CN2324514Y - Smelting furnance - Google Patents

Smelting furnance Download PDF

Info

Publication number
CN2324514Y
CN2324514Y CN 97246600 CN97246600U CN2324514Y CN 2324514 Y CN2324514 Y CN 2324514Y CN 97246600 CN97246600 CN 97246600 CN 97246600 U CN97246600 U CN 97246600U CN 2324514 Y CN2324514 Y CN 2324514Y
Authority
CN
China
Prior art keywords
coal
combustion chamber
smelting furnace
burner hearth
reduced
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 97246600
Other languages
Chinese (zh)
Inventor
屈筠画
屈大伟
屈大涌
张通基
李占春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qu Junhua
Zhou Hong
Original Assignee
屈筠画
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 屈筠画 filed Critical 屈筠画
Priority to CN 97246600 priority Critical patent/CN2324514Y/en
Application granted granted Critical
Publication of CN2324514Y publication Critical patent/CN2324514Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model relates to a smelting furnace, particularly a smelting furnace with takes moulded coal as fuel. One side of a furnace body is provided with a combustion chamber in which moulded coal is arranged, the end part of the furnace body is provided with a coal inlet and a coal slag outlet, the upper part of the furnace body is provided with a heat gathering plate, and the upper part of the heat gathering plate is provided with a high-temperature cavity which is communicated with a hearth on the other side; the four walls of the combustion chamber are provided with a longitudinal secondary air pipe whose both ends are bent towards the inside of the combustion chamber, and the lower part of the combustion chamber is provided with a track; one end of the coal inlet is provided with a propeller, and the end part of the hearth on the other side is provided with an exhaust passage which is connected with an exhaust funnel. The utility model has advantages that the moulded coal is taken as the fuel, the exhaust of smoke dust can be reduced, environmental pollution can be reduced, the surrounding environment can be altered, and the labour intensity can be reduced.

Description

Smelting furnace
The utility model relates to a kind of smelting furnace, specifically fusible tin metallurgy ore in sand form, copper ore and be the smelting furnace of fuel with the moulded coal.
At present, known to the people is that tin ore obtains tin slab by reverberatory smelting, and fuel used is high-quality lump coal (calorific value 7, the 000 kilocalorie/kilograms) burning of loosing, and in the fiery storehouse is to adopt cast iron stove strip holder coal, forces to wind combustion-supporting by air blast.Its labour intensity is big, the fuel consumption height, and the thermal efficiency is low, and only about 20%; Last cinder carbon content height reaches about 40%, and raw coal can not fully burn, and causes energy waste big; Dense smoke is emerged with more than 30 meters high chimney, and the Lin Geman index is more than 4 grades, and severe contamination air and environment also need be combustion-supporting with air blast, and flue gas is discharged and also needed a cover air-introduced machine cleaner.
The purpose of this utility model is the shortcoming at above-mentioned existence, provides a kind of discharging flue dust few, alleviates environmental pollution, energy-saving tin ore, the copper ore smelting furnace of cancellation smokestack and air blast, air-introduced machine and cleaner.
Technical essential of the present utility model is: body of heater is made up of combustion chamber (21) and burner hearth (17), one side is provided with built in type burning of coal chamber, the end has coal feed point G and cinder outlet C, and heat collector panel (6) is put on top, is that the high temperature chamber communicates with the burner hearth (17) of opposite side on the top of heat collector panel (6); Combustion chamber (21) wall contains to be established two ends and bends towards indoor vertical secondary air channel (14), and bottom, combustion chamber (21) is provided with track (1) (2); Be provided with propeller (25) at coal feed point one end, make moulded coal car (16) enter combustion chamber (21); The end of opposite side burner hearth (17) is provided with the exhaust duct (8) that links to each other with aiutage (9).Locate to establish an adjustment plate (10) at aiutage (9) and can regulate the exhaust flow rate, combustion chamber (21) inwall and burner hearth (17) inwall and arc arch inwall all are built into hard refractory brick.
The utility model has the advantages that: be fuel with the moulded coal, cancel chimney, reduced soot emissions, reduced environmental pollution, environment around having changed, reduce labor intensity, air blast, air-introduced machine and a whole set of cleaner, energy savings are used in cancellation, the stove expense is built in saving, be applicable to the melting of tin ore, copper ore, it is simple in structure, and is easy to utilize.
Description of drawings:
Fig. 1 is a structural representation of the present utility model.
Fig. 2 is the A-A cutaway view of Fig. 1.
Fig. 3 is the B-B cutaway view of Fig. 1.
Whole stove is outside to be built into for common brick (3), and the centre is heat-insulation layer (4), and stove is outside fastening with section material frame (23).But body of heater integrated stand device is put on the platform.
Its operation principle is:
After moulded coal entered combustion chamber (21) by coal feed point G by coal car (16) from the track, with match firing point fire bed, pyrolysis produced high temperature in five minutes, and through conduction, put coal-fired body, secondary air hole (14) oxygen supply is fully burnt the coal body simultaneously.Fire combustion high temperature chamber in heat collector panel (6) enters arch is fired the interior tin ore of burner hearth and is made it be melt into Xi Shui in tin pot (11), emits from discharge port (18).Material is added by charging aperture (7) or burner hearth (17) both sides fire door, and per 2.5~4 h are put tin once.Residual air is discharged by burner hearth exhaust outlet (9).Advance coal, slag tap and finish by combustion chamber door (22).It is negative pressure that material is fired the state furnace pressure, and temperature is adjusted plate (10) and realized temperature control by thermocouple monitoring.
Provide below the reverberatory furnace of original melting tin ore and smelting furnace Performance Ratio of the present utility model:
Index subjet Former smelting furnace Existing smelting furnace
Advance coal 1 (20 Kg)/10min 1 (90 Kg)/2h
The thermal efficiency 20%  70%
Pollution condition 4 grades of Lin Geman 0.1 grade of Lin Geman
Power consumption 50 KW  1KW
The coal calorific value 7000 Kcal/Kg  3500~400 Kcal/Kg
Manually 4 people 2 people
In the accompanying drawing 5 is the observation test hole, and 12,19,20 is refractory brick, and 13 is bearing support, and 15 is moulded coal, and 24 are Heat-insulation layer.

Claims (2)

1. smelting furnace, body of heater comprises burner hearth and combustion chamber, it is characterized in that a side is provided with built in type burning of coal chamber, and the end has coal feed point G and cinder outlet C, heat collector panel (6) is put on top, is that the high temperature chamber communicates with the burner hearth (17) of opposite side on the top of heat collector panel (6); Combustion chamber (21) wall contains to be established two ends and bends towards indoor vertical secondary air channel (14), and bottom, combustion chamber (21) is provided with track (1) (2); Be provided with propeller (25) at coal feed point one end; The end of opposite side burner hearth (17) is provided with the exhaust duct (8) that links to each other with aiutage (9).
2. according to the described smelting furnace of claim 1, it is characterized in that locating to establish one at aiutage (9) adjusts plate (10).
CN 97246600 1997-12-31 1997-12-31 Smelting furnance Expired - Fee Related CN2324514Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 97246600 CN2324514Y (en) 1997-12-31 1997-12-31 Smelting furnance

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 97246600 CN2324514Y (en) 1997-12-31 1997-12-31 Smelting furnance

Publications (1)

Publication Number Publication Date
CN2324514Y true CN2324514Y (en) 1999-06-16

Family

ID=33954747

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 97246600 Expired - Fee Related CN2324514Y (en) 1997-12-31 1997-12-31 Smelting furnance

Country Status (1)

Country Link
CN (1) CN2324514Y (en)

Similar Documents

Publication Publication Date Title
CN101294770A (en) Crucible furnace for alloy melting and heat preservation
CN201081538Y (en) Tubular oven
CN2635677Y (en) Air and gas double-preheating hot-blast stove
CN201053820Y (en) Highly effective crucible furnace
CN2324514Y (en) Smelting furnance
CN202175560U (en) Gas electric arc double heat type thermal storage waste heat waste gas backdraft environment protection energy conservation efficient silicon refining furnace
CN1091243C (en) Cupola with external hot air and flue dust elimination device
CN201077861Y (en) Secondary lead energy-saving smelting-furnace
CN219713993U (en) Special biomass gasification combustion furnace for aluminum melting furnace
CN2733248Y (en) Novel hot-water boiler
CN2504552Y (en) Mobile burning boiler
CN216845660U (en) Novel multi-fuel high-temperature flue gas fluidized bed furnace
CN2704010Y (en) Roller-bed kiln using water-coal as fuel
CN201203342Y (en) Direct combustion type overhead combustion chamber cupola
CN2416359Y (en) Smoke prevention and dust control combustion apparatus
CN2483614Y (en) Smokeless combustion apparatus
CN203605476U (en) Equivalent combustion chamber of coal hot air furnace
CN2585117Y (en) Coal-fired hot-air stove for greenhouse
CN105890356A (en) Biomass double-crucible aluminum melting furnace
CN2205533Y (en) Apical cap hot wind smelting steel and iron filing furnace
CN2137571Y (en) Half-gas forge heating-furnace
CN2239431Y (en) Pollution-free reclaiming coke burner
CN2385224Y (en) Smoke-relieving coal-saving furnace device
CN2196760Y (en) Heating boilor
CN2192836Y (en) Horizontal energy-saving atmospheric boiler

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C53 Correction of patent for invention or patent application
CB03 Change of inventor or designer information

Designer after: Qu Junhua

Designer after: Zhou Hong

Designer after: Qu Dawei

Designer after: Qu Dayong

Designer after: Zhang Tongji

Designer after: Li Zhanchun

Designer before: Qu Junhua

Designer before: Qu Dawei

Designer before: Qu Dayong

Designer before: Zhang Tongji

Designer before: Li Zhanchun

COR Change of bibliographic data

Free format text: CORRECT: DESIGNER; FROM: QU YUNHUA; QU DAWEI; QU DAYONG; ZHANG TONGJI; LI ZHANCHUN TO: QU YUNHUA; ZHOU HONG; QU DAWEI; QU DAYONG; ZHANG TONGJI; LI ZHANCHUN

CP01 Change in the name or title of a patent holder

Patentee after: Qu Junhua

Patentee after: Zhou Hong

Patentee before: Qu Junhua

C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee