CN2898293Y - Simple oil extraction water injection metering device - Google Patents

Simple oil extraction water injection metering device Download PDF

Info

Publication number
CN2898293Y
CN2898293Y CNU2006200125440U CN200620012544U CN2898293Y CN 2898293 Y CN2898293 Y CN 2898293Y CN U2006200125440 U CNU2006200125440 U CN U2006200125440U CN 200620012544 U CN200620012544 U CN 200620012544U CN 2898293 Y CN2898293 Y CN 2898293Y
Authority
CN
China
Prior art keywords
valve
oil
pipeline
well
straight
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CNU2006200125440U
Other languages
Chinese (zh)
Inventor
向瑜章
蒲子宁
杨广
赵美刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Petrochina Co Ltd
Original Assignee
Petrochina Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Petrochina Co Ltd filed Critical Petrochina Co Ltd
Priority to CNU2006200125440U priority Critical patent/CN2898293Y/en
Application granted granted Critical
Publication of CN2898293Y publication Critical patent/CN2898293Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Measuring Volume Flow (AREA)

Abstract

The utility model relates to a simple and easy oil recovery water injection metering device, the single well oil pipe line that comes that is connected with the oil well is connected with a three-way valve, export through a three-way valve and through valve connection, through valve and deoiling pipe connection, another exit end of three-way valve and oil well measurement pipe connection, the one end and the separator of oil well measurement pipe line are connected, the separator is connected with a three-way valve entry, another entry of three-way valve is connected with the gas meter, the other end and the separator of gas meter are connected, three-way valve exit end and deoiling pipe connection, the level gauge is located separator outside below, the other end of oil well measurement pipe line passes through valve and oil transfer jar, oil transfer pump, through valve connect the back with deoiling pipe connection, the relief valve is located separator outside top; the tap water pipeline is sequentially connected with the control valve, the electronic flow meter and the water quantity regulating valve and is connected with the water injection well pipeline, the structure is simple, the operation procedure is reduced by 80 percent, the energy consumption is reduced by 90 percent, and the single-well metering time is only 5 to 15 minutes.

Description

Simple and easy oil-withdrawal water-injection metering device
Technical field
The utility model relates to the simple and easy oil-withdrawal water-injection metering device that in a kind of oil exploitation process oilwell produced fluid amount, gas production, water injection well injection rate is measured.
Background technology
At oil recovery, water injecting metering station that early eighties, mid-term go into operation, the operation through more than 20 years progressively enters regeneration period, because of these stations go into operation initial stages with compare at present, the oil field background difference is huge, now will be updated to which type of oil recovery, water filling multi-purpose station, has following problem to research and solve:
The initial stage of building a station single station daily oil production reaches 150-300t, and the single seat measuring station is equipped with tens people, under the abundant background of output height at that time, administrative staff, has built that function is more complete, big (the about 100m of area of construction scope 2), the oil recovery of cost height (700,000 yuan /), water filling associating measuring station.And our factory list station daily average oil production has been reduced to 19.2t at present, eight to 1/10th of the first level of only building a station, and single station personnel configuration has only 2-3 people, just builds a station 1/5th of the initial stage.At this moment, as also upgrading oil recovery, water filling associating measuring station, will bring two problems by former scale, proterotype:
(1) dispose excessive because of oil recovery, water filling associating measuring station, have only tens tons level with respect to present single station daily oil production, the measuring station cost is too high, list is stood running cost height (ten thousand yuan/year of 15-17), oversize problems such as (1-2 hours/well) of metering time is very outstanding.
(2) proterotype recovers the oil, the scale of water filling associating measuring station is big, and management workload is many, and single at present station configuration personnel are few, causes per capita that workload increases considerably, and management difficulty strengthens.
Therefore, the pattern of present newly-built oil recovery, water filling associating measuring station, will be according to existing single station, oil field daily oil production, single station personnel's configuring condition, and follow the principle of " building major station when output is high; build simple and easy station when yielding poorly ", still, build which type of simple and easy oil recovery, water filling associating measuring station, do not have unified standard, be without a fixed pattern yet.
Address the above problem, just must development and Design go out to be fit to simple and easy oil recovery, the water filling associating measuring station of oil field present situation, simultaneously, also former oil recovery, water filling will be united " five is big " problem of measuring station existence: big house (100m 2), big eliminator (800 type eliminator), (60-80m is joined at single station to big oil tank 3Big oil tank), large power, electrically insulation (prevent winter manifold from freezing join the 10-12KW electric heater), metering time oversize (40 minutes to 1 hour), solve together.
The utility model content
The purpose of this utility model is the simple and easy oil-withdrawal water-injection metering device that development and Design goes out that cost is low, operating cost is low, the metering time is short, easy to operate.
Simple and easy oil-withdrawal water-injection metering device described in the utility model is realized by following structure:
It is made up of oil well measurement pipe, running water pipe, commentaries on classics oil tank, commentaries on classics oil pump, eliminator, incubator, content gauge, gas meter, electronic flow instrument, safety valve, control valve, control valve, three way cock and straight-through valve.The single-well oil-mining pipeline that is connected with oil well, be connected with a triple valve inlet end, be connected with a straight-through valve inlet end by three way cock one port of export, the straight-through valve port of export is connected with the pipeline that deoils, another port of export of three way cock is connected with the oil well measurement pipeline, one end of oil well measurement pipeline is connected with separator inlet, separator outlet is connected with a triple valve inlet end, another arrival end of three way cock is connected with an end of gas meter, the other end of gas meter is connected with eliminator, the three way cock port of export is connected with the pipeline that deoils, content gauge is positioned at the outer side-lower of eliminator, and the other end of oil well measurement pipeline is connected with commentaries on classics oil tank inlet by a straight-through valve, changes oil tank outlet and commentaries on classics oil pump, after one straight-through valve connects, be connected with the pipeline that deoils by straight-through valve, safety valve is positioned at top, the eliminator outside; Tap water pipeline connects control valve, electronic flow instrument, water regulating valve successively, is connected with the water injection well pipeline, and the said equipment is contained in the incubator.
The flow process of simple and easy oil-withdrawal water-injection metering device can be divided into by duty, the flow process of (well is in the metering state all the time), washing pipe line states flow process when oil well does not measure state flow journey, oil well measurement state.Below will discuss respectively the operating principle of above-mentioned flow process.
Flow process when simple and easy oil-extracting and water-injecting 2220.-metering device does not measure state, the oil well gas-liquid mixture fluid enters through single-well oil-mining pipeline, enters gathering line through three way cock, straight-through valve.The injection water that comes tap water pipeline through control valve, electronic flow instrument, water regulating valve, enter the water injection well pipeline, because of the water that injects well obtains metering by the electronic flow instrument.
When needs measured single oil well, by the three way cock switching flow, the gas-liquid mixture fluid of this well entered in the 400 type eliminators, and liquid is owing to be sunken to the eliminator bottom under the effect of gravity, and its liquid level can show by content gauge; Enter the interior liquid measure of eliminator in unit interval as calculated again, can obtain the well daily fluid production rate.Enter the gas of eliminator because density is little, the top outlet by eliminator enters the gas meter metering, can obtain this well daily output tolerance as calculated.As also measuring other well, the oil pressure in the eliminator can be gone out, this number well is switched to production status after, again other number well is switched in the eliminator.
Oil well behind the closing well, solidifies in-line in order to prevent oil well to the residual liquid in the surface line between the simple and easy metering dress in the winter time, and the liquid in it is poured to be changeed in the oil tank.Gas-liquid mixture fluid enters the commentaries on classics oil tank from gauge line (the about 0.5MPa of fluid pressure), and the natural gas body enters atmosphere from blow-down pipe.Liquid remains in to be changeed in the oil tank, and (about 0.5MPa) flows back to gauge line after gear pump boosts again, removes gathering line.
The utility model:
1, oil well measurement flow process, well flow journey have been carried out integrated design,, become intensive little cuboid flowage structure original loose long line style flowage structure.
2, the pressuring oil pipe line is designed in the eliminator bottom, make it have draining, two kinds of functions of blowdown, make eliminator need not periodical blowdown.
3, designed 2.3m 3Change the small-sized commentaries on classics oil device that oil tank and gear pump are formed, increase and change functional oil winter.
4, on the oil well measurement pipe, designed the three way cock measurement flow of corresponding one of one group of every mouthful of oil well, made gauging more convenient to operate.
(3) because the manifold of this device is shaped as the cuboid of rule, be convenient to the sealing insulation, reduced energy consumption.
(4) the one-well metering time dropped to 5-15 minute by original 40 minutes to 1 hour.
(5) the gauging operation sequence reduces 80%.
(6) replacing amounts to when closing the valve door, need not to stand full closing well, has reduced the oil well output loss.
Description of drawings
The simple and easy oil-withdrawal water-injection metering device structural representation of Fig. 1.
0-blow-down pipe 1-turns oil tank 2-triple valve 3-and turns oil pump 4-straight-through valve 5-oil well measurement pipe 6-triple valve 7-straight-through valve 8-single-well oil-mining pipeline 9-single-well oil-mining pipeline 10-400 type separator 11-safety valve 12-gas meter 13-L type triple valve 14-liquid level gauge 15-and go gathering line 16-control valve 17-well metering manifold incubator 18-well gauge line 19-electronic flow instrument 20-water regulating valve 21-to go water injection well pipeline 22-to go water injection well pipeline 23-to come water pipeline 24-straight-through valve 25-straight-through valve
The specific embodiment
Detailed in addition to simple and easy oil-withdrawal water-injection metering device structure described in the utility model with reference to the accompanying drawings below narration.
The single-well oil-mining pipeline that is connected with oil well (8), (9), be connected with three way cock (6) (2) inlet respectively, be connected with straight-through valve (7) (4) by three way cock one outlet, straight-through valve is connected with the pipeline that deoils (15), another outlet of three way cock is connected with 400 type eliminators (10) inlet by an end of oil well measurement pipeline (5), 400 type separator outlets are connected with three way cock (13) one inlets, another inlet of three way cock is connected with an end of gas meter (12), the other end of gas meter is connected with 400 type eliminators, the three way cock outlet is connected with the pipeline that deoils (15), content gauge (14) is contained in the outer side-lower of 400 type eliminators, the other end of oil well measurement pipeline (5) is connected with commentaries on classics oil tank (1) inlet by straight-through valve (24), change the oil tank outlet and change oil pump (3), after straight-through valve (25) connects, be connected with the pipeline that deoils (15) by straight-through valve (25), safety valve (11) is contained in top, the 400 type eliminators outside; Tap water pipeline (23) connects control valve (16), connect electronic flow instrument (19), water regulating valve (20), be connected by well gauge line (18) with water injection well pipeline (21) (22), blow-down pipe (0) is contained in changes the oil tank top, and the said equipment is contained in the incubator (17).

Claims (1)

1. simple and easy oil-withdrawal water-injection metering device, it is by the oil well measurement pipe, running water pipe, change oil tank, change oil pump, eliminator, incubator, content gauge, gas meter, the electronic flow instrument, safety valve, control valve, control valve, three way cock and straight-through valve are formed, it is characterized in that: the single-well oil-mining pipeline that is connected with oil well, be connected with a triple valve inlet end, be connected with a straight-through valve inlet end by three way cock one port of export, the straight-through valve port of export is connected with the pipeline that deoils, another port of export of three way cock is connected with the oil well measurement pipeline, one end of oil well measurement pipeline is connected with separator inlet, separator outlet is connected with a triple valve inlet end, another arrival end of three way cock is connected with an end of gas meter, the other end of gas meter is connected with eliminator, the three way cock port of export is connected with the pipeline that deoils, content gauge is positioned at the outer side-lower of eliminator, the other end of oil well measurement pipeline is connected with commentaries on classics oil tank inlet by a straight-through valve, change the oil tank outlet and change oil pump, after one straight-through valve connects, be connected with the pipeline that deoils by straight-through valve, safety valve is positioned at top, the eliminator outside; Tap water pipeline connects control valve, electronic flow instrument, water regulating valve successively, is connected with the water injection well pipeline, and the said equipment is contained in the incubator.
CNU2006200125440U 2006-04-28 2006-04-28 Simple oil extraction water injection metering device Expired - Lifetime CN2898293Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2006200125440U CN2898293Y (en) 2006-04-28 2006-04-28 Simple oil extraction water injection metering device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2006200125440U CN2898293Y (en) 2006-04-28 2006-04-28 Simple oil extraction water injection metering device

Publications (1)

Publication Number Publication Date
CN2898293Y true CN2898293Y (en) 2007-05-09

Family

ID=38073629

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2006200125440U Expired - Lifetime CN2898293Y (en) 2006-04-28 2006-04-28 Simple oil extraction water injection metering device

Country Status (1)

Country Link
CN (1) CN2898293Y (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101525995B (en) * 2009-04-22 2012-05-09 西安三林能源科技工程有限公司 Gas and liquid multiphase quantitative measuring device and method thereof
CN111691858A (en) * 2020-06-10 2020-09-22 中国石油天然气集团公司 Multi-well oil collecting and water distributing device for carbonate oil reservoir and using method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101525995B (en) * 2009-04-22 2012-05-09 西安三林能源科技工程有限公司 Gas and liquid multiphase quantitative measuring device and method thereof
CN111691858A (en) * 2020-06-10 2020-09-22 中国石油天然气集团公司 Multi-well oil collecting and water distributing device for carbonate oil reservoir and using method

Similar Documents

Publication Publication Date Title
CN201120256Y (en) Reverse osmosis membrane cleaning apparatus
CN202419137U (en) Bulk multi-way valve intelligent well-selecting metering station
CN106595802A (en) Method of monitoring of underground water outside deep foundation pit, warning and automatic recharge construction
CN2898293Y (en) Simple oil extraction water injection metering device
CN204960918U (en) Multi -well type oil gas metering device
CN204371273U (en) Foam drainage system for centralized foam drainage and centralized defoaming of multi-well wellhead
CN216952632U (en) Multifunctional integrated system for metering and conveying oil gas on oil well site
CN206384822U (en) A kind of tank car automatic filling equipment
CN111927430A (en) Oil well oil gas gathering, transportation, extraction, measurement and pressurization device
CN102322911B (en) Continuous metering device for produced liquid of oil well
CN210738546U (en) Well head metering device
CN2858948Y (en) Single well split meter
CN210069492U (en) Well group falls back pressure metering device
CN212272168U (en) Oil well oil gas gathering, transportation, extraction, measurement and pressurization device
CN202126288U (en) Continuous measuring device of oil well-produced liquid
CN108086968B (en) Coal bed gas cluster well skid-mounted device
CN201241684Y (en) Well head oil sand separator
CN208594917U (en) A kind of clear water water-injection station
CN109611690B (en) Well group falls back pressure metering device
CN201375976Y (en) Timed automatic ball collecting device
CN204877407U (en) Oil recovery water injection metering device
CN2758469Y (en) Polymer fillig station of single pump or multipump to multi well set
CN204247636U (en) The main skid of integration large-scale oil storage tank mechanical cleaning system is put
CN109652154B (en) Skid-mounted type integrated device and method for deoiling and dewatering natural gas
CN2869147Y (en) Waste water reusing device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20070509

EXPY Termination of patent right or utility model