DE2604703A1 - STRUCTURE OF THE STRUCTURE AND METHOD OF ITS PRODUCTION - Google Patents
STRUCTURE OF THE STRUCTURE AND METHOD OF ITS PRODUCTIONInfo
- Publication number
- DE2604703A1 DE2604703A1 DE19762604703 DE2604703A DE2604703A1 DE 2604703 A1 DE2604703 A1 DE 2604703A1 DE 19762604703 DE19762604703 DE 19762604703 DE 2604703 A DE2604703 A DE 2604703A DE 2604703 A1 DE2604703 A1 DE 2604703A1
- Authority
- DE
- Germany
- Prior art keywords
- columns
- bars
- beams
- openings
- base plates
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/35—Extraordinary methods of construction, e.g. lift-slab, jack-block
- E04B1/3511—Lift-slab; characterised by a purely vertical lifting of floors or roofs or parts thereof
Description
Gebäudeskelett und Verfahren zu seiner Herstellung.Building skeleton and process for its manufacture.
Die Erfindung betrifft ein Gebäudeskelett und ein Verfahren zu seiner Herstellung.The invention relates to a building skeleton and a method for its production.
Derzeit werden im Hochbau die Säulen und Balken überwiegend an Ort und Stelle gefertigt, d. h. es werden die Betonsäulen an Ort und Stelle gegossen und nach ihrem Abbinden werden dann gleichzeitig die Balken und Decken gegossen.At the moment, the pillars and beams are mostly manufactured on site in building construction, i. H. it will be the concrete pillars poured in place and after they have set, the beams and ceilings are then poured at the same time.
Dieses Bauverfahren erfordert es, die verlorenen Schalwände und Lehrgerüste an Ort und Stelle zu errichten.This construction method requires the lost formwork walls and falsework to be erected on the spot.
Bei der industrialisierten Errichtung von Gebäuden geht die Tendenz überwiegend in Richtung auf die Vorfertigung selbsttragender Wandelemente. Ihre Errichtung und ihr Zusammenbau erfordert hochqualifizierte Arbeitskräfte und technische Ausrüstungen, wobei ihr Ergebnis eine Konstruktion ist, die genormt und insofern starr ist, als keine Abweichung gegenüber einer vorgegebenen Norm möglich ist.In the industrialized construction of buildings, the tendency is predominantly towards the prefabrication of self-supporting ones Wall elements. Their erection and assembly require highly skilled labor and technical Equipment, the result of which is a construction that is standardized and rigid in that it does not deviate from it a given standard is possible.
609334/0731609334/0731
ORIGINAL INSPECTEDORIGINAL INSPECTED
Es ist eine Aufgabe dieser Erfindung, ein Gebäudeskelett zu schaffen, dessen Bestandteile in der Werkstatt hergestellt und an Ort und Stelle in den fertigen und endgültigen Zustand gebracht werden können, wodurch der Bedarf an verlorenen Schalwänden und Lehrgerüsten entfällt.It is an object of this invention to provide a building skeleton the components of which are manufactured in the workshop and can be brought to the finished and final state on the spot, eliminating the need for lost shuttering walls and falsework is omitted.
Es ist eine weitere Aufgabe der Erfindung, ein Gebäudeskelett zu schaffen, dessen Errichtung und Zusammenbau keine qualifizierten oder spezialisierten Arbeitskräfte und Ausrüstungen erfordert, obwohl diese Errichtung und dieser Zusammenbau in einem Zehntel der Zeit durchführbar ist, die bei herkömmlichen, konventionellen Verfahren erforderlich ist.It is a further object of the invention to provide a building skeleton that is unqualified to erect and assemble or requires specialized manpower and equipment, although this construction and assembly in one-tenth of the time required by conventional, conventional processes.
Es ist eine weitere Aufgabe der Erfindung, ein Gebäudeskelett zu schaffen, das unstarr ist, d. h. für jede Art von Gebäudekonstruktion geeignet ist.It is another object of the invention to provide a building skeleton that is non-rigid, i.e., non-rigid. H. for every type of building construction suitable is.
Die Lösung der gestellten Aufgaben besteht darin, daß das Gebäudeskelett aus einer Mehrzahl von Säulen, aus horizontalen Balken mit darin angebrachten Öffnungen zur Aufnahme der Säulen und aus Mitteln zur Befestigung der Balken an den Säulen in vorgegebenen Höhenlagen besteht.The solution to the problem is that the building skeleton of a plurality of pillars, of horizontal beams with openings made therein for receiving the pillars and consists of means for fastening the beams to the pillars at predetermined heights.
Die Säulen werden in den Fundamenten in parallelen Reihen angeordnet, wobei der Abstand der Säulen einer jeden Reihe gleich dem Abstand der Öffnungen in den horizontalen Balken ist, die in gewünschten Höhenlagen an den Säulen befestigt werden, wobei der Abstand zwischen den Balken der gleichen Höhenlage und benachbarter Reihen durch Deckenplatten überbrückt wird.The columns are arranged in parallel rows in the foundations, the spacing of the columns of each row being equal to the spacing of the openings in the horizontal beams which be attached to the pillars at the desired elevation, with the distance between the beams of the same elevation and adjacent rows is bridged by ceiling tiles.
Die Befestigung der horizontalen, die Decke tragenden Balken an den Säulen und in der gewünschten Höhenlage kann auf viele Arten erfolgen; eine der einfachsten besteht darin, in diesen Höhenlagen in den Säulen Perforationen vorzusehen und in diese oder durch diese einen Stift oder Bolzen zu stecken, der aus diesen Perforationen hervorsteht. Der vorstehende Abschnitt der Bolzen dient als Stütze für die Balken.The fastening of the horizontal beams supporting the ceiling to the columns and at the desired height can be done by many Types are made; one of the simplest is to provide perforations in and into the columns at these altitudes or to stick a pin or bolt through them protruding from these perforations. The previous section the bolt serves as a support for the beams.
609834/0731609834/0731
Anhand der nun folgenden Beschreibung der in der Zeichnung dargestellten
Ausführungsbeispiele der Erfindung wird diese näher erläutert.
Es zeigt:This will be explained in more detail on the basis of the following description of the exemplary embodiments of the invention shown in the drawing.
It shows:
Fig. 1 drei Säulen mit daraufgeschobenen Balken,
Fig. 2 Säulen benachbarter Reihen mit darauf befestigten Balken und mit den Abstand zwischen benachbarten Balken
überbrückenden Deckenplatten,
eine andere Ausführungsform eines Balkens, eine Ausführungsform einer Aussteifung der Verbindungsstelle
zwischen Säule und Balken, eine mögliche Endöffnung eines Balkens, den Einbau einer vorgefertigten Deckenplatte zwischen
benachbarten Balken,Fig. 1 shows three columns with beams pushed onto them, Fig. 2 columns of adjacent rows with beams fastened on them and with ceiling panels bridging the distance between adjacent beams,
another embodiment of a beam, an embodiment of a stiffening of the connection point between column and beam, a possible end opening of a beam, the installation of a prefabricated ceiling plate between adjacent beams,
das Gießen an Ort und Stelle einer teilweise vorgefertigten Deckenplatte und
eine mögliche Bolzenkonstruktion.pouring in place a partially prefabricated ceiling slab and
a possible bolt construction.
Mit dem Bezugszeichen 1 sind die Säulen gekennzeichnet, die in Plinthen oder Sockelplatten 2 eingesetzt sind. In Fig. 1 sind fünf Balken 3 gezeigt, die auf drei Säulen 1 aufgesetzt sind und bereit sind auf die gewünschte Höhenlage angehoben und dort befestigt zu werden, während ein sechster Balken in bereits angehobener und in seiner Lage befestigter Stellung dargestellt ist. Jeder Balken 3 ist mit Öffnungen 4 versehen, durch welche die Säulen 1 eingesetzt werden. In den Säulen sind Perforationen 5a, 5b, 5c, 5d, 5e, 5f vorgesehen, durch die Stifte oder Bolzen 6 gesteckt werden, auf welchen die Balken aufsitzen. Die Fig. 8 zeigt eine Bolzenart, die wegen ihrer Festigkeit und ihrer einfachen Herstellungsweise vorteilhaft ist. Sie besteht aus einem Stück eines I-Profils, das durch Armierungseisen und Zementmörtel verstärkt ist.The columns which are inserted in plinths or base plates 2 are identified by the reference numeral 1. In Fig. 1 are five bars 3 are shown, which are placed on three pillars 1 and ready to be raised to the desired height and to be attached there while a sixth beam is in already raised and in its position fixed position is shown. Each beam 3 is provided with openings 4 through which the columns 1 are used. In the columns, perforations 5a, 5b, 5c, 5d, 5e, 5f are provided through the pins or bolts 6, on which the bars sit. Fig. 8 shows a type of bolt, because of its strength and its simple manufacturing is advantageous. It consists of a piece of an I-profile that is reinforced with reinforcement bars and Cement mortar is reinforced.
Die Figur 3. zeigt eine Variante der in Fig. 2 gezeigten Balken. Die Abwandlung besteht darin, daß an der Unterseite der Balken an der Stelle, an der sie auf den Bolzen 6 aufliegen, eine Nut 7FIG. 3 shows a variant of the bars shown in FIG. The modification is that on the underside of the beams at the point where they rest on the bolt 6, a groove 7
- 4 609834/0731 - 4 609834/0731
vorgesehen ist, in der der Bolzen 6 in Eingriff bleibt, wenn der Balken einmal auf ihn abgesenkt worden ist. Die Balken 3 können aus jedem geeigneten Material und von jeder geeigneten Bauart sein. Die in der Zeichnung gezeigte Bauart ist besonders vorteilhaft. Es handelt sich um ein vorgefertigtes, flaches Element mit abgestuften Längsseiten, wobei die Stufe 8 längs jeder Längsseite verläuft, um ein Auflager für die entgegengesetzt abgestuften Deckenplatten 9 oder 10 zu bilden.is provided in which the bolt 6 remains engaged once the beam has been lowered onto it. The bars 3 can be of any suitable material and of any suitable type. The type shown in the drawing is special advantageous. It is a prefabricated, flat element with stepped long sides, with step 8 longitudinal each longitudinal side extends to form a support for the oppositely stepped ceiling panels 9 or 10.
Die Öffnungen 4 in den Balken 3 sind dem Säulenquerschnitt angepaßt, jedoch mit etwas Übermaß mit Rücksicht auf die Toleranzen, die durch die Erfordernisse des Zusammenbaus mit den Säulen notwendig erscheinen. Die Zwischenräume, die zwischen dem Rand der Öffnung und den Seitenflächen der durch sie geführten Säule verbleiben, werden abgedichtet, wenn der Balken an seinem Platz montiert ist, indem eine Füllung 11 aus Zementmörtel in die Zwischenräume eingefüllt wird. Auf diese Weise erfüllen die Balken zusätzlich zu ihrer normalen Funktion, die Deckenplatten zu tragen, noch die Aufgabe, die Querverbindung zwischen den Säulen der gleichen Reihe zu sichern. Obwohl die Figur 1 Balken zeigt, die drei Säulen verbinden, ist es offensichtlich, daß die Balken kurzer ausgeführt werden können, um zwei Säulen zu verbinden, oder länger, um eine Reihe von mehr als drei Säulen zu verbinden. Es können auch die Öffnungen, insbesondere die beiden am Ende gelegenen Öffnungen, nach der kurzen Seite der Balken geöffnet sein, wie die Öffnung 12 in Fig. 5. Dies ergibt eine größere Toleranz bei der Errichtung des Skeletts, macht aber andererseits die Fertigstellung des Skeletts schwieriger.The openings 4 in the beams 3 are adapted to the column cross-section, however with a little oversize with regard to the tolerances caused by the requirements of the assembly with the pillars seem necessary. The spaces between the edge of the opening and the side surfaces of the column passing through it remain, are sealed when the beam is mounted in place by inserting a filling 11 of cement mortar into the Gaps is filled. In this way, in addition to their normal function, the joists also fulfill the ceiling tiles to carry, nor the task of securing the cross connection between the columns of the same row. Although the figure 1 bar shows the three pillars connecting, it is evident that the beams can be made shorter to make two pillars join, or longer to join a series of more than three pillars. The openings, in particular the two openings located at the end, to the short side of the beam, as the opening 12 in Fig. 5. This results a greater tolerance in the erection of the skeleton, but on the other hand makes the completion of the skeleton more difficult.
Die Säulen 1 werden vorzugsweise durchlaufend für die gesamte Skeletthöhe hergestellt und können entweder aus Stahl oder armiertem Beton bestehen.The columns 1 are preferably continuous for the whole Skeleton height and can be made of either steel or reinforced concrete.
Die Fig. 6 zeigt die Anbringung einer vollständig vorgefertigten Deckenplatte 9. Das durch die Augen 14 gezogene Seil 13 wird durch eine nicht gezeigte Winde gespannt und an den Enden des Skeletts befestigt, um die Längsausrichtung sicherzustellen. 6 shows the attachment of a completely prefabricated ceiling plate 9. The rope 13 drawn through the eyes 14 is tensioned by a winch (not shown) and fastened to the ends of the skeleton in order to ensure the longitudinal alignment.
- 5 -6098 34/0731- 5 -6098 34/0731
Die Fig. 7 zeigt die Anbringung einer teilweise vorgefertigten Deckenplatte 10, die auf der Baustelle fertiggestellt wird. Diese Vollendung geschieht dadurch, daß Beton vergossen wird, bis die Armierung der Deckenplatte vollständig bedeckt ist.Fig. 7 shows the attachment of a partially prefabricated ceiling plate 10, which is completed on the construction site. This completion takes place in that concrete is poured until the reinforcement of the ceiling plate is completely covered.
Ein bevorzugtes Verfahren zur Errichtung des Skeletts wird wie folgt durchgeführt:
Schritt 1 A preferred method of erecting the skeleton is performed as follows:
Step 1
Verankerung der Sockelplatte 2 im Boden, wobei ihre Ausnehmungen entsprechend den Abständen der Öffnungen 4 und/oder 12 .in den
Balken 3 angeordnet sind.
Schritt 2 Anchoring of the base plate 2 in the ground, with its recesses being arranged in the beams 3 according to the distances between the openings 4 and / or 12.
step 2
Aufstapeln der erforderlichen Anzahl von Balken, einer über
den anderen, auf den Sockelplatten 2, wobei ihre Öffnungen 4 mit den Ausnehmungen der Sockelplatten fluchten. Abstandshalter
15 halten den Balkenstapel mit Abstand oberhalb der Ausnehmungen der Sockelplatten, um die Befestigung der Säulen entsprechend
Schritt 3 zu ermöglichen.
Schritt 3 Stack the required number of beams, one on top of the other, on the base plates 2, with their openings 4 aligned with the recesses in the base plates. Spacers 15 hold the stack of beams at a distance above the recesses in the base plates in order to enable the columns to be fastened in accordance with step 3.
step 3
Die Säulen 1 werden durch die Öffnungen 4 in die Ausnehmungen
der Sockelplatten 2 eingesetzt, wo sie zunächst durch Keile befestigt werden, worauf der Spalt zwischen dem Rand der Ausnehmungen
und den Seitenflächen der Säulen mit Zementmörtel ausgefüllt wird.
Schritt 4 The columns 1 are inserted through the openings 4 into the recesses of the base plates 2, where they are first fastened by wedges, after which the gap between the edge of the recesses and the side surfaces of the columns is filled with cement mortar.
Step 4
Der oberste Balken 3 des Stapels wird etwas über die oberste Säulenperforation 5a angehoben, durch die ein Bolzen 6 gesteckt wird, auf den der Balken 3 aufgelagert wird. Der Balken wird gegen jegliche horizontale Verschiebung dadurch gesichert, daß Zementmörtel in den Spalt zwischen den Seitenflächen der Säule 1 und dem Rand der Öffnung 4 eingefüllt wird (Fig. 4). Dieser Schritt wird für die weiteren Balken des Stapels wiederholt, die nacheinander über die Säulenperforationen 5b, 5c, 5d usw. angehoben und wie beschrieben befestigt werden. Schritt 5 The top bar 3 of the stack is raised slightly above the top column perforation 5a, through which a bolt 6 is inserted, on which the bar 3 is supported. The beam is secured against any horizontal displacement in that cement mortar is poured into the gap between the side surfaces of the column 1 and the edge of the opening 4 (Fig. 4). This step is repeated for the other beams of the stack, which are lifted one after the other over the column perforations 5b, 5c, 5d etc. and fastened as described. Step 5
Deckenplatten der Form 9 oder 10 werden zwischen die Balken 3 benachbarter Säulenreihen eingefügt und dicht mit ihnen verbunden.Ceiling panels of the form 9 or 10 are inserted between the beams 3 of adjacent rows of columns and tightly connected to them.
609834/0731609834/0731
Ohne vom Erfindungsgedanken abzuweichen, können viele Abwandlungen an den hier beschriebenen und gezeigten Ausführungsformen der Erfindung vorgenommen werden. So können beispielsweise die Säulen 1 jeden Querschnitt aufweisen und können auch auf anderen Fundamenten als den beschriebenen Sockelplatten verankert sein. Die Balken können jede Form und Länge aufweisen, um beispielsweise unterschiedliche Decken - etwa durchlaufende Decken - zu tragen und um zwei oder mehr als drei Säulen zu verbinden, wie sie im Beispiel gezeigt sind.Many modifications can be made without deviating from the inventive concept on the embodiments of the invention described and shown here. For example the columns 1 have any cross-section and can also be anchored on other foundations than the base plates described. The bars can be any shape and length have, for example, to carry different blankets - such as continuous blankets - and by two or more than to connect three pillars as shown in the example.
609834/0731609834/0731
Claims (7)
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
IT4350275A IT1056357B (en) | 1975-02-07 | 1975-02-07 | OPEN PREFABRICATED ELEMENTS FOR MULTI-STOREY BUILDING STRUCTURES |
Publications (1)
Publication Number | Publication Date |
---|---|
DE2604703A1 true DE2604703A1 (en) | 1976-08-19 |
Family
ID=11254862
Family Applications (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE19767603410 Expired DE7603410U1 (en) | 1975-02-07 | 1976-02-06 | PREFABRICATED BUILDING SKELETON |
DE19762604703 Pending DE2604703A1 (en) | 1975-02-07 | 1976-02-06 | STRUCTURE OF THE STRUCTURE AND METHOD OF ITS PRODUCTION |
Family Applications Before (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DE19767603410 Expired DE7603410U1 (en) | 1975-02-07 | 1976-02-06 | PREFABRICATED BUILDING SKELETON |
Country Status (7)
Country | Link |
---|---|
AT (1) | AT347084B (en) |
BE (1) | BE838329A (en) |
CH (1) | CH606652A5 (en) |
DE (2) | DE7603410U1 (en) |
FR (1) | FR2300182A1 (en) |
GB (1) | GB1529502A (en) |
IT (1) | IT1056357B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
AT383168B (en) * | 1984-07-24 | 1987-05-25 | Ebenseer Betonwerke Gmbh | SLOPE COVERING |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2117025A (en) * | 1982-03-17 | 1983-10-05 | R E P S Y Sa | Load bearing structure for buildings |
GB2543513A (en) * | 2015-10-20 | 2017-04-26 | Bryden Wood Tech Ltd | Building system |
-
1975
- 1975-02-07 IT IT4350275A patent/IT1056357B/en active
-
1976
- 1976-02-03 FR FR7603533A patent/FR2300182A1/en not_active Withdrawn
- 1976-02-04 AT AT77676A patent/AT347084B/en not_active IP Right Cessation
- 1976-02-04 GB GB435576A patent/GB1529502A/en not_active Expired
- 1976-02-05 CH CH143376A patent/CH606652A5/xx not_active IP Right Cessation
- 1976-02-06 DE DE19767603410 patent/DE7603410U1/en not_active Expired
- 1976-02-06 DE DE19762604703 patent/DE2604703A1/en active Pending
- 1976-02-06 BE BE164138A patent/BE838329A/en unknown
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
AT383168B (en) * | 1984-07-24 | 1987-05-25 | Ebenseer Betonwerke Gmbh | SLOPE COVERING |
Also Published As
Publication number | Publication date |
---|---|
DE7603410U1 (en) | 1977-08-04 |
ATA77676A (en) | 1978-04-15 |
BE838329A (en) | 1976-05-28 |
GB1529502A (en) | 1978-10-25 |
IT1056357B (en) | 1982-01-30 |
AT347084B (en) | 1978-12-11 |
FR2300182A1 (en) | 1976-09-03 |
CH606652A5 (en) | 1978-11-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE2354316C2 (en) | Prefabricated building | |
DE1807716A1 (en) | Prefabricated, transportable room element for the production of buildings | |
DE1287302B (en) | Prefabricated, transportable room element for the production of buildings | |
DE2101084A1 (en) | Procedure for erecting a structure | |
DE1759915B2 (en) | METHOD OF MANUFACTURING ROOM BOXES FOR FABRIC HOUSES | |
DE2231943A1 (en) | MODULAR UNIT AND PROCESS FOR MANUFACTURING A BUILDING ACCORDING TO A MODULAR SYSTEM | |
DE1284076B (en) | Method of erecting a building | |
DE4407000C2 (en) | Round support for building buildings | |
DE2604703A1 (en) | STRUCTURE OF THE STRUCTURE AND METHOD OF ITS PRODUCTION | |
DE2645910C2 (en) | Formwork for erecting funnel-shaped or conical concrete structures | |
WO2017046365A1 (en) | Flat component, stiffening plate, building module, stairwell module and multi-storey building | |
DE19941603C2 (en) | Reinforced concrete part for the production of foundations for buildings | |
DE1684213C3 (en) | Buildings with frames made from individual parts | |
DE820068C (en) | Process for the production of monolithic masonry between removable formwork and formwork supports for this purpose | |
DE2051002C3 (en) | Frame construction, consisting of prefabricated reinforced concrete parts | |
DE3027019C2 (en) | ||
DE3505592A1 (en) | Shuttering for structures which are rotationally symmetrical, in particular cylindrical and conical, e.g. tapering slightly upwards | |
DE1221422B (en) | Method for erecting walls from posts and wall elements inserted between them, and then erected wall and posts for the wall | |
DE3206535A1 (en) | Floor structure using prefabricated parts | |
DE721195C (en) | Structure that can be dismantled | |
DE1609558C3 (en) | Wall construction | |
DE1609708C (en) | Shear connector for multi-layer concrete slabs, process for its production and multi-layer concrete slab equipped with it | |
DD296528A5 (en) | BUILDING | |
DE824255C (en) | Process for erecting buildings with incomplete skeleton construction | |
DE1509038A1 (en) | Process for the production of prefabricated wall construction elements and a device for its implementation |