DE102010006142A1 - Energy portal for controlling and/or regulating energy supply in power distribution network of wind power plant, has control device controlling and/or regulating parameters as variables based on variables, factors and information - Google Patents

Energy portal for controlling and/or regulating energy supply in power distribution network of wind power plant, has control device controlling and/or regulating parameters as variables based on variables, factors and information Download PDF

Info

Publication number
DE102010006142A1
DE102010006142A1 DE102010006142A DE102010006142A DE102010006142A1 DE 102010006142 A1 DE102010006142 A1 DE 102010006142A1 DE 102010006142 A DE102010006142 A DE 102010006142A DE 102010006142 A DE102010006142 A DE 102010006142A DE 102010006142 A1 DE102010006142 A1 DE 102010006142A1
Authority
DE
Germany
Prior art keywords
energy
feed
factors
information
network
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
DE102010006142A
Other languages
German (de)
Inventor
Frank 21465 Pfeil
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ABE KUNZE BETRIEBSFUEHRUNGS GmbH
ABE KUNZE BETR SFUEHRUNGS GmbH
Abe Kunze Betriebsfuehrungs 22885 GmbH
Original Assignee
ABE KUNZE BETRIEBSFUEHRUNGS GmbH
ABE KUNZE BETR SFUEHRUNGS GmbH
Abe Kunze Betriebsfuehrungs 22885 GmbH
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ABE KUNZE BETRIEBSFUEHRUNGS GmbH, ABE KUNZE BETR SFUEHRUNGS GmbH, Abe Kunze Betriebsfuehrungs 22885 GmbH filed Critical ABE KUNZE BETRIEBSFUEHRUNGS GmbH
Priority to DE102010006142A priority Critical patent/DE102010006142A1/en
Publication of DE102010006142A1 publication Critical patent/DE102010006142A1/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/381Dispersed generators
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • H02J13/00006Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by information or instructions transport means between the monitoring, controlling or managing units and monitored, controlled or operated power network element or electrical equipment
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/18Arrangements for adjusting, eliminating or compensating reactive power in networks
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/46Controlling of the sharing of output between the generators, converters, or transformers
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2300/00Systems for supplying or distributing electric power characterised by decentralized, dispersed, or local generation
    • H02J2300/20The dispersed energy generation being of renewable origin
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2300/00Systems for supplying or distributing electric power characterised by decentralized, dispersed, or local generation
    • H02J2300/20The dispersed energy generation being of renewable origin
    • H02J2300/28The renewable source being wind energy
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/76Power conversion electric or electronic aspects
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/30Reactive power compensation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/70Smart grids as climate change mitigation technology in the energy generation sector
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/12Monitoring or controlling equipment for energy generation units, e.g. distributed energy generation [DER] or load-side generation
    • Y04S10/123Monitoring or controlling equipment for energy generation units, e.g. distributed energy generation [DER] or load-side generation the energy generation units being or involving renewable energy sources
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/22Flexible AC transmission systems [FACTS] or power factor or reactive power compensating or correcting units

Abstract

The portal (1) has a receiving device (10) receiving predetermined supply factors of a power distribution network operator, and another receiving device (20) receiving measuring variables of power generators (230-250). A prognosis information receiving device (30) receives prognosis information, and an evaluation device (40) evaluates the variables, factors and information. An operational parameter-control device (50) controls and/or regulates operational parameters of the power generators as control variables on the basis of the evaluated variables, factors and information. The prognosis information is selected from requirement prognosis information, supply history prognosis information, weather prognosis information, power prognosis information and operating prognosis information. An independent claim is also included for a method for observing supply factors of a power distribution network operator during energy supply from a power generator into a power distribution network.

Description

Gebiet der ErfindungField of the invention

Die vorliegende Erfindung betrifft ein Energieportal, und insbesondere ein Energieportal zur Steuerung beziehungsweise Regelung einer Energieeinspeisung aus einem Erzeugernetz in ein Energieverteilungsnetz, wodurch vorgebare Einspeisefaktoren eingehalten werden können zur Einhaltung von Regelvorgaben.The present invention relates to an energy portal, and in particular an energy portal for controlling or regulating an energy supply from a generator network in an energy distribution network, whereby vorgebare feed factors can be met to comply with regulatory requirements.

Hintergrund der ErfindungBackground of the invention

Dezentrale erzeugte elektrische Energie, wie beispielsweise elektrische Energie aus Windkraftanlagen, Biogas- oder Photovoltaikanlagen, wird in die öffentlichen Netze der Verteilnetzbetreiber bzw. Übertragungsnetzbetreiber (ÜNB) eingespeist. In der Regel erfolgt die Einspeisung in die Mittel- oder Hochspannungsebenen der Verteilnetzbetreiber. Die Nennspannung der Mittelspannungsnetze ist in Bereichen von 6 KV bis 30 KV vorgesehen. Die Spannungsebenen der Hochspannungsnetze sind in der Regel 110 KV. In seltenen Fällen erfolgt die Einspeisung in die Höchstspannungsebene auf beispielsweise 220 KV oder 400 KV.Distributed electrical energy generated, such as electrical energy from wind turbines, biogas or photovoltaic systems, is fed into the public networks of the distribution system operators or transmission system operators (TSOs). As a rule, the feed-in takes place in the medium or high-voltage levels of the distribution system operators. The rated voltage of the medium-voltage networks is provided in the range from 6 KV to 30 KV. The voltage levels of the high voltage networks are usually 110 kV. In rare cases, it is fed into the maximum voltage level at, for example, 220 kV or 400 kV.

Der Punkt, an dem eine Gesellschaft elektrische Energie in das Netz eines Verteilnetzbetreibers einspeist wird als Netzverknüpfungspunkt-NVP bezeichnet. Die Voraussetzungen und Regeln der Einspeisung dezentral erzeugter elektrischer Energie in einen Netzverknüpfungspunkt des Verteilnetzbetreibers werden in einem Netzeinspeisevertrag zwischen dem Verteilnetzbetreiber und dem Betreiber des Energieerzeugungsnetzes geregelt. Ferner sind Netzanschlussrichtlinien des Verteilnetzbetreibers einzuhalten. Die Netzanschlussrichtlinien sowie die Netzeinspeiseverträge, sowie das EEG (Erneuerbare Energien Gesetz01.01.2009) regeln also unter anderem das elektrische Verhalten der Anlagen des Betreibers an dem Netzverknüpfungspunkt. Zu den allgemein gültigen elektrischen Größen gehören unter anderem die Höhe der eingespeisten elektrischen Leistung, die vertraglich beispielsweise in ihrer Höhe begrenzt sein kann. Aus Gründen z. B der Netzauslastung der Verteilnetzbetreiber wird darüber hinaus eine variable Einstellung der maximal eingespeisten Energie zu bestimmten Zeitpunkten gefordert. Hier wird von dem Erzeugungsmanagement bzw. Einspeisemanagement (Eisman) gesprochen.The point at which a company feeds electrical energy into the network of a distribution system operator is referred to as a grid connection point NVP. The requirements and rules for the supply of decentrally generated electrical energy to a grid connection point of the distribution system operator are regulated in a grid feed-in contract between the distribution system operator and the operator of the power generation grid. Furthermore, grid connection guidelines of the distribution system operator must be adhered to. The Grid connection guidelines and the grid feed-in contracts, as well as the EEG (Renewable Energies Act01.01.2009) Thus, among other things, they regulate the electrical behavior of the operator's installations at the grid connection point. Among the generally valid electrical variables include, among other things, the amount of electrical power fed in, which may be contractually limited in their amount, for example. For reasons z. In addition, network utilization of the distribution system operators requires a variable setting of the maximum energy input at specific times. This is referred to as generation management or feed-in management (Eisman).

Ferner ist die Einhaltung eines Leistungsfaktors am Netzverknüpfungspunkt geregelt. Der Leistungsfaktor kann in verschiedenen physikalischen Größen vom Verteilnetzbetreiber vorgegeben werden. In der Regel wird ein variabler Leistungsfaktor als cosφ (über- bis untererregter Größe) vereinbart. Speisen mehrere dezentrale elektrische Energieerzeuger, wie beispielsweise Windparks mit einer oder mehreren Windenergieanlagen ihre Energie in einen Netzverknüpfungspunkt, so sind die vertraglich geregelten elektrischen Größen am Netzverknüpfungspunkt einzuhalten. Dabei ist zu beachten, dass alle Komponenten berücksichtigt werden, die Einfluss auf die elektrischen Größen am Netzverknüpfungspunkt haben. Zu den Komponenten gehören neben den Generatoren von beispielsweise Windenergieanlagen auch die Kabelanlagen und erforderlichen Transformatoren. Diese Gesamtheit wird als Netzanschlussanlage bezeichnet.In addition, compliance with a power factor is regulated at the grid connection point. The power factor can be specified in different physical quantities by the distribution system operator. As a rule, a variable power factor is agreed as cosφ (over- or under-excited size). If several decentralized electrical energy producers, such as wind farms with one or more wind turbines, feed their energy into a grid connection point, the contractually regulated electrical quantities at the grid connection point must be adhered to. It should be noted that all components are considered that have an influence on the electrical quantities at the network connection point. In addition to the generators of, for example, wind turbines, the components also include the cable systems and required transformers. This whole is referred to as grid connection system.

Seit dem 1.1.2009 ist das Erneuerbare Energien Gesetz (EEG) novelliert in Kraft getreten. Die Novellierung umfasst zum einen die Verpflichtung, Erzeugungsanlagen unter bestimmten Voraussetzungen mit bestimmten elektrischen Eigenschaften (so genannten Systemdienstleistungen) auszustatten. Bei bestimmten Anschlusssituationen kann der Einbau von kapazitiven oder induktiven Baugruppen am Netzverknüpfungspunkt erforderlich werden. Diese Baugruppen sind wiederum am Netzverknüpfungspunkt in Abstimmung mit den Leistungsgrößen dezentraler Erzeuger zu steuern. Zum anderen bietet das EEG die Möglichkeit der freien Vermarktung erzeugter Wirkarbeit am nationalen Stromhandel. Grundsätzlich erfolgt die Vergütung eingespeister elektrischer Energie an dem Netzverknüpfungspunkt des Verteilnetzbetreibers. Die vergütete elektrische Größe ist die Wirkarbeit in KWh.Since 1.1.2009 this is Renewable Energy Law (EEG) amended came into force. The amendment includes, on the one hand, the obligation to equip generating plants with certain electrical properties (so-called ancillary services) under certain conditions. In certain connection situations, it may be necessary to install capacitive or inductive modules at the grid connection point. In turn, these modules are to be controlled at the network connection point in coordination with the output quantities of decentralized generators. On the other hand, the EEG offers the possibility of free marketing of generated active work in the national electricity trade. Basically, the remuneration of injected electrical energy takes place at the grid connection point of the distribution system operator. The tempered electrical quantity is the active work in KWh.

Um die Energieeinspeisung von einem Energieerzeugungsnetz in ein Netz des Verteilnetzbetreibers zu steuern beziehungsweise zu regeln werden Energieportale verwendet. Derartige Energieportale sind beispielsweise beschrieben in Windkraftjournal, Ausgabe 1/2007, Seiten 58 bis 61, beziehungsweise Ausgabe 4/2008, Seiten 40 bis 41 .In order to control the energy supply from a power generation network into a network of the distribution system operator, energy portals are used. Such energy portals are described for example in Windkraftjournal, issue 1/2007, pages 58 to 61, and issue 4/2008, pages 40 to 41 ,

Darüber hinaus sind beispielsweise Verfahren und ein System zur Vorhersage einer Solarenergieproduktion bekannt aus DE 60 2004 010 281 T2 .In addition, for example, methods and a system for predicting solar energy production are known DE 60 2004 010 281 T2 ,

Zusammenfassung der ErfindungSummary of the invention

Es kann als eine Aufgabe der vorliegenden Erfindung betrachtet werden ein Energieportal bereitzustellen, das in der Lage ist auf der Grundlage verschiedener Information eine Anpassung der Betriebsgrößen eines Energieerzeugungsnetzes vorzunehmen, um vorgebbare Einspeisefaktoren einzuhalten, bei gleichzeitiger Optimierung einer Wirkleistungs- und Blindleistungseinspeisung (Leistungsfaktor) in ein Energieverteilungsnetz.It may be considered as an object of the present invention to provide an energy portal capable of adapting the operation quantities of a power generation network based on various information to comply with predetermined injection factors while optimizing a real power and reactive power injection (power factor) power distribution network.

Die vorliegende Erfindung betrifft dabei eine Vorrichtung in Form eines Energieportals, ein zugehöriges Verfahren, ein Computerprogramm und ein computerlesbares Speichermedium, gemäß den unabhängigen Ansprüchen, wobei weitere Ausführungsformen in den abhängigen Ansprüchen verkörpert sind. Es sollte dabei verstanden werden, dass sich die im Folgenden beschriebenen Ausführungsformen der Erfindung gleichermaßen auf die Vorrichtung, das Verfahren, das Computerprogramm und das computerlesbare Speichermedium beziehen.The present invention relates to a device in the form of an energy portal, an associated method, a computer program and a computer-readable storage medium, according to the independent claims, wherein further embodiments are embodied in the dependent claims. It should be understood that the embodiments of the invention described below relate equally to the apparatus, method, computer program and computer-readable storage medium.

Gemäß einer Ausführungsform der Erfindung wird ein Energieportal zur Steuerung beziehungsweise Regelung einer Energieeinspeisung aus einem Erzeugernetz in ein Energieverteilungsnetz bereitgestellt, wobei das Energieportal umfasst: eine Einspeisefaktoren-Empfangsvorrichtung zum Empfangen von vorgebbaren Einspeisefaktoren eines Energieverteilungsnetzbetreibers, eine Erzeugermessgrößen-Empfangsvorrichtung zum Empfangen von Messgrößen eines Erzeugernetzes, eine Prognoseinformations-Empfangsvorrichtung zum Empfangen von Prognoseinformation, eine Auswertevorrichtung zum Auswerten der Messgrößen, Einspeisefaktoren und Prognoseinformation, und eine Betriebsparameterregelvorrichtung zum Steuern beziehungsweise Regeln von Betriebsparametern des Erzeugernetzes auf der Grundlage der ausgewerteten Messgrößen, Einspeisefaktoren und Prognoseinformation mit den Einspeisefaktoren als Regelgröße.According to one embodiment of the invention, an energy portal is provided for controlling a power feed from a generator network to a power distribution network, the power portal comprising: a feed factor receiving device for receiving predetermined feed factors of a power distribution system operator, a generator size receiving device for receiving measurements of a generator network, a forecast information receiving device for receiving forecast information, an evaluation device for evaluating the measured variables, feed factors and forecast information, and an operating parameter control device for controlling operating parameters of the generator network on the basis of the evaluated measured variables, feed factors and forecast information with the feed factors as controlled variable.

Auf diese Weise kann erreicht werden, dass die von einem z. B. Energieverteilnetzbetreiber vorgegebenen Einspeisefaktoren eingehalten werden können, beziehungsweise diese Einspeisefaktoren möglichst genau getroffen werden, um auf diese Weise eine effiziente Einspeisung zu ermöglichen. Dies ermöglicht im Rahmen der vorgebbarenbeziehungsweise vorgegebenen Einspeisefaktoren im Rahmen der zulässigen maximalen Einspeisung einen möglichst hohen Energieanteil in das Energieverteilungsnetz einzuspeisen, was zur Netzstabilität des Energieverteilungsnetzes beiträgt.In this way it can be achieved that the z. B. energy distribution network operator predetermined feed factors can be met, or these feed factors are met as accurately as possible, to allow in this way an efficient feed. In the context of the predeterminable feed-in factors given in the context of the permissible maximum feed, this allows the highest possible proportion of energy to be fed into the energy distribution network, which contributes to the grid stability of the energy distribution network.

Gemäß einer Ausführungsform der Erfindung wird ein Energieportal bereitgestellt, bei dem die Erzeugernetzmessgrößen-Empfangsvorrichtung zum Empfangen von Messgrößen bezüglich Blindleistung des Erzeugernetzes ausgelegt ist, wobei die Betriebsparameterregelvorrichtung zum dynamischen Steuern beziehungsweise Regeln von Blindleistungskompensation ausgelegt ist.According to an embodiment of the invention, there is provided an energy portal in which the generator grid measure receiving means is arranged to receive reactive power measurements of the generator grid, the operating parameter controller being adapted to dynamically control reactive power compensation.

Auf diese Weise kann eine sich verändernde Blindleistungskomponente dynamisch so ausgeglichen werden, dass die eingespeiste Energie einen möglichst hohen Wirkanteil aufweist, der maßgeblich ist für die Effizienz der Energieeinspeisung.In this way, a changing reactive power component can be dynamically balanced so that the energy fed in has the highest possible active component, which is decisive for the efficiency of the energy feed.

Gemäß einer Ausführungsform der Erfindung wird ein Energieportal bereitgestellt, bei dem die Erzeugernetzmessgrößen-Empfangsvorrichtung ausgelegt ist zum Empfangen von Erzeugernetzmessgrößen mehrerer Sub-Erzeugernetze.According to one embodiment of the invention, there is provided an energy portal in which the generator grid measurer is adapted to receive generator grid metrics of a plurality of subgenerator networks.

Auf diese Weise kann das Energieportal auch mehrere Erzeugernetze, die hier als Sub-Erzeugernetze bezeichnet werden, an einem Netzverknüpfungspunkt managen. Dies ist insbesondere dann relevant, wenn die mehreren Sub-Erzeugernetze geographisch unterschiedlich liegen, und beispielsweise bei Windparks einer unterschiedlichen Windsituation ausgesetzt sind.In this way, the energy portal can also manage multiple producer networks, referred to herein as subgenerator networks, at a network connection point. This is particularly relevant if the multiple sub-generation networks are geographically different, and are exposed to a different wind situation, for example, in wind farms.

Gemäß einer Ausführungsform der Erfindung wird ein Energieportal bereitgestellt, bei dem die Betriebsparameter-Regelvorrichtung ausgelegt ist zum Steuern beziehungsweise Regeln von Betriebsparametern des Erzeugernetzes auf der Grundlage von jeweils notwendiger Blindleistungskompensation unterschiedlicher Sub-Erzeugernetze in Abhängigkeit der jeweils von den Sub-Erzeugernetzen bereitgestellten Energie.According to one embodiment of the invention, there is provided an energy portal in which the operating parameter control device is adapted to control operating parameters of the generating network based on respectively required reactive power compensation of different sub-generating networks depending on the respective energy provided by the sub-generating networks.

Auf diese Weise kann insbesondere eine Anpassung der notwendigen Blindleistungskompensation bei geographisch unterschiedlich gelegenen Sub-Erzeugungsnetzen erreicht werden, die auf Grund beispielsweise unterschiedlich langer Zuleitungen zu dem Netzverknüpfungspunkt unterschiedliche Reaktanzen aufweisen. Liegen bei diesen unterschiedlichen Reaktanzen auch noch geographisch bedingt unterschiedliche Windsituationen vor, so variiert die notwendige Blindleistungskompensation in der Abhängigkeit nicht nur vom Sub-Erzeugernetz, sondern auch von der dort vorherrschenden Windsituation, so dass eine entsprechend dynamische Anpassung der Blindleistungskompensation in Abhängigkeit der jeweils von den Sub-Erzeugernetzen bereitgestellten Energie vorgenommen werden kann.In this way, in particular an adaptation of the necessary reactive power compensation can be achieved with geographically different sub-generation networks, which have different reactances due to, for example, different lengths of leads to the network connection point. If, at these different reactances, different wind situations also exist geographically, the necessary reactive power compensation in the dependence varies not only from the subgenerator network but also from the prevailing wind situation there, so that a correspondingly dynamic adaptation of the reactive power compensation depending on the respective Sub-generation networks provided energy can be made.

Gemäß einer Ausführungsform der Erfindung wird ein Energieportal bereitgestellt, bei dem die Einspeisefaktoren-Empfangsvorrichtung zum wiederholten beziehungsweise zyklischen oder dynamischen Empfangen von vorgebbaren Einspeisefaktoren eines Betreibers des Energieverteilungsnetzes ausgelegt ist.According to one embodiment of the invention, an energy portal is provided in which the feed-factor receiving device is designed for the repeated or cyclic or dynamic reception of predefinable feed-in factors of an operator of the energy distribution network.

Auf diese Weise kann das Erzeugernetz beziehungsweise die mehreren Sub-Erzeugernetze dynamisch an die veränderte Einspeisefaktoren des Betreibers des Energieverteilungsnetzes angepasst werden, ohne dass die Gefahr besteht, bei wechselnden Einspeisefaktoren mit den Betriebsparametern den erlaubten Einspeisefaktorenbereich zu verlassen und damit einer Abschaltung des Erzeugernetzes beziehungsweise der mehreren Sub-Erzeugernetze zu entgehen.In this way, the generator network or the plurality of sub-generator networks can be dynamically adapted to the changed feed factors of the operator of the power distribution network, without the risk to leave the permitted feed factor range with changing feed factors with the operating parameters and thus a shutdown of the generator network or more Escape sub-producer networks.

Gemäß einer beispielhaften Ausführungsform der Erfindung wird ein Energieportal bereitgestellt, bei dem die Erzeugernetzmessgrößen-Empfangsvorrichtung ausgelegt ist zum Empfangen von herstellerspezifischen Messgrößen eines Erzeugernetzes.According to an exemplary embodiment of the invention, an energy portal in which the generator set measurement quantity receiving device is designed to receive manufacturer-specific measured variables of a generator network.

Da sich in einem Erzeugernetz Komponenten bzw. Baugruppen unterschiedlicher Hersteller befinden können, beziehungsweise bei unterschiedlichen Sub-Erzeugernetzen diese von unterschiedlichen Herstellern dominiert sein können, kann mit einer derartigen Erzeugernetzmessgrößen-Empfangsvorrichtung dynamisch auf die herstellerspezifischen Messgrößen eingegangen werden können, die beispielsweise unterschiedliche Datenformate sowie unterschiedliche Bezugsgrößen aufweisen können. Insbesondere können die Messgrößen beispielsweise auch in unterschiedlichen Messintervallen vorliegen beziehungsweise Formate aufweisen, die herstellerspezifisch ausgelegt sind, so dass mit einer derartigen Erzeugernetzmessgrößen-Empfangsvorrichtung auch derartige Unterschiede aufgefangen werden können. Dies kann beispielsweise mit unterschiedlichen herstellerspezifischen Programmelementen realisiert werden, bzw. mit einer Datenbank mit herstellerspezifischen Datensätzen, die als Grundlage für eine weitere Verarbeitung dienen können. Gemäß einer Ausführungsform der Erfindung wird ein Energieportal bereitgestellt, bei dem die Prognoseinformations-Empfangsvorrichtung ausgelegt ist zum Empfangen von Information aus einer Gruppe von Prognoseinformation, wobei die Gruppe aus einer Bedarfsprognoseinformation, einer Einspeisehistorieprognoseinformation, einer Leistungsprognose, einer Arbeitsprognose und einer Wetterprognoseinformation besteht.Since components or modules of different manufacturers can be located in a generator network or, in the case of different sub-generator networks, these can be dominated by different manufacturers, the generator-specific measured variables can be dynamically entered into with such a generator network measurement receiver, for example, different data formats and different Reference variables may have. In particular, the measured variables can also be present, for example, in different measuring intervals or have formats that are designed manufacturer-specifically, so that such differences can also be compensated with such a generator set measuring quantity receiving device. This can be realized, for example, with different manufacturer-specific program elements, or with a database with manufacturer-specific data records, which can serve as a basis for further processing. According to one embodiment of the invention, there is provided an energy portal in which the forecast information receiving apparatus is configured to receive information from a group of forecast information, the group consisting of demand forecasting information, feed-in history forecasting information, power forecasting, work forecasting, and weather forecasting information.

Auf diese Weise kann das Energieportal auf eine bevorstehende Änderung der Energieerzeugung auf der Grundlage einer prognostizierten Änderung reagieren. Insbesondere können entsprechende Vorbereitungen beziehungsweise Anpassungen vorgenommen werden, die beispielsweise auf einen geänderten Bedarf schnell reagieren können. Analog kann aus der Einspeisehistorie eine Prognose hergeleitet werden, auf Grund der eine geänderte beziehungsweise Energiebereitstellung vorgenommen werden kann. Bei wetterabhängigen Energieerzeugungsnetzen, insbesondere bei Windkraftanlagen ist die Einspeiseprognose eine wichtige Information, auf Grund der, der Rahmen einer möglichen Energieerzeugung in der nahen bis mittleren Zukunft abgeschätzt werden kann. Die unterschiedlichen Prognoseinformationen können selbstverständlich auch kombiniert berücksichtigt und verarbeitet werden.In this way, the energy portal can respond to an impending change in power generation based on a predicted change. In particular, appropriate preparations or adjustments can be made, which can react quickly, for example, to a changed need. Similarly, a prognosis can be derived from the feed-in history, on the basis of which a modified or energy provision can be made. In weather-dependent power generation networks, especially in wind power plants, the feed-in forecast is an important piece of information on the basis of which the scope of possible energy production in the near to medium future can be estimated. Of course, the different prognosis information can also be considered and processed in combination.

Gemäß einer Ausführungsform der Erfindung wird ein Energieportal bereitgestellt, bei dem das Erzeugernetz wenigstens einen Teil Winderzeugungskomponenten aufweist, wobei die Erzeugernetzmessgrößen-Empfangsvorrichtung ausgelegt ist zum Empfangen von Windenergieanlagen-Messgrößen.According to one embodiment of the invention, an energy portal is provided in which the generator grid has at least a portion of wind generating components, the generator grid measuring apparatus being configured to receive wind turbine measured quantities.

Auf diese Weise kann insbesondere auf die besonderen bei Windenergieanlagen vorliegenden Messgrößen eingegangen werden um eine entsprechende Regelung beziehungsweise Steuerung der Betriebsparameter vornehmen zu können.In this way, it is possible in particular to discuss the particular measured variables present in wind turbines in order to be able to carry out a corresponding regulation or control of the operating parameters.

Gemäß einer Ausführungsform der Erfindung wird ein Verfahren bereitgestellt zur Einhaltung von Einspeisefaktoren eines Energieverteilungsnetzbetreibers bei einer Energieeinspeisung aus einem Erzeugernetz in einer Energieverteilungsnetz, wobei das Verfahren umfasst: Empfangen von vorgebbaren Einspeisefaktoren eines Energieverteilungsnetzbetreibers, Empfangen von Messgrößen eines Erzeugernetzes, Empfangen von Prognoseinformation, Auswerten der Messgrößen, der Einspeisefaktoren und der Prognoseinformation, und Steuern beziehungsweise Regeln von Betriebsparametern des Erzeugernetzes auf der Grundlage der ausgewerteten Messgrößen, Einspeisefaktoren und Prognoseinformation mit den Einspeisefaktoren als Regelgröße.According to one embodiment of the invention, a method is provided for compliance with feed-in factors of an energy distribution system operator when feeding energy from a generator network in an energy distribution network, the method comprising: receiving predeterminable feed-in factors of an energy distribution system operator, receiving measurements of a generator network, receiving prognosis information, evaluating the measured variables , the feed factors and the forecast information, and controlling or regulating operating parameters of the generator network on the basis of the evaluated measured variables, feed factors and forecast information with the feed factors as the controlled variable.

Auf diese Weise kann ein Verfahren bereitgestellt werden, das die Einhaltung von Einspeisefaktoren eines Energieverteilungsnetzbetreibers einhalten kann, um auf diese Weise eine optimiertere Energieeinspeisung vornehmen zu können, um nicht der Gefahr zu unterliegen, dass das Erzeugernetz beziehungsweise Sub-Erzeugernetze seitens des Energieverteilungsnetzbetreibers vom Netz getrennt werden und auf diese Weise keine Energie mehr in das Versorgungsnetz einspeisen können.In this way, a method can be provided which can comply with the feed-in factors of an energy distribution system operator, in order to be able to carry out a more optimized energy supply in order not to run the risk of disconnecting the producer network or sub-producer networks from the grid by the energy distribution system operator and in this way can no longer feed energy into the supply network.

Gemäß einer Ausführungsform der Erfindung wird ein Computerprogramm bereitgestellt, welches, wenn es durch einen Prozessor ausgeführt wird, ausgelegt ist, um das Verfahren zur Einhaltung von Einspeisefaktoren eines z. B Energieverteilungsnetzbetreibers durchzuführen.According to one embodiment of the invention, a computer program is provided which, when executed by a processor, is adapted to implement the method of maintaining feed factors of e.g. B energy distribution system operator.

Auf diese Weise können die unterschiedlichen angegebenen Schritte des Verfahrens zur Einhaltung von Einspeisefaktoren eines Energieverteilungsnetzbetreibers über Software beziehungsweise Programmbausteine ausgeführt werden, um auf diese Weise eine Implementierbarkeit auf unterschiedlichen Rechnerplattforen durchführen zu können.In this way, the different specified steps of the method for compliance with feed-in factors of an energy distribution network operator can be executed via software or program modules, in order to be able to implement implementability on different computer platform forums in this way.

Gemäß einer Ausführungsform der Erfindung wird ein computerlesbares Medium bereitgestellt, auf dem das erfindungsgemäße Computerprogramm gespeichert ist.According to one embodiment of the invention, a computer-readable medium is provided on which the computer program according to the invention is stored.

Gemäß einer Ausführungsform der Erfindung wird eine Verwendung des Verfahrens bzw. der Vorrichtung zur Einhaltung von Einspeisefaktoren eines Energieverteilungsnetzbetreibers in einem Energieerzeugungsnetz angegeben mit wenigstens einem Teil Windenergieerzeugungskomponenten, wobei die Prognoseinformation eine Wetterprognose umfasst.According to one embodiment of the invention, a use of the method or the device for maintaining feed-in factors of an energy distribution system operator in one A power generation network specified with at least a portion of wind power generation components, the forecast information comprising a weather forecast.

Die einzelnen angegebenen Merkmale können selbstverständlich auch untereinander kombiniert werden, wodurch sich zum Teil auch vorteilhafte Wirkungen einstellen können, die über die Summe der Einzelwirkungen hinausgehen.Of course, the individual characteristics given may also be combined with one another, which may in some cases also result in advantageous effects which exceed the sum of the individual effects.

Diese und andere Aspekte der vorliegenden Erfindung werden durch die Bezugnahme auf die hiernach beschriebenen beispielhaften Ausführungsformen erläutert und verdeutlicht.These and other aspects of the present invention are illustrated and clarified by reference to the exemplary embodiments hereinafter described.

Kurze Beschreibung der ZeichnungenBrief description of the drawings

Beispielhafte Ausführungsformen werden im Folgenden mit Bezugnahme auf die folgenden Zeichnungen beschrieben.Exemplary embodiments will be described below with reference to the following drawings.

1 zeigt eine schematische Übersicht einer Einspeisesituation an einem Netzverknüpfungspunkt. 1 shows a schematic overview of a feed-in situation at a grid connection point.

2 zeigt eine schematische Übersicht eines erfindungsgemäßen Energieportals gemäß einer beispielhaften Ausführungsform. 2 shows a schematic overview of an energy portal according to the invention according to an exemplary embodiment.

3 zeigt eine weitere schematische Übersicht eines Energieportals im Umfeld einer Energieeinspeisesituation mit mehreren Sub-Erzeugungsnetzen. 3 shows a further schematic overview of an energy portal in the environment of a power feed situation with multiple sub-generation networks.

Detaillierte Beschreibung beispielhafter AusführungsformenDetailed description of exemplary embodiments

Anhand von 1 wird beispielhaft die Einspeisesituation in ein Energieversorgungsnetz beschrieben. Dabei erfolgt die Einspeisung der Energie eines Energieerzeugungsnetzes 230, 240, 250 in ein Energieversorgungsnetz 105 über ein Umspannwerk 100. Dieses Umspannwerk wird verwendet, um die erzeugte elektrische Energie in das Netz eines Verteilnetzbetreibers einzuspeisen. Hierzu wird beispielsweise ein Umspannwerk mit einem Netzverknüpfungspunkt auf der 110 KV Ebene errichtet, bei dem ein Transformator 120 vorgesehen ist, der das 110 KV Netz mit dem Netzverknüpfungspunk 110 einerseits und die Einspeisepunkte auf der 20 KV Seite andererseits koppelt. Dabei wird die Energie von verschiedenen Sub-Erzeugungsnetzen 230, 240, 250 eingespeist, die beispielsweise Windparks sein können. Die Einspeisung wird auf der 20 KV Ebene vorgenommen, wobei die Einspeisung über entsprechende Netzverknüpfungspunkte 130, 140, 150 in dem Umspannwerk 100 erfolgt. Diese Netzverknüpfungspunkte 130, 140, 150 sind jeweils den Sub-Energieerzeugungsnetzen 230, 240, 250 zugewiesen. Diese Netzverknüpfungspunkte 130, 140, 150 werden beispielsweise über eine Busschiene 125 an den Transformator 120 gekoppelt. Parallel dazu kann an dieselbe Busschiene 125 kapazitive oder induktive Leistung 160 zu Blindleistungskompensation angekoppelt werden, die bei Bedarf ganz oder variabel zugeschaltet sein kann. Die Sub-Energieerzeugungsnetze 230, 240, 250 können beispielsweise in der Region des Umspannwerkes 100 gelegen sein und die von ihr erzeugte Energie lokal in dem Umspannwerk 100 einspeisen. Der Betreiber des Energieverteilungsnetzes 105 kann dabei Vorgaben machen, die von den Energieeinspeisern eingehalten werden müssen, so dass eine stabile Netzführung im Energieverteilungsnetz 105 gewährleistet werden kann. Wird beispielsweise der Betreiber des Umspannwerkes von dem Netzbetreiber des Energieverteilungsnetzes 105 zu einem beliebigen Zeitpunkt aufgefordert die elektrische Leistung zu reduzieren, so erfolgt diese Anforderung durch beispielsweise ein elektrisches Signal. Dieses Signal kann beispielsweise an den Leitrechner der Windparks weitergegeben werden, die gleichermaßen die Leistung auf den geforderten Wert reduzieren. Dies wird später noch mit Bezugnahme auf 3 detaillierter beschrieben. Es sei verstanden, dass verschiedene schaltanlagentypische Einrichtungen in dem in 1 gezeigten Prinzipbild des Umspannwerkes nicht gezeigt sind, insbesondere sind keine Messwandler zum Messen der Spannung beziehungsweise des Stromes eingezeichnet, noch sind Leistungsschalter oder Trenner eingezeichnet, die selbstverständlich in jedem Umspannwerk vorhanden sind.Based on 1 For example, the feed-in situation in a power grid is described. In this case, the energy is fed into a power generation network 230 . 240 . 250 into a power grid 105 via a substation 100 , This substation is used to feed the generated electrical energy into the network of a distribution system operator. For this purpose, for example, a substation is built with a grid connection point on the 110 kV level, in which a transformer 120 provided that the 110 kV network with the network connection point 110 on the one hand and the entry points on the 20 KV side on the other hand. In doing so, the energy of different sub-generation networks 230 . 240 . 250 fed, which may be wind farms, for example. The feed-in is made on the 20 kV level, whereby the feed-in via corresponding grid connection points 130 . 140 . 150 in the substation 100 he follows. These network connection points 130 . 140 . 150 are each the sub-power generation networks 230 . 240 . 250 assigned. These network connection points 130 . 140 . 150 for example, via a busbar 125 to the transformer 120 coupled. Parallel to this, you can connect to the same busbar 125 capacitive or inductive power 160 be coupled to reactive power compensation, which can be switched on completely or variably as needed. The sub-power generation networks 230 . 240 . 250 For example, in the region of the substation 100 be located and the energy generated by it locally in the substation 100 feed. The operator of the power distribution network 105 can thereby make specifications that must be complied with by the power feeders, so that a stable network management in the power distribution network 105 can be guaranteed. If, for example, the operator of the substation of the network operator of the power distribution network 105 prompted at any time to reduce the electrical power, so this request is made by, for example, an electrical signal. This signal can be passed on, for example, to the main computer of the wind farms, which likewise reduces the power to the required value. This will be explained later with reference to 3 described in more detail. It should be understood that various switchgear typical devices in the in 1 shown circuit diagram of the substation are not shown, in particular, no transducers for measuring the voltage or the current are located, nor circuit breakers or disconnectors are located, which are of course available in each substation.

2 zeigt eine beispielhafte Skizze eines Energieportals 1 gemäß einer beispielhaften Ausführungsform. Dabei weißt das Energieportal 1 eine Empfangsvorrichtung 10 zum Empfangen von vorgebbaren Einspeisefaktoren eines z. B. Energieverteilungsnetzbetreibers auf, über die vom Energieverteilungsnetzbetreiber die Vorgaben beziehungsweise die Einspeiseregeln empfangen werden können, an die sich der Energieerzeuger und der Einsgeiser zu halten hat. Hier sei verstanden, dass als Energieverteilungsnetzbetreiber auch ein privater Betreibe oder jeder andere Betreiber gesehen werden kann. Darüber hinaus ist in dem Energieportal eine Empfangsvorrichtung 20 zum Empfangen von Messgrößen eines Erzeugungsnetzes vorgesehen, wobei diese Empfangsvorrichtung informationstechnisch angebunden ist an die unterschiedlichen Erzeugernetze oder Erzeugern 230, 240, 250. Die Erzeugermessgrößen-Empfangsvorrichtung empfängt dabei von den unterschiedlichen Erzeugernetzteilen oder Erzeugernetzen 230, 240, 250 entsprechende Messgrößen, die Auskunft geben über den Zustand des entsprechenden Sub-Netzes. Ferner weist das Energieportal eine Prognoseinformations-Empfangsvorrichtung 30 auf, über die Prognoseinformation empfangen werden kann. Diese Prognoseinformation kann beispielsweise eine Bedarfsprognose, eine Historieinformation oder Wetterprognose empfangen. Dabei kann die Prognoseinformations-Empfangsvorrichtung 30 beispielsweise an einen Wetterdienst angeschlossen sein, der bezüglich der Sub-Netze 230, 240, 250 entsprechend geographisch diversifiziert relevante Wetterinformationen bereitstellt, aus denen dann eine entsprechende Prognose abgeleitet werden kann. Ferner kann die Prognoseinformations-Empfangsvorrichtung 30 auf eine Datenbank zurückgreifen, die beispielsweise eine Einspeisehistorie beinhaltet oder auf der Grundlage historischer Daten eine Bedarfsprognose abgibt und ggf. weiter beeinflussende Faktoren zur berücksichtigt. Dabei ist nicht ausgeschlossen, dass zwischen der Informationsbasis, beispielsweise dem Online-Wetterdienst bzw. der Datenbasis eine zusätzliche Aufbereitungseinheit vorgesehen ist, die die entsprechende Information derartig aufbereitet, dass eine Prognoseinformation bereitgestellt werden kann. Eine derartige Reckenleistung kann dabei sowohl innerhalb als auch außerhalb der Prognoseinformations-Empfangsvorrichtung 30 bereitgestellt werden. 2 shows an exemplary sketch of an energy portal 1 according to an exemplary embodiment. The energy portal knows that 1 a receiving device 10 for receiving predeterminable feed-in factors of a z. B. Power distribution network operator, over which the power distribution network operator, the specifications or the feed-in rules can be received, to which the power generator and the Eingeiser has to comply. Here it should be understood that as a power distribution network operator, a private operator or any other operator can be seen. In addition, in the energy portal is a receiving device 20 provided for receiving measured variables of a generating network, this receiving device being connected by information technology to the different generator networks or generators 230 . 240 . 250 , The generator size receiving device receives from the different generator power supplies or generator networks 230 . 240 . 250 corresponding measured variables that provide information about the state of the corresponding subnetwork. Furthermore, the energy portal has a forecast information receiving device 30 on, over which prognosis information can be received. These Forecast information may, for example, receive a demand forecast, history information or weather forecast. In this case, the forecast information receiving device 30 For example, be connected to a weather service, with respect to the sub-networks 230 . 240 . 250 according geographic diversified relevant weather information provides, from which then a corresponding forecast can be derived. Further, the prediction information receiving device 30 to use a database that, for example, contains a feed-in history or makes a demand forecast based on historical data and, if necessary, takes into account factors that influence further. It is not excluded that between the information base, for example, the online weather service or the database, an additional processing unit is provided, which prepares the corresponding information such that a prognosis information can be provided. Such stretching performance can occur both inside and outside the forecast information receiving device 30 to be provided.

Das Energieportal weist ferner eine Auswertevorrichtung 40 auf, die Daten empfängt von der Einspeisefaktoren-Empfangsvorrichtung 10, der Erzeugernetzgrößen-Empfangsvorrichtung 20 und der Prognoseinformations-Empfangsvorrichtung 30. Die Auswertevorrichtung 40 wertet dabei die Messgrößen, Einspeisefaktoren und die Prognoseinformation aus, um auf dieser Grundlage einer Betriebsparameter-Regelvorrichtung eine entsprechende Regelinformation bereitstellen zu können, um mittels der in dem Energieportal 1 bereitgestellten Betriebsparameter-Regelvorrichtung 50 eine Steuerung beziehungsweise Regelung von Betriebsparametern der Erzeugernetze auf der Grundlage der ausgewerteten Messgrößen, Einspeisefaktoren und Prognoseinformation vornehmen zu können, wobei die Einspeisefaktoren als Regelgröße verwendet werden. Dabei gibt die Betriebsparameter-Regelvorrichtung entsprechende Regelsignale an die Energieerzeugungsnetze beziehungsweise Sub-Energieerzeugernetze 230, 240, 250 weiter, auf deren Grundlage die Einspeisung über ein Umspannwerk 100 in das Energieverteilungsnetz 105 vorgenommen werden kann.The energy portal also has an evaluation device 40 which receives data from the feed factor receiving device 10 , the producer grid size receiver 20 and the forecast information receiving device 30 , The evaluation device 40 evaluates the measured variables, feed factors and the prognosis information in order to be able to provide corresponding control information on the basis of an operating parameter control device in order to use the energy portal in the energy portal 1 provided operating parameter control device 50 to be able to make a control or regulation of operating parameters of the generator networks on the basis of the evaluated measured variables, feed factors and forecast information, wherein the feed factors are used as a controlled variable. In this case, the operating parameter control device outputs corresponding control signals to the power generation networks or sub-energy generator networks 230 . 240 . 250 on the basis of which the supply via a substation 100 into the power distribution network 105 can be made.

Hierbei sei verstanden, dass die in 2 gezeigten Pfeile mit einer einfachen Linie einen Informationsfluss darstellen, während die Doppellinien einen Energiefluss darstellen.It should be understood that the in 2 arrows with a simple line represent an information flow, while the double lines represent an energy flow.

Analog der Komponenten 10, 20, 30, 40 und 50 läuft ein korrespondierendes Verfahren ab, demgemäß Einspeisefaktoren eines z. B. Energieverteilungsnetzbetreibers empfangen werden, Messgrößen eines Erzeugernetzes empfangen werden sowie Prognoseinformation empfangen wird, wobei dann eine Auswertung der Messgrößen, der Einspeisefaktoren und der Prognoseinformation erfolgt, so dass daran anschließend eine Steuerung beziehungsweise Regelung von Betriebsparametern des Erzeugernetzes auf der Grundlage der ausgewerteten Messgrößen, Einspeisefaktoren und Prognoseinformation erfolgen kann, wobei die Einspeisefaktoren als Regelgröße dienen.Analogous to the components 10 . 20 . 30 . 40 and 50 runs a corresponding method from, accordingly Einspeisefaktoren a z. B. Power distribution network operator, measured variables of a generator network are received and forecast information is received, then an evaluation of the variables, the feed factors and the forecast information is carried out, so that subsequently a control or regulation of operating parameters of the generator network on the basis of the evaluated parameters, feed factors and prognosis information can be made, with the feed factors serve as a controlled variable.

Mit Bezugnahme auf 3 werden nun anhand einer beispielhaften Ausführungsform der Erfindung detaillierter die Vorgänge bei der Einspeisung beschrieben.With reference to 3 Now, with reference to an exemplary embodiment of the invention, the feed-in operations will be described in more detail.

3 zeigt dabei schematisch die Signal- und Energieflüsse, wobei die Signalflüsse durch strichlierte Linien dargestellt sind, während die Energieflüsse durch Doppellinien dargestellt sind. 3 shows schematically the signal and energy flows, the signal flows are shown by dashed lines, while the energy flows are represented by double lines.

Die in 3 gezeigte Umspannwerkkonfiguration, insbesondere mit der Anordnung und Positionierung der Schalter und Trennelemente ist lediglich beispielhaft und kann selbstverständlich auch anders ausgestaltet sein, insbesondere ist dies nicht relevant für den Energiemanagementaspekt der Erfindung, sondern dient zum besseren Verständnis.In the 3 shown substation configuration, in particular with the arrangement and positioning of the switches and separating elements is merely exemplary and may of course be designed differently, in particular, this is not relevant to the energy management aspect of the invention, but is used for better understanding.

In 3 ist ein Umspannwerk 100 dargestellt, in dem sich der Netzverknüpfungspunkt 110 für das Energieverteilungsnetz 105 befindet. Der Netzverknüpfungspunkt 110 ist vom Energieverteilungsnetz 105 getrennt durch einen Schalter 113, der als eine Reihenschaltung eines Leistungsschalters und entsprechender Trennschalter vorgesehen sein kann. Der Netzverknüpfungspunkt 110 weist dabei einen Spannungswandler 111 und einen Stromwandler 112 auf, wobei diese beiden Wandler 111, 112 entsprechende Messgrößen bereitstellen, die dem Energieportal zusätzlich zu den Messgrößen der Erzeugernetze bereitgestellt werden können. Insbesondere kann an dieser Stelle überprüft werden, ob die Einspeisefaktoren eingehalten werden. Auf der z. B. Unterspannungsseite ist eine Bussschiene 125 vorgesehen, die über eine Schalteranordnung 123 mit dem Transformator 120 verbunden ist. Die Schalteranordnung 123 kann wiederum aus einer Reihenschaltung von Leistungsschalter und Trennschaltern bestehen. An die Bussschiene 125 können unterschiedliche Energieversorgungsnetze 230, 240 angekoppelt werden über entsprechende Netzverknüpfungspunkte 130, 140 auf der Unterspannungsseite. Diese Netzverknüpfungspunkte 130, 140 können wiederum über entsprechende Schalteranordnungen 133, 143 analog der Schalteranordnungen 123 an die Bussschiene 125 angekoppelt sein. An den entsprechenden Netzverknüpfungspunkten 130, 140 können wiederum Stromwandler 132, 142 sowie Spannungswandler 131, 141 vorgesehen sein, um entsprechende Information an das Energieportal 1 bereitzustellen, die als Grundlage für die Regelung beziehungsweise Steuerung der Energieverteilungsnetze beziehungsweise deren Betriebsparameter herangezogen werden kann. Die unterschiedlichen Energieerzeugungsnetze 230, 240 sind über Leitungen 235, 245 an das Umspannwerk 100 angekoppelt. Diese Leitungen können zum Teil sehr unterschiedliche Längen und damit sehr unterschiedliche Impedanzen aufweisen. Beispielsweise kann die Leitung 235 eine Länge von etwa 10 km aufweisen, während die Leitung 245 nur eine Länge von etwa 3 km aufweisen kann, wodurch sich für die Zuleitungen unterschiedliche Impedanzen ergeben, die aufgrund unterschiedlicher Leistungen der Sub-Netze unterschiedliche Blindleistungswerte hervorrufen. Die unterschiedlichen Energieerzeugungsnetze 230, 240 können dabei selbst wiederum unterschiedliche Winderzeugungsanlagen 231, 232 beziehungsweise 241, 242 aufweisen, die über entsprechende Leitungen 233, 243 miteinander gekoppelt sind, um auf diese Weise die erzeugte Energie über die entsprechenden Zuleitungen 235, 245 an das Umspannwerk zu liefern. Dabei kann in den entsprechenden Energieerzeugungsnetzen 230, 240 eine so genannte Masteranlage 231, 241 vorgesehen sein, die letztendlich stellvertretend als Signalempfangsvorrichtung beziehungsweise als Messpunkt herangezogen werden kann. Diese Masteranlage 231, 241 kann dabei über eine entsprechende Übergabebox 234, 244 informationsmäßig mit dem Energieportal verknüpft sein, so dass Energieportal über diese Übergabebox mit den entsprechenden Mastern 231, 241 kommunizieren kann. Über diese Übergabebox kann beispielsweise auch eine entsprechende Messwertinformation an das Energieportal weitergegeben werden. Das Energieportal 1 wiederum empfängt von einem Betreiber 106 des Energieverteilungsnetzes 105 entsprechende Information bezüglich Einspeisefaktoren, die beispielsweise in einem zentralen Rechner 70 verarbeitet werden können. Innerhalb dieses Rechners 70 können dabei die in 2 gezeigten Komponenten 10, 20, 30, 40 und 50 realisiert sein, etwa durch unterschiedliche Bausteine oder auch durch eine diese Komponenten 10, 20, 30, 40 und 50 abdeckende Software realisiert sein. Dazu kann eine entsprechende Hilfs- bzw. Dokumentationsvorrichtung 60 vorgesehen sein, die entsprechend Messwerte von unterschiedlichen Netzverknüpfungspunkten sowohl auf der Oberspannungsseite als auch der Unterspannungsseite protokolliert und diese Information gesammelt an die zentrale Recheneinheit 70 weitergeben kann.In 3 is a substation 100 represented in which the network connection point 110 for the power distribution network 105 located. The network connection point 110 is from the power distribution network 105 separated by a switch 113 , which may be provided as a series circuit of a circuit breaker and corresponding circuit breaker. The network connection point 110 has a voltage transformer 111 and a current transformer 112 on, these two converters 111 . 112 provide appropriate metrics that can be provided to the energy portal in addition to the measures of the producer networks. In particular, it can be checked at this point whether the feed-in factors are complied with. On the z. B. Undervoltage side is a busbar 125 provided by a switch arrangement 123 with the transformer 120 connected is. The switch arrangement 123 may in turn consist of a series connection of circuit breakers and disconnectors. To the busbar 125 can have different power grids 230 . 240 are connected via corresponding network connection points 130 . 140 on the low voltage side. These network connection points 130 . 140 in turn, via appropriate switch arrangements 133 . 143 analogous to the switch arrangements 123 to the busbar 125 be coupled. At the corresponding network connection points 130 . 140 can turn current transformers 132 . 142 as well as voltage transformers 131 . 141 be provided to provide appropriate information to the energy portal 1 provide as a basis for the regulation or control of Energy distribution networks or their operating parameters can be used. The different power generation networks 230 . 240 are over lines 235 . 245 to the substation 100 coupled. These lines can sometimes have very different lengths and thus very different impedances. For example, the line 235 have a length of about 10 km while the line 245 can only have a length of about 3 km, resulting in different impedance for the leads that cause different reactive power values due to different performance of sub-networks. The different power generation networks 230 . 240 can themselves turn different wind generators 231 . 232 respectively 241 . 242 have, via appropriate lines 233 . 243 coupled to each other in this way the energy generated via the corresponding supply lines 235 . 245 to deliver to the substation. In this case, in the corresponding power generation networks 230 . 240 a so-called master plant 231 . 241 be provided, which can ultimately be used representative as a signal receiving device or as a measuring point. This master system 231 . 241 can do this via an appropriate transfer box 234 . 244 be informally linked to the energy portal, so that energy portal via this transfer box with the appropriate masters 231 . 241 can communicate. By way of example, a corresponding measured value information can also be forwarded to the energy portal via this transfer box. The energy portal 1 in turn, receives from an operator 106 of the power distribution network 105 corresponding information regarding feed factors, for example, in a central computer 70 can be processed. Within this calculator 70 can do the in 2 shown components 10 . 20 . 30 . 40 and 50 be realized, for example, by different components or by one of these components 10 . 20 . 30 . 40 and 50 be realized covering software. For this purpose, a corresponding auxiliary or documentation device 60 be provided, which logs according to measured values of different network connection points on both the high voltage side and the low voltage side and collected this information to the central processing unit 70 can pass on.

Wird beispielsweise das Umspannwerk 100 von dem Netzbetreiber 106 des Energieversorgungsnetzes 105 zu einem beliebigen Zeitpunkt aufgefordert die elektrische Leistung zu reduzieren, erfolgt diese Aufforderung durch ein elektrisches Signal zwischen dem Betreiber 106 und dem Energieportal 1. Dieses Signal kann beispielsweise an den Leitrechner der Windparks weitergegeben werden, wobei diese Leitrechner in der Übergabebox 234, 244 realisiert sein können. Auf diese Weise können die entsprechenden Energieerzeugungsnetze 230, 240 geleitet durch beispielsweise den Master 231, 241 die Energie beziehungsweise die Leistung auf den geforderten Wert reduzieren oder erhöhen.For example, the substation 100 from the network operator 106 of the power supply network 105 prompted at any time to reduce the electrical power, this request is made by an electrical signal between the operator 106 and the energy portal 1 , This signal can be passed, for example, to the host computer of the wind farms, these host computers in the transfer box 234 . 244 can be realized. In this way, the appropriate power generation networks 230 . 240 directed by, for example, the master 231 . 241 reduce or increase the energy or the output to the required value.

Wenn jedoch einer der Windparks beziehungsweise der Sub-Energieerzeugungsnetze 230, 240 nicht auf dieses Steuerungssignal reagiert, so erfolgt auch keine Leistungsreduzierung, so dass der Betreiber 106 beispielsweise die gesamte Energieeinspeisung über das Umspannwerk 100 vom Netz trennen kann, so dass nicht nur der nicht reagierende Windpark, beispielsweise der Windpark 230 vom Netz genommen wird, sondern ebenfalls die ordnungsgemäß arbeitenden Windparks 240. Das gleiche Prinzip gilt beispielsweise auch für die Einhaltung eines Leistungsfaktors an dem entsprechenden Netzverknüpfungspunkt 110.However, if one of the wind farms or sub-energy generation networks 230 . 240 does not respond to this control signal, so there is no power reduction, so that the operator 106 for example, the entire energy supply via the substation 100 disconnect from the grid, so not only the unresponsive wind farm, such as the wind farm 230 taken from the grid, but also the properly operating wind farms 240 , The same principle applies, for example, to the maintenance of a power factor at the corresponding network connection point 110 ,

Zum Erreichen eines vorgegebenen Leistungsfaktors an einem Netzverknüpfungspunkt 110 ist es erforderlich, den Leistungsfaktor und die ihn beeinflussenden elektrischen Größen zu berücksichtigen. Diese elektrischen Größen können beispielsweise die Recktanzen der Kabelanlagen 235, 245 und der Transformatoren zwischen den Generatoren und den Netzverknüpfungspunkten 130, 140 sein. Dies gilt insbesondere bei unterschiedlichen beziehungsweise unterschiedlich langen Kabelanbindungen zweier Windparks. Bei bestimmten Anschlusssituationen können dabei zusätzliche induktive oder kapazitive Baugruppen 160 notwendig sein, die an den Netzverknüpfungspunkt angekoppelt werden, um die Regelanforderung am Netzverknüpfungspunkt sicherzustellen. Zu diesem Zweck kann beispielsweise an die Bussschiene 125 eine entsprechende Blindleistungskompensationseinrichtung 160 angekoppelt werden, beispielsweise über eine Schalteranordnung 163.To achieve a given power factor at a network connection point 110 It is necessary to take into account the power factor and the electrical variables affecting it. These electrical variables can be, for example, the reactances of the cable systems 235 . 245 and the transformers between the generators and the mesh nodes 130 . 140 be. This applies in particular to different or different length cable connections of two wind farms. In certain connection situations, additional inductive or capacitive components can be used 160 be necessary, which are coupled to the network connection point to ensure the rule request at the network connection point. For this purpose, for example, to the busbar 125 a corresponding reactive power compensation device 160 be coupled, for example via a switch assembly 163 ,

Vor dem Hintergrund dieser Betrachtungen ist es daher erforderlich die elektrischen Verhaltensweisen der einspeisenden Windparks im Umspannwerk zu messen. Die einspeisenden Windparks haben ihre Netzverknüpfungspunkte 130, 140 am Eingang der 20 KV Einspeisung im Umspannwerk. Der durch den Netzbetreiber vorgegebene maximale Blindleistungsbetrag ist an dem beispielsweise 110 KV Netzverknüpfungspunkt 110 einzuhalten und wird durch die Reaktanzen der Windparks sowie des Umspannwerkes beeinflusst. Es ist also im Hinblick auf den 110 KV Netzverknüpfungspunkt 110 die gesamte Netzanschlussanlage zu betrachten und entsprechend übergeordnet zu regeln. Dabei kann die unterschiedliche Reaktanz der entsprechenden Zuleitungen 235, 245 überlagert werden durch die unterschiedliche Windsituation an den entsprechenden Windparks 230, 240, so dass die notwendige Blindleistungskompensation über eine entsprechende Anlage 160 abhängig ist von sowohl der Leitungskonfiguration 235, 245 als auch der entsprechenden Windsituation in den Windparks 230, 240. Der Zentralrechner 70 im Energieportal 1 kann dabei eine entsprechende Ansteuerung der Blindleistungskompensationsanalge 60 vornehmen, um eine dynamische Blindleistungsanpassung vornehmen zu können.Against the background of these considerations, it is therefore necessary to measure the electrical behavior of the feeding wind farms in the substation. The feeding wind farms have their grid connection points 130 . 140 at the entrance of the 20 KV supply in the substation. The maximum reactive power amount given by the network operator is at, for example, the 110 KV grid connection point 110 and is influenced by the reactances of the wind farms and the substation. So it is with regard to the 110 KV grid connection point 110 to look at the entire grid connection system and to regulate it accordingly. In this case, the different reactance of the corresponding supply lines 235 . 245 are superimposed by the different wind situation at the corresponding wind farms 230 . 240 so that the necessary reactive power compensation via a corresponding investment 160 depends on both the line configuration 235 . 245 as well as the corresponding wind situation in the wind farms 230 . 240 , The central computer 70 in the energy portal 1 can be a corresponding control of the reactive power compensation 60 to make a dynamic reactive power adjustment.

Zur direkten Vermarktung von elektrischer Energie ist es erforderlich zu bestimmten Tageszeiten die Strommenge zu prognostizieren. Hierzu ist es erforderlich Informationen an dem Netzverknüpfungspunkt entgegen zu nehmen, zu verarbeiten, zu versenden und gegebenenfalls Regeleingriffe vorzunehmen. Zu diesem Zwecke kann beispielsweise über eine oder mehrere externe Datenbank 31 entsprechende Prognoseinformation bereitgestellt werden, die in den Zentralrechner 70 eingespeist werden kann. Auf der Grundlage dieser Prognoseinformation, beispielsweise eine Wetterprognose, eine Bedarfsprognose oder auch eine Einspeisehistoriebasierte Prognoseinformation kann eine entsprechende Regelung der Erzeugungsnetze 230, 240 vorgenommen werden. Diese Prognosedaten können in entsprechenden Rechner- bzw. Programmbaugruppen, die in den Zentralrechner 70 vorgesehen sein können entsprechend verwaltet werden. Gegebenenfalls können die entsprechenden Prognosedaten aufbereitet und höher integriert ausgewertet werden, so dass sich daraus eine entsprechende Notwendigkeit für einen Steuer- beziehungsweise Regeleingriff ergibt.For the direct marketing of electrical energy, it is necessary to forecast the amount of electricity at certain times of the day. For this purpose, it is necessary to receive information at the network connection point, to process, to send and, if necessary, to carry out control interventions. For this purpose, for example, via one or more external database 31 corresponding forecast information is provided in the central computer 70 can be fed. On the basis of this prognosis information, for example a weather forecast, a demand forecast or also feed-in report-based forecast information, a corresponding regulation of the generation networks can be made 230 . 240 be made. These forecast data can be stored in appropriate computer or program modules that are in the central computer 70 be provided can be managed accordingly. If appropriate, the corresponding prognosis data can be processed and evaluated in a more integrated manner, so that a corresponding need for a control or regulating intervention results from this.

In dem Dokumentationsmodul 60 kann dabei die Aufnahme der elektrischen Größen der Netzverteilungspunkte 110, 130, 140 erfolgen. Ferner kann dort die elektrische Leistung ermittelt und dokumentiert werden, sowie die elektrische Arbeit bezüglich der Netzverknüpfungspunkte bei entsprechenden Regelverstößen. In dem Steuerungsrechner beziehungsweise Regler 70 kann dabei die Befehlserfassung vom Verteilnetzbetreiber erfolgen sowie eine entsprechende Rückmeldung an den Verteilnetzbetreiber, eine Befehlsausgabe an die Masterrechnung der Einspeise- beziehungsweise der Übergabeboxen, oder anderer Signalübertrager eine Werteannahme der verfügbaren Leistungen der Einsgeiser beziehungsweise ein Abgleich der geforderten und der gelieferten Werte der Leistungen. Ferner kann der Leistungsfaktor zwischen Ist und Soll an den Netzverknüpfungspunkten abgeglichen werden und eine entsprechende Regelung des Leistungsfaktors durch die Anforderung von Blindleistung erfolgen. Weiterhin kann in dem Steuerungsrechner und dem Regler eine Anforderung weiterer Leistungsreduzierung bei Regelverstößen beziehungsweise ein Abgleich der verfügbaren Energiemenge beziehungsweise Leistungsmenge erfolgen. In einem in dem Steuerungsrechner beziehungsweise Regler implementierten Prognosetool kann eine Erfassung von Wetterprognosen, eine Erfassung von Verfügbarkeiten der Einsgeiser, eine Erfassung von gelieferten Energiemengen, eine Berechnung von Lieferprognosen beziehungsweise eine Ausgabe von Lieferprognosen in genormten Datenformaten erfolgen. Das Prognosetool kann auch als ein separates Prognosetool innerhalb des Energieportals ausgeführt sein.In the documentation module 60 can thereby record the electrical parameters of the network distribution points 110 . 130 . 140 respectively. Furthermore, the electrical power can be determined and documented there, as well as the electrical work with regard to the network connection points in the case of corresponding rule violations. In the control computer or controller 70 In this case, the command acquisition can be carried out by the distribution system operator and a corresponding feedback to the distribution system operator, a command output to the master invoice of the feed or the transfer boxes, or other signal transmitter an acceptance of the available services of the Einsgeiser or a comparison of the required and the delivered values of the services. Furthermore, the power factor between actual and desired can be adjusted at the grid connection points and a corresponding regulation of the power factor by the request for reactive power. Furthermore, in the control computer and the controller, a request for further power reduction in case of rule violations or a balance of the available amount of energy or amount of power can be done. In a forecasting tool implemented in the control computer or controller, a recording of weather forecasts, a recording of availability of the singers, a recording of supplied energy quantities, a calculation of delivery forecasts or an output of delivery forecasts in standardized data formats can take place. The forecasting tool can also be executed as a separate forecasting tool within the energy portal.

Zusammenfassend lässt sich die Funktion des Energieportals so beschreiben, dass eine Messwerterfassung der elektrischen Größen bezüglich aller relevanten Netzverknüpfungspunkte vorgenommen wird und diese Messwerte bei Bedarf über beliebige Zeiträume dokumentiert werden. Diese Messwerte sind beispielsweise der Strom und die Spannung an den Netzverknüpfungspunkten. Aus diesen Größen können alle relevanten elektrischen Einheiten errechnet werden.In summary, the function of the energy portal can be described in such a way that a measurement value recording of the electrical quantities is made with respect to all relevant network connection points and these measured values are documented over any periods of time if required. These measured values are, for example, the current and the voltage at the network connection points. From these quantities all relevant electrical units can be calculated.

Darüber hinaus können von dem Energieportal Signalgröße zur Leistungsreduzierung vom z, B. Verteilnetzbetreiber sowie der Signalgrößen zum Leistungsfaktor vom z. B. Verteilnetzbetreiber entgegengenommen werden und eine entsprechende Rückmeldung der Signalgrößen zur Leistungsreduzierung beziehungsweise des Leistungsfaktors an den Verteilnetzbetreibers gegeben werden. Ferner können die Signalgrößen zur Leistungsreduzierung beziehungsweise zum Leistungsfaktor an die einspeisenden Sub-Netzwerke gegeben werden sowie entsprechende Regelbefehle an die stationäre Blindleistungseinrichtung 160 ausgegeben werden. Weiterhin können Signalgrößen zur verfügbaren Leistung vom Einsgeiser sowie weiterer Signalgrößen wie beispielsweise der Windgeschwindigkeit eines Windparks oder die Verfügbarkeit eines Windparks entgegengenommen werden, ebenso wie Wettervorhersagen und entsprechende Lieferprognosen ausgegeben werden. Die Übertragung der Signalgrößen können dabei in beliebiger Form erfolgen, zum Beispiel über Stromschnittstellen, eine binäre Signalausgabe oder beliebige Befehls- oder Informationsprotokolle.In addition, from the energy portal signal size for power reduction of z, B. distribution network operator and the signal magnitudes to the power factor of z. B. distribution system operators are received and given a corresponding feedback of the signal sizes for power reduction or power factor to the distribution system operator. Furthermore, the signal sizes for power reduction or power factor can be given to the feeding sub-networks and appropriate control commands to the stationary reactive power device 160 be issued. Furthermore, signal quantities regarding the available power can be received by the encoder and other signal variables such as the wind speed of a wind farm or the availability of a wind farm, as well as weather forecasts and corresponding delivery forecasts can be output. The transmission of the signal quantities can take place in any form, for example via current interfaces, a binary signal output or any command or information protocols.

Die Leistungsregelung kann dabei als ein ständiger Abgleich zwischen der Soll- und der Ist-Leistung durch das Energieportal erfolgen. Bei Anforderung einer Leistungsreduzierung durch den z. B. Verteilnetzbetreiber können die Leistungen der Einsgeiser auf Einhaltung der Leistungsreduzierung überwacht werden. Sofern ein oder mehrere Einsgeiser der Leistungsreduzierung nicht folgen, und dadurch ein Regelverstoß, d. h. eine Vertragsverletzung vorliegt, können die entsprechenden Einsgeiser der Leistungsreduzierung am Netzverknüpfungspunkt des Verteilnetzbetreibers reduziert werden, so dass die durch die angeforderte Leistungsreduzierung verminderte Maximalleistung des Verteilnetzbetreibers eingehalten wird. Dies kann auch dadurch erfolgen, dass beispielsweise das entsprechende Sub-Energieerzeugungsnetz 230 seitens des Umspannwerkbetreibers singulär vom Netz genommen wird, bevor z. B. der Verteilnetzbetreiber die Gesamtheit der Sub-Energieverteilungsnetze 230, 240 am Netzverknüpfungspunkt 110 in ihrer Gesamtheit vom Netz nimmt.The power control can be done as a constant balance between the target and the actual power through the energy portal. When requesting a power reduction by the z. B. Distribution system operators, the services of the Einsgeiser can be monitored for compliance with the power reduction. If one or more sinners do not follow the reduction in performance and there is a breach, ie a breach of contract, the corresponding reducers of the power reduction at the grid connection point of the distribution system operator can be reduced so that the maximum power of the distribution grid operator reduced by the requested power reduction is maintained. This can also be done by, for example, the corresponding sub-power generation network 230 on the part of the Substation operator is taken singularly from the network before z. As the distribution system operator, the entirety of the sub-power distribution networks 230 . 240 at the network connection point 110 taken in its entirety from the network.

Zeitgleich kann eine Aufzeichnung der zusätzlich reduzierten Leistungen als Wertermittlung mit einem Zeitstempel der zusätzlichen Leistungsreduzierung weiterer Einspeiser oder des vertragsverletzenden Einsgeisers aufgezeichnet werden, um auf diese Weise eine entsprechende Verrechnung der geschuldeten elektrischen Arbeit beziehungsweise der geschuldeten Minderung der elektrischen Arbeit vornehmen zu können. Dies kann durch ein entsprechendes Verrechnungstool des Energieportals vorgenommen werden. Für eine Blindleistungsregelung kann ein ständiger Abgleich der Soll- und Istwerte des Leistungsfaktors am Netzverknüpfungspunkt des Verteilnetzbetreibers und dem Netzverknüpfungspunkten der Einspeiser erfolgen. Zur Einhaltung des Leistungsfaktors kann das Energieportal ständig durch eine entsprechende Werteausgabe die Masterrechner der Einspeiser regeln und den Blindleistungsbedarf überwachen. Zur Einhaltung des Leistungsfaktors kann bei Bedarf die Ansteuerung stationärer Blindleistungsbaugruppen (kontinuierlich sowie stufenweise) sowie deren Überwachung am Netzverknüpfungspunkt erfolgen. Sofern ein oder mehrere Einspeiser beispielsweise nicht den geforderten Blindleistungsbedarf erbringen, so kann beispielsweise ein Regelverstoß, d. h. eine Vertragsverletzung vorliegen, so dass weitere Einspeiser zur Veränderung des Blindleistungsbedarfes aufgefordert werden können. Sofern eine relevante Blindleistungserbringung eines Einspeisers zur Kompensation eines Regelverstoßes eines anderen vorliegt, werden die Blindleistungsbereitstellungen mit einem Zeitstempel versehen und dokumentiert, so dass eine anschließende Verrechnung der unterschiedlichen Einspeiser erfolgen kann. Eine derartige Verrechnung der geschuldeten elektrischen Arbeit kann beispielsweise durch ein entsprechendes Verrechnungstool am Energieportal erfolgen.At the same time, a record of the additionally reduced services can be recorded as value determination with a time stamp of the additional power reduction of further feeders or the infringer infringing the contract, in order to be able to make a corresponding set-off of the owed electrical work or the due reduction of the electrical work. This can be done by a corresponding accounting tool of the energy portal. For reactive power control, a constant comparison of the setpoint and actual values of the power factor at the grid connection point of the distribution system operator and the grid connection points of the feeders can be carried out. In order to comply with the power factor, the energy portal can constantly regulate the master computers of the feeders by means of an appropriate value output and monitor the reactive power demand. If required, the control of stationary reactive power modules (continuously and stepwise) as well as their monitoring at the grid connection point can be carried out to maintain the power factor. For example, if one or more feeders do not provide the required reactive power demand, for example, a rule violation, i. H. there is a breach of contract, so that additional feeders can be asked to change the reactive power demand. If there is a relevant reactive power provision of one feeder to compensate for a rule violation of another, the reactive power provisions are provided with a time stamp and documented, so that a subsequent settlement of the different feeders can take place. Such a settlement of the owed electrical work can be done for example by a corresponding Verrechnungstool the energy portal.

Ferner können die elektrischen Leistungen der Einspeiser vom Energieportal aufgezeichnet werden. Bei einer Übermittlung von Einflussgrößen, beispielsweise Windgeschwindigkeiten, zur Energieerzeugung durch den Masterrechner der Erzeugungsanlagen können durch das Energieportal Tendenzrechnungen erfolgen. Diese Tendenzrechnungen lassen einen Rückschluss auf die tatsächliche Leistungsfähigkeit der Energieerzeugungsanlage zu.Furthermore, the electrical power of the feeders can be recorded by the energy portal. When transmitting influencing variables, for example wind speeds, for the generation of energy by the master computer of the production plants, the energy portal can make calculations for the future. These trend calculations allow a conclusion on the actual performance of the power generation plant.

Über ein Prognosetool kann beispielsweise eine Prognose der Tagesproduktion durch die Berücksichtigung durch Windvorhersagen erfolgen. Darüber hinaus kann beispielsweise eine Verfügbarkeit der Erzeugungsanlagen aus beispielsweise historischen Daten der Produktionen erfolgen, um eine entsprechende Prognose zu erstellen. Dabei können derartige Prognosen sowohl automatisch als auch manuell beeinflusst beziehungsweise korrigiert für den Steuerungs- beziehungsweise Regelmechanismus verwendet werden. Die entsprechenden Prognosen können dabei beispielsweise auch (beispielsweise in genormten Dateiformaten) weiter gesendet werden, um diese beispielsweise einen Stromhändler zur Verfügung zu stellen.By means of a forecasting tool, for example, a forecast of the daily production can be made by taking into account wind forecasts. In addition, for example, an availability of the production facilities from, for example, historical data of the productions can be made in order to create a corresponding forecast. In this case, such predictions can be both automatically and manually influenced or corrected used for the control or regulating mechanism. The corresponding forecasts can, for example, also be forwarded (for example in standardized file formats) in order, for example, to make these available to a power trader.

Es sollte angemerkt werden, dass die vorliegende Erfindung neben der Anwendung in Windkraftanlagen auch beispielsweise bei Photovoltaik- oder Wasserkraftanlagen angewendet werden kann.It should be noted that the present invention, in addition to application in wind turbines, can also be used for example in photovoltaic or hydropower plants.

Es sei angemerkt, dass der Begriff „umfassend” weitere Elemente oder Verfahrensschritte nicht ausschließt, ebenso wie der Begriff „ein” und „eine” mehrere Elemente und Schritte nicht ausschließt.It should be noted that the term "comprising" does not exclude other elements or method steps, just as the term "a" and "an" does not exclude multiple elements and steps.

Die verwendeten Bezugszeichen dienen lediglich zur Erhöhung der Verständlichkeit und sollen keinesfalls als einschränkend betrachtet werden, wobei der Schutzbereich der Erfindung durch die Ansprüche wiedergegeben wird.The reference numerals used are for convenience of reference only and are not to be considered as limiting, the scope of the invention being indicated by the claims.

ZITATE ENTHALTEN IN DER BESCHREIBUNG QUOTES INCLUDE IN THE DESCRIPTION

Diese Liste der vom Anmelder aufgeführten Dokumente wurde automatisiert erzeugt und ist ausschließlich zur besseren Information des Lesers aufgenommen. Die Liste ist nicht Bestandteil der deutschen Patent- bzw. Gebrauchsmusteranmeldung. Das DPMA übernimmt keinerlei Haftung für etwaige Fehler oder Auslassungen.This list of the documents listed by the applicant has been generated automatically and is included solely for the better information of the reader. The list is not part of the German patent or utility model application. The DPMA assumes no liability for any errors or omissions.

Zitierte PatentliteraturCited patent literature

  • DE 602004010281 T2 [0007] DE 602004010281 T2 [0007]

Zitierte Nicht-PatentliteraturCited non-patent literature

  • Netzanschlussrichtlinien sowie die Netzeinspeiseverträge, sowie das EEG (Erneuerbare Energien Gesetz01.01.2009) [0003] Grid connection guidelines and the grid feed-in contracts, as well as the EEG (Renewable Energies Act01.01.2009) [0003]
  • Erneuerbare Energien Gesetz (EEG) [0005] Renewable Energy Law (EEG) [0005]
  • Windkraftjournal, Ausgabe 1/2007, Seiten 58 bis 61, beziehungsweise Ausgabe 4/2008, Seiten 40 bis 41 [0006] Windkraftjournal, issue 1/2007, pages 58 to 61, and issue 4/2008, pages 40 to 41 [0006]

Claims (10)

Energieportal zur Steuerung bzw. Regelung einer Energieeinspeisung aus einem Erzeugernetz (230, 240, 250) in ein Energieverteilungsnetz (105), wobei das Energieportal (1) umfasst: eine Einspeisefaktoren-Empfangsvorrichtung (10) zum Empfangen von vorgebbaren Einspeisefaktoren eines Energieverteilungsnetzbetreibers, eine Erzeugernetzmessgrößen-Empfangsvorrichtung (20) zum Empfangen von Messgrößen eines Erzeugernetzes (230, 240, 250), eine Prognoseinformations-Empfangsvorrichtung (30) zum Empfangen von Prognoseinformation, eine Auswertevorrichtung (40) zum Auswerten der Messgrößen, Einspeisefaktoren und Prognoseinformation, und eine Betriebsparameter-Regelvorrichtung (50) zum Steuern bzw. Regeln von Betriebsparametern des Erzeugernetzes auf der Grundlage der ausgewerteten Messgrößen, Einspeisefaktoren und Prognoseinformation mit den Einspeisefaktoren als Regelgröße.Energy portal for controlling or regulating an energy feed from a generator network ( 230 . 240 . 250 ) into an energy distribution network ( 105 ), whereby the energy portal ( 1 ) comprises: a feed factor receiving device ( 10 ) for receiving predeterminable feed-in factors of a power distribution system operator, a generator grid measurement receiving device ( 20 ) for receiving measured quantities of a generator network ( 230 . 240 . 250 ), a forecast information receiving device ( 30 ) for receiving prognosis information, an evaluation device ( 40 ) for evaluating the measured quantities, feed factors and forecast information, and an operating parameter control device ( 50 ) for controlling or regulating operating parameters of the generator network on the basis of the evaluated measured variables, feed factors and forecast information with the feed factors as controlled variable. Energieportal gemäß Anspruch 1, wobei die Erzeugernetzmessgrößen-Empfangsvorrichtung (20) zum Empfangen von Messgrößen bezüglich Blindleistung des Erzeugernetzes (230, 240, 250) ausgelegt ist, wobei die Betriebsparameter-Regelvorrichtung zum dynamischen Steuern bzw. Regeln von Blindleistungskompensation ausgelegt ist.An energy portal according to claim 1, wherein the generator set measurement receiving apparatus ( 20 ) for receiving reactive power measurements of the generating network ( 230 . 240 . 250 ), wherein the operating parameter control device is adapted to dynamically control reactive power compensation. Energieportal gemäß einem der Ansprüche 1 und 2, wobei die Erzeugernetzmessgrößen-Empfangsvorrichtung (20) ausgelegt ist zum Empfangen von Erzeugernetzmessgrößen mehrerer Sub-Erzeugernetze (230, 240, 250).Energy portal according to one of the claims 1 and 2, wherein the generator set measurement receiving device ( 20 ) is adapted to receive generation grid metrics of multiple sub-generation networks ( 230 . 240 . 250 ). Energieportal gemäß einem der Ansprüche 1 bis 3, wobei die Betriebsparameter-Regelvorrichtung (50) ausgelegt ist zum Steuern bzw. Regeln von Betriebsparametern des Erzeugernetzes auf der Grundlage von jeweils notwendiger Blindleistungskompensation unterschiedlicher Sub-Erzeugernetze (230, 240, 250) in Abhängigkeit der jeweils von den Sub-Erzeugernetzen bereitgestellten Energie.Energy portal according to one of claims 1 to 3, wherein the operating parameter control device ( 50 ) is designed to control operating parameters of the generator network on the basis of respectively necessary reactive power compensation of different sub-generator networks ( 230 . 240 . 250 ) depending on the respective energy provided by the sub-producer networks. Energieportal gemäß einem der Ansprüche 1 bis 4, wobei die Einspeisefaktoren-Empfangsvorrichtung (10) zum wiederholten bzw. zyklischen Empfangen von vorgebbaren Einspeisefaktoren eines Betreibers des Energieverteilungsnetzes (105) ausgelegt ist.Energy portal according to one of claims 1 to 4, wherein the feed factor receiving device ( 10 ) for repeatedly or cyclically receiving predefinable feed-in factors of an operator of the energy distribution network ( 105 ) is designed. Energieportal gemäß einem der Ansprüche 1 bis 5, wobei die Erzeugernetzmessgrößen-Empfangsvorrichtung (20) ausgelegt ist zum Empfangen von herstellerspezifischen Messgrößen eines Erzeugernetzes (230, 240, 250).An energy portal according to any one of claims 1 to 5, wherein the generator set measurement receiving device ( 20 ) is designed to receive manufacturer-specific measured variables of a generator network ( 230 . 240 . 250 ). Energieportal gemäß einem der Ansprüche 1 bis 6, wobei die Prognoseinformations-Empfangsvorrichtung (30) ausgelegt ist zum Empfangen von Information aus einer aus einer Gruppe von Prognoseinformation, wobei die Gruppe besteht aus: Bedarfsprognoseinformation, Einspeisehistorieprognoseinformation, Wetterprognoseinformation, Leistungsprognoseinformation, und Arbeitsprognoseinformation.An energy portal according to any one of claims 1 to 6, wherein the forecast information receiving apparatus ( 30 ) is arranged to receive information from one of a group of forecast information, the group consisting of: demand forecast information, feed history prediction information, weather forecast information, power prediction information, and work prediction information. Energieportal gemäß einem der Ansprüche 1 bis 7, wobei das Erzeugernetz (230, 240, 250) wenigstens einen Teil Windenergieerzeugungskomponenten (231, 232, 241, 242) aufweist, wobei die Erzeugernetzmessgrößen-Empfangsvorrichtung (20) ausgelegt ist zum Empfangen von Windenergieanlagen-Messgrößen.Energy portal according to one of claims 1 to 7, wherein the producer network ( 230 . 240 . 250 ) at least a part of wind energy production components ( 231 . 232 . 241 . 242 ), wherein the generator set measurement receiving device ( 20 ) is adapted to receive wind turbine measurements. Verfahren zur Einhaltung von Einspeisefaktoren eines Energieverteilungsnetzbetreibers bei einer Energieeinspeisung aus einem Erzeugernetz in ein Energieverteilungsnetz, umfassend: Empfangen von vorgebbaren Einspeisefaktoren eines Energieverteilungsnetzbetreibers, Empfangen von Messgrößen eines Erzeugernetzes, Empfangen von Prognoseinformation, Auswerten der Messgrößen, der Einspeisefaktoren und der Prognoseinformation, Steuern bzw. Regeln von Betriebsparametern des Erzeugernetzes auf der Grundlage der ausgewerteten Messgrößen, Einspeisefaktoren und Prognoseinformation mit den Einspeisefaktoren als Regelgröße.A method for compliance with feed-in factors of an energy distribution system operator when feeding energy from a generator network into an energy distribution network, comprising: Receiving predeterminable feed-in factors of an energy distribution system operator, Receiving measured quantities of a generator network, Receiving forecast information, Evaluation of the measured variables, the feed factors and the forecast information, Controlling or regulating operating parameters of the generator network on the basis of the evaluated measured variables, feed-in factors and forecast information with the feed-in factors as controlled variable. Verwendung des Verfahrens nach Anspruch 9 in einem Energieerzeugungsnetz (230, 240, 250) mit wenigstens einem Teil Windenergieerzeugungskomponenten (231, 232, 241, 242), wobei die Prognoseinformation eine Wetterprognose, eine Leistungsprognose beziehungsweise eine Arbeitsprognose umfasst.Use of the method according to claim 9 in a power generation network ( 230 . 240 . 250 ) with at least one part of wind energy production components ( 231 . 232 . 241 . 242 ), wherein the forecast information comprises a weather forecast, a performance forecast or a work forecast.
DE102010006142A 2010-01-29 2010-01-29 Energy portal for controlling and/or regulating energy supply in power distribution network of wind power plant, has control device controlling and/or regulating parameters as variables based on variables, factors and information Withdrawn DE102010006142A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
DE102010006142A DE102010006142A1 (en) 2010-01-29 2010-01-29 Energy portal for controlling and/or regulating energy supply in power distribution network of wind power plant, has control device controlling and/or regulating parameters as variables based on variables, factors and information

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE102010006142A DE102010006142A1 (en) 2010-01-29 2010-01-29 Energy portal for controlling and/or regulating energy supply in power distribution network of wind power plant, has control device controlling and/or regulating parameters as variables based on variables, factors and information

Publications (1)

Publication Number Publication Date
DE102010006142A1 true DE102010006142A1 (en) 2011-08-04

Family

ID=44315931

Family Applications (1)

Application Number Title Priority Date Filing Date
DE102010006142A Withdrawn DE102010006142A1 (en) 2010-01-29 2010-01-29 Energy portal for controlling and/or regulating energy supply in power distribution network of wind power plant, has control device controlling and/or regulating parameters as variables based on variables, factors and information

Country Status (1)

Country Link
DE (1) DE102010006142A1 (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102013106393A1 (en) 2012-06-22 2013-12-24 Sma Solar Technology Ag Network planning and management
DE102012012750A1 (en) * 2012-06-27 2014-01-02 Konrad Marek Method for enhancing weather forecasting and climate prediction calculations on mainframe computers, involves performing weather forecast and/or climate prediction calculation, and providing target values to control wind power station
DE102012105721A1 (en) * 2012-06-28 2014-01-02 Sma Solar Technology Ag Controlling a plurality of inverters connected to a common grid transfer point
WO2014071948A1 (en) * 2012-09-17 2014-05-15 Vestas Wind Systems A/S A method of determining individual set points in a power plant controller, and a power plant controller
DE102013009793A1 (en) 2013-06-12 2014-12-18 Konrad Marek Improvement of weather forecasts - and ocean - atmosphere - calculation models
WO2015018613A1 (en) 2013-08-06 2015-02-12 Wobben Properties Gmbh Method for controlling wind turbines
DE102013215398A1 (en) * 2013-08-06 2015-02-12 Wobben Properties Gmbh Method for controlling wind turbines
WO2015022206A1 (en) * 2013-08-15 2015-02-19 Wobben Properties Gmbh Method for feeding electric power into a supply grid
WO2015018509A3 (en) * 2013-08-05 2015-04-09 Technische Universität Dortmund System and method for controlling the frequency stability and/or voltage stability of the distribution network
DE202017100343U1 (en) 2017-01-24 2017-02-27 EWC Weather Consult GmbH System for generating real-time information and forecasting of power regulations due to network bottlenecks in a power grid
EP3352326A1 (en) 2017-01-24 2018-07-25 Ubimet GmbH System for generating real-time information and forecasting power rules due to network bottlenecks in a power supply network
DE102017101265A1 (en) 2017-01-24 2018-07-26 UBIMET GmbH System for generating real-time information and forecasting of power regulations due to network bottlenecks in a power grid
DE102017120946A1 (en) * 2017-09-11 2019-03-14 Innogy Se Control and / or regulation of power generation plants

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE602004010281T2 (en) 2003-08-20 2008-10-02 New Energy Options, Inc., Littleton METHOD AND SYSTEM FOR PREDICTING SOLAR ENERGY PRODUCTION

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE602004010281T2 (en) 2003-08-20 2008-10-02 New Energy Options, Inc., Littleton METHOD AND SYSTEM FOR PREDICTING SOLAR ENERGY PRODUCTION

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
Erneuerbare Energien Gesetz (EEG)
Netzanschlussrichtlinien sowie die Netzeinspeiseverträge, sowie das EEG (Erneuerbare Energien Gesetz01.01.2009)
PFEIL, F.: Das EP-Grid, ein Energieportal für ein 100MW Umspannwerk *
ROSIN,M.: Erzeugungsmanagement - Herausforderung für den Netzbetreiber. ETG-Tagung>Technische Innovation in Verteilungsnetzen< Würzburg, 01.-02.03.2005. Im Internet: http://www.blitzschutz-blitzforschung.de/de/fg/ETG/Exklusiv-Mitglieder/verteilungsnetze2005/Documents/MCMS/42rosin.pdf [abger. am 01.12.2010] *
Windkraftjournal, Ausgabe 1/2007, Seiten 58 bis 61, beziehungsweise Ausgabe 4/2008, Seiten 40 bis 41

Cited By (33)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US10247537B2 (en) 2012-06-22 2019-04-02 Sma Solar Technology Ag Grid diagram creation and operation control
WO2013189967A2 (en) 2012-06-22 2013-12-27 Sma Solar Technology Ag Network diagram creation and management
CN104396111A (en) * 2012-06-22 2015-03-04 艾思玛太阳能技术股份公司 Network diagram creation and management
WO2013189967A3 (en) * 2012-06-22 2014-02-20 Sma Solar Technology Ag Network diagram creation and management
CN104396111B (en) * 2012-06-22 2017-03-29 艾思玛太阳能技术股份公司 Electrical network figure builds and runs guiding
DE102013106393A1 (en) 2012-06-22 2013-12-24 Sma Solar Technology Ag Network planning and management
DE102012012750A1 (en) * 2012-06-27 2014-01-02 Konrad Marek Method for enhancing weather forecasting and climate prediction calculations on mainframe computers, involves performing weather forecast and/or climate prediction calculation, and providing target values to control wind power station
US10027123B2 (en) 2012-06-28 2018-07-17 Sma Solar Technology Ag Control of a plurality of inverters connected to a common grid connection point
DE102012105721A1 (en) * 2012-06-28 2014-01-02 Sma Solar Technology Ag Controlling a plurality of inverters connected to a common grid transfer point
DE102012105721B4 (en) 2012-06-28 2017-02-09 Sma Solar Technology Ag Controlling a plurality of inverters connected to a common grid transfer point
US9556852B2 (en) 2012-09-17 2017-01-31 Vestas Wind Systems A/S Method of determining individual set points in a power plant controller, and a power plant controller
WO2014071948A1 (en) * 2012-09-17 2014-05-15 Vestas Wind Systems A/S A method of determining individual set points in a power plant controller, and a power plant controller
EP2896102B1 (en) 2012-09-17 2017-02-22 Vestas Wind Systems A/S A method of determining individual set points in a power plant controller, and a power plant controller
DE102013009793A1 (en) 2013-06-12 2014-12-18 Konrad Marek Improvement of weather forecasts - and ocean - atmosphere - calculation models
WO2015018509A3 (en) * 2013-08-05 2015-04-09 Technische Universität Dortmund System and method for controlling the frequency stability and/or voltage stability of the distribution network
DE102013215398A1 (en) * 2013-08-06 2015-02-12 Wobben Properties Gmbh Method for controlling wind turbines
RU2662238C2 (en) * 2013-08-06 2018-07-25 Воббен Пропертиз Гмбх Method for controlling wind turbines
US10724500B2 (en) 2013-08-06 2020-07-28 Wobben Properties Gmbh Method for controlling wind power plants
US10320315B2 (en) 2013-08-06 2019-06-11 Wobben Properties Gmbh Method for controlling wind turbines
WO2015018612A1 (en) 2013-08-06 2015-02-12 Wobben Properties Gmbh Method for controlling wind power plants
AU2014304829B2 (en) * 2013-08-06 2017-08-10 Wobben Properties Gmbh Method for controlling wind power plants
AU2014304830B2 (en) * 2013-08-06 2017-08-31 Wobben Properties Gmbh Method for controlling wind turbines
AU2014304830C1 (en) * 2013-08-06 2018-04-12 Wobben Properties Gmbh Method for controlling wind turbines
DE102013215396A1 (en) * 2013-08-06 2015-02-12 Wobben Properties Gmbh Method for controlling wind turbines
CN105453368A (en) * 2013-08-06 2016-03-30 乌本产权有限公司 Method for controlling wind turbines
WO2015018613A1 (en) 2013-08-06 2015-02-12 Wobben Properties Gmbh Method for controlling wind turbines
US10132294B2 (en) 2013-08-15 2018-11-20 Wobben Properties Gmbh Method for feeding electric power into a supply grid
WO2015022206A1 (en) * 2013-08-15 2015-02-19 Wobben Properties Gmbh Method for feeding electric power into a supply grid
DE102017101265A1 (en) 2017-01-24 2018-07-26 UBIMET GmbH System for generating real-time information and forecasting of power regulations due to network bottlenecks in a power grid
EP3352326A1 (en) 2017-01-24 2018-07-25 Ubimet GmbH System for generating real-time information and forecasting power rules due to network bottlenecks in a power supply network
DE202017100343U1 (en) 2017-01-24 2017-02-27 EWC Weather Consult GmbH System for generating real-time information and forecasting of power regulations due to network bottlenecks in a power grid
US10581250B2 (en) 2017-01-24 2020-03-03 UBIMET GmbH System for generating real-time information and forecasts on power output regulation due to grid congestion in at least one power grid
DE102017120946A1 (en) * 2017-09-11 2019-03-14 Innogy Se Control and / or regulation of power generation plants

Similar Documents

Publication Publication Date Title
DE102010006142A1 (en) Energy portal for controlling and/or regulating energy supply in power distribution network of wind power plant, has control device controlling and/or regulating parameters as variables based on variables, factors and information
EP2084801B1 (en) Method for operating a low-voltage electrical system
EP2467920B1 (en) Power regulation for solar power station
EP2495838B1 (en) Method and device for stabilising the power supply operation of an energy supply network
EP3336995B1 (en) Method, control device and system for determining state values for describing operating states in a subnetwork of an energy supply network
EP2463980B1 (en) Operation of an energy producer in an energy supply network
EP3031112B1 (en) System and method for controlling the transmission grid frequency and/or voltage from the distribution network
DE102015201085A1 (en) Method for controlling an electrical power distribution network
DE102010056456A1 (en) Wind farm and method for operating a wind farm
WO2018122405A1 (en) Method for controlling an electrical distribution network
DE102011106114A1 (en) Method for distributing electrical energy in a power network having a plurality of distribution cells
DE102018001763A1 (en) Method and system for servicing a wind turbine from a group of wind turbines
EP3042428A1 (en) Device and method for controlling the stability of a local network using an adjustable local network transformer
EP3092697B1 (en) Method and control device for controlling an operating frequency of an energy source in an ac voltage network
DE102011122580B4 (en) Method for operating an electrical supply network and associated control unit
DE102011078895A1 (en) Energy network system useful for generating and transferring electrical energy between primary energy producers and consumers, comprises e.g. primary energy generating units, energy consumption units, and frequency control units
DE102010023113A1 (en) System for dynamic regulation of regenerative energy generation installation with multiple energy generation units, has signal input for receiving pre-determined nominal value
DE102014101809A1 (en) Method for controlling a regenerative power generation plant and regenerative power generation plant
AT514766B1 (en) Method for stabilizing an energy distribution network
DE102016217748A1 (en) Provision of primary control power
WO2020104450A1 (en) Feed-in method for a wind power system, and wind power system
EP3621169A1 (en) Isolated network and method for operating same
EP4022731B1 (en) Method for operating an electrical storage station
DE102018124612A1 (en) Control of a local network area to implement a local energy community with a timetable
EP2930812B1 (en) Reactive power management

Legal Events

Date Code Title Description
R016 Response to examination communication
R119 Application deemed withdrawn, or ip right lapsed, due to non-payment of renewal fee

Effective date: 20130801