CN220909080U - Lifting hanging basket for building construction - Google Patents

Lifting hanging basket for building construction Download PDF

Info

Publication number
CN220909080U
CN220909080U CN202322589339.7U CN202322589339U CN220909080U CN 220909080 U CN220909080 U CN 220909080U CN 202322589339 U CN202322589339 U CN 202322589339U CN 220909080 U CN220909080 U CN 220909080U
Authority
CN
China
Prior art keywords
basket body
wall
hanging basket
building construction
fixed block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322589339.7U
Other languages
Chinese (zh)
Inventor
李政
朱翠芹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Eryang Construction Engineering Co ltd
Original Assignee
Shandong Eryang Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Eryang Construction Engineering Co ltd filed Critical Shandong Eryang Construction Engineering Co ltd
Priority to CN202322589339.7U priority Critical patent/CN220909080U/en
Application granted granted Critical
Publication of CN220909080U publication Critical patent/CN220909080U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The utility model discloses a lifting hanging basket for building construction, which relates to the technical field of building construction and comprises a hanging basket body, wherein a protective door is hinged to the hanging basket body through a hinge, a guide groove is formed in the outer wall of the bottom of the hanging basket body, a guide rod is fixedly connected between the inner walls of the two sides of the guide groove, a buffer assembly is arranged at the bottom of the hanging basket body and comprises a first fixing block, a second fixing block and a bottom plate, and the first fixing block and the second fixing block are all connected to the guide rod in a jogged mode. According to the utility model, the buffer assembly is arranged, so that the impact force applied to the hanging basket body can be buffered when the bottom of the hanging basket body is contacted with the ground, the safety of workers is protected, the service life of the device is effectively prolonged, and the impact force of the hanging basket body to a wall surface or other working surfaces can be weakened by arranging the protection assembly, so that the wall surface or other working surfaces can be protected, and the hanging basket body can be protected.

Description

Lifting hanging basket for building construction
Technical Field
The utility model relates to the technical field of building construction, in particular to a lifting hanging basket for building construction.
Background
The hanging basket is a construction machine for building engineering high-altitude operation, can replace a traditional scaffold, lightens working intensity, is generally used in working scenes such as curtain wall installation, outer wall cleaning and the like, is erected on a building by an overhanging structure in the hanging basket in the use process, drives a hanging platform by utilizing a lifting mechanism, and runs up and down along a building elevation through a steel wire rope, and can be divided into a steel frame electric hanging basket and an aluminum alloy electric hanging basket according to materials, and is divided into a manual hanging basket, an electric hanging basket and the like according to different power sources of lifting.
But the impact force of traditional hanging flower basket when the landing is great, great impact force not only can cause the injury to constructor, also can very big reduction device's life. For this purpose, we propose a lifting basket for building construction.
Disclosure of utility model
The present utility model has been made in view of the above-mentioned problems with existing lifting baskets for building construction.
Therefore, the utility model aims to provide a lifting hanging basket for building construction, which solves the problems that the traditional hanging basket has larger impact force when being landed, the larger impact force can cause injury to constructors, and the service life of a device can be greatly shortened.
In order to achieve the above object, the present utility model provides the following technical solutions:
The utility model provides a construction lifts up hanging flower basket, includes the hanging flower basket body, there is the guard gate through the hinge on the hanging flower basket body, the guide way has been seted up on the bottom outer wall of hanging flower basket body, fixedly connected with guide bar between the both sides inner wall of guide way, the bottom of hanging flower basket body is equipped with buffer assembly, buffer assembly includes first fixed block, second fixed block and bottom plate, first fixed block and second fixed block all gomphosis are connected on the guide bar, it has first connecting rod and second connecting rod to articulate respectively on first fixed block and the second fixed block, the top outer wall of bottom plate is connected with first connecting rod, second connecting rod are articulated, the nested first spring that has on the guide bar, the both ends of first spring respectively with the outer wall of first fixed block, the outer wall fixed connection of second fixed block.
Preferably, a rubber gasket is adhered to the outer wall of the bottom plate, and the size and the structure of the rubber gasket are matched with those of the bottom plate.
Preferably, the number of the buffer assemblies is two, and the two buffer assemblies are symmetrically distributed on two sides of the bottom of the hanging basket body.
Preferably, the connecting blocks are welded on the outer wall of the top of the hanging basket body, the number of the connecting blocks is four, and the four connecting blocks are distributed at four corners of the outer wall of the top of the hanging basket body.
Further, be equipped with the protection subassembly on the outer wall of hanging flower basket body, the protection subassembly includes fixed plate, telescopic link and second spring, fixedly connected with telescopic link on the outer wall of fixed plate, the other end and the outer wall fixed connection of hanging flower basket body of telescopic link, the nested second spring that has on the telescopic link, the both ends of second spring respectively with the outer wall of fixed plate, the outer wall fixed connection of hanging flower basket body.
Preferably, the outer wall of the fixing plate is provided with a collision buffer layer, and the size and the structure of the collision buffer layer are matched with those of the fixing plate.
In the technical scheme, the utility model has the technical effects and advantages that:
1. According to the utility model, by arranging the buffer component, when the bottom of the hanging basket body is contacted with the ground, the impact force born by the hanging basket body is buffered by the buffer component, so that the safety of workers is protected, and the service life of the device is effectively prolonged.
2. According to the utility model, the protective component is arranged, so that the impact force of the hanging basket body on the wall surface or other working surfaces can be weakened when the hanging basket body shakes, and the wall surface or other working surfaces can be protected, and the hanging basket body can be protected.
Drawings
In order to more clearly illustrate the embodiments of the present utility model or the technical solutions in the prior art, the drawings required for the embodiments will be briefly described below, and it is apparent that the drawings in the following description are only some embodiments described in the present utility model, and other drawings may be obtained according to these drawings for a person having ordinary skill in the art.
FIG. 1 is a schematic perspective view of the present utility model;
FIG. 2 is a schematic cross-sectional view of the present utility model;
fig. 3 is a schematic structural view of a protection component of the present utility model.
Reference numerals illustrate:
1. a basket body; 2. a protective door; 3. a connecting block; 4. a guide groove; 5. a guide rod; 6. a buffer assembly; 61. a first fixed block; 62. a second fixed block; 63. a first link; 64. a second link; 65. a bottom plate; 66. a rubber gasket; 67. a first spring; 7. a protective assembly; 71. a fixing plate; 72. a telescopic rod; 73. a second spring; 74. and (3) colliding with the buffer layer.
Detailed Description
In order to make the technical scheme of the present utility model better understood by those skilled in the art, the present utility model will be further described in detail with reference to the accompanying drawings.
The embodiment of the utility model discloses a lifting hanging basket for building construction.
The utility model provides a lifting basket for building construction, as shown in fig. 1-3, which comprises a basket body 1, wherein a protective door 2 is hinged on the basket body 1 through a hinge, a guide groove 4 is formed on the outer wall of the bottom of the basket body 1, a guide rod 5 is fixedly connected between the inner walls of the two sides of the guide groove 4, a buffer component 6 is arranged at the bottom of the basket body 1, the buffer component 6 comprises a first fixed block 61, a second fixed block 62 and a bottom plate 65, the first fixed block 61 and the second fixed block 62 are respectively connected to the guide rod 5 in an embedded manner, a first connecting rod 63 and a second connecting rod 64 are respectively hinged on the first fixed block 61 and the second fixed block 62, a first spring 67 is nested on the guide rod 5, two ends of the first spring 67 are respectively fixedly connected with the outer wall of the first fixed block 61 and the outer wall of the second fixed block 62, and through the buffer component 6, when the bottom of the basket body 1 is contacted with the ground, the buffer force of the basket body 1 is buffered through the buffer component 6, so that the safety life of workers is effectively prolonged.
According to the lifting basket for building construction, the rubber gasket 66 is adhered to the outer wall of the bottom plate 65, the rubber gasket 66 is matched with the bottom plate 65 in size and structure, the rubber gasket 66 is arranged, preliminary buffering can be carried out when the bottom plate 65 is contacted with the ground, friction between the bottom plate 65 and a contact surface can be improved, stability of the basket body 1 when the basket body is contacted with the ground is improved, and random shaking of the basket body 1 in the placing process is prevented.
According to the lifting hanging basket for building construction, the number of the buffer assemblies 6 is two, and the two buffer assemblies 6 are symmetrically distributed on two sides of the bottom of the hanging basket body 1, so that the buffering effect on the hanging basket body 1 can be improved.
According to the lifting hanging basket for building construction, the connecting blocks 3 are welded on the outer wall of the top of the hanging basket body 1, the number of the connecting blocks 3 is four, the four connecting blocks 3 are distributed at four corners of the outer wall of the top of the hanging basket body 1, the hanging basket body 1 can be conveniently connected with a steel wire rope, and the four connecting blocks 3 can improve stability in the connection process.
According to the lifting hanging basket for building construction, the protective component 7 is arranged on the outer wall of the hanging basket body 1, the protective component 7 comprises the fixed plate 71, the telescopic rod 72 and the second spring 73, the telescopic rod 72 is fixedly connected to the outer wall of the fixed plate 71, the other end of the telescopic rod 72 is fixedly connected with the outer wall of the hanging basket body 1, the second spring 73 is nested on the telescopic rod 72, two ends of the second spring 73 are respectively fixedly connected with the outer wall of the fixed plate 71 and the outer wall of the hanging basket body 1, and the protective component 7 is arranged, so that the impact force of the hanging basket body 1 to a wall surface or other working surfaces can be weakened when the hanging basket body 1 shakes, the wall surface or other working surfaces can be protected, and the hanging basket body 1 can be protected.
According to the lifting hanging basket for building construction, the collision buffer layer 74 is arranged on the outer wall of the fixed plate 71, the size and the structure of the collision buffer layer 74 are matched with those of the fixed plate 71, a primary buffer effect can be provided, and the fixed plate 71 can be prevented from being damaged due to high hardness when colliding with a wall surface or other working surfaces.
When the device is used, the hanging basket body 1 is connected with the steel wire rope through the connecting block 3, normal operation can be achieved, the hanging basket body 1 is prevented from shaking in the lifting process, when the hanging basket body 1 shakes, the collision buffer layer 74 is firstly contacted with the wall surface and other contact surfaces to provide a primary buffer effect, then a certain pressure is applied to the fixing plate 71, so that the second spring 73 is extruded, the second spring 73 is stressed to counteract the received force through the elastic effect of the second spring 73, the impact force between the hanging basket body 1 and the wall surface or other contact surfaces is weakened, when the hanging basket body 1 is contacted with the ground, the bottom plate 65 is firstly contacted with the ground, then the bottom plate 65 is stressed, the first fixing block 61 and the second fixing block 62 are pushed to synchronously move towards the middle through the first connecting rod 63 and the second connecting rod 64, the first spring 67 is extruded, the impact force received by the hanging basket body 1 is buffered through the elastic effect of the first spring 67, the safety of workers is protected, and the service life of the device is effectively prolonged.
While certain exemplary embodiments of the present utility model have been described above by way of illustration only, it will be apparent to those of ordinary skill in the art that modifications may be made to the described embodiments in various different ways without departing from the spirit and scope of the utility model. Accordingly, the drawings and description are to be regarded as illustrative in nature and not as restrictive of the scope of the utility model, which is defined by the appended claims.

Claims (6)

1. The utility model provides a construction lifts hanging flower basket, includes hanging flower basket body (1), its characterized in that, there is guard gate (2) through the hinge on hanging flower basket body (1), guide slot (4) have been seted up on the bottom outer wall of hanging flower basket body (1), fixedly connected with guide bar (5) between the both sides inner wall of guide slot (4), the bottom of hanging flower basket body (1) is equipped with buffer assembly (6), buffer assembly (6) include first fixed block (61), second fixed block (62) and bottom plate (65), all gomphosis connection on guide bar (5) of first fixed block (61) and second fixed block (62), articulated first connecting rod (63) and second connecting rod (64) on first fixed block (61) and second fixed block (62) respectively, the top outer wall and first connecting rod (63), second connecting rod (64) of bottom plate (65) are articulated to be connected, the nested first spring (67) that has on guide bar (5), the both ends of first spring (67) are connected with outer wall (61) of first fixed block (62) respectively.
2. The building construction lifting basket according to claim 1, wherein a rubber gasket (66) is adhered to the outer wall of the bottom plate (65), and the rubber gasket (66) is matched with the bottom plate (65) in size and structure.
3. The lifting basket for building construction according to claim 1, wherein the number of the buffer assemblies (6) is two, and the two buffer assemblies (6) are symmetrically distributed on two sides of the bottom of the basket body (1).
4. The building construction lifting basket according to claim 1, wherein connecting blocks (3) are welded on the top outer wall of the basket body (1), the number of the connecting blocks (3) is four, and the four connecting blocks (3) are distributed at four corners of the top outer wall of the basket body (1).
5. The lifting basket for building construction according to claim 1, wherein a protection component (7) is arranged on the outer wall of the basket body (1), the protection component (7) comprises a fixing plate (71), a telescopic rod (72) and a second spring (73), the telescopic rod (72) is fixedly connected to the outer wall of the fixing plate (71), the other end of the telescopic rod (72) is fixedly connected with the outer wall of the basket body (1), the second spring (73) is nested on the telescopic rod (72), and two ends of the second spring (73) are fixedly connected with the outer wall of the fixing plate (71) and the outer wall of the basket body (1) respectively.
6. The lifting basket for building construction according to claim 5, wherein the outer wall of the fixing plate (71) is provided with a collision buffer layer (74), and the collision buffer layer (74) is matched with the fixing plate (71) in size and structure.
CN202322589339.7U 2023-09-23 2023-09-23 Lifting hanging basket for building construction Active CN220909080U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322589339.7U CN220909080U (en) 2023-09-23 2023-09-23 Lifting hanging basket for building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322589339.7U CN220909080U (en) 2023-09-23 2023-09-23 Lifting hanging basket for building construction

Publications (1)

Publication Number Publication Date
CN220909080U true CN220909080U (en) 2024-05-07

Family

ID=90903914

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322589339.7U Active CN220909080U (en) 2023-09-23 2023-09-23 Lifting hanging basket for building construction

Country Status (1)

Country Link
CN (1) CN220909080U (en)

Similar Documents

Publication Publication Date Title
CN220909080U (en) Lifting hanging basket for building construction
CN111163604A (en) Building electrical construction safety device
CN213626579U (en) Construction steel structure construction protection device
CN216342206U (en) Soft rock mass supporting device for underground coal mine island in dynamic pressure environment
CN215055562U (en) Building engineering safety device
CN210176265U (en) Single-rail climbing-free device
CN208633334U (en) A kind of wind-proof building curtain wall
CN113526297A (en) Elevator buffer with multistage safeguard function
CN106481087B (en) A kind of spring-piece type steel tower climbing safety device
CN217296837U (en) Building construction elevator with prevent weighing down buffer
CN217398156U (en) Elevator base with shock-absorbing structure
CN219689176U (en) Tower crane protection canopy
CN213505760U (en) Building lifting construction platform
CN215885939U (en) Safety device of elevator for building construction
CN218809944U (en) Electric single-beam crane protection device
CN219100678U (en) Wall collision preventing structure of hanging basket for building high-altitude construction
CN212128945U (en) Bus stop uses intelligent banister ware
CN220889367U (en) Support base with protection structure
CN215167885U (en) Attached lifting scaffold
CN212477533U (en) Highway traffic safety device
CN216638582U (en) Household elevator with anti-collision function
CN211338418U (en) Rail guard is used in elevator installation dimension
CN218621824U (en) Highway bridge construction hanging flower basket
CN217264098U (en) Elevator trouble emergency protection device
CN217173216U (en) Stress dispersion's lift extends rail guard for platform

Legal Events

Date Code Title Description
GR01 Patent grant