Eu-bitumen deslagging jar
Technical field:
The utility model relates to a kind of equipment that is used for pitch at fusing and storage process removal of contamination.
Technical background:
Solid bitumen can be sneaked into various impurity in conveying, storage process, these impurity are deleterious to production, need clean out.The impurity of bulk (as: linkrusta and ironware) can be removed in siccative fragmentation, transportation, and fine particle impurity (as sand) can only be removed in asphalt melting and conveying afterwards thereof, storage process.To the impurity in the eu-bitumen was to let alone to precipitate in asphalt melting groove and pitch storage tank in the past, after after a while, eu-bitumen is discharged, adopt manual type that sedimentary contaminant removal is fallen again, because overlong time, sedimentary impurity hardens easily, and cleaning is difficulty very, and environment is abominable in asphalt melting groove and the pitch storage tank, the health of fettler constituted greatly threaten, and corresponding asphalt melting groove and pitch storage tank need be stopped using during scarfing cinder.
The utility model content:
The purpose of this utility model is: a kind of eu-bitumen deslagging jar is provided, makes scarfing cinder work simple, safe and reliable, solve the difficulty of eu-bitumen scarfing cinder.
The utility model is to constitute like this: it comprises feed valve (1), tank body (2), cleaning door (3), pitch outlet (4), feed valve (1) one end is connected with the opening for feed of tank body (2), feed valve (1) the other end then is connected with the slag-drip opening of pitch storage tank or asphalt melting device (5), cleaning door (3) is located at a side of tank body (2), and pitch outlet (4) is located at opposite side.
Feed valve (1) and tank body (2) all are with the thermal oil insulation jacket, and thermal oil communicating pipe (6) is with the insulation jacket connection of feed valve (1) and tank body (2).
Because the setting of eu-bitumen deslagging jar; make scarfing cinder work not influence the normal use of pitch storage tank or asphalt melting device; make the scarfing cinder work can day-to-day; thereby avoid impurity to produce the phenomenon that hardens because of long-time the accumulation; make scarfing cinder work simple,, close feed valve during scarfing cinder owing to before tank body, be provided with feed valve; can avoid the interior hard pitch of pitch storage tank or asphalt melting device to gush out suddenly and cause security incident, fundamentally solve the problem of eu-bitumen scarfing cinder difficulty.
The utility model compared with prior art has advantages such as simple in structure, easy to operate, safety and sanitation.And can improve the operation factor of pitch storage tank or asphalt melting device, improve working conditions.
Description of drawings:
Accompanying drawing 1 is a synoptic diagram of the present utility model.
Embodiment:
Embodiment of the present utility model: the utility model eu-bitumen deslagging jar disposes feed valve (1), tank body (2), cleaning door (3) etc.Wherein an end of feed valve (1) is connected by flange and bolt with the opening for feed of tank body (2), the other end of feed valve (1) then is connected by flange and bolt with the slag-drip opening of pitch storage tank or asphalt melting device (5), adopt between cleaning door (3) and the tank body (2) and flexibly connect, so that can open during scarfing cinder, pitch outlet (4) is located at the opposite side of tank body (2).Feed valve (1) and tank body (2) all require band thermal oil insulation jacket, and thermal oil communicating pipe (6) is with the insulation jacket connection of feed valve (1) and tank body (2).
Before the use, tank body (2) and feed valve (1) feed thermal oil from import (7), and to avoid the pitch condensation caking in tank body (2) and the feed valve (1), thermal oil can be discharged from outlet (8); Close the asphalt valve of cleaning door (3) and pitch outlet (4) side; During work, open feed valve (1), at first be that pitch will enter in the tank body (2), impurity will be deposited in the tank body (2) gradually afterwards, for some time post precipitation just can begin deslagging work, sedimentation time can be determined and guarantees that a jar intravital impurity end face is lower than the pitch outlet according to the pitch foreign matter content, in order to avoid stop up pitch pipeline and feed valve (1); During deslagging, close feed valve (1) earlier, the asphalt valve of opening pitch outlet (4) side then partially liq pitch in tank body (2) and the feed valve (1) of draining is closed the asphalt valve that pitch exports (4) side again, opens cleaning door (3) at last and carries out artificial scarfing cinder work; Behind the scarfing cinder end-of-job, should note closing cleaning door (3) and open feed valve (1), so that begin the next deslagging cycle.