CN220619958U - Construction slope protection device - Google Patents

Construction slope protection device Download PDF

Info

Publication number
CN220619958U
CN220619958U CN202321590365.5U CN202321590365U CN220619958U CN 220619958 U CN220619958 U CN 220619958U CN 202321590365 U CN202321590365 U CN 202321590365U CN 220619958 U CN220619958 U CN 220619958U
Authority
CN
China
Prior art keywords
recovery box
fixedly connected
protection device
fixing
seat
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN202321590365.5U
Other languages
Chinese (zh)
Inventor
赵燕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Zhongyi Ecological Construction Co ltd
Original Assignee
Anhui Zhankun Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Zhankun Construction Engineering Co ltd filed Critical Anhui Zhankun Construction Engineering Co ltd
Priority to CN202321590365.5U priority Critical patent/CN220619958U/en
Application granted granted Critical
Publication of CN220619958U publication Critical patent/CN220619958U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

The utility model discloses a construction slope protection device, which relates to the technical field of construction slope protection and comprises a recovery box, wherein a winding rod is rotatably connected to the inner wall of the recovery box, a protection net is fixedly connected to the outer surface of the winding rod, the protection net penetrates through the recovery box and extends to the outside of the recovery box, a fixing seat is fixedly connected to one end, far away from the winding rod, of the protection net, and a limiting mechanism is arranged above the recovery box. According to the utility model, through the arrangement of the recovery box, the limiting mechanism, the winding rod, the protective net and the fixing seat, the protective net can be neatly wound on the outer surface of the winding rod for storage after construction, so that the problem that the storage of the protective net is not neatly or difficultly neat due to the existing storage mode of directly grouping or winding the protective net together is avoided, the protective net is conveniently and neatly stored, and meanwhile, the subsequent placement of the protective net and the rapid expansion of the protective net in next use are facilitated.

Description

Construction slope protection device
Technical Field
The utility model relates to the technical field of construction slope protection, in particular to a construction slope protection device.
Background
The hydraulic engineering is used for controlling and allocating surface water and underground water in the nature to achieve the aim of removing harm and benefiting, is also called as water engineering, water is an indispensable precious resource for human production and life, but the naturally occurring state of the hydraulic engineering does not completely meet the human needs, only the hydraulic engineering is constructed to control water flow, prevent flood disasters, regulate and allocate water quantity to meet the needs of people living and production on water resources, and in the hydraulic engineering construction, a protective net is arranged at a slope position to protect workers in order to avoid stone or soil slipping on the slope from influencing construction or injuring the workers by smashing.
According to the water conservancy construction slope protection device disclosed in the patent number CN208762962U, the device can use the winding net twine to twine in the upper and lower both sides of bank protection net, uses the cooperation of protection network retainer plate and telescopic to fix the winding net twine wherein, and the rethread is connected with the connection shackle later, can fix the bank protection net on the surface of bank protection main part, has solved traditional water conservancy bank protection surface fragment of brick, soil block easily and has become flexible from this, has the problem of hidden danger to constructor and people's life safety.
But the technical scheme of above-mentioned patent is at the in-process of implementing, is inconvenient to accomodate the protection network, before the hydraulic construction, can install the protection network on the side slope and protect, and can withdraw so that use next time after the construction, current protection network can directly be clustered or roll up together to accomodate mostly, and this kind of storage mode can lead to accomodating neatly or hardly accomodate neatly to be inconvenient for place, also can lead to being difficult for expanding when using next time simultaneously. Thus, a construction slope protection device is proposed herein.
Disclosure of Invention
Technical problem to be solved
The utility model aims to make up the defects of the prior art and provides a construction slope protection device.
Technical proposal
In order to achieve the above purpose, the present utility model provides the following technical solutions: the utility model provides a construction bank protection device, includes the collection box, the inner wall of collection box rotates and is connected with the rolling pole, the surface mounting of rolling pole has the protection network, the protection network runs through the collection box and extends to the outside of collection box, the one end fixedly connected with fixing base of rolling pole is kept away from to the protection network, the top of collection box is provided with stop gear, stop gear includes spacing dish and fixed connection at the spacing seat of collection box upper surface, the top of rolling pole runs through the collection box and extends to the top of collection box, the top fixed connection of rolling pole is in the bottom surface of spacing dish, spacing dish sliding connection is at the inner wall of spacing seat, the top of spacing seat is provided with the movable block, the bottom surface fixedly connected with gag lever post of movable block, the outside of collection box is provided with fixed establishment.
Above-mentioned, the gag lever post runs through the spacing seat and extends to the inside of spacing seat, gag lever post and spacing seat sliding connection, gag lever post and spacing dish looks adaptation have been seted up on the spacing dish a plurality of equidistance and arranged and with the spacing hole of gag lever post looks adaptation, insert the gag lever post in the spacing hole of spacing dish, can carry out spacingly to the spacing dish.
Above-mentioned, the bottom surface fixedly connected with spring of movable block, the bottom fixed connection of spring is at the upper surface of spacing seat, and the setting of spring can avoid the gag lever post to follow the spacing dish and not break away from by the people.
Above-mentioned, the inner wall sliding connection of movable block has the dog, dog and spacing seat looks adaptation lift up the movable block back, make the gag lever post pull out from the spacing dish to remove the dog to gag lever post direction, make the dog keep off between spacing seat and movable block, can make the gag lever post steadily keep away from the spacing dish.
Above-mentioned, fixed establishment includes fixed frame and fixed block of fixed connection at the fixing base surface of fixed connection at the recovery tank surface, fixed frame and fixed block looks adaptation, and the fixed block can be stably placed inside the fixed frame.
Above-mentioned, the fixed surface of frame is installed through the bolt and is dismantled the board, it is close to a side fixedly connected with of fixed frame to dismantle the board and inserts the board, insert the board and run through the fixed frame and extend to the inside of fixed frame, insert board and fixed frame sliding connection, insert board and fixed block looks adaptation, insert the board and can insert simultaneously in fixed frame and the fixed block to fix the fixed block.
Above-mentioned, the surface fixedly connected with first mounting panel of fixing base, the surface fixedly connected with second mounting panel of collection box expandes the back with the protection network, through fixing first mounting panel and second mounting panel on the side slope, can fix the protection network on the side slope and play the guard action for follow-up construction work.
The beneficial effects are that:
compared with the prior art, the construction slope protection device has the following beneficial effects:
1. according to the utility model, through the arrangement of the recovery box, the limiting mechanism, the winding rod, the protective net and the fixing seat, the protective net can be neatly wound on the outer surface of the winding rod for storage after construction, so that the problem that the storage of the protective net is not neatly or difficultly neat due to the existing storage mode of directly grouping or winding the protective net together is avoided, the protective net is conveniently and neatly stored, and meanwhile, the subsequent placement of the protective net and the rapid expansion of the protective net in next use are facilitated.
2. According to the utility model, through the arrangement of the fixing mechanism, after the protective net is rolled, the dismounting plate is dismounted from the fixing frame through unscrewing the bolts on the dismounting plate, the inserting plate is pulled out from the fixing frame, then the fixing block is placed in the fixing frame, the inserting plate is simultaneously inserted into the fixing frame and the fixing block, the dismounting plate is fixed on the fixing frame again through the bolts, and at the moment, the fixing seat and the fixing block can be stably fixed.
Additional advantages, objects, and features of the utility model will be set forth in part in the description which follows and in part will become apparent to those having ordinary skill in the art upon examination of the following or may be learned from practice of the utility model.
Drawings
FIG. 1 is a schematic perspective view of the present utility model;
FIG. 2 is a schematic view of the internal structure of the recovery tank of the present utility model;
FIG. 3 is a schematic diagram of a split structure of a limiting plate and a limiting seat according to the present utility model;
fig. 4 is a schematic view showing a split structure of the fixing frame and the insertion plate of the present utility model.
In the figure:
1. a recovery box;
2. a limiting mechanism; 21. a limiting disc; 22. a limit seat; 23. a spring; 24. a moving block; 25. a limit rod; 26. a stop block;
3. a fixing mechanism; 31. a fixed frame; 32. a fixed block; 33. disassembling the plate; 34. an insertion plate;
4. a winding rod; 5. a protective net; 6. a fixing seat; 7. a first mounting plate; 8. and a second mounting plate.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Referring to fig. 1 to 4, the present utility model provides a technical solution: the utility model provides a construction slope protection device, includes recovery case 1, and the inner wall of recovery case 1 rotates and is connected with rolling pole 4, and the external surface fixedly connected with protection network 5 of rolling pole 4 can prevent on the side slope that stone or earth landing from influencing the construction or injuring constructor by smashing with protection network 5 setting up on the side slope.
The protection network 5 runs through the recovery box 1 and extends to the outside of the recovery box 1, and one end of the protection network 5, which is far away from the winding rod 4, is fixedly connected with a fixing seat 6, and the protection network 5 can be pulled out from the recovery box 1 by pulling the fixing seat 6.
The surface fixedly connected with first mounting panel 7 of fixing base 6, the surface fixedly connected with second mounting panel 8 of recovery tank 1 expandes the back with protection network 5, through fixing first mounting panel 7 and second mounting panel 8 on the side slope, can fix protection network 5 on the side slope and play the guard action for follow-up construction work.
Referring to fig. 2 and 3, a limit mechanism 2 is disposed above the recovery box 1, the limit mechanism 2 includes a limit plate 21 and a limit seat 22 fixedly connected to the upper surface of the recovery box 1, the top end of the winding rod 4 penetrates through the recovery box 1 and extends to the upper side of the recovery box 1, the top end of the winding rod 4 is fixedly connected to the bottom surface of the limit plate 21, and the winding rod 4 can be rotated by rotating the limit plate 21 or setting a handle on the limit plate 21.
The limiting plate 21 sliding connection is at the inner wall of limiting seat 22, the top of limiting seat 22 is provided with movable block 24, the bottom surface fixedly connected with gag lever post 25 of movable block 24, gag lever post 25 runs through limiting seat 22 and extends to the inside of limiting seat 22, gag lever post 25 and limiting seat 22 sliding connection, gag lever post 25 plays the guide effect for the removal of limiting seat 22, gag lever post 25 and limiting plate 21 looks adaptation, set up a plurality of equidistance range on the limiting plate 21 and with the spacing hole of gag lever post 25 looks adaptation, insert gag lever post 25 to the spacing downthehole of limiting plate 21, can carry out spacing to limiting plate 21.
The bottom surface fixedly connected with spring 23 of movable block 24, the bottom fixed connection of spring 23 is at the upper surface of spacing seat 22, and spring 23 is slight tensile state when spacing pole 25 inserts in spacing dish 21, and the setting of spring 23 can avoid spacing pole 25 to follow spacing dish 21 non-artificial breaking away from.
The inner wall sliding connection of movable block 24 has dog 26, and the spout with dog 26 looks adaptation is seted up to the bottom surface of movable block 24, makes dog 26 can stabilize in movable block 24 internal sliding, and dog 26 and limit seat 22 looks adaptation lifts up the movable block 24 the back, makes gag lever post 25 pull out from limit plate 21 to remove dog 26 to gag lever post 25 direction, make dog 26 keep off between limit seat 22 and movable block 24, can make gag lever post 25 steadily keep away from limit plate 21.
Referring to fig. 1 and 4, a fixing mechanism 3 is disposed outside the recycling bin 1, the fixing mechanism 3 includes a fixing frame 31 fixedly connected to the outer surface of the recycling bin 1 and a fixing block 32 fixedly connected to the outer surface of the fixing base 6, the fixing frame 31 is adapted to the fixing block 32, and the fixing block 32 can be stably placed inside the fixing frame 31.
The surface of fixed frame 31 has the dismantlement board 33 through the bolt installation, all offered the screw on dismantlement board 33 and the fixed frame 31, screw down the bolt simultaneously in dismantlement board 33 and the fixed frame 31, can make dismantlement board 33 be close to a side fixedly connected with insert plate 34 of fixed frame 31, insert plate 34 runs through fixed frame 31 and extends to the inside of fixed frame 31, insert plate 34 and fixed frame 31 sliding connection, insert plate 34 and fixed block 32 looks adaptation, insert plate 34 can insert simultaneously in fixed frame 31 and the fixed block 32 to fix fixed block 32.
Working principle: when the protective net is used, the movable block 24 is moved upwards, the limiting rod 25 is pulled out of the limiting disc 21, the spring 23 is stretched, the stop block 26 is pushed towards the direction close to the limiting rod 25, the stop block 26 is blocked between the movable block 24 and the limiting seat 22, then the protective net 5 is pulled out of the recovery box 1 and unfolded through the pulling fixing seat 6, the stop block 26 is pushed away from the limiting rod 25, at the moment, the limiting rod 25 is pushed to be inserted into the limiting disc 21 under the action of the elastic force of the stretching spring 23, limiting of the protective net 5 is completed, when the protective net 5 is retracted, the limiting rod 25 is pulled out of the limiting disc 21, the outer surface of the winding rod 4 is wound up through rotating the limiting disc 21 or a handle arranged on the limiting disc 21, the fixing block 32 is fixed in the fixing frame 31, the protective net 5 can be retracted and placed, and the protective net 5 can be wound up to the outer surface of the winding rod 4 in order after construction, so that the protective net 5 can be stored in order, and the protective net 5 can be used for being quickly and unfolded in the next time.
Although embodiments of the present utility model have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made therein without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. Construction bank protection device, including collection box (1), its characterized in that: the utility model discloses a recovery box, including recovery box (1), inner wall rotation of recovery box (1) is connected with rolling pole (4), the surface fixedly connected with protection network (5) of rolling pole (4), protection network (5) run through recovery box (1) and extend to the outside of recovery box (1), one end fixedly connected with fixing base (6) of rolling pole (4) are kept away from to protection network (5), the top of recovery box (1) is provided with stop gear (2), stop gear (2) include spacing dish (21) and fixed connection spacing seat (22) at recovery box (1) upper surface, the top of rolling pole (4) runs through recovery box (1) and extends to the top of recovery box (1), the top fixed connection of rolling pole (4) is in the bottom surface of spacing dish (21), the top of spacing seat (22) is provided with movable block (24), the bottom surface fixedly connected with spacing pole (25) of movable block (24), the outside of recovery box (1) is provided with fixed establishment (3).
2. A construction slope protection device according to claim 1, wherein: the limiting rod (25) penetrates through the limiting seat (22) and extends to the inside of the limiting seat (22), the limiting rod (25) is in sliding connection with the limiting seat (22), and the limiting rod (25) is matched with the limiting disc (21).
3. A construction slope protection device according to claim 1, wherein: the bottom surface fixedly connected with spring (23) of movable block (24), the bottom fixed connection of spring (23) is at the upper surface of spacing seat (22).
4. A construction slope protection device according to claim 1, wherein: the inner wall sliding connection of movable block (24) has dog (26), dog (26) and spacing seat (22) looks adaptation.
5. A construction slope protection device according to claim 1, wherein: the fixing mechanism (3) comprises a fixing frame (31) fixedly connected to the outer surface of the recovery box (1) and a fixing block (32) fixedly connected to the outer surface of the fixing seat (6), and the fixing frame (31) is matched with the fixing block (32).
6. The construction slope protection device according to claim 5, wherein: the outer surface of fixed frame (31) is installed through the bolt and is dismantled board (33), dismantle a side fixedly connected with of board (33) near fixed frame (31) and insert board (34), insert board (34) run through fixed frame (31) and extend to the inside of fixed frame (31), insert board (34) and fixed frame (31) sliding connection, insert board (34) and fixed block (32) looks adaptation.
7. A construction slope protection device according to claim 1, wherein: the outer surface fixedly connected with first mounting panel (7) of fixing base (6), the surface fixedly connected with second mounting panel (8) of recovery tank (1).
CN202321590365.5U 2023-06-20 2023-06-20 Construction slope protection device Withdrawn - After Issue CN220619958U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321590365.5U CN220619958U (en) 2023-06-20 2023-06-20 Construction slope protection device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321590365.5U CN220619958U (en) 2023-06-20 2023-06-20 Construction slope protection device

Publications (1)

Publication Number Publication Date
CN220619958U true CN220619958U (en) 2024-03-19

Family

ID=90229955

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321590365.5U Withdrawn - After Issue CN220619958U (en) 2023-06-20 2023-06-20 Construction slope protection device

Country Status (1)

Country Link
CN (1) CN220619958U (en)

Similar Documents

Publication Publication Date Title
CN220619958U (en) Construction slope protection device
CN210067392U (en) Full-assembly type scaffold overhanging assembly
CN209412951U (en) A kind of sewer falling proof device
CN208056671U (en) A kind of safe fence for building
CN113016403B (en) Green building planting structure
CN109372326A (en) Outdoor deep embeded type hydraulic lifting safe fence bar and method for arranging
CN217840037U (en) High steep side slope protection network
CN213742134U (en) Indoor autonomous movement intelligent plastering machine
CN216476654U (en) Hydraulic engineering protection network
CN206433483U (en) A kind of device for laying bird prevention net
CN217098463U (en) Abandonment plastic tubing cutting crushing equipment is with putting support in advance
CN219931820U (en) Electric power purse net support
CN205073564U (en) A control mechanism that drains for fire control well -bucket
CN218997666U (en) Lightning arrester hybrid installation structure
CN218757374U (en) Equipment is salvaged to dam water inlet floating garbage
CN212607966U (en) Cross bar pushing device in inductance processing equipment
CN205442450U (en) Long -range controlled tower crane device
CN213038330U (en) Hydraulic engineering is with automatic start-stop gate
CN217630074U (en) Hydraulic engineering retaining wall
CN218437309U (en) Novel fire hydrant device
CN217354103U (en) Passive low-energy-consumption building door and window structure
CN213273985U (en) Pressure-resistant water hole spacer
CN219001978U (en) Stage rope guider
CN213952138U (en) Novel water sluicegate with block dirty function
CN220304617U (en) Underground waterproof engineering supervision device is built in room

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240319

Address after: 231121 West side of Zhushuang Road, Xiatang Town, Changfeng County, Hefei City, Anhui Province

Patentee after: Anhui Zhongyi Ecological Construction Co.,Ltd.

Country or region after: China

Address before: 230041 3-1004, 10th floor, area C, jiruitaisheng international living Plaza, Qimen road and Airport Road, Baohe District, Hefei City, Anhui Province

Patentee before: Anhui Zhankun Construction Engineering Co.,Ltd.

Country or region before: China

AV01 Patent right actively abandoned
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20240319

Effective date of abandoning: 20240415

AV01 Patent right actively abandoned

Granted publication date: 20240319

Effective date of abandoning: 20240415