CN220768777U - Prefabricated case roof construction integration operation platform - Google Patents

Prefabricated case roof construction integration operation platform Download PDF

Info

Publication number
CN220768777U
CN220768777U CN202322549274.3U CN202322549274U CN220768777U CN 220768777 U CN220768777 U CN 220768777U CN 202322549274 U CN202322549274 U CN 202322549274U CN 220768777 U CN220768777 U CN 220768777U
Authority
CN
China
Prior art keywords
operation platform
box girder
sides
utility
model
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322549274.3U
Other languages
Chinese (zh)
Inventor
雷振东
段攀龙
王强
王军刚
鲁福禄
徐俊飞
胡菊艳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202322549274.3U priority Critical patent/CN220768777U/en
Application granted granted Critical
Publication of CN220768777U publication Critical patent/CN220768777U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses an integrated operation platform for prefabricated box girder top plate construction, which comprises box girder frame bodies, rails, lower supporting beams, operation platforms, stairs and guardrails, wherein the two box girder frame bodies are symmetrically arranged, the operation platforms are arranged at the upper ends of the box girder frame bodies, one side of each box girder frame body is provided with a stair which is in butt joint with the operation platform, guardrails are arranged at the two sides of each stair and the outer side of each operation platform, the lower supporting beams are uniformly arranged at the lower ends of the box girder frame bodies, rollers are arranged at the two sides of the lower ends of the lower supporting beams, the rails are symmetrically arranged at the two sides of the lower parts of the lower supporting beams, and the rails are matched with the corresponding rollers.

Description

Prefabricated case roof construction integration operation platform
Technical Field
The utility model relates to the technical field of precast box girder top plate construction equipment, in particular to a precast box girder top plate construction integrated operation platform.
Background
The box girder is a necessary structure for bridge construction, and is generally prefabricated in advance, so that the construction is convenient;
when the box girder is prefabricated, a box girder top plate is needed, and the traditional box girder top plate steel bars and concrete are poured and constructed, because no construction operation platform is arranged on two sides of the template top, a worker tramples on the top plate steel bars during construction, secondary deformation and damage of the top plate steel bars are easily caused, and safety accidents are easily caused due to inconvenient movement of the worker during concrete pouring construction, so that the box girder is quite unsafe;
therefore, in view of the technical problems described above, there is a need for an integrated operation platform for prefabricated box girder roof construction.
Disclosure of Invention
The utility model aims to overcome the defects of the technology and provide an integrated operation platform for the construction of a top plate of a prefabricated box girder.
In order to solve the technical problems, the technical scheme provided by the utility model is that the integrated operation platform for the construction of the top plate of the prefabricated box girder is as follows: including case roof beam support body, track, lower part supporting beam, operation platform, stair and guardrail, case roof beam support body symmetry is provided with two, case roof beam support body upper end is equipped with operation platform, case roof beam support body one side is equipped with the stair with operation platform butt joint, stair both sides and operation platform outside all are equipped with the guardrail, lower part supporting beam evenly is equipped with a plurality of in case roof beam support body lower extreme, lower part supporting beam lower extreme both sides all are equipped with the gyro wheel, lower part supporting beam below both sides all symmetry are equipped with the track, track and the gyro wheel cooperation that corresponds.
Compared with the prior art, the utility model has the advantages that: an operation platform is additionally arranged on the box girder frame body, so that people can be prevented from trampling the top plate steel bars during the construction of the top plate steel bars and the concrete pouring, a safe operation platform is provided for the workers, and the construction quality of the box girder top plate is improved;
the both sides of lower part supporting beam lower extreme all are equipped with the gyro wheel, and lower part supporting beam below both sides all symmetry are equipped with the track, and track and corresponding gyro wheel cooperation are convenient for remove equipment like this.
Drawings
Fig. 1 is a schematic view of a first structure of an integrated operation platform for constructing a top plate of a prefabricated box girder.
Fig. 2 is a second structural schematic diagram of the prefabricated box girder roof construction integrated operation platform of the present utility model.
As shown in the figure:
1. the box girder frame body, 2, the track, 3, lower part supporting beam, 4, operation platform, 5, stair, 6, guardrail, 7, gyro wheel.
Detailed Description
For the purpose of making the objects, technical solutions and advantages of the embodiments of the present utility model more apparent, the technical solutions of the embodiments of the present utility model will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present utility model, and it is apparent that the described embodiments are some embodiments of the present utility model, but not all embodiments of the present utility model. The components of the embodiments of the present utility model generally described and illustrated in the figures herein may be arranged and designed in a wide variety of different configurations.
Referring to fig. 1-2, the prefabricated box girder top plate construction integrated operation platform comprises a box girder frame body 1, rails 2, a lower supporting beam 3, an operation platform 4, stairs 5 and guardrails 6, wherein the box girder frame body 1 is symmetrically provided with two operation platforms 4, one side of the box girder frame body 1 is provided with the stairs 5 which are in butt joint with the operation platforms 4, the guardrails 6 are respectively arranged on two sides of the stairs 5 and the outer side of the operation platforms 4, the lower supporting beam 3 is uniformly provided with a plurality of rollers 7 at the lower end of the box girder frame body 1, the rails 2 are symmetrically arranged on two sides of the lower end of the lower supporting beam 3, and the rails 2 are matched with the corresponding rollers 7.
In the concrete implementation of the utility model, the operation platform 4 is additionally arranged on the box girder frame body 1, so that people can be prevented from stepping on the top plate steel bars during the construction of the top plate steel bars and the concrete pouring, and meanwhile, a safe operation platform is provided for the workers, so that the construction quality of the top plate of the box girder is improved;
the both sides of lower part supporting beam 3 lower extreme all are equipped with gyro wheel 7, and lower part supporting beam 3 below both sides all symmetry are equipped with track 2, and track 2 and corresponding gyro wheel 7 cooperation are convenient for remove equipment like this.
In the description of the embodiments of the present utility model, it should be noted that, if the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc. indicate an azimuth or a positional relationship based on that shown in the drawings, or an azimuth or a positional relationship in which the product of the present utility model is conventionally put when used, it is merely for convenience of describing the present utility model and simplifying the description, and it does not indicate or imply that the apparatus or element to be referred to must have a specific azimuth, be configured and operated in a specific azimuth, and thus should not be construed as limiting the present utility model. Furthermore, the terms "first," "second," "third," and the like are used merely to distinguish between descriptions and should not be construed as indicating or implying relative importance.
Furthermore, the terms "horizontal," "vertical," "overhang" and the like, if any, do not denote a requirement that the component be absolutely horizontal or overhang, but rather may be slightly inclined. As "horizontal" merely means that its direction is more horizontal than "vertical", and does not mean that the structure must be perfectly horizontal, but may be slightly inclined.
In the description of the embodiments of the present utility model, "plurality" means at least 2.
In the description of the embodiments of the present utility model, it should also be noted that, unless explicitly specified and limited otherwise, the terms "disposed," "mounted," "connected," and "connected" should be construed broadly, and may be, for example, fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; can be directly connected or indirectly connected through an intermediate medium, and can be communication between two elements. The specific meaning of the above terms in the present utility model can be understood by those of ordinary skill in the art according to the specific circumstances.
The utility model and its embodiments have been described above with no limitation, and the actual construction is not limited to the embodiments of the utility model as shown in the drawings. In summary, if one of ordinary skill in the art is informed by this disclosure, a structural manner and an embodiment similar to the technical solution should not be creatively devised without departing from the gist of the present utility model.

Claims (1)

1. The utility model provides a prefabricated roof beam roof construction integration operation platform which characterized in that: including case roof beam support body (1), track (2), lower part supporting beam (3), operation platform (4), stair (5) and guardrail (6), case roof beam support body (1) symmetry is provided with two, case roof beam support body (1) upper end is equipped with operation platform (4), case roof beam support body (1) one side is equipped with stair (5) with operation platform (4) butt joint, stair (5) both sides and operation platform (4) outside all are equipped with guardrail (6), lower part supporting beam (3) evenly are equipped with a plurality of in case roof beam support body (1) lower extreme, lower part supporting beam (3) lower extreme both sides all are equipped with gyro wheel (7), lower part supporting beam (3) below both sides all symmetry are equipped with track (2), track (2) and corresponding gyro wheel (7) cooperation.
CN202322549274.3U 2023-09-20 2023-09-20 Prefabricated case roof construction integration operation platform Active CN220768777U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322549274.3U CN220768777U (en) 2023-09-20 2023-09-20 Prefabricated case roof construction integration operation platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322549274.3U CN220768777U (en) 2023-09-20 2023-09-20 Prefabricated case roof construction integration operation platform

Publications (1)

Publication Number Publication Date
CN220768777U true CN220768777U (en) 2024-04-12

Family

ID=90599500

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322549274.3U Active CN220768777U (en) 2023-09-20 2023-09-20 Prefabricated case roof construction integration operation platform

Country Status (1)

Country Link
CN (1) CN220768777U (en)

Similar Documents

Publication Publication Date Title
CN110965470A (en) Main tower cross brace structure system capable of bearing three-way load and construction method
CN112663971A (en) Steel structure roof pre-assembly sliding installation device and installation method
CN209384110U (en) Pier stud bent cap protective platform
JP2006077521A (en) Bridge constructing apparatus
CN220768777U (en) Prefabricated case roof construction integration operation platform
CN107338809B (en) Subway station portal template and its Fast Installation construction method under super-high voltage
CN113373815A (en) Construction method for on-site wet joint of prefabricated bent cap
CN110846462B (en) Method for integrally mounting converter oxygen lance fixing rail and steel structure upright post
CN210948697U (en) Door type steel formwork supporting system for construction of rectangular tunnel secondary lining structure
CN116949946A (en) Construction method for bridge bridging of small-radius curve bridge
CN113738125B (en) Construction method for lifting limited-space large-span steel structure of station house under line
CN115573597A (en) Fully-assembled concrete canopy and construction method thereof
CN215803328U (en) Sliding device for mounting prefabricated PK plate
CN210214149U (en) Transit station crossing original coal conveying trestle
CN114108499A (en) Suspended casting beam reference section hinged type triangular bracket combined hanging basket integrated device and construction method thereof
CN108797350B (en) Tower column inner and outer stiff skeleton device and construction method thereof
CN109403674B (en) Assembled prefabrication factory for bridge construction and construction method thereof
JPH05280012A (en) Movable formwork process and device used therefor
CN209114884U (en) A kind of high-altitude steel structure on-site consolidation H profile steel rail mounted moulding bed
CN219527354U (en) Pouring template system of oblique leg steel structure bridge
CN112681148A (en) Floor-free pier column capping beam template dismounting device and construction method
CN210458956U (en) Template of prefabricated bent cap
CN218911129U (en) Prefabricated post-pouring construction structure of bottom mould of hollow tower column middle partition plate
CN220950728U (en) Steel construction elevator basis in car ramp department
CN219316360U (en) Stair operation platform tool

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant