- CN2477804Y CN2477804Y CN 00252754 CN00252754U CN2477804Y CN 2477804 Y CN2477804 Y CN 2477804Y CN 00252754 CN00252754 CN 00252754 CN 00252754 U CN00252754 U CN 00252754U CN 2477804 Y CN2477804 Y CN 2477804Y
- Authority
- CN
- China
- Prior art keywords
- well
- liner tube
- pipe lining
- inner sleeve
- wells
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Abstract
The utility model provides a well completion device used to complete a branch well with an oil drilling lateral liner tube for the development and use of old oil wells in an oil field. The technical proposal of the utility model is that a plurality of branch wells are drilled in a main well to achieve the purpose of preventing the branch wells from connecting with each, ensuring the stability and reliability of the side drilling operation. The utility model increases the unit output of oil and natural gas from a single well, improves the overall production, and has the advantages of low cost and obvious economic benefit. The device arranges a liner tube in each side well, strengthens the branch well so that all the liner tubes and the internal casings form a rigid body, avoids the mutual influence of the branch wells in the main well, prevents the branch wells from connecting each other easily, and ensures the reliability and stability of the side drilling operation. The device can be widely used for the development and use of old wells in an oil field.
Description
The utility model provides a kind of oil drilling lateral liner tube Multilateral Wells completion system of oilfield old well development and use.
Along with the development of petroleum drilling technology, Oilfield using is beaten a plurality of Multilateral Wells in a main borehole at present, to improve the well yield of petroleum and natural gas, reduces drilling cost.But Multilateral Wells construction technology complexity depends primarily on the structure of completion tool.Conventional sidetracked hole mainly divides the sleeve pipe forging to mill sidetracked hole and casing window sidetracking well.Because conventional sidetracked hole has only a side well, and the casing hanger of side well is on the sleeve pipe of main borehole.But under the situation of a plurality of side wells, be unallowed, so both influenced the unimpeded of main borehole, make each casing not have rational suspension place again.Therefore, influence the development of drilling well new technology.
At above-mentioned the problems of the prior art, the purpose of this utility model is to overcome deficiency of the prior art and a kind of oil drilling lateral liner tube Multilateral Wells completion system is provided, it has solved the problem that can beat a plurality of Multilateral Wells in a main borehole, it has not only solved a plurality of Multilateral Wells sleeve pipes rational suspension place, make main borehole unimpeded, and can be implemented in the main borehole and beat a plurality of Multilateral Wells, improve the well yield of petroleum and natural gas, reduce drilling cost.
The utility model is achieved in that at first from market or oilfield material department buys material requested and component by accompanying drawing and designing requirement; At first make inner sleeve 1, baffle ring 2, pipe lining 3, lateral liner tube 4, sealing-plug 5 by Fig. 1, the fluid sealant 7 with elastic steel sheet is made the husband of sister 6, feather key 8 and bought connects them; As Fig. 1 baffle ring 2 and inner sleeve 1, pipe lining 3 welds respectively with lateral liner tube 4, pipe lining 3 tops link to each other by the husband of sister 6 with inner sleeve 1, and the husband of sister 6 is welded to connect with inner sleeve 1, pipe lining 3 respectively, the end of each lateral liner tube 4 is provided with sealing-plug 5, and above-mentioned parts is assembled lateral liner tube Multilateral Wells completion system; Then in oil well, forge the miller tool down, mill the main borehole sleeve pipe of a segment length at certain depth, sleeve pipe 17 and setting of casing 9 descend the reaming hole instrument again in the formation, carry out the reaming hole operation forging the well section of milling, thereby reserved a hole in the down-hole, directed packer then, directed packer are mainly by directed seat envelope body 15, slips 14, sealing cup 13, fixed several feather keys 12 are formed.Certain position under the directed packer in setting of casing 9 carries out the operation of seat envelope, itself and setting of casing 9 is connected together by slips 14 , and positioning and guiding key 12, fixes on the certain orientation; Following lateral liner tube Multilateral Wells completion system, one guiding keyway is arranged in the bottom of this device, the guiding keyway snaps in the positioning and guiding key 12 during to packer top, location under this device, make its location as Fig. 3, lower center tube 16 then, it is that it extrudes lateral liner tube 4 during by this device that central tube 16 mainly contains two effects one, makes pipe lining 3 crowded being posted on the baffle ring 2; Owing to scribble fluid sealant 7 on the bushing pipe 3, pipe lining 3 passes through fluid sealant 7 sealings with baffle ring 2.The 2nd, 16 pairs of forgings of central tube are milled, the annular injection behind the reaming hole is gone into cement 10, make the lateral liner tube of all extruding all obtain solidifying, after cement 10 solidifies as can be seen from Figure 2, central tube 16 has tripped out the performance of inner sleeve 1, this device just can be paid drillng operation after above-mentioned operation was finished, and next directed wedge deflection tool of elder generation descends drilling tool to carry out drillng operation then before drilling well, bore a Multilateral Wells with regard to next time branch joint 11, had the several branch well just to repeat operation several times.
The utility model is compared with prior art: have each side well all in lateral liner tube, and pre-well cementation makes all lateral liner tubes and inner sleeve all form rigid body, adopting this device to have each Multilateral Wells is independent of each other in main borehole, be difficult for channelling between each Multilateral Wells, stability and good reliability in the sidetracking construction; Solved the well yield problem that improves petroleum and natural gas owing to beat a plurality of Multilateral Wells in a main borehole, it not only reduces drilling cost, and improves oil, gas production, remarkable in economical benefits.
Fig. 1 is a lateral liner tube Multilateral Wells completion system overall structure schematic diagram, and 1 is inner sleeve, the 2nd among the figure, baffle ring, the 3rd, bushing pipe, the 4th, lateral liner tube, the 5th, sealing-plug, the 6th, the husband of sister, the 7th, fluid sealant, the 8th, feather key.
Fig. 2 is that schematic diagram is finished in the construction of lateral liner tube Multilateral Wells completion system, and figure state 1 is an inner sleeve, the 2nd, baffle ring, the 3rd, pipe lining, the 4th, lateral liner tube, 5 sealing-plugs, the 6th, the husband of sister, the 8th, feather key, the 9th, setting of casing, the 10th, cement, the 11st, branch joint, the 17th, last sleeve pipe.
Fig. 3 is a lateral liner tube Multilateral Wells completion system construction schematic diagram, and 1 is inner sleeve, the 4th among the figure, lateral liner tube, the 8th, feather key, the 9th, setting of casing, the 10th, cement, the 12nd, positioning and guiding key, the 13rd, sealing cup, the 14th, slips, the 15th, directed seat envelope body,, the 16th, central tube, the 17th, last sleeve pipe.
Embodiment is described in conjunction with the accompanying drawings: at first by designing requirement from market or oilfield material department buy material requested and component, pressing Fig. 1 makes: make inner sleeve 1 with the sleeve in oil field material, lateral liner tube 4, make baffle ring 2 with common iron, pipe lining 3, feather key 8, make sealing-plug 5 with plastics or cast aluminium, make the husband of sister 6 with elastic steel sheet, adopt the fluid sealant of buying 7, they are connected by Fig. 1: the side opening outside that baffle ring 2 is welded on inner sleeve 1, the pipe lining 3 and the side opening of inner sleeve 1 are matched, lateral liner tube 4 is welded on the pipe lining 3 by design angle, pipe lining 3 is to link to each other by the husband of sister 6 that elastic steel sheet is made with inner sleeve 1, an end of the husband of sister 6 is welded on the upper opening portion of inner sleeve 1, and at its underpart welding feather key 8, end is welded on the upper end of pipe lining 3 in addition, the end of lateral liner tube 4 is provided with the sealing-plug 5 that can bore out, also be provided with the step of a undergauge in its end, make casing head be suspended on this step when being used for setting of casing, after extruding the pipe lining, pipe lining mouth can not be out of shape being provided with on the inner sleeve 1, pipe lining 3 outward flanges (closing part with baffle ring 2 cards) are covered with fluid sealant 7, and above-mentioned parts is assembled lateral liner tube Multilateral Wells completion system; Then in oil well, forge the miller tool down, mill the main borehole sleeve pipe of one section design length at certain depth, sleeve pipe 17 and setting of casing 9 in the formation, the well section of descending the reaming hole instrument that forging is milled is again carried out the reaming hole operation, thereby reserved a hole in the down-hole, directed packer then, directed packer mainly are made up of directed seat envelope body 15, slips 14, sealing cup 13, directed feather key 12.The operation of the capable seat envelope of certain position under the directed packer in setting of casing 9, itself and setting of casing 9 are riveted together by slips 14, and positioning and guiding key 12, fix on the certain orientation, following lateral liner tube Multilateral Wells completion system, one guiding keyway is arranged in the bottom of this device, the guiding keyway snaps in the positioning and guiding key 12 during to packer top, location under this device, make its location as Fig. 3, lower center tube 16 then, it has two effects, extrudes lateral liner tube 4 when necessarily it is by this device, pipe lining 3 is squeezed be posted on the baffle ring 2; Because pipe serves as a contrast on 3 and scribbles fluid sealant 7, pipe lining 3 seals by fluid sealant 7 with lower baffle ring 2.The 2nd, 16 pairs of forgings of central tube are milled, annular injection behind the reaming hole is gone into cement (cementing concrete) 10, make the lateral liner tube of all extruding all obtain solidifying, after cement 10 solidified as can be seen from Figure 2, central tube 16 had tripped out the performance of inner sleeve 1, after above-mentioned operation is finished, this device just can be paid drillng operation, and next directed wedge deflection tool of elder generation creeps into capable drillng operation then down before drilling well, bore a Multilateral Wells with regard to next time branch joint 11, had the several branch well just to repeat several times.
Claims (1)
1, a kind of oil drilling lateral liner tube Multilateral Wells completion system of oilfield old well development and use is characterized in that:
A, baffle ring (2) is welded on the side opening outside of inner sleeve (1), the pipe lining (3) and the side opening of inner sleeve (1) are matched, lateral liner tube (4) is welded on the pipe lining (3) by design angle, pipe lining (3) is to link to each other by the husband of sister (6) that elastic steel sheet is made with inner sleeve (1), the husband of sister's (6) a end is welded on the upper opening portion of inner sleeve (1), and at its underpart welding feather key (8), end is welded on the upper end of pipe lining (3) in addition;
B, the end of lateral liner tube (4) is provided with the sealing-plug (5) that can bore out also is provided with a undergauge in its end step;
C is provided with pipe lining window on inner sleeve (1);
D, pipe lining 3 outward flanges (with baffle ring 2 fitting parts) are covered with fluid sealant 7.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 00252754 CN2477804Y (en) | 2000-11-02 | 2000-11-02 | Side liner-type well completion appts. of branching well |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 00252754 CN2477804Y (en) | 2000-11-02 | 2000-11-02 | Side liner-type well completion appts. of branching well |
Publications (1)
Publication Number | Publication Date |
---|---|
CN2477804Y true CN2477804Y (en) | 2002-02-20 |
Family
ID=33610340
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 00252754 Expired - Fee Related CN2477804Y (en) | 2000-11-02 | 2000-11-02 | Side liner-type well completion appts. of branching well |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN2477804Y (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102124180A (en) * | 2007-08-30 | 2011-07-13 | 普拉德研究及开发股份有限公司 | Dual bha drilling system |
CN102852460A (en) * | 2012-08-31 | 2013-01-02 | 吉林大学 | Downhole deflecting device for drilling ice layer of polar region and downhole deflecting method |
-
2000
- 2000-11-02 CN CN 00252754 patent/CN2477804Y/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102124180A (en) * | 2007-08-30 | 2011-07-13 | 普拉德研究及开发股份有限公司 | Dual bha drilling system |
CN102124180B (en) * | 2007-08-30 | 2014-05-14 | 普拉德研究及开发股份有限公司 | Dual BHA drilling system |
CN102852460A (en) * | 2012-08-31 | 2013-01-02 | 吉林大学 | Downhole deflecting device for drilling ice layer of polar region and downhole deflecting method |
CN102852460B (en) * | 2012-08-31 | 2014-11-05 | 吉林大学 | Downhole deflecting device for drilling ice layer of polar region and downhole deflecting method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101906946B (en) | Hydraulic expansion-type rotary liner hanger | |
CN101413384A (en) | Method for sealing branch well window by using metal expansion pipe | |
CN201232532Y (en) | Hydraulic combination window opening tool | |
CN201705252U (en) | Hydraulic expansion type rotating liner hanger | |
CN2477804Y (en) | Side liner-type well completion appts. of branching well | |
CN2700556Y (en) | Wireline steering tool for horizontal well with ultra-short radius | |
CN105401931B (en) | A kind of sliding sleeve of bushing fracturing integrated pipe column and its fracturing method | |
CN209556950U (en) | The equal diameter drilling well coiled tubing connector of enlarged outside diameter | |
CN207377510U (en) | Coiled tubing slips connects integrated tool of giving up | |
CN208417841U (en) | A kind of stock joint brazing structure | |
CN101718170B (en) | Preformed six-stage branch well system tool | |
CN113931591B (en) | Top-recyclable whipstock and application method thereof | |
CN205135416U (en) | Inflation formula tail pipe drilling operation device | |
CN205243458U (en) | High temperature resistant big latus rectum hydraulic pressure reinforcement inflation hangs instrument | |
CN103806862B (en) | reliable hanging packer | |
CN2651429Y (en) | Compensative hot producing packer | |
CN206707644U (en) | Hydraulic casing centralizer | |
CN205955693U (en) | Easy compound bridging plug of brill formula | |
CN2816342Y (en) | Cement-filling type packer | |
CN201810204U (en) | Preformed six-stage multilateral well system tool | |
CN106320998A (en) | Horizontal well technique pipe and casing hanger releasing method for same | |
CN2736529Y (en) | Sand proof packing tool | |
CN201606005U (en) | Temporary seal structure with pored casing tube for cementing and completing lateral wells | |
CN2154904Y (en) | Sleeve connector | |
CN2929156Y (en) | Oil-water well casing tandem connector |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C19 | Lapse of patent right due to non-payment of the annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |