Summary of the invention:
The purpose of this utility model be at above-mentioned technological deficiency put forward a kind of rational in infrastructure, welding quality good, welding junction intensity height, bearing capacity are big, can be applicable to the adding pressure type electric smelting welder in extra-high-speed, superhigh molecular weight polyethylene pipe road.
The technical solution of the utility model is such: the adding pressure type electric smelting welder in a kind of extra-high-speed, superhigh molecular weight polyethylene pipe road, be to be provided with inner support in the pipeline the inside of required welding, plastic pipe hoop at the pipeline outside of need welding cover certain-length, between the outer wall of the inwall of plastics hoop and required welding, lay heater strip, double team outside install the outside of plastics hoop, tighten up outer double team or enlarge inner support and form pressure, under uniform temperature and pressure, plastics hoop and required welded pipe line melt to one, are closely linked after cooling.
Utilize interface duct thickness that the utility model method welds out greater than pipeline itself, in that its bearing capacity is bigger than pipeline (material) itself under similar circumstances.Because the three merges fully, so sealing is also good than general butt welding mode, is particularly suitable for the high situation of those sealing requirements bearing requirements.
The specific embodiment:
As figure, the pipeline in required welding of device described in the utility model (4) lining is provided with inner support (1), plastics hoop (2) at the outside cover certain-length of the pipeline (4) of need welding, the heating wire (5) that between the outer wall of the inwall of plastics hoop (2) and required welded pipe line, distributes, double team (3) outside install the outside of plastics hoop (2).Wherein,
Described inner support (1) be can be for convenience detach inner ring, or fixing inner ring.
Described inner support (1) can be adjustment of tonicity, but also adjustment of tonicity not.
Described plastics hoop (2) is a whole circle, or forms a whole circle by some blocks of plastics.
Described plastics hoop (2) is the plastic products of certain girth and certain width; Its inwall girth is more than or equal to 1/2 times and smaller or equal to the outer wall girth of 1 times of soldered pipeline (4); Its width is 1/10-1000 a times of soldered pipeline (4) wall thickness.
Described heating wire (5) is laid in interface outer wall that needs welded pipe line (4) or the inwall that is laid in plastics hoop (2).
Heating wire (5) can be laid simultaneously at the outer wall of need welded pipe line (4), the inwall of plastics hoop (2).
Described outer double team (3) is one can regulate the outer double team of pressure, or one is exerted pressure in advance and fixes dead outer double team then.
Described outer double team (3) is one can regulate the outer double team of pressure, or one is exerted pressure in advance and fixes dead outer double team then.
Described outer double team (3) is one can regulate the outer double team of pressure, or one is exerted pressure in advance and fixes dead outer double team then.
When the plastics hoop is not a whole circle, but a plurality of unit of plastic is when forming, can the cloth silk between the unit of plastic that then is connected also cloth silk not.
The purpose of this utility model is achieved in that at first places an inner support in the pipeline (material) of required welding, and required welding junction to together, hoop (or several unit of plastics) is arranged in the outside of required welded pipe line, heating wire on the cloth between them, add the outer double team that to regulate pressure in hoop (or several unit of plastics) outside again, the energising heater strip is regulated outer double team simultaneously, makes hoop and required welding junction be subjected to certain pressure; Regulate temperature value, hoop (or some unit of plastics) and institute's welding junction are at high temperature melted, plastics hoop and institute's welding junction just are integrated, the cooling aftershaping.Because the existence of pressure increases the density of tubing, thereby guaranteed the quality of the weld seam that welds out.For example: some need under the situation of high temperature pressure, by this welding method, can guarantee the weld seam good airproof performance that welds out, and bearing capacity is strong, can be widely used in coal gas, feedwater, oil, chemical industry, mine, blowdown, river course and dredge fields such as person of outstanding talent, slurry transportation.