DE202014003187U1 - Fixing and centering element for at least two pipe pairs of geothermal probes - Google Patents

Fixing and centering element for at least two pipe pairs of geothermal probes Download PDF

Info

Publication number
DE202014003187U1
DE202014003187U1 DE202014003187.8U DE202014003187U DE202014003187U1 DE 202014003187 U1 DE202014003187 U1 DE 202014003187U1 DE 202014003187 U DE202014003187 U DE 202014003187U DE 202014003187 U1 DE202014003187 U1 DE 202014003187U1
Authority
DE
Germany
Prior art keywords
fixing
centering element
tube
pairs
pipe pairs
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
DE202014003187.8U
Other languages
German (de)
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Geowell Holding De GmbH
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to DE202014003187.8U priority Critical patent/DE202014003187U1/en
Publication of DE202014003187U1 publication Critical patent/DE202014003187U1/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24TGEOTHERMAL COLLECTORS; GEOTHERMAL SYSTEMS
    • F24T10/00Geothermal collectors
    • F24T10/10Geothermal collectors with circulation of working fluids through underground channels, the working fluids not coming into direct contact with the ground
    • F24T10/13Geothermal collectors with circulation of working fluids through underground channels, the working fluids not coming into direct contact with the ground using tube assemblies suitable for insertion into boreholes in the ground, e.g. geothermal probes
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/10Geothermal energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Sustainable Development (AREA)
  • Sustainable Energy (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Heat-Exchange Devices With Radiators And Conduit Assemblies (AREA)

Abstract

Fixier- sowie Zentrierelement für wenigstens zwei Rohrpaare von Erdwärmesonden mit einem mittig zwischen den Rohrpaaren angeordneten Verpressschlauch, wobei die Rohrpaare und der Verpressschlauch ein Rohrbündel bilden, wobei das Fixier- sowie Zentrierelement aus einem Rohr gefertigt ist, an dem bogenförmig nach außen, entgegen der Einbaurichtung des Rohrbündels in eine Vertikal-Erdbohrung ragende Flügel angeordnet sind und wobei zwischen den seitlichen Flanken der Flügel die Rohrpaare angeordnet sind, dadurch gekennzeichnet, dass die Seitenkanten der Flügel auf gleicher Höhe Erhebungen aufweisen, deren Abstände zueinander geringfügig kleiner sind als der Durchmesser der Wärmetauscherrohre und dass die Wärmetauscherrohre hinter die Erhebungen in Richtung Verpressschlauch einrastbar sind.Fixing and centering element for at least two pairs of tubes of geothermal probes with a compression hose arranged centrally between the pairs of tubes, the pairs of tubes and the compression tube forming a tube bundle, the fixing and centering element being made from a tube, on the outside in an arc shape, counter to the installation direction of the tube bundle are arranged in a vertical earth hole projecting wing and wherein the tube pairs are arranged between the lateral flanks of the wing, characterized in that the side edges of the wing have elevations at the same height, the distances from each other are slightly smaller than the diameter of the heat exchanger tubes and that the heat exchanger tubes can be snapped behind the elevations in the direction of the injection hose.

Description

Die Erfindung betrifft ein Fixier- sowie Zentrierelement für wenigstens zwei Rohrpaare von ErdwärmesondenThe invention relates to a fixing and centering element for at least two pipe pairs of geothermal probes

Ein solches Fixier- sowie Zentrierelement ist in der DE 10 2010 054 514 A1 gezeigt und beschrieben. Die dort gezeigte Vorrichtung wird in Verbindung mit Erdwärmesonden, also Wärmetauscher, die vertikal ins Erdreich eingebracht werden, in zunehmendem Maße eingesetzt, um in Verbindung mit einer Wärmepumpe für deren Verdampferkreislauf Wärme aus dem Erdreich zu entnehmen.Such a fixing and centering is in the DE 10 2010 054 514 A1 shown and described. The device shown there is used in conjunction with geothermal probes, so heat exchangers, which are introduced vertically into the ground, increasingly used to remove in conjunction with a heat pump for the evaporator cycle heat from the ground.

In dem oben genannten Dokument ist ausführlich ein Stand der Technik beschrieben, in dem derartige Fixierelemente gezeigt und beschrieben sind.The above-mentioned document describes in detail a prior art in which such fixing members are shown and described.

Allen dort offenbarten bekannten Zentrierelementen haftet der Nachteil an, dass diese sehr sperrig ausgebildet sind. so dass sie zusammen mit den Wärmetauscherrohren nur schwer in das Erdreich vertikal eingebracht, geschweige denn im Falle einer Fehlmontage wieder aus dem Erdreich herausgebracht werden können.All known centering elements disclosed therein have the disadvantage that they are very bulky. so that they are difficult to bring into the ground together with the heat exchanger tubes, let alone brought out of the ground in the event of incorrect assembly again.

Hier schafft das oben genannte Dokument insofern Abhilfe, als das Fixierelement fingerartige, nach außen ragende Flügel aufweist, die beidseitig bzw. nach Anspruch 10 in Verbindung mit der Beschreibung Index 0037 auch einseitig an einem Montagerohr befestigt sein können. Damit das Montagerohr auf dem mittig in dem Rohrbündel angeordneten Pressschlauch befestigt werden kann, ist dieses zwangsläufig geschlitzt, d. h. es ist möglich, das Montagerohr der Flügel so weit auseinander zu biegen, dass ein Aufrasten auf den Verpressschlauch möglich ist.Here, the above-mentioned document remedy insofar as the fixing element has finger-like, outwardly projecting wings that can be attached on both sides or according to claim 10 in conjunction with the description index 0037 also on one side of a mounting tube. So that the mounting tube can be fastened on the press tube arranged centrally in the tube bundle, this tube is necessarily slotted, d. H. it is possible to bend the mounting tube of the wings so far apart that it is possible to snap onto the injection tube.

Insofern ergeben sich mit dieser dort gezeigten Einrichtung gegenüber dem Stand der Technik schon erhebliche Vorteile.In this respect, there are considerable advantages with this device shown there compared to the prior art.

Der Grund, warum ein so großes Augenmerk auf eine korrekte Fixierung der Wärmetauscherrohre an dem Verpressschlauch gezeigt ist, liegt an der VDI-Vorschrift 4640, BI. 2 , und weiteren Leitfäden von Bundesländern zur Nutzung von Erdwärme, die dort präziser beschrieben ist. In diesen Vorschriften wird die vollständige Umhüllung der eingebauten Rohre mit Verpressmaterial und der Einbau mit Abstands- und Zentrierhalter empfohlen bzw. gefordert. Konkret wird in den wassertechnischen Erlaubnisbescheiden dies so gefordert. Dies ist allerdings Sache der jeweiligen Landkreise, entsprechend deren Einstellungen, Kenntnissen, Voreingenommenheiten und länderspezifischen Vorgaben. Danach wird genehmigt, bzw. auferlegt. Außerdem ist es aus Gründen eines effizienten Betriebes notwendig, die einzelnen Wärmetauscherrohre gegeneinander zu beabstanden, damit kein thermischer Kurzschluss entsteht, denn die Temperatur des in die Wärmetauscher hineinströmenden Mediums ist deutlich kälter, als die des wiederhochströmenden.The reason why such a great attention is paid to a correct fixation of the heat exchanger tubes to the injection hose is due to the VDI regulation 4640, BI. 2 , and further guides from federal states to the use of geothermal energy, which is described there more precisely. These regulations recommend or require the complete enclosure of the installed pipes with grouting material and the installation with spacer and centering brackets. Specifically, this is required in the water technical permit notices. However, this is a matter for the respective districts, according to their attitudes, knowledge, biases and country-specific requirements. After that, it is approved or imposed. In addition, it is necessary for reasons of efficient operation, the individual heat exchanger tubes from each other to space, so that no thermal short circuit occurs, because the temperature of the flowing into the heat exchanger medium is significantly colder than that of re-flowing.

Es ist also schon von erheblicher Bedeutung, dass hier eine zuverlässige Fixierung und Zentrierung der Wärmetauscherrohre innerhalb einer Vertikalbohrung eingehalten wird.So it is already of considerable importance that here a reliable fixation and centering of the heat exchanger tubes is maintained within a vertical bore.

Die vorliegende Erfindung, die von dem Fixier- sowie Zentrierelement nach der vorgenannten DE ausgeht, liegt die Aufgabe zugrunde:

  • • die Fixierwirkung der Wärmetauscherrohre innerhalb des Rohrbündels deutlich zu verbessern und eine sichere Zentrierung des Rohrbündels innerhalb des Bohrloches zu gewährleisten,
  • • das Herstellverfahren des Fixier- sowie Zentrierelementes zu vereinfachen und
  • • das Ein- und eventuelle Wiederherausbringen des Rohrbündels in bzw. aus einer Vertikalbohrung zu erleichtern.
The present invention, which proceeds from the fixing and centering element according to the aforementioned DE, is based on the object:
  • To significantly improve the fixing effect of the heat exchanger tubes within the tube bundle and to ensure a secure centering of the tube bundle within the bore hole,
  • • To simplify the manufacturing process of the fixing and centering and
  • • facilitating the insertion and eventual re-launching of the tube bundle into or out of a vertical hole.

Dies wird mit den Maßnahmen erreicht, die im Anspruch 1 aufgeführt sind. Weitere vorteilhafte Gestaltungen sind den Maßnahmen der Unteransprüche zu entnehmen.This is achieved with the measures listed in claim 1. Further advantageous designs can be found in the measures of the subclaims.

Anhand von Zeichnungen soll der Gegenstand der Erfindung beispielhaft erläutert werden.The subject matter of the invention will be explained by way of example with reference to drawings.

Dabei zeigen:Showing:

1 eine perspektivische Darstellung eines Rohrbündels mit einem erfindungsgemäßen Fixier- sowie Zentrierelement, 1 a perspective view of a tube bundle with a fixing and centering element according to the invention,

2 einen Querschnitt eines in einer Erdbohrung montierten Rohrbündels nebst Fixier- sowie Zentrierelement und 2 a cross section of a tube bundle mounted in a well bore together with fixing and centering and

3 ein Bespiel einer Rastverbindung des die Flügel des Fixier- sowie Zentrier-elementes tragenden Rohres. 3 an example of a locking connection of the wings of the fixing and centering element bearing tube.

Die 1 zeigt mit Pos. 1 das Fixier- sowie Zentrierelement. Wesentlicher Bestandteil dieses Elementes sind Flügel (2, 3, 4 und 5), die an einem Rohr (6) befestigt, bevorzugt mit diesem Rohr (6) fertigungstechnisch mitgespritzt sind. Sie sind nach dem Spritzen schräg zum Rohr und entgegen der Einbaurichtung in die Vertikalbohrung positioniert und weisen einen max. Durchmesser an den Flügelenden auf, der deutlich größer ist, als der Durchmesser der Vertikalbohrung, in die das oben bereits beschriebene Rohrbündel einzubringen ist. Dadurch wird auf die Flügelenden beim Einbringen des Rohrbündels in eine Vertikalbohrung ein radialer Druck ausgeübt, der ein verlässliches Zentrieren des Rohrbündels gewährleistet und es wird weiterhin eine Fixierwirkung auf die Wärmetauscherrohre in Bezug auf ihre Positionierung ausgeübt, wie unten noch beschrieben.The 1 shows with pos. 1 the fixing and centering element. An essential part of this element are wings ( 2 . 3 . 4 and 5 ) attached to a pipe ( 6 ), preferably with this tube ( 6 ) are injected with production technology. They are positioned after spraying at an angle to the pipe and against the installation direction in the vertical bore and have a max. Diameter at the wing tips, which is significantly larger than the diameter of the vertical bore, in which the above-described tube bundle is to be introduced. As a result, a radial pressure is exerted on the wing ends during introduction of the tube bundle into a vertical bore, which ensures a reliable centering of the tube bundle and it is further exerted a fixing effect on the heat exchanger tubes with respect to their positioning, as described below.

Diese Art der Doppelwirkung verkörpert das besondere Wesen dieser Erfindung.This type of dual action embodies the special nature of this invention.

Das Rohr (6) besteht aus zwei identischen Hälften (9, 10, 2), die miteinander an den Stellen (7, 8) verbunden sind.The pipe ( 6 ) consists of two identical halves ( 9 . 10 . 2 ), which are in contact with each other ( 7 . 8th ) are connected.

Ein Beispiel einer Verbindungstechnik zeigt die 3, in der auf der Stirnseite der einen Hälfte eine Steckleistenanordnung (11) und auf der Stirnseite der anderen Hälfte eine Buchsenleiste (12) angeordnet ist, die bevorzugt unter Zuhilfenahme eines Werkzeuges miteinander verrastet werden.An example of a connection technique shows the 3 in which on the front side of the one half a connector strip arrangement ( 11 ) and on the front side of the other half a female connector ( 12 ) is arranged, which are preferably locked together with the aid of a tool.

An Stelle dieser dort gezeigten Verbindungstechnik wäre aber durchaus auch eine an sich bekannte Kabelverbindungstechnik möglich, d. h. auf der einen Seite des halbförmig ausgebildeten Rohres wären dann die weiblichen Teile des Kabelbinders und auf der anderen Seite die männlichen festgelegt, die mit einfachsten Mitteln miteinander verbindbar wären. Diese Kabelbinderhälften könnten selbstverständlich beim Spritzprozess der Rohrhälften mitgespritzt werden.Instead of this connection technology shown there but also quite a known cable connection technology would be possible, d. H. on one side of the semi-shaped tube then the female parts of the cable tie and on the other side would be set the male, which would be connected to each other by the simplest means. These cable tie halves could of course be injected with the injection process of the tube halves.

In 1 ist weiterhin der Pressschlauch (13) gezeigt, um den herum vier Wärmetauscherrohre (14, 15, 16 und 17) angeordnet sind. Durch diese Wärmetauscherrohre wird in Pfeilrichtung, siehe oben in 1, ein frostsicheres Medium gepumpt, entsprechende Verbindungen zwischen den Rohrpaaren sind in 1 unten gestrichelt dargestellt. Das Wärmetauschermedium nimmt, vetreinfacht dargestellt, dabei Wärme aus dem Erdreich auf, überführt diese auf den Verdampfer einer Wärmepumpenanlage, die diese Wärme mit hoher Effizienz auf die Kondensatorseite der Wärmepumpe überführt, von der aus dann die entsprechende Beheizung von Räumen gespeist wird.In 1 is still the press hose ( 13 ) around which four heat exchanger tubes ( 14 . 15 . 16 and 17 ) are arranged. Through these heat exchanger tubes is in the direction of arrow, see above in 1 , a frost-proof medium pumped, appropriate connections between the pipe pairs are in 1 shown in dashed lines below. The heat exchanger medium takes, shown in simplified form, while heat from the soil, transferred to the evaporator of a heat pump system, which transfers this heat with high efficiency to the condenser side of the heat pump, from which then the corresponding heating of rooms is fed.

Dies sind Vorgänge, die dem Durchschnittsfachmann derartiger Anlagen wohl bekannt sind.These are processes well known to those of ordinary skill in the art of such equipment.

Zusammengefasst kann gesagt werden, dass die Wärmetauscherrohre zusammen mit dem Verpressschlauch und mit Hilfe der Fixier- und Zentrierelemente zu einem mechanisch relativ fest zueinander gehörenden Bündel, also einem Rohrbündel, aufbereitet sind, das dann in eine Vertikalbohrung in das Erdreich eingebracht wird.In summary, it can be said that the heat exchanger tubes, together with the injection tube and with the aid of the fixing and centering elements, are processed into a bundle which is mechanically relatively fixed to one another, ie a tube bundle, which is then introduced into a vertical bore in the soil.

Der Verpressschlauch (13) dient dazu, nachdem dieses Rohrbündel in das Erdreich eingebracht ist, ein Verpressmedium von unten nach oben fortschreitend in die Vertikalbohrung einzubringen, das sich dann um diese Einheit dichtend herumlegt, dabei diese Rohrbündeleinheit fixiert und letztendlich auch die Wärme vom Erdreich gut auf die Wärmetauscherrohre überträgt.The injection hose ( 13 ) serves, after this tube bundle is introduced into the soil, progressively introduce a Verpressmedium from bottom to top in the vertical bore, which then wraps around this unit sealingly, this tube bundle unit fixed and ultimately transmits the heat from the soil well on the heat exchanger tubes ,

Dieses Verpressmaterial ist dem Beton ähnlich, weist aber neben den nahezu identischen Festigkeitseigenschaften weitere spezifische auf, die hier für den Wärmetausch notwendig sind. Die Konsistenz jedenfalls beim Einbringen ist einer gießfähigen Betonmischung ähnlich.This grout material is similar to concrete, but in addition to the almost identical strength properties, further specific, which are necessary here for the heat exchange. The consistency at least when introducing is similar to a pourable concrete mixture.

Beim Auffüllen des Vertikal-Bohrloches mit diesem Verpressmaterial ist es wichtig, dass an keiner Stelle die Wärmetauscherrohre mit dem Erdreich in Berührung kommen, so dass Querverbindungen unterschiedlicher Grundwasserstockwerke unterbrochen und, sollte einmal eine Undichtigkeit eines Wärmetauscherrohres erfolgen, was dann einen Austritt der Wärmtauscherflüssigkeit in der Erdreich bedeuten würde, zuverlässig verhindert wird.When filling the vertical borehole with this grout material, it is important that at no point the heat exchanger tubes come into contact with the soil, so that cross connections of different groundwater floors interrupted and, should a leak of a heat exchanger tube occur, which then a leakage of heat exchange fluid in the Soil would be reliably prevented.

Damit die Wärmetauscherrohre sowohl in axialer wie auch in vertikaler Montagerichtung zuverlässig fixiert werden und bleiben, sind an den Seitenkanten der Flügel etwa im Bereich der Montagestellen der Wärmetauscherrohre Erhebungen (18, 19) vorgesehen, über die in Richtung zum Verpressschlauch die Wärmetauscherrohre gedrückt werden, um dann hinter den Erhebungen eingerastet zu sein.Thus, the heat exchanger tubes are reliably fixed both in the axial and in the vertical mounting direction and remain, are on the side edges of the wings approximately in the region of the mounting points of the heat exchanger tubes surveys ( 18 . 19 ) are provided, over which the heat exchanger tubes are pressed in the direction of the injection tube, in order then to be engaged behind the elevations.

Diese Erhebungen umgreifen gewissermaßen dabei zuverlässig die Wärmetauscherrohre (20, 21) und dadurch, dass die Öffnungsbreite zwischen den Erhebungen (a, in 2) kleiner ist, als der Durchmesser (b, in 2) der Wärmetauscherrohre, wird zuverlässig verhindert, dass diese aus ihrer eingerasteten Position wieder herausgehen können.To a certain extent, these elevations reliably surround the heat exchanger tubes ( 20 . 21 ) and in that the opening width between the elevations (a, in 2 ) is smaller than the diameter (b, in 2 ) of the heat exchanger tubes, is reliably prevented that they can go out of their locked position again.

Das Einrasten bereitet keinerlei Probleme, denn die Flügel sind so elastisch an dem Befestigungsrohr (6) befestigt, bzw. an diese angespritzt, dass ein seitliches Ausweichen und damit Vergrößern des Abstandes zwischen den Erhebungen erfolgen kann. Selbst wenn drei Wärmetauscherrohre eingerastet sind, ist es kein Problem auch das vierte noch einzurasten, hierzu ist es lediglich notwendig, die Flügel, in die dieses vierte Rohr eingerastet werden soll, in ihrer radialen Ebene zu verschränken, so dass wieder Raum zum Einrasten für das Rohr gegeben ist.The snapping does not cause any problems, because the wings are so elastic on the mounting tube ( 6 ), or sprayed on this, that a lateral deflection and thus increase the distance between the surveys can be done. Even if three heat exchanger tubes are engaged, there is no problem even the fourth still engage, this is only necessary to interlock the wings in which this fourth tube is to be locked in its radial plane, so again space for snapping for the Tube is given.

In dem Moment, wo das Rohrbündel mit dieser Fixier- und Zentriereinheit in ein Bohrloch eingebracht ist, mithin also auf die Flügel über das Bohrloch noch ein radialer Druck ausgeübt wird, setzt sich dieser Druck verständlicherweise auch auf die Erhebungen fort, so dass die Fixierwirkung letzt noch erhöht wird, so dass eine absolut zuverlässige Positionierung des Fixier- und Zentrierelementes innerhalb des Rohrbündels gewährleistet ist.At the moment when the tube bundle is introduced into a borehole with this fixing and centering unit, and thus a radial pressure is exerted on the wings via the borehole, this pressure is understandably also extended to the elevations, so that the fixing effect is last is still increased, so that is an absolutely reliable Positioning of the fixing and centering element is ensured within the tube bundle.

In 1 sind diese Erhebungen (18, 19) gezeigt, die hier Bereiche (20 und 21) des in diesem Falle mit Pos. 14 gekennzeichneten Wärmetauscherrohres umgreifen.In 1 are these surveys ( 18 . 19 ) shown here areas ( 20 and 21 ) of the in this case with pos. 14 embrace the marked heat exchanger tube.

Die Enden der Flügel sind nach Art einer Gleitkufe geformt, so, wie das bei Schlitten bzw. Skiern und anderen Gegenständen, die störungsfrei gleiten müssen, an sich bekannt ist.The ends of the wings are shaped in the manner of a skid, as is known in sledges or skis and other objects that must slide smoothly.

Es ist ersichtlich, dass bei derartiger geometrischer Ausbildung der Flügelenden nicht nur ein problemloses, also hakelfreies Einbringen der Rohrbündel möglich ist, sondern auch ein Wiederherausziehen, wozu die kurzen, ebenfalls Gleitstummel-Charakter aufweisenden Flügelenden hilfreich sind.It can be seen that with such geometric design of the wing tips not only a trouble, so hakelfreies introduction of the tube bundle is possible, but also a Wiederherausziehen what the short, also Gleitstummel character having wing tips are helpful.

In 2 ist mehr schematisch noch mit der Pos. 22 eine Anordnung von Erhebungen gezeigt, die dem Rohr (6) beim Aufbringen auf den Pressschlauch (13) eine gewisse Elastizität verleihen sollen, um z. B. unterschiedliche Durchmessertoleranzen des Verpressschlauches auszugleichen. Statt der dort gezeigten Erhebungen, die beispielsweise lippenähnlich ausgebildet sein können, ist es aber auch denkbar, das Montagesrohr (6) so zu gestalten, dass es elastisch gegenüber dem Pressschlauch verbleibt, was dadurch erreicht werden kann, dass der Teilkreisdurchmesser der beiden Rohrhälften gegenüber dem Durchmesser des Pressschlauches deutlich größer ausgebildet ist, so dass dieser den Pressschlauch nicht völlig eng, sondern mehr mittig umschließt, sodass eine gewisse Elastizität bei der Montage verbleibt.In 2 is more schematic still with the pos. 22 shown an array of bumps that the pipe ( 6 ) when applied to the compression tube ( 13 ) should give a certain elasticity to z. B. compensate for different diameter tolerances of Verpressschlauches. Instead of the surveys shown there, which may be formed, for example, lip-like, but it is also conceivable, the mounting tube ( 6 ) so that it remains elastic with respect to the compression tube, which can be achieved in that the pitch circle diameter of the two tube halves compared to the diameter of the compression tube is much larger, so that it surrounds the compression tube not completely tight, but more centrally, so a certain elasticity remains during assembly.

Weiterhin günstig ist es, wenn die Erhebungen (22) ein Material aufweisen, das deutlich elastischer ist, als das übrige Material, was heute im Rahmen der Integralspritztechnik ohne weiteres möglich ist.It is furthermore advantageous if the surveys ( 22 ) have a material that is significantly more elastic than the rest of the material, which is readily possible today in the integral injection molding technique.

ZITATE ENTHALTEN IN DER BESCHREIBUNG QUOTES INCLUDE IN THE DESCRIPTION

Diese Liste der vom Anmelder aufgeführten Dokumente wurde automatisiert erzeugt und ist ausschließlich zur besseren Information des Lesers aufgenommen. Die Liste ist nicht Bestandteil der deutschen Patent- bzw. Gebrauchsmusteranmeldung. Das DPMA übernimmt keinerlei Haftung für etwaige Fehler oder Auslassungen.This list of the documents listed by the applicant has been generated automatically and is included solely for the better information of the reader. The list is not part of the German patent or utility model application. The DPMA assumes no liability for any errors or omissions.

Zitierte PatentliteraturCited patent literature

  • DE 102010054514 A1 [0002] DE 102010054514 A1 [0002]

Zitierte Nicht-PatentliteraturCited non-patent literature

  • VDI-Vorschrift 4640, BI. 2 [0007] VDI regulation 4640, BI. 2 [0007]

Claims (9)

Fixier- sowie Zentrierelement für wenigstens zwei Rohrpaare von Erdwärmesonden mit einem mittig zwischen den Rohrpaaren angeordneten Verpressschlauch, wobei die Rohrpaare und der Verpressschlauch ein Rohrbündel bilden, wobei das Fixier- sowie Zentrierelement aus einem Rohr gefertigt ist, an dem bogenförmig nach außen, entgegen der Einbaurichtung des Rohrbündels in eine Vertikal-Erdbohrung ragende Flügel angeordnet sind und wobei zwischen den seitlichen Flanken der Flügel die Rohrpaare angeordnet sind, dadurch gekennzeichnet, dass die Seitenkanten der Flügel auf gleicher Höhe Erhebungen aufweisen, deren Abstände zueinander geringfügig kleiner sind als der Durchmesser der Wärmetauscherrohre und dass die Wärmetauscherrohre hinter die Erhebungen in Richtung Verpressschlauch einrastbar sind.Fixing and centering element for at least two pipe pairs of borehole heat exchangers with a centrally located between the pipe pairs Verpressschlauch, wherein the pipe pairs and the Verpressschlauch form a tube bundle, wherein the fixing and centering element is made of a tube, at the arcuate outward, against the installation direction of the tube bundle are arranged in a vertical Erdbohrung projecting wings and wherein the tube pairs are arranged between the side flanks of the wings, characterized in that the side edges of the wings at the same height have elevations whose distances from each other are slightly smaller than the diameter of the heat exchanger tubes and the heat exchanger tubes can be latched behind the elevations in the direction of the injection tube. Fixier- sowie Zentrierelement für wenigstens zwei Rohrpaare von Erdwärmesonden nach Anspruch 1, dadurch gekennzeichnet, dass als Erhebung die Seitenkantengeometrie der Flügel im Bereich der Wärmetauscherrohre einen Kreisabschnitt bilden, der größer ist als der halbe Umfang der Wärmetauscherrohre.Fixing and centering element for at least two pipe pairs of geothermal probes according to claim 1, characterized in that form as survey the side edge geometry of the wings in the heat exchanger tubes a circular section which is greater than half the circumference of the heat exchanger tubes. Fixier- sowie Zentrierelement für wenigstens zwei Rohrpaare von Erdwärmesonden nach Anspruch 1, dadurch gekennzeichnet, dass die Seitenkanten der Flügel Erhebungen aufweisen, die dreieckförmig ausgebildet sind.Fixing and centering element for at least two pipe pairs of geothermal probes according to claim 1, characterized in that the side edges of the wings have elevations which are triangular in shape. Fixier- sowie Zentrierelement für wenigstens zwei Rohrpaare von Erdwärmesonden nach Anspruch 1, dadurch gekennzeichnet, dass die Flügelenden nach Art einer Gleitkurve gekrümmt sind.Fixing and centering element for at least two pipe pairs of geothermal probes according to claim 1, characterized in that the wing ends are curved in the manner of a sliding cam. Fixier- sowie Zentrierelement für wenigstens zwei Rohrpaare von Erdwärmesonden nach Anspruch 1, dadurch gekennzeichnet, dass dieses aus zwei identischen Hälften mit jeweils halbem Montagerohr aufgebaut ist, wobei an den Seiten der das Montagerohr bildenden Halbrohre Befestigungselemente nach Art miteinander verrastbarer Teile angeordnet sind.Fixing and centering element for at least two pipe pairs of geothermal probes according to claim 1, characterized in that it is constructed of two identical halves with each half mounting tube, being arranged on the sides of the mounting tube forming half-tubes fasteners in the nature of each other latchable parts. Fixier- sowie Zentrierelement für wenigstens zwei Rohrpaare von Erdwärmesonden nach Anspruch 5, dadurch gekennzeichnet, dass die Befestigungselemente nach Art bekannter Kabelbinder aufgebaut sind, die beim Herstellprozess der identischen Hälften mitgespritzt werden.Fixing and centering element for at least two pipe pairs of geothermal probes according to claim 5, characterized in that the fastening elements are constructed in the manner of known cable ties, which are injected with the same process during the production of identical halves. Fixier- sowie Zentrierelement für wenigstens zwei Rohrpaare von Erdwärmesonden nach Anspruch 1, dadurch gekennzeichnet, dass auf der Innenseite der Montagerohre bzw. deren Montagerohrhälften Erhebungen angeordnet sind.Fixing and centering element for at least two pipe pairs of geothermal probes according to claim 1, characterized in that elevations are arranged on the inside of the mounting tubes or their mounting tube halves. Fixier- sowie Zentrierelement für wenigstens zwei Rohrpaare von Erdwärmesonden nach Anspruch 7, dadurch gekennzeichnet, dass die Erhebungen elastisch aufgebaut sind.Fixing and centering element for at least two pipe pairs of geothermal probes according to claim 7, characterized in that the elevations are constructed elastically. Fixier- sowie Zentrierelement für wenigstens zwei Rohrpaare von Erdwärmesonden nach Anspruch 7, dadurch gekennzeichnet, dass der Querschnitt der zu einem Montagerohr zusammengesetzten Halbrohre ellipsenförmig aufgebaut ist.Fixing and centering element for at least two pipe pairs of geothermal probes according to claim 7, characterized in that the cross section of the composite to a mounting tube half-tubes is constructed elliptical.
DE202014003187.8U 2014-04-14 2014-04-14 Fixing and centering element for at least two pipe pairs of geothermal probes Expired - Lifetime DE202014003187U1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DE202014003187.8U DE202014003187U1 (en) 2014-04-14 2014-04-14 Fixing and centering element for at least two pipe pairs of geothermal probes

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE202014003187.8U DE202014003187U1 (en) 2014-04-14 2014-04-14 Fixing and centering element for at least two pipe pairs of geothermal probes

Publications (1)

Publication Number Publication Date
DE202014003187U1 true DE202014003187U1 (en) 2014-05-07

Family

ID=50778588

Family Applications (1)

Application Number Title Priority Date Filing Date
DE202014003187.8U Expired - Lifetime DE202014003187U1 (en) 2014-04-14 2014-04-14 Fixing and centering element for at least two pipe pairs of geothermal probes

Country Status (1)

Country Link
DE (1) DE202014003187U1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108385690A (en) * 2018-04-13 2018-08-10 薛 � A kind of annular mud jacking distributor and mud jacking system
DE102017008566A1 (en) 2017-09-12 2019-03-14 Blz Geotechnik Gmbh Hose-pipe system and apparatus and method of making a hose-pipe system

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102010054514A1 (en) 2010-12-15 2012-06-21 Robert Kreikenbohm Fixing element and centralizer for two pairs of pipes of geothermal, has grouting hose arranged in center between pairs of pipes, where pair of pipe and grouting hose forms pipe bundle

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102010054514A1 (en) 2010-12-15 2012-06-21 Robert Kreikenbohm Fixing element and centralizer for two pairs of pipes of geothermal, has grouting hose arranged in center between pairs of pipes, where pair of pipe and grouting hose forms pipe bundle

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
VDI-Vorschrift 4640, BI. 2

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102017008566A1 (en) 2017-09-12 2019-03-14 Blz Geotechnik Gmbh Hose-pipe system and apparatus and method of making a hose-pipe system
WO2019052592A1 (en) 2017-09-12 2019-03-21 Blz Geotechnik Gmbh Hose-pipe system and device and method for producing a hose-pipe system
CN108385690A (en) * 2018-04-13 2018-08-10 薛 � A kind of annular mud jacking distributor and mud jacking system
CN108385690B (en) * 2018-04-13 2023-09-05 薛一 Annular mud jacking distributor and mud jacking system

Similar Documents

Publication Publication Date Title
EP3364090B1 (en) Connector for connection between two fluid-conveying elements
EP2669561B1 (en) Pipe connection device
WO2017036922A1 (en) Cooling plate of a battery cooler
DE202014003187U1 (en) Fixing and centering element for at least two pipe pairs of geothermal probes
DE102012107263B4 (en) Plug-in device in an end area of a line and method for producing a plug-in device
DE102014106802A1 (en) Covering a pipe section, in particular a junction of district heating pipes
DE102008060914A1 (en) Fastening device and method for connecting hydraulic lines
DE102017207053B4 (en) Exhaust pipe and method for cutting an exhaust pipe
DE102008017659A1 (en) Storage container i.e. buffer storage, for heater, has circular upper, lower and intermediate segments detachably connected and/or clamped with each other, where upper and/or lower segments have uniformly pressed bumped boiler head
EP2626610B1 (en) Device for connecting tube sections
DE10002974B4 (en) Pipe coupling with tolerance compensation
DE102013009687B4 (en) Pipe connection for thermoplastic pipes
EP3064849A1 (en) Distributor system, in particular air distributor system
WO2002053870A1 (en) Rod linkage
DE4010234A1 (en) Pipe connection esp. for cable protection conduits - has inner and outer side smooth wall course in region of pipe connection places suitable for transmitting traction
DE102013103534A1 (en) "Plug connection part for a line connector, in particular for a ready-made media line"
DE2038697C3 (en) Pipe coupling
DE202015100630U1 (en) Hose clamp for securing a corrugated hose
DE102016223634A1 (en) filling device
EP1519096A1 (en) Pressure-tight coupling between a corrugated pipe, or a connector and a connecting member
DE102016100405A1 (en) Plug connection for connecting pipes with an oval cross-section
DE102014115639A1 (en) Door seal system
DE102007053002A1 (en) Connector arrangement for use with connecting element as expansion joint, particularly for connection of solar collectors, has connecting element, where sealed connection is made between connecting element and collector tube
EP2789742B1 (en) Connecting device for an essentially leakproof connection of a first channel element with a second channel element of a channel
EP2558762B1 (en) Connection between a pipe and a pipe component

Legal Events

Date Code Title Description
R086 Non-binding declaration of licensing interest
R207 Utility model specification

Effective date: 20140612

R081 Change of applicant/patentee

Owner name: STIEBEL ELTRON GMBH & CO. KG, DE

Free format text: FORMER OWNER: KREIKENBOHM, ROBERT, 37627 STADTOLDENDORF, DE

Effective date: 20140912

Owner name: GEOWELL HOLDING GMBH, DE

Free format text: FORMER OWNER: KREIKENBOHM, ROBERT, 37627 STADTOLDENDORF, DE

Effective date: 20140912

R081 Change of applicant/patentee

Owner name: GEOWELL HOLDING GMBH, DE

Free format text: FORMER OWNER: STIEBEL ELTRON GMBH & CO. KG, 37603 HOLZMINDEN, DE

R150 Utility model maintained after payment of first maintenance fee after three years
R151 Utility model maintained after payment of second maintenance fee after six years
R079 Amendment of ipc main class

Free format text: PREVIOUS MAIN CLASS: F24J0003080000

Ipc: F24T0010130000

R152 Utility model maintained after payment of third maintenance fee after eight years
R071 Expiry of right