CN220768773U - Building construction frame - Google Patents

Building construction frame Download PDF

Info

Publication number
CN220768773U
CN220768773U CN202322444149.6U CN202322444149U CN220768773U CN 220768773 U CN220768773 U CN 220768773U CN 202322444149 U CN202322444149 U CN 202322444149U CN 220768773 U CN220768773 U CN 220768773U
Authority
CN
China
Prior art keywords
fixing
column
support column
holes
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322444149.6U
Other languages
Chinese (zh)
Inventor
任治安
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202322444149.6U priority Critical patent/CN220768773U/en
Application granted granted Critical
Publication of CN220768773U publication Critical patent/CN220768773U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model relates to the technical field of building construction, in particular to a building construction frame which comprises a long plate and a plurality of fixing hooks symmetrically arranged on the long plate, wherein a plurality of first support columns and second support columns are arranged at the bottom of the long plate and are in sliding connection, a plurality of fixing feet and fixing components used for stabilizing the construction frame are respectively connected to the first support columns and the second support columns.

Description

Building construction frame
Technical Field
The utility model relates to the technical field of building construction, in particular to a building construction frame.
Background
The construction frame, namely the scaffold, is a temporary building tool erected for workers to operate and solve vertical and horizontal transportation at a construction site, is mainly used for outer walls, interior decoration or places where the layer height is higher and cannot be directly constructed, and is mainly used for maintenance of upper and lower movable safety nets or peripheral safety nets of constructors, high-altitude installation members and the like;
referring to the patent reference document with the application number of CN202120318150.2, the name of a building construction frame is that a first hoop is matched with a second hoop for use, so that the first diagonal draw bar and the second diagonal draw bar can be driven to rotate on a first frame body and a second frame body, and meanwhile, a connecting sleeve and a rotating shaft are matched for use, so that the first frame body and the second frame body can be rotated, and the scaffold is integrally folded;
but the high of scaffold is higher, and constructor can lead to the scaffold focus unstable when the scaffold edge walks, and the scaffold has the risk of empting, exists very big potential safety hazard.
For this purpose, we have devised a construction work frame.
Disclosure of Invention
The utility model aims to solve the problem that the center of gravity of a construction frame is unstable and the falling risk exists in the prior art, and provides a building construction frame.
In order to achieve the above purpose, the present utility model adopts the following technical scheme:
the utility model provides a building construction frame, includes longeron and symmetry setting a plurality of fixed hooks on the longeron, the bottom of longeron is equipped with a plurality of first support columns and second support columns, and first support column and second support column sliding connection, a plurality of be connected with a plurality of fixed feet and the fixed subassembly that are used for stable construction frame on first support column and the second support column respectively.
Preferably, a plurality of connecting holes and fixing holes are formed in the first support columns and the second support columns.
Preferably, a plurality of connecting rods are connected between two adjacent first support columns and two adjacent second support columns, a plurality of end fixedly connected with connecting pins of fixed feet, a plurality of threaded holes are formed in both ends of the connecting pins and the connecting rods, and bolts are connected to the threaded holes.
Preferably, a plurality of connecting pins and two ends of the connecting rod are inserted into the connecting holes, and the bolts penetrate through the fixing holes to be in threaded connection with the threaded holes.
Preferably, a plurality of fixing hooks symmetrically arranged on the long plate are buckled on the connecting rod.
Preferably, the fixing assembly includes:
the first fixing column is rotationally connected with the second support column through a rotating shaft;
the second fixing column is connected with the first fixing column in a sliding manner;
the third fixing column is connected with the second fixing column in a sliding manner;
the jacks are arranged on the first fixing column, the second fixing column and the third fixing column, and fixing pins are connected in the jacks.
The beneficial effects of the utility model are as follows:
1. the utility model adopts the fixing feet and the fixing components to enlarge the contact area between the construction frame and the ground, thereby achieving the purpose of reinforcing the construction frame, avoiding the unstable gravity center of the construction frame when constructors walk at the edges of the long plates, and further avoiding the problem of dumping the construction frame caused by the unstable gravity center.
2. According to the utility model, the fixing assembly is contracted, the fixing assembly and the second support column are folded, the fixing legs and the connecting rods are detached from the first support column and the second support column by rotating the bolts, so that the occupation of space is reduced, and the transportation is facilitated.
Drawings
Fig. 1 is a schematic structural view of a construction frame according to the present utility model;
FIG. 2 is a partial cross-sectional view of a construction work frame according to the present utility model;
FIG. 3 is a schematic illustration of the connection of a second support column and a fixing assembly of a construction frame according to the present utility model;
fig. 4 is a schematic connection diagram of a long plate, a connecting rod and a second support column of a construction frame according to the present utility model.
In the figure: 1. a long plate; 2. a first support column; 3. a second support column; 4. a fixed foot; 5. a first fixing column; 6. a second fixing column; 7. a third fixing column; 8. a connecting pin; 9. a connecting rod; 10. a connection hole; 11. a fixing hole; 12. a bolt; 13. a fixing pin; 14. a jack; 15. and a fixing hook.
Detailed Description
Referring to fig. 1 to 4, a construction frame comprises a long plate 1 and a plurality of fixing hooks 15 symmetrically arranged on the long plate 1, wherein a plurality of first support columns 2 and second support columns 3 are arranged at the bottom of the long plate 1, the first support columns 2 and the second support columns 3 are in sliding connection, and a plurality of fixing feet 4 and fixing components for stabilizing the construction frame are respectively connected to the plurality of first support columns 2 and the plurality of second support columns 3.
Referring to fig. 1, a plurality of connection holes 10 and fixing holes 11 are formed in each of the plurality of first support columns 2 and the plurality of second support columns 3, the connection rod 9 is mounted through the connection holes 10, and the connection rod 9 is fixed through the fixing holes 11.
Referring to fig. 1 and 2, a plurality of connecting rods 9 are connected between two adjacent first support columns 2 and two adjacent second support columns 3, connecting pins 8 are fixedly connected to the ends of the plurality of fixing legs 4, threaded holes are formed in both ends of the plurality of connecting pins 8 and the connecting rods 9, and bolts 12 are connected to the threaded holes; the plurality of connecting pins 8 and the two ends of the connecting rod 9 are inserted into the connecting holes 10, and bolts 12 penetrate through the fixing holes 11 and are in threaded connection with the threaded holes.
When the construction frame is installed, two ends of the connecting rod 9 are inserted into the connecting holes 10, threaded holes on the connecting rod 9 are opposite to the fixing holes 11 on the first support column 2 and the third support column 3, then the bolts 12 are inserted into the fixing holes 11, the bolts 12 are screwed by a tool, the bolts 12 are in threaded connection with the threaded holes on the connecting rod 9, so that the connecting rod 9 is installed, the second support column 3 can be limited by the connecting rod 9 to slide, and constructors can climb onto the long plate 1 by means of the connecting rod 9;
the connecting pin 8 on the fixed foot 4 is inserted into the connecting hole 10, the threaded hole on the connecting pin 8 is opposite to the lowest fixing hole 11 of the first support column 2, then the bolt 12 is inserted into the fixing hole 11, the bolt 12 is screwed by a tool, the bolt 12 is in threaded connection with the threaded hole on the connecting pin 8, the installation of the fixed foot 4 is realized, the contact area between the construction frame and the ground can be increased by the fixed foot 4, and the placement of the construction frame is more stable.
Referring to fig. 1, a plurality of fixing hooks 15 symmetrically provided on the long plate 1 are fastened on the connecting rod 9, and the installation is fast and the disassembly is convenient.
Referring to fig. 2, 3 and 4, the fixing assembly includes a first fixing post 5, and the first fixing post 5 is rotatably connected with the second support post 3 through a rotation shaft; the fixed assembly further comprises a second fixed column 6, and the second fixed column 6 is in sliding connection with the first fixed column 5; the fixing assembly further comprises a third fixing column 7, and the third fixing column 7 is in sliding connection with the second fixing column 6; the fixing assembly further comprises a plurality of insertion holes 14, the insertion holes 14 are formed in the first fixing column 5, the second fixing column 6 and the third fixing column 7, and the insertion holes 14 are connected with fixing pins 13.
During installation, the first support column 5 is rotated, the second support column 6 and the third support column 7 are sequentially pulled out, the fixing pin 13 is inserted into the insertion hole 14, the second support column 6 and the third support column 7 are limited to slide, the third support column 7 is in contact with the ground, and the construction frame is reinforced;
during transportation, the connecting rod 9, the fixing feet 4 and the long plate 1 are removed, the third fixing column 7 is retracted into the second fixing column 6, the second fixing column 6 is retracted into the first fixing column 5, the first fixing column 5 and the second supporting column 3 are rotated to be folded, and finally the second supporting column 3 is retracted into the second supporting column 2, so that space occupation is reduced, and accordingly transportation is convenient, the cross sections of the first supporting column 2, the second supporting column 3 and the fixing component are U-shaped, the weight of the first supporting column 2, the weight of the second supporting column 3 and the weight of the fixing component are greatly reduced, and convenience is brought to transportation of a construction frame and installation and disassembly of the construction frame by constructors.
The working principle of the utility model is as follows:
the heights of the first support column 2 and the second support column 3 are adjusted, the connecting rod 9 is inserted into the connecting hole 10 to limit the second support column 3 to slide, the connecting pin 8 is inserted into the connecting hole 10, and the connecting pin 8, the connecting rod 9 and the first support column 2 and the second support column 3 are fixed through the bolt 12;
then rotate first support column 5, pull out second support column 6 and third support column 7 in proper order, insert fixed pin 13 again in jack 14, restrict second support column 6 and third support column 7 slip, third support column 7 and ground contact consolidate the scaffold, buckle the fixed hook 15 buckle on connecting rod 9 that the symmetry set up on longboard 1 at last, realize the equipment of scaffold.
The foregoing is only a preferred embodiment of the present utility model, but the scope of the present utility model is not limited thereto, and any person skilled in the art, who is within the scope of the present utility model, should make equivalent substitutions or modifications according to the technical scheme of the present utility model and the inventive concept thereof, and should be covered by the scope of the present utility model.

Claims (6)

1. The utility model provides a building construction frame, includes longeron (1) and symmetry setting a plurality of fixed hooks (15) on longeron (1), its characterized in that, the bottom of longeron (1) is equipped with a plurality of first support column (2) and second support column (3), and first support column (2) and second support column (3) sliding connection, a plurality of be connected with a plurality of fixed foot (4) and the fixed subassembly that are used for stabilizing the scaffold on first support column (2) and second support column (3) respectively.
2. A building construction frame according to claim 1, characterized in that a plurality of connecting holes (10) and fixing holes (11) are formed in a plurality of the first support columns (2) and the second support columns (3).
3. A construction kit according to claim 2, wherein a plurality of connecting rods (9) are connected between two adjacent first support columns (2) and two adjacent second support columns (3), the ends of a plurality of the fixing feet (4) are fixedly connected with connecting pins (8), threaded holes are formed in the two ends of the connecting pins (8) and the connecting rods (9), and bolts (12) are connected to the threaded holes.
4. A construction kit according to claim 3, wherein a plurality of said connecting pins (8) and connecting rods (9) are inserted into the connecting holes (10) at both ends thereof, and said bolts (12) are screwed into the threaded holes through the fixing holes (11).
5. A building construction frame according to claim 3, characterized in that a plurality of fixing hooks (15) symmetrically arranged on the long plate (1) are snapped onto the connecting rod (9).
6. A construction kit according to claim 1, wherein the securing assembly comprises:
the first fixing column (5) is rotationally connected with the second support column (3) through a rotating shaft;
the second fixing column (6) is connected with the first fixing column (5) in a sliding manner;
the third fixing column (7), the said third fixing column (7) is connected with second fixing column (6) slidably;
the jack (14) is arranged on the first fixing column (5), the second fixing column (6) and the third fixing column (7), and the fixing pin (13) is connected in the jack (14).
CN202322444149.6U 2023-09-08 2023-09-08 Building construction frame Active CN220768773U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322444149.6U CN220768773U (en) 2023-09-08 2023-09-08 Building construction frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322444149.6U CN220768773U (en) 2023-09-08 2023-09-08 Building construction frame

Publications (1)

Publication Number Publication Date
CN220768773U true CN220768773U (en) 2024-04-12

Family

ID=90611975

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322444149.6U Active CN220768773U (en) 2023-09-08 2023-09-08 Building construction frame

Country Status (1)

Country Link
CN (1) CN220768773U (en)

Similar Documents

Publication Publication Date Title
US20120006621A1 (en) Movable modular scaffold system for building works and method to form it
CN213626572U (en) Tool type external cantilever operation platform
CN220768773U (en) Building construction frame
CN113431311A (en) Scaffold with adjustable height
CN114856144B (en) Scaffold for building construction and use method
CN215254436U (en) Scaffold with adjustable height
CN212201195U (en) Scaffold for construction
CN206205407U (en) It is a kind of can flexible combination multi-functional scaffold
CN210264006U (en) Building faces limit structure post construction protection frame
CN211114732U (en) Portable movable reinforcement operation platform
CN112538960A (en) Make things convenient for dismouting and firm scaffold frame
CN219773544U (en) Scaffold for building engineering
CN220014009U (en) Movable scaffold
CN220487168U (en) Safety construction protection frame for assembled stairway
CN217518109U (en) Multipurpose operation platform that encorbelments
SU1587220A1 (en) Emergency resscue arrangement for lifting people in unequipped ascending workings
CN219753883U (en) Stair room operation platform with telescopic upright rod and telescopic supporting leg
CN214364801U (en) Portable operation platform for building of formula of encorbelmenting
CN216190562U (en) Device for assisting high-rise ALC (autoclaved lightweight concrete) batten installation
CN219327289U (en) Movable formwork support protection frame for outer window roof structure
CN220203345U (en) Detachable and assembled portable climbing support
CN210421869U (en) Strutting arrangement for building engineering
CN219219718U (en) Telescopic gate-type scaffold
CN210738044U (en) Bottom passage platform of full hall scaffold
CN221141126U (en) Mobile support for high slope drilling support

Legal Events