CN2240009Y - Concrete-jacketing steel pipe tower - Google Patents

Concrete-jacketing steel pipe tower Download PDF

Info

Publication number
CN2240009Y
CN2240009Y CN 95236612 CN95236612U CN2240009Y CN 2240009 Y CN2240009 Y CN 2240009Y CN 95236612 CN95236612 CN 95236612 CN 95236612 U CN95236612 U CN 95236612U CN 2240009 Y CN2240009 Y CN 2240009Y
Authority
CN
China
Prior art keywords
steel pipe
concrete
steel
joint
external wrapping
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 95236612
Other languages
Chinese (zh)
Inventor
邓晓曦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 95236612 priority Critical patent/CN2240009Y/en
Application granted granted Critical
Publication of CN2240009Y publication Critical patent/CN2240009Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Rod-Shaped Construction Members (AREA)

Abstract

The utility model relates to an epiboly concrete steel pipe tower which is composed of a plurality of epiboly concrete steel pipe sections, wherein, the connection parts of the epiboly concrete steel pipe sections are provided with flanges for connection, steel rings and ribbed slabs. The epiboly concrete steel pipe tower has the advantages of high intensity and low manufacture cost. In addition, the large-area treatment for rust and corrosion resistance of metals does not need to be done. The utility model is widely suitable for overhead power delivery lines, and is particularly for overhead power delivery lines in cities.

Description

The external wrapping concrete steel tube tower
The external wrapping concrete steel tube tower belongs to the supporter that uses in the aerial power transmission line.
At present, the supporter that uses in the power transmission sequence mainly contains reinforced concrete pole, angle steel tower, steel tube tower etc.The reinforced concrete pole insufficient strength, and angle steel tower and steel tube tower just involve great expense.The thin wall steel tube concrete bar that Chinese patent provides for No. 90208878.5, though existing certain intensity, cost is also not very expensive, because its thin-wall steel tube is exposed among the air, must carry out antirust, preservative treatment outward, trouble and will increase cost.
The purpose of this utility model is to provide a kind of intensity enough, low cost, needn't carry out antirust, preservative treatment, the external wrapping concrete steel tube tower that floor space is little in the use.
The utility model is realized by following proposal: do bone with steel pipe, the outside encases with steel concrete, makes external wrapping concrete steel pipe joint, forms the external wrapping concrete steel tube tower with number joint external wrapping concrete steel pipe joint.The upper/lower terminal of every joint all leaves to connect uses flange, between the flange with welding with electric welding again after the Bolt Connection.Whole steel tube tower is down thick thin, the bottom of next joint and go up a top of saving most and do not stay flange, and use concrete enclosing.
Below in conjunction with accompanying drawing the utility model is further described:
Accompanying drawing 1 is an external wrapping concrete steel pipe joint schematic diagram.
Accompanying drawing 2 is that A is to schematic diagram.
Accompanying drawing 3 is B-B face cross-sectional schematic.
Accompanying drawing 4 is C-C face cross-sectional schematic.
In the accompanying drawings, [1] is gusset, and [2] are flange, and [3] are steel rings, and [4] are screws, and [5] are steel pipes, and [6] are trivet iron, and [7] are main muscle, and [8] are spiral bars, and [9] are screw-thread steels.Gusset [1] has some, and all weld with electric welding the junction of it and flange [2], steel ring [3], steel pipe [5].Screw-thread steel [9] welds together with main muscle [7].The two ends of main muscle [7] and steel ring [3] welding.Steel ring [3], flange [2] all weld with steel pipe [5].Trivet iron [6] also is welded in the two ends of steel pipe [5].Enrich with high-intensity concrete the outside of steel pipe [5], makes main muscle [7], spiral bar [8], screw-thread steel [9], steel pipe [5] and concrete form a cylinder that has certain taper together.Whole external wrapping concrete steel tube tower saves external wrapping concrete steel pipe joint by number to be formed, and thick down going up carefully generally all made 1/75 taper, with bolt flange [2] tightened up earlier between joint and the joint, welds with two flange that tighten up of electric weld handle [2] again.Descend most the bottom of external wrapping concrete steel pipe joint of joint and the top of going up the external wrapping concrete steel pipe joint of joint most all not to want gusset [1] and flange [2], get final product and steel ring [3] and trivet iron [6] are sealed with concrete, certainly, at this moment steel ring [3] position that should be put into flange [2] is gone.
The utility model intensity height, cost are low, needn't carry out large-area antirust, anti-corrosive again and handle, and can be widely used among the aerial power transmission line, particularly the power transmission sequence within the city.

Claims (3)

1. external wrapping concrete steel tube tower, formed by number joint external wrapping concrete steel pipe joint, it is characterized in that: in every joint external wrapping concrete steel pipe joint, steel pipe [5] is arranged all, steel pipe [5] is outer to be concrete, be equipped with main muscle [7], spiral bar [8], screw-thread steel [9] in the concrete, be welded with trivet iron [6] in the two ends pipe of steel pipe [5], the outside at steel pipe [5] two ends is welded with steel ring [3], flange [2], gusset [1].
2, external wrapping concrete steel tube tower as claimed in claim 1, it is characterized in that: steel tube tower descends the bottom of joint external wrapping concrete steel pipe joint most and goes up the top that joint external wrapping concrete steel pipe saves does not most have flange [2] and gusset [1], and seals steel ring [3] and trivet iron [6] with concrete.
3, external wrapping concrete steel tube tower as claimed in claim 1 is characterized in that: not only use bolt between every joint external wrapping concrete steel pipe joint, but also two flange [2] that the electricity consumption solid welding is tightly joined.
CN 95236612 1995-04-13 1995-04-13 Concrete-jacketing steel pipe tower Expired - Fee Related CN2240009Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 95236612 CN2240009Y (en) 1995-04-13 1995-04-13 Concrete-jacketing steel pipe tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 95236612 CN2240009Y (en) 1995-04-13 1995-04-13 Concrete-jacketing steel pipe tower

Publications (1)

Publication Number Publication Date
CN2240009Y true CN2240009Y (en) 1996-11-13

Family

ID=33879568

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 95236612 Expired - Fee Related CN2240009Y (en) 1995-04-13 1995-04-13 Concrete-jacketing steel pipe tower

Country Status (1)

Country Link
CN (1) CN2240009Y (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108425538A (en) * 2018-03-23 2018-08-21 于逸飞 A kind of ladder-like taper ductile iron pipe and tower bar

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108425538A (en) * 2018-03-23 2018-08-21 于逸飞 A kind of ladder-like taper ductile iron pipe and tower bar

Similar Documents

Publication Publication Date Title
CN209943788U (en) Steel wire mesh framework polyethylene composite pipe connecting structure
CN2240009Y (en) Concrete-jacketing steel pipe tower
CN102312601A (en) Steel pipe pole of power transmission line
CN202017376U (en) Power transmission line steel pipe rod
CN202401142U (en) Anode carbon block
CN208750561U (en) A kind of hot fit structure street lamp
CN206820420U (en) A kind of female sliding support gold utensil of pipes of ¢ 450
CN201236515Y (en) Cylinder joint type steel pipe rod
CN208792865U (en) A kind of detachable concrete wire pole
CN2276112Y (en) Combined chimney or flue with lining and its connecting piece
CN2199268Y (en) Steel pipe tower cross arm for power transmission line
CN2494403Y (en) Socketed round wire pole
CN204901208U (en) It is stifled that outer tube seals gas
CN2913530Y (en) Assembled metal square pipe wall fence components
CN204112828U (en) A kind of connector of steel tube
CN218348099U (en) Corrosion-resistant galvanized steel pipe
KR20080002735U (en) Durable Coffin
CN2212826Y (en) Synthesized isolator aluminium equalizing ring
CN213086665U (en) Combined assembled type isolated gate upright post convenient to transport and install
CN2460956Y (en) Compound aluminium alloy post-wing type radiator
CN2300799Y (en) Demountable coal-saving boiler
CN219447230U (en) Bicycle frame with anticorrosion structure
CN211080296U (en) Inside support unit of utility tunnel
CN211976149U (en) Concrete pipeline for building construction
CN212924291U (en) Forklift type electromechanical engineering pipeline installation lifting device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee