CN2804613Y - 4t/h sub-pressure boiler - Google Patents

4t/h sub-pressure boiler Download PDF

Info

Publication number
CN2804613Y
CN2804613Y CN 200520072459 CN200520072459U CN2804613Y CN 2804613 Y CN2804613 Y CN 2804613Y CN 200520072459 CN200520072459 CN 200520072459 CN 200520072459 U CN200520072459 U CN 200520072459U CN 2804613 Y CN2804613 Y CN 2804613Y
Authority
CN
China
Prior art keywords
boiler
heater
communicated
loop
utility
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 200520072459
Other languages
Chinese (zh)
Inventor
袁克
王慈
朱霞
薛燕
臧炜
陆子龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong Wanda Boiler Co Ltd
Original Assignee
Nantong Wanda Boiler Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nantong Wanda Boiler Co Ltd filed Critical Nantong Wanda Boiler Co Ltd
Priority to CN 200520072459 priority Critical patent/CN2804613Y/en
Application granted granted Critical
Publication of CN2804613Y publication Critical patent/CN2804613Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Air Supply (AREA)

Abstract

The utility model discloses a 4t/h times high pressure boiler which comprises a boiler body, wherein a water cooling system is arranged on the boiler body, a chain grate is arranged in the boiler body and five independent wind chambers are arranged under the chain grate. Both sides of the lower part of the boiler body are provided with air inlets, a boiler chamber is arranged above the chain grate and the boiler chamber is communicated with a convection zone which is composed of convection banks. The convection banks are connected with an upper and a lower boiler barrels, and a front arch pipe is communicated with a front header tank and is communicated as a loop with the upper boiler barrel. Both side water-cooled walls are respectively communicated with a left and a right header tanks and are connected with the upper boiler barrel via a descending pipe so as to form two independent loops, a back arch pipe is connected with a back header tank and is connected as a loop with the upper and the lower boiler barrels and the rear part of the boiler body is connected with a coal economizer. The utility model has the advantages of reasonable structure and high combustion efficiency, rated capacity is 4t/h, and the utility model is suitable for the special gas use requirements of chemical industry enterprises.

Description

4t/h sub-high pressure boiler
Technical field:
The utility model relates to a kind of combustion apparatus, relates in particular to a kind of boiler.
Background technology:
Existing sub-high pressure boiler, owing to reasons such as structures, efficiency of combustion is undesirable, can not adapt to the use of II class bituminous coal.
Summary of the invention:
It is a kind of rational in infrastructure that the purpose of this utility model is to provide, the 4t/h sub-high pressure boiler that efficiency of combustion is high.
Technical solution of the present utility model is:
A kind of 4t/h sub-high pressure boiler comprises body of heater, and body of heater is provided with water-cooling system, it is characterized in that: be provided with traveling-grate stoker in the body of heater, fire grate is divided into five independent air compartments, and both sides, body of heater bottom are provided with air inlet, the fire grate top is a burner hearth, and burner hearth communicates with the convective region of being made up of convection bank; Convection bank connects upper and lower drum; Preceding arch tube communicates with preceding collection case, and is communicated with into the loop with upper drum; Respectively with about two side walls that communicate of collection case, connect into independently two loops by down-comer and upper drum; Back wall coil is connected with rear set box, and is linked to be a loop with last lower drum; The body of heater rear portion is connected with economizer.
Be provided with in the convective region and make flue gas be the partition wall that broken line flows.
The utility model is rational in infrastructure, the efficiency of combustion height, and rated capacity is 4t/h, adapts to the special in the gas needs of chemical enterprise.
Description of drawings:
The utility model is described in further detail below in conjunction with drawings and Examples.
Fig. 1 is the configuration diagram of an embodiment of the utility model.
Fig. 2 is the A-A view of Fig. 1.
Fig. 3 is the vertical view of Fig. 1.
The specific embodiment:
A kind of 4t/h sub-high pressure boiler comprises body of heater 1, and body of heater 1 is provided with water-cooling system, be provided with traveling-grate stoker 2 in the body of heater 1, fire grate 2 is divided into five independent air compartments, and both sides, body of heater bottom are provided with air inlet, fire grate 2 tops are burner hearth 6, and burner hearth 6 communicates with the convective region of being made up of convection bank 7; Convection current 7 tube banks connect upper and lower drum 8,9; Preceding arch tube 10 communicates with preceding collection case 11, and is communicated with into the loop with upper drum 8; Respectively with about two side walls 14,15 that communicate of collection case 12,13, connect into independently two loops by down-comer and upper drum 8; Back wall coil 16 is connected with rear set box 4, and is linked to be a loop with last lower drum 8,9; The body of heater rear portion is connected with economizer 5.Be provided with in the convective region and make flue gas be the partition wall 3 that broken line flows.Also has coal bunker 17 among the figure.

Claims (2)

1, a kind of 4t/h sub-high pressure boiler comprises body of heater, and body of heater is provided with water-cooling system, it is characterized in that: be provided with traveling-grate stoker in the body of heater, fire grate is divided into five independent air compartments, and both sides, body of heater bottom are provided with air inlet, the fire grate top is a burner hearth, and burner hearth communicates with the convective region of being made up of convection bank; Convection bank connects upper and lower drum; Preceding arch tube communicates with preceding collection case, and is communicated with into the loop with upper drum; Respectively with about two side walls that communicate of collection case, connect into independently two loops by down-comer and upper drum; Back wall coil is connected with rear set box, and is linked to be a loop with last lower drum; The body of heater rear portion is connected with economizer.
2,4t/h sub-high pressure boiler according to claim 1 is characterized in that: setting makes flue gas be the partition wall that broken line flows in the convective region.
CN 200520072459 2005-06-09 2005-06-09 4t/h sub-pressure boiler Expired - Fee Related CN2804613Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200520072459 CN2804613Y (en) 2005-06-09 2005-06-09 4t/h sub-pressure boiler

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200520072459 CN2804613Y (en) 2005-06-09 2005-06-09 4t/h sub-pressure boiler

Publications (1)

Publication Number Publication Date
CN2804613Y true CN2804613Y (en) 2006-08-09

Family

ID=36909902

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200520072459 Expired - Fee Related CN2804613Y (en) 2005-06-09 2005-06-09 4t/h sub-pressure boiler

Country Status (1)

Country Link
CN (1) CN2804613Y (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103267276A (en) * 2013-05-31 2013-08-28 冀州市华昌机械厂 Coalification deep processing heating equipment
CN105042572A (en) * 2015-08-31 2015-11-11 衡阳市大成锅炉有限公司 Boiler capable of effectively lowering nitrogen oxide emission

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103267276A (en) * 2013-05-31 2013-08-28 冀州市华昌机械厂 Coalification deep processing heating equipment
CN103267276B (en) * 2013-05-31 2017-05-24 河北齐工环保科技有限公司 Coalification deep processing heating equipment
CN105042572A (en) * 2015-08-31 2015-11-11 衡阳市大成锅炉有限公司 Boiler capable of effectively lowering nitrogen oxide emission

Similar Documents

Publication Publication Date Title
CN105164469B (en) Include the fluidized-bed combustion boiler of multifunctional inertia gravity separator
CN201148443Y (en) AOD converter flue gas waste heat recovery device
CN2804613Y (en) 4t/h sub-pressure boiler
CN201795467U (en) Corner tube boiler capable of reducing accumulated ash, sunken ash and dew point ash of heating surface
CN204787217U (en) Large -scale gas boiler of high -efficient forced circulation of support formula
CN102679309B (en) 350MW MW supercritical W flame anthracite boiler
CN205897085U (en) Bubbling fluidized bed boiler of burming biomass granule
CN202013015U (en) Vertical half gas positive burning heating boiler
CN2849577Y (en) Radiation heated surface structure for large horizontal square box coal burning organic heat carrier boiler
CN2935003Y (en) Single drum horizontal type coal hot water boiler with boiler shell coal-saver angle pipe support structure
CN201892198U (en) Efficient waste-heat boiler
CN201476291U (en) Hot water boiler
CN101761914B (en) Smoke circulation heat-exchange compound cycle water pipe steam boiler
CN2754005Y (en) Coal-fired superconducting dual combustion chamber boiler
CN206817521U (en) The burner hearth of biomass fired boiler
CN2869588Y (en) Vertical after-heat boiler
CN101191661A (en) Five-barrel longitudinal positioned type large-sized layer combustion water tube boiler
CN101187501A (en) Low discharge high energy efficiency vertical shell type water-fire tube boiler
CN100561041C (en) A kind of large-sized natural circulation boiler with water pipe
CN107654990A (en) A kind of vertical corner tube type bubbling bed boiler
CN2382952Y (en) Vertical internal combustion wet back type fire-tube coal burning boiler
CN108332417B (en) Forced circulation hot water boiler
CN1670443A (en) Energy-saving low-discharge heating boiler
CN2789677Y (en) New heating furnace liner for vacuum heating furnace
CN2337399Y (en) Energy-saving verticle fire-tube boiler

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20060809

Termination date: 20130609