DE3309046A1 - Track rebuilding method without rail removal, characterised in that, in short track sections, the sleepers are displaced and the remaining ballast is conveyed to the displaced sleepers - Google Patents

Track rebuilding method without rail removal, characterised in that, in short track sections, the sleepers are displaced and the remaining ballast is conveyed to the displaced sleepers

Info

Publication number
DE3309046A1
DE3309046A1 DE19833309046 DE3309046A DE3309046A1 DE 3309046 A1 DE3309046 A1 DE 3309046A1 DE 19833309046 DE19833309046 DE 19833309046 DE 3309046 A DE3309046 A DE 3309046A DE 3309046 A1 DE3309046 A1 DE 3309046A1
Authority
DE
Germany
Prior art keywords
sleepers
track
displaced
ballast
rails
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
DE19833309046
Other languages
German (de)
Inventor
Josef Dipl.-Ing. 8000 München Spindler
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to DE19833309046 priority Critical patent/DE3309046A1/en
Publication of DE3309046A1 publication Critical patent/DE3309046A1/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B27/00Placing, renewing, working, cleaning, or taking-up the ballast, with or without concurrent work on the track; Devices therefor; Packing sleepers
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B29/00Laying, rebuilding, or taking-up tracks; Tools or machines therefor
    • E01B29/06Transporting, laying, removing or renewing sleepers
    • E01B29/09Transporting, laying, removing or renewing sleepers under, or from under, installed rails
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2203/00Devices for working the railway-superstructure
    • E01B2203/01Devices for working the railway-superstructure with track
    • E01B2203/012Devices for working the railway-superstructure with track present, i.e. in its normal position

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Machines For Laying And Maintaining Railways (AREA)

Abstract

In this connection, the installed rails remain in their old position, the sleepers are displaced with a displacing device, moved to the new place of installation with a sleeper transport waggon and mounted here. The ballast then exposed is conveyed to the newly mounted sleepers and installed here. Advantages: a) From the point of view of railway operation No interruption of the continuously welded-together rails and consequently no additional welded joints. Increased travelling safety and travelling comfort as no rail joints present. Reliability of maintaining the stipulated closure period and consequently reliability of the scheduled running of the railway operation, as the track can always be used again in approximately 30 minutes. b) From an economical point of view No installation and removal of yoke rails (auxiliary rails) No additional welding work with the associated loosening and retightening work. Considerably greater rebuilding capacity in short closure periods Diverse application possibilities, above all in limited space conditions (e.g. in a tunnel), in short closure periods, in sleeper replacement, in ballast cleaning and ballast replacement and in track formation improvement work without an adjacent track. e

Description

Das technische Gebiet ist der Gleisbau bei der Deutschen Bundesbahn,Ver-The technical field is track construction at the Deutsche Bundesbahn, Ver

kehrsbetrieben und Privatgleisanschlüssen, Die Erfindung betrifft ein Umbauverfahren, wobei die eingebauten Gleisschienen belassen werden; speziell bei beengten Platzverhältnissen und kurzen Sperrpausen Bei dem heutigen Stand der Technik werden diese Arbeiten entweder durch reine Handarbeit oder durch den Ausbau des umzubauenden Gleisstückes ausgeführt, Die Kritik am Stand der heutigen Technik ist die Gefahr einer Sperrzeitenüberschreitung und die geringere Fahrsicherheit, sowie eine Reduzierung des Fahrkomforts durch das Schneiden der Schienen und eine entsprechend geringe Leistung in der kurzen Sperrpause, die für die Arbeiten zur Verfügung steht.Sweeping operations and private sidings, The invention relates a remodeling process, whereby the built-in track rails are left; special in the case of cramped space conditions and short breaks Technique, this work is either done by hand or by expansion of the track section to be rebuilt, the criticism of the current state of technology is the risk of exceeding the blocking times and the lower driving safety, as well as a reduction in driving comfort by cutting the rails and a correspondingly low performance in the short lockout period required for work on Available.

Der Erfindung liegt die Aufgabe zugrunde, einen sicheren und wirtschaftlichen Gleisumbau in Sperrpausen durchzuführen. Diese Aufgabe wird erfindungsgemäß dadurch ausgelöst, daß die Schienen nicht ausgebaut werden. Die Schwellen werden entweder nur verschoben oder ausgewechselt. Der Schotter wird umgeschichtet, kann dabei auch gereinigt werden. Auch ist es möglich den Schotter zu verladen. Bei entsprechend ungeeignetem Untergrund unter dem Schotter ist es möglich, dieses Material auszubauen und zu verladen.The invention is based on the object of a safe and economical Track renewal to be carried out during closed breaks. This object is achieved according to the invention triggered that the rails are not removed. The sleepers will either only postponed or replaced. The gravel is shifted, it can also getting cleaned. It is also possible to load the ballast. With accordingly unsuitable subsoil under the gravel, it is possible to develop this material and to load.

Ein Ausführungsbeispiel für die Erfindung ist der Einbau von Unterschottermatten (Schallschutzmatten) in der S-Bahnröhre (Tunnel), um den geforderten Schallschutz im nahe gelegenen Kulturzentrum (Konzertsaal) der Stadt München am " Gasteig " zu erreichen. Da der S-Bahnbetrieb nicht eingestellt werden konnte, mußten die Arbeiten in nächtlichen Sperrpausen durchgeführt werden.One embodiment of the invention is the installation of sub-ballast mats (Noise protection mats) in the S-Bahn tube (tunnel) to achieve the required noise protection in the nearby cultural center (concert hall) of the city of Munich on "Gasteig" reach. Since the S-Bahn could not be stopped, the work had to be done can be carried out during nightly closed breaks.

-1 1. Abschnitt ( 1. Umbautt ) Bei Umbaubeginn werden 8 Schwellen ausgebaut und für den späteren Wiedereinbau gelagert. Der unter den ausgebauten Schwellen nun freiliegende Schotter wird auf eine Länge von 5 m mit einem auf den Schienen fahrenden Bagger auf einem Schottertransportwagen verladen. Nach dem Reinigen der zu isolierenden Tunnelsohle von Schotterabrieb und dem Ausgleich von Betonunebenheiten werden die Schallisoliermatten verlegt bzw. auf der Tunnelsohle verklebt.-1 1st section (1st conversion) At the start of the renovation, 8 sleepers will be removed and stored for later reinstallation. The one under the dismantled sleepers now exposed ballast is laid to a length of 5 m with one on the rails loaded moving excavator on a gravel transport wagon. After cleaning the tunnel floor to be isolated from gravel abrasion and to compensate for uneven concrete the sound insulation mats are laid or glued to the tunnel sole.

2. Abschnitt und weitere: Abschnitte Nunmehr beginnt der zweite Umbautakt.2nd section and others: sections Now the second renovation cycle begins.

Die noch im Schotter liegende erste Schwelle wird mit einem am gleisfahrbaren Bagger angebrachten an jeweils einer Schwelle angesetzten Verschiebegerät (in Richtung bereits mit Matten ausgelegten Abschnitt) aus dem Schotterbett ca. 1 m weit verschoben. Die zu verschiebende Schwelle ist an einem auf den Schienen rollenden Schwellentransportwagen in der Rippenplatte aufgehängt und wird bis zu der neuen Montagestelle (ca. 5 m ) von Hand weitergeschoben.The first sleeper, which is still in the gravel, is fitted with a track-driven one Excavator attached to one sleeper each shifting device (in direction section already covered with mats) moved approx. 1 m from the gravel bed. The sleeper to be moved is on a sleeper transport trolley that rolls on the rails suspended in the ribbed plate and is moved up to the new assembly point (approx. 5 m ) pushed further by hand.

An der mit Schwelleneinteilung versehenen Stelle wird die Schwelle mit einer Montagevorrichtung, welche am Schwellentransportwagen angebracht ist bis zum Schienenfuß angehoben und in ihrer endgültigen Lage montiert.The threshold is at the point provided with the threshold division with a mounting device which is attached to the sleeper transport trolley up to raised to the rail foot and mounted in their final position.

Die zweite und dritte Schwelle wird wie eben beschrieben mit dem Bagger aus dem Schotterbett geschoben und an der vorgesehenen Stelle montiert.The second and third threshold are as just described with the excavator pushed out of the ballast bed and mounted in the intended place.

Der nun freiliegende Schotter (auf ca. 1.80 m Länge ) wird mit dem Bagger aufgenommen, bis zu den 3 neu montierten Schwellen verfahren und hier wieder eingebaut.The now exposed gravel (approx. 1.80 m long) is covered with the Excavator picked up, move up to the 3 newly installed sleepers and here again built-in.

Dieser Arbeitsablauf wiederholt sich bis im Bereich von 8 Schwellen ( 5 m) die Tunnelsohle wieder freiliegt und die Schallisoliermatten eingebaut werden können.This workflow is repeated up to a range of 8 thresholds (5 m) the tunnel floor is exposed again and the sound insulation mats are installed can.

Alle weiteren Abschnitte verlaufen wie im Abschnitt 2, .1 3. Abschnitt, letzter Aschnitt in einer Sperrpuse In den vom vorhergehenden Arbbitstakt freiliegenden ca. 5 m Abschnitt werden nach dem Einlegen der Isoliermatten die im 1. Umbautakt ausgebauten Schwellen wieder eingebaut und der ebenfalls im 1. Umbautakt verladene Schotter an dieser Stelle entladen.All other sections proceed as in section 2, .1 3rd section, last section in a blocking puse In the from the previous Arbbitstakt exposed approx. 5 m section are after inserting the insulating mats the im 1st conversion cycle removed sleepers and reinstalled in the 1st conversion cycle unload loaded ballast at this point.

Der Arbeitsablauf für eine Sperrpause für dieses zum Patent angemeldeten Umbauverfahren ist damit abgeschlossen. Es folgen noch wie üblich die restlichen Stopfarbeiten und das Räumen der Baustelle für die fahrplanmäßige Wiederaufnahme des Eisenbahnbetriebes.The workflow for a lockout for this patent pending The conversion process is now complete. The rest of them follow as usual Tamping work and the clearing of the construction site for the scheduled resumption of the railway company.

Die vom Auftraggeber geforderte Leistung in der nächtlichen Sperrzeit betrug 12 Meter, die durch die Erfindung erzielte Leistung konnte auf 30 Meter gesteigert werden.The service required by the client during the nightly blocking period was 12 meters, the performance achieved by the invention could be increased to 30 meters will.

Claims (1)

Patentanspruch für ein Gleisumbauterfähren ohne Schienenausbau dadurch gekennzeichnet, daß (nach einem Vorbereitungsabschnitt, bei dem einige Schwellen ausgebaut, seitlich gelagert und der hier freiliegende Schotter ebenfalls ausgebaut wurde) in kurzen Gleisabschnitten die Schwellen mit einem Verschiebeserät (Zusatzgerät am Bagger) verschoben, mit einer Schwellentransport- und Montagewagen an die neue Einbaustelle transportiert, nach der Schwelleneinteilung montiert werten und der eingebaute Schotter zu den verschebenen Schwellen befördert wird.Claim for a track renovation ferry without expanding the track characterized in that (after a preparatory section in which some thresholds removed, stored on the side and the gravel exposed here also removed was) in short track sections the sleepers with a shifting device (additional device on the excavator), with a sleeper transport and assembly trolley to the new one Installation site, evaluate installed according to the threshold division and the built-in ballast is transported to the shifted sleepers.
DE19833309046 1983-03-14 1983-03-14 Track rebuilding method without rail removal, characterised in that, in short track sections, the sleepers are displaced and the remaining ballast is conveyed to the displaced sleepers Withdrawn DE3309046A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DE19833309046 DE3309046A1 (en) 1983-03-14 1983-03-14 Track rebuilding method without rail removal, characterised in that, in short track sections, the sleepers are displaced and the remaining ballast is conveyed to the displaced sleepers

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE19833309046 DE3309046A1 (en) 1983-03-14 1983-03-14 Track rebuilding method without rail removal, characterised in that, in short track sections, the sleepers are displaced and the remaining ballast is conveyed to the displaced sleepers

Publications (1)

Publication Number Publication Date
DE3309046A1 true DE3309046A1 (en) 1984-09-20

Family

ID=6193402

Family Applications (1)

Application Number Title Priority Date Filing Date
DE19833309046 Withdrawn DE3309046A1 (en) 1983-03-14 1983-03-14 Track rebuilding method without rail removal, characterised in that, in short track sections, the sleepers are displaced and the remaining ballast is conveyed to the displaced sleepers

Country Status (1)

Country Link
DE (1) DE3309046A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2588023A1 (en) * 1985-10-02 1987-04-03 Drouard Freres Ets Method and machine for clearing the ballast from a railway track
CN104179093A (en) * 2014-09-04 2014-12-03 昆明学院 Quick sleeper-changing machine

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2588023A1 (en) * 1985-10-02 1987-04-03 Drouard Freres Ets Method and machine for clearing the ballast from a railway track
CN104179093A (en) * 2014-09-04 2014-12-03 昆明学院 Quick sleeper-changing machine
CN104179093B (en) * 2014-09-04 2016-04-27 昆明学院 A kind of fast quick change pillow machine

Similar Documents

Publication Publication Date Title
DE3035910C2 (en)
DE2619131A1 (en) METHOD AND DEVICE FOR REPLACING SECTIONS OF A TRACK
DD261387A5 (en) DRIVEN MACHINE FOR CONTINUOUS EXCHANGE OR BZW. RENEWING A RAILED RAIL THAT IS RAILED AND THREADED
DE3634399A1 (en) TRACKING MACHINE WITH LIFTING, STOPPING AND, IF NECESSARY, DIRECTIONAL UNIT
AT398097B (en) SYSTEM FOR PRODUCING A PLANUM PROTECTIVE LAYER
EP0712961B1 (en) Method and arrangement for the subgrade-rehabilitation of the ballast of a railway track
EP0663470B1 (en) Process for obtaining a superstructure for railway tracks
EP2218871B1 (en) Method for renovating and/or expanding navigable tunnel tubes
DE3309046A1 (en) Track rebuilding method without rail removal, characterised in that, in short track sections, the sleepers are displaced and the remaining ballast is conveyed to the displaced sleepers
EP1644581B1 (en) Method for the construction of a track structure for railborne vehicles, particularly trains
EP3253922A1 (en) Method for track renewal
DE2503590B2 (en) RAILWAY CONSTRUCTION WITH REINFORCED CONCRETE TRACK PLATES
DE19952803C2 (en) Superstructure for rail-bound public transport vehicles and method and device for its manufacture
AT370461B (en) METHOD FOR PRODUCING AN ELASTICALLY BEARED TROUGH FROM REINFORCED CONCRETE AS A STRUCTURAL STRUCTURE CONSTRUCTING SOURCE FOR THE CONSTRUCTION OF A RAILWAY RAILWAY, IN PARTICULAR ON DOWNTOWN TUNNEL RUNS
DD154226A5 (en) METHOD AND DEVICE FOR UNDERGROUND ARMING OF RAILWAY RAILS
DE10301231B3 (en) Superstructure guided over viaducts for rail-bound vehicles
DE3317207A1 (en) Platform with escape tunnel
JP3959570B2 (en) Sleeper and track structure using the sleeper
AT507425B1 (en) LENGTH SWIVEL ELEMENTS FOR RAILWAY TRACK ON SCOTTER
DE371696C (en) Railway superstructure with rail support chairs embedded in concrete
DE102014207489A1 (en) Railbound transport system
US118667A (en) Improvement in construction-trains for railways
US310284A (en) Cable-way for railway traction-cables
CH708506B1 (en) Vehicle association and method of renewing a track.
Traill Mechanized relaying of the coal line