DE2826606B1 - Process for feeding a clamping plate and pre-assembled unit for carrying out the process - Google Patents

Process for feeding a clamping plate and pre-assembled unit for carrying out the process

Info

Publication number
DE2826606B1
DE2826606B1 DE19782826606 DE2826606A DE2826606B1 DE 2826606 B1 DE2826606 B1 DE 2826606B1 DE 19782826606 DE19782826606 DE 19782826606 DE 2826606 A DE2826606 A DE 2826606A DE 2826606 B1 DE2826606 B1 DE 2826606B1
Authority
DE
Germany
Prior art keywords
clamping plate
prefabricated unit
prefabricated
unit
funnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
DE19782826606
Other languages
German (de)
Other versions
DE2826606C2 (en
Inventor
Dipl-Ing Dr Weber Richard A
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Thyssen AG
Original Assignee
August Thyssen Huette AG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by August Thyssen Huette AG filed Critical August Thyssen Huette AG
Priority to DE19782826606 priority Critical patent/DE2826606C2/en
Priority to GB7921110A priority patent/GB2024065B/en
Priority to FR7915534A priority patent/FR2429054A1/en
Publication of DE2826606B1 publication Critical patent/DE2826606B1/en
Application granted granted Critical
Publication of DE2826606C2 publication Critical patent/DE2826606C2/en
Expired legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B22CASTING; POWDER METALLURGY
    • B22DCASTING OF METALS; CASTING OF OTHER SUBSTANCES BY THE SAME PROCESSES OR DEVICES
    • B22D35/00Equipment for conveying molten metal into beds or moulds
    • B22D35/04Equipment for conveying molten metal into beds or moulds into moulds, e.g. base plates, runners
    • B22D35/045Runner base plates for bottom casting ingots

Description

3535

Die Erfindung bezieht sich auf ein Verfahren zum Zustellen einer Gespannplatte für den Unterguß beim Vergießen von Stahlblöcken, wobei aus hochwertigem Feuerfestmaterial bestehende Einzelrohre (Kanalsteine oder Trichterrohre) außerhalb der zuzustellenden Gespannplatte zu einer eine Vielzahl von Einzelrohren umfassenden Einheit vormontiert und anschließend die vormontierte Einheit in die Gespannplatte eingesetzt wird. Außerdem bezieht sich die Erfindung auf eine Einheit zur Durchführung des Verfahrens.The invention relates to a method for adjusting a clamping plate for the casting during Casting of steel blocks, whereby individual pipes (channel stones or funnel tubes) outside of the clamping plate to be delivered to a multitude of individual tubes comprehensive unit pre-assembled and then inserted the pre-assembled unit into the clamping plate will. The invention also relates to a unit for carrying out the method.

Das Einbringen der herkömmlichen Kanalsteine in die Gespannplatte und der Trichterrohre auf die Gespannplatte und in den Gießtrichter ist sehr 5(> personalintensiv und zeitaufwendig. Es kommt hinzu, daß das Bedienungspersonal durch die Wärmestrahlung der Gespannplatte stark belastet wird, da die Gespannplatte während des Gießvorgangs eine höhere Temperatur annimmt und aufgrund ihrer hohen Wärmekapazitat und ihrer relativ beschränkten Kühlfläche nach dem Gießen nur langsam abkühlt. Zur Erleichterung dieser Arbeit ist in der DE-PS 26 19 211 eine Steinlegevorrichtung vorgeschlagen worden, auf der eine Vielzahl von Einzelkanalsteinen zu einer Einheit vormontiert und anschließend die vormontierte Einheit mittels der Steinlegevorrichtung in die Gespannplatte abgesenkt wird. Mittels einer derartigen Steinlegevorrichtung ist somit eine Arbeitserleichterung bei der Zustellung von Gespannplatten möglich.The introduction of the conventional channel stones into the clamping plate and the funnel pipes on the clamping plate and in the pouring funnel is very 5 ( > labor-intensive and time-consuming. In addition, the operating personnel are heavily stressed by the thermal radiation of the clamping plate, since the clamping plate becomes a adopts a higher temperature and due to its high heat capacity and its relatively limited cooling surface cools only slowly after casting the preassembled unit is lowered into the clamping plate by means of the stone-laying device.

Weiterhin ist dem Fachmann geläufig, daß die Abmessungen der zu verwendenden Kanalsteine und Trichterrohre standardisiert sind, um dadurch eine Beschränkung der Zahl von Steinformaten zu erreichen (siehe »Stahl und Eisen« — 1978 — Seiten 32—36). So haben Trichterrohre eine standardisierte Länge von 270 und 330 mm und Kanalsteine eine standardisierte Länge von 170 bis 420 mm. Die Kanalsteine haben üblicherweise quadratische Außenabmessungen. Um die Kosten für das hochwertige feuerfeste Material zu senken, ist im Laufe der 20er Jahre der Vorschlag gemacht worden (DE-PS 4 36 255 und DE-PS 4 54 536), einen Kanalstein aus zwei Schichten aufzubauen, wobei nur der innenliegende Kern aus hochwertigem Feuerfestmaterial besteht, während der außenliegende Mantel aus minderwertigem Stoff, z. B. Lehm, bestehen kann. Nach dem Zusatz-Patent 4 54 536 springt der Kern an der einen Stirnfläche gegen den Mantel etwas vor, so daß die hintereinander angeordneten Kanalsteine über eine Nut/Feder-Verbindung ineinandergeschoben werden können. Die Verlegung der vorbeschriebenen, zweischichtigen Kanalsteine erfolgt zeitaufwendig auf der warmen oder heißen Gespannplatte, so daß die bekannten Belästigungen des Bedienungspersonals unvermeidlich sind.Furthermore, the person skilled in the art is familiar with the fact that the dimensions of the channel stones to be used and Funnel tubes are standardized in order to achieve a limitation in the number of stone formats (see "Steel and Iron" - 1978 - pages 32-36). So funnel pipes have a standardized length of 270 and 330 mm and channel stones have a standardized length from 170 to 420 mm. The channel stones usually have square outer dimensions. In order to reduce the cost of the high quality refractory material, im During the 20s the proposal was made (DE-PS 4 36 255 and DE-PS 4 54 536), a canal stone built up from two layers, with only the inner core made of high quality refractory material consists, while the outer coat made of inferior fabric, such. B. clay, can exist. To the additional patent 4,54,536 protrudes the core at one end face against the jacket slightly so that the channel stones arranged one behind the other are pushed into one another via a tongue and groove connection can. The laying of the two-layer sewer stones described above is time-consuming on the warm or hot clamping plate, so that the known annoyance of the operating staff are inevitable.

Der vorliegenden Erfindung liegt die Aufgabe zugrunde, ein Verfahren und Mittel zur Durchführung des Verfahrens zu entwickeln, die es erlauben, bei erheblicher Verminderung der Belästigungen des Bedienungspersonals eine kostengünstige und zeitsparende Zustellung der Gespannplatte herzustellen.The present invention is based on the object of a method and a means for carrying it out of the procedure that allow, with a considerable reduction in the nuisance of the Operating personnel to produce a cost-effective and time-saving delivery of the clamping plate.

Diese Aufgabe wird erfindungsgemäß dadurch gelöst, daß dünnwandige Einzelrohre aus hochwertigem, feuerfesten Material in einer dem zuzustellenden Querschnitt der Gespannplatte oder des Gießtrichters entsprechenden Form von mit Binder versetzten Mineralstoffen ummantelt werden, worauf nach zumindest teilweiser Abbindung des Binders die geformte mehrschichtige Fertigbaueinheit in Gespannplatte eingesetzt wird.This object is achieved according to the invention in that thin-walled individual tubes made of high quality, Refractory material in one of the cross-section of the clamping plate or the pouring funnel to be delivered corresponding form of minerals mixed with binders are coated, after which at least partial setting of the binder the shaped multi-layer prefabricated unit inserted in clamping plate will.

Die Wandstärke der Einzelrohre wird so gewählt, daß während eines Abgusses die Abnutzung nicht über die Wandstärke des aus hochwertigem Feuerfestmaterial bestehenden Rohres hinausgeht. Es hat sich gezeigt, daß mindestens 40 Gew.%, vorzugsweise 40 bis 60 Gew.°/o, der Fertigbaueinheit aus billigen Mineralstoffen bestehen können. In typischen Ausführungsformen beträgt die Wandstärke des hochwertigen Feuerfestmaterials 5 bis 20, insbesondere 7 bis 15 mm. Die dünnwandigen Einzelrohre haben vorzugsweise eine Feder/Nut-Verbindung. The wall thickness of the individual tubes is chosen so that the wear and tear does not exceed that during a casting Wall thickness of the pipe made of high quality refractory material goes beyond. It has been shown that at least 40% by weight, preferably 40 to 60% by weight, of the prefabricated building unit consist of cheap minerals can. In typical embodiments, the wall thickness of the high-quality refractory material is 5 up to 20, in particular 7 to 15 mm. The thin-walled individual tubes preferably have a tongue and groove connection.

Die Außenabmessungen der geformten, mehrschichtigen Fertigbaueinheit werden nach Maßgabe der zuzustellenden Querschnitte der Gespannplatte oder des Gießtrichters mit einem kleinen Untermaß gewählt, so daß die Fertigbaueinheit leicht eingebaut werden kann. Das verbleibende geringe Untermaß kann z. B. mit Sand ausgefüllt werden. Eine Fertigbaueinheit kann — je nach Länge des Läuferarms der Gespannplatte — eine Länge von mehr als 2 m, insbesondere mehr als 3 m, haben.The external dimensions of the molded, multi-layer prefabricated unit are in accordance with the selected cross-sections of the clamping plate or the pouring funnel with a small undersize, so that the prefabricated unit can be easily installed. The remaining small undersize can, for. B. to be filled with sand. A prefabricated unit can - depending on the length of the rotor arm of the clamping plate - have a length of more than 2 m, in particular more than 3 m.

Als Stoffe für den kostengünstigen Mineralstoffmantel empfehlen sich Sande, Asche, Schlacken und/oder Tuffe (poröses Steinmaterial). Diesen Mineralstoffen werden wasserabbindende oder chemische Binder zugesetzt, so daß eine hinreichende Festigkeit des Mantels gewährleistet ist. Es kann vorteilhaft sein, im Mineralstoffmantel zusätzlich eine Bewehrung, insbesondere eine Eisenarmierung, anzuordnen, um die Stabilität der großformatigen Fertigbaueinheit zu fördern.As substances for the inexpensive mineral coating sand, ash, slag and / or tuff (porous stone material) are recommended. These minerals water-binding or chemical binders are added, so that sufficient strength of the Coat is guaranteed. It can be advantageous to additionally reinforce, in particular an iron reinforcement to be arranged in order to increase the stability of the large-format prefabricated unit support financially.

ORIGINAL INSPECTEDORIGINAL INSPECTED

Gemäß einer weiteren bevorzugten Ausführungsform wird den Stoffen für den Mineralstoffmantel wärmeisolierendes Material beigemischt. So kann es vorteilhaft sein, wenn der Mineralstoffmantel von 10 bis 40 Gew.% wärmeisolierendes Material (z. B. porösen Ton) enthält Das wärmeisolierende Material bewahrt dem im Trichter-Kanalsystem laufenden Stahl vor übermäßiger Abkühlung.According to a further preferred embodiment, the substances for the mineral coating heat-insulating material added. So it can be advantageous if the mineral coat is from 10 to Contains 40% by weight of heat-insulating material (e.g. porous clay) The heat-insulating material is preserved the steel running in the funnel channel system from excessive cooling.

Bei der Herstellung der Fertigteile ist es leicht möglich, vom Gießtrichter in Flußrichtung des Stahles pro Läuferarm unterschiedliche innere Querschnitte vorzusehen. Es ist außerdem vorteilhaft, das Fertigteil spezifisch auf einen Kokillentyp auszulegen und damit immer die zentrische Lage des Steigelochs oder der Steigelöcher zu gewährleisten. isWhen producing the finished parts, it is easy to move from the pouring funnel in the direction of flow of the steel Provide different inner cross-sections for each rotor arm. It is also advantageous to use the finished part specifically designed for a mold type and thus always the central position of the riser hole or the Ensure riser holes. is

Gemäß einer weiteren, bevorzugten Ausführungsform weist die Fertigbaueinheit für die einzelnen Stahlblöcke unterschiedliche Durchmesser auf.According to a further, preferred embodiment, the prefabricated unit for the individual Steel blocks of different diameters.

Die besonderen Vorteile des Erfindungsgegenstandes sind darin zu sehen, daß ohne konstruktiv aufwendige Steinlegevorrichtung eine Vormontage einer preiswerten Fertigbaueinheit möglich ist. Diese Fertigbaueinheit kann von der Bedienungsmannschaft bei erheblich geringerer Hitzebelastung in kurzer Zeit in die Gespannplatte eingesetzt werden. Der durchgehend ausgebildete Außenmantel beim Erfindungsgegenstand bringt den Vorteil mit sich, daß eine Durchbruchgefahr, die z. B. bei einer herkömmlichen Feder- und Nutverbindung gegeben ist, ausgeschlossen ist. Die Kosten für die Herstellung einer Zustellung werden deutlich gesenkt, da der Verbrauch an teurem, hochwertigen Feuerfestmaterial um 40 bis 60% reduziert werden kann.The particular advantages of the subject matter of the invention are to be seen in the fact that it is not structurally complex Stone laying device a pre-assembly of an inexpensive prefabricated unit is possible. This prefabricated unit can be accessed by the operating team in a short time with significantly lower heat exposure Clamping plate are used. The continuously formed outer jacket in the subject matter of the invention has the advantage that a risk of breakthrough z. B. with a conventional tongue and groove connection is given, is excluded. The costs for the production of a delivery are significantly reduced, because the consumption of expensive, high-quality refractory material can be reduced by 40 to 60%.

Nachfolgend wird der Erfindungsgegenstand anhand der in den Figuren gezeigten Ausführungsbeispiele erläutert. Es zeigt F i g. 1 eine Draufsicht auf eine Gespannplatte;The subject matter of the invention is described below on the basis of the exemplary embodiments shown in the figures explained. It shows F i g. 1 is a plan view of a clamping plate;

F i g. 2 einen Schnitt gemäß H-II der Fj g. 1;F i g. 2 shows a section according to H-II of FIG. 1;

F i g. 3 einen Schnitt gemäß III-III der F i g. 1;F i g. 3 shows a section according to III-III of FIG. 1;

F i g. 4 in vergrößerter Darstellung einen Querschnitt durch eine Fertigbaueinheit.F i g. 4 shows, in an enlarged illustration, a cross section through a prefabricated structural unit.

Die F i g. 1 zeigt einen Teil der Gespannplatte 1 mit einem von vier Läuferarmen und dem in der Gespannmitte sitzenden Gießtrichter 3. Der Läuferarm 2 ist mit einer Fertigbaueinheit 4 zugestellt Der Gießtrichter 3 ist mit der Fertigbaueinheit 5 zugestellt (F ig. 3).The F i g. 1 shows part of the clamping plate 1 with one of four rotor arms and the one in FIG Sprue 3 seated in the center of the sprue. The rotor arm 2 is delivered with a prefabricated unit 4 The pouring funnel 3 is delivered with the prefabricated unit 5 (Fig. 3).

Das in F i g. 1 gezeigte Fertigbauteil 4 des Läuferarmes 2 hat etwa eine Länge von 3,60 m, so daß nach dem Stand der Technik für die Zustellung des Läuferarmes 2 etwa 12 Kanalsteine in den Läuferarm 2 einzusetzen wären. Erfindungsgemäß ist dagegen nur ein Fertigbauteil 4 einzusetzen. Vergleichbare Zahlenverhältnisse gelten für die Zustellung des Gießtrichters 3.The in Fig. 1 shown prefabricated part 4 of the rotor arm 2 has a length of about 3.60 m, so that after State of the art to use about 12 channel stones in the runner arm 2 for the delivery of the runner arm 2 would be. According to the invention, however, only one prefabricated component 4 is to be used. Comparable numerical proportions apply to the delivery of the pouring funnel 3.

Die F i g. 2 und 4 verdeutlichen anhand des Fertigbauteils 4 für den Läuferarm 2 den mehrschichtigen Aufbau. Das hochwertige Feuerfestmaterial ist nur für das innenliegende Rohr 6 vorgesehen, welches im einzelnen aus über Nut und Feder verbundenen, dünnwandigen Einzelrohren zusammengesetzt ist Der das Rohr 6 umgebende Außenmantel 7 besteht im wesentlichen aus preiswerten Mineralstoffen, z. B. Sand und Schlacke. Diesen Mineralstoffen kann als wärmedämmendes Material z. B. poröser Ton zugegeben sein. Diese Stoffe werden mit einem Binder vermischt und in einer Form zum Fertigteil 4 geformt Die Form ist so geschalt daß sie unter Berücksichtigung eines geringen Untermaßes dem zuzustellenden Quadratquerschnitt des Läuferarmes 2 entspricht In den mit Mineralstoffen ausgefüllten Ecken des quadratischen Querschnitts ist eine Bewehrung 8 angeordnet um bei der gezeigten, großvolumigen Fertigbaueinheit 4 die Stabilität zu fördern und eine sichere Handhabung von der Form hin zur Gespannplatte zu erlauben. Die im Läuferarm 2 vorzusehenden Steiglöcher tragen die Bezugsziffern 9.The F i g. 2 and 4 illustrate the multi-layer structure based on the prefabricated component 4 for the rotor arm 2. The high-quality refractory material is only provided for the inner tube 6, which in detail The pipe 6 is composed of thin-walled individual pipes connected by tongue and groove surrounding outer jacket 7 consists essentially of inexpensive minerals such. B. Sand and slag. These minerals can be used as a heat insulating material z. B. porous clay may be added. These substances are mixed with a binder and shaped into a finished part 4 in a mold. The mold is formed in such a way that taking into account a slight undersize of the square cross-section of the rotor arm to be delivered 2 corresponds to reinforcement in the corners of the square cross-section filled with minerals 8 arranged to promote stability in the large-volume prefabricated unit 4 shown and a to allow safe handling from the mold to the clamping plate. Those to be provided in the runner arm 2 Riser holes have the reference numbers 9.

Die feuerfeste Zustellung des Gießtrichters 3 ist ebenfalls durch eine Fertigbaueinheit 5 mit einem mehrschichtigen Aufbau gegeben. Innen befinden sich die hochwertigen Rohre 6, umgeben vom preiswerten Mineralstoffmantel 7. Der Mineralstoffmantel 7 ist durchgehend ausgebildet, so daß die Stoßfugen (nicht eingezeichnet) der dünnwandigen Einzelrohre des Rohres 6 überdeckt sind. Ein Durchbruch des flüssigen Stahles ist daher nicht zu befürchten.The refractory lining of the pouring funnel 3 is also through a prefabricated unit 5 with a multi-layer structure given. Inside are the high-quality tubes 6, surrounded by the inexpensive one Mineral jacket 7. The mineral jacket 7 is continuous so that the butt joints (not shown) the thin-walled individual tubes of the tube 6 are covered. A breakthrough of the liquid Steel is therefore not to be feared.

Hierzu 2 Blatt ZeichnungenFor this purpose 2 sheets of drawings

Claims (5)

Patentansprüche:Patent claims: 1. Verfahren zum Zustellen einer Gespannplatte für den Unterguß beim Gießen von Stahlblöcken, wobei aus hochwertigem Feuerfestmaterial bestehende Einzelrohre (Kanalsteine oder Trichterrohre) außerhalb der zuzustellenden Gespannplatte zu einer eine Vielzahl von Einzelrohren umfassenden Einheit vormontiert und anschließend die vormontierte Einheit in die Gespannplatte eingesetzt wird, dadurch gekennzeichnet, daß dünnwandige Einzelrohre aus dem hochwertigen, feuerfesten Material in einer dem zuzustellenden Querschnitt der Gespannplatte oder des Gießtrichters entsprechenden Form von mit Binder versetzten Mineralstoffen ummantelt werden, worauf nach zumindest teilweiser Abbindung des Binders die geformte, mehrschichtige Fertigbau-Einheit in die Gespannplatte eingesetzt wird. 1. Procedure for infeeding a clamping plate for sub-casting when casting steel blocks, whereby individual pipes (sewer stones or funnel pipes) made of high-quality refractory material outside of the clamping plate to be delivered to form a multitude of individual tubes Unit is pre-assembled and then the pre-assembled unit is inserted into the clamping plate, characterized in that thin-walled individual tubes from the high-quality, refractory Material in a corresponding to the cross-section of the clamping plate or the pouring funnel to be delivered Form of minerals mixed with binders are coated, after which at least partial setting of the binder, the shaped, multi-layer prefabricated unit is inserted into the tensioning plate. 2. Fertigbaueinheit zur Durchführung des Verfahrens nach Anspruch 1, dadurch gekennzeichnet, daß der Mineralstoffmantel (7) mindestens 4OGew.°/o des Gewichtes der Fertigbaueinheit (4,5) ausmacht.2. Prefabricated unit for performing the method according to claim 1, characterized in that the mineral coating (7) is at least 40% by weight of the weight of the prefabricated unit (4,5). 3. Fertigbaueinheit nach Anspruch 2, dadurch gekennzeichnet, daß der Mineralstoffmantel (7) Stoffe wie Sande, Asche, Schlacken und/oder Tuffe enthält.3. Prefabricated unit according to claim 2, characterized in that the mineral material jacket (7) Contains substances such as sand, ash, slag and / or tuff. 4. Fertigbaueinheit nach Anspruch 2 oder 3, dadurch gekennzeichnet, daß der Mineralstoffmantel wärmeisolierendes Material enthält.4. Prefabricated unit according to claim 2 or 3, characterized in that the mineral material jacket Contains heat insulating material. 5. Fertigbaueinheit nach einem der Ansprüche 2—4, dadurch gekennzeichnet, daß im Mineralstoffmantel (7) eine Bewehrung (8) angeordnet ist.5. Prefabricated unit according to one of claims 2-4, characterized in that in the mineral material jacket (7) a reinforcement (8) is arranged.
DE19782826606 1978-06-19 1978-06-19 Method for feeding a clamping plate and preassembled unit for carrying out the method Expired DE2826606C2 (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
DE19782826606 DE2826606C2 (en) 1978-06-19 1978-06-19 Method for feeding a clamping plate and preassembled unit for carrying out the method
GB7921110A GB2024065B (en) 1978-06-19 1979-06-18 Runner pipe for a bottom pouring ingot mould plate
FR7915534A FR2429054A1 (en) 1978-06-19 1979-06-18 PROCESS FOR FILLING REFRACTORIES WITH A SOURCE CASTING PLATE FOR THE CASTING OF STEEL LINGOTS AND PREFABRICATED SUB-ASSEMBLY FOR CARRYING OUT THIS PROCESS

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE19782826606 DE2826606C2 (en) 1978-06-19 1978-06-19 Method for feeding a clamping plate and preassembled unit for carrying out the method

Publications (2)

Publication Number Publication Date
DE2826606B1 true DE2826606B1 (en) 1979-06-21
DE2826606C2 DE2826606C2 (en) 1980-02-21

Family

ID=6042031

Family Applications (1)

Application Number Title Priority Date Filing Date
DE19782826606 Expired DE2826606C2 (en) 1978-06-19 1978-06-19 Method for feeding a clamping plate and preassembled unit for carrying out the method

Country Status (3)

Country Link
DE (1) DE2826606C2 (en)
FR (1) FR2429054A1 (en)
GB (1) GB2024065B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2470650A1 (en) * 1979-11-14 1981-06-12 Dyson Refractories Runner system for bottom filling of ingot moulds - where downstick and runner arms consist of row of coaxial tubes in refractory sheath
WO1981001674A1 (en) * 1979-12-15 1981-06-25 Steetley Refractories Ltd Tubular assembly for bottom casting

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107311674B (en) * 2017-07-05 2020-05-12 宝鸡华光铸造材料科技有限公司 Special sprue pipe for casting and preparation method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2470650A1 (en) * 1979-11-14 1981-06-12 Dyson Refractories Runner system for bottom filling of ingot moulds - where downstick and runner arms consist of row of coaxial tubes in refractory sheath
WO1981001674A1 (en) * 1979-12-15 1981-06-25 Steetley Refractories Ltd Tubular assembly for bottom casting

Also Published As

Publication number Publication date
FR2429054B3 (en) 1982-05-28
GB2024065A (en) 1980-01-09
DE2826606C2 (en) 1980-02-21
GB2024065B (en) 1982-10-27
FR2429054A1 (en) 1980-01-18

Similar Documents

Publication Publication Date Title
DE2727742A1 (en) WEARING PARTS FOR SLIDING CLOSURES, METHOD FOR PRODUCING SUCH WEARING PARTS AND SLIDING LOCKING WITH SUCH WEARING PARTS
DE1127508B (en) Process and device for solidifying aqueous nuclear waste
DE1954717A1 (en) Process for the manufacture of refractory parts
CH644340A5 (en) COMPOSITE PRODUCTS MADE OF REFRACTORY MATERIAL.
DE2407753A1 (en) METHOD AND DEVICE FOR THE PRODUCTION OF COMPONENTS AND ELEMENTS PRODUCED THEREOF
DE2602377C2 (en) Arrangement of two interlocking refractory bodies
DE1807731B2 (en) METHOD OF MANUFACTURING FLOAT GLASS
CH617610A5 (en) Horizontal continuous casting machine for metals
DE2826606C2 (en) Method for feeding a clamping plate and preassembled unit for carrying out the method
DE2508445C3 (en) Device for the production of flat glass
DE2318817A1 (en) DEVICE FOR CASTING MOLTEN METAL AND WORKING PROCEDURE FOR OPERATING THE DEVICE
DE3226220C2 (en) Casting process and mold for the production of conical masts made of glass fiber reinforced synthetic resin
DE3815843C2 (en)
DE3340810C2 (en) Method for the production of prismatic components from reinforced concrete, in particular reinforced concrete columns and device for carrying out the method
DE2840398C2 (en) Sliding closure arrangement for tapping on containers containing molten metal
DE2749523C2 (en) Device for preheating parts of a container for molten metal
DE1956550B2 (en) DEVICE FOR MELT FEEDING FOR A CASTING ARRANGEMENT FOR CONTINUOUS WIRE CASTING
AT127420B (en) Channel installation and channel stone for conveying liquid metal, especially for rising cast.
DE2742000C3 (en) Free standing chimney
DE1583572A1 (en) Pouring device
AT147185B (en) Methods and devices for the production of hollow bars and other hollow bodies by casting.
DE1583634C (en) Method and molded body for lining the head of a block form, a goat attachment, riser or the like
DE742527C (en) Process for the manufacture of tap fittings
EP1691961A1 (en) Tool for producing plastic skins
DE1946295A1 (en) Flexible mounting for oxygen blown con- - verter

Legal Events

Date Code Title Description
8339 Ceased/non-payment of the annual fee