CN220955444U - Foundation pile drilling machine for municipal engineering construction - Google Patents

Foundation pile drilling machine for municipal engineering construction Download PDF

Info

Publication number
CN220955444U
CN220955444U CN202322216097.7U CN202322216097U CN220955444U CN 220955444 U CN220955444 U CN 220955444U CN 202322216097 U CN202322216097 U CN 202322216097U CN 220955444 U CN220955444 U CN 220955444U
Authority
CN
China
Prior art keywords
foundation pile
drilling machine
pile drilling
engineering construction
support frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322216097.7U
Other languages
Chinese (zh)
Inventor
董方晓
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Hualu Highway Engineering Co ltd
Original Assignee
Qingdao Hualu Highway Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Hualu Highway Engineering Co ltd filed Critical Qingdao Hualu Highway Engineering Co ltd
Priority to CN202322216097.7U priority Critical patent/CN220955444U/en
Application granted granted Critical
Publication of CN220955444U publication Critical patent/CN220955444U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

The utility model discloses a foundation pile drilling machine for municipal engineering construction, which relates to the technical field of foundation pile drilling, in particular to a foundation pile drilling machine for municipal engineering construction, comprising a movable platform, a mounting seat arranged on the movable platform, a support frame movably sleeved on the mounting seat, a dustproof barrel with an opening at the bottom and arranged on the side surface of the support frame, a bearing platform arranged in the dustproof barrel in a sliding manner, a driving motor arranged at the top of the bearing platform, and a drill rod connected to the bottom of an output shaft of the driving motor. This foundation pile drilling machine for municipal works construction is through setting up the bull-dozer board in the both sides of support frame, when having earth to pile up, utilizes hydraulic stem two to promote the bull-dozer board and outwards removes, outwards promotes earth, and the hydraulic stem is removed by the both sides of hydraulic stem three promotion hydraulic stem two directions again, makes the bull-dozer board push away earth to both sides, avoids earth to pile up in punching the position, influences subsequent work of punching.

Description

Foundation pile drilling machine for municipal engineering construction
Technical Field
The utility model relates to the technical field of foundation pile drilling, in particular to a foundation pile drilling machine for municipal engineering construction.
Background
In the process of building a house, foundation piles are required to be built firstly, holes or grooves with a certain depth are required to be drilled into the ground when the foundation piles are built, foundation pile plates are installed in the holes or grooves, and then the foundation pile plates are extended to pile up the wall surface, so that the stability of the house building is ensured, and a foundation pile drilling machine is required to be used in the drilling process.
Patent publication number CN211524707U proposes a building civil engineering construction foundation pile drilling machine, which comprises a bod, the upper end surface of organism is close to the position screwed connection of one side and has the pneumatic cylinder, and the inside of pneumatic cylinder runs through and is provided with the hydraulic stem, the top welding of hydraulic stem has the connecting seat, and the bottom of connecting seat is provided with first bearing frame, the lower extreme of first bearing frame runs through and is provided with first pivot, and the lower extreme of first pivot is provided with the drilling rod, the top screwed connection of connecting seat has first motor, wherein the upper end of organism is provided with spraying mechanism. The drilling machine that sets up has spraying mechanism and can spray the dust fall to the surrounding environment at the in-process that the foundation pile was constructed in the drilling, has set up second bearing and second pivot simultaneously between spraying mechanism and organism and can drive spraying mechanism and carry out 360 rotations to can carry out 360 and spray the dust fall, make the dust fall effect better. When the structure is in actual use, the drill rod rotates and punches, the soil in the hole is upwards conveyed, a large amount of soil piles can be piled around the hole along with the progress of punching work, the continuous soil discharging is affected, the traditional process requires workers to timely clean the conveyed soil aside, a large amount of labor is required to be consumed in the process, and the workers can have great potential safety hazards in cleaning in the rotation process of the drill rod. Therefore, the foundation pile drilling machine for municipal engineering construction is provided.
Disclosure of utility model
Aiming at the defects of the prior art, the utility model provides a foundation pile drilling machine for municipal engineering construction, which solves the problems in the prior art.
In order to achieve the above purpose, the utility model is realized by the following technical scheme: the utility model provides a foundation pile drilling machine for municipal works construction, includes moving platform, installs the mount pad on moving platform, and the activity cup joints the support frame on the mount pad, the side-mounting of support frame has a bottom open-ended dustproof section of thick bamboo, the inside slidable mounting of dustproof section of thick bamboo has load-bearing platform, driving motor is installed at load-bearing platform's top, driving motor output shaft's bottom is connected with the drilling rod, the side-mounting of dustproof section of thick bamboo has the wash pipe, moving platform's bottom is connected with hydraulic stem two, be connected with the bulldozer blade on hydraulic stem two's the output shaft.
Optionally, the top activity of mobile platform has cup jointed hydraulic rod one, the one end that the hydraulic rod one kept away from mobile platform and the side swing joint of support frame.
Optionally, servo motor is installed at the top of support frame, servo motor output shaft's bottom is connected with the lead screw, the external screw thread of lead screw has cup jointed the slider, slider and loading platform fixed connection.
Optionally, water spraying ports distributed at equal intervals are arranged on the side face of the cleaning pipe, and the water spraying ports extend to the inside of the dustproof barrel.
Optionally, storage water tank and water delivery pump are installed at moving platform's top, the input port of water delivery pump and the inside intercommunication of storage water tank, the delivery outlet of water delivery pump is connected with the raceway, the one end and the wash pipe intercommunication of water delivery pump are kept away from to the raceway.
Optionally, the bulldozer plate is in a circular arc structure, and the bulldozer plate is symmetrically distributed on two sides of the supporting frame.
Optionally, a third hydraulic rod is movably sleeved at the bottom of the mobile platform, and an output shaft of the third hydraulic rod is movably connected with the side face of the second hydraulic rod.
The utility model provides a foundation pile drilling machine for municipal engineering construction, which has the following beneficial effects:
1. This foundation pile drilling machine for municipal works construction is through setting up the bull-dozer board in the both sides of support frame, when having earth to pile up, utilizes hydraulic stem two to promote the bull-dozer board and outwards removes, outwards promotes earth, and the hydraulic stem is removed by the both sides of hydraulic stem three promotion hydraulic stem two directions again, makes the bull-dozer board push away earth to both sides, avoids earth to pile up in punching the position, influences subsequent work of punching.
2. This foundation pile drilling machine for municipal works construction through set up dustproof section of thick bamboo in the outside of drilling rod, can reduce the dust and to the diffusion all around, and the water jet is to the inside water spray of dustproof section of thick bamboo simultaneously, can play the effect of dust fall, is favorable to the protection to the environment, and after drilling is accomplished, the water jet can spray water to the surface of drilling rod to wash the drilling rod, avoid earth to be stained with the surface at the drilling rod.
Drawings
FIG. 1 is a schematic diagram of the structure of the present utility model;
FIG. 2 is a schematic view of another angle of the present utility model;
FIG. 3 is a schematic view of the present utility model in semi-section;
FIG. 4 is a schematic view of the dustproof cylinder of the present utility model in a cut-away configuration;
fig. 5 is a schematic bottom view of the present utility model.
In the figure: 1. a mobile platform; 2. a mounting base; 3. a support frame; 4. a first hydraulic rod; 5. a dust-proof cylinder; 6. a servo motor; 7. a screw rod; 8. a slide block; 9. a load-bearing platform; 10. a driving motor; 11. a drill rod; 12. cleaning the tube; 13. a water jet; 14. a water storage tank; 15. a water pump; 16. a water pipe; 17. a second hydraulic rod; 18. a bulldozer plate; 19. and a hydraulic rod III.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments.
Referring to fig. 1 to 2, the present utility model provides a technical solution: the utility model provides a foundation pile drilling machine for municipal works construction, including moving platform 1, install mount pad 2 on moving platform 1, support frame 3 on mount pad 2 is cup jointed in the activity, moving platform 1's top activity has cup jointed hydraulic stem one 4, hydraulic stem one 4 is used for promoting support frame 3 and rotates around mount pad 2, make support frame 3 can overturn to vertical state from the horizontality, hydraulic stem one 4 is kept away from moving platform 1's one end and support frame 3's side swing joint, support frame 3's side-mounting has bottom open-ended dustproof section of thick bamboo 5, through set up dustproof section of thick bamboo 5 in the outside of drilling rod 11, can reduce the dust and to the diffusion all around, be favorable to the protection of environment.
Referring to fig. 2 to 3, a servo motor 6 is installed at the top of the support frame 3, a screw rod 7 is connected to the bottom of an output shaft of the servo motor 6, a sliding block 8 is sleeved on an external thread of the screw rod 7, the screw rod 7 is driven to rotate by the servo motor 6, the sliding block 8 can move up and down along the screw rod 7, so that a drill rod 11 is pushed to move downwards, the sliding block 8 is fixedly connected with a bearing platform 9, the bearing platform 9 is slidably installed in the dustproof barrel 5, a driving motor 10 is installed at the top of the bearing platform 9, a drill rod 11 is connected to the bottom of an output shaft of the driving motor 10, and the drill rod 11 is driven to rotate by the driving motor 10, so that the drill rod 11 can be drilled.
Referring to fig. 1 and 4, a cleaning pipe 12 is installed on the side of the dust-proof barrel 5, water spraying ports 13 distributed at equal intervals are installed on the side of the cleaning pipe 12, the water spraying ports 13 extend into the dust-proof barrel 5, after drilling is completed, the water spraying ports 13 can spray water to the surface of the drill rod 11 so as to clean the drill rod 11, soil is prevented from adhering to the surface of the drill rod 11, a water storage tank 14 and a water delivery pump 15 are installed on the top of the mobile platform 1, the water storage tank 14 is used for storing clean water, an input port of the water delivery pump 15 is communicated with the interior of the water storage tank 14, an output port of the water delivery pump 15 is connected with a water delivery pipe 16, one end, away from the water delivery pump 15, of the water delivery pipe 16 is communicated with the cleaning pipe 12, clean water in the water storage tank 14 is delivered into the water delivery pipe 16 through the water delivery pump 15, and clean water is delivered into the cleaning pipe 12 through the water delivery pipe 16.
Referring to fig. 1 and 5, a second hydraulic rod 17 is connected to the bottom of the moving platform 1, a bulldozer 18 is connected to an output shaft of the second hydraulic rod 17, the bulldozer 18 is in a circular arc structure, when soil is accumulated, the bulldozer 18 is pushed to move outwards by the second hydraulic rod 17 to push the soil outwards, the bulldozer 18 is symmetrically distributed on two sides of the supporting frame 3, a third hydraulic rod 19 is movably sleeved at the bottom of the moving platform 1, an output shaft of the third hydraulic rod 19 is movably connected with the side face of the second hydraulic rod 17, and the third hydraulic rod 19 is arranged to push the second hydraulic rod 17 to move to two sides by the third hydraulic rod 19, so that the bulldozer 18 pushes the soil to two sides to avoid the soil accumulation at a punching position.
In sum, this foundation pile drilling machine for municipal works construction, when using, stop moving platform 1 to suitable position back, promote support frame 3 through hydraulic stem one and rotate, erect drilling rod 11, then driving motor 10 drives drilling rod 11 and rotate, servo motor 6 drives lead screw 7 simultaneously and rotates, make slider 8 drive loading platform 9 and move down, drive drilling rod 11 drills, when the earth of discharging is more, promote the bulldozer blade 18 outwards to remove with hydraulic stem two 17, promote hydraulic stem two 17 to both sides separately by hydraulic stem three 19 afterwards, thereby push away earth to both sides, retrieve drilling rod 11 again to the inside of dustproof section of thick bamboo 5 after the drilling is accomplished, then transport water to water jet 13 department blowout through water pump 15, wash drilling rod 11, can.
In the description of the present utility model, it should be noted that, directions or positional relationships indicated by terms such as "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., are based on directions or positional relationships shown in the drawings, are merely for convenience of description and simplification of description, and do not indicate or imply that the apparatus or element to be referred to must have a specific direction, be constructed and operated in the specific direction, and thus should not be construed as limiting the present utility model; the terms "first," "second," "third," and the like, are used for descriptive purposes only and are not to be construed as indicating or implying relative importance, and furthermore, unless explicitly specified and limited otherwise, the terms "mounted," "connected," "coupled," and the like are to be construed broadly, and may be fixedly coupled, detachably coupled, or integrally coupled, for example; can be mechanically or electrically connected; can be directly connected or indirectly connected through an intermediate medium, and can be communication between two elements. The specific meaning of the above terms in the present utility model will be understood in specific cases by those of ordinary skill in the art. Moreover, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present utility model have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made therein without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. The utility model provides a foundation pile drilling machine for municipal works construction, includes moving platform (1), installs mount pad (2) on moving platform (1), support frame (3) on mount pad (2) are cup jointed in the activity, its characterized in that: the side-mounting of support frame (3) has bottom open-ended dustproof section of thick bamboo (5), the inside slidable mounting of dustproof section of thick bamboo (5) has loading platform (9), driving motor (10) are installed at the top of loading platform (9), the bottom of driving motor (10) output shaft is connected with drilling rod (11), the side-mounting of dustproof section of thick bamboo (5) has cleaning tube (12), the bottom of mobile platform (1) is connected with hydraulic rod two (17), be connected with bull-dozer board (18) on the output shaft of hydraulic rod two (17).
2. The foundation pile drilling machine for municipal engineering construction according to claim 1, wherein: the top of the mobile platform (1) is movably sleeved with a first hydraulic rod (4), and one end, away from the mobile platform (1), of the first hydraulic rod (4) is movably connected with the side face of the support frame (3).
3. The foundation pile drilling machine for municipal engineering construction according to claim 1, wherein: the top of support frame (3) is installed servo motor (6), servo motor (6) output shaft's bottom is connected with lead screw (7), the external screw thread of lead screw (7) has cup jointed slider (8), slider (8) and loading platform (9) fixed connection.
4. The foundation pile drilling machine for municipal engineering construction according to claim 1, wherein: the side face of the cleaning pipe (12) is provided with water spraying ports (13) which are distributed at equal intervals, and the water spraying ports (13) extend into the dustproof barrel (5).
5. The foundation pile drilling machine for municipal engineering construction according to claim 1, wherein: the top of mobile platform (1) is installed storage water tank (14) and water delivery pump (15), the input port of water delivery pump (15) communicates with the inside of storage water tank (14), the delivery outlet of water delivery pump (15) is connected with raceway (16), the one end that water delivery pump (15) was kept away from to raceway (16) communicates with cleaning tube (12).
6. The foundation pile drilling machine for municipal engineering construction according to claim 1, wherein: the bulldozer comprises a supporting frame (3), and is characterized in that the bulldozer body (18) is in a circular arc structure, and the bulldozer body (18) is symmetrically distributed on two sides of the supporting frame (3).
7. The foundation pile drilling machine for municipal engineering construction according to claim 1, wherein: the bottom of the mobile platform (1) is movably sleeved with a hydraulic rod III (19), and an output shaft of the hydraulic rod III (19) is movably connected with the side face of the hydraulic rod II (17).
CN202322216097.7U 2023-08-17 2023-08-17 Foundation pile drilling machine for municipal engineering construction Active CN220955444U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322216097.7U CN220955444U (en) 2023-08-17 2023-08-17 Foundation pile drilling machine for municipal engineering construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322216097.7U CN220955444U (en) 2023-08-17 2023-08-17 Foundation pile drilling machine for municipal engineering construction

Publications (1)

Publication Number Publication Date
CN220955444U true CN220955444U (en) 2024-05-14

Family

ID=91018241

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322216097.7U Active CN220955444U (en) 2023-08-17 2023-08-17 Foundation pile drilling machine for municipal engineering construction

Country Status (1)

Country Link
CN (1) CN220955444U (en)

Similar Documents

Publication Publication Date Title
CN103643970B (en) Multiaxis Swing Drill Rig and construction method thereof
CN220955444U (en) Foundation pile drilling machine for municipal engineering construction
CN112536864A (en) Wood cutting device for civil engineering
CN219412475U (en) Drilling machine for foundation bored pile construction
CN216142705U (en) Drilling equipment is used in construction of drilling bored concrete pile of stable use
CN215169757U (en) Long auger drilling machine with earth cleaning function
CN114086618B (en) Modularization milling flutes device of wall construction is even gone on underground
CN214739966U (en) Civil engineering construction gravel and sand humidification device
CN211038499U (en) Pile drilling and hole drilling device for building
CN114809142A (en) Perpendicular digging device of deep basal pit
CN113775298A (en) Stirring head for in-situ solidification treatment of ultra-soft soil and use method thereof
CN210834236U (en) Soil measuring device for building engineering
CN220929354U (en) In-site pile hole soil cleaning equipment for constructional engineering
CN212835591U (en) Ecological sludge treatment device
CN218894350U (en) Higher wall automatic plastering device suitable for interior decoration
CN219733288U (en) Pile driver for constructional engineering
CN220580948U (en) Novel drilling pile machine
CN217151359U (en) Building decoration is with balcony heat preservation shovel device
CN217139767U (en) Hand propelled for building engineering watering dust suppression equipment
CN218125887U (en) House building afforestation protective structure
CN215804648U (en) Strutting arrangement is used in underground construction
CN220011923U (en) Portal crane convenient to build
CN215632744U (en) Dig and change down-the-hole drill
CN117489158B (en) Supporting framework structure of building unit
CN220013548U (en) Slope protection building device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant