DE1108622B - Procedure for the assembly of pipes in the water to form a pipeline - Google Patents

Procedure for the assembly of pipes in the water to form a pipeline

Info

Publication number
DE1108622B
DE1108622B DEL30478A DEL0030478A DE1108622B DE 1108622 B DE1108622 B DE 1108622B DE L30478 A DEL30478 A DE L30478A DE L0030478 A DEL0030478 A DE L0030478A DE 1108622 B DE1108622 B DE 1108622B
Authority
DE
Germany
Prior art keywords
water
pipes
floating
box
pumped
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
DEL30478A
Other languages
German (de)
Inventor
Dr Hubert Ludwieg
Dipl-Ing Hans Geiger
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HANS GEIGER DIPL ING
HUBERT LUDWIEG DR
Original Assignee
HANS GEIGER DIPL ING
HUBERT LUDWIEG DR
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HANS GEIGER DIPL ING, HUBERT LUDWIEG DR filed Critical HANS GEIGER DIPL ING
Priority to DEL30478A priority Critical patent/DE1108622B/en
Publication of DE1108622B publication Critical patent/DE1108622B/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/26Repairing or joining pipes on or under water

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

Verfahren für den Zusammenbau von Rohren im Wasser zu einer Rohrleitung Es ist bekannt, beim Bau von Dükern (d. h. beim Bau von Rohrleitungen, mit denen man einen Flußlauf, ein Hafenbecken od. dgl. kreuzt) die Rohre zu der notwendigen Länge dadurch an Land und also im Trockenen zusammenzubauen, daß man am Ufer oberhalb des Wasserspiegels eine Helling baut, auf der die Rohre montiert und alsdann zu Wasser gelassen werden.Method for assembling pipes in the water to form a pipeline It is known in the construction of culverts (i.e. in the construction of pipelines to cross a river, a harbor or the like) thereby the pipes to the necessary length to assemble on land and thus in the dry, that one builds a slipway on the bank above the water level, on which the pipes are mounted and then lowered into the water.

Ebenso ist es bekannt, nach Dockbauweise seitlich zum Fluß im geeigneten Uferboden eine trockene Baugrube auszuheben, in der die Rohre ungestört zusammengebaut werden können. Alsdann wird diese Baugrube geflutet und die fertige Rohrleitung (nach Durchstoßen des trennenden Dammes) in das freie Wasser hinausgeschwommen.It is also known to use a dock construction to the side of the river in a suitable manner Excavate a dry construction pit in which the pipes can be assembled undisturbed can be. Then this excavation is flooded and the finished pipeline (after piercing the dividing dam) swam out into the open water.

Neu ist es auch nicht mehr, die Rohre auf der Plattform eines Schiffes stückweise zusammenzusetzen und dann (ähnlich einer Seekabelverlegung) vom Schiff aus in das Wasser abzusenken.It is no longer new either, the pipes on the platform of a ship put together piece by piece and then (similar to laying submarine cables) from the ship from lowering into the water.

Schließlich ist es auch bekannt, die Rohre rechtwinklig zum Ufer an Land (auf der Geländeoberfläche) zu einem Strang zusammenzubauen und dann mit Winden od. dgl. in den Strom hineinzuziehen.Finally, it is also known to attach the pipes at right angles to the bank To assemble land (on the surface of the land) into a string and then with winches or the like into the stream.

Diese beiden letzten Verfahren sind jedoch nur üblich, wenn der Düker nicht die bekannte gedrungene Trapezforin aufweist, sondern praktisch nur einen geraden langen Stab darstellt, der erst auf dem Flußgrund eine dem Flußquerschnitt angepaßte Form annnimmt.These last two procedures, however, are only common when the culvert does not have the well-known squat trapezoidal shape, but practically only one straight long rod represents, which only on the river bottom one of the river cross-section adopts adapted form.

Ferner ist es bekannt, die Rohre über dem Wasserspiegel und über der bereits fertig ausgehobenen Rinne dadurch im Trockenen zusammenzubauen, daß man in das Wasser hinein feste oder schwimmende Gerüste bringt, an denen die Rohre frei über dem Wasser hängend zusammengebaut und dann mittels Winden abgesenkt werden.It is also known that the pipes above the water level and above the to assemble already finished dug channel in the dry by that one brings fixed or floating scaffolding into the water, on which the pipes are free assembled hanging over the water and then lowered by means of winches.

Schließlich ist es auch noch bekannt, bei Einsatz großer Schwimmkräne und unter Verwendung von Kugelmuffen die zu verbindenden Rohrenden frei über dem Wasser schwebend zu montieren, wobei die bereits zusammengebauten Rohrstränge stufenförmig abgesenkt und auf dem Flußgrund abgelegt werden.Finally, it is also known when using large floating cranes and using ball sockets, the pipe ends to be connected freely above the To mount water floating, whereby the already assembled pipe strings are stepped be lowered and deposited on the river bed.

Auch ist es bekannt, die Rohre im Schutze einer eingespundeten und leergepumpten Grube gleich an Ort und Stelle am Grunde des Flusses im Trockenen zusammenzubauen.It is also known that the pipes are protected by a bungee and emptied pit right on the spot at the bottom of the river in the dry assemble.

Alle diese Verfahren für den Zusammenbau der Rohre zu einem Däker sind jedoch sehr kostspielig. Auch erfordern sie viel Platz am Ufer oder Spezialschiffe, oder aber sie behindern den Schiffsverkehr. 5 Man ist deshalb auch dazu übergegangen, in Meeresgebieten mit wechselnden Tide-Wasserständen den Düker dadurch zusammenzubauen, daß man ihn parallel zum Ufer auf dem Trockenen auslegte und dann Ebbe und Flut ausnutzte, indem man ihn bei Flut regelrecht überfluten und bei Ebbe »trockenfallen« ließ. Man hatte dann die Möglichkeit, die Rohre in der Zeit zwischen Hoch- und Niedrigwasser im Trockenen zu montieren, um sie dann bei Hochwasser leicht ins Wasser hinauszuschwimmen indem man Schwimmkörper anbaute oder die Leitung leerpumpte, wodurch sie den nötigen Auftrieb erhielt.However, all of these methods of assembling the pipes into a roofer are very costly. They also require a lot of space on the bank or special ships, or they hinder shipping traffic. 5 For this reason there has also been a move to assemble the culvert in sea areas with changing tidal water levels by laying it out on dry land parallel to the bank and then exploiting the ebb and flow of the tide by literally flooding it at high tide and "drying it out" at low tide let. It was then possible to assemble the pipes in the dry between high and low tide, and then easily swim them out into the water during high tide by adding floats or pumping out the pipe, which gave it the necessary buoyancy.

Dieses letztere Verfahren ist jedoch nur bei kleineren Durchmessern üblich. Es setzt geeignetes Ufergelände voraus. In der Regel sind die Ufer aber ungeeignet, z. B. zu steil, zu kurvig, zu sehr bebaut oder zu sumpfig.However, this latter method is only applicable to smaller diameters common. It assumes a suitable bank area. As a rule, however, the banks are unsuitable, e.g. B. too steep, too curvy, too built up or too swampy.

Die Frage des Montageplatzes ist jedenfalls, wie man sieht, von erstrangiger Bedeutung für den Dükerbau.In any case, as you can see, the question of the assembly area is of prime importance Significance for culvert construction.

Die vorliegende Erfindung bietet nun die Möglichkeit, die Rohre auch bei ungeeigneten Uferverhältnissen auf dem Wasser ohne großen Schiffsaufwand zusammenzubauen. Eine Wasserfläche von genügender Länge läßt sich erfahrungsgemäß in nicht allzu großer Entfernung vom Versenkungsplatz immer finden. Benötigt wird lediglich ein kleiner Schwimmkasten. Die großen Kosten für den Bau von Hellingen, Docks, Graben, Spezialschiffen usw. entfallen. Bei der vorliegenden Erfindung wird z. B. ein einteiliger oder zweiteiliger Schwimmkasten 1 um die Verbindungsstelle zweier Rohrenden 2 und 3 herumgebaut. Dieser Schwimmkasten 1 wird dann gegen die beiden Rohrenden 2 und 3 mittels Dichtungen 4 abgedichtet, wie das Fig. 1 bis 4 zeigen. Vorher werden die Rohrenden zweckmäßig mittels Blindflanschen 5 verschlossen, wodurch der Auftrieb ausgenutzt wird und kein- Wasser in die Rohre dringen kann.The present invention now offers the possibility of assembling the pipes on the water even with unsuitable bank conditions without great ship effort. Experience has shown that a water surface of sufficient length can always be found at a not too great distance from the dumping site. All you need is a small swimming pool. The high costs of building slipways, docks, trenches, special ships, etc. are eliminated. In the present invention, e.g. B. a one-piece or two-piece floating box 1 built around the junction of two pipe ends 2 and 3. This floating box 1 is then sealed against the two pipe ends 2 and 3 by means of seals 4, as FIGS. 1 to 4 show. Before this, the pipe ends are expediently closed by means of blind flanges 5 , whereby the buoyancy is used and no water can penetrate into the pipes.

Alsdann wird der Schwimmkasten 1 leergepumpt, so daß die beiden zu verbindenden Rohrenden 2 und 3 nun im Trockenen liegen._ Der Schwimmkasten 1 ist in der Regel oben völlig offen. Man kann also ungehindert in diesen Kasten ein- und aussteigen. Während der verschiedenen Wasserstände (Ebbe und Flut) schwimmt der Kasten zusammen mit den beiden zu verbindenden Rohren auf dem Wasser auf und nieder, und die in ihm arbeitenden Monteure können die Verbindung der beiden Rohrenden ungestört im Trockenen vornehmen, nachdem die Blindflanschen 5 an den beiden Rohrenden zuvor entfernt wurden.Then, the float chamber 1 is pumped out, so that the two pipe ends to be joined 2 and 3 now in the dry liegen._ The float chamber 1 is completely open in the rule above. So you can get in and out of this box unhindered. During the different water levels (ebb and flow) the box floats up and down on the water together with the two pipes to be connected, and the fitters working in it can connect the two pipe ends undisturbed in the dry after the blind flanges 5 on the two Pipe ends have been removed beforehand.

In der Zeichnung (Fig. 1 bis 3) ist der Schwimmkasten 1 als einteiliger Kasten gezeichnet.In the drawing (Fig. 1 to 3) the floating box 1 is drawn as a one-piece box.

Die öffnungen 6 in den Stirnwünden des Schwimmkastens 1 sind hier kreisförnüge Ausschnitte mit genügend großem Durchmesser, so daß z. B. im Falle einer Flanschverbindung auch die Flansche noch durch diese öffnung hindurchgehen.The openings 6 in the end walls of the floating tank 1 are circular cutouts with a sufficiently large diameter so that, for. B. in the case of a flange connection, the flanges also pass through this opening.

Fertigt man den Schwimmkasten aus Holz, so ist er im Wasser von Natur aus in jedem Falle schwimmfähig und daher leicht zu handhaben.If you make the swimming pool out of wood, it is natural in the water in any case buoyant and therefore easy to handle.

Die beiden Öffnungen 6 in den Stirnwänden sind z. B. durch eiserne Rohrstutzen 7 eingerahmt, auf welche die Dichtungen 4 wasserdicht aufgeschnürt werden können, wie das die Fig. 2 und 3 zeigen. Das andere Ende jeder Dichtung wird unmittelbar auf das zugehörige Rohr geschnürt, wobei etwaige Falten in der Dichtung nach oben in die wasserfreie Zone gelegt werden. Pumpt man jetzt den Schwimmkasten 1 leer, so kann kein Wasser mehr von außen in den Kasten eindringen. Zweckmäßig führt man dieses Abdichtungsprinzip an jeder Stimwand doppelt durch, um die Sicherheit zu erhöhen. In den Fig. 2 und 3 ist jedoch aus Gründen der übersichtlichkeit nur eine Dichtung an jeder Stirnseite gezeichnet.The two openings 6 in the end walls are z. B. framed by iron pipe stub 7, to which the seals 4 may be unlaced waterproof, as shown in FIGS. 2 and 3. The other end of each seal is immediately laced onto the associated pipe, with any folds in the seal being laid up into the anhydrous zone. If the swimming box 1 is now pumped empty, water can no longer penetrate the box from the outside. This sealing principle is expediently carried out twice on each end wall in order to increase safety. In FIGS. 2 and 3 , however, only one seal is drawn on each end face for the sake of clarity.

Um ein Kippen des Schwimmkastens 1 zu verhindern, wird man ihn zweckmäßig mit zwei seitlichen Schwimmem bzw. Pontons 8 od. dgl. ausrüsten und mit diesen über eiserne Träger 9 zu einer starren Einheit verbinden, wie das die Fig. 1 bis 3 zeigen.In order to prevent the flotation box 1 from tipping over, it will expediently be equipped with two lateral floats or pontoons 8 or the like and connected to these via iron girders 9 to form a rigid unit, as shown in FIGS. 1 to 3 .

Beim Leerpumpen des Schwinunkastens 1 entsteht begreiflicherweise ein entsprechender Auftrieb. Um ein unerwünschtes Aufschwimmen des Kastens zu verhindern, wird das ausgepumpte Wasser mit Vorteil in die beiden benachbarten Pontons 8 übergeleitet, so daß sich an den Tauchtiefen dieser zu einer Einheit verbundenen Schwimmkörper nichts ändert. Die Höhenlage des Schwimmkastens 1 bleibt dann im Wasser unverändert. Die beiden Pontons 8 sind zweckmäßig mit inneren Schotts versehen, damit es innerhalb der Pontons beim Zupumpen des Wassers nicht zu unerwünschten Schülpbewegungen kommt, wodurch die ganze Einheit eventuell instabil im Wasser liegen könnte. Durch mehr oder minder starkes Fluten der Pontons kann im übrigen die Höhenlage der Einheit im Wasser genau einreguliert werden. Werden die beiden Pontons groß genug gewählt, so können sie den beim Leerpumpen des Schwimmkastens entstehenden Auftrieb eventuell auch allein durch ihr großes Eigengewicht aufnehmen, wodurch sich eine überleitung des ausgepumpten Wassers in die Pontons erübrigt.Understandably, when the Schwinunkastens 1 is pumped out, a corresponding buoyancy arises. In order to prevent undesired floating of the box, the pumped-out water is advantageously transferred into the two adjacent pontoons 8 so that nothing changes in the diving depths of these floating bodies connected to form a unit. The height of the floating box 1 then remains unchanged in the water. The two pontoons 8 are expediently provided with inner bulkheads so that undesirable scuffing movements do not occur within the pontoons when the water is pumped in, as a result of which the entire unit could possibly lie unstable in the water. By more or less strong flooding of the pontoons, the height of the unit in the water can also be precisely regulated. If the two pontoons are chosen to be large enough, they can possibly absorb the buoyancy that arises when the floating tank is pumped out due to their own weight alone, which makes it unnecessary to transfer the pumped water into the pontoons.

Beim Leerpumpen des Schwimmkastens 1 versucht der äußere Wasserdruck außerdem, die beiden Rohrenden 2 und 3 tief in den Kasten hineinzuschieben, d. h., es werden die beiden Rohrenden in axialer Richtung aufeinander zu bewegt und gegeneinandergepreßt. Um dennoch diese beiden Rohrenden jederzeit sicher auf Distanz halten zu können, werden diese Rohrenden mittels kleiner Kettenhübe 10 od. dgl. in axialer Richtung geführt, so daß die Rohrenden mit aller Ruhe und Genauigkeit langsam aufeinander zu bewegt bzw. auch auseinandergezogen werden können.When pumping out the floating box 1 , the external water pressure also tries to push the two pipe ends 2 and 3 deep into the box, d. That is, the two pipe ends are moved towards one another in the axial direction and pressed against one another. In order to be able to keep these two pipe ends at a safe distance at all times, these pipe ends are guided in the axial direction by means of small chain lifts 10 or the like, so that the pipe ends can be slowly moved towards each other or pulled apart with complete ease and accuracy.

Sobald die Rohre verbunden sind, wird der Kasten wieder vollgepumpt, wobei das dazu benötigte Wasser eventuell wieder aus den beiden Pontons 8 geholt wird. Ist der innere Wasserspiegel wieder gleich mit dem äußeren Wasserspiegel, so werden die Dichtungen entfernt, und die gesamte schwimmende Einheit kann nun weiter über das Rohr hinweg bis zur nächsten Rohrverbindung verholt werden, wo sich das Spiel wiederholt.As soon as the pipes are connected, the box is pumped full again, the water required for this possibly being fetched from the two pontoons 8 again. When the inner water level is the same as the outer water level, the seals are removed and the entire floating unit can now be moved further over the pipe to the next pipe connection, where the game is repeated.

Die annähernd liniengerade Flucht der beiden Rohrenden bzw. Rohre wird von verankerten Schuten 11 aus mittels Halteseile 12 sichergestellt, wie das Fig. 4 veranschaulicht.The almost straight line alignment of the two pipe ends or pipes is ensured from anchored barges 11 by means of holding ropes 12, as FIG. 4 illustrates.

Im übrigen ist es ein großer Vorteil dieser Wassermontage, daß die Rohre dabei im Wasser schwimmen bzw. durch den Auftrieb nahezu schwerelos geworden sind. Sie können leicht im Wasser gedreht und bewegt werden. Das Wasser trägt mit unerreichter Gleichmäßigkeit und erlaubt jede gewünschte Lageveränderung, ohne daß dabei große Kräfte erforderlich wären. Das paßgerechte Zusammenführen der Flansche bereitet z. B. im Wasser keine Schwierigkeiten, auch wenn die Rohre noch so lang und die Massen noch so groß sind.In addition, it is a great advantage of this water installation that the Pipes float in the water or become almost weightless due to the buoyancy are. They can be easily rotated and moved in the water. The water carries with it unmatched uniformity and allows any desired change in position without great forces would be required. The fitting merging of the flanges prepares z. B. no difficulties in the water, no matter how long the pipes and no matter how big the masses are.

Natürlich kann der Schwimmkasten 1 auch aus Stahl gebaut werden, eventuell mit Hohlwänden nach den Regeln des Schiffbaues, so daß diese Wände unmittelbar geflutet werden können und der Kasten seine stabile Schwimmlage in sich selbst findet.Of course, the floating box 1 can also be made of steel, possibly with hollow walls according to the rules of shipbuilding, so that these walls can be flooded immediately and the box finds its stable floating position in itself.

Die spätere Versenkung einer derart im Wasser zusammengebauten Rohrleitung bereitet in der Regel keine Schwierigkeiten mehr. Sie erfolgt zumeist unmittelbar aus dieser Schwimmlage heraus unter Verwendung kleiner Schlauchboote od. dgl., die mit Seilwinden ausgestattet sind.The later sinking of a pipeline assembled in this way in the water usually no longer causes problems. It usually takes place immediately Od from this floating position using small inflatable boats. Like. That are equipped with winches.

Claims (2)

PATENTANSPRÜCHE: 1. Verfahren zum Zusammenbau von Rohren im Wasser zu einer Rohrleitung, z. B. zu einem Düker, dadurch gekennzeichnet, daß die zu verbindenden einzelnen Rohre oder Rohrleitungsteile als auf dem Wasser schwimmfähig oder durch Tragkörper schwimmend gehalten werden, der Rohrstoß von einem Schwimmkasten (1) umschlossen wird, dessen für den Durchtritt der Rohre in den Wandungen angeordnete Öffnungen (6) gegen die Rohrwandung durch Dichtungen (4) abgedichtet werden, der Schwimmkasten alsdann leergepumpt wird und die Rohrverbindung dann im Trockenen erfolgt. PATENT CLAIMS: 1. Method of assembling pipes in the water to form a pipeline, e.g. B. to a culvert, characterized in that the individual pipes or pipeline parts to be connected are held as floating on the water or floating by supporting bodies, the pipe joint is enclosed by a floating box (1) whose arranged for the passage of the pipes in the walls Openings (6) are sealed against the pipe wall by seals (4), the floating tank is then pumped empty and the pipe connection is then carried out in the dry. 2. Verfahren nach Anspruch 1, dadurch gekennzeichnet, daß nach erfolgter Rohrverbindung der Schwimmkasten (1) geflutet wird, nach dem Fluten die Dichtungen gelöst werden und der Schwimmkasten in axialer Richtung der Rohre verholt wird. 3. Verfahren nach Anspruch 1, dadurch gekennzeichnet, daß das aus dem Schwinunkasten zu pumpende Wasser in zweckmäßig mit Querschotten versehene, mit dem Schwinunkasten verbundene Tragkörper (8) gepumpt wird.2. The method according to claim 1, characterized in that after the pipe connection, the floating box (1) is flooded, after the flooding, the seals are loosened and the floating box is moved in the axial direction of the pipes. 3. The method according to claim 1, characterized in that the water to be pumped from the Schwinunkasten is pumped into supporting body (8) which is expediently provided with transverse bulkheads and connected to the Schwinunkasten.
DEL30478A 1958-05-27 1958-05-27 Procedure for the assembly of pipes in the water to form a pipeline Pending DE1108622B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DEL30478A DE1108622B (en) 1958-05-27 1958-05-27 Procedure for the assembly of pipes in the water to form a pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DEL30478A DE1108622B (en) 1958-05-27 1958-05-27 Procedure for the assembly of pipes in the water to form a pipeline

Publications (1)

Publication Number Publication Date
DE1108622B true DE1108622B (en) 1961-06-08

Family

ID=7265233

Family Applications (1)

Application Number Title Priority Date Filing Date
DEL30478A Pending DE1108622B (en) 1958-05-27 1958-05-27 Procedure for the assembly of pipes in the water to form a pipeline

Country Status (1)

Country Link
DE (1) DE1108622B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019012186A1 (en) 2017-07-14 2019-01-17 Dyke Engineering Oy An arrangement and a method for joining pipes on water

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019012186A1 (en) 2017-07-14 2019-01-17 Dyke Engineering Oy An arrangement and a method for joining pipes on water
EP3461281A4 (en) * 2017-07-14 2020-01-08 Dyke Engineering Oy An arrangement and a method for joining pipes on water

Similar Documents

Publication Publication Date Title
DE2359540A1 (en) UNDERWATER FUNDABLE EQUIPMENT AND PROCEDURE FOR ESTABLISHING IT ON THE SEA FLOOR
DE102008041849A1 (en) Off-shore system, foundation of an off-shore system and method for setting up an off-shore system
DE1271471B (en) Method for inserting an inner pipe into a casing pipe by floating
DE2549859C3 (en) Connection between an overwater platform or the like. and a foundation
DE10101405A1 (en) Offshore wind power unit for supplying energy has a rotor on a tower with a pillar underneath the tower fitted in a steel frame with three legs, leg braces linking the legs and tie-bars between the pillar base and each leg.
DE2316667A1 (en) RETRACTABLE CONSTRUCTION
DE1917819A1 (en) Underwater standpipe for underwater deep drilling
DE2416357A1 (en) METHOD AND DEVICE FOR CONVERTING A FLOATING MONKEY INTO A SEMI-SUBMERSIBLE FLOATING VEHICLE, IN PARTICULAR A FLOATING WORK ISLAND
DE1956328A1 (en) At some distance from the coast, retractable device for the extraction and storage of oil
DE3111408A1 (en) DEVICE FOR TRANSPORTING COMPRESSED GAS, IN PARTICULAR NATURAL GAS, AND METHOD FOR THE PRODUCTION THEREOF
DE2316763A1 (en) PLANT FOR CLEARING DEDUCED MATERIAL
DE2457536A1 (en) Offshore drilling platform - vertically floatable to site with foundation (legs), tanks and platform
DE1108622B (en) Procedure for the assembly of pipes in the water to form a pipeline
DE2024850C3 (en)
DE102008017785A1 (en) Foundation for e.g. wind energy plant, at e.g. seas, has column supported in body such that fitting section is displaceable under influence of forces affecting column relative to body from transportation position in offshore position
DE804183C (en) Underwater tunnel
DE2159378B2 (en)
DE2627658A1 (en) BASIC BODY, IN PARTICULAR FOR PLATFORMS USED IN WORK IN THE SEA
DE2514522A1 (en) Offshore platform which is assembled on shore - with leg pairs hinged to deck and floated to site in horizontal positon
DE2628698C3 (en) Process for underwater laying of lines, e.g. pipelines, in the seabed
DE2731478C2 (en)
DE10206585A1 (en) Tower foundation, e.g. for offshore wind power plants, comprises concrete pipe with diameter of several meters and length directed over water surface for receiving base of wind power plant
DE492669C (en) Process for the production of an underwater tunnel from individual submersible pipe sections
DE2901957A1 (en) Displaceable artificial island for oil and natural gas - is of reinforced concrete with highly buoyant base structure
DE2550621B2 (en) Pillar supporting an above water platform