CN2878522Y - Soil collection device for preformed steel reinforced concrete club-footed pile - Google Patents

Soil collection device for preformed steel reinforced concrete club-footed pile Download PDF

Info

Publication number
CN2878522Y
CN2878522Y CN 200620089022 CN200620089022U CN2878522Y CN 2878522 Y CN2878522 Y CN 2878522Y CN 200620089022 CN200620089022 CN 200620089022 CN 200620089022 U CN200620089022 U CN 200620089022U CN 2878522 Y CN2878522 Y CN 2878522Y
Authority
CN
China
Prior art keywords
earth
soil
utility
model
barrel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 200620089022
Other languages
Chinese (zh)
Inventor
王国奋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 200620089022 priority Critical patent/CN2878522Y/en
Application granted granted Critical
Publication of CN2878522Y publication Critical patent/CN2878522Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Earth Drilling (AREA)

Abstract

The utility model discloses an equipment for the substructure of construction, more particularly relating to an earth collection device for the expanded bore pile of fabricated steel concrete. The device comprises of an earth absorber (1), a soft tube (2), and a negative power supply (9) inside an earth barrel (3) on the ground. The earth is taken to the earth barrel (3) through the earth absorber (1) and the soft tube (2). The negative power supply (9) is connected with a power through a power wire (5). The earth barrel (3) is horizontal in shape. The absorption end of the earth absorber (1) may be any one of rigid round, normal bend, in-line, or flatness. The utility model, compared with prior art, is proved to be fast, clean, and complete at absorbing the earth since a series of technical measures are adopted such as the earth absorber, the soft tube, the earth barrel, and the absorptive negative power supply, thus obviously raising the execution efficiency. The device may be matched with other working procedures so as to facilitate the execution progress as well as save labor and time. Otherwise, the utility model may take dry absorption, moisture absorption, or work alternatively with these two methods. Therefore, the utility model is of wide range for application.

Description

The receipts indigenous equipment of precast reinforced concrete pile
Technical field
The utility model relates to the receipts indigenous equipment of a kind of equipment of building foundation engineering, particularly a kind of precast reinforced concrete pile, is the borrow equipment that immersed tube prefabricated steel concrete expands end first-selection, also can be used for fetching earth of other type stake.
Background technology
Along with the fast development of builing industry, especially the high building of each big and medium-sized cities stands in great numbers, and is seen everywhere and becomes one beautiful view in city, place and landmark building.Well-known these grand magnificent piles are to lean on the Foundation Design of more stable and stronger to support, thereby visible Foundation Design quality is good with bad, quality to building plays crucial effects, each unit in charge of construction especially pays attention to the quality of Foundation Design when paying attention to the superstructure quality for these reasons, expands the Foundation Design at the end for the supporting capacity that improves single pile generally adopts immersed tube prefabricated steel concrete in recent years.After the immersed tube that will have the prefabricated metal pile crown during construction is pressed into the hardpan of design elevation, take out metal pile head, bottom-expanding equipment with expanded bore pile is lowered to immersed tube location back start formation expansion base cavity pocket again, and the soil body pulverized, hang out bottom-expanding equipment, then be that people with waist tether rope is lowered to tens meters dark immersed tube bottom cleanings and expands diffusing soil in the end cavity, because narrow space, put to good use not open, the very low single pile cleaning task of fetching earth of generally finishing of operating efficiency got 24-30 hour, it is consuming time to take a lot of work, and has become the bottleneck operation of Foundation Design, has a strong impact on programming, cause the concern of some related scientific research units already, can up to the present better solution not arranged as yet regrettably, unit in charge of construction has no way out day by day, and adhering to old ways year after year constructed so far.
The utility model content
The problem that the utility model exists at prior art and provide a kind of simple in structure, easy to operate, fetch earth clean, efficient is high, reduces labour intensity, improves the receipts indigenous equipment that is used for pipe sinking prefabricated steel concrete club-footed pile of execution conditions and accelerating construction progress.
The utility model realizes that the purpose technical scheme is:
The receipts indigenous equipment of precast reinforced concrete pile, it is to be made of soil sucking head, flexible pipe and the negative pressure source that soil sucked in the Sheng soil bucket that is arranged on ground by soil sucking head, flexible pipe, negative pressure source is connected with power supply by power line, it is horizontal containing the soil bucket, and the suction side of soil sucking head is any one in rigid circular, elbow bend, in-line and the flat.
Described negative pressure source is connected with battery, and negative pressure source and battery are arranged in the soil-containing bucket cap.
Advantage of the present utility model and effect are as follows:
The utility model compared with prior art, owing to adopted a series of technical measures such as soil sucking head, flexible pipe, Sheng soil bucket and suction-type negative pressure source and had the native speed of suction totally thoroughly, obviously to improve efficiency of construction soon through evidence, and can be complementary with other operation, accelerating construction progress, when the saving of labor saves, do to inhale in addition, wet inhale or two kinds of methods are alternately united and used all rightly, be applied widely.
Description of drawings
Fig. 1 is the utility model master TV structure schematic diagram.
Fig. 2 is the A-A sectional structure schematic diagram of Fig. 1.
Among the figure 1, soil sucking head; 2, flexible pipe; 3, contain the soil bucket; 4, soil-containing bucket cap; 5, power line; 6, inhale native passage; 7, battery; 8, bracing frame; 9, negative pressure source.
The specific embodiment
Embodiment of the present utility model is described in detail in conjunction with the accompanying drawings, but protection domain of the present utility model is not limit by embodiment.
The utility model master TV structure schematic diagram as shown in Figure 1, its structure is as follows:
Containing soil bucket 3 is through the welding processing moulding by steel plate, for making them under normal conditions can all hacks that are absorbed into from base of splendid attire, do the volume of containing the staving of soil bucket 3 enough big, it is horizontal containing and being arranged on ground for native barrel 3, contain the suction soil passage 6 that is provided with a rigid tubular in the soil bucket 3, the lower end is passed the bottom of containing soil bucket 3 and is linked to each other with the upper end of flexible pipe 2, the lower end of flexible pipe 2 links to each other with soil sucking head 1, inhale native passage 6 upper ends and extend to the top of containing soil bucket 3, and fixed with at least one bracing frame 8, fall into smoothly in the Sheng soil bucket 3 for ease of the hack that sucks, inhale the upper end of native passage 6 and make the elbow shape, soil-containing bucket cap 4 spiral-locks are in the upper end of containing soil bucket 3 and keep airtight, the powerful negative pressure source of being located in the soil-containing bucket cap 49 has the structure similar to vacuum cleaner, negative pressure source 9 links to each other with power supply by power line 5, and negative pressure source 9 can also be connected with battery 7, and battery 7 also is arranged in the soil-containing bucket cap 4.Flexible pipe 2 is located at above ground portion has one section to be stereoplasm tube, and the operator holds during convenient work.
The suction side of described soil sucking head 1 is any one in rigid circular, elbow bend, in-line and the flat; Flexible pipe 2 be in flexible metal conduit and the bellows any one; Negative pressure source 9 also can link to each other with the inlet end of air compressor.
When the utility model uses, flexible pipe 2 and soil sucking head 1 are put into immersed tube up to the bottom, when starting working soil sucking head 1 contact hack for last power supply negative pressure source 9, powerful air-flow is inhaled near the soil body rapidly and contains in the soil bucket 3 by flexible pipe 2, the native passage 6 of suction, use the rear base hack will be blotted only, for the very big base of base diameter, after sopping up most of soil body, water filling in the immersed tube sopped up mud then in the past.The inhalation (inhalatio)s that powered-down will be provided with in the Sheng soil bucket 3 on ground again after the exhaustion are outwelled, and prepare operation next time.

Claims (1)

1, the receipts indigenous equipment of precast reinforced concrete pile, it is characterized in that it is to be made of soil sucking head (1), flexible pipe (2) and the negative pressure source (9) that soil sucked in the Sheng soil bucket (3) that is arranged on ground by soil sucking head (1), flexible pipe (2), negative pressure source (9) is connected with power supply by power line (5), it is horizontal containing soil bucket (3), and the suction side of soil sucking head (1) is any one in rigid circular, elbow bend, in-line and the flat.
CN 200620089022 2006-01-20 2006-01-20 Soil collection device for preformed steel reinforced concrete club-footed pile Expired - Fee Related CN2878522Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200620089022 CN2878522Y (en) 2006-01-20 2006-01-20 Soil collection device for preformed steel reinforced concrete club-footed pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200620089022 CN2878522Y (en) 2006-01-20 2006-01-20 Soil collection device for preformed steel reinforced concrete club-footed pile

Publications (1)

Publication Number Publication Date
CN2878522Y true CN2878522Y (en) 2007-03-14

Family

ID=37860937

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200620089022 Expired - Fee Related CN2878522Y (en) 2006-01-20 2006-01-20 Soil collection device for preformed steel reinforced concrete club-footed pile

Country Status (1)

Country Link
CN (1) CN2878522Y (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100383350C (en) * 2006-01-20 2008-04-23 王国奋 Soil taking apparatus for immersed tube prefabricated steel concrete under-reamed pile
CN101200906B (en) * 2006-01-20 2010-12-08 方远建设集团股份有限公司 Soil taking apparatus for immersed tube prefabricated steel concrete under-reamed pile

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100383350C (en) * 2006-01-20 2008-04-23 王国奋 Soil taking apparatus for immersed tube prefabricated steel concrete under-reamed pile
CN101200906B (en) * 2006-01-20 2010-12-08 方远建设集团股份有限公司 Soil taking apparatus for immersed tube prefabricated steel concrete under-reamed pile

Similar Documents

Publication Publication Date Title
CN2878522Y (en) Soil collection device for preformed steel reinforced concrete club-footed pile
CN2878524Y (en) Soil suction device
CN2878525Y (en) Soil suction device for basic construction
CN2878523Y (en) Construction used soil suction device
CN100383350C (en) Soil taking apparatus for immersed tube prefabricated steel concrete under-reamed pile
CN2876191Y (en) Soil collecting equipment
CN2878520Y (en) Construction used soil collection device
CN2878521Y (en) Soil collection device for basic construction
CN2878526Y (en) Soil fetching device for construction
CN101196007B (en) Borrow equipment for pipe sank prefabricated steel concrete bottom expansion pile
CN201095756Y (en) Soil sucking device
CN2876190Y (en) Soil taking equipment
CN101200906B (en) Soil taking apparatus for immersed tube prefabricated steel concrete under-reamed pile
CN201087385Y (en) Novel soil collection device for building construction
CN201087394Y (en) Soil absorption device
CN201095750Y (en) Soil collecting device for prefabricated steel concrete under-reamed pile
CN2918544Y (en) Soil taking apparatus for immersed tube prefabricated steel concrete under-reamed pile
CN201087382Y (en) Novel soil collection device for building construction
CN201087387Y (en) Novel special soil collection device for building construction
CN201095755Y (en) Special-purpose device for sucking soil
CN201095751Y (en) Soil sucking device for building
CN201095754Y (en) Special-purpose soil collecting device for prefabricated steel concrete under-reamed pile
CN201087388Y (en) Borrowing equipment for building construction
CN201095749Y (en) Foundation construction soil collecting device
CN201087391Y (en) Novel soil collection device for prefabricated steel concrete pedestal pile

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP03 Change of name, title or address

Patentee address after: 315176 Zhejiang city of Ningbo province Yinzhou District Ancient Town Village No. 21 Yang Hong Feng

Patentee address before: 315032 Ningbo Jiangbei District, Zhejiang province Zhuang Bridge Industrial Zone Xu Sheng Plastic Factory

C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee