CN221095095U CN202322612272.4U CN202322612272U CN221095095U CN 221095095 U CN221095095 U CN 221095095U CN 202322612272 U CN202322612272 U CN 202322612272U CN 221095095 U CN221095095 U CN 221095095U
Authority
CN
China
Prior art keywords
pile
anchoring
pile body
sleeve
water conservancy
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322612272.4U
Other languages
Chinese (zh)
Inventor
陈孝虎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Liyin Building Material Science And Technology LLC
Original Assignee
Jiangsu Liyin Building Material Science And Technology LLC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Liyin Building Material Science And Technology LLC filed Critical Jiangsu Liyin Building Material Science And Technology LLC
Priority to CN202322612272.4U priority Critical patent/CN221095095U/en
Application granted granted Critical
Publication of CN221095095U publication Critical patent/CN221095095U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a concrete pile for water conservancy river support, which is specially constructed and arranged on the top of a pile body in view of special limitation of water conservancy river support construction equipment selection and requirement of casting a crown beam that a steel bar is required to be connected (exposed) at the top of the pile body, wherein a sleeve with a threaded connection port is arranged in the pile body, the top surface of the sleeve is flush with the top surface of the pile body, and an anchoring steel bar is directly connected into the sleeve in construction application so as to cast the crown beam and integrate the pile forming structure and appearance; the steel mesh protection sheet and the steel bars and pile head concrete on the steel bar cage are wrapped by the peripheral armatures, so that a new protection for reinforcing the pile head against construction striking is provided. According to the utility model, the sleeve is arranged on the pile body and is combined with the anchoring steel bars and the steel bar cage, so that the pile head can be directly knocked in construction engineering, the sleeve structure is stable and cannot be damaged, and the stability of the pile body is improved.

Description

Concrete pile for water conservancy river support
Technical Field
The utility model relates to the field of concrete piles for buildings, in particular to a concrete pile for supporting a water conservancy river channel.
Background
Concrete piles are a common foundation treatment tool and are widely used in river channel remediation engineering. The concrete pile has the advantages of strong bearing capacity, good stability, convenient construction and the like, can effectively increase the bearing capacity and stability of a river channel, and prevents the problems of river channel breach, scouring and the like.
The existing concrete pile has stronger pile body design strength, but the connecting piece at the pile head part is still easy to be damaged in large-scale construction, and the main reason analysis has two: firstly, a construction machine is a clamp refitted for an excavator, and low-frequency vibration pressure is realized; and two meshes and one net cap are added on the pile head, so that the reinforcement density is increased, and the adhesive force of the protective layer is insufficient. Therefore, the application provides a concrete pile structure for supporting a water conservancy river channel, so that a connecting piece at the pile head part is not easy to damage.
Disclosure of Invention
Aiming at the problems, the utility model aims to provide a concrete pile for water conservancy river support, which is easy to construct and install.
In order to achieve the technical purpose, the scheme of the utility model is as follows: the utility model provides a concrete pile for water conservancy river course support, includes the pile body that adopts concrete and steel reinforcement cage to make, set up more than two sleeves in the pile body top surface, sleeve one end is the threaded connection mouth, the sleeve other end is connected with the anchor reinforcing bar, telescopic threaded connection mouth top surface flushes with the pile body top surface; at least one layer of steel mesh protection sheet is arranged on one side, close to the sleeve, of the reinforcement cage; the outer side of the steel mesh protection sheet is welded with a peripheral reinforcing hoop, and the peripheral reinforcing hoop wraps the steel mesh protection sheet and part of the reinforcement cage.
Preferably, the steel reinforcement cage is formed by combining transverse ribs, binding ribs and longitudinal ribs, the transverse ribs are surrounded by the longitudinal ribs, the intersection of the longitudinal ribs and the transverse ribs is fixed by the binding ribs, the length of the transverse ribs of the steel reinforcement cage is smaller than that of the pile body, and the transverse ribs of the steel reinforcement cage are wrapped in the pile body.
Preferably, the tail parts of the anchoring steel bars are U-shaped structures, the total length of the anchoring steel bars is larger than 40cm, and the anchoring steel bars and the longitudinal bars of the steel reinforcement cage are bundled together.
Preferably, the pile body is symmetrically provided with four sleeves, each sleeve is of a hollow cylindrical structure, an anchoring cavity with a convex cross section is arranged in each sleeve, the head of each anchoring steel bar is of a T-shaped structure, the maximum diameter of the head of each anchoring steel bar is larger than the minimum diameter in each anchoring cavity, the diameter of the middle of each anchoring steel bar is smaller than the minimum diameter in each anchoring cavity, the head of each anchoring steel bar can be embedded and fixed in each anchoring cavity, and the middle and tail of each anchoring steel bar extend out of the tail of each sleeve.
Preferably, the width of the peripheral reinforcing hoop is larger than 8cm, and the thickness of the peripheral reinforcing hoop is larger than 1.2mm.
Preferably, the transverse ribs consist of main ribs and auxiliary ribs, the diameter of the main ribs is larger than 14mm, and more than 6 main ribs are arranged in the reinforcement cage.
Preferably, the pile body bottom is provided with a pile tip with stronger penetrating power, and the pile tip is of a conical structure.
Preferably, a cylindrical spike part is welded in the pile tip in an embedded mode, the diameter of the spike part is more than or equal to 20mm, and the length of the spike part extending out of the bottom of the pile tip is more than or equal to 30mm.
The pile body is internally provided with the sleeve which is flush with the surface of the pile body, so that no exposed reinforcing steel bars are arranged, the pile head is not exposed due to knocking in construction and installation, and the sleeve structure is stable and is not damaged. The sleeve is provided with a threaded connection port, so that the connecting piece can be conveniently connected in a butt joint mode, and the pile head is effectively protected. In addition, other reinforced structures are adopted, so that the whole structure is firmer, the safety is high, and the stability of pile body quality is improved.
Drawings
Fig. 1 is a schematic structural view of a reinforcement cage and sleeve of the present utility model;
Fig. 2 is a cross-sectional view of the present utility model using L-shaped anchor bars;
Fig. 3 is a partial cross-sectional view of the present utility model employing straight-type anchoring bars;
Fig. 4 is a schematic structural view of a steel mesh protection sheet according to the present utility model;
fig. 5 is a schematic top view of the reinforcement cage of the present utility model;
fig. 6 is a schematic view of a partial structure of a pile tip according to the present utility model.
In the figure: 1. a reinforcement cage; 11. transverse ribs; 13. Longitudinal ribs; 2. a sleeve; 3. anchoring the steel bars; 4. a steel mesh protection sheet; 5. peripheral reinforced hoops; 6. pile tip; 61. the spike.
Detailed Description
The utility model will be described in further detail with reference to the drawings and the specific examples. For a clear and complete description of the technical solutions, the following examples are chosen for illustration; based on the description of the present utility model, other embodiments obtained without making any inventive effort are within the scope of the present utility model.
In the following embodiments, it should be noted that, in terms of "upper", "lower", "left", "right", "inner", "outer", "top/bottom", and the like, the orientation or positional relationship is based on the orientation or positional relationship shown in the drawings, and is merely for the sake of clarity in describing the present embodiment, and it does not indicate or imply that the apparatus or element to be referred to must have a specific orientation, and therefore, should not be construed as limiting the present application.
As shown in fig. 1-6, the concrete embodiment of the utility model is a concrete pile for supporting a water conservancy river, which comprises a pile body made of concrete and a reinforcement cage 1, wherein more than two sleeves 2 are arranged in the top surface of the pile body, one end of each sleeve 2 is a threaded connection port, the other end of each sleeve 2 is connected with an anchoring reinforcement 3, the top surface of each threaded connection port of each sleeve 2 is level with the top surface of the pile body, and the threaded connection ports of the sleeves 2 are used for butting other pile bodies;
Under the condition that the whole reinforcement is unchanged, one side of the reinforcement cage 1, which is close to the sleeve 2, is also provided with at least one layer of steel mesh protection sheet 4, the outer side of the steel mesh protection sheet 4 is welded with a peripheral reinforcing hoop 5, the peripheral reinforcing hoop 5 wraps the reinforcement on the steel mesh protection sheet 4 and the reinforcement cage 1, and the reinforcement cage is preferably woven by a machine to replace manual binding, so that the quality stability of the reinforcement cage 1 is improved. Wherein, preferably, the width of peripheral reinforcing staple bolt 5 is greater than 8cm, and the thickness of peripheral reinforcing staple bolt 5 is greater than 1.2mm.
The reinforcement cage 1 is formed by combining the transverse ribs 11, the binding ribs and the longitudinal ribs 13, the longitudinal ribs 13 encircle the transverse ribs 11, the intersection of the longitudinal ribs 13 and the transverse ribs 11 is fixed through the binding ribs, the length of the transverse ribs 11 of the reinforcement cage 1 is smaller than that of a pile body, the transverse ribs 11 of the reinforcement cage 1 are wrapped in the pile body, the strength and toughness of the pile body structure are improved, the pile body is prevented from being damaged and cracked in the construction and use processes, and the bearing capacity of the pile body can be further provided, so that the pile body can bear larger load. The transverse ribs 11 are composed of main ribs and auxiliary ribs, the diameter of the main ribs is larger than 14mm, and more than 6 main ribs are arranged in the reinforcement cage 1.
The tail of the anchoring steel bar 3 is of a U-shaped hook structure, so that the contact area between the anchoring steel bar 3 and concrete is increased, the anchoring effect is enhanced, the total length of the anchoring steel bar 3 is greater than 40cm, the anchoring steel bar 3 and the longitudinal steel bars 13 of the steel bar cage 1 are bundled together, the anchoring steel bar 3 can bear transverse load better, and the stability and the bearing capacity of the structure are improved.
Conventionally, when a concrete structure with a crown beam is manufactured on land, a precast concrete pile with a top surface exposed from a reinforcing steel bar is usually selected, and the precast concrete pile is driven into a designated position by adopting a static pressure method; because the construction space on the ground is large, the construction can be performed by adopting a static pressure method, the exposed steel bars at the top of the precast concrete pile can not be damaged and bent, and the exposed steel bars are very convenient to be connected with the steel bar cages of the crown beams in the follow-up process. When the construction position becomes a river course, a static pressure method cannot be adopted, and only a hammering method (such as knocking by an excavator) can be adopted; when the precast concrete pile with the exposed reinforcing steel bars is adopted, the exposed reinforcing steel bars can be flattened due to repeated hammering actions, and the exposed reinforcing steel bars cannot be effectively connected with a reinforcement cage of the crown beam.
Therefore, when the river is constructed, the precast concrete pile without the exposed reinforcing steel bars is usually adopted, after the precast concrete pile is installed in the river, the top of the precast concrete pile is destroyed by the equipment to expose the reinforcing steel bars, so that the operation difficulty is high, the time is long, the exposed reinforcing steel bars and the top surface are uneven, and the construction quality is poor. And because the precast concrete pile is positioned in the river channel, the construction danger coefficient is higher when the top of the precast concrete pile is damaged.
In view of the special limitations of the hydraulic river support construction machine and the requirement that the pile body top is required to be connected with (exposed) steel bars to meet the pouring requirement of the crown beam, the application has a special structure and arrangement (a flush sleeve is arranged in the pile body top) on the pile body top; in the construction application, the anchoring steel bar is directly connected with the sleeve so as to perform crown beam pouring and pile forming structure and appearance integration, and a steel mesh protection sheet for reinforcing the protection of the pile head part against construction impact is arranged on one side of the steel bar cage close to the sleeve; the steel mesh protection sheet and the steel bars and pile head concrete on the steel bar cage are wrapped by the peripheral armatures, so that a new protection for reinforcing the pile head against construction striking is provided.
According to the pile body, the four sleeves 2 are symmetrically arranged on the pile body, the sleeves 2 are of hollow cylindrical structures, the anchoring cavities with the convex cross sections are arranged in the sleeves 2, and the structure can provide enough space, so that the anchoring steel bars 3 can be firmly embedded into the pile body, and the stability is improved; the T-shaped structure of the head of the anchoring bar 3 enables the anchoring bar 3 to be properly installed and firmly anchored in the sleeve, the T-shaped structure providing better load bearing capacity and load distribution. Specifically, the maximum diameter of the head of the anchoring bar 3 is larger than the minimum diameter in the anchoring cavity, the diameter of the middle part of the anchoring bar 3 is smaller than the minimum diameter in the anchoring cavity, the head of the anchoring bar 3 can be embedded and fixed in the anchoring cavity, and the middle part and the tail of the anchoring bar 3 extend out from the tail of the sleeve 2. After the concrete pile is installed in a river channel by adopting a hammering method, the top of the concrete pile is flat and clean, and no protruding exposed structure exists; the steel bars are installed in the sleeve only through threads (very fast and efficient), the steel bars can be connected with the steel reinforcement cage of the crown beam quickly through the newly installed steel bars, the sleeve is tightly connected with the steel bars in the concrete pile, the crown beam formed after casting is tightly connected with the concrete pile, and the connecting surface is smooth.
Pile tip 6 with high penetrating power is arranged at the bottom of the pile body, and pile tip 6 is of a conical structure and plays a guiding role, so that stability of the pile body is ensured, and the pile body is prevented from deviating at the bottom. Specifically, a cylindrical spike 61 is welded in the pile tip 6, the diameter of the spike 61 is greater than or equal to 20mm, and the length of the spike 61 extending from the bottom of the pile tip 6 is greater than or equal to 30mm.
The foregoing description is only of the preferred embodiments of the present utility model, and is not intended to limit the utility model, but any minor modifications, equivalents, and improvements made to the above embodiments according to the technical principles of the present utility model should be included in the scope of the technical solutions of the present utility model.

Claims (8)

1. A concrete pile for water conservancy river support is characterized in that: the pile comprises a pile body made of concrete and a reinforcement cage, wherein more than two sleeves are arranged in the top surface of the pile body, one end of each sleeve is a threaded connection port, the other end of each sleeve is connected with an anchor reinforcement, and the top surface of each threaded connection port of each sleeve is flush with the top surface of the pile body; at least one layer of steel mesh protection sheet for reinforcing the pile head part against construction impact is also arranged on one side of the reinforcement cage close to the sleeve; the outer side of the steel mesh protection sheet is welded with a peripheral reinforcing hoop, and the peripheral reinforcing hoop wraps the steel mesh protection sheet and part of the reinforcement cage.
2. The concrete pile for water conservancy river support according to claim 1, wherein: the steel reinforcement cage is formed by combining transverse ribs, binding ribs and longitudinal ribs, the transverse ribs are surrounded by the longitudinal ribs, the intersection of the longitudinal ribs and the transverse ribs is fixed through the binding ribs, the length of the transverse ribs of the steel reinforcement cage is smaller than that of a pile body, and the transverse ribs of the steel reinforcement cage are wrapped in the pile body.
3. The concrete pile for water conservancy river support according to claim 2, wherein: the tail of the anchoring steel bar is of a U-shaped hook structure, the total length of the anchoring steel bar is larger than 40cm, and the anchoring steel bar and the longitudinal steel bar of the steel bar cage are bundled together.
4. The concrete pile for water conservancy river support according to claim 1, wherein: four sleeves are symmetrically arranged on the pile body, the sleeves are of hollow cylindrical structures, anchoring cavities with convex cross sections are arranged in the sleeves, T-shaped structures of the heads of the anchoring reinforcing steel bars are arranged, the maximum diameter of the heads of the anchoring reinforcing steel bars is larger than the minimum diameter in the anchoring cavities, the diameter of the middle part of the anchoring reinforcing steel bars is smaller than the minimum diameter in the anchoring cavities, the heads of the anchoring reinforcing steel bars can be embedded and fixed in the anchoring cavities, and the middle parts and the tail parts of the anchoring reinforcing steel bars extend out of the tail parts of the sleeves.
5. The concrete pile for water conservancy river support according to claim 1, wherein: the width of the peripheral reinforced hoop is larger than 8cm, and the thickness of the peripheral reinforced hoop is larger than 1.2mm.
6. The concrete pile for water conservancy river support according to claim 2, wherein: the transverse reinforcement consists of main reinforcements and auxiliary reinforcements, the diameter of the main reinforcements is larger than 14mm, and more than 6 main reinforcements are arranged in the reinforcement cage.
7. The concrete pile for water conservancy river support according to claim 1, wherein: pile tip with high penetrating power is arranged at the bottom of the pile body, and the pile tip is of a conical structure.
8. The concrete pile for water conservancy river course support of claim 7, wherein: the pile tip is internally embedded and welded with a cylindrical spike part, the diameter of the spike part is more than or equal to 20mm, and the length of the spike part extending out of the bottom of the pile tip is more than or equal to 30mm.
CN202322612272.4U 2023-09-26 2023-09-26 Concrete pile for water conservancy river support Active CN221095095U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322612272.4U CN221095095U (en) 2023-09-26 2023-09-26 Concrete pile for water conservancy river support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322612272.4U CN221095095U (en) 2023-09-26 2023-09-26 Concrete pile for water conservancy river support

Publications (1)

Publication Number Publication Date
CN221095095U true CN221095095U (en) 2024-06-07

Family

ID=91326629

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322612272.4U Active CN221095095U (en) 2023-09-26 2023-09-26 Concrete pile for water conservancy river support

Country Status (1)

Country Link
CN (1) CN221095095U (en)

Similar Documents

Publication Publication Date Title
CN104674660A (en) Novel hollow plate hinge joint structure and construction method thereof
CN210439306U (en) Slope prestressed anchorage cable frame supporting construction
CN108560613A (en) A kind of opening prestressed high strength coagulation pile pile anti-float method integrated with anti-float anchor rod
CN101225663A (en) Steel boxed cofferdam and recovery method thereof
CN221095095U (en) Concrete pile for water conservancy river support
CN211472481U (en) Combined enhanced uplift anchor rod device
CN108643215B (en) Construction method of anchor pier type foundation after rotary spraying and pressing into variable cross section
CN115839102A (en) Wind power tower prestress stiffening type steel concrete high-rise pile cap foundation
CN211596741U (en) Pretensioned prestressed concrete dado V-shaped pile
CN202989911U (en) Post-grouting pile of precast concrete
CN105970963B (en) A kind of precast concrete channel plate pile head bracing means
JP5562715B2 (en) Underwater foundation construction method and outer shell structure
CN211646342U (en) Pretensioning prestressed concrete dado C-shaped pile
CN211773650U (en) Steel pipe static pile pressing device capable of preventing corrosion and improving pile pressing depth
CN211395661U (en) Prefabricated combined pile
CN209099205U (en) The device of impaired pier stud repairing and reinforcement
CN206815330U (en) A kind of corrosion-resistant corner cut square pile of pre-tensioning system partially prestressed concrete
CN113638361A (en) Connection structure of port and pier PHC tubular pile and superstructure
CN209384243U (en) A kind of prestressing force support pile and piling wall
CN202039343U (en) Hollow foundation concrete square pile
CN215483544U (en) Firm prefabricated composite beam
CN221167889U (en) Anti-scour pier pile foundation structure
CN209741830U (en) Deconstructed finite element assembled prestressed pile suitable for pile bottom hammering pile sinking
CN212077920U (en) High-strength retaining pile with soil-retaining and water-stopping prestress
CN219547778U (en) Large-diameter prefabricated pipe pile

Legal Events

Date Code Title Description