CN220896212U - Super high-rise building cable laying construction equipment - Google Patents

Super high-rise building cable laying construction equipment Download PDF

Info

Publication number
CN220896212U
CN220896212U CN202322883503.5U CN202322883503U CN220896212U CN 220896212 U CN220896212 U CN 220896212U CN 202322883503 U CN202322883503 U CN 202322883503U CN 220896212 U CN220896212 U CN 220896212U
Authority
CN
China
Prior art keywords
plate
rod
rise building
super high
cable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322883503.5U
Other languages
Chinese (zh)
Inventor
曹海芬
付言新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Fuma Communication Information Technology Co ltd
Original Assignee
Shanghai Fuma Communication Information Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Fuma Communication Information Technology Co ltd filed Critical Shanghai Fuma Communication Information Technology Co ltd
Priority to CN202322883503.5U priority Critical patent/CN220896212U/en
Application granted granted Critical
Publication of CN220896212U publication Critical patent/CN220896212U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Clamps And Clips (AREA)

Abstract

The application belongs to the technical field of cable installation equipment, and discloses super high-rise building cable laying construction equipment which comprises an installation seat, wherein a penetrating hole is formed in the center of the installation seat, a pull rod is arranged right above the penetrating hole, two ends of the pull rod are fixedly connected with the installation seat, vertical rods are arranged on the left side and the right side of the penetrating hole, a fixed sleeve plate is fixedly sleeved on the outer wall of the vertical rods, fixed vertical plates are arranged on the left side and the right side of the top end of the installation seat, and clamping mechanisms are arranged on one sides, close to each other, of the two fixed vertical plates; according to the application, the rotating rod is controlled to rotate, so that the two clamping plates clamp the joint cable, the telescopic plate is controlled to adjust the position, the locking screw rod is controlled to clamp the cable, the rotating rod is controlled to rotate, the joint plate clamps the cable, and the limiting screw rod is controlled to rotate, so that the supporting plate supports the joint plate, and the clamping and fixing of cables with different diameters are facilitated.

Description

Super high-rise building cable laying construction equipment
Technical Field
The application relates to the technical field of cable installation equipment, in particular to super high-rise building cable laying construction equipment.
Background
In the construction process of super high-rise building, in order to ensure the normal operation of equipment in the building, cables are required to be laid in the building, and in order to facilitate the laying of the cables in the super high-rise building, the cables are required to be pulled by using laying construction equipment to lay, so that the working efficiency is accelerated.
Via search disclosure (bulletin) number: CN214422075U discloses a super high-rise building cable laying construction equipment, which comprises a substrate, the last fixed surface of base plate is connected with and hangs rope part, the thru hole has been seted up at the middle part of base plate, the first telescopic link of left and right sides fixedly connected with of base plate, both sides are provided with the second telescopic link around the base plate, and it is through seting up the thru hole, pierces through the cable from the thru hole in to pull out a part, guarantee sufficient cable clamping volume, effectively avoid appearing the phenomenon of cable slippage, improve holistic security and reliability.
In the actual use process, the diameter of the through hole is fixed with the structure of the cable clamping part on the square plate, and the cable used in the super high-rise building is different in size, so that the cable cannot be effectively clamped and locked through the square plate if the diameter of the cable is smaller than the diameter of the structure of the cable clamping part by the square plate in the clamping process.
In order to solve the problems, the application provides a super high-rise building cable laying construction device.
Disclosure of utility model
The application provides super high-rise building cable laying construction equipment which adopts the following technical scheme:
The utility model provides a super high-rise building cable lays construction equipment, includes the mount pad, the central point of mount pad puts and is equipped with the penetration hole, be equipped with the pull rod directly over the penetration hole, the both ends fixed connection mount pad of pull rod, both sides all are equipped with the pole setting about the penetration hole, fixed cover is equipped with fixed sleeve plate on the outer wall of pole setting, the top left and right sides of mount pad all is equipped with fixed riser, two one side that fixed riser is close to each other all is equipped with fixture.
Through above-mentioned technical scheme, be convenient for carry out spacing fixed to the cable in the use.
Further, four fixing rods are arranged on the outer wall of the mounting seat, and telescopic rods are arranged on one sides of the fixing rods, which are not connected with the mounting seat, and universal wheels are connected to the telescopic rods.
Through above-mentioned technical scheme, the guarantee mount pad of being convenient for steadily rises.
Further, fixture includes the installation piece, be equipped with the recess on the installation piece, and be equipped with the bull stick in the recess, the bottom fixedly connected with of bull stick stirs the board, install adjustment mechanism on stirring the board, the top of bull stick is connected with splint, just be equipped with two crossbeams on the splint.
Through above-mentioned technical scheme, be convenient for carry out the centre gripping to the cable fixedly.
Further, one side that the diaphragm is close to the through hole is equipped with the expansion plate, both sides are equipped with the screw thread and run through the through-hole around the expansion plate, and are equipped with locking screw in the screw thread runs through the through-hole, are located same two diaphragms of splint all are equipped with locking screw in one side that keeps away from each other.
Through above-mentioned technical scheme, be convenient for consolidate the position of cable.
Further, adjustment mechanism includes the connecting block, be equipped with the mounting groove on the connecting block, and be equipped with the dwang in the mounting groove, fixedly connected with laminating board on the outer wall of dwang.
Through above-mentioned technical scheme, be convenient for consolidate the cable.
Further, adjustment mechanism still includes the fixed plate, the upper and lower both ends of fixed plate are equipped with the screw thread through-hole, and are equipped with stop screw in the screw thread through-hole, the layer board is installed on stop screw's top, be connected with flexible gangbar between the bottom of layer board and the top of fixed plate.
Through above-mentioned technical scheme, be convenient for fix the position of laminating board.
Further, the telescopic linkage rod consists of a positioning rod and a movable rod, and a groove matched with the diameter of the movable rod is formed in the top end of the positioning rod.
Through above-mentioned technical scheme, the vertical concertina movement of guarantee flexible gangbar is convenient for.
In summary, the application has the following beneficial technical effects:
Through controlling the bull stick rotation, make two splint centre gripping laminating cables to after the control expansion plate adjustment position, control locking screw laminating cable, the control dwang rotates again, makes laminating plate clamp cable, and the control spacing screw rotates again, makes the layer board hold the laminating board, conveniently carries out the centre gripping to the cable of different diameters fixedly.
Drawings
FIG. 1 is a schematic diagram of the overall structure of the present application;
FIG. 2 is a schematic view of a clamping mechanism according to the present application;
fig. 3 is a schematic structural view of an adjusting mechanism of the present application.
The reference numerals in the figures illustrate:
1. A mounting base; 2. a penetrating hole; 3. a pull rod; 4. a vertical rod; 5. fixing the sleeve plate; 6. fixing the vertical plate; 7. a clamping mechanism; 8. a fixed rod; 9. a telescopic rod; 10. a universal wheel; 11. a mounting block; 12. a rotating rod; 13. a toggle plate; 14. an adjusting mechanism; 15. a clamping plate; 16. a cross plate; 17. a telescoping plate; 18. locking the screw; 19. locking the screw rod; 20. a connecting block; 21. a rotating lever; 22. bonding plates; 23. a fixing plate; 24. a limit screw; 25. a supporting plate; 26. and a telescopic linkage rod.
Detailed Description
The technical solutions in the embodiments of the present application will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present application; it is apparent that the described embodiments are only some embodiments of the present application, not all embodiments, and that all other embodiments obtained by persons of ordinary skill in the art without making creative efforts based on the embodiments in the present application are within the protection scope of the present application.
In the description of the present application, it should be noted that the positional or positional relationship indicated by the terms such as "upper", "lower", "inner", "outer", "top/bottom", etc. are based on the positional or positional relationship shown in the drawings, are merely for convenience of describing the present application and simplifying the description, and do not indicate or imply that the apparatus or elements referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus should not be construed as limiting the present application. Furthermore, the terms "first," "second," and the like, are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present application, it should be noted that, unless explicitly specified and limited otherwise, the terms "mounted," "configured to," "engaged with," "connected to," and the like are to be construed broadly, and may be either fixedly connected, detachably connected, or integrally connected, for example; can be mechanically or electrically connected; can be directly connected or indirectly connected through an intermediate medium, and can be communication between two elements. The specific meaning of the above terms in the present application will be understood in specific cases by those of ordinary skill in the art.
Examples:
The embodiment of the application discloses a super high-rise building cable laying construction device, referring to fig. 1, which comprises a mounting seat 1, wherein a penetrating hole 2 is arranged at the center position of the mounting seat 1, a pull rod 3 is arranged right above the penetrating hole 2, two ends of the pull rod 3 are fixedly connected with the mounting seat 1, vertical rods 4 are arranged at the left side and the right side of the penetrating hole 2, fixed sleeve plates 5 are fixedly sleeved on the outer walls of the vertical rods 4, fixed vertical plates 6 are arranged at the left side and the right side of the top end of the mounting seat 1, clamping mechanisms 7 are arranged at the sides, close to each other, of the two fixed vertical plates 6, and a cable is wound around the two fixed sleeve plates 5 after passing through the penetrating hole 2, so that the cable can be conveniently reinforced, and the cable is prevented from falling off.
Referring to fig. 1, four fixing rods 8 are disposed on the outer wall of the mounting seat 1, a telescopic rod 9 is disposed on one side of the four fixing rods 8, which is not connected with the mounting seat 1, universal wheels 10 are connected to the telescopic rod 9, the fixing rods 8 are hollow columns, an opening matched with the diameter of the telescopic rod 9 in size is disposed on one side of the fixing rods 8, springs are disposed in the fixing rods 8, and two ends of each spring are fixedly connected with the telescopic rod 9 and the inner wall of the fixing rod 8.
Referring to fig. 2, the clamping mechanism 7 includes a mounting block 11, a groove is formed in the mounting block 11, a rotating rod 12 is arranged in the groove, the rotating rod 12 is connected with the mounting block 11 in a rotating manner, a poking plate 13 is fixedly connected to the bottom end of the rotating rod 12, an adjusting mechanism 14 is arranged on the poking plate 13, the top end of the rotating rod 12 is connected with a clamping plate 15, two transverse plates 16 are arranged on the clamping plate 15, and the clamping plate 15 is attached to the outer wall of a cable through rotation of the rotating rod 12, so that the cable can be clamped.
Referring to fig. 2, a telescopic plate 17 is disposed on one side of a transverse plate 16 near the penetrating hole 2, openings matched with the telescopic plate 17 are disposed on one side of the transverse plate 16 connected with the telescopic plate 17, after the clamping plate 15 clamps a cable, the telescopic plate 17 is controlled to move, the position of the locking screw 18 is adjusted, the locking screw 18 is controlled to rotate to be attached to the cable to reinforce the position of the cable, threaded through holes are disposed on the front side and the rear side of the telescopic plate 17, the locking screw 18 is disposed in the threaded through holes, locking screws 19 are disposed on one sides, far away from each other, of two transverse plates 16 of the same clamping plate 15, and the locking screws 19 are rotated into the transverse plate 16 and connected with the telescopic plate 17, so that the position of the telescopic plate 17 can be fixed.
Referring to fig. 3, the adjusting mechanism 14 includes a connection block 20, the connection block 20 is fixedly connected with the toggle plate 13, a mounting groove is formed in the connection block 20, a rotation rod 21 is arranged in the mounting groove, the rotation rod 21 is rotationally connected with the connection block 20, a laminating plate 22 is fixedly connected to the outer wall of the rotation rod 21, and the laminating plate 22 can be driven to be laminated on the outer wall of the cable through rotation of the rotation rod 21.
Referring to fig. 3, the adjusting mechanism 14 further includes a fixing plate 23, two ends of the fixing plate 23 are fixedly connected with inner walls of grooves on the mounting block 11, threaded through holes are formed in the upper end and the lower end of the fixing plate 23, a limit screw 24 is arranged in the threaded through holes, a supporting plate 25 is mounted on the top end of the limit screw 24, the limit screw 24 is connected with the supporting plate 25 through a hinge, a telescopic linkage rod 26 is connected between the bottom end of the supporting plate 25 and the top end of the fixing plate 23, and the position of the attaching plate 22 can be fixed by controlling the limit screw 24 to rotate upwards and pushing the supporting plate 25 to abut against the attaching plate 22.
Referring to fig. 3, the telescopic link 26 is composed of a positioning rod and a movable rod, and a groove matched with the diameter of the movable rod is formed in the top end of the positioning rod, so that the telescopic link 26 can vertically move up and down.
The implementation principle of the embodiment is as follows: when the cable is used, the cable passes through the penetrating hole 2, is wound around the periphery of the two fixed sleeve plates 5 and is pulled between the two clamping mechanisms 7, the rotating rod 12 is controlled to rotate, the two clamping plates 15 clamp the attached cable, the telescopic plate 17 is controlled to adjust the position, the locking screw 18 is controlled to attach the cable, the rotating rod 21 is controlled to rotate, the attaching plate 22 clamps the cable, the limiting screw 24 is controlled to rotate, and the supporting plate 25 supports the attaching plate 22.
The above embodiments are not intended to limit the scope of the present application, so: all equivalent changes in structure, shape and principle of the application should be covered in the scope of protection of the application.

Claims (7)

1. The utility model provides a super high-rise building cable lays construction equipment, includes mount pad (1), its characterized in that: the center position of mount pad (1) is equipped with through hole (2), be equipped with pull rod (3) directly over through hole (2), both ends fixed connection mount pad (1) of pull rod (3), both sides all are equipped with pole setting (4) about through hole (2), fixed cover is equipped with fixed sleeve board (5) on the outer wall of pole setting (4), the top left and right sides of mount pad (1) all is equipped with fixed riser (6), two one side that fixed riser (6) are close to each other all is equipped with fixture (7).
2. The super high-rise building cabling construction equipment according to claim 1, wherein: four fixing rods (8) are arranged on the outer wall of the mounting seat (1), one sides of the four fixing rods (8) which are not connected with the mounting seat (1) are provided with telescopic rods (9), and universal wheels (10) are connected to the telescopic rods (9).
3. The super high-rise building cabling construction equipment according to claim 1, wherein: the clamping mechanism (7) comprises a mounting block (11), a groove is formed in the mounting block (11), a rotating rod (12) is arranged in the groove, a stirring plate (13) is fixedly connected to the bottom end of the rotating rod (12), an adjusting mechanism (14) is arranged on the stirring plate (13), a clamping plate (15) is connected to the top end of the rotating rod (12), and two transverse plates (16) are arranged on the clamping plate (15).
4. A super high-rise building cabling construction apparatus according to claim 3, wherein: one side of the transverse plate (16) close to the penetrating hole (2) is provided with a telescopic plate (17), the front side and the rear side of the telescopic plate (17) are provided with threaded penetrating holes, locking screws (18) are arranged in the threaded penetrating holes, and one side, away from each other, of the two transverse plates (16) of the clamping plate (15) is provided with the locking screws (19).
5. A super high-rise building cabling construction apparatus according to claim 3, wherein: the adjusting mechanism (14) comprises a connecting block (20), a mounting groove is formed in the connecting block (20), a rotating rod (21) is arranged in the mounting groove, and a laminating plate (22) is fixedly connected to the outer wall of the rotating rod (21).
6. A super high-rise building cabling construction apparatus according to claim 3, wherein: the adjusting mechanism (14) further comprises a fixing plate (23), threaded through holes are formed in the upper end and the lower end of the fixing plate (23), a limiting screw (24) is arranged in each threaded through hole, a supporting plate (25) is mounted at the top end of each limiting screw (24), and a telescopic linkage rod (26) is connected between the bottom end of each supporting plate (25) and the top end of the fixing plate (23).
7. The super high-rise building cabling construction equipment according to claim 6, wherein: the telescopic linkage rod (26) consists of a positioning rod and a movable rod, and a groove matched with the diameter of the movable rod is formed in the top end of the positioning rod.
CN202322883503.5U 2023-10-26 2023-10-26 Super high-rise building cable laying construction equipment Active CN220896212U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322883503.5U CN220896212U (en) 2023-10-26 2023-10-26 Super high-rise building cable laying construction equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322883503.5U CN220896212U (en) 2023-10-26 2023-10-26 Super high-rise building cable laying construction equipment

Publications (1)

Publication Number Publication Date
CN220896212U true CN220896212U (en) 2024-05-03

Family

ID=90844084

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322883503.5U Active CN220896212U (en) 2023-10-26 2023-10-26 Super high-rise building cable laying construction equipment

Country Status (1)

Country Link
CN (1) CN220896212U (en)

Similar Documents

Publication Publication Date Title
CN111550119B (en) Installation and construction method of communication tower
CN220896212U (en) Super high-rise building cable laying construction equipment
CN212616777U (en) Pipeline installation is with locking hoisting accessory convenient to installation
CN210576391U (en) Antenna bracket for communication engineering
CN113944851A (en) Balance expansion piece and balance equipment
CN113218976B (en) Split type X-ray detection device for strain clamp of power transmission line
CN211320298U (en) Electronic communication antenna support
CN212203919U (en) Video monitoring equipment with adjustable monitoring height
CN206958531U (en) A kind of adjustable commanding elevation mounting bracket of monitoring device device
CN210137002U (en) Antenna boom for communication engineering
CN214037771U (en) Telescopic wall hanging bracket
CN220982291U (en) House construction straightness measuring device that hangs down
CN220190349U (en) Adjustable cable support
CN216158762U (en) A mounting structure for security protection equipment
CN215417762U (en) Transformer base with lifting and leveling functions
CN219888915U (en) Adjustable anti-seismic support
CN219910041U (en) Component rotating device for steel structure building
CN216133967U (en) Universal 5G antenna mounting support structure
CN214947599U (en) Pole is embraced to tower
CN213930008U (en) Multi-azimuth adjusting bracket of satellite signal receiving device
CN220094422U (en) Auxiliary positioning mechanism for boiler pipeline installation
CN219994884U (en) Temporary installation device of outdoor monitoring equipment
CN216692873U (en) Marine CCTV erecting device
CN216276337U (en) Anti-drop reinforcing assembly of building curtain wall