CN221167945U - Detection device for pile foundation construction - Google Patents
Detection device for pile foundation construction Download PDFInfo
- Publication number
- CN221167945U CN221167945U CN202322656166.6U CN202322656166U CN221167945U CN 221167945 U CN221167945 U CN 221167945U CN 202322656166 U CN202322656166 U CN 202322656166U CN 221167945 U CN221167945 U CN 221167945U
- Authority
- CN
- China
- Prior art keywords
- load
- test pile
- pile
- detection device
- baffle
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000001514 detection method Methods 0.000 title claims abstract description 20
- 238000010276 construction Methods 0.000 title claims abstract description 18
- 238000012360 testing method Methods 0.000 claims abstract description 37
- 238000010030 laminating Methods 0.000 abstract 1
- 230000001105 regulatory effect Effects 0.000 abstract 1
- 238000000034 method Methods 0.000 description 5
- 230000000694 effects Effects 0.000 description 2
- 230000001681 protective effect Effects 0.000 description 2
- 230000004075 alteration Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 230000001788 irregular Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Landscapes
- Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)
Abstract
The utility model discloses a detection device for pile foundation construction, and belongs to the technical field of engineering detection devices. Including test pile, test pile bottom is provided with the load platform who carries out the analysis of sinking, test pile top is provided with protection architecture, a plurality of load weights have been placed in the inboard stack of protection architecture, thereby the bearing capacity of test pile has been analyzed, through protection architecture's setting, the promotion load weight piece makes it remove along the inboard regulating plate of fender bracket, until load piece side and fender bracket inner wall laminating, secondly, the staff is at the load piece top of seting up the constant head tank place another load piece, another load piece bottom fixedly connected with cardboard, the constant head tank is fixed with fixed cardboard block when two load pieces are placed, two load piece sides remain neat at this moment, finally the staff inserts the baffle inboard of spacing groove, baffle and fender bracket constitute a complete frame jointly, thereby fix spacing to load piece bottom.
Description
Technical Field
The utility model relates to the technical field of engineering detection devices, in particular to a detection device for pile foundation construction.
Background
The pile foundation belongs to a deep foundation, and is characterized by the advantages of high bearing capacity, good stability, small settlement, uniformity, good earthquake resistance and the like, the pile foundation is widely used in building engineering, particularly, a building built on a soft foundation is more suitable for the application of the pile foundation, the pile foundation is widely applied in the building engineering, pile foundation detection work is a key link for guaranteeing the construction quality of the pile foundation engineering, the bearing capacity of the pile foundation is required to be detected when the pile foundation is detected, most detection devices realize the effect of increasing the load of the test pile by piling load weights on the test pile in sequence, analyze the bearing capacity of the test pile by observing the settlement of the test pile, but the upper and lower load blocks are not orderly piled, the gravity centers of the piled load blocks are unstable and are easy to skew, and potential safety hazards exist.
Chinese patent No. CN218990277U discloses a pile foundation detection device for construction acceptance belongs to construction technical field, including ground and locates subaerial test stake, test stake upper end is equipped with load platform, load platform lower extreme symmetry is equipped with four slide bars, four the slide bar lower extreme is all slided and is equipped with the U-shaped sleeve, terminal surface and ground upper end mutual contact under the U-shaped sleeve, load platform upper end is equipped with auxiliary assembly, through setting up the protection frame, guarantees that the cuboid load piece side that piles up keeps neat, and then avoids cuboid load piece side irregular to cause the focus of piling up unstable, has solved the unstable problem that has the potential safety hazard of cuboid load piece focus.
Through setting up detachable slide bar and guard frame on load platform in the above-mentioned technique, realize the spacing to the load piece side, but increased more steps in this technique, except that need constructor place the load piece on the load platform that installs, still need staff's installation slide bar, guard frame to after installing one deck load piece, in time adjust guard frame height, the process is more, leads to staff's detection efficiency to reduce, and in view of this, we propose a detection device for pile foundation construction.
Disclosure of utility model
1. Technical problem to be solved
The utility model aims to provide a detection device for pile foundation construction, which solves the problems in the prior art.
2. Technical proposal
A detection device for pile foundation construction, which comprises a test pile,
The test pile, test pile bottom is provided with the load platform who carries out the analysis of sinking, test pile top is provided with protection architecture, a plurality of load weights have been placed to the inboard stack of protection architecture to the bearing capacity of test pile is analyzed.
As an alternative scheme of the technical scheme of the utility model, the protection structure comprises a protection frame, a baffle and an adjusting plate, wherein the protection frame is clamped at the top end of the test pile, the adjusting plate is symmetrically arranged on the inner wall of the protection frame, the baffle is clamped at the other side of the protection frame, the baffle is clamped and connected with a limit groove, and the limit groove is arranged at the side edge of the test pile.
As an alternative scheme of the file technical scheme, a positioning groove is formed in the top end of the load-carrying block, a fixed clamping plate is connected to the inner side of the positioning groove in a clamping mode, and the other end of the fixed clamping plate is fixedly connected with another load-carrying block.
As an alternative to the technical solution of the present utility model, the protection frame is configured as three panels, and the ratio of the height of the three panels to the height of the loading block is 3:2.
As an alternative scheme of the technical scheme of the utility model, the top end of the test pile is fixedly provided with a limit groove, the limit groove is a concave groove, the concave groove is connected with the outer side of the fixing plate in a clamping way, and the top end of the fixing plate is respectively fixed with a protection frame and a baffle plate.
As an alternative scheme of the technical scheme of the utility model, the inner wall of the adjusting plate is embedded with a fixed groove, and the inner side of the fixed groove is rotationally connected with a round wheel.
3. Advantageous effects
Compared with the prior art, the utility model has the advantages that:
According to the utility model, through the arrangement of the protection structure, when pile foundations are detected, the load platform is arranged on the ground, the top end of the load platform is provided with the test pile, firstly, the protection frame is inserted into the top end of the test pile, then, a worker pushes the load block to move along the adjusting plate on the inner side of the protection frame until the side edge of the load block is attached to the inner wall of the protection frame, secondly, the worker places another load block on the top end of the load block provided with the positioning groove, the bottom end of the other load block is fixedly connected with the fixing clamping plate, the positioning groove is clamped and fixed with the fixing clamping plate when the two load blocks are placed, at the moment, the side edges of the two load blocks are kept in order, and finally, the worker inserts the baffle into the inner side of the limiting groove, and the baffle and the protection frame jointly form a complete frame, so that the bottom end of the load block is fixed and limited, the stability of the top end of the test pile is ensured, and the working procedure efficiency of the worker is improved.
Drawings
FIG. 1 is a schematic diagram showing the overall structure of a pile foundation construction detection device according to a preferred embodiment of the present utility model;
FIG. 2 is an exploded view of a protection structure of a detection device for pile foundation construction according to a preferred embodiment of the present utility model;
FIG. 3 is a schematic side cross-sectional view of a main body of a pile foundation construction inspection device according to a preferred embodiment of the present utility model;
The reference numerals in the figures illustrate: 1. testing piles; 11. a limit groove; 2. a load carrying platform; 3. a protective structure; 31. a protective frame; 32. a baffle; 33. an adjusting plate; 4. a load block; 41. a fixing groove; 42. and fixing the clamping plate.
Detailed Description
Referring to fig. 1-3, the present utility model provides a technical solution:
Referring to fig. 1, fig. 2 and fig. 3, test pile 1 bottom fixedly connected with load platform 2, load platform 2 sets up on test pile 1 top, limit groove 11 has been seted up on test pile 1 top, limit groove 11 sets up to the concave groove, the concave groove is connected with the fixed plate outside block, the fixed plate top is fixed with protection architecture 3, protection architecture 3 includes fender bracket 31, fender bracket 31 and baffle 32, fender bracket 31 sets up to three panels, fender bracket 31 opposite side block has baffle 32, baffle 32 bottom is connected with limit groove 11 block, three panel height is 3 with load piece 4 height ratio: 2, the inner wall of the protection frame 31 is symmetrically provided with an adjusting plate 33, the inner wall of the adjusting plate 33 is embedded with a fixed groove, the inner side of the fixed groove is rotationally connected with a round wheel, the top end of the load block 4 is provided with a positioning groove 41, the inner side of the positioning groove 41 is connected with a fixed clamping plate 42 in a clamping way, and the other end of the fixed clamping plate 42 is fixedly connected with the other load block 4;
When pile foundation is detected, firstly, the loading platform 2 is arranged on the ground, then the top end of the loading platform 2 is provided with the test pile 1, a worker firstly inserts the protection frame 31 into the top end of the test pile 1, and then the worker pushes the load block 4 to move along the adjusting plate 33 on the inner side of the protection frame 31 until the side edge of the load block 4 is attached to the inner wall of the protection frame 31;
Secondly, the staff is at the load piece 4 top of seting up constant head tank 41 and is placed another load piece 4, another load piece 4 bottom fixedly connected with fixed cardboard 42, constant head tank 41 and fixed cardboard 42 block are fixed when two load pieces 4 are placed, two load piece 4 sides keep neat this moment, the staff inserts spacing groove 11 inboard with baffle 32 at last, baffle 32 and fender bracket 31 constitute a complete frame jointly this moment, thereby carry out fixed spacing to load piece 4 bottom, complete frame also guarantees the stability on test stake 1 top, staff's process efficiency has been improved.
Although an example of the present invention has been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.
Claims (5)
1. Detection device is used in pile foundation construction contains experimental stake (1), its characterized in that:
The test pile comprises a test pile (1), wherein a loading platform (2) for carrying out sinking analysis is arranged at the bottom end of the test pile (1), a protection structure (3) is arranged at the top end of the test pile (1), and a plurality of load blocks (4) are stacked and placed on the inner side of the protection structure (3), so that the bearing capacity of the test pile (1) is analyzed; the protection structure (3) comprises a protection frame (31), a baffle (32) and an adjusting plate (33), wherein the protection frame (31) is arranged at the top end of the test pile (1) in a clamping mode, the adjusting plate (33) is symmetrically arranged on the inner wall of the protection frame (31), the baffle (32) is arranged at the other side of the protection frame (31) in a clamping mode, the baffle (32) is connected with the limiting groove (11) in a clamping mode, and the limiting groove (11) is formed in the side edge of the test pile (1).
2. The pile foundation construction detection device according to claim 1, wherein: the locating groove (41) is formed in the top end of the load block (4), the inner side of the locating groove (41) is connected with the fixed clamping plate (42) in a clamping mode, and the other end of the fixed clamping plate (42) is fixedly connected with the other load block (4).
3. The pile foundation construction detection device according to claim 2, wherein: the protection frame (31) is provided with three panels, and the height ratio of the three panels to the height ratio of the load block (4) is 3:2.
4. A pile foundation construction detection device according to claim 3, wherein: the test pile is characterized in that a limiting groove (11) is fixedly formed in the top end of the test pile (1), the limiting groove (11) is a concave groove, the concave groove is connected with the outer side of the fixing plate in a clamping mode, and a protection frame (31) and a baffle (32) are respectively fixed on the top end of the fixing plate.
5. The pile foundation construction detection device according to claim 4, wherein: the inner wall of the adjusting plate (33) is embedded with a fixed groove, and the inner side of the fixed groove is rotationally connected with a round wheel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202322656166.6U CN221167945U (en) | 2023-09-28 | 2023-09-28 | Detection device for pile foundation construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202322656166.6U CN221167945U (en) | 2023-09-28 | 2023-09-28 | Detection device for pile foundation construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN221167945U true CN221167945U (en) | 2024-06-18 |
Family
ID=91531889
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202322656166.6U Active CN221167945U (en) | 2023-09-28 | 2023-09-28 | Detection device for pile foundation construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN221167945U (en) |
-
2023
- 2023-09-28 CN CN202322656166.6U patent/CN221167945U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US10590622B2 (en) | Drop hammer height adjusting device for high strain detection of pile foundation | |
US9066585B2 (en) | Storage rack, flexible moment frame for reducing seismic damage to stored goods | |
CN103061360B (en) | Stress application system for large-tonnage static load tests | |
CN205954716U (en) | A counterforce device for foundation pile resistance to compression static test | |
CN209798851U (en) | static pressure pile foundation static load detection device | |
CN210177554U (en) | Pile foundation static load test equipment | |
CN221167945U (en) | Detection device for pile foundation construction | |
CN108797628A (en) | Lift-off formula subtracts shock insulation pile foundation construction | |
CN207829029U (en) | A kind of preloading formula static load of pile foundation experimental provision | |
CN213173858U (en) | Static load detection tool for static pressure pile foundation of traffic hub engineering | |
CN212612282U (en) | Fixed hydraulic engineering bank protection of tractive | |
CN208155760U (en) | A kind of hollow square pile beam test device | |
CN110206156A (en) | A kind of jack-up system of jacking type building roof platform | |
CN111487028B (en) | Loading platform device for civil engineering structure explosion damage experiment | |
CN211596858U (en) | Pile foundation static load experimental device suitable for narrow space | |
CN220167001U (en) | Engineering foundation pile detection device | |
CN211773950U (en) | Support for high strain detection of pile foundation | |
CN107130649A (en) | A kind of large-tonnage concrete block preloading static load of pile foundation device | |
CN209260781U (en) | A kind of foundation loading test protective device | |
CN106320402A (en) | Vertical pressure-resistant static load test device for engineering piles | |
CN213390261U (en) | Steel pipe pile bearing capacity test structure | |
CN215004728U (en) | Pile foundation static load test equipment for improving safety | |
CN205662955U (en) | Foundation pile detection device | |
CN105544624B (en) | A kind of test for static load device of asymmetric counterweight | |
CN217399747U (en) | Pile foundation static load test equipment for improving safety |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |