (1)
Publication Number | Publication Date |
---|---|
DE3309046A1 true DE3309046A1 (en) | 1984-09-20 |
Family
ID=6193402
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE19833309046 Withdrawn DE3309046A1 (en) | 1983-03-14 | 1983-03-14 | Track rebuilding method without rail removal, characterised in that, in short track sections, the sleepers are displaced and the remaining ballast is conveyed to the displaced sleepers |
Country Status (1)
Country | Link |
---|---|
DE (1) | DE3309046A1 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2588023A1 (en) * | 1985-10-02 | 1987-04-03 | Drouard Freres Ets | Method and machine for clearing the ballast from a railway track |
CN104179093A (en) * | 2014-09-04 | 2014-12-03 | 昆明学院 | Quick sleeper-changing machine |
-
1983
- 1983-03-14 DE DE19833309046 patent/DE3309046A1/en not_active Withdrawn
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2588023A1 (en) * | 1985-10-02 | 1987-04-03 | Drouard Freres Ets | Method and machine for clearing the ballast from a railway track |
CN104179093A (en) * | 2014-09-04 | 2014-12-03 | 昆明学院 | Quick sleeper-changing machine |
CN104179093B (en) * | 2014-09-04 | 2016-04-27 | 昆明学院 | A kind of fast quick change pillow machine |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE3035910C2 (en) | ||
DE2619131A1 (en) | METHOD AND DEVICE FOR REPLACING SECTIONS OF A TRACK | |
DD261387A5 (en) | DRIVEN MACHINE FOR CONTINUOUS EXCHANGE OR BZW. RENEWING A RAILED RAIL THAT IS RAILED AND THREADED | |
DE3634399A1 (en) | TRACKING MACHINE WITH LIFTING, STOPPING AND, IF NECESSARY, DIRECTIONAL UNIT | |
AT398097B (en) | SYSTEM FOR PRODUCING A PLANUM PROTECTIVE LAYER | |
EP0712961B1 (en) | Method and arrangement for the subgrade-rehabilitation of the ballast of a railway track | |
EP0663470B1 (en) | Process for obtaining a superstructure for railway tracks | |
EP2218871B1 (en) | Method for renovating and/or expanding navigable tunnel tubes | |
DE3309046A1 (en) | Track rebuilding method without rail removal, characterised in that, in short track sections, the sleepers are displaced and the remaining ballast is conveyed to the displaced sleepers | |
EP1644581B1 (en) | Method for the construction of a track structure for railborne vehicles, particularly trains | |
EP3253922A1 (en) | Method for track renewal | |
DE2503590B2 (en) | RAILWAY CONSTRUCTION WITH REINFORCED CONCRETE TRACK PLATES | |
DE19952803C2 (en) | Superstructure for rail-bound public transport vehicles and method and device for its manufacture | |
AT370461B (en) | METHOD FOR PRODUCING AN ELASTICALLY BEARED TROUGH FROM REINFORCED CONCRETE AS A STRUCTURAL STRUCTURE CONSTRUCTING SOURCE FOR THE CONSTRUCTION OF A RAILWAY RAILWAY, IN PARTICULAR ON DOWNTOWN TUNNEL RUNS | |
DD154226A5 (en) | METHOD AND DEVICE FOR UNDERGROUND ARMING OF RAILWAY RAILS | |
DE10301231B3 (en) | Superstructure guided over viaducts for rail-bound vehicles | |
DE3317207A1 (en) | Platform with escape tunnel | |
JP3959570B2 (en) | Sleeper and track structure using the sleeper | |
AT507425B1 (en) | LENGTH SWIVEL ELEMENTS FOR RAILWAY TRACK ON SCOTTER | |
DE371696C (en) | Railway superstructure with rail support chairs embedded in concrete | |
DE102014207489A1 (en) | Railbound transport system | |
US118667A (en) | Improvement in construction-trains for railways | |
US310284A (en) | Cable-way for railway traction-cables | |
CH708506B1 (en) | Vehicle association and method of renewing a track. | |
Traill | Mechanized relaying of the coal line |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
8139 | Disposal/non-payment of the annual fee |