CN220728969U - Condensing device for condensing gas module boiler - Google Patents

Condensing device for condensing gas module boiler Download PDF

Info

Publication number
CN220728969U
CN220728969U CN202322414463.XU CN202322414463U CN220728969U CN 220728969 U CN220728969 U CN 220728969U CN 202322414463 U CN202322414463 U CN 202322414463U CN 220728969 U CN220728969 U CN 220728969U
Authority
CN
China
Prior art keywords
baffle
condensing
box
gas
several
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322414463.XU
Other languages
Chinese (zh)
Inventor
解汉凤
袁仕杰
徐文芳
怀富民
高健
金迪
高存
刘辉
张洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Honghua Jicheng Energy Service Co ltd
Original Assignee
Shandong Honghua Jicheng Energy Service Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Honghua Jicheng Energy Service Co ltd filed Critical Shandong Honghua Jicheng Energy Service Co ltd
Priority to CN202322414463.XU priority Critical patent/CN220728969U/en
Application granted granted Critical
Publication of CN220728969U publication Critical patent/CN220728969U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Separating Particles In Gases By Inertia (AREA)

Abstract

The utility model provides a condensing equipment for condensing gas module boiler, the power distribution box comprises a box body, gas outlet and air inlet are seted up in proper order to the left and right sides of box, the inside fixed mounting of box several first baffle, the inside partition of first baffle is the inside hollow baffle of several intercommunication each other with the inside partition of box, the inside fixed mounting of first baffle several second baffle, the inside partition of second baffle is the water course of several intercommunication each other with the inside partition of first baffle, the inside left side of box and the first baffle on right side fixed mounting outlet pipe and inlet tube in proper order, respectively through U-shaped pipeline intercommunication between the two liang of first baffle. The utility model has simple structure and ingenious conception, increases the stay time of the gas generated by the boiler in the condensing device, improves the recovery effect of the gas, meets the market demand, and is suitable for popularization.

Description

Condensing device for condensing gas module boiler
Technical Field
The utility model belongs to the field of condensing devices, and particularly relates to a condensing device for a condensing gas module boiler.
Background
The module boiler is controlled by a plurality of boilers, and according to related parameters such as a set heating temperature curve and the like, the number of boilers which are required to be started and stopped is intelligently and automatically judged by referring to the outdoor temperature, so that a near-unattended mode is automatically realized; the condensing gas module boiler can generate a lot of gases when in use, the generated gases need to be recovered in order to reduce waste and cost, the existing gas recovery device mostly carries out condensation recovery in a water coil mode, but the recovery effect of the mode has a certain defect, the residence time of the gases in the condensing device is short, and the condensation recovery cannot be carried out well, so the condensing device for the condensing gas module boiler is designed.
Disclosure of Invention
The utility model provides a condensing device for a condensing gas module boiler, which is used for solving the defects in the prior art.
The utility model is realized by the following technical scheme:
the utility model provides a condensing equipment for condensing gas module boiler, the power distribution box comprises a box body, gas outlet and air inlet are seted up in proper order to the left and right sides of box, the inside fixed mounting of box several first baffle, the inside partition of first baffle is the inside hollow baffle of several intercommunication each other with the inside partition of box, the inside fixed mounting of first baffle several second baffle, the inside partition of second baffle is the water course of several intercommunication each other with the inside partition of first baffle, the inside left side of box and the first baffle on right side fixed mounting outlet pipe and inlet tube in proper order, respectively through U-shaped pipeline intercommunication between the two liang of first baffle.
According to the condensing device for the condensing gas module boiler, the plurality of through holes corresponding to the air channels are formed in the top side of the box body, push rods are mounted in the through holes in a sealing sliding mode, and scraping plates are fixedly mounted on the push rods respectively.
According to the condensing device for the condensing gas module boiler, the ash discharge ports corresponding to the scraping plates one by one are formed in the bottom side of the box body, and the sealing plugs are arranged in the ash discharge ports.
According to the condensing device for the condensing gas module boiler, one end of the push rod, which is positioned outside the box body, is fixedly arranged on the same cross rod.
The condensing device for the condensing gas module boiler has the advantages that the ash discharge port has a certain inclination.
In the condensing device for the condensing gas module boiler, the first baffle plate has a certain inclination angle.
The utility model has the advantages that: the utility model has simple structure and ingenious conception, increases the stay time of the gas generated by the boiler in the condensing device, improves the recovery effect of the gas, meets the market demand, and is suitable for popularization. When the utility model is used, cold water for condensation is firstly introduced into the first baffle plate through the water inlet pipe, the second baffle plate in the first baffle plate can increase the residence time of the cold water in the first baffle plate, so that the condensation recovery effect on gas is increased, after the cold water is introduced, the gas generated by the boiler is introduced into the box body through the air inlet, the gas is condensed and recovered in the box body and then is discharged from the air outlet for recycling, and the cold water in the first baffle plate is used for condensation and then is discharged from the water outlet pipe, and the first baffle plate is staggered to divide the interior of the box body into a plurality of mutually communicated air channels, so that the residence time of the gas generated by the boiler in the box body is increased, and the condensation recovery effect of the gas is improved; and the dust scale accumulated on the surface of the first baffle plate is more convenient to clean.
Drawings
In order to more clearly illustrate the embodiments of the present utility model or the technical solutions of the prior art, the drawings that are needed in the embodiments or the description of the prior art will be briefly described below, it will be obvious that the drawings in the following description are some embodiments of the present utility model, and that other drawings can be obtained according to these drawings without inventive effort to a person skilled in the art.
FIG. 1 is a schematic diagram of the structure of the present utility model; FIG. 2 is an enlarged view of the A-direction view of FIG. 1; fig. 3 is an enlarged view of the B-direction view of fig. 1.
Reference numerals: 1. the box, 2, the gas outlet, 3, the air inlet, 4, first baffling board, 5, second baffling board, 6, outlet pipe, 7, inlet tube, 8, U-shaped pipeline, 20, push rod, 21, scraper blade, 30, ash discharge port, 31, sealing plug, 40, horizontal pole.
Detailed Description
For the purpose of making the objects, technical solutions and advantages of the embodiments of the present utility model more apparent, the technical solutions of the embodiments of the present utility model will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present utility model, and it is apparent that the described embodiments are some embodiments of the present utility model, but not all embodiments of the present utility model. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
The utility model provides a condensing equipment for condensing gas module boiler, as shown in fig. 1, 2, 3, including box 1, gas outlet 2 and air inlet 3 are seted up in proper order to the left and right sides of box 1, the inside fixed mounting of box 1 several first baffle 4, the inside of box 1 separates the wind channel of several intercommunication each other to first baffle 4 crisscross distribution, first baffle 4 is inside hollow baffle, the inside fixed mounting of first baffle 4 several second baffle 5, the inside of second baffle 5 crisscross distribution separates the water course of several intercommunication each other with first baffle 4, the inside left side of box 1 and the first baffle 4 on right side fixed mounting outlet pipe 6 and inlet tube 7 in proper order, respectively through U-shaped pipeline 8 intercommunication between the two first baffles 4. The utility model has simple structure and ingenious conception, increases the stay time of the gas generated by the boiler in the condensing device, improves the recovery effect of the gas, meets the market demand, and is suitable for popularization. When the utility model is used, cold water for condensation is firstly introduced into the first baffle plate 4 through the water inlet pipe 7, the second baffle plate 5 in the first baffle plate 4 can increase the residence time of the cold water in the first baffle plate 4, so that the condensation recovery effect on gas is increased, after the cold water is introduced, the gas generated by the boiler is introduced into the box body 1 through the air inlet 3, the gas is discharged from the air outlet 2 for recycling after condensation recovery in the box body 1, the cold water in the first baffle plate 4 is used for condensation and then is discharged from the water outlet pipe 6, and the first baffle plate 4 is distributed in a staggered manner to divide the interior of the box body 1 into a plurality of mutually communicated air channels, so that the residence time of the gas generated by the boiler in the box body 1 is increased, and the gas condensation recovery effect is improved; and the dust scale accumulated on the surface of the first baffle 4 is more convenient to clean.
Specifically, as shown in the figure, the top side of the box 1 in this embodiment is provided with a plurality of through holes corresponding to the air channels, push rods 20 are installed in the through holes in a sealing and sliding manner, scraping plates 21 are respectively and fixedly installed on the push rods 20, and the scraping plates 21 are located in the box 1. By pushing the push rod 20, the push rod 20 pushes the scraper 21 to move, so that dust adhering to the first baffle 4 can be scraped off.
Specifically, as shown in the figure, the bottom side of the box 1 in this embodiment is provided with ash discharge ports 30 corresponding to the scrapers 21 one by one, and sealing plugs 31 are arranged in the ash discharge ports 30. The sealing plug 31 is removed, and dust scraped by the scraper 21 can be discharged from the dust discharge port 30.
Further, as shown in the figure, one end of the push rod 20 located outside the case 1 in this embodiment is fixedly mounted on the same cross bar 40. The push rod 20 can be pushed simultaneously through the cross rod 40 to drive the scraping plate 21 to scrape off dust adhered on the first baffle plate 4, so that the device is more convenient to operate.
Further, as shown, the ash hole 30 of the present embodiment has a certain inclination. The slope of the dust discharge port 30 can collect scraped dust together, facilitating the discharge of the dust.
Further, as shown in the figure, the first baffle 4 of this embodiment has a certain inclination angle. The inclination angle of the first baffle plate 4 can obstruct the flow of the gas, further increase the condensing effect of the gas, and thereby improve the recovery effect of the gas.
Finally, it should be noted that: the above embodiments are only for illustrating the technical solution of the present utility model, and are not limiting; although the utility model has been described in detail with reference to the foregoing embodiments, it will be understood by those of ordinary skill in the art that: the technical scheme described in the foregoing embodiments can be modified or some technical features thereof can be replaced by equivalents; such modifications and substitutions do not depart from the spirit and scope of the technical solutions of the embodiments of the present utility model.

Claims (6)

1. The utility model provides a condensing equipment for condensing gas module boiler which characterized in that: including box (1), gas outlet (2) and air inlet (3) are offered in proper order to the left and right sides of box (1), the inside fixed mounting of box (1) several first baffle (4), the inside partition of box (1) several wind channel of intercommunication each other is crisscross to distribute to first baffle (4), first baffle (4) are inside hollow baffle, the inside fixed mounting several second baffle (5) of first baffle (4), the inside partition several water course of intercommunication each other of second baffle (5) crisscross distribution with first baffle (4), inside left side and right side first baffle (4) of box (1) are fixed mounting outlet pipe (6) and inlet tube (7) in proper order, two liang between first baffle (4) are through U-shaped pipeline (8) intercommunication respectively.
2. The condensing unit for condensing a gas module boiler according to claim 1, wherein: the top side of the box body (1) is provided with a plurality of through holes corresponding to the air channels, push rods (20) are hermetically and slidably arranged in the through holes, and scraping plates (21) are fixedly arranged on the push rods (20) respectively.
3. The condensing unit for condensing a gas module boiler according to claim 2, wherein: the bottom side of the box body (1) is provided with ash discharge ports (30) which are in one-to-one correspondence with the scraping plates (21), and sealing plugs (31) are arranged in the ash discharge ports (30).
4. The condensing unit for condensing a gas module boiler according to claim 2, wherein: one end of the push rod (20) positioned outside the box body (1) is fixedly arranged on the same cross rod (40).
5. A condensing unit for condensing a gas module boiler according to claim 3, characterized by: the ash discharge opening (30) has a certain inclination.
6. The condensing unit for condensing a gas module boiler according to claim 1, wherein: the first baffle plate (4) has a certain inclination angle.
CN202322414463.XU 2023-09-06 2023-09-06 Condensing device for condensing gas module boiler Active CN220728969U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322414463.XU CN220728969U (en) 2023-09-06 2023-09-06 Condensing device for condensing gas module boiler

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322414463.XU CN220728969U (en) 2023-09-06 2023-09-06 Condensing device for condensing gas module boiler

Publications (1)

Publication Number Publication Date
CN220728969U true CN220728969U (en) 2024-04-05

Family

ID=90493329

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322414463.XU Active CN220728969U (en) 2023-09-06 2023-09-06 Condensing device for condensing gas module boiler

Country Status (1)

Country Link
CN (1) CN220728969U (en)

Similar Documents

Publication Publication Date Title
CN108800180B (en) Industrial flue gas optimal utilization whitening system
CN220728969U (en) Condensing device for condensing gas module boiler
CN115425530A (en) Indoor heat dissipation dust collector of high voltage substation
CN108636047B (en) System for discharging, condensing and collecting water and removing pollutants in cooperation
CN105606525A (en) Multifunctional compound test chamber
CN108518701B (en) Phase-change cold condensing device
CN209156712U (en) Utilize the system of the purifying organic polluted soil of heat transfer original position thermal desorption
CN216815114U (en) U-shaped tube rich oil heater with strong heat exchange performance
CN109248911A (en) Utilize the system and method for the purifying organic polluted soil of heat transfer original position thermal desorption
CN210934319U (en) Flue gas dust removal device and flue gas pollutant processing system
CN208398111U (en) A kind of cold coacervation device of phase transformation
CN219036615U (en) Circulating fluidized bed boiler waste heat utilization device
CN106955558B (en) Condensing dust remover
CN212157227U (en) Water cooling device for pyrolysis tail gas
CN215177169U (en) Integrated waste gas treatment and waste heat recovery device
CN218936388U (en) External exhaust condensation recovery system of thermal power plant
CN220062675U (en) High-efficient heat sink of high temperature natural gas
CN217541619U (en) Heat exchange structure
CN218499504U (en) Water-drainage-free industrial electrical cabinet air conditioner structure
CN220601537U (en) Boiler flue gas bypass system
CN217899938U (en) Air preheater with ash removal function
CN111947122B (en) Energy-efficient waste heat recovery system of hierarchical utilization
CN211329821U (en) Secondary purification device for electric precipitation insulation box
CN218380552U (en) Air cooling pipeline header with steam and condensed water separation function
CN220432722U (en) Waste rubber and plastic thermal cracking decoking and impurity removing and condensing equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant