CN220599395U - Inflatable ceiling fixing device - Google Patents

Inflatable ceiling fixing device Download PDF

Info

Publication number
CN220599395U
CN220599395U CN202322196030.1U CN202322196030U CN220599395U CN 220599395 U CN220599395 U CN 220599395U CN 202322196030 U CN202322196030 U CN 202322196030U CN 220599395 U CN220599395 U CN 220599395U
Authority
CN
China
Prior art keywords
fixing device
inflatable
pit
backfill
threaded hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322196030.1U
Other languages
Chinese (zh)
Inventor
张泽磐
刘朋
刘志琳
郭松
张子健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Juntong Electronic Equipment Technology Co ltd
Original Assignee
Hebei Juntong Electronic Equipment Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Juntong Electronic Equipment Technology Co ltd filed Critical Hebei Juntong Electronic Equipment Technology Co ltd
Priority to CN202322196030.1U priority Critical patent/CN220599395U/en
Application granted granted Critical
Publication of CN220599395U publication Critical patent/CN220599395U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Tents Or Canopies (AREA)

Abstract

The utility model relates to the technical field of ceiling fixing, and provides an inflatable ceiling fixing device, which comprises an inflatable tent arranged on the ground, and comprises: the pit is arranged on the ground; the fixing device is arranged in the pit; the backfill rammer is arranged in the pit and positioned on the fixing device; the hooks are arranged on the fixing device at intervals; and one end of the traction rope is arranged on the inflatable tent, and the other end of the traction rope is arranged on the hook and is used for fixing the inflatable tent. Through the technical scheme, the problem that the inflatable ceiling is difficult to fix in the related art is solved, and the inflatable ceiling can be fixed only through a huge counterweight.

Description

Inflatable ceiling fixing device
Technical Field
The utility model relates to the technical field of ceiling fixing, in particular to an inflatable ceiling fixing device.
Background
Because the occupied area of buildings such as large venues is too large, the span between the walls is large, and the problem of material bearing caused by the arrangement of a huge ceiling cannot be solved from the aspect of structural mechanics. For example, football stadium, the field plus the stand have a length of 200 meters and a width of 100 meters, so that the modern building level cannot design and install a ceiling for the football stadium. Therefore, the large-scale stadium is only designed into an open-air structure, the problem brought is that large-scale activities or games are held in rainy and snowy weather, participants, sponsors, audiences, athletes and performers can play rainy and snowy, the athletes and performers can not exert the due level, the ornamental value of the games and activities is reduced, meanwhile, pain and health problems are brought to the participants and the audiences, and the games or activities are delayed or even cancelled sometimes. The inflatable ceiling is convenient to build and can solve the problem that structural mechanics cannot solve, but the existing inflatable ceiling is difficult to fix, and the inflatable ceiling can be fixed only by a huge counterweight.
Disclosure of Invention
The utility model provides an inflatable ceiling fixing device, which solves the problem that the inflatable ceiling is difficult to fix in the related art, and the inflatable ceiling can be fixed only by a huge counterweight.
The technical scheme of the utility model is as follows:
the inflatable ceiling fixing device comprises an inflatable tent arranged on the ground, and comprises:
the pit is arranged on the ground;
the fixing device is arranged in the pit;
the backfill rammer is arranged in the pit and positioned on the fixing device;
the hooks are arranged on the fixing device at intervals;
and one end of the traction rope is arranged on the inflatable tent, and the other end of the traction rope is arranged on the hook and is used for fixing the inflatable tent.
As a further technical scheme, the backfill rammer is sand soil generated when the pit is arranged.
As a further technical solution, the fixing device includes:
the fixed cylinder is provided with a backfill cavity, the backfill cavity is provided with an air hole, and the backfill rammer is arranged in the backfill cavity;
the cutting board, the cutting board has a plurality of, and a plurality of cutting board one end all sets up in the backfilling cavity, the other end is the cutting end, takes the heliciform.
As a further technical scheme, one side of the cutting plate, which is far away from the fixing device, is provided with a plurality of first threaded holes, and one end of each of the hooks is provided with a plurality of first threaded holes.
As a further technical scheme, the outer wall of the fixing device is provided with a spiral material pouring groove.
As a further technical solution, the fixing device is provided with a second threaded hole, and the fixing device further includes:
the mandrel is provided with a third threaded hole, and the mandrel is arranged in the second threaded hole in a threaded manner;
the drill bit is used for being arranged in the third threaded hole in a threaded manner;
and the hanging head is used for being arranged in the third threaded hole in a threaded manner.
As a further technical solution, the fixing device is provided with a cover, and the cover is provided with a plurality of avoidance holes.
The working principle and the beneficial effects of the utility model are as follows:
according to the utility model, as the original inflatable ceiling can only be fixed through the counterweights such as huge stones, the scheme provides that pits are arranged on a sand, sand generated by the pits is used as backfill ramming pieces to be arranged on a fixing device and used as counterweights, and hooks are arranged on the fixing device and connected with the inflatable tent through traction ropes, the inflatable ceiling is fixed, and the inflatable tent is fixed more conveniently and firmly.
Drawings
The utility model will be described in further detail with reference to the drawings and the detailed description.
FIG. 1 is a first axial side view of the fixture of the present utility model;
FIG. 2 is a second axial side view of the fixture of the present utility model;
FIG. 3 is a schematic view of the inflatable tent layout of the present utility model;
FIG. 4 is a schematic view of a drill bit according to the present utility model;
FIG. 5 is a schematic view of a hanging head according to the present utility model;
in the figure: 1. the inflatable tent comprises an inflatable tent body, 2, pits, 3, a fixing device, 4, hooks, 5, a fixing cylinder, 6, a cutting plate, 7, a first threaded hole, 8, a spiral pouring groove, 9, a second threaded hole, 10, a mandrel, 11, a drill bit, 12, a cover, 13, an avoidance hole, 14 and a hanging head.
Detailed Description
The technical solutions of the embodiments of the present utility model will be clearly and completely described below in conjunction with the embodiments of the present utility model, and it is apparent that the described embodiments are only some embodiments of the present utility model, not all embodiments. All other embodiments, which can be made by one of ordinary skill in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Examples
As shown in fig. 1 to 5, the present embodiment proposes
An inflatable ceiling fixing device 3 including an inflatable tent 1 provided on the ground, comprising:
pit 2, set up on ground;
a fixing device 3 arranged in the pit 2;
the backfill ramming piece is arranged in the pit 2 and is positioned on the fixing device 3;
the hooks 4 are arranged on the fixing device 3 at intervals;
and one end of the traction rope is arranged on the inflatable tent 1, and the other end of the traction rope is arranged on the hook 4 and is used for fixing the inflatable tent 1.
In this embodiment, because original inflatable ceiling can only be fixed through huge counter weight such as stone, this scheme has put forward, set up pit 2 at the sand to set up the sand that pit 2 produced and set up on fixing device 3 as backfill ramming spare for as the counter weight, be provided with couple 4 on fixing device 3, couple 4 is connected with inflatable tent 1 through the traction rope, thereby realizes the fixed to inflatable ceiling, makes fixed inflatable tent 1 more convenient and firm.
Further, the backfill tamper is sand soil generated when the pit 2 is provided.
In this embodiment, in order to make fixing device 3 set up more firm in pit 2, this scheme will set up the sand that produces when pit 2 as backfilling ramming spare, has avoided carrying other counter weights when fixing and has stabilized, uses more convenient.
Further, the fixing device 3 includes:
the fixed cylinder 5 is provided with a backfill cavity, the backfill cavity is provided with an air hole, and the backfill rammer is arranged in the backfill cavity;
the cutting board 6, cutting board 6 have a plurality of, and a plurality of cutting board 6 one end all sets up in backfilling cavity, and the other end is the cutting end, is the heliciform.
In this embodiment, in order to make the setting of pit 2 more swift, this scheme has set up fixed section of thick bamboo 5, and is provided with cutting board 6 in fixed section of thick bamboo 5 to be provided with the bleeder vent at fixed section of thick bamboo 5 tip, drive fixed section of thick bamboo 5 rotation with the excavator when setting up pit 2, cutting board 6 that sets up in fixed section of thick bamboo 5 backfill cavity cuts the sand to make the sand become flexible, be convenient for make fixed section of thick bamboo 5 insert ground.
Further, the cutting board 6 is kept away from the fixing device 3 one side and sets up a plurality of first screw hole 7, and a plurality of couple 4 one end screw thread sets up in a plurality of first screw hole 7.
In this embodiment, in order to be able to realize the fixation to the inflatable tent 1, this scheme is provided with a plurality of first screw hole 7 on cutting board 6 to set up a plurality of couple 4 on first screw hole 7, can carry out diversified fixation to the inflatable tent.
Further, the outer wall of the fixing device 3 is provided with a spiral material pouring groove 8.
In this embodiment, in order to make the fixed cylinder 5 smoothly enter the ground, the spiral guide groove is arranged on the outer side of the fixed cylinder 5, and part of soil generated when the fixed cylinder 5 drills into the ground is removed from the spiral guide groove, so that the fixed cylinder 5 is easier to drill into the ground.
Further, the fixing device 3 is provided with a second threaded hole 9, and the fixing device 3 further includes:
a mandrel 10 having a third threaded hole, the mandrel 10 being threadedly disposed within the second threaded hole 9;
a drill 11 for being screwed into the third screw hole;
a hanging head 14 is used for being arranged in the third threaded hole in a threaded mode.
In this embodiment, in order to drill the ground together with the fixing device 3 by the backfill ramming member, i.e. sand, generated when the pit 2 is provided, the mandrel 10 is provided, after the fixing barrel 5 is completely drilled into the ground, a third threaded hole is provided on the mandrel 10, after the drill bit 11 is provided in the third threaded hole, the mandrel 10 is drilled into the second threaded hole 9, and since the mandrel 10 has a constant volume and the volume in the fixing barrel 5 is unchanged, the inner volume of the fixing barrel 5 is occupied after the mandrel 10 is drilled into, so that the backfill ramming member in the fixing barrel 5 is fastened, the backfill ramming member in the fixing barrel 5 is also taken out when the fixing barrel 5 is taken out, and then the counterweight can be increased by placing the side of the fixing barrel 5 with the second threaded hole 9 into the pit 2.
Further, the fixture 3 has a cover 12, the cover 12 having a number of relief holes 13.
In this embodiment, since the cutting blade of the fixing device 3 is disposed above the ground during the fixing process, the cover 12 is provided to avoid injury to a person during an unintentional process, and since the hanging head 14 and the hanging hook 4 are used for connecting with the pulling rope to pull the inflatable tent 1, the cover 12 is provided with a plurality of avoiding holes 13 for allowing the hanging head 14 and the hanging hook 4 to extend out to connect with the pulling rope. The foregoing description of the preferred embodiments of the utility model is not intended to be limiting, but rather is intended to cover all modifications, equivalents, alternatives, and improvements that fall within the spirit and scope of the utility model.

Claims (7)

1. The utility model provides an inflatable ceiling fixing device, includes inflatable tent (1) of setting on ground, its characterized in that includes:
a pit (2) provided on the ground;
a fixing device (3) arranged in the pit (2);
the backfill rammer is arranged in the pit (2) and is positioned on the fixing device (3);
the hooks (4) are arranged on the fixing device (3) at intervals;
and one end of the traction rope is arranged on the inflatable tent (1), and the other end of the traction rope is arranged on the hook (4) and used for fixing the inflatable tent (1).
2. The inflatable roof fixture according to claim 1, characterized in that the backfill rammer is sand produced when the pit (2) is provided.
3. The inflatable roof fixing device according to claim 1, characterized in that the fixing device (3) comprises:
the fixed cylinder (5) is provided with a backfill cavity, the backfill cavity is provided with an air hole, and the backfill rammer is arranged in the backfill cavity;
the cutting board (6), cutting board (6) have a plurality of, and a plurality of cutting board (6) one end all sets up in backfilling the cavity, the other end is the cutting end, is the heliciform.
4. An inflatable roof fixing device according to claim 3, characterized in that a plurality of first threaded holes (7) are formed in one side, far away from the fixing device (3), of the cutting plate (6), and one end of each of the hooks (4) is arranged in each of the first threaded holes (7) in a threaded manner.
5. An inflatable roof fixing device according to claim 1, characterized in that the outer wall of the fixing device (3) is provided with a spiral pouring spout (8).
6. An inflatable roof fixing device according to claim 1, characterized in that the fixing device (3) is provided with a second threaded hole (9), the fixing device (3) further comprising:
a spindle (10) having a third threaded hole, the spindle (10) being threadedly disposed within the second threaded hole (9);
a drill bit (11) for being threadedly disposed in the third threaded hole;
and the hanging head (14) is used for being arranged in the third threaded hole in a threaded manner.
7. The inflatable roof fastening device according to claim 1, characterized in that the fastening device (3) has a cover (12), the cover (12) having a number of relief holes (13).
CN202322196030.1U 2023-08-15 2023-08-15 Inflatable ceiling fixing device Active CN220599395U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322196030.1U CN220599395U (en) 2023-08-15 2023-08-15 Inflatable ceiling fixing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322196030.1U CN220599395U (en) 2023-08-15 2023-08-15 Inflatable ceiling fixing device

Publications (1)

Publication Number Publication Date
CN220599395U true CN220599395U (en) 2024-03-15

Family

ID=90178801

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322196030.1U Active CN220599395U (en) 2023-08-15 2023-08-15 Inflatable ceiling fixing device

Country Status (1)

Country Link
CN (1) CN220599395U (en)

Similar Documents

Publication Publication Date Title
CN210154587U (en) Fixed point marking device for engineering survey
CN220599395U (en) Inflatable ceiling fixing device
CN209493963U (en) A kind of prefabricated wind power generation machine tower base platform
CN112575791B (en) Foundation pit supporting structure and construction method thereof
CN208023560U (en) The dismountable screw pile machine of ultra-deep pile foundation drilling rod
CN206205916U (en) A kind of achievable crept into anchor rod device for intersecting anchoring
CN206554106U (en) Conehead muscle body posttension pile foundation
CN101158230A (en) Lifting screw fine-adjustment outer-bushing regulation rod
CN207891893U (en) A kind of multi-functional deep foundation pit supporting structure
CN209145018U (en) A kind of connection structure of the partition plate of cantilever stair and floor beam
CN206512706U (en) One kind can tuning it is multi-functional it is middle pick fetch earth plant stake device
CN108265707A (en) One kind can the multi-functional middle pick of tuning fetch earth and plant stake device and its construction method
CN110577157B (en) Ultrahigh-rise external hanging movable arm tower crane support frame and construction method thereof
CN113605415B (en) Slope reinforcing apparatus for building municipal works
CN219654634U (en) Drill bit for hole forming of reverse circulation drilling machine of bored pile
CN202090521U (en) Light steel base plate anchor pier device
CN218292051U (en) Anti-floating anchor rod reinforcing structure for pile foundation engineering
CN115653303B (en) Indoor and outdoor wall construction system
CN217055064U (en) Rotary drilling rig drill rod fixing device
CN209817455U (en) Tool for lowering precipitation well pipe
CN216739749U (en) Pile foundation structure for water conservancy construction
CN212296383U (en) Fixed water bores device in top and excavation system
CN213450285U (en) Slip for casing windowing sidetrack whipstock
CN215262519U (en) Drilling sampling device for architectural design
CN212203646U (en) Big data monitoring and analyzing device for meteorological service

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant