CN221030885U CN202322699490.6U CN202322699490U CN221030885U CN 221030885 U CN221030885 U CN 221030885U CN 202322699490 U CN202322699490 U CN 202322699490U CN 221030885 U CN221030885 U CN 221030885U
Authority
CN
China
Prior art keywords
frame
fixedly connected
curtain wall
curtain
front side
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322699490.6U
Other languages
Chinese (zh)
Inventor
赵滕生
王庆明
王伟
赵辉
张勤勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tengyang Construction Technology Co ltd
Original Assignee
Tengyang Construction Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tengyang Construction Technology Co ltd filed Critical Tengyang Construction Technology Co ltd
Priority to CN202322699490.6U priority Critical patent/CN221030885U/en
Application granted granted Critical
Publication of CN221030885U publication Critical patent/CN221030885U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Bearing And Curtain Walls (AREA)

Abstract

The utility model discloses a preassembled energy-saving building curtain wall, which relates to the field of building curtain walls and comprises a curtain wall frame, wherein a curtain wall plate is arranged in an inner cavity of the curtain wall frame, a limiting baffle frame is arranged at the front side of the curtain wall plate, a fixing box is fixedly connected to the top and the bottom of two sides of the rear side of the curtain wall frame, a limiting plate is arranged in the inner cavity of the fixing box, an elastic sheet is fixedly connected to the rear side of the limiting plate, a pull rod is fixedly connected to the front side of the limiting plate, the front side of the pull rod penetrates to the front side of the limiting baffle frame, a pushing block is fixedly connected to the top of the front side of the limiting plate, a bolt is arranged at the top of the fixing box, a pressing block is fixedly connected to the bottom of the bolt, and a fastening mechanism is fixedly connected to the two sides of the rear side of the curtain wall frame. By independently disassembling the baffle frame on the front side of the curtain wall frame, the curtain wall plate can be directly replaced under the condition that the curtain wall frame is not disassembled, so that the problem in the background technology is solved.

Description

Preassembled energy-saving building curtain wall
Technical Field
The utility model relates to the field of building curtain walls, in particular to a preassembled building energy-saving curtain wall.
Background
The energy-saving curtain wall for building is an external wall enclosure of building, which is composed of supporting structure system and panel, and does not share the external wall enclosure structure or decorative structure of main structure.
For example, chinese patent application number CN202221737689.2 discloses a prefabricated energy-saving building curtain wall, which comprises a wall body and a wall body mounting rack, wherein each of four corners on the back of the wall body is fixedly connected with a connecting shaft, the connecting shafts are perpendicular to the wall body, and the connecting shafts are provided with through locking holes, each of four corners on the back of the wall body mounting rack is fixedly provided with a connecting shaft locking mechanism for fixing the connecting shafts, the connecting shaft locking mechanism consists of a spring bolt and a shaft sleeve, the spring bolt consists of a bolt mounting rack, a bolt body and a large spring, the bolt mounting rack is fixed on the wall body mounting rack, the bolt mounting rack is provided with through holes for mounting the bolt body, and the connecting shafts on the wall body are only required to be aligned with the mounting holes and inserted into the shaft sleeve, so that the installation is simple and quick.
Based on the retrieval of above-mentioned patent to and combine the equipment discovery among the prior art, above-mentioned equipment is when using, and though aim at the mounting hole and insert the axle sleeve inside through the connecting axle and can accomplish the installation fixed to the curtain, but this patent has the trouble problem of later maintenance, when a curtain board takes place to damage in the curtain and needs to be changed, the staff need dismantle curtain frame and curtain board simultaneously, install once more after changing, whole operation process is loaded down with trivial details, waste time and energy, and need carry out high altitude construction many times, the danger is higher, be unfavorable for people's use.
Aiming at the problems, the utility model provides a preassembled energy-saving curtain wall for a building.
Disclosure of utility model
The utility model aims to provide a preassembled energy-saving building curtain wall, which can directly replace a curtain wall plate under the condition that a curtain wall frame is not removed by independently disassembling a baffle frame on the front side of the curtain wall frame, so that the problems in the background technology are solved.
In order to achieve the above purpose, the present utility model provides the following technical solutions: the utility model provides a pre-installation formula building energy-saving curtain, includes the curtain frame, the inner chamber of curtain frame is provided with curtain wallboard, the front side of curtain wallboard is provided with spacing fender frame, the top of curtain frame rear side both sides and the equal fixedly connected with of bottom are fixed the case, the inner chamber of fixed case is provided with the limiting plate, the rear side fixedly connected with elastic sheet of limiting plate, the front side fixedly connected with pull rod of limiting plate, the front side of pull rod runs through to the front side of spacing fender frame, the top fixedly connected with ejector pad of limiting plate front side, the top of fixed case is provided with the bolt, the bottom of bolt runs through fixed case and fixedly connected with briquetting, the equal fixedly connected with fastening mechanism in both sides of curtain frame rear side.
Further, the fastening mechanism comprises a positioning frame, a screw is arranged at the rear side of the positioning frame, the front side of the screw penetrates through the positioning frame and is movably connected with a pressing plate, and a rubber protection pad is arranged at the front side of the pressing plate.
Further, the back side fixedly connected with knob of screw rod, the front side and the clamp plate of screw rod pass through bearing swing joint.
Further, the rear side fixedly connected with sealing rubber circle of spacing fender frame, the constant head tank that uses with the pull rod cooperation has all been seted up to the top and the bottom of curtain frame both sides.
Further, the rear side fixedly connected with erection column of fixed box, the rear side fixedly connected with mounting panel of erection column, the mounting hole has all been seted up to the top and the bottom of mounting panel front side.
Further, a threaded hole matched with the bolt is formed in the top of the fixed box, and a movable opening matched with the pull rod is formed in the front side of the fixed box.
Further, the bottom fixedly connected with slider of limiting plate, the spout that uses with the slider cooperation is seted up to the bottom of fixed case inner chamber.
Compared with the prior art, the utility model has the following beneficial effects:
According to the preassembled energy-saving building curtain wall, the curtain wall plate and the limiting baffle frame are tightly attached through the fastening mechanism, so that the curtain wall plate can be stably installed inside the curtain wall frame to prevent the curtain wall plate from shaking, the curtain wall plate can be installed and fixed through the cooperation of the pull rod and the limiting baffle frame, a user can conveniently control the using positions of the limiting plate and the pull rod through the bolts, the user can conveniently install and detach the limiting baffle frame and the curtain wall plate through adjusting the using positions of the pull rod, the whole curtain wall frame is not required to be detached, and the curtain wall plate is convenient to maintain and replace by staff.
Drawings
FIG. 1 is a schematic diagram of the structure of the present utility model;
FIG. 2 is a schematic view of a curtain wall frame, spacing baffle frame and curtain wall panel of the present utility model;
FIG. 3 is a cross-sectional view of the stationary box of the present utility model;
FIG. 4 is a rear view of the curtain wall frame of the present utility model;
fig. 5 is an enlarged view of a portion of fig. 3 a in accordance with the present utility model.
In the figure: 1. a curtain wall frame; 2. curtain wall plates; 3. a limit baffle frame; 4. a fixed box; 5. a limiting plate; 6. an elastic sheet; 7. a pull rod; 8. a pushing block; 9. a bolt; 10. briquetting; 11. a fastening mechanism; 1101. a positioning frame; 1102. a screw; 1103. a pressing plate; 1104. a knob; 12. sealing the rubber ring; 13. a positioning groove; 14. a mounting column; 15. a mounting plate; 16. a mounting hole; 17. a movable opening; 18. a slide block; 19. and a sliding groove.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
In order to solve the technical problems of troublesome operation, time and labor waste when the curtain wall plate 2 is replaced by the existing building curtain wall, as shown in fig. 1 to 5, the following preferred technical scheme is provided:
The utility model provides a preassembled energy-conserving curtain of building, including curtain frame 1, curtain frame 1's inner chamber is provided with curtain wallboard 2, curtain wallboard 2's front side is provided with spacing fender frame 3, curtain frame 1 both sides's top and the equal fixedly connected with of bottom fixed box 4, fixed box 4's inner chamber is provided with limiting plate 5, limiting plate 5's rear side fixedly connected with elastic sheet 6, limiting plate 5's front side fixedly connected with pull rod 7, pull rod 7's front side runs through to spacing fender frame 3's front side, limiting plate 5 front side's top fixedly connected with ejector pad 8, fixed box 4's top is provided with bolt 9, fixed box 4 and fixedly connected with briquetting 10 are run through to bolt 9's bottom, curtain frame 1 rear side's both sides equal fixedly connected with fastening mechanism 11.
The fastening mechanism 11 comprises a positioning frame 1101, a screw 1102 is arranged on the rear side of the positioning frame 1101, a pressing plate 1103 is movably connected with the front side of the screw 1102, and a rubber protection pad is arranged on the front side of the pressing plate 1103.
The rear side of the screw 1102 is fixedly connected with a knob 1104, and the front side of the screw 1102 is movably connected with a pressing plate 1103 through a bearing.
Specifically, fix curtain frame 1 in the building surface through the cooperation of erection column 14 and mounting panel 15 when using, when curtain board 2 takes place to damage and need change, rotate knob 1104, make screw rod 1102 drive clamp plate 1103 no longer extrude curtain wallboard 2, afterwards rotate bolt 9, bolt 9 drives briquetting 10 no longer extrudees push block 8, simultaneously elastic slice 6 resets and drives limiting plate 5 and pull rod 7 and remove, pull rod 7 removes and does not contact with spacing fender frame 3, pull out the inner chamber of curtain frame 1 with spacing fender frame 3 and curtain wallboard 2, can take out curtain board 2, insert new curtain board 2 between spacing fender frame 3 and curtain frame 1, reset curtain wallboard 2 and spacing fender frame 3 and rotate bolt 9 again, make pull rod 7 block spacing fender frame 3, afterwards rotate knob 1104 makes clamp plate 1103 extrude curtain wallboard 2, accomplish the change of curtain wallboard 2, do not need the staff to dismantle whole curtain frame 1, reduce staff's overhead operation's time, improve the security.
In order to solve the technical problem that the sealing effect after the installation of the curtain wall plate 2 is poor, rainwater and dust easily enter the inside of the curtain wall frame 1, as shown in fig. 2, the following preferred technical scheme is provided:
The back side of the limiting baffle frame 3 is fixedly connected with a sealing rubber ring 12, and the top and the bottom of two sides of the curtain wall frame 1 are provided with positioning grooves 13 matched with the pull rods 7.
The rear side fixedly connected with erection column 14 of fixed case 4, the rear side fixedly connected with mounting panel 15 of erection column 14, mounting hole 16 has all been seted up to the top and the bottom of mounting panel 15 front side.
Specifically, can closely laminate with spacing fender frame 3 and curtain board 2 through sealing rubber circle 12, prevent rainwater and dust entering curtain frame 1 inside, can make things convenient for the installation of curtain frame 1 fixed through erection column 14 and mounting panel 15.
In order to solve the technical problem of poor stability when the limiting plate 5 moves, as shown in fig. 3 and 5, the following preferred technical scheme is provided:
The top of the fixed box 4 is provided with a threaded hole matched with the bolt 9, and the front side of the fixed box 4 is provided with a movable opening 17 matched with the pull rod 7.
The bottom of the limiting plate 5 is fixedly connected with a sliding block 18, and a sliding groove 19 matched with the sliding block 18 is formed in the bottom of the inner cavity of the fixed box 4.
Specifically, the pull rod 7 can be conveniently moved through the movable opening 17, and the limit plate 5 can be stably moved back and forth through the sliding block 18 and the sliding groove 19.
Working principle: when the curtain wall frame 1 is fixed on the outer surface of a building through the cooperation of the mounting posts 14 and the mounting plates 15, when the curtain wall plate 2 is damaged and needs to be replaced, the knob 1104 is rotated, the screw rod 1102 drives the pressing plate 1103 to not squeeze the curtain wall plate 2 any more, then the bolt 9 is rotated, the bolt 9 drives the pressing block 10 to not squeeze the push block 8 any more, meanwhile, the elastic piece 6 resets to drive the limiting plate 5 and the pull rod 7 to move, the pull rod 7 moves to be not in contact with the limiting baffle frame 3, the limiting baffle frame 3 and the curtain wall plate 2 are pulled out of the inner cavity of the curtain wall frame 1, the curtain wall plate 2 can be pulled out, the new curtain wall plate 2 is inserted between the limiting baffle frame 3 and the curtain wall frame 1, the curtain wall plate 2 and the limiting baffle frame 3 are reset, the bolt 9 is rotated again, the pull rod 7 is clamped to clamp the limiting baffle frame 3, then the knob 1104 is rotated to enable the pressing plate 1103 to squeeze the curtain wall plate 2, replacement of the curtain wall plate 2 is completed, the whole curtain wall frame 1 is not required to be disassembled by workers, the high-altitude operation time of workers is shortened, and the safety is improved.
To sum up: this energy-conserving curtain of pre-installation formula building uses through curtain wall board 2, spacing fender frame 3, fixed box 4, limiting plate 5, elastic piece 6, pull rod 7, pusher 8, bolt 9 and briquetting 10's cooperation, has solved the troublesome operation when current building curtain changes curtain wall board 2, the problem of wasting time and energy.
It is noted that relational terms such as first and second, and the like are used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Moreover, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present utility model have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made therein without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. The utility model provides a preassembled energy-conserving curtain of building, includes curtain frame (1), its characterized in that: the utility model discloses a curtain frame, including curtain frame (1), fixed box (4), fixed box (5), fixed box (4) and fastening mechanism (11), curtain frame (1) are provided with curtain wallboard (2) in the inner chamber of curtain frame (1), the front side of curtain board (2) is provided with spacing fender frame (3), the top and the equal fixedly connected with of bottom of curtain frame (1) rear side both sides, the inner chamber of fixed box (4) is provided with limiting plate (5), the rear side fixedly connected with elastic sheet (6) of limiting plate (5), the front side fixedly connected with pull rod (7) of limiting plate (5), the front side of pull rod (7) runs through to the front side of spacing fender frame (3), the top fixedly connected with ejector pad (8) of limiting plate (5) front side, the top of fixed box (4) is provided with bolt (9), the bottom of bolt (9) runs through fixed box (4) and fixedly connected with briquetting (10), the both sides of curtain frame (1) rear side all fixedly connected with fastening mechanism (11).
2. The prefabricated building energy-saving curtain wall according to claim 1, wherein: the fastening mechanism (11) comprises a positioning frame (1101), a screw rod (1102) is arranged at the rear side of the positioning frame (1101), the front side of the screw rod (1102) penetrates through the positioning frame (1101) and is movably connected with a pressing plate (1103), and a rubber protection pad is arranged at the front side of the pressing plate (1103).
3. A prefabricated building energy saving curtain wall according to claim 2, wherein: the rear side of the screw rod (1102) is fixedly connected with a knob (1104), and the front side of the screw rod (1102) is movably connected with the pressing plate (1103) through a bearing.
4. The prefabricated building energy-saving curtain wall according to claim 1, wherein: the rear side of the limiting baffle frame (3) is fixedly connected with a sealing rubber ring (12), and the top and the bottom of two sides of the curtain wall frame (1) are provided with positioning grooves (13) matched with the pull rods (7).
5. The prefabricated building energy-saving curtain wall according to claim 1, wherein: the rear side fixedly connected with erection column (14) of fixed box (4), the rear side fixedly connected with mounting panel (15) of erection column (14), mounting hole (16) have all been seted up at top and the bottom of mounting panel (15) front side.
6. The prefabricated building energy-saving curtain wall according to claim 1, wherein: screw holes matched with the bolts (9) are formed in the top of the fixed box (4), and a movable opening (17) matched with the pull rod (7) is formed in the front side of the fixed box (4).
7. The prefabricated building energy-saving curtain wall according to claim 1, wherein: the bottom of limiting plate (5) fixedly connected with slider (18), spout (19) that use with slider (18) cooperation are seted up to the bottom of fixed box (4) inner chamber.
CN202322699490.6U 2023-10-09 2023-10-09 Preassembled energy-saving building curtain wall Active CN221030885U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322699490.6U CN221030885U (en) 2023-10-09 2023-10-09 Preassembled energy-saving building curtain wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322699490.6U CN221030885U (en) 2023-10-09 2023-10-09 Preassembled energy-saving building curtain wall

Publications (1)

Publication Number Publication Date
CN221030885U true CN221030885U (en) 2024-05-28

Family

ID=91132390

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322699490.6U Active CN221030885U (en) 2023-10-09 2023-10-09 Preassembled energy-saving building curtain wall

Country Status (1)

Country Link
CN (1) CN221030885U (en)

Similar Documents

Publication Publication Date Title
CN109024895B (en) Wall body board convenient to install for assembly building
CN221030885U (en) Preassembled energy-saving building curtain wall
CN210053471U (en) Energy-saving monitoring device convenient to overhaul
CN211209412U (en) Noise reduction type gear low-speed motor
CN111980525A (en) Energy-conserving window mounting structure of assembled
CN220628636U (en) Direct current screen cabinet body
CN219867032U (en) Wall-mounted power auxiliary equipment monitoring display screen
CN221057270U (en) Intelligent capacitor capable of improving overhaul efficiency
CN211377963U (en) Solar aluminum profile with heat insulation function
CN219451199U (en) Assembled curtain wall convenient to installation
CN217204874U (en) Partition wall prefabricated component mounting structure based on ultra-thin steel frame
CN217105717U (en) Novel energy-saving unit type super high-rise building curtain wall mounting structure
CN216044815U (en) Aluminum honeycomb panel convenient to dismantle equipment
CN218894254U (en) Curtain wall convenient to install
CN214531433U (en) Steel construction top cap is used in power station factory building construction
CN220082772U (en) Wall-mounted structure convenient to assemble and disassemble for installing camera at construction site
CN217473021U (en) Ordinary temperature aluminium baffle PP composite filter
CN221236542U (en) Shower door handle convenient to installation is dismantled
CN220705152U (en) Building aluminum profile aluminum template convenient to detach
CN220150630U (en) Photovoltaic glass wall structure with decoration function
CN212453287U (en) Integrated furred ceiling mounting bracket convenient to installation
CN220397209U (en) Lifting adjustment control structure of monitor
CN217106339U (en) Shelter capable of realizing quick installation and disassembly effects
CN218295113U (en) Power distribution monitor
CN217028399U (en) Automatic protection frame for engineering construction

Legal Events