CS251627B1 - Tunnel boarding - Google Patents

Tunnel boarding Download PDF

Info

Publication number
CS251627B1
CS251627B1 CS847463A CS746384A CS251627B1 CS 251627 B1 CS251627 B1 CS 251627B1 CS 847463 A CS847463 A CS 847463A CS 746384 A CS746384 A CS 746384A CS 251627 B1 CS251627 B1 CS 251627B1
Authority
CS
Czechoslovakia
Prior art keywords
formwork
tusks
tunnel
lock
longitudinal
Prior art date
Application number
CS847463A
Other languages
Czech (cs)
Other versions
CS746384A1 (en
Inventor
Vladimir Pavel
Vojtech Becvar
Original Assignee
Vladimir Pavel
Vojtech Becvar
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Vladimir Pavel, Vojtech Becvar filed Critical Vladimir Pavel
Priority to CS847463A priority Critical patent/CS251627B1/en
Publication of CS746384A1 publication Critical patent/CS746384A1/en
Publication of CS251627B1 publication Critical patent/CS251627B1/en

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

Tunelevé bednění má lcaždý bednicí dílec pedélně rezdělen na základní díl a na závěrevý díl prestřednictvím spejitéhe zámku, umístěné!»· ve střední třetině strepníhe trámce příěnéhe rámu, urěenéhe pre zesílení bednicíhe dílce, přičemž každý díl bednicíhe dílce je pesazen na pedélném nesníku, epatřeném stavěcími Sreuby a pejezdevými kely, jejichž esy jseu k pedélným nesníkům připevněny zdela. Závěrevý díl bednicíhe dílce je pesazen níže e výěkevý rezdíl mezi částí strepníhe trámce závěrevéhe dílu a mezi částí strepníhe trámce zákledníhe dílu při rezepnutém spejitém zámku, prestřednictvím pejezdevých kel e menším průměru. Alternativně může být závěrevý díl bednicíhe dílce pesazen níže prestřednictvím pejezdevých kel, jejichž esy jseu k pedélnému nesníku připevněny shera.The tunnel formwork has every single formwork the panel lengthwise divided into a base part and to the final part through the film the castle, located in the middle third the roof beams of the frame, fixed to amplify the workpiece flap, wherein each part of the panel is displaced on the longitudinal sap, the epatorn settled creeks and tusked tusks They are attached to the longitudinal uneven Zdela. The final part of the bedniceh the part is shifted below e the difference between the part of the roof of the beam part and between the part of the beam of the beam part with the bonded joint of the castle, through tusks smaller diameter. Alternatively, it may be the final part of the unitary part is lowered below through the tusk, whose You are attached to the longitudinal beam shera.

Description

Vynález se týká tunelového bednění, zajištujícího svislest stěn bednění při odbednění.The present invention relates to a tunnel formwork providing a vertical formwork formwork.

Peužívaná tunelová bednění jseu vesměs tveřena jednotlivými padélnými bednícími dílci, z nichž každý je sležen z bednících stěn zesílených nejméně jedním příčným rámem, jehož součástí je vodorovný stropní trámec, rozdělený na dva díly prostřednictvím spojitého zámku.The tunnel formwork in use is largely made up of individual counterfeit formwork panels, each of which is descended from the formwork walls reinforced by at least one cross frame comprising a horizontal ceiling beam divided into two parts by means of a continuous lock.

Používaná tunelová bednění jsou opatřena spojitým zámkem, kterým je rozdělen bednící dílec podélně na základní díl opatřený horní částí spojitého zámku a na závěrový díl opatřený spodní částí spojitého zámku. Každý díl bednícího dílce je v dolní části opatřen podélným nosníkem se stavěcími Šrouby, a pojezdovými koly tak, že podvozek bednícího dílce je souměrný. Po odbednění, to je po uvolnění stavěčích Šroubů, po uvol nSní rektifikační rozpěry a po rozepnutí spojitého zámku, poklesne a podsune se závěrový díl pod základní díl bednícího dílce asi o 5 cm.The tunnel formwork used is provided with a continuous lock which divides the formwork longitudinally into a base part provided with an upper part of the continuous lock and into a closing part provided with a lower part of the continuous lock. Each part of the formwork is provided at its lower part with a longitudinal beam with adjusting screws and traveling wheels so that the chassis of the formwork is symmetrical. After unforming, i.e. after loosening the setscrews, after releasing the rectifying struts and after opening the continuous lock, the shutter is lowered and pushed under the base part of the formwork by about 5 cm.

Zároveň dosedne základní díl i závěrový díl bednícího dílce na pojezdová kola ve stejné výšce, což způsobí naklonění bednícího dílce ve směru jeho základního dílu a jeho zpříčení uvnitř vybudované tunelové konstrukce.At the same time, the base part and the shutter part of the shuttering panel rest on the traveling wheels at the same height, which causes the shuttering panel to tilt in the direction of its base panel and its buckling inside the built-in tunnel structure.

Doba nutná k vysunuti bednících dílců se i několikanásobně prodlouží a potřebný čas nelze předem přesně určit, čímž je narušena plynulost dopravy betonové směsi a navazujících úkonů. Doba výstavby se prodlužuje, narůstají stavební náklady a zhoršují se podmínky pro dodržování bezpečnosti práce. Proto byly pokusně základní bednící dílce podkládány, například fošnou, pro usnadnění jejich vysunutí.The time required to eject the shuttering elements is extended several times, and the required time cannot be precisely determined in advance, thereby disrupting the flow of the concrete mixture and the subsequent operations. Construction time increases, construction costs increase and conditions for safety at work deteriorate. Therefore, the base formwork panels have been tentatively supported, for example by a plank, to facilitate their ejection.

Proces vysouvání se tím však podstatně nezkrátil a navíc nebylo možno dodržet konstrukční výšku podlaží, což způsobovalo značné problémy při montáži obvodového pláště budovy, prefabrikovaných schodišťových ramen a podobně.However, the ejection process has not been substantially reduced and, moreover, the construction height of the floors could not be maintained, which caused considerable problems in the assembly of the building envelope, prefabricated stair arms and the like.

Uvedené nedostatky odstraňuje tunelové bednění, sestávající z nejméně jednoho bednícího dílce, složeného z bednících stěn, zesílených nejméně jedním příčným rámem tvořeným vodorovným stropním trámcem a dvěma svislými stěnovými trámci, v dolní části vzájemně spojenými roktifikovanou rozpěrou.These drawbacks are eliminated by a tunnel formwork consisting of at least one formwork panel composed of formwork walls reinforced by at least one cross frame formed by a horizontal ceiling beam and two vertical wall beams, connected at the bottom by a mutually spaced spacer.

Každý stěnový trámec je pevně uložen na podélném nosníku, opatřeném nejméně dvěma stavěcími šrouby a nejméně dvěma za sebou situovanými pojezdovými koly, jejichž osy jsou pevně spojeny s podélním nosníkem.Each wall beam is fixedly mounted on a longitudinal beam, provided with at least two set screws and at least two successive traveling wheels, the axes of which are fixedly connected to the longitudinal beam.

Bednící dílec je podélně rozdělen prostřednictvím spojitého zámku na základní díl, jehož část stropního trámce je opatřena horní částí spojitého zámku a na závěrový díl, jehož část stropního trámce je opatřena spodní částí spojitého zámku. Podstata vynálezu spočívá v tom, že závěrový díl bednícího dílce je ne pojezdových kolech posazen níže o výškový rozdíl mezi částí stropního trámce závěrového dílu a mezi částí stropního trámce základního dílu při rozepnutém spojitém zámku.The shuttering is longitudinally divided by means of a continuous lock into a base part whose part of the ceiling beam is provided with the upper part of the continuous lock and into a breech part whose part of the ceiling beam is provided with the lower part of the continuous lock. SUMMARY OF THE INVENTION The shutter element of the shuttering element is positioned lower on the traveling wheels by a height difference between the ceiling beam section of the shutter section and the ceiling beam section of the base section with the continuous lock open.

Závěrový díl může být posazen níže přostřednictvlm pojezdových kol o menším průměru. Alternativně může být závěrový díl posazen níže prostřednictvím pojezdových kol, jejichž osy jsou s podélným nosníkem pevně spojeny shora.The locking part can be set lower by means of the traveling wheels of smaller diameter. Alternatively, the breech block may be lowered by means of traveling wheels, the axes of which are fixedly connected to the longitudinal member from above.

Výhodou tunelového bednění podle vynálezu je, že usnadňuje vysunutí bednících dílců po odbednění, pretože jejich stěny zůstávají svislé a nepříčí se ve vnitřním prostoru vybudované kontstrukce. Je možno vysouvat i několik bednících dílců současně a tím urychlit demontáž při podstatě změněeném objemu nutně vynaložené práce. Zároveň se tím urychlí i nástup následných pracovních úkonů, což vede ke zkrácení doby výstavby a zvýěení její hospodárnosti. Při použití pojezdových kol o větším průměru se zmenší valivý edper pedvezku.The advantage of the tunnel formwork according to the invention is that it facilitates the ejection of the formwork panels after the formwork, since their walls remain vertical and do not interfere with the interior space of the built-in construction. It is also possible to pull out several shuttering elements at the same time, thereby speeding up the dismantling process with a substantially changed workload. At the same time, it will speed up the onset of subsequent work operations, which leads to a shorter construction time and increased its economy. The use of larger diameter castors reduces the rolling edper of the pre-trailer.

Na výkresech je schematicky znózerněn v ebr. 1 příčný řez budevaneu stavební kenstrukcí a příslušným tunelevým bedněním a v ebr. 2 řez bedněním, kde esy kel jseu nad pedélným nesníkem.It is schematically shown in the drawings in FIG. 1 is a cross-sectional view of the building construction and the corresponding tunnel formwork and in FIG. 2 is a sectional view of the formwork where the aces are above the front rail.

Příklad 1Example 1

Tunelevé bednění sestává ze tří bednících dílců, z nichž každý je sležen z bednících stěn zesílených dvěma příčnými rámy. Každý příčný rám je tveřen vederevným strepním trámcem £ a dvěma svislými stěnovými trámci 2, v dělní části vzájemně spejenými rektifikevatelneu rezpěreu £ a je pevně uležen na pedélném nesníku 4, tveřeném válcevaným U prefilem epatřeným dvěma stavěcími šreuby £ a dvěma za sebeu situevanými pejezdevými kaly 6, jejichž esy 2 jseu zdela pevně spejeny s pedélním nesníkem £.Bednící dílec je pedélně rezdělen prestřednictvím spejitéhe zámku 8 na základní díl 11 . jehež část strepníhe trámce £ je epatřena herní částí spejitéhe zámku 8 a na zévěrevý díl 1 2. jehež část strepníhe trámce i je epatřena spední částí £0 spejitéhe zámku 8, přičemž závěrevý díl 12 je na pejezdevých kelech 6 pesazen níže e výškevý rezdíl mezi částí strepníhe trámce £ základníhe dílu 11 při rezepnutém zámku 8, prestřednictvím pejezdevých kel 6 e menším průměru.The tunnel formwork consists of three formwork panels, each of which is descended from formwork walls reinforced by two transverse frames. Each transverse frame is formed by a superposed roof beam 8 and two vertical wall beams 2, in the working part interconnected by a rectifiable resistor 4, and is firmly supported on a front rail 4, formed by a rolled U-profile with two adjusting screws 6 and two adjusting screws 6 behind two The aces 2 are rigidly coupled to the pedestal 4. The shuttering panel is cut longitudinally through the interlocking lock 8 to the base member 11. the part of the roof beam 8 is epained by the game part of the latch 8 and on the closure part 2. The part of the beam 8 is also at the front part of the latch 8, wherein the end piece 12 is moved below the elevation In the case of the lock 8, the crossbeam 6 of the base part 11 is cut off by means of the tapering tines 6 and of a smaller diameter.

Příklad 2Example 2

Tunelevé bednění je sestavene stejně jaké v příkladu 1 s tím rezdílem, že závěrevý díl 12 .1e pesazen níže prestřednictvím pejezdevých kel 6 jejichž esy £ jsou s podélným nos níkem spejeny shera. Pre vyrevnání výškevéhe rezdílu na pežadevaneu hednetu musel být průměr pejezdevých kel 6 závěrevéhe dílu 12 přiměřeně zvětšen.The tunnel formwork is assembled in the same way as in Example 1 with the exception that the end piece 12e is lowered by means of running tusks 6 whose aces 8 are shera connected to the longitudinal beam. In order to level the elevation on the hednet, the diameter of the running tusks 6 of the final part 12 had to be appropriately increased.

PŘEDMĚT VYNÁLEZUSUBJECT OF THE INVENTION

Claims (2)

PŘEDMĚT VYNÁLEZUSUBJECT OF THE INVENTION 1. Tunelevé bednění sestávající z nejméně jednehe bednicíhe dílce sleženéhe z bednících stěn, zesílených nejméně jedním příčným rámem tveřeným vederevným strepním trámcem a dvěma svislými stěnevými trámci, v dělní části vzájemně spejenými rektifikevatelneu rezpěreu, zatímce každý stěnevý trámec je pevně uležen na pedélném nesníku, epatřeném nejméně dvěma stavěcími šreuby a nejméně dvěma za sebeu situevanými pejezdevými kely, jejichž esy jseu pevně spejeny s pedélným nesníkem, přičemž bednící dílec je pedélně rezdělen prestřednictvím spejitéhe zámku na základní díl, jehež část strepníhe trámce je epatřena herní částí spejitéhe zámku a na závěrevý díl, jehež část strepníhe trámce je epatřena spední částí spejitéhe zámku, vyznačené tím, že zévěrevý díl (12) bednicíhe dílce je na pejezdevých kelech (6) pesazen níže e výškevý rezdíl mezi částí strepníhe trámce (1) závěrevéhe dílu (12) a mezi částí strepníhe trámce (1) základníhe dílu (11) při rezepnutém spejitém zámku (8).1. Tunnel-shaped formwork consisting of at least one formwork panel supported by formwork walls, reinforced by at least one transverse frame formed by a superb ceiling beam and two vertical wall beams, in a section connected to each other by a rectifiable cross-section, while each wall is fixed on the wall at least two setscrews and at least two superimposed tusks, the aces of which are fixedly connected to the front unbore, the formwork being cut in a longitudinal direction through the lock to the base part, the part of the joist being covered with the play part of the lock and the part of the strepboard is epithetized by the front part of the same lock, characterized in that the closure part (12) of the formwork part is placed below the tusks (6) and the height difference between the part of the strepni tr the frame (1) of the final part (12) and between the part of the strepboard (1) of the base part (11) with the coupled lock (8) disconnected. 2. Tunelevé bednění pedle bědu 1, vyznačené tím, že závěrevý díl (12) je pesazen níže prestřednictvím pejezdevých kel (6) e menším průměru.Tunnel formwork of the runner pedal 1, characterized in that the end piece (12) is lowered by means of running tusks (6) of smaller diameter. 3. Tunelevé bednění pedle bědu 1, vyznačené tím, že závěrevý díl (12) je pesazen níže prestřednictvím pejezdevých kel (6) jejichž esy (7) jseu s pedélným nesníkem (4) pevně spejeny shera.Tunnel formwork of the runner pedal 1, characterized in that the end piece (12) is lowered by means of running tusks (6) whose aces (7) are rigidly connected to the front rail (4). 2 výkresy2 drawings
CS847463A 1984-10-02 1984-10-02 Tunnel boarding CS251627B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CS847463A CS251627B1 (en) 1984-10-02 1984-10-02 Tunnel boarding

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CS847463A CS251627B1 (en) 1984-10-02 1984-10-02 Tunnel boarding

Publications (2)

Publication Number Publication Date
CS746384A1 CS746384A1 (en) 1986-12-18
CS251627B1 true CS251627B1 (en) 1987-07-16

Family

ID=5423812

Family Applications (1)

Application Number Title Priority Date Filing Date
CS847463A CS251627B1 (en) 1984-10-02 1984-10-02 Tunnel boarding

Country Status (1)

Country Link
CS (1) CS251627B1 (en)

Also Published As

Publication number Publication date
CS746384A1 (en) 1986-12-18

Similar Documents

Publication Publication Date Title
US2703003A (en) Wall panel
US4156999A (en) Beam for concrete forming structures
US3787020A (en) Concrete forming structure
KR100305141B1 (en) Method of constructing stairs and staircase, and an apparatus for supporting stairs
US3210903A (en) Method of erecting building constructions and means for carrying out the method
CS251627B1 (en) Tunnel boarding
DE2210342A1 (en) REINFORCED CONCRETE ROOM FOR FINISH
CN109025281A (en) A kind of construction system and method suitable for business superelevation super-span Atrium Structure
DE10233145A1 (en) Procedure for erection of buildings entails erecting repetitive filigree structures with precast concrete parts produced by concrete mixing plants which may be located at building sites and/or in vicinity of building sites
US3410041A (en) Building structures with an intermediate floor and socket-connected uprights
DE19641744C1 (en) Modular construction multistorey garage
DE1807257A1 (en) Formwork scaffolding
DE2132091C3 (en) Precast concrete building
DE652777C (en) Ceiling and roof construction
DE19804008A1 (en) Double-layer house
DE10356975A1 (en) Between towering, load-bearing building suspended building
FI79587B (en) FOERFARANDE OCH ANORDNING FOER UTFOERANDE AV KANTUPPHAENGNING VID EN IHAOLIG PLATTA.
NL8201173A (en) Building construction method - using movable formworks removed for pouring next unit after pouring and hardening
SU723082A1 (en) Multistorey building of prefabricated-monolythic type
Meeson Plank-walled building techniques and the church of St. Lawrence, Rushton Spencer
SU1020546A1 (en) Frame
DE809100C (en) Reinforced concrete skeleton structure
JP3069879B2 (en) System formwork
DE1609361C3 (en) Buildings with prefabricated, closed, single-cell frame elements made of reinforced concrete
CH440131A (en) High storage rack element