CN2421312Y - Preburied plastic sleeve and screw spike for concrete sleeper - Google Patents

Preburied plastic sleeve and screw spike for concrete sleeper Download PDF

Info

Publication number
CN2421312Y
CN2421312Y CN 99250407 CN99250407U CN2421312Y CN 2421312 Y CN2421312 Y CN 2421312Y CN 99250407 CN99250407 CN 99250407 CN 99250407 U CN99250407 U CN 99250407U CN 2421312 Y CN2421312 Y CN 2421312Y
Authority
CN
China
Prior art keywords
screw spike
plastic bushing
concrete sleeper
buried plastic
spike
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 99250407
Other languages
Chinese (zh)
Inventor
李桂成
傅振馗
林茂春
刘忠惠
阎富生
苏厚庆
张永学
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anshan public works equipment factory
Original Assignee
ANSHAN PERMANENT WAY EQUIPMENT FACTORY MINISTRY OF RAILWAYS
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ANSHAN PERMANENT WAY EQUIPMENT FACTORY MINISTRY OF RAILWAYS filed Critical ANSHAN PERMANENT WAY EQUIPMENT FACTORY MINISTRY OF RAILWAYS
Priority to CN 99250407 priority Critical patent/CN2421312Y/en
Application granted granted Critical
Publication of CN2421312Y publication Critical patent/CN2421312Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model relates to a prestressed concrete sleeper, which is additionally provided with an anchor device. A spike used by the concrete needs to be done insulating treatment with the concrete sleeper; the anchor device is a member specially used in a prestressed structure, and is a reinforcing member which can be manufactured with materials except steel, such as a reinforcing structural member manufactured with glass and plastic or incompletely manufactured with steel; the inner of a concrete sleeper body is provided with a pre-embedded plastic casing pipe, and the inner of the pre-embedded plastic casing pipe is provided with a screw thread spike. The screw thread spike has the advantages of easy and quick disassembly, simple and compact structure, low cost, etc., the operation cycle of laying track and laying sleeper can be shortened, and the service life of the concrete sleeper can be prolonged.

Description

A kind of pre-buried plastic bushing and screw spike of concrete sleeper
The utility model relates to the prestressed reinforced concrete tie that sleeper adds anchor device; Railway spike that concrete is used needs and sleeper be done insulation and handles, railway spike top can supporting clamping element direct fixing rail on sleeper; Anchor device is specifically designed to the member in the prestressed structure, anchor device uses the reinforcement of the other materials making except that steel as using glass, the pre-buried plastic bushing and the screw spike of plastics or the reinforcing structural members, particularly a kind of concrete sleeper not exclusively done with steel.
The railroad sleeper member mostly is that the screw spike that adopts is fixed in the concrete crosstie with the sulphur grappling at present, ubiquity concrete sleeper and is needed prefabricated preset hole, adopt sulphur that the screw spike grappling is fixed in the sleeper, the generation longitudinal splitting is scrapped whole sleepers between two preformed holes owing to the sulphur volume expansion causes concrete sleeper to be everlasting, screw spike can't be dismantled when sleeper is scrapped, complicated cumbersome cost is higher when changing the concrete sleeper construction, need a large amount of man-hours of waste and expense, the intact screw spike local damage of concrete sleeper screw spike grappling fixing back sleeper need be changed screw spike particularly outstanding difficulty inconvenience especially, waste time and energy, it is comparatively serious when the operation of the sulphur of being grappling retaining thread railway spike is arranged again to environment generation pollution, the screw spike grappling is fixing need be bigger at the required occupation of land site area of construction of railways field operation, the longer construction operation efficient of pillow cycle of laying a railway track is lower, the concrete sleeper bulk strength is relatively poor, weight capacity is lower, stability and shock resistance are relatively poor, the application life of concrete sleeper is lower, the shortcomings such as normal running speed of railway transportation of having changed concrete sleeper amount considerable influence, for overcoming above-mentioned existing weak point, the utility model has designed a kind of pre-buried plastic bushing and screw spike of concrete sleeper.
The purpose of this utility model provides a kind of screw spike convenient disassembly of concrete sleeper, it is simply simple and efficient to change the concrete sleeper construction, time saving and energy saving, shortening lays a railway track rests the head on duty cycle, improve construction operation efficient, improve bulk strength, weight capacity, stability and the shock resistance of concrete sleeper, improve and prolong concrete sleeper application life, the pre-buried plastic bushing and the screw spike of concrete sleeper.
The utility model is achieved in that and is separately installed with four pre-buried plastic bushings in the concrete sleeper body, pre-buried plastic bushing is socket shape for highstrenghtpiston's material, on the outside wall surface of pre-buried plastic bushing, be cast with anti-skidding enhancing circular arc line, on the interior sidewall surface of pre-buried plastic bushing, be cast with down cup type wood snail line, pre-buried plastic bushing outer wall is cast contact mutually with the concrete sleeper body and is one precast construction part, in the pre-buried plastic bushing of concrete sleeper body, be rotatably installed with screw spike, screw spike is cylindrical, upper segment at screw spike has regular screw threads, have at the middle part of screw spike be hexagonal square screw boss, the lower face cover that screws boss at the screw spike middle part is equipped with seal washer, the lower section of screw spike have with pre-buried plastic bushing interior sidewall surface on correspondingly fall cup type wood snail line, the screw spike lower section is fallen cup type wood snail line and falling of the pre-buried plastic bushing interior sidewall surface cup type wood snail line phasing that is fastened and is contacted, and anchor ring contacts on the seal washer lower face that the screw spike middle part screws the boss lower face and the pre-buried plastic bushing.
The utility model has been avoided because of the sulphur volume expansion causes concrete sleeper to produce longitudinal splitting whole sleepers being scrapped with sulfur cement mortar anchorage method retaining thread railway spike, screw spike convenient disassembly when sleeper is scrapped, simple cost is lower when changing the concrete sleeper construction, a large amount of man-hours of waste and expense have been avoided, it is simple and efficient particularly outstanding when the intact screw spike local damage of concrete sleeper need be changed screw spike, time saving and energy saving, environmentally safe, the required occupation of land site area of construction of railways field operation is less, having shortened lays a railway track rests the head on duty cycle, construction operation efficient is greatly improved, improved the bulk strength of concrete sleeper, weight capacity, stability and shock resistance, improve the application life that has prolonged concrete sleeper, the expense and the operating cost that switches tracks of year replacing concrete sleeper have been reduced, it is less to change concrete sleeper and screw spike amount, avoid and reduced influence the railway transportation normal running speed, the economic results in society effect is obviously remarkable, screw spike is fixedly connected easy for installation simple when construction, reduced the consumption of material, easy to maintenance, safe and reliable, and it is simple and compact for structure, it is easy to be easy to manufacture craft, be easy to promote and use, advantage such as with low cost.
Concrete structure of the present utility model and embodiment are provided by the following drawings.
Fig. 1 is a general structure schematic diagram of the present utility model;
Fig. 2 is an A-A part section structural representation of the present utility model.
To be described in further detail concrete structure of the present utility model and embodiment below in conjunction with accompanying drawing.
Referring to accompanying drawing 1, shown in Figure 2: as in concrete sleeper body 1, to be separately installed with four pre-buried plastic bushings 4, pre-buried plastic bushing 4 is socket shape for highstrenghtpiston's material, on the outside wall surface of pre-buried plastic bushing 4, be cast with anti-skidding enhancing circular arc line, on the interior sidewall surface of pre-buried plastic bushing 4, be cast with down cup type wood snail line, pre-buried plastic bushing 4 outer walls are cast contact mutually with concrete sleeper body 1 and are one precast construction part, in concrete sleeper body 1 pre-buried plastic bushing 4, be rotatably installed with screw spike 2, screw spike 2 is cylindrical, upper segment at screw spike 2 has regular screw threads, have at the middle part of screw spike 2 be hexagonal square screw boss 3, the lower face cover that screws boss 3 at screw spike 2 middle parts is equipped with seal washer 5, the lower section of screw spike 2 have with pre-buried plastic bushing 4 interior sidewall surface on correspondingly fall cup type wood snail line, screw spike 2 lower section are fallen cup type wood snail line and falling of the pre-buried plastic bushing 4 interior sidewall surface cup type wood snail line phasing that is fastened and are contacted, and seal washer 5 lower faces that screw spike 2 middle parts screw boss 3 lower faces contact with pre-buried plastic bushing 4 upper end anchor rings.

Claims (2)

1, a kind of pre-buried plastic bushing and screw spike of concrete sleeper, it is by concrete sleeper body (1), pre-buried plastic bushing (4), screw spike (2) and seal washer (5) are formed, it is characterized in that: have four pre-buried plastic bushings (4) in the concrete sleeper body (1) respectively, pre-buried plastic bushing (4) is socket shape, on the outside wall surface of pre-buried plastic bushing (4), has anti-skidding enhancing circular arc line, on the interior sidewall surface of pre-buried plastic bushing (4), has down cup type wood snail line, pre-buried plastic bushing (4) outer wall is cast contact mutually with concrete sleeper body (1) and is one precast construction part, in the pre-buried plastic bushing of concrete sleeper body (1) (4), has screw spike (2), screw spike (2) is cylindrical, upper segment at screw spike (2) has regular screw threads, have at the middle part of screw spike (2) be hexagonal square screw boss (3), the lower face that screws boss (3) at screw spike (2) middle part has seal washer (5), the lower section of screw spike (2) have with pre-buried plastic bushing (4) interior sidewall surface on correspondingly fall cup type wood snail line, screw spike (2) lower section is fallen the cup type wood snail line phasing that is fastened that falls of cup type wood snail line and pre-buried plastic bushing (4) interior sidewall surface and is contacted, and anchor ring contacts on seal washer (5) lower face that screw spike (2) middle part screws boss (3) lower face and the pre-buried plastic bushing (4).
2, the pre-buried plastic bushing and the screw spike of concrete sleeper according to claim 1 is characterized in that: pre-buried plastic bushing (4) is highstrenghtpiston's material.
CN 99250407 1999-11-29 1999-11-29 Preburied plastic sleeve and screw spike for concrete sleeper Expired - Fee Related CN2421312Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 99250407 CN2421312Y (en) 1999-11-29 1999-11-29 Preburied plastic sleeve and screw spike for concrete sleeper

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 99250407 CN2421312Y (en) 1999-11-29 1999-11-29 Preburied plastic sleeve and screw spike for concrete sleeper

Publications (1)

Publication Number Publication Date
CN2421312Y true CN2421312Y (en) 2001-02-28

Family

ID=34035148

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 99250407 Expired - Fee Related CN2421312Y (en) 1999-11-29 1999-11-29 Preburied plastic sleeve and screw spike for concrete sleeper

Country Status (1)

Country Link
CN (1) CN2421312Y (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101974872A (en) * 2010-10-14 2011-02-16 中铁三局集团有限公司 Device and method for fixing track plate and cement emulsified asphalt slurry template
CN101787667B (en) * 2009-01-22 2011-12-28 尹学军 Easy-maintenance floating ballast bed
CN102713065A (en) * 2009-12-09 2012-10-03 福斯洛工厂有限责任公司 Screw anchor for rail attachments
CN104704172A (en) * 2012-08-22 2015-06-10 沃斯洛工厂有限公司 Plastic plug for securing a rail
CN105019317A (en) * 2014-04-17 2015-11-04 宁波曙翔新材料股份有限公司 Pre-embedded sleeve and method thereof
CN108221506A (en) * 2018-02-27 2018-06-29 中铁二院工程集团有限责任公司 It is a kind of to reduce railway roadbed hurt and direct burial fastener system easy to install

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101787667B (en) * 2009-01-22 2011-12-28 尹学军 Easy-maintenance floating ballast bed
CN102713065A (en) * 2009-12-09 2012-10-03 福斯洛工厂有限责任公司 Screw anchor for rail attachments
CN102713065B (en) * 2009-12-09 2015-07-08 福斯洛工厂有限责任公司 Screw anchor for rail attachments
CN101974872A (en) * 2010-10-14 2011-02-16 中铁三局集团有限公司 Device and method for fixing track plate and cement emulsified asphalt slurry template
CN101974872B (en) * 2010-10-14 2012-04-18 中铁三局集团有限公司 Device and method for fixing track plate and cement emulsified asphalt slurry template
CN104704172A (en) * 2012-08-22 2015-06-10 沃斯洛工厂有限公司 Plastic plug for securing a rail
CN105019317A (en) * 2014-04-17 2015-11-04 宁波曙翔新材料股份有限公司 Pre-embedded sleeve and method thereof
CN105019317B (en) * 2014-04-17 2017-02-15 宁波曙翔新材料股份有限公司 Pre-embedded sleeve and method thereof
CN108221506A (en) * 2018-02-27 2018-06-29 中铁二院工程集团有限责任公司 It is a kind of to reduce railway roadbed hurt and direct burial fastener system easy to install
CN108221506B (en) * 2018-02-27 2024-01-05 中铁二院工程集团有限责任公司 Direct-buried fastener system capable of reducing track bed injury and easy to install

Similar Documents

Publication Publication Date Title
CN201495454U (en) High-speed railway plate type ballastless track longitudinal connecting structure
CN2421312Y (en) Preburied plastic sleeve and screw spike for concrete sleeper
CN103485270A (en) Setting technology of second-phase pre-stressed tendons in straddle type single-traffic-track girder bridge
CN206859423U (en) A kind of fabricated shear wall mid-side node
CN2661748Y (en) Plastic casing for concrete sleeper
CN114086435B (en) Full-assembled prefabricated plate type track structure
CN215947749U (en) Prefabricated assembled ballast bed
CN215104799U (en) Town road bridge crack reinforced structure
CN214089628U (en) Prefabricated road rail guard
CN201433333Y (en) Built-in barricade type slab ballastless track
CN2443076Y (en) Prestress external anchoring device
CN2609957Y (en) Prestressed reinforced concrete sleeper
CN202247670U (en) Anti-shock stopping block for high level bridge
CN2587918Y (en) Expansion screw fastening mechanism with screw fastener for railway concreter sleeper
CN2131896Y (en) Broad gauge pre-stressed reinforce concrete rail bearing
CN216891774U (en) Light steel sleeper for track traffic integral ballast bed
CN219010825U (en) Sinking type two-way connection integral steel plate structure shear hinge
CN220846875U (en) Unidirectional prefabricated track slab for railway ballastless track and vibration reduction ballastless track
CN201990902U (en) Ballast turnout sleeper for line for passenger transportation
CN201485755U (en) Concrete sleeper of pre-embedded combined casing
CN212560954U (en) Double-anchoring elastic split rail panel fastener for medium-low speed magnetic levitation traffic
CN215947748U (en) Prefabricated combined assembled ballast bed
CN211922092U (en) Double-block sleeper for mounting quick elastic strip fastener
CN211285229U (en) Full-prefabricated assembled track structure on steel truss girder
CN212405218U (en) Connection structure of prefabricated pier and cushion cap

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C53 Correction of patent for invention or patent application
COR Change of bibliographic data

Free format text: CORRECT: PATENTEE; FROM: ANSHAN PERMANENT WAY EQUIPMENT FACTORY, MINISTRY OF RAILWAYS TO: ANSHAN RAILROADING SERVICE EQUIPMENT + MATERIALS PLANT

CP01 Change in the name or title of a patent holder

Patentee after: Anshan public works equipment factory

Patentee before: Anshan Permanent Way Equipment Factory, Ministry of Railways

C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee