CN220828029U - Clamping and positioning pile for cantilever beam - Google Patents

Clamping and positioning pile for cantilever beam Download PDF

Info

Publication number
CN220828029U
CN220828029U CN202321224665.1U CN202321224665U CN220828029U CN 220828029 U CN220828029 U CN 220828029U CN 202321224665 U CN202321224665 U CN 202321224665U CN 220828029 U CN220828029 U CN 220828029U
Authority
CN
China
Prior art keywords
plate
steel
clamping
sleeve
positioning plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321224665.1U
Other languages
Chinese (zh)
Inventor
王世刚
吴申申
张菊连
李兆元
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Hongtu Equipment Engineering Co ltd
Original Assignee
Guangzhou Hongtu Equipment Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Hongtu Equipment Engineering Co ltd filed Critical Guangzhou Hongtu Equipment Engineering Co ltd
Priority to CN202321224665.1U priority Critical patent/CN220828029U/en
Application granted granted Critical
Publication of CN220828029U publication Critical patent/CN220828029U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The utility model discloses a clamping and positioning pile for cantilever beams, which comprises the following components: the locating plate, the sleeve and the clamping plate; the positioning plate is arranged on the I-steel, a hook is arranged on one side of the positioning plate and can hook the I-steel, the other side of the positioning plate and the clamping plate clamp the I-steel from two sides of the I-steel respectively, the sleeve is arranged on the positioning plate, and a jacking piece is arranged on one side of the sleeve. This cantilever beam is with pressing from both sides tight locating pile can realize the installation fixed to the locating plate, and the pole setting is adorned in the sleeve pipe and is tightly held up through the top tight piece, can realize the fixed to the pole setting, compares prior art, can dismantle the setting, does not need cutting locating piece, labour saving and time saving, also does not harm the I-steel.

Description

Clamping and positioning pile for cantilever beam
Technical Field
The utility model relates to the technical field of cantilever scaffold positioning structures, in particular to a clamping positioning pile for a cantilever beam.
Background
In the building field or bridge field, the locating piece of traditional scaffold pole setting of encorbelmenting is the direct welding on scaffold frame I steel of encorbelmenting, can not adjust at will according to outer frame pole interval after the welding. If the adjustment is needed, only the original welded upright rod positioning piece can be cut off, a new upright rod positioning piece is welded again at a designated position, the working procedures are more, and the adjustment can be completed only by cooperation of multiple persons, so that the time and the labor are consumed; in addition, in the process of cutting the original vertical rod locating piece and re-welding the vertical rod locating piece, fatigue damage is easily caused to the I-steel, after a certain number of cyclic welding operations, cracks and even fracture occur to the I-steel, the service life of the I-steel is greatly reduced, and the construction process has a large potential safety hazard.
Disclosure of utility model
Aiming at the problems in the prior art, the clamping and positioning pile for the cantilever beam is provided.
The specific technical scheme is as follows:
the utility model provides a cantilever beam is with pressing from both sides tight locating pile mainly includes: the locating plate, the sleeve and the clamping plate;
the positioning plate is arranged on the I-steel, a hook is arranged on one side of the positioning plate and can hook the I-steel, the other side of the positioning plate and the clamping plate clamp the I-steel from two sides of the I-steel respectively, the sleeve is arranged on the positioning plate, and a jacking piece is arranged on one side of the sleeve.
The cantilever beam clamping positioning pile is characterized in that a first mounting hole is formed in the other side of the positioning plate, a second mounting hole is formed in the clamping plate, and a fastener penetrates through the first mounting hole and the second mounting hole.
The clamping and positioning pile for the cantilever beam is characterized in that the fastening piece is a first screw, and a nut is arranged on the first screw.
The clamping and positioning pile for the cantilever beam is characterized in that the jacking piece is a jackscrew or a second screw.
In the above-mentioned clamping and positioning pile for cantilever beam, the positioning plate is made of steel material, and the clamping plate is made of steel material.
The technical scheme has the positive effects that:
According to the clamping and positioning pile for the cantilever beam, the positioning plate is arranged on the I-steel, the hook on one side of the positioning plate hooks the I-steel, the other side of the positioning plate is clamped and fastened through the independent clamping plate, the positioning plate can be installed and fixed, the vertical rod is arranged in the sleeve and is tightly propped through the propping piece, and the vertical rod can be fixed.
Drawings
Fig. 1 is a schematic diagram of a front view structure of a clamping and positioning pile for an overhanging beam;
FIG. 2 is a schematic view of a part of the clamping spud for the cantilever beam of FIG. 1;
fig. 3 is a schematic top view of the clamping and positioning pile for cantilever beams.
In the accompanying drawings: 1. a positioning plate; 11. a hook; 2. a sleeve; 3. a clamping plate; 31. a clamping groove; 4. i-steel; 5. a tightening member; 52. a jackscrew; 61. a first screw; 62. a nut; 7. and (5) standing a pole.
Detailed Description
The following description of the embodiments of the present utility model will be made apparent and fully in view of the accompanying drawings, in which some, but not all embodiments of the utility model are shown. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
In the description of the present utility model, it should be noted that, if terms such as "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", and the like are used, the indicated orientation or positional relationship is based on the orientation or positional relationship shown in the drawings, only for convenience of describing the present utility model and simplifying the description, and does not indicate or imply that the indicated apparatus or element must have a specific orientation, be configured and operated in a specific orientation, and thus should not be construed as limiting the present utility model. Furthermore, the terms "first," "second," "third," and the like, as used herein, are used for descriptive purposes only and are not to be construed as indicating or implying any relative importance.
In the description of the present utility model, it should be noted that unless explicitly stated and limited otherwise, the terms "mounted," "connected," and "connected" should be construed broadly, and may be, for example, fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; can be directly connected or indirectly connected through an intermediate medium, and can be communication between two elements. The specific meaning of the above terms in the present utility model will be understood in specific cases by those of ordinary skill in the art.
Referring to fig. 1 to 3, there is shown a preferred embodiment, showing a clamping spud for cantilever beams, comprising: the positioning plate 1, the sleeve 2 and the clamping plate 3;
The positioning plate 1 is arranged on the I-steel 4, a hook 11 is arranged on one side of the positioning plate 1 and can hook the I-steel 4, the I-steel 4 is clamped by the other side of the positioning plate 1 and the clamping plate 3 from two sides of the I-steel 4 respectively, the sleeve 2 is arranged on the positioning plate 1, and a jacking piece 5 is arranged on one side of the sleeve 2.
Wherein one side of the positioning plate 1 is bent downward to form an acute angle of the hook 11.
Optionally, the sleeve 2 is vertically arranged on the positioning plate 1, and the sleeve 2 is welded with the positioning plate 1 to form an integral structure.
The other side of the locating plate 1 is provided with a first mounting hole, the clamping plate 3 is provided with a second mounting hole, and a fastener penetrates through the first mounting hole and the second mounting hole.
The fastening piece is a first screw 61, and a nut 62 is arranged on the first screw 61. The splint 3 is the hang plate, is provided with draw-in groove 31 on the splint 3, and draw-in groove 31 and the edge looks block of locating plate 1 to realize the location to splint 3, make things convenient for first mounting hole with the hole process of registering of second mounting hole.
Optionally, the tightening member 5 is a jackscrew 52 or a second screw. The jacking piece 5 penetrates through the side wall of the sleeve 2 and stretches into the sleeve 2 to prop against the upright rod 7, and the upright rod 7 is inserted into the sleeve 2 to be jacked through the jacking piece 5. Optionally, the propping piece 5 is provided with multiple stems, and is arranged in an array in the axial direction of the upright rod 7 or the sleeve 2, so that a more stable propping support can be realized on the upright rod 7.
Alternatively, the positioning plate 1 is made of steel, and the clamping plate 3 is made of steel, and the shape of the clamping plate is formed by stamping through a die. For example, the steel plate can be used for manufacturing.
According to the clamping and positioning pile for the cantilever beam, the positioning plate 1 is arranged on the I-steel 4, the hook 11 at one side of the positioning plate 1 hooks the I-steel 4, the other side of the positioning plate 1 is clamped and fastened through the independent clamping plate 3, the positioning plate 1 can be installed and fixed, the vertical rod 7 is arranged in the sleeve 2 and is tightly supported through the supporting piece 5, and the vertical rod 7 can be fixed. When in use, the device can be singly used or matched with a plurality of positioning piles.
In addition, 1, the movable positioning pile is realized by connecting the upright posts 7 of the overhanging outer scaffold or the upright posts 7 of the protective rails at two sides of the bridge platform with the section steel through the positioning pile, and the positioning pile can be intensively processed in a factory, so that the forming quality and the processing quality are ensured, the site operation is simple and convenient, the time and the labor are saved, the turnover rate is high, and the on-site electric welding is reduced, so that the construction accords with the green construction characteristics of the construction engineering;
2. When the cantilever type steel bridge platform is used, the positioning pile is fastened at the selected part of the I-steel 4, then the upright posts 7 of the cantilever type outer scaffold or the upright posts 7 of the protection rails at the two sides of the bridge platform are positioned, and finally the positioning pile is fixed at the existing position, so that on-site workers do not have barriers to prevent constructors from moving when lifting, installing the I-steel 4 and installing the upright posts 7 of the cantilever type outer scaffold or the upright posts 7 of the protection rails at the two sides of the bridge platform, and the safety is improved.
3. The sleeve 2 adopted by the positioning pile is tightly fixed by the jacking piece 5, so that the positioning pile is safer and more reliable and does not slip when being used as a guardrail.
The foregoing description is only illustrative of the preferred embodiments of the present utility model and is not to be construed as limiting the scope of the utility model, and it will be appreciated by those skilled in the art that equivalent substitutions and obvious variations may be made using the description and illustrations of the present utility model, and are intended to be included within the scope of the present utility model.

Claims (4)

1. The utility model provides a cantilever beam is with pressing from both sides tight spud, which characterized in that includes: the locating plate, the sleeve and the clamping plate;
The positioning plate is arranged on the I-steel, one side of the positioning plate is provided with a hook which can hook the I-steel, the other side of the positioning plate and the clamping plate clamp the I-steel from two sides of the I-steel respectively, the sleeve is arranged on the positioning plate, and one side of the sleeve is provided with a jacking piece; the jacking piece is a jackscrew or a second screw; the jacking piece penetrates through the side wall of the sleeve and stretches into the sleeve to prop against the vertical rod, the vertical rod is inserted into the sleeve to jack tightly through the jacking piece, the clamping plate is an inclined plate, the clamping plate is provided with a clamping groove, and the clamping groove is clamped with the edge of the positioning plate.
2. The cantilever beam clamping spud of claim 1, wherein a first mounting hole is formed on the other side of the positioning plate, a second mounting hole is formed on the clamping plate, and a fastener is inserted through the first mounting hole and the second mounting hole.
3. The clamped spud for a cantilever beam according to claim 2, wherein the fastener is a first screw, and the first screw is provided with a nut.
4. A clamping spud for a cantilever beam according to claim 3, wherein the locating plate is made of steel material and the clamping plate is made of steel material.
CN202321224665.1U 2023-05-19 2023-05-19 Clamping and positioning pile for cantilever beam Active CN220828029U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321224665.1U CN220828029U (en) 2023-05-19 2023-05-19 Clamping and positioning pile for cantilever beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321224665.1U CN220828029U (en) 2023-05-19 2023-05-19 Clamping and positioning pile for cantilever beam

Publications (1)

Publication Number Publication Date
CN220828029U true CN220828029U (en) 2024-04-23

Family

ID=90722366

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321224665.1U Active CN220828029U (en) 2023-05-19 2023-05-19 Clamping and positioning pile for cantilever beam

Country Status (1)

Country Link
CN (1) CN220828029U (en)

Similar Documents

Publication Publication Date Title
CN220828029U (en) Clamping and positioning pile for cantilever beam
US4462573A (en) Support post for temporary guard-rail chains
CN210326963U (en) Adjustable bracket special for tunnel
CN209817385U (en) Cantilever beam for cantilever scaffold
CN110295607B (en) Larsen steel sheet pile supporting structure and supporting method
CN211114837U (en) Earthwork supporting template
CN212688718U (en) Bent cap reinforcement bed-jig structure
CN109038232B (en) Embedded part structure for lightning rod
CN220868905U (en) Telescopic guard rail support structure
CN219951712U (en) Detachable steel beam guardrail free of drilling
CN214533854U (en) Accurate positioning device for foundation embedded bolt
CN218518055U (en) Telescopic tool for adjusting deviation of socket joint type steel column
CN211839648U (en) Top support device and auxiliary correction device of crane girder
CN218061459U (en) A template supporting device for building engineering
CN217027112U (en) Foundation pit supporting device
CN218708745U (en) Metal external wall panel lifting and positioning device
CN212803279U (en) Supporting device for vault construction formwork of shield split starting underground excavation channel structure
CN108980537B (en) On-spot precast concrete post stands up support
CN211545645U (en) Box roof beam installation lug
CN213951950U (en) Sleeve type steel box girder guardrail upright rod
CN219509262U (en) Novel detachable horizontal safety net hook
CN214246567U (en) Reusable wall connecting component
CN220036070U (en) Adjustable pole setting connection structure of support body encorbelments
CN211923449U (en) Tool type overhanging protective frame
CN216196804U (en) Horizontal protector encorbelments

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant